Bombay High Court
THE MAHARASHTRA STATE ELECTRICITY DISTRIBUTION COMPANY LTD THROUGH ITS EXECUTIVE ENGINEERversusM/S NAVJEEVAN TYRES PVT LTD THROUGH ITS AUTHORIZED SIGNATORY
- Disposal
- DISPOSED OFF
Holding
The Court quashed the Electricity Ombudsman’s order, holding that the respondent is a Commercial consumer and the electricity company may recover the differential charges notwithstanding the Section 56(2) limitation.
Summary
The Maharashtra State Electricity Distribution Company Ltd (MSEDCL) issued an assessment bill to Navjeevan Tyres Pvt. Ltd for differential charges, alleging the consumer had been billed under an Industrial tariff instead of the correct Commercial tariff for its tyre re‑treading business. The Electricity Ombudsman limited the recovery to a short period and waived delayed payment charges and interest. MSEDCL challenged the Ombudsman’s order, arguing that the consumer’s activity falls under the Commercial category per circulars and that Section 56(2) of the Electricity Act, 2003 does not bar recovery of the earlier dues. The High Court examined the classification issue, the applicability of the two‑year limitation, and cited Supreme Court precedents on bonafide billing mistakes. It held that the Ombudsman erred in its interpretation, that the consumer is indeed a Commercial user, and that the electricity company may recover the differential amount despite the limitation, quashing the Ombudsman’s order and allowing the writ petition.
Issues considered
- Whether Section 56(2) of the Electricity Act, 2003 bars recovery of differential charges for periods prior to the discovery of a billing mistake.
- Whether the respondent's tyre re‑treading activity falls under the Commercial (LT‑II) tariff category or the Industrial (LT‑V) category.
- Whether the Electricity Ombudsman correctly limited the recovery period and waived delayed payment charges and interest.
Legislation cited
- Electricity Act, 2003 — s. 56
- General Clauses Act, 1897 — s. 6
Subjects
- tariff classification
- Electricity Act 2003
- Section 56
- limitation period
- bonafide mistake
- electricity billing
- consumer classification
- Electricity Ombudsman
- writ petition
Judgment
2026:BHC-AUG:16430
1 83-WP-1861-18 judgment.odt
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
BENCH AT AURANGABAD
83 WRIT PETITION NO. 1861 OF 2018
The Maharashtra State Electricity }
Distribution Company Ltd, }
Circle Office, Latur, }
Through its Executive Engineer }
Petitioner
(Orig. Respondent)
Versus
M/s. Navjeevan Tyres Pvt. Ltd., }
Plot No.F-8, Kallam Road, }
MIDC Latur Tq. District Latur-431512, }
Through its Authorized Signatory }
Respondent
(Orig. Complainant)
...
Advocate for the Petitioner : Mr. A. S. Shelke
Advocate for Respondent : Mr. J. R. Shah
...
CORAM : SIDDHESHWAR S. THOMBRE, J.
DATE : 02.04.2026
JUDGMENT :
1. Rule. Rule made returnable forthwith. Heard finally with the
consent of the parties at the stage of admission.
2. The petitioner is aggrieved by the order dated 03.10.2017 passed
by the Electricity Ombudsman, Nagpur in Representation No. 35 of 2017,
more particularly to the extent of clauses (c) and (d) of the operative
order.
3. The brief facts of the case:-
3.1 It is the case of the petitioner that the petitioner is an authority of
2 83-WP-1861-18 judgment.odt
the Maharashtra State Electricity Distribution Company Limited, engaged
in distribution and supply of electricity under the provisions of the
Electricity Act, 2003 (for short, “the Act”). The respondent is a consumer,
carrying on business of tyre re-treading. The respondent obtained
electricity supply on 16th September, 1989. As per Commercial Circular
No.243 dated 3rd July, 2015, the activity of Tyre re-treading falls under
LT-II (Non-Residential / Commercial) category.
3.2 On 23.02.2016, the Flying Squad, Ratnagiri, inspected the premises
of the respondent and, upon verification of the installation, noticed
irregularities. It was observed that the respondent was being billed under
Industrial Tariff instead of Commercial Tariff. Accordingly, the concerned
Sub-Division of the petitioner issued an assessment bill dated 10.03.2016
for an amount of Rs.6,17,870/-. Being aggrieved thereby, the respondent
approached the Internal Grievance Redressal Cell (IGRC) on 21st
September, 2016. After considering the contentions of both sides, the
grievance came to be rejected, holding that categorization of the
consumer was proper in view of Circular Nos.175 and 243. Being further
aggrieved, the respondent approached the Consumer Grievance Redressal
Forum (CGRF), Latur. The CGRF, after hearing both sides, partly allowed
the grievance and directed the petitioner to revise the assessment bill of
Rs.6,17,870/-. It further directed that recovery be restricted to a period of
two years prior to 24.02.2016 i.e. till 24.02.2014 without application of
delayed payment charges (DPC) and interest.
