Bombay High Court
KUSHAL R AGARWALversusMUMBAI MUNICIPAL CORPORATION THR THE MUNICIPAL CORPORATION AND ORS
- Decided
- Disposal
- Dismissed
Holding
The Court held that the impugned communication is not amenable to interference under Article 227 and dismissed the petition.
Summary
The petitioner sought to purchase Flat No. 9 in Malboro House and, under the Right to Information Act, obtained copies of repair plans dated 1972 and 1995 along with a signed plan. The BMC later issued a communication declaring those plans null and void, citing the existence of a different sanctioned plan from 1967 and alleging the RTI‑supplied plans were forged. The petitioner challenged the legality of this declaration, arguing that the BMC lacked authority to deem the plans invalid, that no hearing was afforded, and that the authenticity of the plans was a factual matter. The respondents contended that the communication merely reflected the BMC’s records and that the issue was not maintainable before the High Court. The Court held that the dispute over plan authenticity is a factual issue not suitable for interference under Article 227, and that the petitioner must pursue remedies in the appropriate forum. Consequently, the petition was dismissed and the interim application disposed.
Issues considered
- Whether the High Court can interfere under Article 227 of the Constitution with a municipal corporation's communication declaring RTI‑obtained plans null and void.
- Whether Respondent No.2 (BMC) is empowered to declare the plans furnished under the RTI Act as null and void.
- Whether the petitioner was entitled to a hearing before such a declaration was made.
- Whether the question of authenticity of the building plans is a factual dispute beyond the scope of the Court's extraordinary writ jurisdiction.
Legislation cited
- Constitution of India — s. Article 227
- Right to Information Act, 2005
Subjects
- Article 227
- Right to Information Act
- municipal corporation
- building plans
- authenticity of documents
- writ petition
- administrative law
- court jurisdiction
Judgment
17-WP-10303-2026.DOC
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
CIVIL APPELLATE JURISDICTION
WRIT PETITION NO. 10303 OF 2026
Kushal R Agarwal ..Petitioner
Versus
Mumbai Municipal Corporation Through The …Respondents
Municipal Corporation and Ors
WITH
INTERIM APPLICATION (ST) NO. 24883 OF 2026
IN
WRIT PETITION NO. 10303 OF 2026
Mr. M. M. Vashi, Senior Advocate, with Itisha Ranka, i/b M.P. Vashi
and Associates, for the Petitioner.
Adv. Pooja Khandeparkar, with D.R. Kawale, for Respondent Nos. 1
and 2 -BMC.
Mr. Ashish Kamat, Senior Advocate, with Karl Tamboly, Shlok Parekh,
Yash Dhruva, Ruchita Jain, Rajlaxmi Pwar and Shanmukh
Puranik, i/b MDP Legal, for Respondent Nos. 3, 4 and 5.
Mr. Pradeep Thorat, i/b Aditi Naikare, for Respondent No. 6.
Mr. Ashwajeet Adhav, JEBF, ‘D’ Ward, present.
ARUN
RAMCHANDRA
CORAM: N. J. JAMADAR, J.
SANKPAL
DATE : 11th SEPTEMBER 2026
Digitally signed
by ARUN
RAMCHANDRA
SANKPAL
Date: 2026.09.15
16:47:18 +0530
ORDER:
1. By this Petition under Article 227 of the Constitution of India, the
Petitioner assails the legality and validity of a communication dated 13 th
July 2026 issued by the Assistant Engineer (B & F) ‘D’ Ward, Brihan
Mumbai Municipal Corporation (“BMC”) (R2), thereby informing the
ARS 1/6
17-WP-10303-2026.DOC
Petitioner that the Plans; the copies of which were issued to the
Petitioner under Right to Information Act, 2005 (“the RTI Act”), are null
and void.
2. The Petitioner was desirous of purchasing a flat, being Flat No. 9,
Malboro House (originally known as “Kamani House”), CS No. 4E/738,
Malabar Hill, Pedder Road, Mumbai. The Petitioner claimed to have
filed an Application with the Punblic Information Officer, BMC seeking
all documents in regard to the said property. Pursuant thereto, the
Petitioner was furnished a number of documents including a Repairs
NOC granted by the office of Respondent No.2 to M/s Kamani Brothers,
along with a signed Plan dated 3rd May 1972 and Repairs permission
dated 10th August 1995, with a copy of duly signed plan.
3. Respondent Nos. 3 to 5, who are the members of the Respondent
No. 6-Housing Society which holds Malboro House, purportedly lodged
a complaint recording the authenticity and genuineness of the above
referred plants furnished to the Petitioner under RTI Act and alleged
that those plans were forged and fabricated.
