Created byFuzzy Cloud

Supreme Court of India

VISAKHAPATNAM PORT TRUSTversusM/S CONTINENTAL CONSTRUCTION COMPANY

Citation
2009 INSC 230
Decided
20 February 2009
Disposal
Disposed off

Holding

The amendment to Section 17 is inapplicable to the 1985 award, courts cannot assess the reasonableness of arbitrators’ reasons, the Rs 74,810.38 claim is time‑barred and dismissed, and the Rs 6,44,500 claim is within limitation and upheld.

Summary

The Supreme Court examined two appeals arising from a High Court judgment involving Visakhapatnam Port Trust (VPT) and M/s Continental Construction Company. The first appeal concerned a claim of Rs 74,810.38 for recovered jack‑rods, which the Court held was time‑barred under Section 37 of the Arbitration Act, 1940 and Article 137 of the Limitation Act, 1963, and therefore dismissed. The second appeal dealt with a claim of Rs 6,44,500 for a survey boat, where the Court found the arbitration had commenced within the limitation period, so the claim was upheld. The Court also ruled that the 1990 amendment to Section 17 of the Arbitration Act (requiring reasons for awards) did not apply to an award dated 20 Nov 1985, and that courts cannot scrutinise the reasonableness of the arbitrators’ reasons. Consequently, the first High Court judgment was set aside and the second affirmed.

Issues considered

  • Whether the 1990 amendment to Section 17 of the Arbitration Act, 1940 requiring reasons for awards applies to an award dated 20 November 1985.
  • Whether a court may examine the reasonableness of the reasons given by arbitrators.
  • Whether the claim of Rs 74,810.38 is barred by limitation under Section 37 of the Arbitration Act, 1940 and Article 137 of the Limitation Act, 1963.
  • Whether the claim of Rs 6,44,500 is time‑barred.
  • When an arbitration is deemed to have commenced for the purpose of limitation under Section 37(3) of the Arbitration Act, 1940.

Legislation cited

Subjects

ArbitrationArbitration awardSection 17Section 37LimitationTime-barred claimNon‑reasoned awardSupreme Court of IndiaVisakhapatnam Port TrustContinental Construction

Judgment

                                [2009) 2 S.C.R. 840


     A                 VISAKHAPATNAM PORT TRUST                              .......
                                         v
               MIS CONTINENTAL CONSTRUCTION COMPANY
                    Civil Appeal No 5849-5850 of 2002··-
                              FEBRUARY 20, 2009
     B
               (MARKANDEY KATJU AND R.M. LODHA,. JJ.)
               Arbitration Act, 1940 :
                                                                             ~
                Sections 17, 37 :-Arbitration Award- Reasons given by
     c    the 'Arbitrators subsequently - Held: Reasonableness of the
          reasons given i:JY arbitrators·cannot be gone into by the Court
          - Also, the amendment in s. 17 vide Andhra Pradesh Act not
          attracted since award was passed prior to the amendment -
          Limita_(ion Act, 1963, Section 137.
                                                                              ;k
     D         The two appeals arising from the common judgment
          of the High Court, ~elate to s.37 of the Arbitration Act, 1940
          and Article 137 of the Limitation Act, 1963 as also the
./
          amendment in s.17 of the Arbitration Act vide Andhra
          Pradesh Act 1 of 1990.
     E.
               Disposing of the appeals, the Court
               HELD: 1. Th.e amendment in Section 17 of the
                                                                              ---
                                                                            .............

                                                                             ~
         Arbitration Act, 1940 vide A.ndhra Pradesh Act (1 of 1990)
         is not attracted in the present fact situation as the award
     F was passed by the arbitrators o_n 20th November, 1985
         i.e. much before the amendment. As per Section 17 then
         obtaining, it \Xas not imperative for the arb.itrators to give
         reasons in support of the award. Secondly, upon the.
         award dated 20th November, 1985 being challenged by
     G   Visakhapatnam      Port Trust (VPT) before Principal Sub-
         ordinate Judge, Visakhapatnam, he has· directed the
                                                                            ,,.        1"

       · arbitrators to· give reasons for the award in the light of the
         amendment. [Para 25] [850-D]

