FOOD CORPORATION OF INDIAversusM/S. A.M. AHMED & CO. AND ANR.
2006 INSC 75331 October 2006Case Partly allowed
The Food Corporation of India (FCI) awarded a contract to A.M. Ahmed & Co. for cargo‑handling services without an escalation clause. During the contract, the State Government raised statutory wages, and the contractor sought additional payment for the increased labour cost. An arbitrator was appointed, who allowed the …
DEO NARAIN CHOUDHURYversusSHREE NARAIN CHOUDHURY
2000 INSC 49731 October 2000Dismissed
The appellant and respondent, brothers, were in dispute over a property and referred the matter to arbitration. An arbitral award was made on 21 January 1996 and filed in the Sub‑Judge's court on 14 May 1996. The respondent filed a caveat on 11 June 1996 seeking notice before any order, but the court only issued its st…
STATE OF TAMIL NADU, ETC. ETC.versusL. ABU KAVUR BAI AND ORS. ETC.
1983 INSC 16831 October 1983Disposed off
The Supreme Court examined the constitutionality of the Tamil Nadu Stage Carriages and Contract Carriages (Acquisition) Act, 1973, which sought to nationalise stage and contract carriage services and their assets. Operators challenged the Act as violative of Articles 14, 19 and 31, alleging it was confiscatory and lack…
SMITA CONDUCTORS LTD.versusEURO ALLOYS LTD.
2001 INSC 41731 August 2001Dismissed
Smita Conductors Ltd. (appellant) and Euro Alloys Ltd. (respondent) entered into contracts for the supply of aluminium rods that contained an arbitration clause but were never signed by the appellant. The appellant opened irrevocable letters of credit and made shipments, but later invoked a force‑majeure clause after R…
MADAN MOHAN RAJGARHIAversusM/S. MAHENDRA R. SHAH & BROS. AND ANR.
2003 INSC 34931 July 2003Dismissed
Madan Mohan Rajgarhia, a non‑member trader, sued M/s Mahendra R. Shah & Bros., a broker and member of the Bombay Stock Exchange, for recovery of Rs.5,63,334. The respondents invoked Section 34 of the Arbitration Act, 1940, seeking a stay on the ground that the dispute fell within the arbitration clause printed on the e…
STATE OF U.P.versusALLIED CONSTRUCTIONS
2003 INSC 35031 July 2003Disposed off
The State of Uttar Pradesh contracted Allied Constructions to build a bridge-cum-fall, but a flood in August 1991 damaged the partially completed work. Allied claimed loss and obtained an arbitral award of Rs.12,55,365 with interest. The State contended that Clause 47 of the contract, a force‑majeure provision covering…
ANSAL ENGINEERING PROJECTS LTD.versusTEHRI HYDRO DEVELOPMENT CORPORATION LTD. AND ANR.
1996 INSC 80731 July 1996Dismissed
Ansal Engineering Projects Ltd entered into a construction contract with Tehri Hydro Development Corporation Ltd (THDC) and furnished a bank guarantee of Rs 57,57,970 issued by UCO Bank in favor of THDC. After THDC terminated the contract, it invoked the guarantee and demanded payment. Ansal sought an injunction under …
JAMMU & KASHMIR STATE FOREST CORPORATIONversusABDUL KARIM WANI
1989 INSC 11331 March 1989Appeal(s) allowed
The Jammu & Kashmir State Forest Corporation awarded a timber extraction contract to Abdul Karim Wani for 6 lakh cft. Wani later claimed entitlement to the remaining 4.08 lakh cft based on alleged custom, practice and assurances, which the Corporation denied. Wani filed an application under the Jammu & Kashmir Arbitrat…
K.N. SATHYAPALAN (DEAD) BY LRS.versusSTATE OF KERALA AND ANR.
2006 INSC 93130 November 2006Appeal(s) allowed
The appellant, K.N. Sathyapalan (deceased) by legal representatives, entered into a construction contract with the State of Kerala. The work could not be completed within the stipulated eleven months due to law‑and‑order disturbances, lack of a suitable quarry and dumping yard, and the State’s failure to remove anti‑so…
DANDASI SAHUversusSTATE OF ORISSA
1989 INSC 36930 November 1989Dismissed
The contractor Dandasi Sahu claimed payment for work and interest before an arbitrator, later filing a supplemental claim and a consolidated abstract totalling Rs.31.44 million. The arbitrator awarded a lump sum of Rs.25.00 million with 9% interest, which the State of Orissa challenged. The High Court set aside the awa…
ASIA RESORTS LTD.versusUSHA BRECO LTD.
2001 INSC 54030 October 2001Disposed off
Asia Resorts Ltd. contracted Usha Breco Ltd. to install a ropeway system which failed to meet specifications. Asia Resorts issued a notice on 17 April 1990 and received a definitive denial on 17 May 1990, after which it filed a petition under Section 20 of the Arbitration Act on 30 November 1993. The Supreme Court held…
ASHUTOSHversusSTATE OF RAJASTHAN AND ORS.
2005 INSC 39030 August 2005Disposed off
A decree for a construction work claim was passed against the State of Rajasthan and the partnership firm Sharma & Co. The State recovered the decree amount and sought execution against the firm’s securities, including a house owned by partner Smt. Dhanwanti Devi, who had earlier executed a will bequeathing the house t…
UMRI POOPH PRATAPPUR (UPP) TOLLWAYS PVT. LTD.versusM.P. ROAD DEVELOPMENT CORPORATION AND ANOTHER
2025 INSC 90730 July 2025Disposed off
Umri Pooph Pratappur (UPP) Tollways Pvt. Ltd. entered into a 2012 concession agreement with Madhya Pradesh Road Development Corporation (MPRDC) for a state highway project. Disputes over cost overruns and delays led the appellant to first file a reference before the Madhya Pradesh Arbitration Tribunal under the 1983 Ac…
M/S CHAHAL ENGINEERING CONSTRUCTION CO.versusIRRIGATION DEPARTMENT, PUNJAB, SIRSA
1993 INSC 25130 July 1993Disposed off
The appellant, Mis Chahal Engineering, entered a turn‑key lump‑sum contract with the Punjab Irrigation Department to construct an aqueduct. Design changes increased quantities, and the contractor claimed extra payment, leading to arbitration. The first arbitrator treated the contract as having shifted from lump‑sum to …
LACHHMAN DASSversusRAM LAL & ANR.
1989 INSC 11130 March 1989Appeal(s) allowed
Lachhman Dass and Ram Lal entered into an arbitration agreement to settle a land dispute. The arbitrator awarded that half of the appellant's share in the land would now belong to the respondent, effectively creating a new right in immovable property valued over Rs 100. The award was filed for making it a rule of court…
URMILA DEVI & ORS.versusBRANCH MANAGER, NATIONAL INSURANCE COMPANY LTD. & ANR.
2020 INSC 10730 January 2020Appeal(s) allowed
The claimants filed a claim under the Motor Vehicles Act after the husband/father suffered a road accident, and the Motor Vehicle Accidental Claim Tribunal ordered the National Insurance Company to pay Rs.2,47,500. The insurer appealed to the Patna High Court, challenging its liability to pay, and the claimants filed a…
PARADIP PORT TRUST AND ORS. ETC.versusUNIQUE BUILDERS ETC.
2001 INSC 5030 January 2001Case Partly allowed
Paradip Port Trust entered into a scrap‑sale agreement with Unique Builders that contained an arbitration clause. Disputes were referred to an arbitrator who awarded a lump‑sum of Rs 8,51,315 with interest, without giving reasons and based solely on documentary evidence. The Sub‑Judge set aside the award under Sections…
STATE BANK OF INDIAversusRAM DAS AND ANR.
2003 INSC 58129 October 2003Dismissed
The State Bank of India entered into a construction contract with a contractor that contained an arbitration clause. An umpire awarded Rs. 15.85 lakh to the contractor in 1984, then filed the award himself in the Hyderabad Civil Court and engaged a lawyer to conduct the proceedings, making the award a rule of court. Th…
PRABHU SHANKAR JAISWALversusSRI SHEO NARAIN JAISWAL
1996 INSC 125029 October 1996Appeal(s) allowed
The appellant and several respondents were partners in an unregistered partnership firm and a suit for dissolution and accounts was filed by one partner. The partnership deed contained an arbitration clause, leading the appellant to obtain a stay of the suit under Section 34 of the Arbitration Act and to file a petitio…
GURU NANAK FOUNDATIONversusRATTAN SINGH & SONS
1981 INSC 17529 September 1981Case Allowed
The parties entered into a building contract containing an arbitration clause. After a series of applications and a change of arbitrator, the Supreme Court appointed the final arbitrator and gave directions for the conduct of the arbitration. The arbitrator made an award on 11 November 1977 and, on advice of a court of…
JINDAL VIJAYANAGAR STEEL (JSW STEEL LTD.)versusJINDAL PRAXAIR OXYGEN COMPANY LTD.
2006 INSC 56429 August 2006Dismissed
The appellant, JSW Steel, was setting up a steel plant in Bellary, Karnataka and entered into a pipeline supply agreement with the respondent, Jindal Praxair, which contained an arbitration clause specifying Bombay as the seat of arbitration. A dispute arose and the respondent filed a petition under Section 9 of the Ar…
BHARAT COKING COAL LTD.versusM/S. ANNAPURNA CONSTRUCTIONS
2003 INSC 43529 August 2003Case Partly allowed
The parties entered into a contract for constructing 140 temporary hutments which contained an arbitration clause. After delays, the arbitrator awarded the contractor a sum with 18% interest, but the subordinate court, in making the award a rule of court, did not grant interest under Section 29 of the Arbitration Act, …
SURESH RAGHO DESAI & ANR.versusSMT. VIJAYA VINAYAK GHAG & ANR.
1988 INSC 24829 August 1988Dismissed
The petitioners, Suresh Ragho Desai and another, participated in an arbitration proceeding in 1979 without objection and an award was rendered in 1981. They later challenged the award on the ground that it was unreasoned and that relevant documents had not been considered. The Bombay High Court dismissed the challenge,…
SECRETARY TO THE GOVERNMENT, TRANSPORT DEPTT., MADRASversusMUNUSWAMY MUDALIAR & ORS.
1988 INSC 25129 August 1988Appeal(s) allowed
The Secretary to the Government of Tamil Nadu sought to enforce a bridge construction contract, while the contractor claimed damages and refund of earnest money. The contract contained an arbitration clause naming the Superintending Engineer of the relevant circle as arbitrator. During arbitration the arbitrator was tr…
S. RAJANversusSTATE OF KERALA AND ANOTHER
1992 INSC 18529 July 1992Dismissed
The appellant, a contractor, entered into a 1966 agreement with the State of Kerala to complete work within ten months, but failed to do so and the contract was terminated in 1968. The State served a demand notice under the Revenue Recovery Act on 30 May 1974, which the appellant contested by a writ petition. In 1983 t…
M/S UMESH GOELversusHIMACHAL PRADESH COOPERATIVE GROUP HOUSING SOCIETY LTD.
