DILIP NATHU KANK AND ORS.versusTHE STATE OF MAHARASHTRA AND ORS.

Disposal
Disposed Off

Holding

The writ petition is dismissed as vague, delayed and barred by laches, and the petitioners are directed to make a representation to the Government.

Summary

The petitioners, five individuals claiming to be project‑affected persons, filed a writ petition in 2021 seeking execution of an order dated 11 August 2000 that allegedly allotted them land under Section 16 of the Maharashtra Project Affected Persons Rehabilitation Act, 1999. The petition was filed more than two decades after the original order and contained no specific relief, family relationship details, or supporting documents, rendering it vague and incomplete. The Court observed that the delay was unexplained, the petition was hit by laches, and the relief sought could not be granted in its extraordinary writ jurisdiction. Consequently, the Court directed the petitioners to make a proper representation to the Government, which would consider any entitlement under the Act in accordance with law. The petition was dismissed, costs of ₹5,000 were imposed on the petitioners, and the accompanying interim application was also disposed.

Issues considered

  • Whether a writ petition seeking execution of a 2000 land‑allotment order can be entertained after a delay of over 20 years
  • Whether a vague and non‑specific petition is maintainable in the extraordinary writ jurisdiction of the High Court
  • Whether the doctrine of laches bars the petition
  • Whether the Court may direct the petitioners to approach the Government for relief instead of granting the writ

Legislation cited

Subjects

  • writ petition
  • delay
  • laches
  • land allotment
  • rehabilitation
  • Project Affected Persons
  • Section 16
  • Maharashtra
  • vague petition
  • costs

Judgment

                                                                            5-IA-2583-2023 (C).doc


                                  IN THE HIGH COURT OF JUDICATURE AT BOMBAY
                                           CIRCUIT BENCH AT KOLHAPUR
                                          CIVIL APPELLATE JURISDICTION

                                         WRIT PETITION NO. 5107 OF 2021

                                            Dilip Nathu Kank And Ors.
                                                      VERSUS
                                         The State of Maharashtra And Ors.


                                                  ALONG WITH
                                      INTERIM APPLICATION NO. 2583 OF 2023
                                                       IN
                                         WRIT PETITION NO. 5107 OF 2021

                                               Shivaji Dagadu Kank

                                           IN THE MATTER BETWEEN :

                                            Dilip Nathu Kank And Ors.
                                                      VERSUS
                                         The State of Maharashtra And Ors.

                                                         ...
                        Ms. Bhagyashri Mangale, Advocate for Petitioners.

                        Mr. Y. B. Lengare ( Through V.C.) a/w Mr. Rutik Kashid, Advocate for
                        the Intervenor.

                        Mr. Vikas M. Mali, AGP for the Respondent-State.
                                                         ...

                                               CORAM : MILIND N. JADHAV, &
                                                       NANDESH S. DESHPANDE, JJ.

                                               DATE    : 22nd JULY, 2026

                        P. C. :

           Digitally
           signed by
           SAJAKALI
SAJAKALI   LIYAKAT
LIYAKAT    JAMADAR
JAMADAR    Date:
           2026.07.23
                                                       1 of 5
           14:35:04
           +0530
                                                      5-IA-2583-2023 (C).doc


1.       Heard Ms. Mangale, learned Advocate for the Petitioners,

Mr.      Lengare   (Through   V.C.),     learned   Advocate     for    the

Intervenor/Applicant and Mr. Mali, learned AGP for the Respondent-

State.

2.       The present Petition No.5107 of 2021 is filed by the

Petitioners on 07.01.2021 seeking implementation of the order

dated 11.08.2000.

3.       Petitioner No.1 was 13 years old when the said order dated

11.08.2000 was passed. A copy of the said order is claimed to be

annexed at Exhibit "F" to the Petition. The allotment order,

presumably, is not in the name of Petitioner No. 1, save and except

the surname.

