BHARAT COKING COAL LTD.versusM/S I.K. AHUJA AND CO.
- Citation
- 2001 INSC 102
- Decided
- 21 February 2001
- Disposal
- Disposed off
- Bench
- S RAJENDRA BABU
Holding
The Supreme Court set aside the hybrid awards, held the arbitrator disqualified and the award contained an error apparent on its face, and allowed condonation of the delayed objections under Section 5 of the Limitation Act, directing fresh arbitration by a new arbitrator.
Summary
Bharat Coking Coal Ltd. awarded two construction contracts to L.K. Ahuja & Co. which later led to disputes and were referred to a sole arbitrator, M.P. Sharma, a former officer of the employer. The arbitrator issued hybrid awards that largely relied on joint statements but decided only the material‑escalation claim, leaving many other claims unaddressed. The appellant challenged the awards, arguing the arbitrator was biased, the award was neither a pure speaking nor non‑speaking award, and contained an error apparent on its face. The court also examined whether objections filed after the statutory limitation period could be condoned under Section 5 of the Limitation Act. The Supreme Court held that the arbitrator was disqualified, the awards contained apparent errors, and the delay in filing objections was condoned; consequently, both awards were set aside, a new arbitrator was appointed, and costs were imposed on the appellant.
Issues considered
- The nature of the arbitrator's award: speaking, non‑speaking, or hybrid, and the scope of judicial review
- Whether an error apparent on the face of the award justifies setting it aside
- Whether the arbitrator was disqualified due to prior employment and correspondence with the employer (bias)
- Whether objections filed beyond the limitation period under Article 119 of the Limitation Act can be condoned under Section 5 of the Limitation Act
- Applicability of Section 30 of the Arbitration Act to the objections and the related limitation period
Legislation cited
- Arbitration Act, 1940s. 29, s. 30
- Limitation Act, 1963s. 5
Subjects
Judgment
1
A BHARAT COKING COAL LTD.
v.
MIS L.K. AHUJA AND CO.
FEBRUARY 21, 2001
B [S. RAJENDRA BABU AND S.N. PI-IUKAN, JJ.]
Arbitration Act-Section 30-Award-Selling aside of-Non speaking
award, speaking al\'ard--Scupe of challenge-Claim of Parties not referred
by Arbitrator-Award nut clear-Error apparent-Award set aside.
c
Arbitrator erstwhile officer of employer-Had correspondence with
contractor earlier-Cannot act as an arbitrator.
Limitation Act, I 91J3-Section 5-Delay in filing objections-
D Application for condonatiun can be filed
The Appellant placed two work orders to the respondent on certain
terms and conditions mentioned therein and two separate agreements were
executed by the parties. The schedule dates for completion of the respective t
works were fixed as 24.3.1983 and 19.3.1983 The respondent sought for
E extension of time which was granted by the appellant. Disputes arose between
the parties, the matter was referred to the sole arbitrator. The arbitrator
made two awards in respect of the two contracts which were filed in the court
of the Civil Judge in two Title (Arbitration) Suits. Tbe arbitrator made the
two awards after making elaborate reference to the pleadings on either side
but not deciding any one of the claims except the claim relating to payment of
F material escalation in the two claims. Civil Judge held that the objections for
Title (Arbitration) Suit No. 37/86 was fil~ in time. In Title (Arbitration)
Suit No. 40/86, the objections in question were filed after a delay of five days
beyond the period of limitation prescribed under Article 119 of the Schedule
to the Limitation Act, 1963, and hence they were not considered. Decrees
G were passed in terms of awards. Appeals filed in the High Court by Appellant
were dismissed.
