Created byFuzzy Cloud

Supreme Court of India

STATE OF RAJASTHAN & ANR.versusMIS. FERRO CONCRETE CONSTRUCTION PVT. LTD.

Citation
2009 INSC 580
Decided
22 April 2009
Disposal
Appeal(s) allowed

Holding

The Supreme Court set aside the arbitrator's awards on claim 1 and claim 37A due to legal misconduct and error apparent on the face of the award, reduced the interest rate to 9% per annum, and upheld the remaining awards.

Summary

The State of Rajasthan entered into a contract with Ferro Concrete for a water‑pipeline project. After the contractor failed to complete the work, arbitration was instituted and the arbitrator awarded various sums, including loss of profit (claim 1), idle‑machinery compensation (claim 37A), and interest at 18% per annum. The employer challenged the award, alleging legal misconduct and errors apparent on the face of the award, particularly that the arbitrator ignored contract terms on mobilization advance and awarded interest above the permissible rate. The Supreme Court held that the arbitrator had committed legal misconduct and made a clear error in claims 1 and 37A, setting those awards aside and reducing the interest rate to 9% p.a., while upholding the remainder of the award. The appeals were partly allowed, modifying the award accordingly.

Issues considered

  • When did the arbitrator commit legal misconduct or an error apparent on the face of the award in claim 1 (loss of profit) and claim 37A (idle‑machinery compensation)?
  • Whether the award of interest at 18% per annum under the Arbitration Act, 1940 and the Interest Act, 1978 exceeds the permissible rate and is therefore erroneous.
  • Whether the arbitrator had jurisdiction to award interest for pre‑reference, pendente‑lite and future periods in the absence of an express contractual bar.
  • Whether claim 37A was beyond the reference as it was based on a claim not made and on a hypothetical future breach.
  • Whether any other claims or counter‑claims suffered from infirmities that would justify setting aside the award.

Legislation cited

Subjects

ArbitrationSection 30 Arbitration ActLegal misconductError apparent on the face of the awardInterest awardMobilization advanceContract breachJurisdiction of arbitratorAward modification

Judgment

-I
                                 [2009) 10 S.C.R. 31
     "<


1
                          STATE OF RAJASTHAN & ANR.                           A
                                           v.
              MIS. FERRO CONCRETE CONSTRUCTION PVT. LTD.
                       (Civil Appeal No.· 2764 of 2009)
                                   APRIL 22, 2009
                                                                              B
                 [R.V. RAVEENDRAN AND LOKESHWAR SINGH
                                PANTA, JJ.]

                 ARBITRATION ACT, 1940
                                                                              c
                  s.30- Setting aside of award- Held: When there is no
            allegation of moral misconduct against arbitrator, award can
            be attacked if there was legal misconduct on the part of the
     ~      arbitrator in making the award and/or if there was an error
            apparent on the face of the award - In the instant case, the
                                                                             D
            arbitrator, in respect of claims 1 and 37-A of the contractor
            and rate of interest payable to contractor (claims 12 and 13)
            committed a legal misconduct by ignoring terms of contract
            and it was also a case of error apparent on the face of award
            - In a reasoned award if claim of contractor is equated to proof
            of the claim, then it is obviously a legal misconduct and an E
      .-4
            error apparent on the face of award - Allowing of interest at
            18% in an award governed by 1978 Act was an error on the
            face of award - The rate of interest could not exceed the
            current rate of interest - As regards the award in respect of
            other claims and counter claims, neither want of jurisdiction F
            nor legal misconduct nor any error apparent on the face of
            award was made out, therefore, the award in respect of those
            claims and counter-claims is upheld - Award modified
            accordingly - Interest Act, 1978.
     ~
                                                                             G
                 INTEREST ACT, 1978 :

                 S.3- Interest on claims allowed in an award made under
..          Arbitration Act, 1940 - Held: In the absence of an express bar,
                                          31                                  H
-
        32       SUPREME COURT REPORTS               [2009] 10 S.C.R.
                                                                                 ~



        arbitrator had jurisdiction to award interest for pre-reference,    •
    A
                                                                                 ~
        pendente lite and future periods - However, award of interest
        at a rate higher than the current rate is an error on the face of
        award - Award modified accordingly - Arbitration Act, 1940.

           The appellant (employer) entered into a contract with
    B
      the respondent-contractor for manufacture, laying,
      testing and commissioning of water pipeline at a length               ~
                                                                                 •
      of 37.41 kilometers. The value of the work as per the work
      order was Rs. 9,91,94,602.50. Since the contractor could
      not complete the work within the stipulated time, the
    c employer    got the work completed through alternate
      agency by treating the contract as having been
      abandoned. As regards the settlement of disputes
      between the parties through arbitration, the matter
      reached the Supreme Court and ultimately a sole
    D arbitrator was appointed. Before the arbitrator the
                                                                            .
      contractor filed its claim in 43 heads aggregating to
      Rs.6,21,29,626/-. The employer, besides filing its reply to
      the claim statement, made five counter claims to the tune
      of Rs.11,55,98,388/-. The arbitrator allowed certain claims
    E of the contractor amounting to about Rs.1,&7,00,000 and
      one counter claim of the employer (amounting to
      Rs.59,42,275/-. The contractor filed an application to make
                                                                            j.
      the award a rule of the court. The civil court allowed the
      application subject to modification of the award made on
    F claim 37-A of the contractor (direction to employer to pay
      Rs.12,072/- per day towards idle charges for machinery
      and staff etc. from the date of award) holding that the said
      charges would be payable per day from the date of
      decree. Both, the employer as also the contractor filed
    G appeals. The High Court dismissed the appeal of the
                                                                            i-
      employer and allowed that of the contractor restoring the
      direction of the arbitrator to pay the compensation of
      Rs.12,072/- per day from the date of the award.

             In the appeals filed by the employer, the question for
    H
            STATE OF RAJASTHAN v. FERRO CONCRETE                   33
                    CONSTRUCTION PVT. LTD.
    _,
         consideration before the Court was : whether there was          A
         any legal misconduct or error apparent on the face of the
         award, in regard to the award of the arbitrator in respect
         of the claims and counter-claims.

             Allowing the appeals in part, the Court                     B
              HELD: 1.1. Section 30 of the Arbitration Act, 1940 inter
         alia provides that the award can be set aside on the
         ground that the arbitrator had misconducted himself or
         the proceedings, or that the award had been improperly
         procured or is otherwise invalid. An error apparent on the      c
         face of the award, is a ground for setting aside the award
         u/s 30 or for remitting the award to the arbitrator u/s 16(1)
         (c) of the Act. [Para 13] [46-8-C]
.   ~

            Champsey Bhara & Co. vs. Jivraj Ba/loo Spinning &            D
         Weaving Co. Ltd. AIR 1923 PC 66, referred to.

              1.2. Under the Arbitration Act, 1940, an award was not
         open to challenge on the ground that the arbitrator
         reached a wrong conclusion or failed to appreciate facts,       E
         as under the law the arbitrator is made the final arbiter of
         the dispute between the parties. While considering the
    .J   challenge to an award, the court will not sit in appeal over
         the award nor re-appreciate the evidence for the purpose
         of finding whether on the facts and circumstances, the
                                                                         F
         award in question could have been made. When there is
         no allegation of moral misconduct ~gainst the arbitrator
         with regard to the award, and where the arbitration has
         not been superseded there were only two grounds of
         attack (i) that there was legal misconduct on the part of
         the arbitrator in making the award and (ii) that there was      G
         an error apparent on the face of the award. [Para 13] [46-
         E-H; 47-A]

              State of Rajasthan vs. Puri Construction Co. Ltd. 1994
         (6) sec 485, referred to.                                       H
    34       SUPREME COURT REPORTS            [2009] 10 S.C.R.


A      2.1. In the instant case, as regards claim-1 of the
  contractor towards loss of profits and overheads on
  account of alleged inordinate delay in releasing the
  mobilization advance, it is true that clause 3 of Common
  Terms Reference did not contemplate the mobilization
B advance being released in 3 installments. But the CTR
  was followed by work order dated 23.8.1988 and by
  amendment dated 8.11.1988 which specifically stated that
  the mobilization advance would be paid in 3 installments
  of which the second and the third installments would be
c paid on production of a certificate of the Chartered
  Accountant about utilization of the previously paid
  amount on verification by the department towards
  progress of the factory. The arbitrator has held that the
  said clause was unilaterally introduced and,. therefore,
0 was not binding on the contractor. On the face of it, this
  is erroneous. [Para 18] [53-B-E]

        2.2. It is evident that the mobilization advance had to
   be released only against bank guarantee to be furnished
   liy the contractor. The mobilization amount
E corresponding to the first bank guarantee was released
   within two days. The amount corresponding to the
   second and third bank guarantees was to be released
   only after the contractor had produced a certificate in
   regard to the utilization of the earlier advance. Therefore,
J! it cannot be said that there was delay or breach on the
   part of the employer in releasing mobilization advance. If
   at all there was any delay, it was on the part of the
   contractor. (Paras 18 and 19] (54-C, E-G; 55-A-B]