     H                                   840




                       '
-1                          VISAKHAPATNAM PORT TRUST V. M/S                   841
                           CONTINENTAL CONSTRUCTION COMPANY
k-._'>\
                     2. Subsequently the arbitrators did give their reasons. A
                 Reasonableness of the reasons given by arbitrators cannot
                 be gone into by the Court. [Para 27] [851-B]
                      3.1 The judgment of the High Court of Judicature of
                 Andhra Pradesh in CMA No. 1559/1994 is set aside. The
                 claim of Mis Continental Construction Company for Rs. B
                 74,810.38 stands dismissed. The amount of Rs. 74,810.38
                 deposited with the executing Court by Visakhapatnam ·
            "-   Port Trust pursuant to the order dated 27th September,
                 2004 of this Court shall be refunded to them ~tongwith
                 interest accrued thereon. [Para 28] [851-D]              c
                     3.2 The judgment of the High Court in CMA No.77/
                 1995 is affirmed. The amount of Rs. 6,44,500/- deposited
                 by Visakhapatnam Port Trust with the executing Court .
     '   -..I,   pursuant to the order of this Court dated 27th September,
                 20~4 shall be paid to Mis Continental Construction D
                 Company alongwith interest accrued thereon. [Para 28]
                 [851-E]
                     · CIVILAPPELLATE JURISDICTION: Civil Appeal No 5849-
                 5850 of 2002
 ,.                                                                                  E
                      From the Judgement and Order dated 26.04.2002 of the
                 Hon'ble High Court of JudicatureAndhra Pradesh at Hyderabad
           ~     in CMA Nos. 1559 of 1994 & 77of1995.


•
 (

                      Kailash Vasdev, Gopal Singh, for the Appellants .
 I
                     S.S. Upadhyay, Santosh Mishra, Kumud Das, Rajesh R.             F
                 Dubey, Sharmila Upadhyay, for the Respondent.
                      The Judgement of the Court was delivered by
                      R.M. LODHA, J.
                      Both these appeals by ~ecial leave, arise out of one and G
             ~
                 the same judgment dated 26 April, 2002 rendered by the High
                 Court of JudicatureAndhra Pradesh whereby it allowed the two
                 appeals
                    .
                          being CMA No. 1559/1994- and CMA No. 77/1995.
                      2. For the sake of convenience, we shall refer the appellant
                                                                                     H
    842       SUPREME COURT REPORTS                   [2009) 2 S.C.R.               ,,.


A   - Visakhapatnam Port Trust, "VPT" and the respondent - M/s
    Continental Construction Company, "the Contractor".
          3. In CMA No. 1559/1994 before the High Court, the dispute
    between the parties was in respect of refund of an amount of
    Rs. 74,810.38 which was recovered by VPT from the contractor's
B   running-bill no. 21. VPT entered into an agreement with the
                    th
    contractor on 7 January, 1973 where under the contractor was
    to construct the ore berth 263 meters long 29. 73 meters wide
    comprising of eight numbers of 18 meters x 27.73 meters long
    concrete cribs spaced at 35M centres on prepared foundations
c   and connected by pre-cast pre-stressed deck and R.C.C. slab
    and construction of two Mooring Dolphins comprising concrete
    deck supported on 900mm internal diameter Racker bored
    piles. For the execution of the said contract, VPT was to supply
    various equipments comprising of hydraulic jacks, hydraulic
                                                                              /Ir
D   pumps, steel yoke assembly, jack rods etc. and it appears to
    be fairly admitted position that 950 nos. of jack rods were
    supplied btY VPT to the contractor. Towards cost of 500 jack
    rods, on 8t August, 1974, from the contractor's running bill no.
    21, an amount of Rs.74,810.38 was recovered by VPT.
E          4. As there was a dispute between VPT and the contractor
    with regard to return of 950 jack rods valuing Rs. 9,65, 155/-,
    VPT referred to the dispute to arbitration in the year 1975. The
                                                                          }-
    statement of claim was filed by VPT before the arbitrators on
    4th June, 1976. On 23rd March, 1980, the arbitrators rejected
F the claim of VPT. The award dated 23rd March, 1980 was
    challenged by VPT before the Civil Judge, Visakhapatanam by
    filing a petition under Sections 30 & 33 of the Arbitration Act,
  . 1940 (for short, 'Act, 1940' ). The Civil Judge, Visakhapatanam
                                        1
    dismissed the said petition on 10 h September, 1984.
G
         5. It is pertinent to notice here that until the rejection of   ;.
    claim made by VPT for Rs. 9,65d 155/- towards the cost of 950
    jack rods vide award dated 23r March, 1980, the contractor                       "
    did not raise any dispute with regard to recovery of Rs.
                                        th
    74,810.38 made by VPT on 8 ,A,ugust, 1974 from the
H
              VISAKHAPATNAM PORT TRUST V. M/S      843
      CONTINENTAL CONSTRUCTION COMPANY [R.M. LODHA, J.]

