BHARAT COKING COAL LTD.versusM/S. ANNAPURNA CONSTRUCTIONS
- Citation
- 2003 INSC 435
- Decided
- 29 August 2003
- Disposal
- Case Partly allowed
- Bench
- V N KHARE
Holding
The High Court could not grant interest as it was not within its revisional jurisdiction, and the arbitrator had exceeded his jurisdiction by ignoring essential contract provisions; the contractor was not estopped from raising further claims.
Summary
The parties entered into a contract for constructing 140 temporary hutments which contained an arbitration clause. After delays, the arbitrator awarded the contractor a sum with 18% interest, but the subordinate court, in making the award a rule of court, did not grant interest under Section 29 of the Arbitration Act, 1940. The contractor sought interest via a petition under Section 152 CPC, which was rejected, and the High Court later granted interest in revision, a decision the Supreme Court held to be beyond its revisional jurisdiction. The Court also ruled that the contractor was not estopped from raising further claims merely because it had accepted the final bill, and that the arbitrator had exceeded his jurisdiction by ignoring material contract clauses. It distinguished errors within jurisdiction from errors in excess of jurisdiction, holding that only the latter can invalidate an award. Consequently, the Supreme Court allowed the appeals in part, set aside the High Court's grant of interest, and referred specific disputed claim items to a retired High Court judge for fresh determination.
Issues considered
- The High Court's power to grant interest under Section 29 of the Arbitration Act, 1940 when the trial court did not.
- Whether the contractor is estopped from raising further claims after accepting the final bill.
- The scope of the arbitrator's jurisdiction and whether he exceeded it by ignoring contract clauses.
- The distinction between error within jurisdiction and error in excess of jurisdiction in arbitration awards.
- The applicability of Section 152 CPC for correcting the award as a clerical mistake.
Legislation cited
- Arbitration Act, 1940s. 14, s. 15, s. 16, s. 29, s. 30, s. 33
- Code of Civil Procedure, 1908s. 152
Subjects
Judgment
A BHARAT COKING COAL LTD.
V.
MIS. ANNAPURNA CONSTRUCTIONS
AUGUST 29, 2003
-
B [V.N. KHARE, CJ. AND S.B. SINHA, J.)
Arbitration Act, 1940; Ss. 14, 15, 16, 29 and 30:
Contract of construction-Arbitration clause-Disputes-Arbitrator
C made award with interest thereon infavour of contractor-Court while
making award a rule did not grant interest-Appeal of the company and
application for interest ofthe contractor dismissed by the trial Court-Appeal
dismissed but application for interest allowed by the High Court-Held:
Since interest was not allowed by the trial Court in terms of provision of
D law, High Court could not grant the same in exercise ofits revisional power.
Jurisdiction of the Arbitrator:
Jurisdiction-Extent of-Held: Confines to the terms ofthe contract-
Since the Arbitratorfailed to take into consideration relevant material while
E making the award, his order would amount to misdirection in law-Hence,
disputes on certain issues referred to a retired Judge of the High Court for
making award afresh-Civil Procedure Code, 1908-Section 152.
'An error within the jurisdiction' and 'an error in excess of
jurisdiction '-Distinction between-Discussed.
F
Appellant Company and the respondent-Contractor entered into
a contract for construction of hutments. The contract contained an
arbitration clause. Since the work was not completed in time and
disputes arose between the parties, the arbitration clause of the
G contract was invoked. The Arbitrator made an award in favour of the
Contractor, awarding certain sum with interest thereon. The
subordinate judge Court made award Rule of the Court but did not
allow interest. Appeal against the award and petition as well as review
petition for grant of interest were dismissed by the trial Court. High
H Court, however, allowed the revision petition and granted interest but
122
-- BHARAT COKING COAL LTD. v. ANNAPURNA CONSTRUCTIONS 123
dismissed the appeal of the company. Hence the present appeal. A
It was contended for the appellant that since the respondent had
accepted the final bill, he could not file further claim; that the running
bills were required to be adjusted out of the advance granted to
respondent; that the respondent could not claim against escalation in B
the price of the material; and that the arbitrator committed illegality
in entertaining certain claims ignoring the terms of the contract/
relevant material.
On behalf of the respondent, it was submitted that since the
appellant did not challenge the legality of the award, Supreme Court C
could not interfere in exercise of its jurisdiction under Section 30 of
the Act.
Partly allowing the appeals, the Court
HELD: 1.1. Only because the respondent has accepted the final D
bill, the same would not mean that it was not entitled to raise any claim.