G     2.3. The fact that release of mobilization advance was
  governed by clause 5(1 )(b) of the work order (as amended
  on 8.11.1988) and clause 7 of the agreement dated
  11.1.1989 was totally overlooked by the arbitrator by
  proceeding on the basis that mobilization advance was
H governed by the CTR alone. The arbitrator committed a
   STATE OF RAJASTHAN v. FERRO CONCRETE                35
           CONSTRUCTION PVT. LTD.
legal misconduct by ignoring the terms of contract, i.e., A
the agreement dated 11.1.1989, which specifically
provided that in addition to the CTR, the work order and
amendment to work order dated 8.11.1988 would also
form part of the contract. The arbitrator also overlooked
the fact that the additional provision regarding 8
mobilization advance was introduced in the agreement
itself. Therefore, the mobilization advance was governed
by the terms in the CTR, the work order, the amendment
to the work order dated 8.11.1988 and the agreement
dated 11.1.1989 read together. If so read, it was clear that C
there was no breach on the part of the employer but the
contractor itself was responsible for the delay and,
therefore, the question of compensating the contractor on
that score does not arise. [Para 19) [55-A-E]

       3.1. Claim No. 37-A i.e. compensation at the rate of D
 Rs. 12,072/- per day towards idle charges for machinery,
 staff etc. was linked to mobilization advance. The
 arbitrator considered claim 37-A with three other claims
 (36, 36-A and 37) and held that none of the 4 claims was
 maintainable as the factory built out of mobilization E
 advance had been mortgaged in favour of the employer.
 As a consequence, he did not award any amount in.
 res.pect of these 4 claims, still he directed payment of
 Rs.12,072/- per day from the date of award not because
 he held that there was any loss of production as a F
 consequence of any breach by the employer, but
 because he had made an award against the contractor
 in favour of the employer for Rs. 59,42,275/- with interest.
 The arbitrator was of the view that if that sum was
 adjusted against the amount due by the employer, there G
 was no need for the mortgage of the plant to continue and,
 therefore, the employer should release the document of
 title deposited by way of equitable mortgage, within 30
 days from the date of award; and if the employer failed .
ito do so, the employer should pay the contractor Rs. H
    36       SUPREME COURT REPORTS            (2009] 10 S.C.R.


A 12,072/- per day from the date of the award till the date
  of release of the mortgage. Thus, the award under claim
  37-A was made not on account of any breach committed
  by the employer, but in respect a breach if made in future
  after the date of the award. There was no such claim and
B the award was, therefore, beyond the refere:ice. It is a
  clear case of an error apparent on the face of the award
  and a legal misconduct. [Paras 21, 23 and 24] [56-B; 57-
  B-C-F-H; 58-A-F-H; 59-A-B]

         3.2. It is significant to note that as per the award of
c the arbitrator, made under claim 37-A , on a claim that
  was never made, the amount that would become due at
  Rs.12,072/- per day from 21.9.1994 to date will be
  approximately Rs.6,42,70,000/-. This is a strange situation
  where the arbitrator makes an award in favour of the
D employer directing the contractor to refund the employer
  Rs.59,42,275/- with interest at 18% per annum from
  18.9.1990 upto date of decree/payment and then even
  though the said payment was not made, awards
  damages to the contractor which works out to
E Rs.6,42,70,000/-. This again is a legal misconduct and an
  error apparent on the face of the award. [Para 26] [60-8-
    D]
       3.3. In a reasoned award if the claim of a contractor
F is  equated   to proof of the claim, then it is a legal
  misconduct and an error apparent on the face of the
  award. While the quantum of evidence required to accept
  a claim may be a mater within the exclusive jurisdiction
  of the arbitrator to decide, if there was no evidence at all
  and if the arbitrator makes an award of the amount
G
  claimed merely on the basis of the claim statement
  without anything more, it has to be held that the award
  on that count would be invalid. In the instant case, the
  sum of Rs. 12,072/- per day under claim 37-A was claimed
  as damages by the contractor in a two line calculation
H                                                                  ,
        STATE OF RAJASTHAN v. FERRO CONCRETE                  37
                CONSTRUCTION PVT. LTD.

     without any supporting evidence document. The claim is A
-·   made on the ground that the contractor was disabled
     from manufacturing the stated number of pipes
     elsewhere. There is no evidence that it had other
     contracts where it was required to manufacture that
     number of pipes or that it could not manufacture the B
     required pipes for want of plant and machinery. However,
     in the award the arbitrator neither considered the validity
     of the claim of Rs.12,072/- per day-nor did he accept the
     said claim as valid or correct. Therefore, the entire award
     under this head being wholly illegal and beyond the C
     jurisdiction of the arbitrator, cannot be sustained and is
     set aside. [Paras 27 and 29] [61-D, E; 60-G, H; 61-C]

          4.1. So far as claims 12 and 13 of the contractor are
     concerned, it is no doubt true that the position of law
                                                                    0
     earlier was that in regard to award of damages, interest
     was not payable before quantification by a court. But, the
      position regarding award of interest after the Interest Act,
     1978 came into force, can be stated thus : (a) where a
     provision has been made in any contract, for interest on E
     any debt or damages, interest shall be paid in accordance
     with such contract; (b) where payment of interest on any
     debt or damages is expressly barred by the contract, no
     interest shall be awarded; (c) where there is no express
     bar in the contract and where there is also no provision
     for payment of interest then the principles of s.3 of Interest F
     Act will apply in regard to the pre-suit or pre-reference
     period and consequently interest will be payable: (i)
     where the proceedings relate to a debt (ascertained sum)
     payable by virtue of a written instrument at a certain time,
     then from the date when the debt is payable to the date G
     of institution of the proceedings, (ii) where the
     proceedings is for recovery of damages or for recovery
     of a debt which is not payable at a certain time, then
     interest will be payable from the date mentioned in the
                                                                    H
    38       SUPREME COURT REPORTS             [2009] 10 S.C.R.


A written notice (given by the person making a claim to the
    person liable for the claim), to date of institution of
    proceedings; (d) payment of interest pendente lite (date
    of institution of proceedings to date of decree) and future
    interest (from the date of decree to date of payment) shall
8   not be governed by the provisions of Interest Act, 1978
    but by the provisions of s.34 of Code of Civil Procedure,
    1908 or the provisions of the law governing Arbitration
    as the case may be. In the instant case, there was no           ..
    express bar in the contract in regard to interest and,
c   therefore, the arbitrator had the jurisdiction and authority
    to award interest for all the three periods- pre reference,
    pendente lite and future. Since interest has been awarded
    only from 3.9.1990, i.e. the date of the petition u/s 20 of
    the Act for appointment of arbitrator, there is no reason
    to alter the date of commencement of interst. [Paras 31,
0
    32 and 34-35] [63-E; 65-C-H; 66-A-B-E]

        Bhagwati Oxygen vs. Hindustan Copper Ltd. 2005(6)
    SCC 462; Secretary, Irrigation Department, Government of
    Orissa vs. G.C. Roy 1992(1) SCC 508 and Executive
E   Engineer, Dhenkana/ Minor Irrigation Division vs. N. C.
    Budharaj 2001(2) SCC 721, relied on.

         Iron & Hardware {India) Co. vs. Firm Sham/al & Bros. AIR
    1954 Bombay 423, referred to.
F
       4.2. However, the awarding of interest at 18% per
  annum, in an award governed by the Arbitration Act, 1940
  was an error apparent on the face of the award. In regard
  to award of interest governed by the Interest Act, 1978,
  the rate of interest could not exceed the current rate of
G interest which means the highest of the maximum rates
  at which interest may be paid on different classes of              ....
  deposits by different classes of scheduled banks in
  accordance with the directions given or issued to
  banking companies generally by the Reserve Bank of
H
                 STATE OF RAJASTHAN v. FERRO CONCRETE                 39
                         CONSTRUCTION PVT. LTD.
              India under the Banking Regulation Act. Therefore, pre-       A
    -+        reference interest_ should be only at the rate of 9% per
              annum. It is appropriate to award the same rate of
              interest even by way of pendente lite interest and future
              interest upto date of payment. [Para 36] [66-F-H; 67-At
                                                                            ·B
                  5. As regards allowing or rejecting of other claims or
              counter claims, by the arbitrator, the awards on these
              counts do not suffer from any infirmity which can be the
              basis for interference either u/s 30 or u/s 16 of the
              Arbitration Act, 1940. Neither want of jurisdiction, nor       C
              legal misconduct, nor any error apparent on the face of
              the award, are made out in regard to these claims. No
              ground is made out to interfere with the same. Judgments
              of courts below modified accordingly.
              [Paras 37, 38 and 40) (67-E, G; 68-G]
                                                                            D
                                  Case Law Reference:

                  AIR 1923 PC 66           referred to         Para 13..

                  1994(6) sec 485          referred to         Para 13
                                                                             E
                  2005(6) sec 462          relied on .         Para 31

                  1992(1) sec 508          relied on           Para 31
         "'       2001(2) sec 121          relied on           Para 31
                                                                             F
                  AIR 1954 Bombay 423 referred to              Para 32

                  CIVIL APPELLATE JURISDICTION : Civil Appeal No.
              2764 of 2009.

                  From the Judgment & Order dated 5.2.2007 of the High      G
              Court of Rajasthan Jaipur Bench, Jaipur in S.8. Civil Misc.
-         J   Appeal No. 872 of 2003.

                                         WITH
                                                                             H
    40           SUPREME COURT REPORTS           [2009] 10 <;;'>('.} R


A            C.A. No. 2767 of 2009.

         Vijay Hansaria, Jatinder Kumar Bhatia, B.N. Jha and Sneh
    Kalita for the Appellants.

             Dushyant Dave, Ravindra Shrivastava, Kishore
8 Shrivastava, Kunal Verma, Rajul, Shrivastava, Aniruddh Rajput,
    Manish Chaudhary, C. G. Solshe for the Respondents.