3 83-WP-1861-18 judgment.odt
3.3 Being aggrieved by the said order, the respondent preferred
Representation No.35/2017 before the Electricity Ombudsman, Nagpur.
The petitioner appeared and supported the order of CGRF, Latur. The
Electricity Ombudsman, Nagpur, by the impugned order, directed the
petitioner to charge the differential amount between LT-II (Commercial)
and LT-V (Industrial) tariff only for the period from 24.02.2016 (date of
inspection) to 30.10.2016, without imposing any delayed payment
charges (DPC) or interest. It was further directed to revise the bills
accordingly and refund the excess amount after re-calculation, if any. The
petitioner thereafter filed Review Application No.05/2017 before
Electricity Ombudsman, Nagpur which came to be rejected on
09.02.2018. Being aggrieved by the said order, the present petition is
filed.
4. The learned counsel for the petitioner, Mr. Shelke submits that the
impugned order passed by the Electricity Ombudsman is contrary to the
facts on record. He submits that the respondent is carrying on the
business of Tyre re-treading, which is classified under the Commercial
category as per Circular Nos.175 and 243. However, the respondent-
consumer was erroneously billed under the Industrial tariff category since
the year 2012. This irregularity came to be noticed on 23.02.2016 during
inspection carried out by the Flying Squad, Ratnagiri.
5. Pursuant to the inspection, the petitioner-company issued an
assessment bill towards differential charges for the period from August,
4 83-WP-1861-18 judgment.odt
2012 till 24.02.2016. It was the contention of the petitioner that though
judgments of the this Court and the Hon’ble Apex Court were cited before
the Electricity Ombudsman, the same were not considered. It was
contended that the bar of two years under Section 56(2) of the Electricity
Act, 2003 would not apply to such recovery, even if the period exceeds
two years.
6. The learned counsel for petitioner further submits that the
Electricity Ombudsman, Nagpur has relied on an order passed by the
Maharashtra Electricity Regulatory Commission dated 11.02.2003 in Case
No.24 of 2001, which was rendered prior to the coming into force of the
Act. He submits that the present assessment has been made under the
provisions of the Act and, therefore, such reliance is misplaced and not
sustainable in law. The learned counsel for the petitioner, therefore,
submits that the impugned order passed by the Electricity Ombudsman
deserves to be quashed and set aside.
7. In support of his submissions, the learned counsel relies upon the
following judgments:—
i) Maharashtra State Electricity Distribution Company Limited v.
Suhasini D. Naik, AIR Online 2024 BOM 1209.
ii) Maharashtra State Electricity Distribution Company Limited v.
Electricity Ombudsman and ors., 2019 AIR (Bom) 113.
iii) Assistant Engineer (D1), Ajmer Vidyut Vitran Nigam Limited and
Another v. Rahamatullah Khan alias Rahamjulla, 2020 (4) SCC 650.
iv) Prem Cottex v. Uttar Haryana Bijli Vitran Nigam Limited, 2021
5 83-WP-1861-18 judgment.odt
DGLS(SC) 564
v) Maharashtra State Electricity Distribution Company Limited v. M/s.
Jamiya Mohamad Education Society, AIR 2024 Bombay 379.
8. Per contra, the learned counsel for the respondent, Mr. J. R. Shah,
supports the impugned order passed by the Electricity Ombudsman. He
submits that the respondent is running a Tyre re-treading unit, which is
an industrial undertaking, and has been regularly paying electricity bills
under the Industrial tariff category.
9. He submits that the primary activity of the respondent falls within
the ambit of industrial activity involving a manufacturing process.
According to him, till the inspection conducted by the Flying Squad on
23.02.2016, the petitioner had consistently billed the respondent under
the Industrial tariff category, which was appropriate and justified.
10. It is further submitted that the change in tariff category from
Industrial to Commercial, pursuant to the inspection dated 23.02.2016,
and issuance of the assessment bill with retrospective effect from August,
2012, is illegal and unsustainable. The respondent, therefore, approached
the Internal Grievance Redressal Cell contending that the unit is a
manufacturing unit and does not involve any commercial activity.