4.       We have reasoned with the learned Advocate, Ms. Mangale,

that the prayers in the Petition are extremely general, omnibus,

vague and insufficient. Ms. Mangale, despite repeated queries from

the Court, persisted with her submissions. Equally, while the matter

was being argued, Petitioner No.1, who was presumably present in

Court, also tried to interrupt the proceedings. We reasoned out with

Ms. Mangale and explained to her that such innocuous, incomplete,

vague and insufficient prayers, as sought in the Petition, can never



                                2 of 5
                                                   5-IA-2583-2023 (C).doc


be granted in our extraordinary writ jurisdiction. She refused to

listen and repeatedly argued the same issue, stating that the

allotment order had been passed under Section 16 of the

Maharashtra Project Affected Persons Rehabilitation Act, 1999 in

favour of the Petitioners and it required execution by way of present

Petition now filed in 2021.

5.       The delay in filing the Petition is unexplained. We do not

know whether the Petitioners before us, namely, Dilip Nathu Kank,

Alka Sanjay Sathe, Ramdas Laxman Kank, Santosh Shankar Kank

and Pandharinath Dhondiba Kank, are in any way related to

Dhondiba Madhu Kank. The name "Dhondiba" appears only in the

name of Petitioner No.5. No family tree or any other material has

been placed on record. We cannot embark upon an inquiry for all

the 5 Petitioners who have woken up from their long shumber after

almost 21 years and have filed the present Petition.       Petition is

devoid of material facts. We cannot embark upon an enquiry on

facts.    Petition is hit by delay and laches. What we gather from

Ms. Mangale is that Petitioners are project affected persons, who

have been given alternate lands, but those are inadequate. Order

passed in of the year 2000 in some other persons’ name. Execution



                                3 of 5
                                                            5-IA-2583-2023 (C).doc


is sought after 21 years without even approaching the competent

Authority.

6.     We     direct     the   Petitioners      to   make   an    appropriate

representation to the Government on the basis of the alleged order.

If any such representation is made, the Government shall deal with

the same in accordance with law with regard to any allotment to the

concerned person named in the said order and decide the same.

7.     Needless to state that any representation made by the

Petitioners shall be strictly considered by the Government in

accordance with law and on the basis of the applicable legal and

statutory requirements.

8.     For filing such vague and frivolous a Petition, we direct the

Petitioners to pay costs of ₹5,000/- to the “Bombay High Court

Kolhapur Bench Action Committee” within a period of two weeks

from today. The details of the Bank Account of the said Committee

are as under :

बँकेच नांव             : ि कमि यल को-ऑप बँक िल. को्हापूर
खातेचे नांव            : को्हापूर ि ्हा बार असोिसए न को्हापूर खंडपीठ िनधी
खाते नंबर              : 009011100000175
आय एफ.सी कोड           : HDFC0CTCCBK (अंडरलाईन केलेले ि'रो अंक आहे.)
 ाखा                   : कसबा बावडा को्हापूर.



                                     4 of 5
                                                               5-IA-2583-2023 (C).doc


           9.    Needless to state that we have not expressed any opinion on

           the substantive rights of the Petitioners. If the Petitioners are

           entitled to any additional area in rehabilitation or allotment in

           terms of the Project Affected Persons Rehabilitation Act, 1999, the

           State Government shall duly consider the representation of the

           Petitioners, if made, in accordance with law and determine the same

           strictly in accordance with law.

           10.   The Writ Petition is dismissed with the above directions.

           11.   In view of the dismissal of the Writ Petition, the Interim

           Application No.2583 of 2023 does not survive and stands disposed

           of accordingly.




           [NANDESH S. DESHPANDE, J.]                  [MILIND N. JADHAV, J.]
Sajakali




                                              5 of 5


Continue reading with your account

Sign in to read the full judgment. It’s free.

Sign in to read

Checking your session…

For a signed copy suitable for filing, refer to the court's website.