             The Judgment of the Court was delivered by                      ..
c            R.V. RAVEENDRAN, J. 1. Leave granted. Heard learned
    counsel.

       2. The appellants (also referred to as 'employer') invited
  tenders for the manufacture, laying, testing and commissioning
  of water pipeline of a length of 37.41 km. under a water supply
0
  scheme in Ajmer District. Tenders were received from various
  tenderers including respondvnt (hereinafter referred to as the
  'contractor'). As different tenderers had stipulated different
  terms and conditions, the tenderers were invited for
  discussions, and common terms of reference (for short 'CTR')
E were formulated on 22.2.1988 and the original tender
  conditions stood modified to the extent of the alterations in the
  CTR.

        3. Thereafter the offer of the respondent was accepted and
F a work order dated 23.8.1988 was issued to him stipulating the
  period for completing the contract as two years from that date.
  There was an amendment to the work order on 8.11.1988. The
  employer and the contractor entered into an agreement dated
  11.1.1989 enumerating and stipulating the documents which
G will form part of the contract and the modifications agreed in
  regard to certain terms. The value of the work as per the work
  order was Rs.9,91,94,602.50. Ten percent of the value of work          ~        ...
  (Rs.99.19 lakhs) which was agreed to be released as

H    '   .
  mobilization advance, was released to the contractor betweenJ
                        STATE OF RAJASTHAN v. FERRO CONCRETE                       41
                       CONSTRUCTION PVT. LTD. [R.V. RAVEENDRAN, J.]
                      25.1.1989 and 5.5.1989. The contractor created an equitable        A
        -I-           mortgage over its plant by depositing its title deeds thereto as
.....                 security for the mobilization advance. By letter dated
                      15.12.1990, the contractor confirmed that the original title
                      deeds will remain in deposit with the employer till the entire
                      amount of advance was repaid in full with interest.                B

                             4. The contract (clause 23 of General Conditions of
         ...           Contract) provided for settlement of disputes by arbitration. By
                       letter dated 18.6.1990 respondent invoked the provision for
                       arbitration and sought appointment of an arbitrator to decide
                       its claims aggregating to Rs.2,01,66,547, arising on account
                                                                                        c
                       of certain alleged omissions and commissions of the employer.
                      Another dispute was raised in respect of the rate payable for
                       work done subsequent to the due date of completion
                      (22.8.1990). On 22.8.1990 the contractor stopped the work. By
                      that date it had manufactured 15.26 km. of pipes and had laid D
                       11.6 km. out of them anc. tested only 1.4 km. of pipeline as
                      against the total contracted quantity of 37.41 km. On 13.9.1990
                      the··employer notified the contractor that if he did not resume
                      the Work, the balance of the work would be got executed through
                     .an alternative agency in terms of the contract, by treating the E
                      contract as having been abandoned on 22.8.1990, and recover
                      the excess cost from the contractor.
               ,,            5. The respondent-contractor sent a reply dated 3.11.1990
                       stating its efforts to complete the work were rendered futile on F
                       account of the delays and breaches on the part of the employer;
                       and it was necessary to enter into a fresh agreement as the
                       tender was not accepted in the manner in which it ought to have
                       been accepted. The contractor did not resume the work. The
                       contractor's stand was that in the absence of an extension of G


-               ,\
                       time for completion by mutual consent before the stipulated date
                       for completion, it was not liable to continue the work on the
                       tendered rates. The employer on 30.3.1991 made a final
                     . demand calling upon the contractor to state whether it was ready
                     i to re-start and complete the remaining work and if so to submit
                                                                                        H
    42        SUPREME COURT REPORTS               [2009] 10 S.C.R.


A a revised time schedule for such completion. As the contractor             +
  did not resume the work, the employer initiated steps to get the
                                                                                 .;
  balance work executed through an alternative agency. In the
  meanwhile the contractor filed a suit against the appellant in the
  District Court, Ajmer and obtained a temporary injunction
B restraining the employer from imposing liquidated damages.
        6. The contractor made an application to the District Court,
   Aimer, under section 20 read with section 8 of the Arbitration        ...
   Act, 1940 (Act for short) for filing the arbitration agreement into
c cpurt   and seeking appointment of an arbitrator. The District
   Court. Ajmer by order dated 27.4.1991 held that it had
   jurisdiction to appoint an arbitrator but deferred the actual
   appointment to a future date. The contractor revised its claim
   to Rs.5,51,90,306/- in the notice of appointment of arbitrator.
   The employer challenged the order of the District Judge and
D the High Court allowed the appeal on 9.8.1991 and set aside
   the order of the District Judge. The contractor in turn
 · approached this Court. On 12.11.1991, this Court recorded the
   consent of parties for appointment of Mr. B L Mathur as sole
   arbitrator and directed the employer (Chief Engineer, Public
E Health Engineering Department, State of Rajasthan) to appoint
   him as the arbitrator. On being appointed, the arbitrator entered
   upon the reference and the contractor filed a claim statement
   before the arbitrator on 13.1.1992 making 43 claims.
   aggregating to Rs.6,21,29,626/-.
F
         7. The employer filed its reply to the claim statement, and
    al~o made five counter-claims aggregating for Rs.863,46,505/
  - before the arbitrator. In the meanwhile, the employer having
  concluded the arrangements to get the work completed through
G an alternative agency, on the contractor's failure to resume the
  work, awarded the work to M/s. Indian Hume Pipes Co. Ltd. on
  10.8.1992. On the basis of the contract value in regard to the
  ba'lance work, the employer revised its counter claim No. 2
  relating to extra cost to Rs.6,66,62,000/-and consequently the
                                                                         +
                                                                                 -
  total of the counter claims stood increased to Rs.11,55,98,388.
H
       STATE OF RAJASTHAN v. FERRO CONCRETE·                                 43
      CONSTRUCTION PVT. LTD. [RV. RAVEENDRAN, J.]
~-         8. After considering the claims and counter claims, the A
     learned arbitrator made an award dated 21.9.1994. He rejected
     claim nos. 4, 7,8,10, 14 21,22,23,26,36,36A, 37,38,39,40,41,
     & 41 A,42, & 42A and 43 of ·the contractor. He awarded the
     following amounts to the contractor in regard to the remaining
     claims:                                                        B
     S. Claim      Description of                         Amount       Amount
     No No.        claim                                  claimed      awarded
                                                               Rs.         Rs.
     1.   1        Loss of profitability due to late     83,49,913    33,06,500
                   release of mobilization advance                                 c
     2.   2 & 16 Refund of excess sales tax               2,94, 142    2,94,142
                 deducted
     3.   3 & 15 5% amount withheld for testing          14,70,956    14,70,956
                 of pipeline
     4.   5 & 18 Excess recovery of security             13,28,457    13,28,457
                                                                                   D
                 deposit
     5.   6 & 17 Price escalation                       58,83,854     43,47,520
     6.   9 & 19 Refusal of employer for re-            10, 11,354     6,95,910
                 designing pressure pipes from
                 higher into lower.
                                                                                   E
     7.   11 & 20 Slow progress due to reduction        21,32,496     21,07, 195
                  of width of trench
     8.   24      Refund of deduction for want of        4,31,926      4,31,926
                  BG renewal
     9.   27 & 28 Gap pipes fitted                       2,60,200        67,098
                                                                                   F
     10. 29       Payment for 8 kg pipes but paid
                  for 6 kg pipes
     11. 30       Refunds for paint of specials             9,759         9,759
     12. 31       Deduction from running bill for          22,385        22,385
                  pipes
                                                                                   G
     13. 32       Refund for deduction for                 46,569        46,569
                  insufficient refilling
     14. 33       Less measurement of pipe               1, 15,738     1, 15,738
     15. 35 with Difference in final bill bedding      1,47,00,000    23,74,458
         25      Less payment re: sand                    7,31,676
                                                                                   H
    44        SUPREME COURT REPORTS                [2009] 10 S.C.R.


A        34     Payment for excavation             2,50,740 ..
    16. 37A     Idle charges for machinery.         12.072    12,072 per
                staff etc.                    per day from     day from
                                                   13.1.92        date of
                                                                award, if
B                                                            the factory
                                                                was not
                                                            leased from
                                                               mortgage
                                                                 security
                                                               within 30
c                                                                  days.
    17. 12 & 13 Interest (pre-reference,          18% per       18% per
                pendente lite and future)          annum         annum

    The arbitrator rejected counter claims 1, 2, 4 and 5 of the
    employer. In regard to counter-claim No. 3 (Rs.79,87,846/-               ~
D
    towards refund of mobilization advance with interest), the
    arbitrator awarded a sum of Rs.59,42,275 with interest at 18%
    per annum from 18 9.1990 up to the date or decree or payment
    whichever was earlier.