2016 INSC 45729 June 2016Appeal(s) allowed
The appellant, an unregistered partnership firm, entered into a construction contract with the respondent and later contested the respondent's claim in arbitration. The respondent argued that Section 69(3) of the Partnership Act, 1932 barred the firm from participating in arbitral proceedings because "other proceedings…
NATIONAL ALUMINIUM CO. LTD. & ANR.versusG.C. KANUNGO
2009 INSC 64629 April 2009Appeal(s) allowed
National Aluminium Co. Ltd. & Anr. (appellant) entered into a works contract with G.C. Kanungo (respondent). After completion of the work, the respondent sought arbitration for additional dues, and an arbitrator appointed at his request passed an award. The civil judge later made the award a rule of court. The appellan…
G. RAMACHANDRA REDDY AND CO.versusCHIEF ENGINEER, MADRAS ZONE, MILITARY ENGINEERING SERVICE
1994 INSC 18129 April 1994
The appellant, G. Ramachandra Reddy & Co., invoked clause 17 of its contract with the respondent, the Chief Engineer of the Military Engineering Service, to have a sole arbitrator appointed. After the respondent failed to appoint an arbitrator despite a notice, the appellant filed a suit under Section 20 of the Arbitra…
MINERALS & METALS TRADING CORPORATION OF INDIA LTD.versusOCEAN KNIGH MARITIME CO. LTD. AND OTHERS
2012 INSC 15229 March 2012Appeal(s) allowed
The appellant, Minerals & Metals Trading Corporation of India Ltd., entered into a charter party with Ocean Knight Maritime Co. Ltd., which contained an arbitration clause. Disputes over demurrage led each party to appoint its own arbitrator, but the arbitrators could not reach a consensus and the award deadline expire…
INTERNATIONAL AIRPORT AUTHORITY OF INDIAversusK.D. BALI & ANOTHER
1988 INSC 8929 March 1988Dismissed
The International Airport Authority of India (IAAI) entered into a construction contract that contained an arbitration clause. When disputes arose, the Chief Engineer appointed K.D. Bali as sole arbitrator under the Arbitration Act, 1940. IAAI later challenged the arbitrator’s authority, alleging bias and seeking revoc…
STATE OF HARYANA & ORS.versusS. L. ARORA & COMPANY
2010 INSC 6929 January 2010Appeal(s) allowed
The State of Haryana awarded a construction contract to S.L. Arora & Co., which was completed late, leading to arbitration. The arbitrator awarded Rs 14.94 lakh with 12% simple interest from 19‑Dec‑1990 to the award date and future interest of 18% per annum on the "total amount of award" if not paid within 30 days. The…
STATE OF ORISSAversusB.N. AGARWALLA
1997 INSC 7729 January 1997Dismissed
The Supreme Court examined whether an arbitrator under the Arbitration Act, 1940 could award interest for three distinct periods – pre‑reference, pendente lite, and post‑award – in light of the Interest Act, 1978 and contractual terms. It held that an arbitrator may award pre‑reference interest only when the dispute ar…
U.P HOTELS ETC.versusU.P. STATE ELECTRICITY BOARD
1988 INSC 33428 October 1988Case Allowed
U.P. Hotels entered into a bulk‑supply agreement with Agra Electric Supply Co. which was later taken over by the U.P. State Electricity Board (SEB). The SEB unilaterally imposed a uniform tariff under section 49 of the Electricity Supply Act, 1949, withdrawing agreed discounts. The dispute was referred to arbitration; …
HINDUSTAN CONSTRUCTION CO. LTD.versusSTATE OF JAMMU AND KASHMIR
1992 INSC 22528 August 1992Appeal(s) allowed
Hindustan Construction Co. Ltd. entered into a bridge‑construction contract with the State of Jammu & Kashmir and, after disputes, the matter was referred to arbitration. The arbitrators awarded the contractor on several items, including full amounts on items 2 and 5 and interest on the total claim, but the Jammu & Kas…
S. HARCHARAN SINGHversusUNION OF INDIA
1990 INSC 25828 August 1990Disposed off
S. Harcharan Singh was contracted to perform hard‑rock cutting for a bridge project at a fixed rate of Rs 129 per 1,000 cft. The work required far more cutting than anticipated, and the contractor claimed a higher rate of Rs 200 per 1,000 cft for the additional work. The dispute over four claims was referred to arbitra…
M/S. SUMITOMO HEAVY INDUSTRIES LIMITEDversusOIL & NATURAL GAS COMPANY
2010 INSC 44428 July 2010Appeal(s) allowed
The appellant, Sumitomo Heavy Industries, entered into a turn‑key offshore platform contract with the respondent, ONGC, which contained a clause (17.3) obligating the respondent to compensate the contractor for any necessary and reasonable extra cost caused by a change in Indian law after the bid closing date. After th…
KAMAL PUSHP ENTERPRISESversusD.R. CONSTRUCTION COMPANY
2000 INSC 36228 July 2000Dismissed
Kamal Pushp Enterprises (appellant) had a contract with Gas Authority of India Ltd. and subcontracted the work to D.R. Construction Company (respondent), an unregistered partnership under the Partnership Act, 1932. A dispute led to arbitration under the Arbitration Act, 1940, and the arbitrator awarded in favour of the…
SH. BHUPINDER SINGH BINDRAversusUNION OF INDIA AND ANR.
1995 INSC 42928 July 1995Dismissed
The dispute arose under a contract that named the Superintending Engineer, Planning Circle, Chandigarh as the arbitrator. After the arbitrator was appointed and began his duties, the contractor (appellant) complained that the arbitrator delayed the award and sought the court’s intervention to revoke his appointment and…
P. ANAND GAJAPATHI RAJU AND ORS.versusP.V.G. RAJU (DIED) AND ORS.
2000 INSC 16428 March 2000Disposed off
During the pendency of an appeal, the parties executed an arbitration agreement and sought to have the Supreme Court refer the dispute to arbitration under Section 8 of the Arbitration and Conciliation Act, 1996. The Court examined whether the phrase "which is the subject of an arbitration agreement" required the agree…
FOOD CORPORATION OF INDIA & ANR.versusGREAT EASTERN SHIPPING CO. LTD.
1988 INSC 8828 March 1988Dismissed
The Food Corporation of India entered into a charter‑party with Great Eastern Shipping for bulk cargo transport and later disputed demurrage and overtime charges. The contract required joint arbitration, each party appointing an arbitrator; the appellant’s arbitrator was instructed in writing to give reasons for his aw…
THE STATE OF J & K AND ANR.versusDEV DUTT PANDIT
1999 INSC 35827 August 1999Case Partly allowed
The State of Jammu & Kashmir terminated a measurable‑item rate contract with contractor Dev Dutt Pandit after less than 50% of the work was completed and the contractor filed a petition under Section 20 of the Arbitration Act. An arbitrator awarded Rs. 20,08,000 based on a final bill prepared from measurements taken by…
HINDUSTAN STEEL WORKS CONSTRUCTION LTD.versusC. RAJASEKHAR RAO
1987 INSC 18527 July 1987
Hindustan Steelworks Construction Ltd entered into a contract with C. Rajasekhar Rao for certain works. Disputes arose and, after the appointed arbitrators could not agree, the Supreme Court directed the appointment of party‑appointed arbitrators and, in case of disagreement, an umpire (Justice Jaganmohan Reddy). The u…
UNION OF INDIAversusR. B. CH RAGHUNATH SINGH & CO.
1979 INSC 13127 July 1979Dismissed
The Union of India appealed against R.B. Ch. Raghunath Singh & Co. under the Arbitration Act, 1940, seeking appointment of an arbitrator after the designated Director of Storage post was abolished and the Chief Commissioner refused to act. The issue was whether the court could fill the vacancy under Section 8(1)(b) of …
D.D. SHARMAversusUNION OF INDIA
2004 INSC 31627 April 2004
The Union of India invited tenders for six bridges and incorporated an arbitration clause. The contractor D.D. Sharma submitted a tender with conditional offers of rebates subject to the award of a 10% interest‑free advance and timely allotment of the work. The Union failed to hand over the site on time, leading the co…
SRI K. MARAPPAN (DEAD) THROUGH SOLE LR. BALASUBRAMANIANversusTHE SUPERINTENDING ENGINEER T.B.P.H.L.C. CIRCLE ANANTAPUR
2019 INSC 40627 March 2019Case Partly allowed
The State invited tenders for irrigation works and the appellant, having quoted the lowest rates, entered into three contracts. He later raised nine claims, of which the arbitrator awarded several and rejected others. The State sought to set aside the award under sections 30 and 33 of the Arbitration Act, 1940, and the…
RAMACHANDRA REDDY AND CO.versusSTATE OF ANDHRA PRADESH AND ORS.
2001 INSC 12027 February 2001
The appellant, a contractor, claimed a higher rate for extra hard‑rock excavation under a government contract, invoking Clause 63 and alleged an error apparent on the face of the arbitral award. The arbitral panel had rejected the claim, and the trial court remitted the award for reconsideration under Section 16 of the…
K. ARUMUGA VELAIAHversusP.R. RAMASAMY AND ANR.
2022 INSC 10327 January 2022Dismissed
The appellant‑plaintiff, K. Arumuga Velaiyah, claimed a one‑fourth share in ancestral joint family property based on a 1994 will of his grandfather, Periyaiya Servai, and sought partition and separate possession. The lower courts dismissed the suit, holding that a partition had already been effected in 1964 by a pancha…
VISHNU BHAGWAN AGRAWAL & ANR.versusNATIONAL INSURANCE CO. LTD.
2017 INSC 105426 October 2017Appeal(s) allowed
The appellant, Vishnu Bhagwan Agrawal, insured jute stock with National Insurance Co. and later purchased additional jute, seeking an increase in the sum insured. The insurer did not formally acknowledge the increase, leading to a dispute over whether the policy was effectively amended and whether the value of the jute…
M/S. S.B.P. AND CO.versusM/S. PATEL ENGINEERING LTD. AND ANR.
2005 INSC 52626 October 2005Disposed off
The case concerned the nature of the power exercised by the Chief Justice of a High Court or the Chief Justice of India under Section 11(6) of the Arbitration and Conciliation Act, 1996 to appoint arbitrators when parties fail to do so. The petitioners argued that this power is judicial, requiring the Chief Justice to …
NATIONAL AGRICULTURAL COOPERATIVE MARKETING FEDERATION OF INDIA LTD.versusALIMENTA S.A.
1988 INSC 32626 October 1988Dismissed
The National Agricultural Cooperative Marketing Federation of India Ltd. entered into two contracts with Swiss firm Alimenta S.A. for groundnut supplies, but a government export ban prevented performance. The first contract contained an arbitration clause, leading Alimenta to invoke arbitration through FOSFA, while the…
J.K JAIN AND ORS.versusDELHI DEVELOPMENT AUTHORITY AND ORS.