Disposing of the appeals, the Court
HELD: I. The a11bitrator's awards are neith~r speaking awards nor
H non-speaking-partly speaking and partly non-speaking awards. The law is
1152
-<
)
BHARAT COKING COAL LTD. v. L.K.AHUJA 1153
well settled that if the award made by the arbitrator is a non-speaking one the A
difficulty of showing that there is an error apparent on the face of the award
becomes insurmountable and ordinarily such award cannot be challenged at
all unless it is shown that the arbitrator has wholly travelled outside the
contract which give him the jurisdiction. The law is equally well settled that
in cases of speaking awards the court can interfere if there is an error B
apparent on the face of the award itself; it could also be shown that the
arbitrator has misconducted himself in arriving at certain conclusions which
are either plainly contrary to law or to the terms of the contract or ignored
the provisions of contract or the evidence on record and such other similar
matters. (1159-H; 1160-A-B)
c
2. It is not clear from the pleadings whether the claim made by the
respondent is in respect of escalation in the costs of material such as plants,
~- tools, appliances, implements, ladders, cordage, tackle, scaffolding, and
tempers, works, etc. in as much as the appellant has the obligation to supply
the most essential building materials such as cement, steel and such other
building material. It is also not clear either from the pleadings or from the D
award as to whether the escalation claim is in respect of the material provided
by the respondent or in respect of escalation arising from delay in non-
supply of materials which was due to be supplied by the appellant. So far as
-t the plant and other equipment are concerned, they had already been provided
for the purpose of the execution of the work and how the delay in non-supply E
of building materials such as cement, steel, etc. caused escalation so far as
the building materials provided by the appellant is concerned is not clear.
The arbitrator has not applied his mind to this aspect of the matter at all.
Having lost sight of the importance of clause 17 and application of the same
to the circumstances of the case will clearly disclose that there is an error
apparent on the fact of the award. (1161-D-Fl F
3. The entire award in respect of both the agreements made by the
arbitrator is set aside and the matter is remitted back. A new arbitrator be
appointed in place of the old arbitrator because the arbitrator has dealt with
the matter himself as au officer who had correspondence with the contractor G
at the time when he was an officer of the appellant. Therefore, it is fair
neither to the appellant nor to the respondent to continue him as au arbitrator
in the proceedings. (1161-Hl
4. An application for condonation. of delay is permissible to file objections
under Section 30 of the Arbitration Act by resorting to Section 5 of the H
.,
'
1154 SUPREME COURT REPORTS [2001] I S.C.R.
A Limitation Act, Section 5 of the Limitation Act, 1963 provides ·that any
application, other than those contemplated under Order XXI CPC could be
admitted after the prescribed period if the applicant satisfies the court that
he had sufficient cause for not preferring the appeal or making the application
within such period. It is clear that Section 5 of the Limitation Act is applicable
B within such period. It is clear that Section 5 of the Limitation Act is applicable
to all applications other than those under Order XXI CPC. Hence scheme of
an enactment cannot be availed of to defeat such a right conferred under the -~
statute of limitation in clear terms. fl162-H; 1163-AI
Madan Lal v. Sunder/a/ & Anr., 1196713 SCR 147, referred to.
C The objections filed on 18.8.1990 are in the nature of an application
under Section 30 of the Arbitration Act to set aside the award and is an
application under Article 119 of the Schedule to the Limitation Act Therefore,
Section 5 necessarily would get attracted to such a situation.
5. In this case, the notice of fding of award was served upon the appellant
D on 13.7.1990 and the appellant filed objections on 18.8.1990 and those
objections have shut out from the consideration on the ground that the same
have been filed beyond the period of limitation prescribed under the relevant
provisions of the Limitations Act On the _totality of the cin:umstances, the
court is satisfied that there was a sufficient cause of delay in making the t
E application and the time should be extended till 18.8.1990 when the application
was made. The delay in filing such objections upto that date is condoned.
11163-D-E]
6. There is a clear lapse on the part of the Advocate appearing in the
case in neither making a proper application for enlargement of time in the
F civil court nor pursuing this aspect of the matter in the High Court. In this
Court too even, at the time of arguments, no application was forthcoming.