E         9. The contractor made an application for making the
    award, a rule of the court. The employer challenged the award
    by filing objections under section 30 read with section 33 of the
    Act. By orde.r dated 17 .2.2003, the District Judge, Ajmer              ..
    allowed the application of the contractor and made the award
F   a rule of the court subject to a modification in regard to the
    award made on claim No.37 A. In place of the award made by
    the Arbitrator (direction to employer to pay Rs.12072/- per day
    from the date of award), the District Judge directed that the
    employer shall return the original title deeds to the contractor
G   and pay the amounts awarded to the contractor after deducting
    the amount awarded by way of counter-claim (that is                     .. ...
    Rs.59,42,275/- towards refund of mobilization advance due
    with 18% interest) within 30 days from the date of decree, failing
    which, the employer shall pay Rs.12072 per day from the date
    of decree.
H
                  STATE OF RAJASTHAN v. FERRO CONCRETE                         45
                CO~'STRUCTION PVT. LTD. [R.V. RAVEENDRAN, J.]
     •·             10. The employer filed an appeal (Civil Misc. Appeal A
               No.872/2003) against the said judgment and decree
               contending that the award ought to have been set aside. The
               contractor also filed an appeal (Civil Misc. Appeal No. 910/
               2003) aggrieved by the modification by the Learned District
               Judge directing compensation of Rs.12,072/- per day only from B
               the date of decree (instead of the date of award). The High court
     I         dismissed the appeal filed by the employer by judgment dated
               5.2.2007. The High Court allowed the appeal filed by the
               contractor by judgment dated 30.5.2007 and restored the
               direction of the arbitrator that the payment of compensation at        c
               Rs.12,072/- per day should be from the date of the award itself
               (21.9.1994). The High Court also granted interest at 18% per
               annum from the date of the award. Thus the High Court upheld
               the award .
         ...
                   11. Feeling aggrieved the employer has filed these two D
               appeals by special leave. The first of the appeals (arising out .
               of SLP [CJ No.10818/2007) is against the dismissal of its
               appeal on 5.2.2007. The second of the appeals (arising out of
               SLP(C)No.22565/2007) is against the judgment dated
               30.5.2007 allowing the contractor's appeal. One of the E
               contentions urged by the appellants before the court below was

"-
          ..   that the Arbitrator did not have jurisdiction to enter upon the
               reference and make an award, as the appointing authority under
               the arbitration clause had merely appointed the arbitrator, but
               had not referred any dispute to him for arbitration. The said          F
               contention was rejected by both courts on the ground that when
               the authority competent to appoint the arbitrator appointed the
               arbitrator, in pursuance of the agreement reached before this
               Court to have the pending disputes of both parties settled by
               arbitration, the employer could not be permitted to raise a            G
.~         1   technical plea that the arbitrator had no jurisdiction to proceed
               with the arbitration, in the absence of a further specific reference
               by the employer. Realising the unsoundness of the said
               contention, the appellants did not press it before us.
                                                                                      H
    46        SUPREME COURT REPORTS                (2009] 10 S.C.R.


A      12. On the contentions urged, the question that arises for
                                                                               •
  consideration is whether there is any legal misconduct or error
  apparent on the face of the award, in regard to the award of
  the Arbitrator in respect of (i) claims 1 and 37 A; (ii) claims 12
  & 13; (iii) claims 2 & 16, 3 & 15, 5 & 18, 6 & 17, 9 & 19, 11 &
B 20, 24, 27 & 28, 29, 30, 31, 32, 3:., 35 (with claim nos. 25,
  34); and (iv) counter claims 1, 2, 4 and 5.

        13. Section 30 of the Act inter alia provides that an award
  can be set aside on the ground that an arbitrator had
  misconducted himself or the proceedings, or that the award had
c been improperly procured or is otherwise invalid. An error
  apparent on the face of the award, is a ground for setting aside
  the award under section 30 or for remitting the award to the
  Arbitrator under section 16(1 )(c) of the Act. In Champsey Bhara
  & Co. vs. Jivraj Ba/loo Spinning & Weaving Co. Ltd. [AIR
D 1923 PC 66] the Privy Council explained the term ·an error of
  law on the face of the award' thus :

         "An error of law on the face of the award means that you
         can find in the award or a document actually incorporated
E        thereto as for instance, a note appended by the arbitrator
         stating the reasons for his judgment, some legal
         proposition which is the basis of the award and which you
         can then say is erroneous."                                      ..
    It was well settled that under the Arbitration Act, 1940, an award
F was not open to challenge on the ground that the arbitrator has
  reached a wrong conclusion or failed to appreciate facts, as
  under the law, the arbitrator is made the final arbiter of the
  dispute between the parties. While considering the challenge
  to an award, the court will not sit in appeal over the award nor
G re-appreciate the evidence for the purpose of finding whether
                                                                         ·I.
  on the facts and circumstances, the award in question could
  have been made. When there is no allegation of moral
  misconduct against the arbitrator with reference to the award,
  and where the arbitration has not been superseded, there were
H only two grounds of attack. First was that there was legal
              STATE OF RAJASTHAN v. FERRO CONCRETE                      47
                                        '
             CONSTRUCTION PVT. LTD. [R.V, RAVEENDRAN, J.]

•            misconduct on the part of the arbitrator in making the award. A
             Second was that there was an error apparent on the face of
             the award. This Court explained the principles relating to
             interference with awards under the 1940 Act in State of
             Rajasthan v. Puri Construction Co. Ltd. (1994 (6) SCC 485]
             thus:                                                         B

                  "Similarly, an award rendered by an arbitrator is open to
.,.               challenge within the parameters of several provisions of
                  the Arbitration Act. Since the arbitrator is a judge by choice
                  of the parties, and more often than not, a person with little
                  or no legal background, the adjudication of disputes by an
                                                                              c
                 arbitration by way of an award can be challenged only
                  within the limited scope of several provisions of the
                 Arbitration Act and the legislature in its wisdom has limited
                  the scope and ambit of challenge to an award in the
      ''         Arbitration Act. Over the decades, judicial decisions have D
                  indicated the parameters of such challenge consistent with
                  the provisions of the Arbitration Act. By and large the courts
                  have disfavoured interference with arbitration award on
                 account of error of law and fact on the score of mis-
                 appreciation and misreading of the materials on record E
                  and have shown definite inclination to preserve the award
                  as far as possible. As reference to arbitration of disputes
       ...       in commercial and other transactions involving substantial
                 amount has increased in recent times, the courts were
                 impelled to have fresh look on the ambit of challenge to F
                 an award by the arbitrator so that the award does not get
                 undesirable immunity. In recent times, error in law and fact
                 in basing an award has not been given the wide immunity
                 as enjoyed earlier, by expanding the import and
                 implication of "legal misconduct" of an arbitrator so that G
                 award by the arbitrator does not perpetrate gross
                 miscarriage of justice and the same is not reduced to
                 mockery of a fair decision of the lis between the parties
                 to arbitration. Precisely for the aforesaid reasons, the
                 erroneous applicatibn of law constituting the very basis of H
    48        SUPREME COURT REPORTS                (2009) 10 S.C.R.


A        the award and improper and incorrect findings of fact,                 •
         which without closer and intrinsic scrutiny, are
         demonstrable on the face of the materials on record, have
         been held, very rightly, as legal misconduct rendering the
         award as invalid. It is necessary, however, to put a note of
B        caution that in the anxiety to render justice to the party to
         arbitration, the court should not reappraise the evidences
         intrinsically with a close scrutiny for finding out that the
         conclusion drawn from some facts, by the arbitrator is,
         according to the understanding of the court, erroneous.
c        Such exercise of power which can be exercised by an
         appellate court with power to reverse the finding of fact, is
         alien to the scope and ambit of challenge of an award
         under the Arbitration Act. Where the error of finding of facts
         having a bearing on the award is patent and is easily
         demonstrable without the necessity of carefully weighing
0                                                                         _;,
         the various possible viewpoints, the interference with
         award based on erroneous finding of fact is permissible.
         Similarly, if an award is based by applying a principle of
         law which is patently erroneous, and but for such erroneous
         application of legal principle, the award could not have
E        been made, such award is liable to be set aside by
         holding that there has been a legal misconduct on the part
         of the arbitrator. In ultimate analysis, it is a question of
         delicate balancing between the permissible limit of error        ..
         of law and fact and patently erroneous finding easily
F        demonstrable from the materials on record and application
         of principle of law forming the basis of the award which is
         patently erroneous."

       Keeping the said principles in mind let us examine the
G various claims.
    Re: Claim 1 :

       14. The contractor claimed that the mobilization advance
  had to be released to it immediately on entrustment of work,
H to enable it to set up the factory for manufacturing the pipes. It
           STATE OF RAJASTHAN v. FERRO CONCRETE                      49
         CONSTRUCTION PVT. LTD. [R.V. RAVEENDRAN, J.]
·-"     was contended that prompt release of mobilization advance A
        was crucial and fundamental to the contract as manufacture of
        pipes depended upon setting up a factory for that purpose.
         Even assuming that the mobilization advance could be released
        in three instalments, as per modified terms and conditions, the
        contractor contended that there was inordinate delay on the part B
        of the employer in releasing the instalments, that too, in five
        instalments. It was further contended that if the mobilization
       advance had been released immediately on award of the work,
        it would have set up a factory and commenced production
       within three months; that in view of the delay, it lost production c
       for a period of eight months that is nearly one third of the
       contract period, and that as a consequence they were not able
       to execute the work of the value of Rs.5,56,66,086/- and the
       loss of profits and overheads on the said amount at a standard
       15% was Rs.83,49,913/- and it was entitled to that amount as
  '-                                                                      D
       compensation for the breach by the employer. The calculation
       of the said loss of profit and overheads in claim no.(1) was as
       follows:
         Amount of Contract (with "DIV)           Rs.9,91,94,602.00
         Payment already received from the                                E
         Department                              Rs. 2,88,28,516.00
                                               -----
         Balance                                 Rs. 7,03,66,086.00

                                                                          F
         Amount due to contractor against
         work Done                               Rs.1,47,00,000.00
                                               -------------
         Balance                                 Rs. 5,56,66,086.00
                                               ----------
                                                                          G
  j.     Loss of Profitability & overheads         Rs. 83,49,913.00
         @ 15% (0.15 x 5,56,66,086)            -----------------------
            15. The employer resisted the said claim contending that
       having regard to the relevant conditions in the work order and
                                                                          H
    50       SUPREME COURT REPORTS                 [2009] 10 S.C.R.


