Bombay High Court
SUSHANT DNYANOBA SUTARversusTHE STATE OF MAHARASHTRA THR. ITS URBAN DEVELOPMENT DEPARTMENT AND ORS
Work with this judgment
Open a tool with this judgment prefilled as editable reference text. Add your question or case details. You choose when to generate.
Use this judgment as a legal authority. Your own parties and facts stay for you to enter.
- Decided
- Disposal
- Disposed Off
Holding
The Court declined to adjudicate the merits and ordered physical measurement and demarcation of the disputed site, thereby disposing of the PIL and the interim application without deciding the substantive issues.
Summary
The Court heard a Public Interest Litigation filed by Sushant Dnyanoba Sutar seeking restoration of a public road, revocation of commencement certificates, demolition of alleged illegal construction, prosecution of the builder, and a status‑quo order. The respondents, including the State of Maharashtra and its Urban Development Department, challenged the maintainability of the PIL on the ground that the petitioner was pursuing his own grievance. The Court noted that the core dispute concerned whether the builder had encroached on public land and that a physical verification and demarcation of the site were necessary. While refusing to pass any substantive judgment on the merits, the Court directed the Pune Municipal Commissioner to ensure measurement of the site in the presence of the parties within six weeks. Consequently, the interim application and the PIL were disposed of, with the Court leaving all substantive contentions open for future determination.
Issues considered
- Whether the PIL is maintainable when the petitioner appears to be advancing a personal grievance.
- Whether the alleged construction by Respondent No.6 encroaches upon public land.
- Whether the authorities should revoke the commencement certificates issued for the construction.
- Whether the court can direct demolition of the alleged unauthorized construction.
- Whether the authorities should prosecute the builder under applicable laws.
Legislation cited
- Constitution of India — s. Article 226
Subjects
- Public Interest Litigation
- Article 226
- encroachment
- public road
- demarcation
- interim relief
- maintainability
- municipal authority
Judgment
Digitally
signed by
CHITRA
CHITRA SANJAY
SANJAY SONAWANE
SONAWANE Date:
2026.09.18
11:16:08 61-PIL-24-2026 (C).odt
+0530
Chitra Sonawane
[ Corrected as per speaking to the minutes order dated 17.09.2026. ]
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
CIVIL APPELLATE JURISDICTION
PUBLIC INTEREST LITIGATION NO.24 OF 2026
A/W
INTERIM APPLICATION NO. 6162 OF 2026
Sushant Dnyanoba Sutar ...Applicant
Versus
The State Of Maharashtra
Thr. Its Urban Development Department
And Ors. ...Respondents
...
Mr. Kamran S. Shaikh a/w Ranveersingh A. Solanki for the
Applicant.
Mrs. Neha S. Bhide, GP a/w Mrs. Shruti D. Vyas, Addl. G.P.,
Mr. S.P. Kamble, AGP for the Respondent No.1.
Mr.Prashant Darandale a/w Bajrang M. Solanke for
Respondent No.6.
...
CORAM : MAHESH CHANDRA TRIPATHI, CJ. &
ADVAIT M. SETHNA, J.
DATE : 11th SEPTEMBER, 2026.
P.C.:
1. Heard Mr Kamran Shaikh, learned Counsel for the
Petitioner and Mr Prashant Darandale, learned Counsel for
Respondent No.6.
1
61-PIL-24-2026 (C).odt
2. The instant Public Interest Litigation (in short 'PIL') is
preferred inter alia seeking following reliefs :
A. This Hon'ble Court by invoking powers under Art. 226
of the constitution of India and may be pleased to issue
the writ of Mandamus or any other writ and direct the
Respondents to restore the 9-meter-wide public road
infront of Hissa No.9, S. No. 152(Old), S. No. 2/9 (New),
Sutarwadi, Pashan, Pune.
