Bombay High Court
UDAY SUDHAKAR DESSAIversusALCHEMIST ASSET RECONSTRUCTION CO. LTD THR AKSHAT SHARMA AND ANR
- Disposal
- Allowed
Holding
The High Court quashed the NGT order restraining the petitioner’s commercial activities as it was issued without complying with Section 19(4)(i) of the NGT Act.
Summary
The petitioner, Uday Sudhakar Dessai, challenged an order dated 09.09.2026 passed by the National Green Tribunal (NGT) that imposed an interim injunction preventing him from carrying out commercial activities at his premises. The petitioner argued that the NGT order violated principles of natural justice and Section 19(4)(i) of the National Green Tribunal Act, 2010, by granting the injunction ex parte without notice. The respondents contended that the High Court should not interfere, invoking Section 22 of the Act which provides for a direct appeal to the Supreme Court. The High Court found that the NGT had indeed granted the injunction without affording a hearing, contrary to statutory requirements, and noted that the unauthorised temporary structures were already demolished. Consequently, the Court quashed the NGT order to the extent it restrained the petitioner’s commercial activities and allowed the writ petition.
Issues considered
- The NGT order was passed in violation of natural justice and Section 19(4)(i) of the National Green Tribunal Act, 2010.
- Whether the High Court can entertain the writ petition despite the provision of a direct appeal under Section 22 of the Act.
- Whether an ex parte interim injunction can be granted without notice and hearing.
Legislation cited
- National Green Tribunal Act, 2010 — s. 19(4)(i), 22
Subjects
- natural justice
- interim injunction
- National Green Tribunal
- environmental law
- writ petition
- jurisdiction
- Section 19
- Section 22
- commercial activity
- unauthorised structures
Judgment
904 WP 1329 2026
Andreza
IN THE HIGH COURT OF BOMBAY AT GOA
WRIT PETITION NO.1329 OF 2026
UDAY SUDHAKAR DESSAI ... PETITIONER
Versus
ALCHEMIST ASSET RECONSTRUCTION CO.
LTD THR AKSHAT SHARMA AND ANR ... RESPONDENTS
Mr. Shivan Desai, Advocate with Mr. Jatin Ramaiya, Advocate
for Petitioner.
Mr. Karan Batura, Advocate with Mr. Sarvesh Sawant, Advocate
for Respondent no. 1.
Mr. Shubham Priolkar, Additional Government Advocate for
Respondent no. 2.
CORAM:- S. G. CHAPALGAONKAR, J.
DATED :- 29th September, 2026
P.C.
1. This Writ Petition takes exception to Order dated 09.09.2026,
passed by learned National Green Tribunal (NGT), Western Zone
Bench, Pune, in Appeal No. 612/2025.
2. Mr. Desai, learned Advocate appearing for Petitioner, would
assail the impugned Order firstly on ground that it has been passed
in gross violation of principles of natural justice and statutory
requirements under Section 19(4)(i) of National Green Tribunal
Act, 2010. Secondly, text of impugned Order suggests that, prima
facie, Green Tribunal was of the view that no case is made out by
Page 1 of 3
29th September, 2026
904 WP 1329 2026
the Appellant, still interim injunction is issued against Petitioner
from continuing commercial activities in the premises.
3. Per contra, Mr. Batura, learned Counsel appearing for
Respondent No.1, supports the impugned Order and endeavours to
contend that extraordinary jurisdiction of this Court ought not be
invoked in view of provisions contained in Section 22 of the Act,
which provides for a direct appeal of any order passed by the
National Green Tribunal. He would endeavour to take this Court
through material in support of impugned Order and justify the
same.
4. Having considered submissions advanced by learned Counsel
appearing for respective parties, this Court is of the view that, in
wake of observations made by Tribunal itself, when no merit was
found in contention of Respondents, ex parte interim injunction
could not have been granted, particularly without issuing notice of
hearing and affording an opportunity of being heard to Petitioner as
mandated under Section 19(4)(i) of the NGT Act.
5. Further, a reference to affidavit in reply filed on behalf of
Respondent no.2 before NGT, indicates that on inspection of
subject site, it was observed that unauthorised temporary structures
which were subject matter of proceedings, had been demolished
and/or removed from site. Admittedly, the grievances raised
Page 2 of 3
29th September, 2026
904 WP 1329 2026
before the Authority were with regard to the structures which were
raised beyond specific licence or construction permission granted
in favour of Petitioner.
6. In wake of aforesaid material, impugned Order cannot be
countenanced in law, to the extent it distanced Petitioner from
continuing the commercial activities within premises which is
legally constructed and put into operation for commercial purpose.
7. In result, Writ Petition is allowed. The impugned Order
dated 09.09.2026 passed by NGT to the extent it restrains
Petitioner from carrying commercial activity, is quashed and set
aside.
8. Needless to state that observations made hereinabove are only
for the purpose of disposing of present Writ Petition and parties are
at liberty to advance their submission on merit before NGT and,
upon consideration of such submissions, further Orders can be
passed by NGT without being impeded by observations made
hereinabove.
9. Writ Petition is disposed of.
S. G. CHAPALGAONKAR, J.
Signed by: ANDREZA PEREIRA
Designation: Senior Private Secretary
Page 3 of 3
to the Hon'ble Judge
Date: 29/09/2026 16:51:49 29th September, 2026