1995 INSC 59926 September 1995Dismissed
The Delhi Development Authority (DDA) invited tenders for steel bars and accepted a tender from J.K. Jain and others for 10,000 metric tonnes. The parties executed a formal agreement that incorporated the tender form and expressly stated that the terms and conditions of the tender form would be binding. Clause 14 of th…
DEPUTY COLLECTOR NORTHERN SUBDIVISION, PANAJIversusCOMMUNIDADE OF BAMBOLIM
1995 INSC 42126 July 1995Appeal(s) allowed
The State sought enhanced compensation for land acquired at Bambolim, Goa, and filed an appeal against the Civil Court's award on August 25, 1967. The Government Pleader was uncertain whether to pursue the appeal under the Portuguese Code (Recurso de Apelacao) or the Code of Civil Procedure (CPC), which had been extend…
SUPERINTENDING ENGINEER AND ORS.versusB. SUBBA REDDY
1999 INSC 20426 April 1999Appeal(s) allowed
The appellant (Superintending Engineer) and respondent (B. Subba Reddy) entered into four contracts which were later arbitrated, resulting in awards that granted damages for delay and interest at 18% per annum on the total award, EM Deposit, Bank Guarantee and damages. The Principal Subordinate Judge, applying the rule…
SARDAR SINGHversusSMT. KRISHNA DEVI AND ANR.
1994 INSC 17226 April 1994
Sardar Singh claimed a half‑share in a house purchased by his brother Kartar Lal, which was later sold by Kartar Lal to Joginder Nath (respondent). A private arbitration award declared that both brothers were co‑owners, each holding an equal share, but the award was not registered. The respondent sued for specific perf…
SUNDER KUKREJA & ORS.versusMOHAN LAL KUKREJA & ANR.
2009 INSC 41126 March 2009Appeal(s) allowed
The brothers Sunder Kukreja and Mohan Lal Kukreja, partners in a firm, disputed the validity of a retirement deed that one brother claimed dissolved the partnership. The appellant filed a petition under Section 20 of the Arbitration Act, 1940 seeking appointment of an arbitrator under the arbitration clause of their 19…
SATWANT SINGH SODHIversusSTATE OF PUNJAB AND ORS.
1999 INSC 13626 March 1999Appeal(s) allowed
The appellant, S.S. Sodhi, entered into a construction contract with the State of Punjab and disputes arose, leading to arbitration. The arbitrator first issued an interim award on 26 November 1992 for Item No. 1 and later a final award on 28 January 1994 covering the same item. Both awards were sought to be made the r…
M/S. P. DASARATHARAMA REDDY COMPLEXversusGOVERNMENT OF KARNATAKA AND ANOTHER
2013 INSC 72125 October 2013Disposed off
The appellant, a contractor, was awarded a bridge construction contract by the Government of Karnataka. Disputes arose and the contract’s Clause 29 required any dispute to be first referred to the Chief Engineer or a Designated Officer, whose decision was subject to court remedy. The contractor applied under Sections 1…
FORASOLversusOIL & NATURAL GAS COMMISSION (AND VICE VERSA)
1983 INSC 16225 October 1983Disposed off
Forasol, a French company, entered into a drilling contract with ONGC that required most payments in French Francs and 20% in Indian rupees at a fixed rate. After the rupee was devalued, Forasol claimed a higher conversion rate, which the arbitrator awarded without specifying a rate for the Franc portion. The Delhi Hig…
TEHRI HYDRO DEV. CORPN. LTD.& ANR.versusJAI PRAKASH ASSO. LTD.
2012 INSC 42025 September 2012Case Partly allowed
The parties entered into a contract for works on the Tehri Hydro Dam project. After completion, the final bill and a security deposit of Rs.12.50 lakhs remained unpaid, leading to arbitration under the contract’s arbitration clause. The first arbitration awarded Rs.10.17 lakhs for the final bill but held the security‑d…
STATE OF A.P. AND ORS.versusM/S. PIONEER BUILDERS, A.P.
2006 INSC 65225 September 2006Case Partly allowed
The State of Andhra Pradesh awarded a canal construction contract to Mis. Pioneer Builders, which later failed to complete the work and was expelled. The contractor filed a petition under Sections 8 and 20 of the Arbitration Act, 1940, seeking arbitration or a civil suit, and later applied for amendment of the plaint, …
MALIK BROTHERSversusNARENDRA DADHICH AND ORS.
1999 INSC 35725 August 1999Appeal(s) allowed
The Indore Development Authority conducted a public auction of a government land parcel; the appellant, Malik Brothers, was the highest bidder but failed to pay the balance, leading to forfeiture of the premium. The appellant challenged the forfeiture and the Authority referred the dispute to an arbitrator, who awarded…
STATE OF ORISSA & ORS.versusLALL BROTHERS
1988 INSC 24025 August 1988Dismissed
The State of Orissa contracted Lall Brothers to complete a minor irrigation project, which was finished late. Disagreements over the final payment led the contractor to invoke the arbitration clause, resulting in the appointment of an arbitrator who awarded a lump sum of Rs. 14.67 lakh with interest. The State challeng…
M/S ISPAT ENGINEERING AND FOUNDRY WORKS, B.S. CITY, BOKAROversusM/S STEEL AUTHORITY OF INDIA LTD. B.S. CITY, BOKARO
2001 INSC 31625 July 2001Appeal(s) allowed
Mis Ispat Engineering & Foundry Works (appellant) and Mis Steel Authority of India Ltd (respondent) referred their disputes to two arbitrators, whose disagreement led to an umpire being appointed. The umpire issued a non‑speaking award directing the respondent to pay Rs 2,44,000 to the appellant, which was made a rule …
J.G. ENGINEER'S PVT. LTD.versusCALCUTTA IMPROVEMENT TRUST AND ANR.
2002 INSC 4825 January 2002Appeal(s) allowed
J.G. Engineer's Pvt. Ltd., a contractor, had its contract with Calcutta Improvement Trust (CIT) terminated on the basis of an engineer's certificate alleging non‑completion of work. The dispute was referred to arbitration, where the arbitrator held that the termination was wrongful and awarded the contractor Rs 24.8 mi…
MUNICIPAL CORPORATION, JABALPURversusKRISHI UPAJ MANDI SAMITI AND ANR.
1990 INSC 1725 January 1990Appeal(s) allowed
The Jabalpur Municipal Corporation levied property, sanitation, water, electricity and development taxes on buildings within a market (Mandi) administered by the Krishi Upaj Mandi Samiti, which claimed the corporation lacked jurisdiction. The corporation commenced recovery proceedings; the Samiti filed a petition under…
MAHANAGAR TELEPHONE NIGAM LTD.versusM/S. APPLIED ELECTRONICS LTD.
2016 INSC 105924 November 2016Directions issued
Mahanagar Telephone Nigam Ltd. appealed a Delhi High Court order that had held the Code of Civil Procedure (CPC) applicable to an appeal under Section 37 of the Arbitration and Conciliation Act, 1996 and had entertained a cross‑objection under Order XLII Rule 22 CPC. The Supreme Court examined whether the 1996 Act is a…
STATE OF ORISSAversusB.N. AGARWALA
1992 INSC 32224 November 1992Case Partly allowed
The State of Orissa contracted B.N. Agarwala to construct an irrigation project. After completion, Agarwala claimed extra work payments, and the dispute was referred to the Superintending Engineer, who acted as sole arbitrator and awarded Rs.1,59,298, including Rs.61,086.61 as interest for the period from 10‑Oct‑1969 t…
INDIAN OIL CORPORATION LTD. & ORS.versusM/S. RAJA TRANSPORT (P) LTD.
2009 INSC 106924 August 2009Appeal(s) allowed
The dispute arose from a dealership agreement between Indian Oil Corporation Ltd. (the appellant) and M/s. Raja Transport (P) Ltd. (the respondent) which contained an arbitration clause mandating that any dispute be referred to the Director, Marketing of the corporation or a person nominated by him. After the corporati…
FIRM RAJASTHAN UDYOG & ORS.versusHINDUSTAN ENGINEERING & INDUSTRIES LTD.
2020 INSC 36224 April 2020Appeal(s) allowed
The appellant partnership firm owned 249.60 bighas of land that was slated for acquisition by the State of Rajasthan for the benefit of the respondent company. An agreement dated 01.02.1980 provided that about 145 bighas would be sold to the respondent, with the price to be fixed by arbitration. The sole arbitrator fix…
HIND BUILDERS ETC.versusUNION OF INDIA AND VICE-VERSA
1990 INSC 15324 April 1990Appeal(s) allowed
The contractors (Hind Builders) were awarded Rs.57,47,198 by two arbitrators for work on the Metro Railway Project, including Rs.6,76,540 as interest. The Calcutta High Court reduced the award on two grounds: the amount for earth consolidation (item c(xii)) and the period for pendente lite interest. The Supreme Court h…
M. DAYANAND REDDYversusA.P. INDUSTRIAL INFRASTRUCTURE CORPORATION LTD. AND ORS.
1993 INSC 11524 March 1993Dismissed
M. Dayanand Reddy, a Class I contractor, entered into a contract with A.P. Industrial Infrastructure Corporation Ltd on 11‑December‑1986 for constructing a sewer line. When disputes arose, Reddy invoked an arbitration clause he claimed existed in Clause 3 of a copy of the agreement (Ex A‑3) that referenced the standard…
MAJOR (RETD.) INDER SINGH REKHIversusDELHI DEVELOPMENT AUTHORITY
1988 INSC 8524 March 1988Appeal(s) allowed
Major (Retd.) Inder Singh Rekhi constructed 240 Janta houses for the Delhi Development Authority, completing the work on 2 April 1980. After the work was finished, he repeatedly requested the Authority to finalise the bills, sending the first letter on 28 February 1983 and a final notice on 4 September 1985, and therea…
SVENSKA HANDELSBM'KEN AND OTHERS ETC.versusINDIAN CHARGE CHROME LTD. AND OTHERS
1994 INSC 2224 January 1994
The plaintiff (borrower) sued the suppliers, lenders and guarantor over a power‑plant project, invoking credit agreements that contained arbitration clauses. The lenders, particularly Svenska Handelsbanken (defendant No. 4), instructed their counsel not to appear or take any step in the main suit, limiting a power of a…
VISHWANATH SOODversusUNION OF INDIA & ANR.
1989 INSC 2624 January 1989Appeal(s) allowed
Vishwanath Sood contracted with the Union of India and the State of Himachal Pradesh to construct a Farmers' Community Centre. The contract contained Clause 2, which imposed a penalty compensation for delay to be determined solely by the Superintending Engineer, and Clause 25, which provided for arbitration of disputes…
GUJARAT WATER SUPPLY & SEWERAGE BOARDversusUNIQUE ERECTORS {GUJARAT) (P) LTD. & ANR.