A   the contract agreement, the mobilization advance had to be              ;.

    released in three instalments against Bank Guarantees; that the
    second and third instalments had to be released only on
    production of the certificate of a chartered accountant on the
    utilization of the previously paid amount and on verification of
8   the department of the progress; and that the mobilization
    advance was released in instalments in terms of contract and
    there was no delay no breach on their part.

          16. We may refer to the relevant provisions of the contract
    in this behalf. Clause 8 of the Special Conditions relating to
c   establishment of factory at site provided thus :

         "Establishment of factory at site :

         The contractor, if he so desires, may establish the pipe
D        factory at site to avoid transportation of pipes. All material   .;,
         and equipment and land required for the purpose shall be
         arranged by the contractor at his own cost. The department
         may assist him in acquisition of land. However, the work
         should not be delayed on this account. The firm should
         commence and continue to supply the pipes etc. from their
E
         existing set up till the factory at site is established. As
         already stated, the supply of pipes etc. should commence
         within 30 days, from the award of contract."

    The above clause was superseded by clause 3 of the Common
F   Terms of Reference which is extracted below :

         "Mobilisation advance (for PSC Pipes only)

         10% of the contract value shall be given against Bank
         Guarantee as mobilization advance at a simple interest
G        rate of 18%. Recovery of mobilization advance shall be
         effecied from 1st Running Bill on pro-rata basis in a way
         that complete mobilization advance is recovered by the
         time 75% work is complete. Interest shall also be
         recovered alongwith recovery of capital mobilization
H
                    STATE OF RAJASTHAN v. FERRO CONCRETE        51
                   CONSTRUCTION PVT. LTD. [R.V. RAVEENDRAN, J.]
                       advance. The assets built by the contractor out of A
                       mobilization advance so made will be mc,rtgaged to the
                       department. In case work is left in-complete, liquidated
                       damages will be imposed as per terms of the document
                       and the assets built by the contractor for manufacturing
                       pipe will become the property of the department. Such B
                       assets can be used by the department for the purpose of
                       completing the remaining work."

                  In the subsequent work order issued on 23.8.1988, clause 5.1
                  relates to mobilization advance. While para (a) of clause 5.1
                  was a reproduction of clause (3) of the Common Terms of C
                  Reference, the following was added as para (b) in clause 5.1
                  of the work order :

                       'The mobilization advance is being given for establishment
                       of factory at site. In case the factory is not established in D
                       3 months period the mobilization advance shall be
                       recovered by way of the Bank Guarantee given in lieu of
                       the mobilization advance."

                  By letter of amendment dated 8.11.1988 issued by the
                                                                                    E
                  employer, several clauses of the work order including clause
                  5.1 (b) were amended/replaced. Para 5.1 (b) as replaced is
'"('
                  extracted below :
         ~
                 ~ "The mobilization advance is being given for establishment
                 0J  of factory at site. The mobilization advance shall be paid F
                     in three instalments of which the second and third ·
                 (J" instalment shall be paid on production of the certificate of
                     the Chartered Accountant about utilization of the previously
                 c'l paid amount and on verification by the department of the
                 ~   progress towards setting up of the factory."                 G
             j
......           This was followed by an agreement executed by both parties
 •
                 on 11.1.1989 and clause (7) thereof extracted below dealt with
                 mobilization advance :
                                                                                    H
    52        SUPREME COURT REPORTS                [2009] 10 S.C.R.


A        "Mobilisation advance:

         10% of the contract value shall be given as mobilization
         advance@ 18% simple ir.'erest subject to production of
         Bank Guarantee from any of the Nationalised Bank equal
         to the amount of such advance. The recovery of such
B
         advance shall be effected from 1st running bill on prorate
         basis in such a way that recovery of this advance is made
         by the time when 75% of the work is completed. Amount
         of interest is recoverable along with the recovery of
         principal amount.
c
         (b) The assets built by the contractor out of the mobilization
         advance shall be mortgaged with the Government. Such
         assets will not be mortgaged with any other agency for any
         purposes.
D
         (c) In case contractor fails to complete the work in specified
         time, the contractor shall pay the compensation as
         liquidated damages as per the terms and conditions of the
         contract and the assets built by the contractor for
         manufacturing of pipes will be the property of the
E
         government and the department will have right to use it as
         government property for completion of remaining work. x
         xx xx
         17. The arbitrator held that clause 8 of the special
F tonditions of contract stood superseded by clause 3 of the
  Common Terms of Reference which required the mobilization
  advance to be released in one instalment and not in three
  instalments. He held that clause 5(1 )(b) inserted by the
  amendment to the work order dated 8.11.1988 was an
G unilateral incorporation by the employer and was not binding
  on the contractor. He further held that the employer ought to
  have released the mobilization advance along with the work
  order dated 23.8.1988, and the employer had abnormally
  delayed the release of mobilization advance by a total period
H of 8.5 months by releasing it in instalments. He held that there
  STATE OF RAJASTHAN v. FERRO CONCRETE          53
 CONSTRUCTION PVT. LTD. [R.V. RAVEENORAN, J.] ·

was a clear delay of about 8 months and during that period the A
contractor could have executed one third of the work of the·
value of Rs.330,64,867.50, and as the contractor was prevented
from executing the said work on account of the delay, the
contractor was entitled to 10% of the said amount, that is
Rs.33,06,500/- as loss of profit. The said sum was therefore B
awarded to the contractor under claim (1).

      18. There is no doubt that clause 8 of the special
 conditions of contract has to be read with clause 3 of the CTR.
It is true that Clause 3 of CTR did not contemplate the               C
 mobilization advance being released in three instalments. But
the CTR was followed by work order dated 23.8.1988 which
was followed by amendment dated 8.11.1988 which specifically
stated that the mobilization advance shall be paid in three
instalments of which the second and third instalments shall be
paid on production of a certificate of the Chartered Accountant       D
about u!Hization of the previously paid amounts and on
verification by the department towards progress of the factory.
The arbitrator has held that the said clause was unilaterally
introduced and therefore is not binding by the contractor. On
the face of it this is erroneous. After the work order, the parties   E
have executed a bilateral agreement dated 11.1.1989 which
specifically states at para 2 and para 6 that the work order
dated 23.8.1988 and subsequent amendment to the work order
dated 8.11.1988 shall be deemed to be a part of the contract
and will bind both the parties. The agreement dated 11.1.1989         F
itself contains a detailed clause (clause 7) relating to
mobilization advance in addition to what was earlier agreed in
regard to mobilization advance. Therefore obviously the
clauses relating to mobilization advance in the amendment to
work order dated 8.11.1988 and the agreement dated                    G _
11.1.1989 had to be read in addition to the earlier provision
relating to mobilization advance contained in the CTR. Clause
5(1 )(b) of the work order, as amended, specifically provided
that the contractor had to provide a Bank guarantee for the
mobilization advance. Sub-clause (b) of clause 7 of the               H
    54        SUPREME COURT REPORTS                 [2009) 10 S.C.R.


A agreement dated 11.1.1989 provided that assets built by the
  contractor by utilizing the mobilization advance should be
  mortgaged to the employer. Sub-clause (c) of clause 7 provided
  that if the contractor fails to comp!1..te the work, th.e assets built
  by the contractor would become the property of the employer
B and the department could use it as government property for
  completion of the remaining work. Sub-clause (d) of clause 7
  provided that if the contractor failed to establish the factory within
  thr~e months of payment the mobilization advance, the said
  advance would be recovered by enforcing the bank guarantee
c given in lieu of the mobilization advance. Thus it is evident that
  the mobilization advance had to be released only against a bank
  guarantee to be furnished by the contractor.

         19. If according to the contractor, the mobilization advance
    had to be released in a single instalment and if the contractor
D wanted the entire mobilization money to be released in one
    lump sum instead of in three instalments, it ought to have given
    a single bank guarantee for the entire sum. But strangely the
  · contractor did not give such a bank guarantee. It gave four bank
    guarantees for Rs.40 lacs on 21.5.1989, Rs.25 lacs on
E 1.2.1989, Rs.15 lacs on 17.2.1989 and Rs.25 lacs on
    23.3.1989. It is thus evident that the contractor had also
    pnbceeded on the basis that the condition in clause 5(1 )(b) of
   the work order amendment letter dated 8.11.1988 governed the
    payment of mobilization advance. We find that the mobilization
F amount corresponding to first bank guarantee was released
   within two days; mobilization amount corresponding to second
   guarantee was released in seven days; and mobilization
   amount corresponding to third guarantee, was partly released
   in 12 days and the balance in two months. The amount
G corresponding to the second and third bank guarantees had
   to be released only after the contractor produced a certificate
   in regard to the utilization of the earlier advance. It is seen that
   in regard to the first mobilization advance the certificate was
   produced on 7.2.1989 and on the same day the second
H instalment was released. Insofar as third instalment, the
                       STATE OF RAJASTHAN v. FERRO CONCRETE                        55
                      CONSTRUCTION PVT. LTD. [R.V. RAVEENDRAN, J.]
ii
                     certificate was only received on 4.4.1989. Therefore it cannot       A
'          ...
     ..              be said that there was delay or breach on the part of the
                     employer in releasing the mobilization advance. If at a'! there
                     was any delay, the delay was on the part of the contractor. The
                     fact that release of mobilization advance was governed by
                     clause 5(1 )(b) of the work order (as amended on 8.11.1988)          B
                     and clause 7 of the agreement dated 11.1.1989 was totally
                     overlooked by the arbitrator by proceeding on the basis that
                     mobilization advance was governed by the CTR alone. The
                     Arbitrator committed a legal misconduct by ignoring the terms
                     of contract: that is the agreement dated 11.1.1989,which             c
                     specifically provided that in addition to the CTR, the work order
                     and amendment to work order dated 8.11.1988 would also form
      ,,             part of the contract. The Arbitrator also overlooked the fact that
                     additional provision regarding mobilization advance was
                     introduced in the agreement itself. Therefore the mobilisation
                                                                                          D
                     advance was governed by the terms in the CTR, the work order,
                     the amendment to the work ore.er dated 8.11.1988 and
                     agreement dated 11 .1.1989 read together. If so read, it was
                     clear that there was no breach on the part of the employer and
                     the contractor was itself responsible for the delay. If so, the
                     question of compensating the contractor on that score does not       E
                     arise.