11. The learned counsel submits that there was no fault or
misrepresentation on the part of the respondent. The respondent had
been continuously charged under the Industrial tariff category since 1989
6 83-WP-1861-18 judgment.odt
till February, 2016, and only after the inspection by the Flying Squad, the
tariff category came to be changed.
12. It is further submitted that such reclassification of tariff cannot be
equated with a case of escaped billing or clerical error. Therefore,
recourse to recovery under Section 56 of the Act is not permissible. He
submits that the Electricity Ombudsman has rightly appreciated these
aspects and has correctly directed revision of bills and refund of excess
amount recovered pursuant to the assessment bill. In view of the
aforesaid submissions, the learned counsel for the respondent prays for
dismissal of the writ petition.
13. Having heard the learned counsel for the parties at length, there is
no dispute that the respondent has been carrying on the business since
1989. Upon considering the nature of activities of the respondent, the
Flying Squad submitted its report and, based thereon, the assessment bill
came to be issued to the respondent on the premise that the respondent’s
classification falls under Commercial use.
14. This Court in the case of Maharashtra State Electricity Distribution
Company Limited (supra) has held in paragraph nos.8, 9 and 10, which
read thus:-
“8. CGRF then has taken into consideration the Judgment of the Hon’ble
Supreme Court in the case of Prem Cottex (supra) and has held that the
electricity company can recover electricity bill for bonafide mistake and it is
further held that the mistake in this case is not bonafide and therefore the
judgment has no application thereto. With this discussion the grievance
Case No. 071 of 2022 was partially allowed. Electricity company was
directed to revise supplementary bill issued in June -2022 considering 793
7 83-WP-1861-18 judgment.odt
units for the month of November- 2020 after adjusting the payment made
by the consumer and the interest was also directed be waived.
9. At this stage, it would be relevant to take note of the Judgment of a three
Judge Bench of Hon’ble Supreme Court in the case of K.C.Ninan Vs. Kerala
State Electricity Board and Others (2023 SCC OnLine SC 663), after taking
into consideration judgment in case of Prem Cottex (Supra) and Assistant
Engineer (D1), Ajmer Vidyut Vitran Nigam Limited and Anr. Vs.
Rahamatullah Khan has passed judgment and it would be fruitful to refer to
the relevant paragraph Nos. 122 to 136 thereof which read thus:
“122…………….
129. The second issue pertains to the implication of the period
of two years provided in Section 56(2) on the civil remedies of
Utilities to recover electricity dues. Section 56(2), which begins
with a non obstante clause, provides a limitation of two years for
recovery of dues by the licensee through the means of
disconnecting electrical supply. It puts a restriction on the right
of the licensee to recover any sum due from a consumer under
Section 56 after a period of two years from the date when such
sum became first due. If this provision is invoked against a
consumer after two years, the action will be permissible when
the sum, which was first due, has been shown continuously as
recoverable as arrears of charges for electricity supplied. Under
Section 56, the liability to pay arises on the consumption of
electricity and the obligation to pay arises when a bill is issued
by the licensee for the first time. Accordingly, the period of
limitation of two years starts only after issuance of the bill.
130. Before we deal with the implication of Section 56(2) on the
civil remedies available to a licensee, it is important to clarify
that when the liability incurred by a consumer is prior to the
period when the 2003 Act came into force, then the bar of
limitation under Section 56(2) is not applicable. In Kusumam
Hotels Pvt Ltd v. Kerala State Electricity Board, this Court has
held that Section 56(2) applies after the 2003 Act came into
force and the bar of limitation under Section 56(2) would not
apply to a liability incurred by the consumer prior to the
enforcement of the Act. In terms of Section 6 of the General
Clauses Act 1897, the liability incurred under the previous
enactment would continue and the claim of the licensee to
recover electricity would be governed by the regulatory
framework which was in existence prior to the enforcement of
the 2003 Act.
131………..”
10. It is thus clear from this judgment, that it is open for the electricity
company to issue a revised bill if it is found that the previous bill issued is
under bonafide mistake. In the instant case, revised bill has been issued
with specific contention that multiplying factor 1 instead of 20 was applied.
There is no dispute made by the consumer with regard to this fact. If it is
so, it does not stand to any reason or justification to hold that this is not
bonafide mistake of the electricity company, as observed by CGRF. In view
8 83-WP-1861-18 judgment.odt
of the judgment of the Hon’ble Supreme Court in the case of K. C.
Ninan(supra), the electricity company is within its right to issue revised bill
once such bonafide mistake is found out.”