      contractor's running bill no. 21. It was only thereafter, to be A
      specific on 2ih March, 1980 that the contractor called upon VPT
                                                        nd
      to release the sum of Rs. 74,810.38. Then on 22 of September,
      1984, the contractor initiated proceedings under the Act, 1940
      in respect of claim of Rs.74,810.38 by appointing its arbitrator
      and also called upon VPT to appoint its arbitrator. The arbitrators B
                                       st
      entered upon the reference on 1 February, 1985 and they also
      appointed an Umpire. The contractor filed its statement of claim
      before the arbitrators on 16th March, 1985. The arbitrators by
      their award dated 2ih October, 1985 accepted the claim of the
      contractor and passed an award for Rs.74,810.38 in favour of c
      the contractor.
            6. VPT challenged the award by filing petition (O.P.No. 10/
      1986) under Sections 30 and 33 of the Act, 1940, inter alia
      raising the objection that the claim of the contractor was time
      barred. The Court of the Principal Subordinate Judge, D
                                                     1
      Visakhapatnam vide his judgment dated 16 h February, 1994
      allowed OP No. 10/1986; set aside the award of the arbitrators
      and held that the claim of the contractor was barred by limitation.
             7. The contractor challenged the judgment of the Principal
      Subordinate Judge, Visakhapatanam dated 16th February, 1994 E
      by filing an appeal before the High Court which was registered
      as CMA No. 1559/1994. The High Court upturned the judgment
      of the Principal Subordinate Judge, Visakhapatnam and held
      that the claim of the contractor for Rs. 74,810.38 was within
      limitation.                                                       F
            8. The other appeal being CMA No. 77/1995 before the
      High Court arose out of C-3 contract for execution of marine
      works and break waters at the outer harbour at Lova Garden,
      Visakhapatnam. The dispute seems to have arisen between G
                                     rd
-t,   VPT and the contractor on 3 February, 1975 in respect of the
      charges for power driven survey boat used by the contractor.
      The dispute was referred to the consulting engineers who opined
      viae their report dated 3rd May, 1975 that it was the responsibility
      of the contractor to provide the survey vessel and consequently,
                                                                         H
    844       SUPREME COURT REPORTS                     [2009] 2 S.C.R.
      '

A   the contractor's claim in this regard"'was untenable. Jhe
                           1
    contractor then on 15 h May, 1975 appointed Shri G.N. Bajpai
    as its arbit~ator and called upon VPT to appoint its arbitrator.
    VPT appointed one Mr. T.V. Rajaram as its arbitrator and the
    arbitrators in turn appointed Mr. AW. De'Lima as Umpire. The
B   arbitrators, however, could not enter upon the reference. The
    contractor, accordingly, approached the Principal Subordinate
    Judge, Visakhapatnam for the appointment of arbitrators by
    invoking Sections 8, 9 and 20 of the Act, 1940. The Principal
    Subordinate Judge, Visakhapatnam treated that suit under
C   Section 8 of the Act, 1940 and vide its order dated 10th
    September 1984 allowed the suit filed by the contractor and
    directed each party to appoint its arbitrators within 15 days
    therefrom. Each party, accordingly, appointed its arbitrator and
    the appointed arbitrators entered upon reference. On 14th fy1arch,
D   1985, the contractor filed claim in the sum of Rs. 8,49,000/-
    with interest and 9ost pertaining to the charges for power driven
    survey boat.
           9. The arbitrators passed the award on 20th November,
E   1985 allowing the claim of the contractor for Rs. 6,44,500/- b~!
    no interest or cost were allowed.
                                                  th
         . 10. VPT challenged the award dated 20 November, 1985
    in the Court of Subordinate Judge, Visakhapatnam by filing ·
    petition numbered as OP No. 164/1986. The award was mainly
F   opposed by VPT on the ground of limitation and that the award
    was non-reasoned.
          11. The sub~ordinate Jud~e, Visakhapatnam allowed the
    petition vide its order dated 16 February, 1994 and set aside
    ~he award holding that the claim was barred by !Imitation.
G
           12. The contractor, then carried the matter to _the High Court   >-
    by filing CMA No. 77/1995. The said appeal has been allowed
    by the High Court vide its judgment dated 26th April, 2002.

          13. As noticed above, it is from the common judgment
H
                  VISAKHAPATNAM PORT TRUST V. M/S      845
          CONTINENTAL CONSTRUCTION COMPANY [R.M. LODHA, ·J.]