In absence of a declaration that the respondent would not raise any
further claim, he cannot be held to be estopped or precluded from
raising any claim. The Court did not grant any interest in terms of
Section 29 of the Act. The same was not by way of a clerical or E
arithmetical mistakP. which could be corrected by the Court in exercise
of its power under Section 152 of the Code of Civil Procedure. Under
the circumstances, the respondent was either to prefer an appeal
thereagainst or file a review petition. As the Court could not have
exercised its jurisdiction under Section 152 of the Code of Civil F
Procedure, the High Court in exercise of its revisional jurisdiction
could not have interfered therewith. [127-H, 128-B-C]
1.2. The jurisdiction of the arbitrator must be held to be confined
to the four-corners of the contract. He could not have ignored an G
important clause in the agreement. [129-C-D)
1.3. In the instant case, the amount which was deducted by way
of penalty and found not justifiable, be refunded. While considering
the claim relating to material escalation, the arbitrator should have
taken into consideration the relevant provisions as well as relevant H
124 SUPREME COURT REPORTS (2003] SUPP. 3 S.C.R.
.
A facts contained in the agreement and also the correspondence made
between the parties. It is well settled that the arbitrator cannot act
arbitrarily, irrationally, capriciously or independent of the contract.
(129-E, 130-D-EI
Associated Engineering v. Govt. of A.P., [19911 4 SCC 93 and
B Mis. Sudarsan Trading Co. v. The Govt. ofKera/a, [198912 SCC 38, relied
on.
1.4. There lies a clear distinction between an error within the
jurisdiction and error in excess of jurisdiction. The role of the arbitrator
C is to arbitrate within the terms of the contract. He has no power apart
from what the parties have given to him under the contract. If he has
travelled beyond the contract, he would be acting without jurisdiction,
however, if he has remained inside the parameter of the contract, his
award cannot be questioned on the ground that it contains an error
apparent on the face of the record. (130-H, 131-A-BI
D
Halsbury's Laws of England 4th Edition, Vol. 2 and 'Commercial
Arbitration' by Mustill and Boyd, Page 598, referred to.
1.5. The arbitrator while passing the award in relation to some
items failed and/or neglected to take into consideration the relevant
E clauses of the contract, nor did he take into consideration the relevant
materials for the purpose of arriving at a correct fact. Such an order
would amount to misdirection in law. [138-D-EI
Alopi Parshad & Sons Ltd. v. Union of India, (19601 2 SCR 793;
F Naihati Jute Mills Ltd. v. Khyaliram Jagannath, (196811SCR821; State
of Orissa v. Dandasi Sahu, [1988) 4 SCC 12; K.P. Pou/ose v. State of
Kera/a [19751 2 SCC 236; KV George v. The Secretary to Government,
Water and Power Deptt., Trivendrum, (1989) 4 SCC 595; Satish Kumar
v. Surinder Kumar, AIR (1970) SC 833; Union ofIndia v. Jain Associates
& Anr., (1994) 4 SCC 665; Sikkim Subba Associates v. State of Sikkim,
G [2001) s sec 629; Maharashtra State Electricity Board v. Sterilite
Industries (India) & Anr., (2001) 8 SCC 482; W.B. State Warehousing
Corporation & Anr. v. Sushi! Kumar Kayan & Ors., [2002) S SCC 579;
Bharat Coking Coal Ltd v. LK Ahuja & Co., (2001) 4 SCC 86 and !spat
Engineering & Foundry Works, B.S. City, Bokaro v. Steel Authority of
H India Ltd., B.S. City, Bokaro, (2001) 6 sec 347, distinguished.
BHARAT COKING COAL LTD. v. ANNAPURNA CONSTRUCTIONS 125
Heyman v. Darwin, (1942) I All ER 327, referred to. A
2. Having regard to the fact that the matter relates to pure
interpretation of the document which gives rise to question of law and
instead and in place of remitting the matter to the named arbitrator,
the disputes in relation to claim of item Nos. 3, 7 and 11 are referred B
to Mr. Justice D.N. Prasad, a retired Judge of the Jharkhand High
Court on such terms and conditions as may be mutually agreed upon
by the parties. (138-F-G)
CIVIL APPELLATE ruRISDICTION : Civil Appeal Nos. 5647-48
of 1997. C
From the Judgment and Order dated 29.4.97 of the Patna High
Court in Appeal from Original Order No. 169/95 (R) and C.R. No. 12 of
1996 (R).
