Supreme Court of India

STATE OF ORISSAversusB.N. AGARWALA

Citation
1992 INSC 322
Decided
24 November 1992
Disposal
Case Partly allowed

Holding

The arbitrator had no power to award interest for the pre‑reference period but could award pendente‑lite interest, and the extra‑work claims were arbitrable.

Summary

The State of Orissa contracted B.N. Agarwala to construct an irrigation project. After completion, Agarwala claimed extra work payments, and the dispute was referred to the Superintending Engineer, who acted as sole arbitrator and awarded Rs.1,59,298, including Rs.61,086.61 as interest for the period from 10‑Oct‑1969 to 24‑Feb‑1980, covering both the pre‑reference period and the pendente‑lite period. The State sought to set aside the award, arguing that (i) extra‑work claims were not arbitrable under Clause 11 of the contract and (ii) the arbitrator lacked authority to award interest for the pre‑reference period. The High Court upheld the award but corrected the interest rate. The Supreme Court held that the arbitrator could award pendente‑lite interest but could not award interest for the pre‑reference period because the award preceded the Interest Act, 1978, and that the extra‑work claims were arbitrable. Consequently, the award was modified to remove pre‑reference interest and the matter was remitted to the Subordinate Judge to determine the correct interest.

Issues considered

  • Whether claims for extra work under Clause 11 are arbitrable or fall within the final jurisdiction of the Superintending Engineer.
  • Whether the arbitrator had the power to award interest for the pre‑reference period.
  • Whether the arbitrator could award pendente‑lite interest during arbitration proceedings.

Legislation cited

Subjects

arbitrationinterestpre‑reference periodpendente‑lite interestextra workcontract clause 11jurisdictionaward modification

Judgment

                          STATE OF ORISSA                                         A
                                     v.
                            B.N. AGARWALA

                          NOVEMBER 24, 1992

             [B.P. JEEVAN REDDY At-.'D G.N. RAY, JJ.]                             B

     Arbitration Act: Sections 14, 29, 30 and 33--Arbitrator-Jurisdiction to
award interest for pre reference period.

      An agreement was entered· into between the appellant-State and the          C
respondent for the construction of an Irrigation Project. The work was
completed on 11.9.69. On 8.8.1977, the respondent claimed certain
amounts 011 account of extra work done by him, and the dispute was
referred to the Superintending Engineer, as the sole Arbitrator, who maae
a reasoned award on 25.2.1980 granting a total sum of Rs.1,59,298. This
amount comprised of Rs. 61,086.61p. towards interest and Rs. 98,212.09p.          D
towards the extra work done by the respondent. The interest amount of
Rs. 61,086.61p. represented interest for the period 10.10.69 to 24.2.80, ire.
for the pre-reference period as well as for the period the Arbitration
proceedings were pending (Pendente lite interest). The Arbitrator_ directed
that the sum awarded be paid within a period of three months, and in              E
default thereof it shall carry interest at 9 per cent per annum till payment
is made or till the passing t ~the decree by the Civil Court, whichever' is
earlier.

      The appellant applied for setting aside the award while the respon-
dent applied for making it the Rule of the Court. The Subordinate Judge           F
over-ruled the objections raised by the appellant and made the award a
rule of the court. So far as interest was concerned, it was directed, evidently
under a mistake, that the amount awarded by the Arb1trator shall carry
"interest at the rate of 6 per cent per annum", whereas the Arbitrator
awarded interest at the rate of 9 per cent.                                       G
       On appeal to the High Court a Single Judge affirmed the Judgment
·of the Subordinate Judge, and corrected the aforesaid error relating to
 interest.

      In the appeal to this Court it was contended on behalf of the               H
                                221
    222                    SUPREME COURT REPORTS (1992] SUPP. 3 S.C.R.