1989 INSC 2824 January 1989Disposed off
The Gujarat Water Supply & Sewerage Board entered into contracts with Unique Erectors for a water‑supply scheme and later referred disputes arising under clause 30 of the contract to arbitration. A sole arbitrator was appointed, decided the arbitrability of the claims, and issued a lump‑sum award on 8 July 1985, which …
M/S. DURGA RAM PRASADversusGOVT. OF ANDHRA PRADESH
1994 INSC 53923 November 1994Dismissed
The appellant, a contractor, entered into a contract to construct a food‑grains godown for the Government of Andhra Pradesh. The engineer withheld part of the payment alleging that the work was not executed as per the contract. The dispute was referred to an arbitrator who awarded the contractor the withheld sum togeth…
DELTA DISTILLERIES LIMITEDversusUNITED SPIRITS LIMITED & ANR.
2013 INSC 64923 September 2013Dismissed
Delta Distilleries supplied Indian Made Foreign Liquor to United Spirits under a contract that made the buyer responsible for sales tax. A dispute arose over a set‑off/refund claimed by Delta from the Sales Tax Department, which United Spirits argued reduced its tax burden. The arbitral tribunal allowed United Spirits …
PAM DEVELOPMENTS PRIVATE LIMITEDversusTHE STATE OF WEST BENGAL & ANR.
2024 INSC 62823 August 2024
Pam Developments Private Ltd entered into a work contract with the State of West Bengal for road widening, which was completed after a five‑month delay. The contractor claimed several sums, including labour charges for uneconomical stoppage, interest on delayed payment of running‑account bills, and pre‑reference intere…
STATE OF PUNJAB AND ORS.versusOM PARKASH BALDEV KRISHAN
1988 INSC 23523 August 1988Dismissed
The Punjab Public Works Department invited tenders for a high‑level bridge. The lowest bidder, Om Prakash Baldev Krishan, was told by the Executive Engineer that his tender was accepted and was asked to sign a pending agreement within ten days, but no agreement was ever executed and the acceptance was not made in the n…
OIL AND NATURAL GAS COMMISSIONversusM/S M.C. CLELLAND ENGINEERS S.A.
1999 INSC 20023 April 1999Dismissed
The Oil and Natural Gas Commission (ONGC) appealed a decree based on an arbitral award that required M.C. Clelland Engineers to pay the principal amount plus interest at 12% and an additional interest on that interest. The appellant argued that the arbitrators had no power to award interest on interest under Section 3 …
PANCHU GOPAL BOSEversusBOARD OF TRUSTEES FOR PORT OF CALCUTTA
1993 INSC 16423 April 1993Dismissed
Panchu Gopal Bose entered into an arbitration agreement on 27 May 1978 to complete work within nine months. He claimed he sent bills on 12 July 1979 but received no payment, and only on 28 November 1989 did he issue a notice invoking arbitration. The respondent filed an arbitration suit under sections 5, 12 and 33 of t…
M/S. LADLI CONSTRUCTION CO. (P) LTD.versusPUNJAB POLICE HOUSING CORPN. LTD. AND ORS.
2012 INSC 10223 February 2012Dismissed
The appellant, Ladli Construction Co., entered into a contract to build 240 houses for the Punjab Police Housing Corporation, but failed to meet the schedule and the contract was rescinded. The parties' agreement contained an arbitration clause (Clause 25A) naming the Corporation's Chief Engineer as arbitrator. The con…
M/S.AGRI GOLD EXIMS LTD.versusM/S. SRI LAKSHMI KNITS & WOVENS AND ORS.
2007 INSC 6923 January 2007Dismissed
The appellant and respondents entered into a Memorandum of Understanding containing an arbitration clause. Disputes arose over post‑dated cheques, two of which were dishonoured, and the appellant filed a money decree suit. The respondents moved to refer the matter to arbitration; the trial court dismissed the applicati…
SANGANER DAL AND FLOUR MILLversusF.C.I. AND. ORS.
1991 INSC 27022 October 1991Dismissed
THE STATE OF JHARKHAND AND ORS.versusM/S. HINDUSTAN CONSTRUCTION CO. LTD.
2017 INSC 97722 September 2017Matter referred to larger bench
The Supreme Court, hearing Civil Appeal No. 1093 of 2006, examined whether it could entertain an application under Section 34 of the Arbitration and Conciliation Act, 1996 to make an arbitral award a rule of the Court when the Court itself had retained seisin over the arbitration proceedings. The award, rendered by a r…
M/S. CONTINENTAL CONSTRUCTION LTD.versusSTATE OF U.P.
2003 INSC 50022 September 2003Appeal(s) allowed
Continental Construction Ltd. entered into a contract with the State of Uttar Pradesh for dam construction. A dispute arose over claims for extra earth and rock, which were referred to arbitration. The respondent failed to appoint an arbitrator, so the appellant's arbitrator acted as sole arbitrator, and later the matt…
EXECUTIVE ENGINEER IRRIGATION GALIMALA & ORS.versusABAADUTA JENA
1987 INSC 25922 September 1987Disposed off
The Supreme Court examined whether an arbitrator, appointed without court intervention, could award interest for the period before the reference and for the pendente lite period of the arbitration. It held that an arbitrator is not a court within the meaning of CPC s.34 and therefore cannot award pendente lite interest…
M/S. S.D. SHINDE TR. PARTNERversusGOVT. OF MAHARASHTRA AND ORS
2023 INSC 75122 August 2023Appeal(s) allowed
The appellant, a construction contractor, entered into a contract with the Government of Maharashtra for earth work on a canal, which was not completed within the stipulated 18 months and required several extensions. After disputes over payment arose, the contractor sought appointment of an arbitrator under the contrac…
STATE OF ORISSAversusDANDASI SAHU
1988 INSC 18422 July 1988Dismissed
The State of Orissa contracted Dandasi Sahu for an irrigation project; after completion and final payment, Sahu claimed extra work and invoked the arbitration clause. The arbitrator awarded Rs 15,23,657 plus interest without giving reasons. The Sub‑ordinate Judge set aside the award, but the Orissa High Court restored …
STATE OF RAJASTHAN & ANR.versusMIS. FERRO CONCRETE CONSTRUCTION PVT. LTD.
2009 INSC 58022 April 2009Appeal(s) allowed
The State of Rajasthan entered into a contract with Ferro Concrete for a water‑pipeline project. After the contractor failed to complete the work, arbitration was instituted and the arbitrator awarded various sums, including loss of profit (claim 1), idle‑machinery compensation (claim 37A), and interest at 18% per annu…
MADHO S/O SHRIHARI DESHPANDEversusMADHAO S/O TRIMBAK DHARMADHIKAREE
1988 INSC 11722 April 1988Appeal(s) allowed
The dispute involved an arbitration award concerning properties mainly located in Warora, Chandrapur, with a small portion in Nagpur. The arbitrator, a resident of Nagpur, filed the award in the Nagpur Civil Court. The Civil Judge held that only the Nagpur property and the arbitrator's residence did not confer jurisdic…
SESH NATH SINGH & ANR.versusBAIDYABATI SHEORAPHULI CO-OPERATIVE BANK LTD. AND ANR.
2021 INSC 19922 March 2021Dismissed
The petitioners, Sesh Nath Singh and others, challenged the National Company Law Tribunal's (NCLT) order admitting a Section 7 application by Baidyabati Sheoraphuli Co‑operative Bank to initiate corporate insolvency resolution against the corporate debtor. The issue was whether the three‑year limitation period for fili…
UNION OF INDIAversusM/S G.S. ATWAL, AND CO. (ASANSOLE)
1996 INSC 29622 February 1996Appeal(s) allowed
The Union of India entered into a contract with M/s G.S. Atwaland Co. for excavation work, and a dispute over equipment hire charges was referred to a sole arbitrator, T. Raja Ram, in the fifth arbitration. The arbitrator unilaterally enlarged the reference to include additional claims not originally pleaded and issued…
M/S KOHINOOR TRANSPORTERSversusSTATE OF UTTAR PRADESH
2018 INSC 73121 August 2018Disposed off
The dispute arose from an arbitral award dated 20 July 1984 under the Arbitration Act, 1940, which was made a rule of the court and later reduced in interest rate. The appellant sought execution of the award, and the State (respondent) deposited Rs 75,65,945, after which the executing court ordered the State to deposit…
M/S KOHINOOR TRANSPORTERSversusSTATE OF UTTAR PRADESH
2018 INSC 73121 August 2018
An arbitral award dated 20 July 1984, made a rule of the court in 1986, was being executed when the State of Uttar Pradesh deposited Rs 75,65,945 and was later directed by the executing court to deposit an additional Rs 1,25,16,969.56, which the State objected to. The State filed a civil revision, and the High Court, i…
ELECTRONICS CORPORATION OF INDIA LTD.versusELECTRONICS CORPORATION OF INDIA SERVICE ENGINEERS UNION
2006 INSC 53121 August 2006Appeal(s) allowed
The Electronics Corporation of India Ltd. engaged about 30 technicians as retainers (service engineers/licencees) on individual contracts between 1972 and 1978. The retainers later demanded permanent absorption, regularisation and parity of pay with regular employees. The Industrial Tribunal held that no employer‑emplo…
BIHAR STATE MINERAL DEVELOPMENT CORPN. AND ANR.versusENCON BUILDERS (I) PVT. LTD.
2003 INSC 40921 August 2003Dismissed
Bihar State Mineral Development Corporation (appellant) awarded a contract to ENCON Builders (respondent) for excavation work. The respondent failed to perform, leading the corporation to re‑allocate the work and incur losses. Clause 60 of the contract stipulated that any dispute would be decided by the Managing Direct…
GWALIOR DUGDHA SANGH SAHAKARI LTD.versusG.M. GOVT. MILK SCHEME, NAGPUR AND ORS.
2003 INSC 41121 August 2003Disposed off
Gwalior Dugdha Sangh Sahakarj Ltd, a society registered under the Madhya Pradesh Co-operative Societies Act, entered into milk supply agreements with the Government Milk Scheme, Nagpur, which were executed in Maharashtra. The agreements contained an arbitration clause designating the Dairy Development Commissioner, Bom…
FOOD CORPORATION OF INDIA AND ORSversusE. KUTTAPPAN
1993 INSC 22121 June 1993Appeal(s) allowed
The Food Corporation of India and others (appellants) sued E. Kutiappan (respondent) under Section 20 of the Arbitration Act, 1940 for appointment of an arbitrator. Arbitrator B.S. Hegde made awards on 3 Oct 1988 and, at the respondent’s request, sent the award to the respondent’s counsel, who filed it in the Kerala Hi…
M/S. MUKUND LTD.versusHINDUSTAN PETROLEUM CORPORATION LTD.
