Decided
Disposal
Disposed Off

Holding

The Court declined to adjudicate the merits and ordered physical measurement and demarcation of the disputed site, thereby disposing of the PIL and the interim application without deciding the substantive issues.

Summary

The Court heard a Public Interest Litigation filed by Sushant Dnyanoba Sutar seeking restoration of a public road, revocation of commencement certificates, demolition of alleged illegal construction, prosecution of the builder, and a status‑quo order. The respondents, including the State of Maharashtra and its Urban Development Department, challenged the maintainability of the PIL on the ground that the petitioner was pursuing his own grievance. The Court noted that the core dispute concerned whether the builder had encroached on public land and that a physical verification and demarcation of the site were necessary. While refusing to pass any substantive judgment on the merits, the Court directed the Pune Municipal Commissioner to ensure measurement of the site in the presence of the parties within six weeks. Consequently, the interim application and the PIL were disposed of, with the Court leaving all substantive contentions open for future determination.

Issues considered

  • Whether the PIL is maintainable when the petitioner appears to be advancing a personal grievance.
  • Whether the alleged construction by Respondent No.6 encroaches upon public land.
  • Whether the authorities should revoke the commencement certificates issued for the construction.
  • Whether the court can direct demolition of the alleged unauthorized construction.
  • Whether the authorities should prosecute the builder under applicable laws.

Legislation cited

Subjects

  • Public Interest Litigation
  • Article 226
  • encroachment
  • public road
  • demarcation
  • interim relief
  • maintainability
  • municipal authority

Judgment

                                                             Digitally
                                                             signed by
                                                             CHITRA
                                                  CHITRA     SANJAY
                                                  SANJAY     SONAWANE
                                                  SONAWANE   Date:
                                                             2026.09.18
                                                             11:16:08                          61-PIL-24-2026 (C).odt
                                                             +0530



Chitra Sonawane


                  [ Corrected as per speaking to the minutes order dated 17.09.2026. ]

                        IN THE HIGH COURT OF JUDICATURE AT BOMBAY
                                CIVIL APPELLATE JURISDICTION

                              PUBLIC INTEREST LITIGATION NO.24 OF 2026
                                                                     A/W
                                  INTERIM APPLICATION NO. 6162 OF 2026

                  Sushant Dnyanoba Sutar                                                   ...Applicant
                          Versus
                  The State Of Maharashtra
                  Thr. Its Urban Development Department
                  And Ors.                                                                 ...Respondents
                                                                          ...
                  Mr. Kamran S. Shaikh a/w Ranveersingh A. Solanki for the
                  Applicant.

                  Mrs. Neha S. Bhide, GP a/w Mrs. Shruti D. Vyas, Addl. G.P.,

                  Mr. S.P. Kamble, AGP for the Respondent No.1.

                  Mr.Prashant Darandale                          a/w            Bajrang   M.   Solanke          for
                  Respondent No.6.
                                                                          ...

                                  CORAM : MAHESH CHANDRA TRIPATHI, CJ. &
                                          ADVAIT M. SETHNA, J.

                                  DATE         : 11th SEPTEMBER, 2026.

                  P.C.:
                  1.      Heard Mr Kamran Shaikh, learned Counsel for the

                  Petitioner and Mr Prashant Darandale, learned Counsel for

                  Respondent No.6.


                                                                           1
                                                      61-PIL-24-2026 (C).odt


2.   The instant Public Interest Litigation (in short 'PIL') is

preferred inter alia seeking following reliefs :

      A. This Hon'ble Court by invoking powers under Art. 226
      of the constitution of India and may be pleased to issue
      the writ of Mandamus or any other writ and direct the
      Respondents to restore the 9-meter-wide public road
      infront of Hissa No.9, S. No. 152(Old), S. No. 2/9 (New),
      Sutarwadi, Pashan, Pune.

      B. This Hon'ble Court by invoking powers under Art. 226
      of the Constitution of India may issue appropriate writ,
      in the nature of Mandamus and direct the Respondent
      No. 2, 3 and 4 to revoke the commencement certificate
      C.C. No. 3477/21 dated 02.02.2022, and all the revised
      commencement certificates issued by the Respondent No.
      2 to the Respondent No. 6 and 7 arising out of the
      building proposals of Natu Dhamale Constructions, at
      Hissa No.9, S. No. 152(Old), S. No. 2/9 (New),
      Sutarwadi, Pashan, Pune.