A   appellant, that all the claims made by the respondent pertain to addition.al
    'fOrk, and that the decision of the Superintending Engineer was final with
    respect to the amount payable therefor. A claim with respect to additional
    work done cannot be the subject matter of arbitration in view of Clause 11
    of the Agreement read with Clause 23 thereof. Relying on the decision in
B   Executive Engineer (Irrigation) v. Abaaduta Jena, [1988] 1 S.C.C. 418 the
    power of the ~bitrator to award interest for the pre reference period was
    assailed.

          Allowing the appeals in part and remitting the matter to the Subor-
    dinate Judge, this Court,
c           HELD: 1. In the event of dispute, the decision of the Superintending
    Engineer is made final. It is evident from the use of the words "as lastly
    hereinbefore mentioned", that the proviso applies to second part of Clause
    11 but not to the first part. The proviso contemplates a situation where
    additional work is done by the contractor before the rates are determined.
D   It is only in 'l°espect of the rates payable for such work that the decision of
    Superintending Engineer is made final. It is not the case of the appel-
    lant/State that the items tor which the Arbitrator has awarded the
    aforesaid amount was a work of the nature contemplated by the proviso.
    If so, there is n,!> bar to the dispute relating to rates for the additional work
E   being referred to the Arbitration. [227 -E·F]

          2. G.C. Roy's case was confined to the power of the Arbitrator to
    award interestpendente lite:It did not pertain to nor did it pronounce upon
    the power of the Arbitrator to award interest for the period prior to his
    entering upon the reference (pre-reference period). [228-A]
F
          3. The Arbitrator had no power to award interest for the pre-refer-
    ence period in.this case inasmuch as the.award was made prior to coming
    into force of the Interest Act, 1978. So far as interest for the period during
    which the arbitration proceedings were pending (pendente lite interest) is
    concerned, the Arbitrator does have the power to award the same.
G                                                                        [228-B-C]
         · Executive Engineer (Irrigation) v. Abaaduta Jena, [1988) 1 S.C.C. 418,
    followed.

          Secretary Irrigation Department, Govt. of Orissa & Ors. v. G.C. Roy,
H [1992] 1 S.C.C. 508, referred to.
          STATEOFORISSA v. B.N.AGARWAI.:A[JEEVANREDDY,J.)                        223

          4. The interest awarded by the Arbitrator (Rs. 61,086.69p.) pertains          A
    both to the pre-reference period as well as period during which the
    arbitration proceedings were pending <pendente lite). It is not clear from
    the material placed before th.e Court when the Arbitrator entered upon the
    reference. In these circumstances the matter has to go back to the Subor-
    dinate Judge for ascertaining the interest for the period prior to the
    Arbitrator entering upon the reference (p~e-reference period). The respon-
                                                                                        B
    dent shall not be entitled to interest for the pre-reference period. The
    award shall stand modified to this extent. [228-E-F]

          CIVIL APPELLATE JURISDICTION : Civil Appeal Nos.3096-97
    of 1981.                                                                            C
         From the Judgment and Order dated 20.4.1981 of the Orissa High
    Court in Misc. Appeal Nos. 253 & 254 of 1980.

          Raj Kumar Mehta for the Appellant.

          Vinoo Bhagat for the Respondent.
                                                                                        D

          The Judgment of the Court was delivered by

          B.P. JEEVAN REDDY, J. Civil Appeal No. 3096of1981 arises from
    the judgment of a learned Single Judge of Orissa High Court in Miscel-
                                                                                        E
    laneous Appeal No. 253 of 1980. Civil Appeal No. 3097of1981 arises from
    Miscellaneous Appeal No.254 of 1980. The appeals pertain to two identical
    contracts entered into between the State of Orissa and the respondent, Sri
    B.N. Agarwala. All the relevant facts and contentions are identical in both
    the appeals. It would, therefore, be sufficient if we refer to the facts in Civil
    Appeal No.3096 of 1981.                                                             F
           An agreement No. 8-F2/67-68 was entered into between the State of
    Orissa (appellant) and the respondent for construction of Kukuteswar
    Minor Irrigation Project. The value of the agreement was Rs. 3,84,690. The
    work was completed on 11.9.69. On 8.8.77, the respondent claimed certain
    amount on account of extra work done by him, which dispute was referred G
    to Sri B.N. Das, Superintending Engineer, as the sole Arbitrator. He made
    a reasoned award on 25.2.1980 granted a total sum of Rs. 1,59,298. This
    amount comprised of Rs. 61,036.61p. towards interest and Rs. 98,212.09p.
    towards the extra work done by the respondent. The interest amount Rs.
    61,086.61p. represented interest for the period 10.10.69 to 24.2.80. In other H



