Bombay High Court
ASHRAF FIROZ SHAIKHversusDOST MOHAMMED GULAM MOHAMMAED ACHHWA
- Decided
- Disposal
- Dismissed
- Bench
- MADHAV JAMDAR
Holding
The court held that there is no ground for interference and the orders directing the petitioner to deposit interim compensation remain valid.
Summary
The petitioner, Ashraf Firoz Shaikh, challenged the validity of two orders—one dated 30 July 2024 directing him to pay interim compensation of Rs.13,000 per month for 52 months, and another dated 30 January 2025 confirming the same—issued by the Small Causes Court and the Trial Court. He alleged that the leave‑and‑license agreement on which the compensation claim was based was obtained through misrepresentation and that the surrender document was forged, creating a cloud on the respondent's title. The respondent, Dost Mohammed Gulam Mohammed, relied on a civil suit (S.C. Suit No.1361 of 2020) which admitted that the petitioner occupied the premises on a leave‑and‑license basis and had not paid any amount since March 2020. The trial court clarified that the order required the petitioner to deposit the stipulated amount before the court, and the appellate bench affirmed this direction. The High Court observed that the petitioner was not the owner, had occupied the property without payment for six years, and that no stay was granted against the trial court order. Consequently, the writ petition under Article 227 was dismissed for lack of merit.
Issues considered
- Whether the order directing the petitioner to pay interim compensation under the leave‑and‑license agreement is legally valid and enforceable.
- Whether the alleged misrepresentation and forged surrender document create a cloud on the respondent's title sufficient to set aside the compensation order.
- Whether a stay should have been granted against the trial court's order pending the writ petition.
- Whether the petitioner, as a non‑owner occupier, is liable to deposit the compensation despite non‑payment of rent.
Subjects
- interim compensation
- leave and license agreement
- Article 227
- Small Causes Court
- stay of execution
- property possession
- forgery allegation
Judgment
926 WP 4924.25.DOC
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
CIVIL APPELLATE JURISDICTION
WRIT PETITION NO.4924 OF 2025
Mr. Ashraf Firoz Shaikh …Petitioner
Versus
Mr. Dost Mohammed Gulam Mohammed …Respondent
Achhwa
Mr. Saiprasad R. Dudhane for Petitioner.
Mr. Hira Gumma for Respondent.
CORAM: MADHAV J. JAMDAR, J.
DATED : 13th January 2026
P.C.:
1. Heard Mr. Saiprasad Dudhane, learned Counsel for the
Petitioner and Mr. Hira Gumma, learned Counsel for the
Respondent.
2. By the present Writ Petition filed under Article 227 of the
Constitution of India, challenge is to the legality and validity of
Order dated 30th January 2025 passed by the learned Appellate
Bench of Small Causes Court, Mumbai in Revision Application No.
222 of 2024 as also Order dated 30 th July 2024 passed by the
learned Judge of Small Causes Court, Mumbai below Exhibit-8 in
L.E. Suit No. 29 of 2023.
Page 1 of 7
Dusane
926 WP 4924.25.DOC
3. By the impugned Order dated 30 th July 2024 passed by the
learned Trial Court, the present Petitioner i.e. the Defendant has
been directed to pay interim compensation from 1 st March 2020 till
30th June 2024 i.e. for 52 months @ Rs.13,000/- per month i.e. the
aggregate of amount of Rs.6,76,000/- and further directed to
deposit Rs.13,000/- per month on or before 10 th day of each
succeeding month till disposal of the suit.
4. The said Order has been confirmed by the Appellate Bench
of Small Causes Court.
5. It is the main submission of Mr. Dudhane learned Counsel
for the Petitioner that there is a cloud on the title of the
Respondent and the F.I.R. has been filed by the Petitioner against
the Respondent that the Leave and License Agreement has been
executed by misrepresentation. He further submits that there is
document of surrender of tenancy and signature of the same is
forged and fabricated.
6. On the other hand, Mr. Gumma, learned Counsel for the
Respondent points out S.C. Suit No.1361 of 2020 filed by the
Page 2 of 7
Dusane
926 WP 4924.25.DOC
present Petitioner and more particularly paragraph No.3 of the
same. He therefore submits that in fact the Petitioner has come up
with the case that there is a Leave and License Agreement executed
with the parties on 18th February 2020 and the period of said
agreement is 1st January 2020 till 30th November 2020. He submits
that admittedly from 1st March 2020 till date, not a single farthing
has been paid by the Petitioner and the Petitioner is in possession
of the suit premises.
7. Before considering the rival contentions, it is necessary to set
out certain factual aspects.
