Bombay High Court
VITTHAL NARAYAN SURYAWANSHI AND ANOTHERversusSATISH KISHAN KHATAWKAR
- Disposal
- DISPOSED OFF
Holding
The High Court upheld the Industrial Court's award of Rs.1,77,200 and dismissed the writ petition.
Summary
The petitioners, owners of Elevators Limited, challenged an order of the Industrial Court, Latur, which had allowed a complaint by a former technician seeking Rs.1,77,200 as unpaid wages. The petitioners argued that no employer‑employee relationship existed and that they were denied proper legal representation, contending the complaint was therefore untenable. The respondent produced bank statements and detailed records showing he was contracted to receive Rs.18,000 per month plus allowances, had been paid Rs.2,30,000, and was owed the balance claimed. The High Court found the documentary evidence credible, noted that the petitioners did not contest the claim, and concluded that the Industrial Court correctly awarded the amount. Consequently, the writ petition was dismissed as lacking merit, with no order as to costs.
Issues considered
- Whether the complaint under the Unpaid Labour Petition (ULP) is maintainable in the absence of a proven employer‑employee relationship.
- Whether the petitioners were denied proper representation, warranting interference with the Industrial Court's order.
- Whether the High Court can exercise supervisory jurisdiction under Article 227 to set aside the Industrial Court's award.
Subjects
- unpaid wages
- industrial court
- supervisory jurisdiction
- Article 227
- employer-employee relationship
- writ petition
- dismissal
Judgment
2026:BHC-AUG:23349
1 of 3 986-WP.4342.2020
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
BENCH AT AURANGABAD
986 WRIT PETITION NO. 4342 OF 2020
VITTHAL NARAYAN SURYAWANSHI AND ANOTHER
VERSUS
SATISH KISHAN KHATAWKAR
...
Mr. Suhas P. Urgunde, Advocate for the Petitioners.
...
CORAM : SIDDHESHWAR S. THOMBRE, J.
DATE : 12th JUNE, 2026
P.C.:-
1. Heard learned Advocate for the Petitioners.
2. By the present petition, the Petitioners have challenged the
order dated 14.12.2018 passed by the learned Member, Industrial
Court, Latur in Complaint (ULP) No. 16 of 2017, whereby the
complaint filed by the Respondent was allowed and the Petitioners
were directed to pay an amount of Rs.1,77,200/-.
3. Mr. Urgunde, learned Advocate for the Petitioners submitted
that Petitioner No. 1 is the owner of Elevators Limited and Petitioner
No. 2 is its Branch Manager. The Respondent, who worked as a
Technician from 07.09.2012 to 07.10.2016, filed the complaint alleging
that an amount of Rs.1,77,200/- towards unpaid wages was due and
payable by the Petitioners.
4. It was further submitted that the Respondent had failed to
2 of 3 986-WP.4342.2020
establish the existence of an employer-employee relationship and,
therefore, the complaint itself was not maintainable. It was also
contended that the Advocate engaged by the Petitioners was
subsequently appointed as a Public Prosecutor and, therefore, the
matter proceeded without proper participation on behalf of the
Petitioners. Consequently, the Respondent was not cross-examined and
the complaint came to be allowed. On these grounds, it was urged that
the impugned order deserved to be set aside.
5. Though duly served, none appeared for the Respondent.
6. Upon hearing the learned Advocate for the Petitioners and on
perusal of the impugned order, it appears that the Respondent had
specifically pleaded that the Petitioners had agreed to pay him
Rs.18,000/- per month along with an allowance of Rs.800/- per floor
for each building. According to the Respondent, he had completed
work valued at Rs.4,07,200/-, out of which he had received
Rs.2,30,000/-, leaving a balance of Rs.1,77,200/-.
7. The Respondent produced his bank statements as well as the
relevant records maintained by him in support of his claim. It is
noteworthy that, after filing their written statement, the Petitioners
chose not to effectively contest the proceedings. It is also not their case
that the documents relied upon by the Respondent were fabricated or
otherwise unreliable. The statement of accounts and other records
3 of 3 986-WP.4342.2020
produced by the Respondent clearly establish his entitlement to recover
the amount of Rs.1,77,200/- from the Petitioners.
8. In view of the documentary evidence available on record, the
learned Industrial Court rightly allowed the complaint and directed
payment of the outstanding amount.
9. Considering the aforesaid circumstances, no case is made out
for interference with the order dated 14.12.2018 passed by the learned
Member, Industrial Court, Latur in Complaint (ULP) No. 16 of 2017 in
exercise of supervisory jurisdiction under Article 227 of the
Constitution of India.
10. Hence, the present petition is devoid of merit and same is
hereby dismissed. No order as to costs.
(SIDDHESHWAR S. THOMBRE, J.)
Tauseef