D
Ajit Kumar Sinha for the Appellant.
S.B. Upadhyay for the Respondent.
The Judgment of the Court was delivered by
E
S.B. SINHA, J : These appeals are directed against the judgment and
order dated 29.4.1997 passed by the High Court of Patna, Ranchi Bench,
Ranchi in Appea'. from Original Order No.169of1995 (R) whereby and
whereunder the appeal preferred by the appellant herein from a judgment
and order dated 3.6.1995 passed by the Subordinate Judge, 4th Court, p
Dhanbad in Title (Arbitration) Suit No.109 of 1994 was dismissed.
FACTS:
The basic fact of the matter is not in dispute. The parties hereto
entered into a contract for construction of 140 numbers of temporary G
hutments, the estimated cost of which was Rs. 49,45,447.81. A fonnal
work order was issued to the respondent herein. Entire work in tenns of
the agreement was to be completed within a period of four months.
A fonnal contract was entered into for the aforementioned work by H
126 SUPREME COURT REPORTS (2003] SUPP. 3 S.C.R.
...
A and between the parties. The said contract contained an arbitration
agreement. The said contractual job was not allegedly completed by the
respondent within the stipulated period wherefor a request was made for
extension of time till 31.12.1986 to complete the work. Further extensions
of time were sought for and granted from time to time.
B Disputes and differences having arisen between the parties, the
arbitration agreement was invoked. The Chief Engineer of the appellant-
Company was appointed as the sole arbitrator. He was to give a reasoned
award. Before the arbitrator the respondent raised a claim of
Rs. 55,01,640.66. The appellant herein also raised a counter claim for a
C sum of Rs. 28,47,860.57. By reason of an award dated 13.7.1994, the sole
arbitrator awarded a sum of Rs. 18,97,729.37 with interest @ 18% per
annum in favour of the respondent. The counter claim of the appellant,
however, was rejected.
The said award was filed before the learned Subordinate Judge,
D Dhanbad for being made a rule of court in terms of Section 14 of the
Arbitration Act, 1940 (for short 'the Act'). The appellant herein in the
said proceedings filed an objection under Sections 15, 16, 30 and 33 of
the Act. The learned trial Judge by reason of a judgment dated 3.6.1995
rejected the said objection of the appellant and made the award as rule of
E court, where-against an appeal was preferred which by reason of the
impugned judgment was dismissed.
However, it may be noticed at this stage that the learned Subordinate
Judge did not grant any interest from the date of decree in favour of the
respondent wherefor an application purported to be under Section 152 of
F the Code of Civil Procedure was filed. The said application was rejected
on 12.12.1995 where-against the respondent preferred a civil revision
application before the High Court. Both the appeal being M.A. No.169
of 1995 (R) filed by the appellant herein and Civil Revision being C.R.
No. 12 of 1996 (R) filed by the respondent herein were heard together.
G While disposing the appeal, the revison petition was allowed by the High
Court by reason of the impugned judgment.
SUBMISSIONS:
Mr. Ajit Kumar Sinha, learned counsel appearing on behalf of the
H appellant, inter alia, submitted that the respondent having accepted the
BHARAT COKING COAL LTD. v. ANNAPURNA CONSTRUCTIONS [SINHA, J.] J27
final bill, a further claim by it was inadmissible. The learned counsel A
pointed out that as a special case the appellant granted 95% advance
wherefor no interest was to be charged. The said advance was to be
adjusted from the running bills. In that view of the matter, the learned
counsel would contend that the arbitrator committed an illegality in
entertaining Claim Item Nos. 3 and 7. The learned counsel would urge B
that the respondent having been granted extension, it was obligatory on the
part of the learned arbitrator to consider as to whether the respondent was
entitled to any compensation for the alleged loss occurred on the ground
of delay in completion of work, particularly when it was agreed that the
-~
extension of time was granted subject to payment of penalty. The learned
counsel would further submit that in terms of the contract the appellant had C
been supplied with all the essential raw materials, namely, cement, steel
etc. which would cover about 95% of the total cost to be incurred for the
construction of the hutments and in that view of the matter the respondent
could not be held to be entitled to any amount by way of escalation in the
price. D
Mr. S.B. Upadhyay, learned counsel appearing on behalf of the
respondent, per contra would submit that the objections filed by the
appellant herein have been thoroughly considered by the learned Subordinate
Judge and the High Court and as such it is not a fit case wherein this Court E
should interfere. The learned counsel would urge that it is not the case
of the appellant that the learned sole arbitrator did not pass a reasoned
award and, thus, this court in exercise of its jurisdiction under Section 30
of the Act would not interfere when two views are possible. The learned
counsel would submit that while exercising its jurisdiction under Section
30 of the Act, the court does not reappraise evidences brought on record. F
Strong reliance, in this connection, has been placed on /spat Engineering
& Foundry Works, B.S. City, Bokaro v. Steel Authority of India Ltd, B.S.