      C. This Hon'ble Court by invoking powers under Art. 226
      of the constitution of India and may be pleased to issue
      a writ of Mandamus or any other writ, order in the like
      nature and may be pleased to direct the Respondent no.
      2, 3 and 4 to demolish the unauthorized construction
      carried out by Respondent No. 6 on Hissa No.9, S. No.
      152(Old), S. No.2/9 (New), Sutarwadi, Pashan, Pune.


      D. This Hon'ble Court by invoking powers under Art. 226
      of the constitution of India and may be pleased to issue
      the writ of Mandamus or any other writ and direct the
      Respondent No. 2 to prosecute the Respondent No. 6
      under the relevant laws.


      E. Pending the hearing and final disposal of this Writ
      Petition, this Hon'ble Court may be pleased to direct all
      the Respondents to maintain status quo on Hissa No.9,
      S. No. 152(Old), S. No. 2/9 (New), Sutarwadi, Pashan,
      Pune Peth.



                                  2
                                                          61-PIL-24-2026 (C).odt


      F. Ad interim and Interim relief in terms of prayer clause
      'E' in favor of the Petitioner may be granted.


      G. Any other suitable and equitable relief may kindly be
      granted in favor of Petitioner in the interest of justice and
      equity.


3.   At the outset, learned Counsel for Respondent-State

raised an objection qua the maintainability of the instant PIL,

on the premise that the Petitioner is infact espousing his own

cause. He submits that an earlier Civil Writ Petition No.12981

of 2025 filed by the Petitioner, was dismissed as withdrawn

and leave was taken to prefer the PIL before appropriate Bench.

Moreover, in the said proceedings, the Petitioner agitated his

own grievances and subsequently on the same grounds

preferred this PIL.

4.   Learned Counsel for the Respondents would urge that

even though this PIL is filed pursuant to the leave accorded by

the Division Bench vide its Order (supra), the PIL be dismissed

on merits. As the PIL Petitioner is espousing his own

interest/cause in the guise of the PIL, which is legally

impermissible.

5.   From the submissions at the Bar, it appears that the

grievance of the parties is only qua the measurement and

                                   3
                                                    61-PIL-24-2026 (C).odt


demarcation of the holding and whether the Respondent No.6

has encroached upon public land. It appears that even

previously, a Notice has been issued by the Municipal

Corporation to hold physical verification and demarcation, as

to whether construction was over the public road. This was

stated to be refused by the Petitioner.

4.   Confronted with this situation, learned Counsel for the

Petitioner fairly submits that the core issue is to determine

whether the Petitioner or Respondent No.6 has encroached

upon public land. Learned Counsel for the parties express no

objection,     in   case    direction     is   issued      to       the

Respondent/Authority to carry out demarcation in presence of

the parties. Similar request has also been made by the Pune

Municipal Corporation. At this stage, we are not inclined to

issue notice to Pune Municipal Corporation.

5.   The Public Interest Litigation stands Disposed Of with

following directions :

      (i)    This order be placed before the Pune Municipal

      Commissioner/Competent Authority within two weeks

      from uploading of this Order.



                                4
                                                61-PIL-24-2026 (C).odt


    (ii) We expect the actual measurement of the site in

    question to be made in presence of parties, within six

    weeks thereafter.

    (iii) We further clarify that we have not adverted to the

    merits of the case, leaving all contentions of the parties

    open.

    (iv) In view of the above, nothing survives in the Interim

    Application and the same is Disposed Of.




[ADVAIT M. SETHNA, J.]                    [CHIEF JUSTICE]




                             5


Continue reading with your account

Sign in to read the full judgment. It’s free.

Sign in to read

Checking your session…

Lawyer court records for this case

Associated through the court’s case reference.

To request removal of this judgment, sign in and send a removal request. We review requests within 10 working days.

For a signed copy suitable for filing, refer to the court's website.