B. This Hon'ble Court by invoking powers under Art. 226
of the Constitution of India may issue appropriate writ,
in the nature of Mandamus and direct the Respondent
No. 2, 3 and 4 to revoke the commencement certificate
C.C. No. 3477/21 dated 02.02.2022, and all the revised
commencement certificates issued by the Respondent No.
2 to the Respondent No. 6 and 7 arising out of the
building proposals of Natu Dhamale Constructions, at
Hissa No.9, S. No. 152(Old), S. No. 2/9 (New),
Sutarwadi, Pashan, Pune.
C. This Hon'ble Court by invoking powers under Art. 226
of the constitution of India and may be pleased to issue
a writ of Mandamus or any other writ, order in the like
nature and may be pleased to direct the Respondent no.
2, 3 and 4 to demolish the unauthorized construction
carried out by Respondent No. 6 on Hissa No.9, S. No.
152(Old), S. No.2/9 (New), Sutarwadi, Pashan, Pune.
D. This Hon'ble Court by invoking powers under Art. 226
of the constitution of India and may be pleased to issue
the writ of Mandamus or any other writ and direct the
Respondent No. 2 to prosecute the Respondent No. 6
under the relevant laws.
E. Pending the hearing and final disposal of this Writ
Petition, this Hon'ble Court may be pleased to direct all
the Respondents to maintain status quo on Hissa No.9,
S. No. 152(Old), S. No. 2/9 (New), Sutarwadi, Pashan,
Pune Peth.
2
61-PIL-24-2026 (C).odt
F. Ad interim and Interim relief in terms of prayer clause
'E' in favor of the Petitioner may be granted.
G. Any other suitable and equitable relief may kindly be
granted in favor of Petitioner in the interest of justice and
equity.
3. At the outset, learned Counsel for Respondent-State
raised an objection qua the maintainability of the instant PIL,
on the premise that the Petitioner is infact espousing his own
cause. He submits that an earlier Civil Writ Petition No.12981
of 2025 filed by the Petitioner, was dismissed as withdrawn
and leave was taken to prefer the PIL before appropriate Bench.
Moreover, in the said proceedings, the Petitioner agitated his
own grievances and subsequently on the same grounds
preferred this PIL.
4. Learned Counsel for the Respondents would urge that
even though this PIL is filed pursuant to the leave accorded by
the Division Bench vide its Order (supra), the PIL be dismissed
on merits. As the PIL Petitioner is espousing his own
interest/cause in the guise of the PIL, which is legally
impermissible.
5. From the submissions at the Bar, it appears that the
grievance of the parties is only qua the measurement and
3
61-PIL-24-2026 (C).odt
demarcation of the holding and whether the Respondent No.6
has encroached upon public land. It appears that even
previously, a Notice has been issued by the Municipal
Corporation to hold physical verification and demarcation, as
to whether construction was over the public road. This was
stated to be refused by the Petitioner.
4. Confronted with this situation, learned Counsel for the
Petitioner fairly submits that the core issue is to determine
whether the Petitioner or Respondent No.6 has encroached
upon public land. Learned Counsel for the parties express no
objection, in case direction is issued to the
Respondent/Authority to carry out demarcation in presence of
the parties. Similar request has also been made by the Pune
Municipal Corporation. At this stage, we are not inclined to
issue notice to Pune Municipal Corporation.
5. The Public Interest Litigation stands Disposed Of with
following directions :
(i) This order be placed before the Pune Municipal
Commissioner/Competent Authority within two weeks
from uploading of this Order.
4
61-PIL-24-2026 (C).odt
(ii) We expect the actual measurement of the site in
question to be made in presence of parties, within six
weeks thereafter.
(iii) We further clarify that we have not adverted to the
merits of the case, leaving all contentions of the parties
open.
(iv) In view of the above, nothing survives in the Interim
Application and the same is Disposed Of.
[ADVAIT M. SETHNA, J.] [CHIEF JUSTICE]