Bombay High Court
STATE BANK OF INDIA THROUGH ITS AUTHORIZED SIGNATORYversusTHE STATE OF MAHARASHTRA AND OTHERS
- Disposal
- DISPOSED OFF
Holding
The court disposed of the writ petition, directing the petitioner to decide on the compromise and approach the Tahsildar thereafter, without ordering immediate possession.
Summary
The State Bank of India filed a writ petition seeking an order directing the Tahsildar to execute a 2019 order under Section 14 of the Securitization and Reconstruction of Financial Assets and Enforcement of Security Interest Act, 2002, and to hand over possession of a secured asset. The bank indicated that the borrower had partially complied with a compromise proposal and was awaiting approval, but also warned that it would seek possession if the remaining amount was not paid. The Tahsildar attempted to hand over possession on 10 February 2026, but the bank's authorized officer was absent. The court observed that the bank must decide whether to proceed with the compromise or continue with the petition and should approach the Tahsildar again if the compromise is accepted. Consequently, the court disposed of the writ petition without ordering immediate possession.
Issues considered
- Whether the Tahsildar should be directed to execute the 2019 order for possession despite ongoing compromise negotiations.
- Whether the writ petition should be dismissed pending the bank's decision on the compromise proposal.
Legislation cited
Subjects
- writ petition
- possession
- compromise proposal
- secured asset
- Securitization Act
- Tahsildar
- enforcement of security interest
Judgment
-1-
wp90.26.odt
IN THE HIGH COURT OF JUDICATURE OF BOMBAY
BENCH AT AURANGABAD
14 WRIT PETITION NO. 90 OF 2026
State Bank of India
Through Its Authorized Signatory ….Petitioner
VERSUS
The State of Maharashtra & others …..Respondents
Mr. S. R. Deshpande, Advocate for the Petitioner.
Mr. S. B. Pulkundwar, AGP for the State.
CORAM : SMT VIBHA KANKANWADI
& HITEN S VENEGAVKAR, JJ.
DATE : 4th MARCH, 2026.
PER COURT :
1. Learned Advocate for the Petitioner has placed on record a
communication by the Petitioner to the Tahsildar and Executive
Magistrate, Gangakhed, wherein it is informed to the Tahsildar that
the borrower has submitted a compromise proposal and it appears
that even half of the amount has also been paid. It is submitted that
the said compromise proposal has been sent to the appropriate
authority for approval and it is waiting for further communication
from the appropriate authority.
2. The said letter is taken on record by marking as Exhibit ‘X’.
-2-
wp90.26.odt
3. It is further say of the Petitioner that if the borrower fails to
deposit the rest of the amount, then the bank would like to proceed
to take possession of the secured asset.
4. Here, the Petitioner has prayed that the Respondent/Tahsildar
be directed to execute the order dated 02.11.2019 passed in
Application No. 07/2019 under Section 14 of the Securitization and
Reconstruction of Financial Assets and Enforcement of Security
Interest Act, 2002 and to deliver physical possession of the secured
asset to the authorised officer of the Petitioner. Learned AGP informs
that the Tahsildar had gone to the spot on 10.02.2026 at 2.00 pm for
handing over possession of the secured asset to the Petitioner.
However, the authorised officer of the Petitioner was absent. Here, if
after the petition was filed, there are talks regarding compromise,
then the Petitioner should make up a mind as to whether to go with
the compromise or with the petition. We do not want to keep the
petition pending. Let there be a decision by the appropriate
authority of the Petitioner on the proposal of compromise and in the
event of the terms of compromise if any right arises for the Petitioner,
then the Petitioner may go before the Tahsildar once again.
-3-
wp90.26.odt
5. With these observations, we dispose of the writ petition.
( HITEN S. VENEGAVKAR ) ( SMT. VIBHA KANKANWADI )
JUDGE JUDGE
dyb
Checking your session…