8. The Petitioner has filed S.C. Suit No. 1361 of 2020 in the
Bombay City Civil Court, seeking injunction and in the said Suit,
the Plaintiff has come up with following contentions:-
“2. The defendant is a tenant and owner of the suit
premises from which the Plaintiff has taken the same
on leave and license basis. The defendant is residing at
the address mentioned in the case title.
3. The Plaintiff states that about three and half
years back the defendant gave the suit premises to the
plaintiff on leave and license basis. However, at that
time no written agreement was executed between the
plaintiff and the defendant. The Plaintiff states that
Page 3 of 7
Dusane
926 WP 4924.25.DOC
thereafter, the defendant insisted on executing written
leave and license agreement and therefore, on 18 th
February, 2020, leave and license agreement has been
executed between the plaintiff and the defendant in
which is shown that the said agreement is deemed to
have commenced on 1st day of January, 2020 and shall
expire on 30th day of November, 2020. Hereto annexed
and marked as "EXHIBIT - A" is copy of leave and
license agreement dated 18 th February, 2020. The
Plaintiff states that he is having documents of the
defendant such as rent receipt, aadhar card, pan card,
etc. Hereto annexed and marked as "EXHIBIT B-Colly"
are copies of Rent receipt, Aadhar card and Pan card of
defendant. The plaintiff states that he is having
documents in respect of the suit premises such as
Aadhar card, Pan card and Electric bill at the address
of the suit premises. Hereto annexed and marked as
"EXHIBIT - C" is copy of Aadhar card. Hereto annexed
and marked as "EXHIBIT - D" is copy of Pan card.
Hereto annexed and marked as "EXHIBIT E" is copy of
Electric bill.”
(Emphasis added)
9. Thus what the present Petitioner in the Bombay City Civil
Court suit, stated that the present Respondent is owner of the suit
premises. The said premises has been taken by the Plaintiff on
leave and license basis. It has been further stated that about 3½
years back, the present Respondent gave the suit premises to the
Petitioner on leave and license basis, however, at that time, no
written agreement was executed and thereafter leave and license
Page 4 of 7
Dusane
926 WP 4924.25.DOC
agreement dated 18th February 2020 has been executed. The
period of said agreement is 1st January 2020 till 30th November
2020. Thus, even as per contentions raised by the present
Petitioner in Bombay City Civil Court suit, it is clear that he has
admitted that the Respondent is the owner of suit premises and the
Petitioner entered in the suit premises on leave and license basis,
initially on the basis of oral leave and license and thereafter
written agreement dated 18th February 2020. Admittedly as per
said leave and license agreement, the agreed compensation is
Rs.13,000/- per month.
10. The learned Trial Court has directed the Petitioner to deposit
said amount Rs.13,000/- per month in the Trial Court.
11. At this stage, it is required to be clarified that although
Clause No.2 of the Order dated 30 th July 2024 mentions that the
Defendant i.e. the present Petitioner is directed to pay interim
compensation, however Clause No. 3 clarifies that the direction is
to deposit the said amount. Thus, it is clear that by reading Clauses
2 and 3 clearly show that the said amount of Rs.13,000/- per
month is required to be deposited before the learned Trial Court.
Page 5 of 7
Dusane
926 WP 4924.25.DOC
12. The learned Appellate Court has confirmed said Order by
giving cogent reasons.
13. Learned Counsel for the Respondent points out Order dated
18th January 2025 passed by the learned Trial Court below Exhibit-
43 in L.E. Suit No. 29 of 2023 by which defence of the Defendant
i.e. the present Petitioner is struck out.
14. It is required to be noted that the challenge in this Petition is
to the Order dated 30th July 2024 passed by the learned Trial Court
as also Order dated 30th January 2025 passed by the learned
Appellate Bench of Small Causes Court.
15. Throughout there was no stay granted to the Order dated
30th July 2024. It is admitted position that the Petitioner has not
paid a single farthing from 1st March 2020 till date i.e. for last
about 6 years. Admittedly, the Petitioner is not the owner of the
property. He is occupying the property without making any
payment. Accordingly in the facts and circumstances, no case is
made out for interference in the impugned Order under Article 227
of the Constitution of India.
Page 6 of 7
Dusane
926 WP 4924.25.DOC
16. Accordingly, Writ Petition is dismissed, however, with no
Order as to costs.
BHALCHANDRA
GOPAL
DUSANE (MADHAV J. JAMDAR, J.)
Digitally signed by
BHALCHANDRA
GOPAL DUSANE
Date: 2026.01.14
19:41:14 +0530
Page 7 of 7
Dusane