However, to meet the ends of justice, the ::ourt adopted this course, but this
indulgence shown by this Court cannot be taken advantage of by the appellant
without paying appropriate costs to the respondent which is quantified to be a
sum of Rs. 40,000 which shall be paid before the new arbitrator commences
G thearbitnttion proceedings. (1163-F-GI
!The court named Shri Justice Uday Sinha, former Judge, High Court
of Patna, as the new arbitrator who is at liberty to fix his terms as he deems
lit and proper to adjudicate the matter in dispute. The new arbitrator should
consider the pleadings and evidence on record already placed by the parties
H and shall not permit either of the party to raise further or fresh pleas or
BHARATCOKINGCOALLTD. v. L.K.AHUJA[RAJENDRA BABU,.1.] 1155
evidence. It would be appropriate for the arbitrator to make an award within A
a period of four months from the date of the receipt of this judgement and
submit the same to .this court after publishing the same to the parties.I
(1164-B-C)
CIVIL APPELLATE JURISDICTION : Civil Appeal NOS. 5489-
5490 of 1995. B
From the Judgment and Order dated 28.9.94 of the Patna High Court in
Appeal from original order Nos. 68-69 of 1993 (R)
M.L. Verma, Ajit Kumar Sinha, Rajendra Kumar Singh and Dhanjay
Kumar Singh for the Appellant.
c
S.B. Upadhaya, Ms. Shweta Venna, Tathagat H. Vardan, Sujeet Kumar
and Santosh Mishra for the Respondent.
The Judgment of the Court was delivered by
RAJENDRA BABU, J. Two works were assigned by the appellant for
construction of 108 and 72 units of B Type quarters at Karmik Nagar, Ohan bad D
pursuant to a tender notice dated 4/13.7.1981. After certain negotiations
between the parties, two work orders were issued by the appellant to the
respondent on certain terms and conditions mentioned therein valuing at
Rs.86,49,730 and Rs.57,64,368 for the said two works on 14.3.1982 and two
separate agreements were executed by the parties. The schedule dates for E
completion of the respective works were fixed as 24.3.1983 and 19.3.1983. The
respondent sought for extension of time which was granted by the appellant.
Disputes having arisen between the parties, the matter was referred to the
sole arbitrator, Shri M.P.Sharma, the then Additional Chief Engineer. The
arbitrator made two awards in respect of the two contracts on 14.5.1989, which
were filed in the court of the Civil Judge on 12.6.1990 in two Title [Atbitration] F
Suits Nos. 37/86 and 40/86. The learned Civil Judge held that the notice for
Title [Arbitration] Suit No.3 7/86 had been served upon the appellant on
28.8.1990 and the objections filed on 14.9.1990 could be examined as they had
been filed in time. So far as Title [Arbitration] Suit No.40/86 is concerned it
appears that the service of notice on the respondent was made on 13.7.1990 G
of the filing of the award and the objections in question were filed on
~ 18.8.1990 and thus apparently there being a delay of five days in filing the
objections beyond the period oflimitation prescribed under Article 119 of the
Schedule to the Limitation Act, 1963 were not considered. On decrees being
passed in terms of awards appeals filed in the High Court having met with
failure, these appeals have been preferred by special leave. H
'
1156 SUPREME COURT REPORTS (2001) I S.C.R.
A The parties filed elaborate pleadings before the arbitrator in respect of
both the agreements. .,.... -
The claim made in the first agreement is as follows:
I. Claim for payment of the final bill amount Rs. 3, 10,000.00
B
2. Claim for payment of PLO escalation Rs. 20,000.00
' . Claim for compensation for making late
.) Rs . 8,00,000.00
payment of running account bill
4. Claim for payment for labour escalation Rs. 4,12,000.00
c
5. Claim for refund of sales tax Rs. 60,000.00
6. Claim for payment of extra items Rs. 10,31,350.00
7. Claim for payment of material escalation Rs. 40,oo,ooo.oo·
D
8. Keep Back Amount Rs. 8,000.00
9. Claim for payment of compensation to loss Rs 10,00,000.00
arising out of turnover due to prolongation
of work
E IO. Claim for payment on account of loss of Rs. 2,00,000.00
reputation etc.
Rs. 78,41,350.00
F -I
11. With interest @ 18 % per annum from Rs. 20,000.00
31.5.84 till date of actual payment of
awarded amount or court decree whichever
is earlier.