2006 INSC 23821 April 2006Disposed off
Mukund Ltd appealed against an arbitral award that ordered it to pay Rs 1.26 crore plus costs and post‑decree interest at 11% per annum to Hindustan Petroleum. The Bombay High Court reduced the quantum to Rs 71.3 lakhs but retained the 11% interest rate. Mukund sought further relief, contending that the award should be…
EAST INDIA HOTELS LTD.versusAGRA DEVELOPMENT AUTHORITY
2001 INSC 16221 March 2001Appeal(s) allowed
The dispute between East India Hotels Ltd. and Agra Development Authority was referred to arbitration, and the umpire filed the award on 13 November 1998, which the trial court made a rule of court on 25 February 1999. The respondent challenged the award in a revision, arguing that the court had not complied with Secti…
PREMIER FABRICATORS, ALLAHABADversusHEAVY ENGINEERING CORPN. LTD., RANCHI
1997 INSC 30421 March 1997Appeal(s) allowed
Premier Fabricators entered into a contract with Heavy Engineering Corp. that contained an arbitration clause. Disputes over items 2‑5 of the claim were referred to two arbitrators, who agreed the items were arbitrable but could not agree on the merits, so they appointed an umpire. The umpire issued a non‑speaking awar…
INDER SAIN MITTALversusHOUSING BOARD HARYANA AND ORS.
2002 INSC 9621 February 2002Appeal(s) allowed
The Housing Board filed civil suits against contractor I.S. Mittal, and the court appointed a Superintending Engineer as arbitrator. The arbitrator was transferred during the proceedings but continued the arbitration and issued an award. The Board objected under Section 30 of the Arbitration Act, 1940, claiming the arb…
BHARAT COKING COAL LTD.versusM/S I.K. AHUJA AND CO.
2001 INSC 10221 February 2001Disposed off
Bharat Coking Coal Ltd. awarded two construction contracts to L.K. Ahuja & Co. which later led to disputes and were referred to a sole arbitrator, M.P. Sharma, a former officer of the employer. The arbitrator issued hybrid awards that largely relied on joint statements but decided only the material‑escalation claim, le…
UP STATE ELECTRICITY BOARDversusSEARSOLE CHEMICALS LTD.
2001 INSC 10321 February 2001Dismissed
The Uttar Pradesh State Electricity Board entered into a contract with Searsole Chemicals Ltd for continuous 24‑hour electricity supply, with a proviso exempting the Board from liability for interruptions caused by accidents, government orders, strikes, etc. A dispute arose and, under the contract’s arbitration clause,…
BHARAT BHUSHAN BANSALversusU.P. SMALL INDUSTRIES CORPORATION LTD., KANPUR
1999 INSC 1821 January 1999Dismissed
The appellant entered into a construction contract with the respondent that contained clauses making the decisions of the Executive Engineer and the Managing Director final and binding on the parties. Disputes arose over payments and work, and the appellant sought appointment of an arbitrator under Section 8 of the Arb…
M/S SANT RAM AND COMPANYversusTHE STATE OF RAJASTHAN AND ORS.
1996 INSC 134720 November 1996Dismissed
The appellant, a contractor, entered into a contract with the State of Rajasthan for bridge widening works. A dispute arose and, by mutual agreement, the matter was referred to an arbitrator. While arbitration was pending, the respondent attempted to adjust amounts due to the appellant against another contract. The app…
UNION OF INDIA & ANR.versusM/S DEEPAK ELECTRIC & TRADING COMPANY & ANR.
2011 INSC 77520 October 2011Appeal(s) allowed
The Union of India and another appealed against a High Court order that held its objections to an arbitral award were time‑barred. The award was filed on 17‑06‑1996 and a notice of filing was served on the Union of India, but not on the Executive Engineer, who was responsible for the Union’s affairs in the arbitration.…
UNION OF INDIAversusPRINCE MUFFAKAM JAH AND ORS.
1994 INSC 47120 October 1994Dismissed
The dispute concerned jewellery belonging to two trusts created by the Nizam of Hyderabad. An arbitration award directed the Union of India to pay Rs 180 crore to purchase the items, which was challenged by the Union and the trustees under Sections 15 and 16 of the Arbitration Act, 1940. Public‑spirited intervenors fil…
UNION OF INDIAversusPRINCE MUFFAKAM JAH AND ORS.
1994 INSC 47220 October 1994
The case concerned 173 items of jewellery belonging to the Nizam of Hyderabad, held in two trusts, which the Union of India sought to purchase under the Antiquities and Art Treasures Act. The parties entered a compromise agreement to resolve all disputes by arbitration, and the umpire fixed a just price of Rs 225,37,33…
M/S LAXMI CONTINENTAL CONSTRUCTION CO.versusSTATE OF U.P. & ANR.
2021 INSC 49820 September 2021Appeal(s) allowed
The appellant, M/s Laxmi Continental Construction Co., entered into a contract with the State of Uttar Pradesh that contained an arbitration clause (Clause 52) appointing a sole arbitrator who must be a Superintending Engineer or higher. The appointed arbitrator, Shri S.S. Manocha, retired during the arbitration procee…
RAJASTHAN STATE MINES AND MINERALS LTD.versusEASTERN ENGINEERING ENTERPRISES AND ANR.
1999 INSC 42520 September 1999Appeal(s) allowed
Rajasthan State Mines and Minerals Ltd. entered into a turnkey contract with Eastern Engineering Enterprises that contained clauses fixing the rate of payment and expressly prohibiting any extra claims. The contractor later claimed escalation and other additional payments, which the arbitrator allowed in a non‑speaking…
M/S. FAIR AIR ENGINEERS PVT. LTD. AND ANR.versusN.K. MODI
1996 INSC 91020 August 1996Appeal(s) allowed
M/s. Fair Air Engineers Pvt. Ltd. entered into a contract with N.K. Modi to install a centrally air‑conditioned plant in his house. After alleged breach, the respondent filed a complaint before the State Consumer Commission, which stayed the proceedings and ordered the parties to arbitrate under clause 12 of the agreem…
RELIANCE CELLULOSE PRODUCTS LTD.versusOIL AND NATURAL GAS CORPORATION LTD.
2018 INSC 62320 July 2018Disposed off
Reliance Cellulose Products Ltd. and ONGC entered into a contract for supply of CMC. A dispute arose over the price, which was referred to arbitration. The arbitrator fixed a higher price and awarded pre‑reference, pendente‑lite and future interest at 18% per annum. The Civil Judge reduced the interest to 10% and the G…
PRASUN ROYversusCALCUTTA METROPOLITAN DEVELOPMENT AUTHORITY & ANR.
1987 INSC 17620 July 1987Appeal(s) allowed
The parties entered into a contract containing an arbitration clause that named the Director/Unit Head of the Calcutta Metropolitan Development Authority as the sole arbitrator. The appellant, fearing bias, applied under Section 20 of the Arbitration Act, 1940, for the appointment of an independent arbitrator, and the …
M.P. HOUSING BOARDversusPROGRESSIVE WRITERS & PUBLISHERS
2009 INSC 37520 March 2009Dismissed
The M.P. Housing Board and Progressive Writers & Publishers entered into three successive agreements concerning the construction and ownership of a press complex. The third agreement of 31 May 1980 required full payment by 31 October 1980, failing which it would be cancelled. The Board alleged the arbitrator exceeded h…
VISAKHAPATNAM PORT TRUSTversusM/S CONTINENTAL CONSTRUCTION COMPANY
2009 INSC 23020 February 2009Disposed off
The Supreme Court examined two appeals arising from a High Court judgment involving Visakhapatnam Port Trust (VPT) and M/s Continental Construction Company. The first appeal concerned a claim of Rs 74,810.38 for recovered jack‑rods, which the Court held was time‑barred under Section 37 of the Arbitration Act, 1940 and …
UTKAL COMMERCIAL CORPORATIONversusCENTRAL COAL FIELDS LTD
1999 INSC 1520 January 1999Appeal(s) allowed
Utkal Commercial Corporation entered into a contract with Central Coal Fields Ltd to supply alumina ferric, which expired in August 1975. A dispute arose and the appellant served a notice on 12 September 1976 demanding the respondent concur in the appointment of an arbitrator under Section 8 of the Arbitration Act, 194…
HAKIM ALI AND ANR.versusBOARD OF REVENUE U.P. AND ORS.
1990 INSC 39119 December 1990Dismissed
Badlu, the father of Hakim Ali, filed a suit under Section 229‑B of the U.P. Zamindari Abolition and Land Reforms Act, 1950 seeking a declaration of bhumidari rights. The suit was dismissed, but the Additional Commissioner reversed the decision, leading the respondent to file a second appeal before the Board of Revenue…
UNION OF INDIA AND ANR.versusM/S. SOHAN LAL PUGLIA
2003 INSC 64819 November 2003Appeal(s) allowed
The Union of India entered into a contract for the supply and construction of a stone ballast machine, which contained an arbitration clause requiring the appointment of Gazetted officers as arbitrators for disputes exceeding Rs.5 lakh. When the Department failed to appoint an arbitrator, the contractor invoked the cla…
M/S RICKMERS VERWALTUNG GMB HversusTHE INDIAN OIL CORPORATION LTD.
1998 INSC 43619 November 1998Dismissed
The appellant, a shipowner, and the respondent, Indian Oil Corporation, negotiated a charter party for shipping pipes but never signed the agreement because they could not agree on the format of a standby letter of credit and a performance guarantee, which were treated as conditions precedent. The appellant later invok…
INDIAN OIL CORPORATION LTD.versusAMRITSAR GAS SERVICE AND ORS.
1990 INSC 36019 November 1990
Indian Oil Corporation (the appellant) terminated a distributorship agreement with Amritsar Gas Service (respondent No.1) under clause 27, alleging unauthorized connections and other misconduct. The distributor sued for a declaration that the termination was illegal and sought restoration of the distributorship. The ma…
U.P. CO-OPERATIVE FEDERATION LTD.versusSINGH CONSULTANTS & ENGINEERS (P) LTD.
1987 INSC 34119 November 1987Appeal(s) allowed
The Uttar Pradesh Cooperative Federation Ltd. (appellant), a state enterprise, contracted with Singh Consultants & Engineers (P) Ltd. (respondent) to supply and install a vanaspati plant, requiring the respondent to furnish two irrevocable bank guarantees. The plant was not completed within the stipulated time, and the…
INDIAN HUME PIPE CO. LTD.versusSTATE OF RAJASTHAN
2009 INSC 118419 October 2009Appeal(s) allowed
The appellant, Indian Hume Pipe Co. Ltd., entered into a contract with the State of Rajasthan for laying a PSC pipeline, which contained an arbitration clause. A dispute led to arbitration, and the arbitrators awarded the appellant the claim along with interest for pre‑reference, pendente lite, and post‑award periods. …
AVITEL POST STUDIOZ LIMITED & ORS.versusHSBC PI HOLDINGS (MAURITIUS) LIMITED
2020 INSC 49819 August 2020Disposed off
Avitel Post Studioz Ltd and its promoters invested USD 60 million in HSBC based on alleged representations that Avitel would secure a lucrative BBC contract, which later proved to be fictitious. HSBC obtained interim awards and a foreign final award from a Singapore tribunal finding the appellants liable for fraudulent…
DECCAN PAPER MILLS CO. LTD.versusREGENCY MAHAVIR PROPERTIES & ORS.