•
    224                   SUPREME COURT REPORTS (1992] SUPP. 3 S.C.R.

A words this sum represented interest both for the pre-reference period as
    well as for the period the Arbitration proceedings were pending (Pendente
    lite interest). The Arbitrator directed that the said sum of Rs.1,59,298
    should be paid within a period of three months, in default where of it shall
    ~rry interest at the rate of 9 pe_r cent per annum till the payment is made
    or till the passing of the decree by the Civil Court, whichever is earlier.
B
          The appellant applied for setting aside the award while the respon-
    dent applied for making it the Rule of the Court. The learned Subordinate
    Judge over-ruled the objections raised by the appellant and made the
    award a rule of the court. Sci far as interest is concerned, he directed,
C   evidently under a mistake, that the amount awarded by the Arbitrator shall
    carry "interest at the rate of 6 per cent per annum as per the award." (As
    stated hereinbefore the arbitrator awarded interest at the rate of 9 per cent
    and not 6 per cent. For the period subsequent to the award, however, he
    awarded interest at the rate of 6 per cent).

D          On appeal, the learned Single· Judge of the Orissa High Court
    affirmed the judgment of the learned Subordinate Judge. He corrected the
    aforesaid error relating to rate of interest. He directed that the sum of
    Rs.1,59,298 shall carry interest at the rate of 9 per cent per annum from
    25.5.80 till the date of decree and at the rate of 6 per cent per annum from
E   the date of the decree of the learned· Subordinate Judge till the date of
    realisation.

           The first contention urged by the learned counsel for the appellant
    before us relates to the very maintainability of the arbitration dispute with
    respect to the claims made by the respondent. The contention is that all
F   the claims made by the respondent pertained to additional work. So far as
    additional work is concerned, the decision of the Superintending Engineer
    is final with respect to the amount payable therefor. A claim with respect
    to additional work done cannot be the subject matter of arbitration. This
    contention is based upon clause-11 of the Agreement read with Clause-23.
G   For a proper appreciation of the said contention it is necessary to set out
    Clause-11 in its entirety. It reads as follows:

            "C/ause-11:

            The Engineer-in-Charge shall have power to make any
H           alterations or addition to the original specifications, draw-
        STATEOFORISSA v. B.N.AGARWALA[JEEVANREDDY,J.]                       225

         ings, designs and instructions that may appear to him to                 A
         be necessary or advisable during the progress of the work,
         and the contractor shall be bound to carry out the work,
         in accordance with any instructions which may be given

-        to him in writing signed by the Engineer-in-Charge, and
         such alteration shall not invalidate the contract and any
         additional work which the contractor may be directed to
         do in the manner above specified as part of the work, shall
                                                                                  B