12. Arbitration Cost Rs. 20,000.00"
G
Claim made in the dispute arising out of second agreement is as
follows: '
I. Claim for payment of the final bill amount Rs. 2,00,000.00
H 2. Claim for payment of PLO escalation Rs. 15,000.00 '
BHARAT COKING COAL LTD. v. LK. AHUJA [RA.IENDRA BABU,J] 1157
3. Claim for compensation for making late Rs. 5,00,000.00 A
payment of running account bill
4. Claim for payment for labour escalation Rs. 3,00,000.00
5. Claim for refund of sales tax Rs. 40,000.00
B
6. Claim for payment of extra items Rs. 6,54,000.00
7. Payment of material escalation Rs. 25,00,000.00
8. Keep Back Amount Rs. 28,000.00
9. Claim for payment of compensation to loss Rs. 7,00,000.00
c
arising out of turnover due to prolongation of work
10. Claim for payment on account of loss of Rs. 2,00,000.00
reputation etc.
D
Rs. 51,27,000.00
11. With interest @ 18 % per annum from
30.4.84 till date of actual payment of awarded
amount or court decree whichever is earlier.
E
12. Arbitration Cost Rs 20,000.00"
He passed two separate awards.
In addition to these pleadings, it appears that the arbitrator asked both F
the parties to file certain joint statements and in this regard stated as follows:
" ....... Before going into the merits of the case the parties were advised
to file joint statement signed by them, showing the quantities, rates
and the payments made for various items and balance payment due
to the claimant under various heads and other particulars on 26.4.89. G
The parties submitted the joint statements duly signed by them
containing details of bricks and cement supply statements, bill
statements with details of delay in payment of R/A bills alongwith
relevant dates of measurements and other particulars, including payable
amounts under various heads and measurements for extra items, rolling
margin etc." H
!
1158 SUPREME COURT REPORTS [200 I] I S.C.R.
A The arbitrator noticed in the course of his award that the joint statements
signed by both the parties is the backbone of the award. The arbitrator rather
strangely made the two awards after making elaborate reference to the
pleadings on either side but not deciding any one of the claims except the
claim relating to payment of material escalation in the two claims. On that
B aspect of the matter, the arbitrator, after adverting to the pleadings, stated as
follows:
" ......... Since the pnces of building materials and labour cost sky
rocketting and the value of rupee going down, the refusal to compensate
increase in material cost on some ground or the other would lead to
C total financial disaster to the claimant. The payment of advances like
mobilisation has been made against rebate of l 'ho/o claimed by the O.P.
and was meant for mobilising resources before commencing work. On
the other hand very partly sum is payable against secured advance
without hardly giving any financial assistance. The planning of
procurement of material is linked with progress at site. Whereas during
D contract period the work hardly progressed 50% and the payment for
work done was restricted to 16% how could the planned procurement
availing secured advance could be made in such solution. The payment
of material escalation for the increase in cost during the extended
period of the contract would give some relief to disaster already
caused financially to the claimant.
E
On examination of the contract provision 1 find that the claimant
had undertaken to complete the work at agreed rates within the
stipulated period with the provision for extension of time to execute
at the agreed rates till completion. This contention shall hold good
F provided the extended period is within a reasonable limit. In this case
the original stipulated period is 12 months and actual completion is
26 months having extension element of 14 months which cannot be
termed reasonable by any yardstick. The grant of extension of time is
a poor consolation. It is not remedy for losses suffered on account
of delay in supply of build_ing materials committed to be supplied by
G the O.P."
But after setting out the other claims of the respondent and the rebuttals
to them by the appellant, the arbitrator concluded as follows:
"NOW, THEREFORE, I, the said M.P. Sharma, Sole Arbitrator after
H hearing the parties at length examining and carefully considering the
BHARAT COKING COAL LTD. v. L.K AHUJA [R/\JENDRA BABU,].] 1159
·evidence adduced the arguments advanced by them·, the discussions A
made above, scrutinising the joint statement signed by the parties and
written arguments filed by O.P. DO HEREBY MAKE AND PUBLISH
MY AW ARD AS FOLLOWS:
1. The Opposite Party M/s Bharat Coking Coal Ltd., Dhanbad, shall
pay the claimant i.e. L.K.Ahuja & Co. a lump sum amount of B
Rs.24,27,686.12 (Rupees Twenty four lacs twenty seven thousand six
hundred eighty six and paise twelve only).