2020 INSC 49719 August 2020Dismissed
Deccan Paper Mills entered into a development agreement with Ashray, which was later assigned to Regency Mahavir Properties containing an arbitration clause. Deccan alleged fraud by a partner of Regency and filed a suit under the Specific Relief Act, seeking cancellation of the 2006 agreement and a deed of confirmation…
PRATAP SINGHversusPREETAM SINGH & ANR.
1969 INSC 18819 August 1969Dismissed
Pratap Singh and Preetam Singh, brothers in partnership, referred their business dispute to arbitration under the Arbitration Act, 1940. The arbitrator failed to render an award within four months and applied to the Subordinate Judge, Delhi, for an extension of time under s.28, which was granted despite an objection to…
M/S. KRISHNA MOTOR SERVICE BY ITS PARTNERSversusH.B. VITTALA KAMATH
1996 INSC 55519 April 1996Appeal(s) allowed
The Supreme Court considered a dispute arising from the dissolution of an unregistered partnership, Krishna Motor Service, where the respondent, a partner without capital contribution, sought arbitration under Section 20 of the Arbitration Act, 1940. The partnership was not registered as required by Section 69 of the P…
UNION OF INDIAversusM/S. JAIN ASSOCIATES AND ANR.
1994 INSC 16119 April 1994
The Union of India entered into a construction contract with M/s. Jain Associates, which was later terminated for non‑completion. The contractor claimed Rs 37,37,885 and the Union counter‑claimed Rs 9,49,701. An umpire under the Arbitration Act, 1940 awarded the contractor Rs 24,10,330, granting interest up to the date…
M/S. P. MANOHAR REDDY & BROS.versusMAHARASHTRA KRISHNA VALLEY DEV. CORPN. & ORS.
2008 INSC 148218 December 2008Dismissed
The contractor, M/s P. Manohar Reddy & Bros., completed an excavation contract for the Maharashtra Krishna Valley Development Corporation, received full payment and accepted the final bill. Later it claimed extra work, but raised the claim after the contract had ended and beyond the 30‑day period prescribed in clauses …
M/S GORA LALversusUNION OF INDIA
2003 INSC 74018 December 2003Dismissed
The appellant, Gora Lal, entered into a work contract with the Union of India that contained an arbitration clause requiring the arbitrator to "indicate his findings, along with the sum awarded, separately on each individual item of the dispute." A dispute arose over the final payment, and an arbitrator was appointed w…
M/S. SATHYANARAYAN BROTHERS (P) LTD.versusTAMIL NADU WATER SUPPLY & DRAINAGE BOARD
2003 INSC 64618 November 2003Appeal(s) allowed
Mis. Sathyanarayana Brothers (P) Ltd. entered into a contract with the Tamil Nadu Water Supply & Drainage Board for the manufacture and supply of prestressed concrete pipes for the Veeranam water project, subject to foreign collaboration clearance and foreign‑exchange assistance. Delays in obtaining foreign exchange an…
M.M.T.C. LIMITEDversusSTERLITE INDUSTRIES (INDIA) LTD.
1996 INSC 131818 November 1996Disposed off
M.M.T.C. Ltd. appealed against a High Court order directing it to appoint an arbitrator under the Arbitration and Conciliation Act, 1996. The dispute arose after the 1996 Act came into force, so the Court examined whether the arbitration clause in a 1993 agreement, which provided for each party to nominate one arbitrat…
K.K. JOHNversusSTATE OF GOA
2003 INSC 49618 September 2003Dismissed
The appellant, a contractor, entered into a construction contract with the State of Goa that provided for arbitration of disputes. An arbitrator rendered an award in 1994, but the civil court remitted the award on two specific points for reconsideration. The arbitrator resigned before completing the reconsideration, an…
RAMESH KUMAR & ANR.versusFURU RAM & ANR. ETC.
2011 INSC 59318 August 2011Appeal(s) allowed
The appellants, brothers who co‑owned land, sued the respondents seeking a declaration that the arbitration awards and the subsequent court decrees granting title to the respondents were null and void because they were obtained through fraud and stamp‑duty evasion. The lower courts dismissed the suits on the ground tha…
V.H. PATEL AND COMPANY AND ORS.versusHIRUBHAI HIMABHAI PATEL AND ORS.
2000 INSC 22218 April 2000Dismissed
The partnership firm V.H. Patel & Co. and its members sued former partner H.H. Patel for declaration that a retirement deed was void and for injunction against his use of three trademarks. The parties entered a consent order referring all disputes arising from the partnership agreement, retirement deed, trademark use a…
UNION OF INDIAversusM/S PAM DEVELOPMENT PVT. LTD.
2014 INSC 10618 February 2014Dismissed
The Union of India entered into a contract with PAM Development for constructing an industrial loco shed, which was later terminated for delay and inferior work. The contractor invoked an arbitration clause, and the Calcutta High Court appointed a former judge as sole arbitrator under Section 11(6) of the Arbitration a…
TAMIL NADU ELECTRICITY BOARDversusM/S. BRIDGE TUNNEL CONSTRUCTIONS AND ORS.
1997 INSC 15518 February 1997Appeal(s) allowed
The Tamil Nadu Electricity Board (TN EB) contracted Bridge Tunnel Constructions to build inter‑connecting tunnels for the Suruliyar Hydroelectric Project. After the contract was completed late, a dispute arose over additional payments. The respondent invoked the arbitration clause (clause 50) and appointed a sole arbit…
ATLANTA LIMITED THR. ITS MANAGING DIRECTORversusUNION OF INDIA REPRESENTED BY CHIEF ENGINEER MILITARY ENGINEERING SERVICE
2022 INSC 5018 January 2022Disposed off
The appellant, a construction firm, entered into a contract with the Union of India for runway construction, which was terminated by the Union. The arbitrator awarded the appellant substantial sums for extension of time, wrongful termination, idle hire charges and value of machinery. A single judge upheld the award, bu…
J.C. BUDHRAJAversusCHAIRMAN, ORISSA MINING CORPN. LTD. & ANR.
2008 INSC 6418 January 2008Case Partly allowed
The contractor (N.C. Budhraja) completed excavation work for Orissa Mining Corp. Ltd. (OMC) and later claimed extra payment for work beyond the contract. OMC acknowledged pending claims in a letter dated 28‑Oct‑1978 and paid Rs.3,50,000 on 4‑Mar‑1980, after which the contractor invoked arbitration on 4‑Jun‑1980. The le…
NORTH DELHI MUNICIPAL CORPORATIONversusM/S S.A. BUILDERS LTD.
2024 INSC 98817 December 2024Dismissed
The North Delhi Municipal Corporation (appellant) contracted with M/s S.A. Builders Ltd. (respondent) for construction work, which was not completed and led to a dispute. An arbitrator awarded Rs. 1,70,70,720.80 with simple interest and later issued a clarification on 15 March 2005 regarding post‑award interest, after …
BOMBAY STOCK EXCHANGEversusJAYA I. SHAH AND ANR.
2003 INSC 56317 October 2003Disposed off
The Bombay Stock Exchange (BSE) held the assets of a defaulting member, C.S. Shah, in its Defaulters' Committee, which is merely an association of persons and not a juristic entity. Ms. Indu Malhotra obtained an arbitration award against Shah, which was made a rule of court and a decree, and sought attachment of the fu…
UNION OF INDIAversusM/S. POPULAR BUILDERS, CALCUTTA
2000 INSC 48217 October 2000Case Partly allowed
The Union of India entered into a construction contract with M/s Popular Builders, who after completing the work, accepted a final bill without objection and received payment. The builder later claimed additional work not covered in the final bill and, at its request, an arbitrator was appointed who awarded the claim i…
NATIONAL FERTILIZERSversusPURAN CHAND NANGIA
2000 INSC 48517 October 2000Dismissed
National Fertilizers Ltd. awarded a works contract to Puran Chand Nangia for 48% of a Rs. 3.39 crore project. The contract contained a clause that quoted rates would remain firm for variations up to ±25% of the contract price, beyond which market rates could apply. After the work was varied both upwards and downwards, …
RENUSAGAR POWER CO. LTD. ETC.versusGENERAL ELECTRIC CO. ETC.
1993 INSC 34217 October 1993Dismissed
Renusagar Power Co. entered into a contract with General Electric for the supply of equipment for a power plant, which later gave rise to disputes and an ICC arbitration. The arbitral tribunal awarded US$12,215,622.14, including regular interest, delinquent interest, compensatory damages, and costs. Renusagar challenge…
STATE OF MAHARASHTRAversusM/S. S.D. SHINDE AND CO.
2003 INSC 49017 September 2003Appeal(s) allowed
The State of Maharashtra contracted Mis. S.D. Shinde & Co. to construct a project, but disputes led to arbitration under the Arbitration Act, 1940. An arbitrator issued an award and later filed an interim award before a Civil Judge seeking to have it made a rule of court, resulting in an interim order directing the gov…
MUNICIPAL CORPORATION OF DELHIversusJAGAN NATH ASHOK KUMAR & ANR.
1987 INSC 25417 September 1987Dismissed
The Municipal Corporation of Delhi (MCD) awarded a construction contract to Jagan Nath Ashok Kumar, which it later rescinded alleging delay. The contract contained an arbitration clause, and an arbitrator was appointed who held that the rescission was wrongful, awarded the contractor Rs.23,820 plus interest, and allowe…
P.A. AHAMMED IBRAHIMversusTHE FOOD CORPORATION OF INDIA
1999 INSC 33517 August 1999Appeal(s) allowed
The appellant, P.A. Ahmed Ibrahim, contracted with the Food Corporation of India (FCI) for loading, unloading and transport of foodgrains from 1973 to 1975, the agreement containing an arbitration clause. In 1978 the appellant sued FCI for recovery of pending dues, while FCI filed a petition under Section 20 of the Arb…
REGISTRAR, CO-OPERATIVE SOCIETIES, WEST BENGALversusKRISHNA KUMAR SINGHANIA AND ORS.
1995 INSC 47917 August 1995Appeal(s) allowed
The Registrar of Co-operative Societies, West Bengal, appointed an arbitrator under the West Bengal Cooperative Societies Act, 1983 to resolve a dispute with a transport contractor. The arbitrator failed to render an award within the one‑year period prescribed by s.96(5)&(6). The contractor approached the Calcutta High…
PETINE SHIPPING INC. OF MONROVIAversusTHE MINERALS AND METAL TRADING CORPORATION OF INDIA LTD.