,_. --s   dated 26th April, 2002 disposing of CMA No. 1559/1994 and            A
          CMA No. 77/1995 that these two appeals arise.
                14. We shall first deal with the contractor's claim of
          Rs. 74,810.38. The only issue thatfalls for our consideration with
          regard to this claim is whether it is barred by limitation.
                                                                               B
                15. Section 37 of the Arbitration Act, 1940 and Article 137
          of the Limitation Act, 1963 are relevant for the purpose.
               The Arbitration Act, 1940;
               "37. Limitations. - (1) All the provisions of the Indian        c
               Limitation Act, 1908 (9of1908), shall apply to arbitrations
               as they apply to proceedings in Court.
               (2) Notwithstanding any term in an arbitration agreement
               to the effect that no cause of action accrue in respect of
               any matter required by the agreement to be referred until D
               an award is made under the agreement, a cause of action
               shall, for the purpose of limitation, be deemed to have
               accrued in respect of any such matter at the time when it
               \'.VOUld have accrued but for that term in the agreement.
               (3) For the purposes of this section and of the Indian          E
               Limitation Act, 1908 (9 of 1908), an arbitration shall be
               deemed to be commenced when one party to the
               arbitration agreement serves on the other parties thereto
               a notice requiring the appointment of an arbitrator, or where
               the arbitration agreement provides that the reference shall     F
               be to a person named or designated in the agreement,
               requiring that the difference be submitted to the person so
               named or designated.
               (4) Where the terms of an agreement to refer further G
               differences to arbitration provide that any claims to which
               the agre_ement applies shall be barred unless notice to
               appoint an arbitrator is given or an arbitrator is appointed
               or some other step to commence arbitration proceedings
               is taken within a time fixed by. the agreement, and a H
    846       SUPREME COURT REPORTS                   [2009] 2 S.C.R.


A         difference arises to which the agreement applies, the Court
          if it is of opinion that in the circumstances of the case
          undue hardship would otherwise be caused, and
          notwithstanding that the time so fixed has expired, may on
          such terms, if any, as the justice of the case may require,
B         extend the time for such period as it thinks proper.
          (5) Where the Court orders that an award be set aside or
          orders, after the commencement of an arbitration, that the
          arbitration agreement shall cease to have effect with
          respect to the difference referred, the period between the
c         commencement of the arbitration and the date of the order
          of the Court shall be excluded in computing the time
          prescribed by the Indian' Limitation Act, 1908 (9 of 1908)
          for the commencement of the proceedings (including
          arbitration) with respect to the difference referred."
D
          The Limitation Act, 1963 ;
          "137. Any other application three years        When the
                for which no period                      of right to
                limitation is provided                   apply
E              ·accrues."
                elsewhere in this division.
          16. It is apparent from the bare reading of Section 37 that
    the law of limitation is applicable to the proceedings before the
    arbitrators as it applies to proceedings before the Courts. Under
F   Sub-section (3), arbitration proceedings are to be deemed to
    have commenced when notice is served by one party upon the
    other - (i) requiring him to appoint an arbitrator, or (ii) if the
    arbitrator was named or designated in the arbitration agreement,
    requiring him to submit the difference to arbitrator named or
G   designated.
                                                                         )-
           17. In the backdrop of aforesaid legal position, let us now
                           th
    turn to the facts. On 8 August, 1974, VPT recovered an amount
    of Rs.74,810.38 being the cost of 500 jack rods from running
    bill no. 21 tendered by the contractor. The dispute with regard
H
        VISAKHAPATNAM PORT TRUST V. MIS      847
CONTINENTAL CONSTRUCTION COMPANY [R.M. LODHA, J.]