City, Bokaro, [2001] 6 SCC 347.
FINDINGS:
G
Only because the respondent has accepted the final bill, the same
would not mean that it was not entitled to raise any claim. It is not the
case of the appellant that while accepting the final bill, the respondent had
unequivocally stated that he would not raise anv further claim. In absence
of such a declaration, the respondent cannot be held to be estopped or H
128 SUPREME COURT REPORTS [2003] SUPP. 3 S.C.R.
A precluded from raising any claim. We, therefore, do not find any merit
in the said submission of Mr. Sinha.
The submission of Mr. Sinha to the effect that the High Court
committed an error in granting interest from the date of the decree
B purported to be in terms of Section 29 of the Arbitration Act appears to
be correct. The learned Subordinate Judge did not grant any interest in
terms of Section 29 of the Act. The same was not by way of a clerical
or arithmetical mistake which could be corrected by the court in exercise
ofits power under Section 152 of the Code of Civil Procedure. The remedy
of the respondent, therefore, was either to prefer an appeal thereagainst or
C file a review petition. As the court could not have exercised its jurisdiction
under Section 152 of the Code of Civil Procedure, the High Court in
exercise of its revisional jurisdiction could not have interfered therewith.
So far as the question of late payment of the bills is concerned, the
D arbitrator has arrived at a finding of fact that there had been an inordinate
delay in respect of 10th RIA bill for Rs. 4,85,403.31 which was paid after
a lapse of one year from the date of completion of work on 15. 1.1988 and
a sum ofRs.54,737.53 was awarded as damages@ 12% on the said amount
for the period of 343 days to the appellant.
E So far as Claim Item No.3 is concerned, the question which arose for
)•
consideration before the arbitrator was as to whether any extra work had
been done or not. The case of the appellant was that the respondent had
not done any extra work. The arbitrator had considered the materials on
record for the purpose of arriving at a finding of fact that certain extra
F work had been done by the respondent wherefor only a sum of
Rs. 84,942.02 was awarded in place and instead of Rs. 1,58,862.26.
However, Mr. Sinha is correct in his submission that the learned
arbitrator has not taken into consideration the effect and purport of the
G following clause in the contract:
"Provided always that :
(a) Contractor/Contractors shall not be entitled to any payment
for any additional work done unless he/they have received
H an order in writing from the Superintending Engineer/Sr.
.•
BHARAT COKING COAL LTD. v. ANNAPURNA CONSTRUCTIONS [SINHA, I.] 129
Executive Engineer/Executive Engineer for such additional A
work;
(b) The contractor/contractors shall be bound to submit his/their
claim for any such additional work done during any month
on or before the 15th day of the following month accompanied B
by the additional work; and
(c) The contractor/contractors shall not be entitled to any
payment in respect of such additional work if he/they fail to
submit his/their claim within the aforesaid period."
The question is as to whether the claim of the contractor is de hors
c
the rules or not was a matter which fell for consideration before the
arbitrator. He was bound to consider the same. The jurisdiction of the
arbitrator in such a matter must be held to be confined to the four-comers
of the contract. He could not have ignored an important clause in the
agreement; although it may be open to the arbitrator to arrive at a finding D
on the materials on records that the claimant's claim for additional work
was otherwise justified.
Claim Item No. 4 was rejected.
The award in respect of Claim Item No. 5 is not in question. Claim E
Item No. 6 was in relation to penalty amount of Rs. 10,000 which was
deducted by way of penalty and was not found to be justifiable, and as such
the appellant was directed to refund the said amount.
We are furthermore concerned with Claim Item Nos. 7 and 11 which F
are under the headings of 'Losses due to prolongation of work' and
'Material Escalation'. It is not in dispute that a secured advance of 95%
of the cost of materials was given in terms of the contract which is to the
following effect :
"Secured Advance will be paid @ 95% of the cost of materials G
as a special case to get the work completed within 4(four) months
as per latest price list of BCCL (copy enclosed), subject to
submissions of Indemnity Bond on non-Judicial stamp paper of
required value in the approved proforma of BCCL and also
Insurance against fire, theft and damages etc. The secured advance H
130 SUPREME COURT REPORTS (2003] SUPP. 3 S.C.R.
A will be paid only on the items on which it was payable in BCCL.