I am dividing the period in three years for calculation and payments
of interest.
(a). The aforesaid amount will carry interest@ 15% per annum for the
c
following periods:
I. From 1.1.85 to 3.10.88 when the claimant submitted the claim.
JI. From 4.10.88 to 14.5.90 when the award is published.
D
III. From 14.5.90 till the date of payment or court decrees whichever
is earlier.
2. A sum of Rs. 15,000 (Rupees fifteen thousand) only towards the
cost of arbitration proceedings along with the interest @ 15% p.a.
w.e.f. 14.6.90 till its date of payment or the date of court decree E
whichever is earlier.
It may be made clear that the power to order award of interest on all
above amounts vests in the Hon 'ble Court from the date of decree till
the decretal amount is paid to the claimant as provided under S.29 of
the Arbitration Act which empowers the Hon'ble Court deems F
reasonable from the date of decree till payment of decretal amount to
the claimant.
He similarly awarded in respect of second agreement a lump sum of Rs.
16,74, 197.29 with interest at certain rates and costs of the arbitration.
G
We cannot but describe the arbitrator's awards as hybrid which are
neither speaking awards nor non-speaking - partly speaking and partly non-
speaking awards. The law is well settled that if the award made by the
arbitrator is a non-speaking one the difficulty of showing that there is an error
apparent on. the face of the award becomes insurmountable and ordinarily
such award cannot be challenged at all unless it is shown that the arbitrator H
'
1160 SUPREME COURT REPORTS [2001) I S.C.R.
A has wholly travelled outside the contract which gives hiin the jurisdiction.
The law is equally well settled that in cases of speaking awards the court can
interfere if there is an error apparent on the face of the award itself; it could
also be shown that the arbitrator has misconducted himself in arriving at
certain conclusions which are either plainly contrary to law or to the terms
B of the contract or ignored the provisions of contract or the evidence on
record and such other similar matters. When a lumpsum award is made, it is
all the more difficult to find out as to what went into the mental process of
the arbitrator in fixing the same particularly when a part of the award is a
speaking award and determines the portion of the claim in a particular manner
\ -
and in respect of other claims merely refers to the pleadings but not decided
C the matter but gives the award. The position of the appellant before the court
is unenviable and bristles with too many complexities to get over the awards.
Realising these difficulties, Shri M.L.Verma, learned senior Advocate ·-+-
and Shri Ajit Kumar Sinha, learned Advocate for the appellant, very cautiously
treaded their path to put forth before us the difficulties in upholding the
D award. Shri S.B. Upadhyay, learned counsel for the respondent, with equal
astuteness and competence contended as to the manner in which the award
made by the arbitrator could be maintained though it is bristles with many
difficulties.
We have adverted in detail to the consideration of the claim on payment
E of material escalation earlier. The terms of the contract in this regard indicate
as follows:
"Clause 17: The contractor shall supply at his own cost all materials
(except such special materials, if any, as may be in accordance with
the contract ~e supplied from the Engineer-in-Chiefs stores), plants,
F tools, appliances, implements, ladders, cordage, tackle, scaffolding,
and tempers, works requisite or proper for the proper execution of the
work whether original, altered or substituted and whether included in
the specification or other documents forming part of the contract or
referred to in these conditions or not or which may be necessary for
the purpose of satisfying or complying with the requirements of the
G
Engineer-in- Chief as to any matter as to which under these conditions
he is entitled to be satisfied, which he is entitled to require together
with carriage therefore, to and from the work. The contractor shall also
supply without charge the requisite number of persons with the means
and materials necessary for the purpose of setting out works, and
H counting, weighing and assisting in the measurement or examination
BHARATCOKINGCOAL LTD. v. LK AHUJA [RAJENDRA BABU, J] 1161
at any time and from time to tim'e of the work or materials. Failing his A
so doing, the same may be provided by the Engineer-in-Chief at the
expense of the contractor and the expenses may be deducted from any
money due to the contractor under the contract from his security
deposit or the proceeds of sale thereof, or of a sufficient portion
thereof. The contractor shall also provide all necessary fencing and B
lights required to protect the public from accident, and shall be bound
to bear the expenses of defence of every suit, action or other
proceeding at law that may be brought by any person for injury
sustained owing to neglect of the above precautions, and to pay any
damages and costs which may be awarded in any such suit, action
or proceeding to any such person or which may with the consent of C
the contractor be paid to compromise any claim by any such person."