15. The Hon’ble Apex Court in the case of Prem Cottex (supra),
particularly in paragraph nos.23 to 25, has stated as follows:-
“23. Coming to the second aspect, namely, the impact of Sub-section (1)
on Sub-section (2) of Section 56, it is seen that the bottom line of Sub-
section (1) is the negligence of any person to pay any charge for electricity.
Sub-section (1) starts with the words “where any person neglects to pay
any charge for electricity or any some other than a charge for electricity
due from him.
24. Sub-section (2) uses the words “no sum due from any consumer
under this Section”. Therefore, the bar under Sub-section (2) is relatable to
the sum due under Section 56. This naturally takes us to Sub-section(1)
which deals specifically with the negligence on the part of a person to pay
any charge for electricity or any sum other than a charge for electricity.
What is covered by section 56, under sub-section (1), is the negligence on
the part of a person to pay for electricity and not anything else nor any
negligence on the part of the licensee.
25. In other words, the negligence on the part of the licensee which led
to short billing in the first instance and the rectification of the same after
the mistake is detected, is not covered by Sub-section (1) of Section 56.
Consequently, any claim so made by a licensee after the detection of their
mistake, may not fall within the mischief, namely, “no sum due from any
consumer under this Section”, appearing in Sub-section (2).”
16. Considering the issue involved, it is necessary to refer to Section 56
of the Electricity Act, 2003, which reads thus:—
“56. Disconnection of supply in default of payment.–
(1)Where any person neglects to pay any charge for electricity or any sum
other than a charge for electricity due from him to a licensee or the
generating company in respect of supply, transmission or distribution or
wheeling of electricity to him, the licensee or the generating company may,
after giving not less than fifteen clear days’ notice in writing, to such
person and without prejudice to his rights to recover such charge or other
sum by suit, cut off the supply of electricity and for that purpose cut or
disconnect any electric supply line or other works being the property of
such licensee or the generating company through which electricity may
have been supplied, transmitted, distributed or wheeled and may
discontinue the supply until such charge or other sum, together with any
expenses incurred by him in cutting off and reconnecting the supply, are
paid, but no longer:Provided that the supply of electricity shall not be cut
off if such person deposits, under protest,–
(a)an amount equal to the sum claimed from him, or
9 83-WP-1861-18 judgment.odt
(b)the electricity charges due from him for each month calculated on
the basis of average charge for electricity paid by him during the
preceding six months,whichever is less, pending disposal of any dispute
between him and the licensee.
(2)Notwithstanding anything contained in any other law for the time being
in force, no sum due from any consumer, under this section shall be
recoverable after the period of two years from the date when such sum
became first due unless such sum has been shown continuously as
recoverable as arrear of charges for electricity supplied and the licensee
shall not cut off the supply of the electricity.”
17. Upon perusal of Section 56(2) of the Act, it is evident that the bar
contained therein is not only in respect of disconnection of supply but
also operates against recovery of dues beyond the prescribed period,
unless the conditions stipulated therein are satisfied.
18. In the present case, it is an admitted position that the respondent
obtained electricity supply on 16th September, 1989. As per Commercial
Circular No.175 dated 05th September, 2012 and Commercial Circular
No.243 dated 03rd July, 2015, the activity of Tyre re-treading falls under
LT-II (Non-Residential / Commercial) category.
19. Merely because the respondent was erroneously billed under the
Industrial tariff due to certain irregularities, the same cannot be a ground
to continue such classification, if in fact the activity falls within the
Commercial category. Once the activity of Tyre re-treading is classified as
Commercial, the respondent is liable to pay charges in accordance with
the applicable Commercial tariff.
20. It is necessary to note that the petitioner is bound to follow the
regulations and tariff classifications framed by the Maharashtra Electricity
10 83-WP-1861-18 judgment.odt
Regulatory Commission. Once the activity of the respondent is
categorized as Commercial, the billing must necessarily be aligned with
such classification.
21. In that view of the matter, the assessment bill issued in the year
2016, pursuant to the Flying Squad inspection, for recovery of differential
charges on account of wrong tariff application, cannot be said to be
illegal merely because the respondent was previously billed under the
Industrial category.
22. In view of the aforesaid discussion, this Court finds that the
Electricity Ombudsman has committed an apparent error while allowing
the representation filed by the respondent. The impugned order,
therefore, warrants interference. Hence, I proceed to pass following
order:-
ORDER
i. The writ petition is allowed.
ii. The order dated 03.10.2017 passed by Electricity Ombudsman,
Nagpur in Representation No.35/2017 is hereby quashed and set
aside.
iii. Rule is made absolute in the above terms.
iv. Pending Civil Applications, if any, stand disposed of.
[ SIDDHESHWAR S. THOMBRE ]
JUDGE