The secured advance thus paid, will be recovered in five equal
instalments from the subsequent running account bills or on the
consumption of materials whichever is earlier."
B The appellant does not dispute the same. It is also not in dispute that
the appellant has not charged any interest in respect of the said advance.
It is further not in dispute that cement @ Rs. 51 per bag, mild steel rounds
@ Rs. 5460 per metric tonne and tor steel @ Rs. 5810 per metric tonne
were supplied by the appellant. However, the claim relating to material
escalation was confined to six articles whicr were allegedly not supplied
C by the appellant, namely, bricks, AC sheets, angles, doors, frames and
shutters etc.
So far as these items are concerned, in our opinion, the learned sole
arbitrator should have taken into consideration the relevant provisions
D contained in the agreement as also the correspondences passed between the
parties. TI1e question as to whether the work could not be completed within
the period of four months or the extension was sought for on one condition
or the other was justifiable or not, which are relevant facts which were
required to be taken into consideration by the arbitrator.
E It is now well settled that the Arbitrator cannot act arbitrarily,
irrationally, capriciously or independent of the contract.
In Associated Engineering v. Govt. of A.P., (1991] 4 SCC 93, this
Court clearly held that the arbitrators cannot travel beyond the parameters
F of the contract. In Mis. Sudarsan Trading Co. v. The Govt. of Kera/a,
[I 989] 2 SCC 18, this Court has observed that an award may be remitted
or set aside on the ground that the arbitrator in making it had exceeded
his jurisdiction and evidence of matters not appearing on the face of it, will
be admitted in order to establish whether the jurisdiction had been
exceeded ~r not, because the nature of the dispute is something which has
G been determined outside the award, whatever might be said about it in the
award by the Arbitrator. This Court further observed that an arbitrator
acting beyond his jurisdiction is a different ground from the error apparent
on the face of the award.
H There lies a clear distinction between an error within the jurisdiction
BHARAT COKING COAL LTD. r. ANNAPURNA CONSTRUCTIONS [SINHA, l.] 131
and error in excess of jurisdiction. Thus, the role of the arbitrator is to A
arbitrate within the terms of the contract. He has no power apart from what
the parties have given him under the contract. If he has travelled beyond
the contract, he would be acting without jurisdiction, whereas if he has
remained inside the parameter of the contract, his award cannot be
questioned on the ground that it contains an error apparent on the face of B
the records.
In paragraph 577 of Halsbury's laws of England 4th Edition Vol 2,
the law has been stated in the following terms:
"As an arbitrator (and subsequently any umpire) obtains his C
jurisdiction solely from the agreement for his appointment it is
never open to him to reject any part of that agreement, or to
disregard any limitations placed on his authority, as, for example,
a limitation on his right to appoint an umpire. Nor can he confer
jurisdiction upon himself by deciding in his own favour some D
preliminary point upon which his jurisdiction depends. Nevertheless
he is entitled to consider the question whether or not he has
jurisdiction to act in order to satisfy himself that it is worth while
to proceed, and an award which expressly or impliedly refers to
such a finding is not thereby invalidated." E
In 'Commercial Arbitration' by Mustill and Boyd at page 598 it is
stated :
"in the first place, it could be argued that an arbitrator who is
appointed in respect of a dispute arising under a contract expressly F
or impliedly governed by English law is authorised by the parties
to pronounce upon the issues in accordance with that law, and in
no other way. Any decision which proceeds, on a different basis
lies outside the scope of the arbitrator's mandate to bind the
parties. The award is accordingly void for want of jurisdiction, G
since the arbitrator has done something which the parties never
authorised him to do. Secondly, it would be possible to draw
support from a line of authority culminating in three important
decisions during the past decade which approach the question
whether a tribunal can effec~ively decide contrary to law by using
the word 'jurisdiction' in the first of the three senses indicated H
.!
132 SUPREME COURT REPORTS [2003] SUPP. 3 S.C.R.
A above. Whilst a reconciliation of this decision is a matter for a
treatise on administrative law, there is no doubt that in relation
to certain kinds of tribunal the law has recognised a distinction
between errors of law which go to jurisdiction and those which
do not, and that there is a difference between tribunal which has
arrived at a decision by asking itself the wrong question, and one
B which has correctly identified the question, but has supplied the
wrong answer in terms oflaw. Following up this line of authority,
it could be said that an arbitrator empowered to decide the rights
of the parties under a contract governed by English law, who asks
himself not what England law has to say about those right, but
c what the rights ought to be if assessed in accordance with his own
ideas of an extra-legal concept of justice, is either asking himself
the wrong question, or not really asking a question at all."