2009 INSC 55517 April 2009Appeal(s) allowed
Petine Shipping Inc., a Liberian shipowner, and Minerals and Metal Trading Corporation of India entered into a charter party containing an arbitration clause. When a dispute arose, each party nominated an arbitrator, but the respondent's nominee was challenged and the respondent filed a petition in the Delhi High Court…
DELHI TRANSPORT CORPORATION LTD.versusROSE ADVERTISING
2003 INSC 23917 April 2003Dismissed
The Delhi Transport Corporation (DTC) entered into a 1993 agreement with Rose Advertising containing an arbitration clause. A dispute arose and the contractor sought appointment of an arbitrator in early 1996; the arbitrator was appointed on 4 July 1996, after the Arbitration and Conciliation Act, 1996 had come into fo…
K. SASIDHARANversusKERALA STATE FILM DEVELOPMENT CORPORATION
1994 INSC 11917 March 1994Dismissed
The appellant, K. Sasidharan, entered into a contract with the Kerala State Film Development Corporation to construct a theatre. A dispute arose during execution and the appellant sought appointment of an arbitrator under Section 20 of the Arbitration Act, 1940, relying on clause 73 of the Madras Detailed Standard Spec…
M/S. ENGINEERS SYNDICATEversusSTATE OF BIHAR AND ORS.
2007 INSC 5117 January 2007Appeal(s) allowed
The dispute between Mis. Engineers Syndicate and the State of Bihar was referred to arbitration under an agreement. The arbitrator issued a lump‑sum award in favour of the syndicate without providing item‑wise reasons, i.e., a non‑speaking award. The Subordinate Judge set aside the award on the ground that it lacked re…
SUDHIR BROTHERSversusDELHI DEVELOPMENT AUTHORITY AND ANR.
1995 INSC 74516 November 1995Appeal(s) allowed
The appellant Sudhir Brothers were awarded a construction contract by the Delhi Development Authority. Disputes led to a reference to arbitration on 1 April 1984; the arbitrator entered the reference on 8 February 1985 and rendered an award on 15 July 1987, granting the appellant the contract sum together with 12 % sim…
RACHAPPA GURUADAPPA BIJAPURversusGURUSIDDAPPA NURANIAPPA & ORS.
1988 INSC 34816 November 1988Dismissed
The petitioners and respondents were partners in a firm that had an arbitration agreement. Respondent No.1 filed a suit for dissolution and accounts, and respondent No.9 applied under Section 34 of the Arbitration Act, 1940 for a stay of the suit. The trial court observed that the petitioner (defendant No.4) had obtain…
SHAILESH DHAIRYAWANversusMOHAN BALKRISHNA LULLA
2015 INSC 79616 October 2015Dismissed
The appeal arose from a dispute where the parties, after settling most issues in a suit, referred two remaining differences to arbitration before a retired Supreme Court judge. The arbitrator resigned, and the respondent sought a substitute arbitrator. The High Court appointed a retired judge as a substitute under Sect…
M/S AROSAN ENTERPRISES LTD.versusUNION OF INDIA AND ANR.
1999 INSC 41816 September 1999Appeal(s) allowed
Mis Arosan Enterprises Ltd entered into a contract with the Union of India/FCI for the supply of 58,000 metric tonnes of sugar, stipulating that shipment by 31 October 1989 was the essence of the contract but also allowing the buyer to extend the delivery period at a discount. The buyer cancelled the contract for non‑s…
M/S. KALIMPONG LAND AND BUILDING LTD. AND ANRversusSTATE 0F WEST BENGAL AND ORS.
1994 INSC 39416 September 1994Appeal(s) allowed
The appellant, Mis. Kalimpong Land and Building Ltd., owned a three‑storeyed godown and 4.9 acres of land that were requisitioned by the State of West Bengal in 1964 under the Requisitioning and Acquisitioning of Immovable Property Act, 1952. After a protracted arbitration process that began in 1967 and stretched over …
STATE OF RAJASTHANversusPURI CONSTRUCTION CO. LTD. AND ANOTHER
1994 INSC 39616 September 1994Disposed off
The State of Rajasthan and Puri Construction Co. Ltd. entered into a dam‑construction contract containing an arbitration clause. Disputes were referred to two retired judges as arbitrators, who awarded Rs 1 crore in favour of the contractor. The State challenged the award on grounds of arbitrator misconduct (one arbitr…
M/S MISRA AND CO.versusDAMODAR VALLEY CORPORATION
2017 INSC 75116 August 2017Hearing Adjourned
MIS Misra & Co. was awarded Rs.5,78,873 by an arbitrator in 1988 for a construction contract with Damodar Valley Corporation (DVC). The Civil Court made the award a decree on 16 March 1991, but DVC neither paid nor appealed, and due to repeated objections the formal decree was only prepared on 21 February 2003. Misra f…
STATE OF RAJASTHANversusR.S. SHARMA & CO.
1988 INSC 22416 August 1988Disposed off
The State of Rajasthan and R.S. Sharma & Co. entered into a construction contract that later led to a dispute. While litigation was pending, the parties agreed to arbitrate, and the arbitrators awarded Rs.75,41,755 to the respondent without providing reasons. The appellant challenged the award on grounds of lack of rea…
NEELAKANTAN & BROS. CONSTRUCTIONversusSUPERINTENDING ENGINEER, NATIONAL HIGHWAYS, SALEM & ORS.
1988 INSC 22716 August 1988Dismissed
Neelakantan & Bros. Construction entered into contracts with the Superintending Engineer for highway works and a reference for arbitration was made to the then‑incumbent engineer, Mohan. Mohan was transferred before completing the arbitration and his successor, Cornelius, took over the proceedings with the petitioner’s…
RENUSAGAR POWER COMPANY LTD.versusGENERAL ELECTRIC COMPANY AND ANR.
1984 INSC 14516 August 1984Dismissed
The Supreme Court examined whether a suit filed by Renusagar Power Co. Ltd. seeking a declaration that three claims (unpaid regular interest, delinquent interest, and compensatory damages) were beyond the scope of an arbitration clause could be stayed under Section 3 of the Foreign Awards (Recognition and Enforcement) …
DLF UNIVERSAL LTD. AND ANR.versusTHE DIRECTOR GENERAL (INVESTIGATION AND REGISTRATION) AND ANR.
2008 INSC 71516 May 2008Dismissed
DLF Universal Ltd. and its trust, the colonizers of a Gurgaon colony, were directed by the Monopolies and Restrictive Trade Practices (MRTP) Commission to execute a fresh lease deed with a complainant who alleged unfair and restrictive trade practices in the allotment of school sites. The appellants did not challenge t…
ADAVYA PROJECTS PVT. LTD.versusM/S VISHAL STRUCTURALS PVT. LTD. & ORS
2025 INSC 50716 April 2025Appeal(s) allowed
The appellant and respondent No.1 formed an LLP governed by an agreement containing an arbitration clause (Clause 40). Disputes arose over the ITF project, and the appellant issued a Section 21 notice of arbitration only to respondent No.1 and filed a Section 11 application appointing an arbitrator, also only naming re…
STATE OF ORISSA ETC.versusKLOCKNER AND COMPANY AND ORS. ETC.
1996 INSC 53116 April 1996Dismissed
Klockner & Co., a German firm, had a marketing agreement with Orissa Mining Corporation (OMC) for exclusive marketing of charge chrome, containing an arbitration clause referring disputes to the ICC in London under Swiss law. After OMC's charge‑chrome division was taken over by the State of Orissa under Ordinance 8 of …
UNION OF INDIAversusM/S. AMBLCA CONSTRUCTION
2016 INSC 26516 March 2016Reference answered
The case concerned whether an arbitrator could award pendente lite interest when the underlying contract expressly barred interest on delayed payments. The dispute arose from a construction contract between the Union of India and M/s. Ambica Construction, which had undergone multiple arbitrations and court intervention…
PUNJAB STATE ELECTRICITY BOARDversusBASSI COLD STORAGE, KHABAR AND ANR.
1994 INSC 11716 March 1994Appeal(s) allowed
Bassi Cold Storage, a consumer of electricity supplied by the Punjab State Electricity Board, claimed that its supply was wrongfully disconnected and sought damages. The consumer invoked Condition 29 of the Board's Abridged Conditions of Supply, which provided that disputes not determinable under the conditions could b…
TARAPORE AND CO.versusSTATE OF MADHYA PRADESH
1994 INSC 7716 February 1994
Tarapore & Co. entered into a contract with the State of Madhya Pradesh for the construction of a masonry dam, which required the contractor to pay not less than "fair wages" and to observe labour laws without any claim against the Irrigation Department. After the State revised minimum wages, the contractor paid the hi…
P. M. PAULversusUNION OF INDIA
1989 INSC 1016 January 1989Disposed off
P.M. Paul, a contractor, entered into a two‑phase construction contract with the Union of India. A dispute arose over the handover of the site and alleged delays, leading the parties to invoke the arbitration clause in the contract. The Supreme Court appointed a former judge, Justice V. Khalid, as arbitrator, who award…
OIL & NATURAL GAS COMMISSIONversusWESTERN COMPANY OF NORTH AMERICA
1987 INSC 1416 January 1987Appeal(s) allowed
The Oil & Natural Gas Commission (ONGC) entered into a drilling contract with Western Company of North America that provided for arbitration under the Indian Arbitration Act, 1940 and the law of India, with hearings to be held in London. An umpire, after the arbitrators could not agree, issued an interim award and a fi…
KAVERI ENGINEERING INDUSTRIES LTD.versusUNITED SHIPPING CORPORATION LTD. AND ANR.
1995 INSC 91415 December 1995Appeal(s) allowed
Kaveri Engineering Industries Ltd entered into a contract with United Shipping Corporation Ltd for the transshipment of 400 MT of fabricated steel structures from Madras to Chittagong for a fixed freight of Rs 2 lakhs, irrespective of cargo volume. The shipping agent later demanded Rs 10.70 lakhs based on volume, refus…
STATE OF ORISSA AND ANR.versusSRI DAMODAR DAS
1995 INSC 90415 December 1995Appeal(s) allowed
The State of Orissa appealed against the appointment of an arbitrator under Sections 8 and 20 of the Arbitration Act, 1940, filed by contractor Sri Damodar Das. The Supreme Court examined whether Clause 25 of the water‑supply contracts, which made the decision of the Public Health Engineer final, amounted to an arbitra…
M/S. SHYAMA CHARAN AGARWALA AND SONSversusUNION OF INDIA
2002 INSC 30115 July 2002Disposed off
The contractors Mis. Shyama Charan Agarwala & Sons entered into construction contracts with the Union of India and, after disputes arose, referred the matters to arbitration. The arbitrator awarded reimbursement for additional costs relating to stone aggregate, excavation of rock, and work in a restricted area. The Uni…
M/S INTERSTATE CONSTRUCTIONversusNATIONAL PROJECTS CONSTRUCTION CORPORATION LTD.