-~ It is not clear from the pleadings whether the claim made by the
respondent is in respect of escalation in the costs of material such as plant,
tools, appliances, implements, ladders, cordage, tackle, scaffolding, and
tempers, works, etc. inasmuch as the appellant has the obligation to supply D
the most essential building materials such as cement, steel and such other
building material. It is also not clear either from the pleadings or from the
award as to whether the escalation claim is in respect of the materials provided
by the respondent or in respect of escalation arising from delay in non-supply
of materials which was due to be supplied by the appellant. So far as the plant E
and other equipments are concerned, they had already been provided for the
purpose of the execution of the work and how the delay in non-supply of
building materials such as cement, steel, etc. caused escalation so far as the
building materials provided by the appellant is concerned· is not clear. The
arbitrator has not applied his mind to this aspect of the matter at all. Having
lost sight of the importance of clause I 7 and application of the same to the F
circumstances of the case will clearly disclose that there is an error apparent
on the face of the award. The claim under this head is Rs. 40 lacs with
reference to the first agreement and Rs. 25 lacs with reference to the second
agreement which is the major chunk being nearly half the claim made by the
respondent. In what manner this aspect has gone into in fixing the lumpsum G
by the arbitrator is not discernible. Therefore, we have no option but to set
aside the entire award in respect of both the agreements made by the arbitrator
and remit the matter. We propose that a new arbitrator be appointed in place
of the old arbitrator because the arbitrator has dealt with the matter himself
as an officer who had correspondence with .the contractor at the time when
he was an officer of the appellant. Therefore, it is fair neither to the appellant H
1162 SUPREME COURT REPORTS (200 I] I S.C.R.
A nor to the respondent to continue him as an arbitrator in the proceedings.
In so far as the other appeal is concerned, certain additional contentions
have been addressed by the respondent and they are based on Article I 19
of the Schedule to the Limitation Act which provides that an application for
setting aside an award or getting an award remitted for reconsideration, the
B period of limitation is fixed as 30 days from the date of the service of the
notice of the making of the award. As stated earlier, the award had been filed
in the court and the notice of which had been served upon the appellant in
Title [Arbitration] Suit No.40/86 and the objection had been filed. Service of
notice has been made on the appellant on 13. 7 .1990 and the objection in
C question had been filed on 18.8.1990; while it should have been filed on or
before 12th August, 1990. The learned counsel for the respondent in this
regard relied on the following observations made by this Court in Madan Lal
v. Sunderfa/ & Anr., [1967] 3 SCR 147:
"It may be conceded that there is no special form prescribed for
making such an application and in an appropriate case an objection
D
of the type made in this case may be treated as such an application,
if it is filed within the period of limitation. But if an objection like this
has been filed after the period of limitation it cannot be treated as an
application to set aside the award,· for if it is so treated it will be barred
by limitation." [p.151]
E
It is obvious from these observations that even an objection setting out
the grounds specified in Section 30 of the Arbitration Act would amount to
an application as contemplated under Article 119 of the Schedule to the
Limitation Act and, therefore, such objection will have to be filed within the
period of limitation. Courts have taken the view that inasmuch as agreement
F of reference to arbitration is an instrument of solemn character, which is
binding on the parties, and so is the award; if, therefore, a party desires to
avoid the effect either of the agreement or the award, he must strictly comply
with the provisions of the law and an objection to the award must be filed
within the time which cannot be extended. In certain circumstances, courts
G have taken the view that by granting time to file objection the Court had
impliedly extended the time even without a formal application under Section
5 of the Limitation Act. An application for condonation of delay is permissible
to file objections under Section 30 of the Arbitration Act by resorting to
Section 5 of the Limitation Act. Section 5 of the Limitation Act, 1963 provides
that any application, other than those contemplated under Order XX! CPC
H could be admitted after the prescribed period if the applicant satisfies the
BHARAT COKING COAL LTD. v L.K AHUJA [RAJENDRA BABU, l] 1163
court that he had sufficient cause for not preferring the appeal or making the A
application within such period. It is clear that Section 5 of the Limitation Act
is applicable to all applications other than those under Order XX! C.P.C.