In Alopi Parshad & Sons Ltd. v. Union of India [1960] 2 SCR 793,
this Court clearly held that if damages are awarded ignoring the expressed
D terms of the contract, the arbitrator would commit misconduct of the
proceedings. Reference in this connection may also be made to Naihati Jute
Mills Ltd. v. Khya/iram Jagannath, [1968] 1 SCR 821.
In Heyman v. Darwin, (1942) I All ER 327, it was held that arbitrator
E as a rule cannot clothe himself with the jurisdiction when it has none.
In paragraph 622 at pages 330-331 Halsbury's Laws of England (4th
Edn) Vol. 2 it has been stated but misconduct occurs, for example;
{I) If the arbitrator or umpire fails to decide all the matters which
F were referred to him.
(2) If by his award the arbitrator or umpire purports to decide
matters which have not in fact been included in the agreement
of reference, for example, where the arbitrator construed the lease
(wrongly), instead of determining the rental and the value of
G buildings to be maintained on the land; or where the award
contains unauthorised directions to the parties, or where the
arbitrator, has power to direct what shall be done but his directions
affect the interest of third persons; or where he decided to the
parties rights, not under the contract upon which the arbitration
H had proceeded but under another contract;
SHARAT COKING COAL LTD. v. ANNAPURNA CONSTRUCTIONS [SINHA, J.] 133
(3) If the award is inconsistent, or is uncertain or ambiguous, or A
even if there is some mistake of fact, although in that case the
mistake must be either admitted or at least clear beyond any
reasonable doubt;"
f
In Associated Engineering (supra), it has been held:
B
"If the arbitrator commits an error in the construction of the
contract, that is an error within his jurisdiction. But if he wanders
outside the contract and deals with matters not allotted to him, he
commits a jurisdiction error. Such error going to his jurisdiction
can be established by looking into material outside the award. C
Extrinsic evidence is admissible in such cases because the dispute
is not something which arises under or in relation to the contract
or dependent on the construction of the contract or to be determined
within the award. The dispute as to jurisdiction is a matter which
is outside the award or outside whatever may be said about it in
the award. The ambiguity of the award can, in such cases, be D
resolved by admitting extrinsic evidence. The rationale of this rule
is that the nature of the dispute is something which has to be
determined outside and independent of what appears in the award.
Such jurisdictional error needs to be proved by evidence extrinsic
to the award. E
In the instant case, the umpire decided matters strikingly outside
his jurisdiction. He outstepped the confines of the contract. He
wandered far outside the designated area. He digressed far away
from the allotted task. His error arose not by misreading or
misconstruing or misunderstanding the contract, but by acting in F
excess of what was agreed. It was an error going to the root of
his jurisdiction because he asked himself the wrong question,
disregarded the contract and awarded in excess of his authority.
In many respects, the award flew in the face of provisions of the
contract to the contrary. G
The umpire, in our view, acted unreasonably, irrationally and
capriciously in ignoring the limits and the clear provisions of the
contract. In awarding claims which are totally opposed to the
provisions of the contract to which he made specific reference in
allowing them, he has misdirected and misconducted himself by H
134 SUPREME COURT REPORTS [2003] SUPP. 3 S.C.R.
A manifestly disregarding the limits of his jurisdiction and the
bounds of the contract from which he derived his authority
thereby acting ultra fines compromissi."
In State of Orissa v. Dandasi Sahu, [1988] 4 SCC 12, this Court
observed:
B
"In our opinion, the evidence of such state of affairs should make
this Court scrutinise the award carefully in each particular case
but that does not make the court declare that all high amounts of
award would be bad per se."
c In K.P. Poulose v. State of Kera/a, [1975] 2 SCC 236, this Court
observed that the case of legal misconduct would be complete if the
arbitrator on the face of the award arrives at an inconsistent conclusion
even on his own finding or arrives at a decision by ignoring the very
material documents which throw abundant light on the controversy to help
D a just and fair decision.
In K. V. George v. The Secretary to Government, Water and Power
Dept, Trivendrum, [1989] 4 SCC 595, this Court held :-
"In the instant case, the contract was terminated by the respondents
E on April 26, 1980, and as such all the issues arose out of the
tem1ination of the contract and they could have been raised in the
first claim petition filed before the Arbitrator by the Appellant.