to claim of Rs. 74,810.38, thus. arose on that date. The A
contractor ought to have given notice calling upon VPT to
appoint arbitrator within three years therefrom or apply to the
Court within this time. However, it was after ten years on 22nd
September. 1984 that the contractor appointed its arbitrator and
called upon VPT to appoint its arbitrator. Significantly, VPT had   s
already made a claim of Rs. 9,65, 155/- against the contractor
for withdrawal and return of jack rods and the dispute was referred
to arbitration at the instance of VPT in the year 1976. Although
the contractor contested the said claim of VPT before the
arbitrators but curiously no counter claim for Rs. 74,810.38 was    c
made in those proceedings. It is true that arbitrators rejected
the claim of VPT on 23rd March, 1980 and the petition before
thefu Civil Judge, Visakhapatnam also came to be   . dismissed on
10 September, 1984 but that does not improve the case of the
contractor in so far as limitation is concerned as the limitation
                        fu                                         ~ 0
began to run from 8 August, 1974. It was too late on 22
September, 1984 for the contractor to agitate the claim of
                                                                   1
Rs.74,810.38 for which the cause of action accrued on 8 h
August, 1874. The contractor ought to have made counter claim
before the arbitrators in the year 1976 itself when VPT made a
claim of 9,65, 155/- for withdrawal of jack rods. In any view of the E
matter, the claim of Rs. 74,810.38 raised for the first time after
10 years of accrual of cause of action is apparently barred by
time and rightly rejected by Principal Subordinate Judge,
Visakhapatnam vide judgment dated 16fu February, 1994.
                                                                     F
       18. As a matter offact, Mr. S.B. Upadhyay, Senior Counsel
for the respondent could not show that claim for Rs. 74,810.38
was within time.

      19. As noticed above, CMA No. 77/1995 before the High
Court related to non-payment of the charges of the power driven G
survey boat used by the contractor. Admittedly, the dispute in
this regard arose between the parties on 3rd February, 1975
and the matter was referred to the consulting engineers. The
consulting engineers rejected the claim of the contractor on 3rd
May, 1975 holding that it was the responsibility of the contractor H
    848       SUPREME COURT REPORTS                    [2009] 2 S.C.R.


A   to provide survey vessel. The contractor on 15th May, 1975
    appointed its arbitrator and gave notice to VPT requiring them
    to appoint their arbitrator. VPT also appointed its arbitrator but
    th·e arbitrators could not enter upon the reference. It was in the
    year 1979, then that the contractor approached the Principal
B   Subordinate Judge, Visakhapatnam by filing suit under the
    Arbitration Act, 1940 which was allowed vide order dated 10th
    September, 1984 directing each party to appoint its arbitrator
    within 15 days. In compliance thereof, the parties appointed their
    arbitrators and on 16th March, 1985 the contractor filed its
C   statement of claim for payment of hire charges for power driven
    survey boat.
           20. Sub-Section (3) of Section 37 of the Act, 1940, inter
    a/ia, · provides that an arbitration· shall be deemed to be
    commenced when one party to the arbitration agreement serves
                                                                                 )r
D   on the other party thereto a notice requiring the appointment of
    an arbitrator. The core controversy is: in the facts and
    circumstances of the case, when the arbitration can be said to
    have commenced.
E         21. In what we have already noticed above, the dispute
    with regard to charges for the power driven survey boat arose
    on 3rd February, 1975 and after the claim was rejected by the
    consulting engineers on 3rd May, 1975, the contractor appointed
    the arbitrator on 15th May, 1975 and asked VPT to appoint its
F   arbitrator. In other words on 15th May, 1975, the contractor served .
    on VPT a notice requiring them to appoint their arbitrator under
    the agreement. Thus under Section 37(3~ the arbitrati~n shall
    be deemed to have commenced on 15 May, 1975 1.e. well
    within time and the High .Court rightly rejected the objection of
G   VPT that the claim with regard to charges for the survey vessel
    was time barred. Merely because, the arbitrators could not enter        ;.
    upon reference and the contractor had to approach the Court in
                                                                      th
    the year, 1979 by filing suit wll~ch was allowed on 10
    September, 1984 and new arbitrators were appointed by the
H   parties and statement of claim was filed by the contractor on
                VISAKHAPATNAM PORT TRUST V. M/S      849
        CONTINENTAL CONSTRUCTION COMPANY [R.M. LODHA, J.]
          1
        14 h March, 1985, that would not render the contractor's claim      A
,-- l   time barred.
             22. Mr. Kailash Vasudev, Senior Counsel contended that
        the non-reasoned award is bad in law. In this connection, learned
        Senior Counsel referred to Section 17 of the Act, 1940 which
        came to be amended by insertion of proviso vide Andhra              B
        Pradesh Act(1 of 1990).
              23. Section 17 of the Act, 1940 reads thus ;
              "17. Judgment in terms of award. - Where the Court
              sees - no cause to remit the award or any of the matters C ·
              referred to arbitration for reconsideration or to set aside
              the award, the Court shall, after the time for making an
              application to set aside the award has expired, or such
              application having been made, after refusing it, proceed
              to pronounce judgment according to the award, and upon D
              the judgment so pronounced a decree shall follow and no
              appeal shall lie from such decree except on the ground
              that it is in excess of, or not otherwise in accordance with,
              the award."
             24. Vide Andhra Pradesh' Act ( 1 of 1990), the following       E
        proviso have been inserted to Section 17;
              "Provided that where as award pending in the Court at
              the commencement of the Arbitration (Andhra Pradesh
              Amendment) Act, 1990 or an award filed in the Court, F
              thereafter does not contain reasons therefore as required
              by the proviso to sub-section ( 1) of Section 14 the Court
              shall not proceed to pronounce the judgment according to
              the award, but shall remit the award to the arbitrators or
              the umpire for giving reasons therefore as required by the G
              said proviso and thereupon the arbitrators or umpire shall,
              within thirty days from the date of remittance of the award
              to them by the Court give reasons for the award and file
              the same in the Court:
              Provided Further that on the application of the arbitrators   H
    850        SUPREME COURT REPORTS                      [2009] 2 S.C.R.