         be carried out by the contractor on the same conditions
         in all respects on which he agreed to do the main work,
         and at the same r-ates as are specified in the tender for
         the main work. The time for the completion of the work                   c
         shall be extended in the proportion that the additional
         work bears to the original contract work and t~e certifi-
         cate o( the Engineer-in-Charge shall be conclusive at to
         such proportion and if the additional work includes any
         class of work, for which no rate is specified in this contract
                                                                                  D
         then such class of work shall be carried out at the rates
""\~'
         entered in the sanctioned schedule of:rates of the locality
         during the period when the work is being carried on and
'   .    if such last mentioned class of work is not entered in the
         schedule of rates of the district then the contract shall
         within seven days of the date of his receipt of his order                E
         to carry out the work inform the Engineer-in-Charge of
         the rate which it is his intention to charge for such class
          of work and if the Engineer-in-Charge does not agree to
          this rate he shall by notice in writing be at liberty to cancel
          his order to carry out such class of work and arrange to                F
          carry it out in such manner as he may consider advisable.
<
               No deviations from the specification stipulated in the
 '•~      contract or additional items of works shall ordinarily be
          carried out by the contractor, nor shall any altered, addi-
          tional or substituted work to be carried out by"him, unless             G
          the rates of the Substituted, altered or additional items
          have been approved and fixed in writing by the Engineer-
          in-Charge. The contractor shall be bound to submit his

-=        claim for any additional work done during any month on
          or before the 15th day· of the following· month accom-                  H
     226                  SUPREME COURT REPORTS [1992] SUPP. 3 S.C.R.

A            panied by a copy of the order in writing of the Engineer-
             in- Charge, for the additional work and that the contractor
             shall not be entitled to any payment in respect of such
             additional work if he fails to submit his claim within the
             aforesaid period.

B                  Provided always that if the contractor shall· com-
              mence work incur any expenditure in . regard thereof
              before the rates shall have been determined as lastly _
              hereinbefore mentioned, then and _in such case he shall only
              be entitled to be paid in respect of the work carried out
C             or expenditure incurred by him JJrior to the date Of the
              determination of the rate as aforesaid according to such
             .rate or rates as shall be fixed by the Engineer-in-Charge.
              In the event of a dispute, the decision of the Superinten-
              q~nt Engineer of the Circle will be final."


D.                                                   (emphasis added)

            Clause 23· is the Arbitration Clause in the agreement. According to
     this Clause all disputes and claims arising out of or relating to the agree-
     ment shall be referred to the arbitration of the Superintending Engineer
     of the State Public Works Department connected with the work nominated
     by the concerned Chief Engineer. For the present purpose only the open-
     ing words of"Cla~se-23 are relevant. The opening words are "except where,
     otherwise providedJn the contract all questions and disputes ............ ".

           The contention of· the learned' counsel for the appellant is that by
F    virtue of the proviso contained in Clause-11, the decision of the Superin-
     tending Engineer of the Circle is final on any dispute relating to the rates
     payable for the extra work done by the Contractor. It is not possible to
     agree. Clause-11 is in three parts.
                                                                                    i
                                                                                    I
           The first part says that a contractor is bound to carry out such extra
G work as he m~y ge called upon to do by the Engineer"in-Charge. The extra
   work shall.have; to :be carried out subject to the same conditions in all
                                                                                    (
   respects as. are applicable to the main work and at the' same rates. If,
   however, the agreement does not contain rates for such work, the rates
 . entered in· the sanctioned schedule of the rates of locality during the
H relevant period shall be applicable. If, however, the schedule of rates also
      STATEOFORISSA v. B.N.AGARWALA[JEEVANREDDY,J.]                        227

does not provide for such work the contractor should, within seven days of A
the order to do such additional work, inform the Engineer-in-Charge of
the rates which he proposes to charge. If the Engineer-in-Charge does not
agree thereto, it is open to the Engineer-in-Charge to get the said extra
work done through some other agency.

      The second part of the Clause-11 says that no deviations from the B
specifications stipulated in the contract or additional items of work shall
ordinarily be carried out by the contractor unless the rates therefor ar~
approved and fixed in writing by the Engineer-in-Charge. The contractor
must submit· his claim for the additional work done during any month on
or before the 15th day of the following month accompanied by a copy of C
the order in writing of the Engineer-in-Chief for doing additional work. If
he does not so submit the claim, he is not entitled to any payment.