                          20. There is yet another aspect. The contractor claimed
                     compensation on the basis that he could not do work of the
                     value of Rs.5,56,66,086/- in view of the delay and he was entitled F
                     to 15% thereof namely Rs.83,49,91~/- as compensation. But
                     the arbitrator made an award in respect of the claim on the
                     ground that there was delay in releasing the mobilization
                     advance and during that period of delay, one third of the contract
                     work could have been done and the value of the work that could G
                     have been done was Rs.3,30,64,867, and 10% thereof was the
                 j
     <Y              loss of profit. Firstly, there was no such plea. Secondly, we have
                     already held that the delay relating to mobilisation advance,
                     was not on the part of the employer. Thirdly, even if there was
                     delay, it was nobody's case that no work was done or that the H
    56        SUPREME COURT REPORTS               [2009110 S.C.R.

                                                                                      ,_
A   contractor had suffered loss for non-execution of the work during
                                                                            •         '
    the contract period. Therefore we are of the view that the award
                                                                                ,.
    of GOmpensation of Rs.33,03,500/- towards claim no.(1) is
    liable to be set aside.

    Re : Claim 37A:
B
        21. Claim No.37Awas linked to mobilization advance. The
   contractor claimed that it had mortgaged its pipe manufacturing
   unit in favour of the employer by deposit of title deeds, as
   security for repayment of the mobilization advance; that the
c machinery installed in the said factory had not been released
   by the employer in its favour and as a consequence, it could
   not be shifted to another place to enable it to start the
   mcinufacturing process elsewhere; and that on account of the
  failure on the part of the employer to release the plant, it had
D to keep the machinery idle and the employer was therefore
  liable to reimburse to the contractor the loss of production from
   13~1.1992 at the rate of Rs.12,072/- per day. The contractor
  contended that if it had been permitted to shift its plant and
  m~chinery, it would have produced 15 pipes per day valued at
E Rs.1,20,000/-, that out of which the overhead and profit element
  was 15% (that is Rs.18,000/- per day); that as there were 306
  working days in a year, the loss of profits/overheads would be
                      =
  18,000 x 306/365 Rs.15,090/- per day; and that if 20% thereof
  (Rs.3,018/-) was deducted therefrom towards labour
  component, the loss of profit per day on account of non-
F
  availability of plant and machinery was Rs.12,072 per day. The
  employer resisted the claim by contending that there was no
  obligation to release the plant and its title deeds until the
  mobilization advance was repaid with interest; that the
  contractor had not repaid the mobilization advance and interest
G
  thereon in spite of the award; and therefore the question of
  compensating any 'daily loss' on that account did not arise. The      l       ...
  employer also contested the correctness of the assumptions
  made for calculating the loss.

H        22. The contractor deposited the title deeds relating to the
       STATE OF RAJASTHAN v. FERRO CONCRETE                      57
      CONSTRUCTION PVT. LTD. [R.V. RAVEENDRAN, J.]

.;
     plant by way of mortgage of deposit of title deeds, in terms of A
     the contract and specifically agreed that the original deeds will
     remain in deposit with the employer till the entire m· 1bilization
     advance was repaid with interest. It is also not in dispute that
     though a mortgage security was created on the plant, it
     continued to be in the possession, enjoyment and control of the B
     contractor, as the employer did not take over physical
     possession of the plant at any point of time.

          23. The arbitrator considered Claim 37A with three other
     claims - (36, 36A and 37). The particulars of the said claims C
     are:
     Claim 36
     Compensation for idling machinery, labour,
     staff due to delay and wrong decisions
     (for the period up to 12.1.1992)                Rs.48.21 lacs    D

     Claim 36 A
     Comp~nsation for idling machinery, staff &
     Labour etc. from 13.1.1992                   Rs.6370 per day
                                                                      E
     Claim 37
     Compensation for loss of production in the
     Factory (for the period upto 12.1.1992)         Rs.61.48 lacs

     Claim 37A
     Compensation for loss of production in the                       F
     Factory from 13.1.1992                   Rs.12,072 per day

     The arbitrator held that none of the four claims was maintainable
     as the factory built out of mobilization advance had been
     mortgaged in favour of the employer. As a consequence he did G
     not award any amount in respect of the four claims. But strangely
     he directed payment of Rs.12,072 per day from the date of
     award not because he held that there was any loss of
     production as a consequence of any breach by the employer,
                                                                       H
    58        SUPREME COURT REPORTS                [2009] 10 S.C.R.


A   but on the following reasoning:

         "After perusal of the arguments of the parties and the
         evidence on record, I come to the finding that it is a case
         of real hardship to the claimants for having been denied
         the use of the factory and machinery elsewhere in their
B
         business venture, but because of legalities involved, such
         as mortgage, the claimants cannot be given the benefit of
         any award. Had the assets of factory built out of
         mobilization advance not being mortgaged in favour of the
         respondent I would have considered making an award in
c        favour of the claimants. In view of the fact that I have
         allowed counter claim No.3 of the respondent for balance
         amount of mobilization advance in full along with interest,
         there is no reason why the assets built out of mobilization
         advance should continue to remain mortgaged with the
D        respondents. I therefore direct the respondent to release
         the documents relating to mortg~ ge as mentioned above
         within a period of 30 days from the date of this award failing
         which the claimants shall be entitled to an award of
         Rs.12,072 per day from the date of this award till the date
E        of release of mortgage. No award in favour of the
         claimants for the period I entered upon, reference to the
         date of the publication of the award."

                                                 [emphasis supplied]
F       24. Thus we find that the award under claims 37A was not
  made on account of any finding of breach on the part of the
  employer. It was made because the Arbitrator had made an
  award against the contractor in favour of the employer for
  Rs.59,42,275 with interest. The Arbitrator was of the view that
G if that sum was adjusted against the amounts due by the
  employer, there was no need for the mortgage of the plant to
  continue and therefore the employer should release the
  documents of title deposited by way of equitable mortgage,
  within 30 days from the date of award; and that if the employer
H failed to do so, the employer should pay to the contractor
                        STATE OF RAJASTHAN v. FERRO CONCRETE                       59
                       CONSTRUCTION PVT. LTD. [R.V. RAVEENDRAN, J.]
                       Rs.12,072 per day from the date of the award till the date of A
                       release of the mortgage. Therefore, the said award under claim
                       37A was made, not on account of any breach committed by
                       the employer, but in respect a breach if made in future after the
                       date of the award. There was no such claim and the award was
                       therefore beyond the reference. Further, the reasoning is very B
                       strange and is a classic case of an error apparent on the face
                       of the award and a legal misconduct. The arbitrator rejected
       ..[
                       the claim No.37A for payment of Rs.12,072/- as compensation
                       for loss of production from 13.1.1992 (which was the subject
                       matter of claim) on the ground that the plant had been           c
                       mortgaged in favour of the employer and therefore there was
                       no justification for the contractor to claim that it should be
·-                     permitted to remove and take away the plant when the mortgage
                      subsisted. Having rejected the claim, the Arbitrator evolved a
                      strange reasoning that though there was a subsisting valid
        -I                                                                               D
                      mortgage in respect of the mobilization advance with interest


-                     in favour of the employer, because he had made an award in
                      favour of the employer for Rs.59,42,275 plus interest, the
                      mortgage came to an end and the employer became liable to
                      return the documents and if it failed to return the documents,
                      the contractor was entitled to damages of Rs.12,072/- per day E
                      from the date of award.

         .1                 25. The arbitrator noticed the fact that the plant and
'·                     machinery was mortgaged by deposit of title deeds in favour
                  1



                       of the employer and that the contract was that "the original F
                      documents will remain in deposit with the employer till the
                      amount of advance is repaid with full interest." The arbitrator in
                      fact makes an award for return of Rs.59,42,276 in favour of the
                      employer with interest at 18% per annum from 1.9.1990 to
                      17.9.1990 and interest at 18% per annum on Rs.59,42,275/- G
,..,         ;.       from 18.9.1990 till date of decree or payment, whichever was
                      earlier. Therefore evidently until the amount of Rs.59,42,275/-
                      with interest was paid by the contractor to the employer, the
                      mortgage would continue. If the mortgage continued, there was
                      no obligation on the part of the employer to return the
                                                                                        H
    60       SUPREME COURT REPORTS              [2009] 10 S.C.R.