2025 INSC 69915 May 2025Appeal(s) allowed
The appellant, M/s Interstate Construction, executed work orders for a power project for the respondent, NPCC, and later disputed certain recoveries, leading to arbitration. The arbitral tribunal awarded the appellant principal sum plus interest, distinguishing pre‑reference, pendente‑lite and future interest periods. …
THE AMRAVATI DISTRICT CENTRAL CO-OPERATIVE BANK LTD.versusUNITED INDIA FIRE AND GENERAL INSURANCE CO. LTD.
2010 INSC 21115 April 2010Dismissed
The Amravati District Central Co‑operative Bank held an insurance policy with United India Fire & General Insurance covering losses caused by its employees. An employee embezzled several amounts totalling Rs.3.44 lakh. The insurer assessed a reimbursable loss of Rs.29,000, but the bank claimed the full amount. An arbit…
G. RAMACHANDRA REDDY & CO.versusUNION OF INDIA & ANR.
2009 INSC 52815 April 2009Disposed off
The appellant submitted a tender for a construction contract, claiming a 2.25% uplift on rates and a 40% labour component, which the respondent contested, leading to arbitration. The arbitrator held that the appellant’s covering letter formed part of the contract, upheld the 2.25% uplift, substituted the contractually …
HIMACHAL PRADESH STATE ELECTRICITY BOARDversusR.J. SHAH AND COMPANY
1999 INSC 18715 April 1999Dismissed
The Supreme Court considered an arbitration award arising from a construction contract for the Giri Hydel project, where the contractor claimed price revision after the total work exceeded a 20% deviation limit. The arbitrators were tasked with interpreting the contract clauses on rate revision and awarded increased ra…
BOARD OF CONTROL FOR CRICKET IN INDIAversusKOCHI CRICKET PVT. LTD. AND ETC.
2018 INSC 23815 March 2018Dismissed
The Board of Control for Cricket in India filed a Section 34 challenge to arbitral awards dated June 2015, and the award creditors sought execution. The award debtor argued that the pre‑amended Section 36 imposed an automatic stay on execution until the Section 34 petition was decided, while the High Court applied the …
D. GOPINATHAN PILLAIversusSTATE OF KERALA AND ANR.
2007 INSC 4015 January 2007Appeal(s) allowed
The State of Kerala filed an application to condone a 3320‑day delay in filing a petition to set aside an arbitral award under the Arbitration Act, 1940. The civil court allowed the condonation, noting gross negligence of officials but refusing to penalise the State, and the High Court dismissed the appellant’s revisio…
JAJODIA (OVERSEAS) PVT. LTD.versusTHE INDUSTRIAL DEVELOPMENT CORPORATION OF ORISSA LTD.
1993 INSC 1915 January 1993Case Partly allowed
STATE OF ANDHRA PRADESH & ANR. ETC.versusR.V. RAYANIM ETC. ETC.
1990 INSC 815 January 1990Dismissed
The State of Andhra Pradesh entered into a contract with contractor R.V. Rayanim for constructing an earth dam. A dispute led to arbitration, where the arbitrator issued a non‑speaking award of Rs.19.39 lakhs in favour of the contractor, mentioning consideration of escalation damages but not quantifying any amount for …
M/S INDIAN DRUGS AND PHARMACEUTICALS LTD.versusM/S INDO SWISS SYNTHETICS GEM MANUFACTURING CO. LTD. AND ORS.
1995 INSC 72914 November 1995Appeal(s) allowed
The appellant, Indian Drugs & Pharmaceuticals Ltd., entered into a contract with respondent No.2 for filling medicine vials, which was terminated on 1 April 1984. After discovering defects in the vials in 1985, the appellant sought reimbursement and invoked the arbitration clause (clause 19) to refer the dispute to an …
JAWAHARLAL WADHWA AND ANOTHERversusHARIPADA CHAKROBERTY
1988 INSC 32014 October 1988Disposed off
The appellants, Jawahar Lal Wadhwa and another, entered into a sale and construction agreement with the respondent, Haripada Chakrobarty, involving monthly instalments and a construction contract. The respondent later repudiated the agreement, leading to a dispute over possession of the property and the applicability o…
RAJ KUMAR DEY AND OTHERSversusTARAPADA DEY AND OTHERS
1987 INSC 24814 September 1987
The appellants and respondent entered into a partition agreement which was referred to arbitration; the arbitrators rendered an award on 28 November 1977. The award was filed in court on 28 January 1978 and an interim injunction was issued on 26 July 1978, keeping the award in the court's custody until the injunction w…
TRUSTEES OF THE PORT OF MADRASversusENGINEERING CONSTRUCTIONS CORPORATION LIMITED
1995 INSC 45614 August 1995Appeal(s) allowed
The Madras Port Trust invited tenders in 1957; the contractor submitted a tender with deviations, notably that the Trust would import and supply plant and machinery. The Trust refused to incorporate the contractor’s modifications, and the contract was signed without them. Delays in importing the machinery caused the co…
RESERVE BANK OF INDIAversusS.S. INVESTMENTS AND ORS.
1992 INSC 20514 August 1992Appeal(s) allowed
The Reserve Bank of India (RBI) entered into a sale agreement with S.S. Investments that contained an arbitration clause. Two arbitrators – a former judge and a lawyer – were appointed but each issued a separate award, indicating a disagreement. The RBI sought to refer the matter to the appointed Umpire under Clause 4 …
PUNJAB STATE & ORS.versusDINA NATH
2007 INSC 57014 May 2007Dismissed
The Punjab State issued a work order containing a clause that any dispute between the department and the contractor would be referred to the Superintending Engineer, whose decision would be final and binding. After the contractor completed the work, a dispute arose over final bills and measurements, and the contractor …
FOOD CORPORATION OF INDIAversusSREEKANTH TRANSPORT
1999 INSC 25814 May 1999Dismissed
The Food Corporation of India (FCI) and Sreekanth Transport entered into a government contract containing an arbitration clause and an excepted‑matter clause (clause 12) that vested final authority in the Senior Regional Manager. Sreekanth Transport filed a suit under Section 20 of the Arbitration Act, 1940 seeking to …
SUKANYA HOLDINGS PVT. LTDversusJAYESH H. PANDYA AND ANR.
2003 INSC 23014 April 2003Dismissed
Sukanya Holdings Pvt. Ltd. and J.H. Pandya entered into a partnership agreement that contained an arbitration clause. After the partnership fell into dispute, the respondent filed a suit for dissolution, accounts and other reliefs, including claims against purchasers of flats who were not parties to the partnership. Th…
CHANDIGARH CONSTRUCTION CO. PVT. LTDversusSTATE OF PUNJAB & ANR.
2020 INSC 18714 February 2020Case Partly allowed
The contractor, Chandigarh Construction Co., entered into a contract with the State of Punjab for construction of the Sutlej Yamuna Link Canal and later claimed additional payment for extra work. An arbitrator awarded the claims using a 93.12% premium and 18% interest, but did not give reasons as required by a contract…
MANAGEMENT OF M/S. SONEPAT COOPERATIVE SUGAR MILLS LTD.versusAJIT SINGH
2005 INSC 7714 February 2005Appeal(s) allowed
The appellant, Management of M/s. Sonepat Co‑operative Sugar Mills Ltd., terminated the services of Ajit Singh, who was employed as a Legal Assistant. Singh claimed that he was a "workman" under Section 2(s) of the Industrial Disputes Act, 1947 and sought reinstatement with back wages. The Labour Court and the Punjab &…
M/S BHARAT COKING COAL LTD.versusM/S C.K. AHUJA AND ANR.
1995 INSC 11414 February 1995Disposed off
The Supreme Court had earlier referred the disputes between M/s Bharat Coking Coal Ltd. and M/s C.K. Ahuja to arbitration by consent, appointing an arbitrator who rendered an award on 14 February 1994. The award was filed before the Court and notice of filing was given on 29 April 1994. The respondents filed applicatio…
SADHU SINGH GHUMANversusFOOD CORPORATION OF INDIA & ORS.
1990 INSC 3714 February 1990Appeal(s) allowed
Food Corporation of India sued Sadhu Singh and others for recovery of Rs.2 lakh based on a contract that contained an arbitration clause. The defendants appeared, sought production of the original agreement to enable filing of a written statement, and then invoked Section 34 of the Arbitration Act, 1940 for a stay of t…
SUDARSAN TRADING CO.versusGOVT. OF KERALA & ANR.
1989 INSC 5714 February 1989Appeal(s) allowed
Sudarsan Trading Co. entered into a construction contract with the Government of Kerala which was later cancelled, leading the parties to refer their disputes to the arbitrator named in the agreement. The arbitrator issued three non‑speaking awards granting the contractor claims totalling Rs.31.15 lakhs, without provid…
M/S SUBHASH AGGRAWAL AGENCIESversusM/S BHILWARA SYNTHETICS LTD. AND ORS.
1994 INSC 59713 December 1994Appeal(s) allowed
Mis Subhash Aggarwal Agencies (appellant) and Mis Bhilwara Synthetics Ltd. (respondent) were members of the Delhi Hindustani Mercantile Association. The appellant claimed Rs 4,51,246.50 and the dispute was referred to a sole arbitrator who, following a High Court direction dated 20‑Nov‑1981, gave a reasoned award on 19…
STATE OF WEST BENGALversusNATIONAL BUILDERS
1993 INSC 33113 October 1993Dismissed
The State of West Bengal (Public Works Department) and National Builders disputed a claim arising from the construction of a 250‑bed hospital. Clause 25 of their contract appointed the Chief Engineer as sole arbitrator, who in turn nominated a Superintending Engineer. After 59 sittings the arbitrator refused to resign,…
EVEREST CO-OWNERS, A.B.C.versusM.P. STATE WARE HOUSING CORPORATION AND ANOTHER
1992 INSC 27513 October 1992Appeal(s) allowed
The appellant, Everest Co‑owners, owned three godowns that were leased to the Food Corporation of India and later occupied by the respondent, M.P. State Ware Housing Corporation, without the appellant’s consent. After the lease expired, the appellant claimed damages of Rs 4,76,984 and invoked the arbitration clause in …
M/S SHRIRAM EPC LIMITEDversusRIOGLASS SOLAR SA
2018 INSC 81613 September 2018Dismissed
The parties obtained an ICC arbitral award in London ordering RioGlass Solar to pay Shriram EPC Ltd €4.36 million. Shriram filed a petition under Section 47 of the Arbitration and Conciliation Act, 1996 to enforce the foreign award in India, while RioGlass contended that the award was unenforceable because it had not b…
M/S. NORTHERN COALFIELD LTD.versusHEAVY ENGINEERING CORP. LTD. & ANR.
2016 INSC 51813 July 2016Appeal(s) allowed
Northern Coalfield Ltd., a government-owned corporation, entered into two contracts with Heavy Engineering Corp. Ltd. which contained an arbitration clause. Disputes were referred to the Government's "permanent machinery of arbitration" and awards were made, which Northern Coalfield challenged before the Law Secretary …