A         or the umpire and for reasons to be recorded in writing, it
          shall be competent for the Court, to extend the period of
          thirty days aforesaid for a further period not exceeding
          fifteen days:
          Provided also that where an award pending in the court
B         as aforesaid does not contain any reasons and there is
          no possibility to remit the award to the arbitrator or panel
          of arbitrators or umpire due to their incapacity, negligence,
          refusal to act or death, the Court shall set aside the award
          and direct the parties to initiate fresh arbitration in
c         accordance with the terms of the agreement."
          25. Firstly, amendment in Section 17 vide Andhra Pradesh
    Act (1 of 1990) is not attracted in the present fact situation as
    the award was passed by the arbitrators on 20th November, 1985
    i.e. much before the amendment. As per Section 17 then
0
    obtaining, it was not imperative for the arbitrators
                                                  .
                                                         to give reasonsth
    in support of the award. Secondly, upon the award dated 20
    November, 1985 being challenged by VPT before Principal Sub-
    ordinate Judge, Visakhapatnam, the Principal Sub-ordinate
    Judge, Visakhapatnam, directed the arbitrators to give reasons
E   for the award in the light of the amendment aforenoticed.
         26. Consequently, the arbitrators gave the following
    reasons:
          "Having gone through the various provisions in the contract
F         docum-ents which have a bearing on the dispute between
          the parties and after applying correct and proper
          interpretation for adjudication of the said dispute, we find
          that the Visakhapatnam Port trust, the Respondents in
          this case, were under a Contractual obligation to make
G         available a Survey Boat for use on these works and that,
          although the survey boat was available with them, they               ,,_
          failed totally to fulfil that contractual obligation necessitating
          the claimants to obtain a boat from their own resources
          and deploy the same on the works throughout the
H         construction period. We find that after allowing some
            VISAKHAPATNAM PORT TRUST V. M/S      851
    CONTINENTAL CONSTRUCTION COMPANY [R.M. LODHA, J.]

           adjustments found necessary on perusal of the contract A
           and after having considered the written as also the oral
           submissions made to us by the parties, the claimants are
           entitled to be paid by the Respondent the sum as
           determined by us in our award."
           27. Although this exercise was unnecessary but the fact of 8
  the matter is, that subsequently the arbitrators did give their
  reasons. Reasonableness of the reasons given by arbitrators
~ cannot be gone into by the Court. This objection of the Senior
  Counsel is, accordingly, overruled.
                                                                      c
        28. For the foregoing reasons, we dispose of these
    appeals as follows:-
          (1) The judgment of the High Court of Judicature of Andhra
    Pradesh in CMA No. 1559/1994 is set aside. The claim of M/s
~   Continental Construction Company for Rs. 74,810.38 stands D
    dismissed. The amount of Rs. 74,810.38 deposited with the
    executing Court by Visakhapatnam Port Trust pursuant to the
    order dated 27th September, 2004 of this Court shall be refunded·
    to them alongwith interest accrued thereon.
         (2) The judgment of the High Court irtCMA No,--77/1995 is    E
   affirmed. The amount of Rs. 6,44,500/- deposiled by
   Visakhapatnam Port Trust with the executing Court pursuant to
-" the order of this Court dated 27th September, 2004 shall be
   paid to M/s Continental Construction Company alongwith
   interest accrued thereon.                                          F
           (3) The parties shall bear their own costs.

    G.N.                                       Appeals disposed of.


Search Indian case law

Ask in plain English, not just keywords. 25,000 AI words free, no card.

Try "Arbitration"Sign in to search

For a digitally signed copy suitable for filing, refer to the court's own website. Only the court can issue one.