This having not been done the second claim petition before the
Arbitrator raising the remaining disputes is clearly barred. With
F regard to the submission as to the applicability of the principles
of res judicata as provided in Section 11 of the Code of Civil
Procedure to arbitration case, it is to be noted that Section 41 of
the Arbitration Act provides that the provisions of the Code of
Civil Procedure will apply to the Arbitration proceedings. The
provisions of res judicata are based on the principles that there
G
shall be no multiplicity of proceedings and there shall be finality
of proceedings. This is applicable to the arbitration proceedings
as well."
This Court referred to the decision in Satish Kumar v. Surinder
H Kumar, AIR (1970) SC 833 and held:
BHARAT COKING COAL LTD.'" ANNAPURNA CONSTRUCTIONS [SINHA, J.] 135
"The true legal position in regard to the effect of an award is not A
in dispute. It is well settled that as a general rule, all claims which
are the subject-matter of a reference to arbitration merge in the
award which is pronounced in the proceedings before the arbitrator
and that after an award has been pronounced, the rights and
liabilities of the parties in respect of the said claims can be B
determined only on the basis of the said award. After an award
is pronounced, no action can be started on the original claim
which had been the subject-matter of the reference ....... This
conclusion, according to the learned Judge, is based upon the
elementary principle that, as between the parties and their privies,
an award is entitled to that respect which is due to judgment of C
a court of last resort. Therefore, if the award which has been
pronounced-between the parties has in fact, or can in law, be
deemed to have dealt with the present dispute, the second
reference would be incompetent. This position also has not been
and cannot be seriously disputed." D
In Union ofIndia v. Jain Associates and Anr. [ 1994] 4 SCC 665, this
Court upon following K.P. Poulose (supra) and Dandasi Sahu (supra)
held:
"8. The question, therefore, is whether the umpire had E
committed misconduct in making the award. It is seen that claims
11 and 12 for damages and loss of profit are founded on the breach
of contract and Section 73 encompasses both the claims as
damages. The umpire, it is held by the High Court, awarded
mechanically, different amounts on each claim. He also totally
failed to consider the counter-claim on the specious plea that it F
is belated counter-statement. These facts would show, not only the
state of mind of the umpire but also non-application of the mind,
as is demonstrable from the above facts. It would also show that
he did not act in a judicious manner objectively and dispassionately
which would go to the root of the competence of the arbitrator G
to decide the disputes."
In Sikkim Subba Associates v. State ofSikkim, [2001] 5 SCC 629, this
Court held:
"It would be difficult for the courts to either exhaustively define H
136 SUPREME COURT REPORTS [2003] SUPP. 3 S.C.R.
A the word "misconduct" or likewise enumerate the line of cases in
which alone interference either could or could not be made.
Courts of law have a duty and obligation in order to maintain
purity of standards and preserve full faith and credit as well as
to inspire confidence in alternate dispute redressal method of
arbitration, when on the face of the award it is shown to be based
B
upon a proposition of law which is unsound or findings recorded
which are absurd or so unreasonable and irrational that no
reasonable or right-thinking person or authority could have
reasonably come to such a conclusion on the basis of the materials
on record or the governing position of law to interfere."
c
In Maharashtra State Electricity Board v. Sterilite Industries (India)
and Anr., [2001] 8 SCC 482, it was observed:
"In the light of this enunciation of law, we are of the view that
D unless the error of law sought to be pointed out by the learned
counsel for the petitioners in the instant case is patent on the face
of the award, neither the High Court nor this Court can interfere
with the award. The exercise to be done by examining clause
14(ii) of the contract entered into between the parties, construing
the same properly and thereafter applying the law to it to come
E
to a conclusion one way or the other, is too involved a process
and it cannot be stated that such an error is apparent or patent on
the face of the award. Whether under the context of the terms and
conditions of a contract, a stipulation in the form and nature of
clause 14(ii) operates as a special provision to the exclusion of
F Section 73 of the Indian Contract Act is a matter of appreciation
of facts in a case, and when the decision thereon is not patently
absurd or wholly unreasonable, there is no scope for interference
by courts dealing with a challenge to the award."