Hence scheme of an enactment cannot be availed of to defeat such a right
conferred under the statute of limitation in clear terms.
In the instant case, it is set out in the course of the order made by the B
·1 Civil Judge that the award was filed in the sealed cover and presented to the
court and unless the same was made available to the parties, they could not
file the objections. The object of filing the objections is to question the
validity of the award on the grounds mentioned in Section 30 of the Arbitration
Act. If such a course is nqt possible for want of copy in respect of award, C
certainly the circumstances, as arising in the present case, should be taken
.... note of. The objections filed on 18.8.1990 are in the nature of an application
under Section 30 of the Arbitration Act to set aside the award and is an
application under Article 119 of the Schedule to the Limitation Act. Therefore,
Section 5 necessarily would get attracted to such a situation. In this case, the
notice of filing of award was served upon the appellant on 13. 7.1990 and the D
appellant filed objections on 18.8.1990 and those objections have been shut
out from the consideration on the ground that the same have been filed
beyond the period of limitation prescribed under the relevant provisions of
the Limitation Act. On the totality of the circumstances, we are satisfied that
there was a sufficient cau:;e for delay in making the application and the time E
should be extended till 18.8.1990 when the application was made. We condone
the delay in filing such objections upto that date.
There is a clear lapse on the part of the Advocate appearing in the case
in neither making a proper application for enlargement of time in the civil court
nor pursuing this aspect of the matter in the High Court. In this Court too F
. even, at the time of arguments, no application was forthcoming. However, to
meet the ends of justice, we have adopted this course, but this indulgence
shown by this Court cannot be taken advantage of by the appellant without
paying appropriate costs to the respondent which we quantify to be a sum
of Rs. 40,000 which shall be paid before the new arbitrator commences the G
arbitration proceedings. This cost shall not be the costs in the cause and are
payable by way of penalty.
So far as the main matter is concerned, there is no difference between
the award passed in Title [Arbitration] Suit No.37/86 and the proceedings in
Title [Arbitration] Suit No. 40/86 and the same also deserves to be set aside H
1164 SUPREME COURT REPORTS (200 I] I S.C.R.
A for the very reasons stated earlier and shall be governed by the. same· terms
as to remittal of the award for fresh consideration by a new arbitrator.
As suggested by the learned counsel on both sides, we name Shri
Justice Uday Sinha, former Judge, High Court of Patna, as the new arbitrator
who is at liberty to fix his tenns as he deems fit and proper to adjudicate the
B matter in dispute. The new arbitrator shall consider the pleadings and evidence
on record already placed by the parties and shall not pennit either of the party
to raise further or fresh pleas or evidence. It would be appropriate for the
arbitrator to make an award within a period of four months from the date of
the receipt of this judgment and submit the same to th is Court after publishing
C the same to the parties.
The Registry of this Court is directed to transmit a copy of this
judgment to Shri Justice Uday Sinha, former Judge, High Court of Patna, 308,
Patliputra Colony, Patna-13 forthwith. The parties are directed to appear
before Shri Justice Uday Sinha for further directions, as may be deemed fit
D by him, within one week from the date of this judgment.
In the result, the appeals are disposed of accordingly. In the
circumstances of this case, the appellant is directed to pay a sum of Rs. 40,000
[Rupees forty thousand only] to the respondent as costs.
E VM Appeals disposed of.
Search Indian case law
Ask in plain English, not just keywords. 25,000 AI words free, no card.