      ·The third part of clause-11 contains the proviso relied upon by the
counsel for the appellant before us. It says that if the contractor shall. D
commence work and incur any expenditure before the rates shall have been
determined "as lastly hereinbefore mentioned" he shall only be entitled to
be paid for such work at such rate as may be determined by the Engineer-
in-Charge. In the event of dispute, the decision of the Superintending
Engineer is made final. It is evident from the use of the words "as lastly
hereinbefore mentioned" that the proviso applies ~o second part of Clause- E
11 but not to the first part. The proviso contemplates a situation where
additional work is done by the contractor before the rates are determined.
It is only in respect of the rates payable for such work that the decision of
Superintending Engineer .is made final. It is not the case of the appel-
lant/State that the items for which the Arbitrator has awarded the aforesaid F
amount was a work of the nature contemplated by the proviso. If so we see
no bar to the dispute relating to rates for the additional work being
referred to arbitration. The first contention is accordingly rejected.

      The next contention of learned counsel for the appellant/State relates
to the power of the Arbitrator to award interest for the pre-reference            G
period. Reliance is placed upon the decision of this Court in Er:ecutive
Engineer (Irrigation) v. Abaaduta Jena, [1988] 1 S.C.C. 418. Sri Bhagat,
learned counsel appearing for the respondent, however, submits that the
said decision is no longer good law in view of the Constitution Bench
decision in Secretary1, Irrigation Departmellt, Govt.. of Orissa & Ors. v. G.C.   H
    228                   SUPREME COURT REPORTS [1992] SUPP. 3 S.C.R.

A   Roy, [1992] 1 S.C.C. 508. We cannot agree with Sri Bhagat. Both of us were
    members of the Constitution Bench which decided G.C. Roy. It was con-
    fined to the power of the Arbitrator to award interest pendente lite. ·It did
    not pertain to nor did it pronounce upon the power of the Arbitrator to
    award interest for the period prior to his entering upon the reference
    (pre-reference period). This very aspect has been clarified by one of us
B   (B.P. Jeevan Reddy, J.) in his co~curring order in I.A. No.10 in Civil
    Appeal No;l763of1980 etc. disposed of on 22.10.92. Accordingly, we hold
    following the decision in Jena that the Arbitrator had no power to award
    interest for the pre-reference period in this case inasmuch as the award
    was made prior to coming into force of the Interest Act, 1978. (The Interest
c   Act, 1978 came into force with effect from 19th August, 1981) So far as
    interest for the period during which the arbitration proceedings were
    pending (pendente lite interest) is concerned, the Arbitrator does have the
    power to award the same as held in G.C. Roy. A request iS made by Sri
    Bhagat to refer the matter to a larger Bench to decide the question relating
    to the power of the Arbitrator to award interest for the pre-reference
D   period even in cases where the award is made before the coming into force
    of Interest Act, 1978. Jena was decided by a Bench of three Judges. We
    do not also feel persuaded to refer the matter to a larger Bench.

          The interest awarded by the Arbitrator (Rs. 61,086.69p.) pertains
E   both to the pre-reference period as well as period during which the
    arbitration proceedings were pending (pendente lite). It is not clear from
    the material placed before us when did the Arbitrator enter upon the
    reference. In the circumstances the matter has to go back to the learned
    Subordinate Judge for ascertaining the interest for the period period to the
    arbitrator entering upon the reference (pre-reference period). The respon-
F   dent shall not be entitled to interest for the pre- reference period as stated
    above. The award shall stand modified to the above extent. In all other
    respects, the award is affirmed.

          The Appeals are accordingly allowed in part. The matter is remitted
G   to the learned Subordinate Judge for working out the direction contained
    in the preceding paragraph. 'No orders to costs.

    N.V.K.                                               Appeals partly allowed.


Search Indian case law

Ask in plain English, not just keywords. 25,000 AI words free, no card.

Try "arbitration"Sign in to search

For a digitally signed copy suitable for filing, refer to the court's own website. Only the court can issue one.