4. Thereupon, Respondent No.2 seems to have ascertained the facts
and entered into internal correspondence with the Executive Engineer
(Building Proposal) City- I of BMC. On the basis of the response to the
Office Note, Respondent No.2 informed the Petitioner that the above
referred plans furnished to the Petitioner under RTI Act were not
ARS 2/6
17-WP-10303-2026.DOC
available on the record of the Executive Engineer (Building Proposal)
City-I and there was a final approved building plan dated 13 th October
1967 in respect of Malboro House with the said office. Further noting
that there were discrepancies in the plans furnished to the Petitioner,
Respondent No.2 informed the Petitioner that, above-referred plans
issued to the Petitioner under the RTI Ac are null and void.
5. Mr. Vashi, the learned Senior Advocate, for the Petitioner
submitted that the impugned order suffers from multiple legal
infirmities. First, Respondent No.2 is not empowered to declare the
plans furnished by the BMC under RTI Act as null and void. Second, the
impugned communication is in teeth of fundamental principles of
judicial process as no opportunity was given to the Petitioner before
arriving at the conclusion that the above-referred plans were not
genuine. Third, the aforesaid plans were issued by the Building and
Factory Department which was empowered to grant Repairs permission
and thus their non availability with the Building Proposal Department
was of non significance. Fourth, there is nothing to indicate that the
purported plan of the year 1967 is the sanctioned building plan.
6. Mr. Thorat, the leaned Counsel for Respondent Nos. 6-society
supplemented the submission of Mr. Vashi. It was urged that without
providing an opportunity of hearing to Respondent No.6-Society,
Respondent No. 2 could not have issued the impugned communication
ARS 3/6
17-WP-10303-2026.DOC
which had the effect of rendering the structures in the Malboro House
unauthorised.
7. Ms. Pooja Khandeparkar, the learned Counsel for Respondent
Nos. 1 and 2-BMC and Mr. Ashish Kamat, the learned Senior Advocate
for Respondent Nos. 3 to 5 questioned the very maintainability of the
Petition.
8. Ms. Khandeparkar submitted that Respondent No.2 has simply
communicated the position as it obtains from the record of BMC.
Development/Building permission can be granted by the Building
Proposal Deparment. Building and Factory Department has no
authority to sanction a building plan.
9. I have perused the impugned order and the material on record. It
is a stated case of the Petitioner that he was supplied the copies of the
Repairs plans of the year 1972 and 1995. What the impugned
communication in essence informs the Petitioner is that, those Repairs
plans do not find place on record of the Executive Engineer (Building
Proposal) City-I and that the Building Proposal Department has
informed that there is a sanctioned plan of the year 1967. This becomes
evident from the copy of the communication dated 3 rd July 2026,
addressed by the Assistant Engineer (Building Proposal) Department
(which is the basis of impugned communication). It reads as under:
ARS 4/6
17-WP-10303-2026.DOC
“ Ref: Note received from Designated Officer (B & F) ‘D’
Ward u/no. OACD/542/214/B&F dated 19.06.2026.
Reference is requested to note received from Designated
Officer (B&F) ‘D’ Ward requesting to confirm authenticity of
plans of approved building on plot bearing CS No. 4E/738 of
Malbar Hill Division in the alleged complaint matter.
The copies of the attached plans are checked for verifying
authenticity. In this regard, it is to inform you that, the copies of
plans attached alon giwth the note from D.O. (D Ward) are not
available on record of this office. Therefore the authenticity of
same cannot be verified. Further, as per this office available
records, the plans bearing no. EB/9838/D dated 13.10.1967 are
available. The copies of the plans on this office record are
attached herewith for your ready reference. (pageC/25 to
C/41).”
10. The essential controvery thus boils down to the genuineness,
legality and validty of the plans. Whther the plans purportedly issued by
the Building and Factory Department authorising the repairs of the
Malboro Building are genuine or otherwise, or for that matter, the
sanctioned building plan of the year 1967 is genuine and holds the field
or whether any rights and obligations emanate from the repairs plans of
the year 1972 and 1995, authorising the repairs, are all matters which
are rooted in facts.
ARS 5/6
17-WP-10303-2026.DOC
11. In the considered view of this Court, the impugned
communication is not amenable to interference in exercise of the
powers under Article 227 of the Constitution of India. Nor this Court
would not be justified in delving into the aforesaid disputed questions
of facts in the exercise of its extraordinary writ jurisdiction. The
Petitioner would be required to workout his remedies before an
appropriate forum seeking appropriate reliefs in regard to the plans in
question.
12. The Petition stands dismissed with liberty to workout the
remedies as avilable in law.
13. In view of the dismissal of the Petition, the Interim Application
stands disposed.
[N. J. JAMADAR, J.]
ARS 6/6