A   documents; and if there was no obligation on the part of the
    employer to teturn the documents, the contractor could not
    complain that the documents were wrongly held by the employer
    nor could it claim loss of production as a result of employer
    wrongly withholding the documents.
B
       26. It is of some interest to note that as per the award of
  the arbitrator, made under claim 37A, on a claim that was never
  made, the amount that would become due at Rs.12,072/- from
  21.9.1994 to date will be approximately Rs.6,42,70,000/-. We
  have a strange situation where the arbitrator makes an award
C in favour of an employer directing the contractor to refund the
  employer Rs.59,42,275/- with interest at 18% per annum from
  18.9.1990 upto date of decree/payment and then even though
  the said payment was not made, awards damages to the
  contractor which works out to Rs.6,42,70,000/- to the contractor.
D This to say the least is legal misconduct and an error apparent
  on the face of the award.

       27. We may also refer to another aspect. A sum of
                                                                      -
  Rs.12,072/- per day was claimed as damages by the contractor
E in a two line calculation without any supporting evidence or
  document. As noticed above, the claim was on the basis that
  the contractor would have manufactured 15 pipes per day of
  the value of Rs.1,20,000/- and that the profit and overhead
  element out of it would have been 15% or Rs.18,000/- per day.
F By taking the working days as 306 in a year and deducting 20%
  of labour component, the loss of profit per day was calculated
  to be Rs.12,072/- per day. There is no evidence to show that
  the contractor was at any point of time manufacturing 15 pipes
  a day of the value of Rs.8000/- each or that he would have made
G a profit of 15% on the cost thereof. The claim is made on the
  ground that it is disabled from manufacturing that many number
  of pipes elsewhere. There is no evidence that it had other
  contracts where it was required to manufacture that number of
  pipes or that it could not manufacture the required pipes for
  want of plant and machinery. Nor is there any evidence as to
H
            STATE OF RAJASTHAN v. FERRO CONCRETE                        61
           CONSTRUCTION PVT. LTD. [R.V. RAVEENDRAN, J.]

•          th~ value of the plant and machinery that had been mortgaged A
           toithe employer and what would-be the cost of an alternative
              ' with a capacity to manufacture 15 pipes per day. If the
           plant
           plant and machinery was of the value of say Rs.25 lakhs, or if
           the contractor could install another similar plant at a cost of
           Rs.25 lakhs, then the loss at best would be interest on Rs.25 B
           lakhs and not anything more. In fact even though there is no
           evidence, while making claim nos.36 and 37 the contractor has
•          given value of the plant and machinery as Rs.36,84, 161/-. Even
           assuming the said figure. to be true, at best the blocked up
           investment was only Rs. 36,84,161/- and the loss would be c
           around 1% thereon per month by way of interest which would
           be Rs.36,841/- per month. What is more strange is nowhere
           in the award the arbitrator considers the validity of the claim of
           Rs.12072 per day nor accepts the said claim as valid or
         . correct. In a reasoned award if the claim of a contractor is
                                                                               D
           equated to proof of the claim, then it is obviously a legal
           misconduct and an error apparent on the face of the award.
          While the quantum of evidence required to accept a claim, may
           be a matter within the exclusive jurisdiction of the arbitrator to
          decide, if there was no evidence at all and if the arbitrator
                                                                               E
           makes an award of the amount claimed in the claim statement,
           merely on the basis of the claim statement without anything
           more, it has to be held that the award on that account would
l         be invalid. Suffice it to say that the entire award under this head
          is wholly illegal and beyond the jurisdiction of the arbitrator, and
          wholly unsustainable.                                                F

              28. Learned counsel for the contractor submitted that
         though there was an award in favour of the employer for refund
         of mobilization advance of Rs.59,42,275/- with interest, there
         was a larger award in its favour aggregating to about Rs.1.67 G
    j.   crores and interest and it was legitimately entitled to adjust the·
         sum of Rs.59,42,275/- with interest towards the amount due by:
         the employer under the award namely Rs.1.67 crcires with
         interest and therefore as on the date of the award the liability
         towards mobilization advance stood wiped out on account of H
     62        SUPREME COURT REPORTS               (2009] 10 S.C.R.


 A  the same being adjusted towards the amount claimed by him
    and therefore as on the date of the award, the liability to refund              _,.
    the mobilization advance ceased. This contention is not sound.
    The mobilization advance amount was an ascertained sum due
   to the employer from the contractor, with a specific provision
 B for  interest. There was a specific contract for continuation of
   the mortgage until the said amount was paid. On the other hand
   the amounts that allegedly became due to the contractor under
   the award were mostly towards damages and escalation in
   prices validity of which were under challenge and there was
 c no provision in the contract for payment of interest thereon. As
   noticed above at best the arbitrator could have directed return
   of the documents of title to the contractor and could not have
   directed payment of damages at the rate of Rs. 12072/- per
   day.
 0         29. We therefore hold that viewed from any angle,
     awarding Rs.12,072/- per day as damages, from the date of
     award under Claim 37A cannot be sustained and the same is
     liable to be set aside.

E    Re : Claim Nos. 12 and 13 :

        30. The contractor claimed pre-reference interest at 18%
  per annum on all its claims from the date of claim to date of
  arbitrator entering upon the reference (18.6.1990 to
  15.12.1991), as also pendente lite interest from 16.12.1991
F tp 21.9.1994 and future interest from the date of award till date
  of payment or decree whichever was earlier. The Arbitrator
  awarded the following interest : ia) pre-reference interest on
  all sums awarded except claim no.(1), from 3.9.1990 (date of
  contractor's application under section 8 and 20 of the Act) to
G 15.12.1991at18% per annum; (b) pendente lite interest on
                                                                         ..I
  all sums awarded including claim No. 1, from 16, 12.1991 to                  ,,;...._

  21.9.1994 at 18% per annum; and (c) future interest on all sums
  awarded from 22. 9.1994 till date of decree or payment
  whichever is earlier at the rate of 18% per annum. The District
H Court did not award any post decretal interest, but the High
        STATE OF RAJASTHAN v. FERRO CONCRETE                       63
       CONSTRUCTION PVT. LTD. [R.V. RAVEENDRAN, J.]
      Court, however, granted interest from the date of decree till date A
      of payment at 18% per annum.

           31. The appellants contend that there was no provision in
      the contract for payment of interest on any of the amounts
      payable to the contractor and therefore no interest ought to be B
      awarded. But this Court has held that in the absence of an
      express bar, the arbitrator has the jurisdiction and authority to
      award interest fair all the three periods - pre reference,
      pendente lite and future (vide decisions of Constitution Bench
      in Secretary, Irrigation Department, Government of Orissa vs.
      G. C. Roy - 1992 (1) SCC 508, Executive Engineer, C
      Dhenkanal Minor Irrigation Division vs. N. C. Budharaj -
      2001 (2) SCC 721 and the subsequent decision in Bhagawati
      Oxygen vs. Hindustan Copper Ltd - 2005 (6) SCC 462). In this
      case as there was no express bar in the contract in regard to.
      interest, the Arbitrator could award interest.                 ""'Q"~
             32. The appellant next contended that in regard to claims
      in the nature of damages, as contrasted from ascertained sums
      due, interest becomes payable only on quantification and
      therefore award of interest prior to the date of arbitrator's award E
      was illegal. It is no doubt true that the position of law earlier was
      that in regard to award of damages, interest was not payable·
      before quantification by a court. This was on the assumption
      that in so far as damages are concerned, there is no liability
      till determination of the quantum of damages. We may refer to F
      a decision of the Bombay High Court in Iron & Hardware
      (India) Co. v. Firm Sham/a/if& Bros [AIR 1954 Bombay 423],
      where Chagla CJ, speaking for the Bench, stated the principle
      thus:

           "In my opinion it would not be true to say that a person who G
..l        commits a breach of the contract incurs any pecuniary
           liability, nor would it be true to say that the other party to
           the contract who complains of the breach has any amount
           due to him from the other party ...... As already stated the
                                                                          H
    64          SUPREME COURT REPORTS                [2009) 10 S.C.R.

A        only right which he has is the right to go to a Court of law
         and recover damages. Now, damages are the
         compensation which a Court of law gives to a party for the
         injury which he has sustained. But, and this is most
         important to note, he does not get damages or
B        compensation by reason of any existing obligation on the
         part of the person who has committed the breach. He gets
         compensation as a result of the fiat of the Court. Therefore,
         no pecuniary liability arises till the Court has determined
         that the party complaining of the breach is entitled to
c        damages. Therefore, when damages are assessed, it
         would not be true to say that what the Court is doing is
         ascertaining a pecuniary liability which already existed.
         The Court in the first place must decide that the defendant
         is liable and then it proceeds to assess what that liability
         is. But till that determination there is no liability at all upon
D
         the defendant."