G In W.B. State Warehousing Corporation and Another v. Sushi/ Kumar
Kayan and Others, [2002] 5 SCC 679, this Court opined:
"In order to determine whether the arbitrator has acted in excess
of his jurisdiction what has to be seen is whether the claimant can
H raise a particular claim before the arbitrator. If there is a specific
BHARAT COKING COAL fro. v. ANNAPURNA CONSTRUCTIONS [SINHA, J.] 13 7
term in the contract or the law which does not permit the parties A
to raise a point before the arbitrator and if there is a specific bar
in the contract to the raising of the point, then the award passed
by the arbitrator in respect thereof would be in excess of his
jurisdiction."
The High Court was, therefore, required to consider, the objections B
filed by the Appellant herein from the aforementioned points of view.
Bharat Coking Coal Ltd v. L.K. Ahuja & Co., (2001] 4 SCC 86,
whereupon Mr. Sinha has placed strong reliance cannot be held to be
applicable in this case as therein the court was concerned with hybrid C
award. The court was not in a position to ascertain as to whether escalation
charges had been made against the materials supplied by the principal or
also other materials.
It is no doubt true that the jurisdiction of this Court while considering
the validity of an award is limited as has been stated by this Court in /spat D
Engineering & Foundry Works (supra):
"4. Needless to record that there exists a long catena of cases
through which the law seems to be rather well settled that the
reappraisal of evidence by the court is not permissible. This Court E
in one of its latest decisions Arosan Enterprises Ltd. v. Union of
India, [1999] 9 SCC 449 upon consideration of decisions in
Champsey Bhara & Co. v. Jivraj Ba/loo Spg. & Wvg. Co. Ltd.
AIR(l923) PC 66: (1923)AC 480, Union ofIndia v. Bungo Steel
Furniture (P) Ltd, AIR (1967) SC 1032 : (1967] I SCR 324,
N. Chellappan v. Secy., Kera/a SEB, [1975] I SCC 289, Sudarsan F
Trading Co. v. Govt. of Kera/a, [1989] 2 SCC 38, State of
Rajasthanv. Puri Construction Co. Ltd., [1994] 6 SCC485 as also
in Olympus Superstructures (P) Ltd v. Meena Vijay Khetan,
(1999] 5 sec 651 has stated that reappraisal of .evidence by the
court is not permissible and as a matter of fact, exercise of power G
to reappraise the evidence is unknown to a proceeding under
Section 30 of the Arbitration Act. This Court in Arosan Enterprises,
(1999] 9 sec 449 categorically stated that in the event of there
being no reason in the award, question of interference of the court
would not arise at all. In the event, however, there are reasons, H
138 SUPREME COURT REPORTS [2003) SUPP. 3 S.C.R.
A interference would still be not available unless of course, there
exist a total perversity in the award or the judgment is based on
a wrong proposition of law. This Court went on to record that in
the event, however, two views are possible on a question of law,
the court would not be justified in interfering with the award of
B the arbitrator ifthe view taken recourse to is a possible view. The
observations of Lord Dunedin in Champsey Bhara, AIR (1923)
PC 66: (1923) AC 480 stand accepted and adopted by this Court
in Bungo Steel Furniture AIR (1967) SC 1032 : [1967] I SCR
324 to the effect that the court had no jurisdiction to investigate
into the merits of the case or to examine the documentary and oral
c evidence in the record for the purposes of finding out whether or
not the arbitrator has committed an error of law. The court as a
matter of fact, cannot substitute its own evaluation and come to
the conclusion that the arbitrator had acted contrary to the bargain
between the parties."
D
However, as noticed hereinbefore, this case stands on a different
footing, namely, that the arbitrator while passing the award in relation to
some items failed and/or neglected to take into consideration the relevant
clauses of the contract, nor did he take into consideration the relevant
E materials for the purpose of arriving at a correct fact. Such an order would
amount to misdirection in law.
We are, therefore, of the opm10n that the matter requires
reconsideration. Having regard to the facts and circumstances of this case
and particularly keeping in view the fact that the matter relates to pure
F interpretation of document which gives rise to question of law and instead
and in place of remitting the matter to the named arbitrator, we would direct
that the disputes in relation to Claim item Nos. 3, 7 and 11 be referred to
Hon'ble Mr. Justice D.N. Prasad, a retired Judge of the Jharkhand High
Court on such terms and conditions as may be mutually agreed upon by
G the parties. The learned arbitrator is requested to consider the desirability
of making his award as expeditiously as possible keeping in view the fact
that the matter has been pending for a long time.
These appeals are allowed to the aforementioned extent. No costs.
H S.K.S. Appeals partly allowed.
.
Search Indian case law
Ask in plain English, not just keywords. 25,000 AI words free, no card.