         33. The legal position, ho,.ever, underwent a change after
  the enactment of Interest Act, 1978. Sub-section (1) of section
  3 of the said Act provided that a court (as also an arbitrator)
E can in any proceedings for recovery of any debt or damages,
  if it thinks fit, allow interest to the person entitled to the debt or
  damages at a rate not exceeding the current rate of interest,
  for the whole or part of the following period, that is to say, -

F         (a)    if the proceedings relate to a debt payable by virtue
                 of a written instrument at a certain time, then, from
                 the date when the debt is payable to the date of
                 institution of the proceedings;

          (b)    if the proceedings do not relate to any such debt,
G                then, from the date mentioned i~ this regard in a
                 written notice given by the pers9n entitled or the
                 person making the claim to the person liable that
                 interest will be claimed, to the date of institution of
                 the proceedings.
H
  STATE OF RAJASTHAN v. FERRO CONCRETE                           65
 CONSTRUCTION PVT. LTD. [R.V. RAVEENDRAN, J.]
Sub-section (3) of section 3 made it clear that nothing in that         A
section shall apply to any debt or damages upon which interest
is payable as of right, by virtue of any agreement; or to any debt
or damages upon which payment of interest is barred, by virtue
of an express agreement. The said sub-section also made it
clear that nothing in that section shall empower the court to           B
award interest upon interest. Section 5 of the said Act provides
that nothing in the said Act shall affect the provisions of section
34 of Code of Civil .Procedure 1908.

     34. The position regarding award of interest after the             C
Interest Act, 1978 came into force, can be stated thus :

      (a)     where a provision has been made in any contract,
              for interest on any debt or damages, interest shall
              be paid in accordance with the such contract.
                                                                        D
      (b)     where payment of interest on any debt or damages
              is expressly barred by the contract, no interest shall
              be awarded.
      (c)      where there is no express bar in the contract and
            ·· where there is also no provision for payment of          E
               interest then the principles of section 3 of Interest
               Act will apply in regard to the pre-suit or pre-
               reference period and consequently interest will be
               payable:
                                                                        F
               (i)    where the proceedings relate to a debt
                      (ascertained sum) payable by virtue of a
                      written instrument at a certain time, then from
                      the date when the debt is payable to the date
                      of institution of the proceedings;                G

               (ii)   where the proceedings is for recovery of
                      damages or for recovery of a debt which is
                      not payable at a certain time, then from the
                      date mentioned in a written notice given by
                                                                        H
    66          SUPREME COURT REPORTS              [2009] 10 S.C.R.

A                      the person making a claim to the person
                       liable for the claim that interest will be
                       claimed, to date of institution of proceedings.

          (d)    payment of interest pendente lite (date of institution
                 of proceedings to date of decree) and future
B
                 interest (from the date of decree to date of payment)
                 shall not be governed by the provisions of Interest
                 Act, 1978 but by the provisions of section 34 of
                 Code of Civil Procedure 1908 or the provisions of
                 the law governing Arbitration as the case may be.
c
       35. Therefore, even in regard to claims for damages,
  interest can be awarded for a prior to the date of ascertainment
  or quantification thereof if (a) the contract specifically provides
  for such payment from the date provided in the contract; or (b)
O a written demand had been made for payment of interest on
  the amount claimed as damages before initiation of action, from
  the date mentioned in the notice of demand (that is from the
  date of demand or any future date mentioned therein). In regard
  to claims for ascertained sums due, interest will be due from
E the date when they became due. In this case, interest has been
  awarded only from 3.9.1990, the date of the petition under
  Section 20 of the Act for appointment of arbitrator. We find no
  reason to alter the date of commencement of interest.

       36. In regard to th' rate of interest, we are of the view that
F the award of interest at 18% per annum, in an award governed
  by the old Act (Arbitration Act, 1940), was an error apparenf
  on the face of the award. In regard to award of interest governed
  by the Interest Act, 1978, the rate of interest could not exceed
  the current rate of interest which means the highest of the
G maximum rates at which interest may be paid on different
  classes of deposits by different classes of scheduled banks in
  accordance with the directions given or issued to banking
  companies generally by the Reserve Bank of India. under' the
  Banking Regulation Act. Therefore, we are of the view that pre-
H
                STATE OF RAJASTHAN v. FERRO CONCRETE                             61'
               CONSTRUCTION PVT. LTD. [R.V. RAVEENDRAN, J.]
               reference interest should be only at the rate of 9% per annum.          A
     ";
               It is appropriate to award the same rate of interest even by way
               of pendente lite interest and future interest upto date of
               payment.

               Re: Claims 2 and 16 1 3 and 151 5 and 18 1 6 and 17 1 9 and
                                                                                       B
               19 1 11 and 20 1 24 1 27 1 and 28 1 29 1 30 1 31 1 32 1 33 1 35 {with
               25 and 34) of the contractor.

                     37. Claims 9 & 19, 27 & 28, 29, 33, 35 (with 25 & 35) are
               for payment for work aone by the contractor. Claims 2 & 16, 3
               & 15, 5 & 18/24, 30, 31 and 32 are for release/refund of                c
               amounts withheld or excess deductions. Claims 6 & 17are for
               escalation in prices. Claims 11 & 20 are for compensation for
               slow progress due to reduction of width of trench. The arbitrator
               has awarded certain amounts against these claims by
               examining the material placed before him and the terms of               D
               contract. He has also assigned reasons for awarding the
               amount against these claims. Courts can .not sit in judgment
               over the award of the arbitrator, nor re-appreciate the evidence.
               The awards on these claims do not suffer from any infirmity
               which can be the basis for interference either under Section 30         E
..             or under Section 16 of the Arbitration Act, 1940. Neither want
               of jurisdiction, nor legal misconduct, nor any inconsistency nor
               error apparent on the face of the award are made out in regard
               to awards made in regard to these claims. The awards in
               regard to these claims are therefore upheld.                            F
               Re: Claims 41 71 81 101 & 21 1 141 22 1 23 1 26 1 38 1 39 1 40 1 41 &
               41A 1 42 & 42A 1 43 of the contractor

                   38. These claims of the contractor have been examined
               and rejected by the Arbitrator and upheld by the courts below.          G
               No ground is made out to interfere with the same.
          >-
               Re: Counter claims of the em~lo)ler

                    39. Out of the five counter-claims of the employer, the
                                                                                       H
     68         SUPREME COURT REPORTS             [2009] 10 S.C.R. .


A   Arbitrator has allowed only counter-claim no.(3). Counter-claim
    no. (3) was for refund of mobilization advance (Rs.79,87,846)
    with interest and the Arbitrator has awarded Rs.59,42,275/- with
    interest at the contract rate of 18% per annum up to the date
    of decree/payment whichever was earlier. Counter-claims 1, 2,
s   4 and 5 made by the appellant against the contractor have
    been rejected. They are:
    Counter Brief description of counter                 Amount of
    claim No. claim                           .       counter claim

c    1           Liquidated damages                 Rs.99, 19,460/-

     2           Extra cost in getting work       Rs.6,66,62,000/-
                 completed through another
                 agency
D    4.         Interest on payments made to      Rs.2, 17,42, 168/-
                the contractor and not utilized
                          .
     5.         Costs                                Rs.2,50,000/-

E Counter-claims 1, 2, & 4 have been considered by the arbitrator
   and rejected by the arbitrator on the ground that the delays/       ,
   breaches were on the part of the appellant and therefore, the
   question of claiming these amounts does not arise. Rejection
   of counter-claim (5) is consequential. As noticed above, the
F court does not sit in appeal over the award of the arbitrator and
   cannot re-appreciate the evidence to arrive at a different
   conclusion. The award on these items do not attract any of the
 · grounds on which award could be set aside. Therefore,
   rejection of these claims is also not open to interference.

G       40. We therefore allow these appeals in part and modify
    the judgments of the courts below as indicated above.
    Resultantly:

          (A)   The award of Arbitrator on claim no.(1)
H               (Rs.33,06,500/-) and claim 37A (Rs.12,072/- per
            STATE OF RAJASTHAN v. FERRO CONCRETE                         69
           CONSTRUCTION PVT. LTD. [R.V. RAVEENDRAN, J.]

                       day from 21.9.1994 till date of payment) are set        A
                       aside.

                 (B)   The award of Arbitrator on claims 2 and 16, 3 and
                       15, 5 and 18, 6 and 17, 9 and 19, 11 and 20, 24,
                       27 and 28, 29, 30, 31, 32, 33, 35 (with 25 & 24)
                                                                               B
                       aggregating to Rs.1,34,24,407/- is upheld.

                 (C)   Interest shall be payable at 9% p.a. on
·-                     Rs.1,34,24,407/- from 3.9.1990 till date of payment.
                       The award on claims 12 & 13 is modified
                       accordingly.                                            c
                 (D)   Award of Rs.59,42,275/- in respect of counter-claim
                       no.(3) of appellant with interest at the rate of 18%
                       per annum from the respective dates of release upto
                       the date of payment is upheld.                          D
                 (E)   The direction for adjustment of the amount due
                       under counter-claim no.(3) calculated as on
                       21.9.1994, against the amounts found due to the
                       contractor calculated as on 21.9.1994 is upheld.
                       Consequently, the appellant shall release the title     E
                       deeds deposited in regard to the planUmachinery
                       of the contractor. The contractor will be entitled to
                       remove the plant, if it is not already done.

                 (F)   Rejection of claims 4, 7, 8, 10 & 21, 14, 22, 23, 26,   F
                       38, 39, 40, 41 & 41A, 42 & 42A and 43 of the
                       contractor and counter-claims 1, 2, 4, and 5 of the
                       employer are upheld.

                 ~G)   Parties to bear their respective costs.
                                                                               G
     >-   R.P.                                    Appeals partly allowed.


Search Indian case law

Ask in plain English, not just keywords. 25,000 AI words free, no card.

Try "Arbitration"Sign in to search

For a digitally signed copy suitable for filing, refer to the court's own website. Only the court can issue one.