Created byFuzzy Cloud

Supreme Court of India

M.P. HOUSING BOARDversusPROGRESSIVE WRITERS & PUBLISHERS

Citation
2009 INSC 375
Decided
20 March 2009
Disposal
Dismissed

Holding

The arbitrator possessed full powers to frame issues, time was not of the essence, and the award was not vitiated by misconduct; therefore the award stands and the appeal fails.

Summary

The M.P. Housing Board and Progressive Writers & Publishers entered into three successive agreements concerning the construction and ownership of a press complex. The third agreement of 31 May 1980 required full payment by 31 October 1980, failing which it would be cancelled. The Board alleged the arbitrator exceeded his jurisdiction by framing additional issues, ignored the contract terms, and committed misconduct, seeking to set aside the award. The Supreme Court examined whether the third agreement was automatically cancelled, whether time was of the essence, and whether the arbitrator could validly frame issues under Section 23 of the Arbitration Act, 1940. It held that the arbitrator’s power is equivalent to a court’s, allowing him to frame necessary issues, that time was not essential to the contract, and that the award was not vitiated by any legal misconduct. Consequently, the award was deemed final and the appeal was dismissed.

Issues considered

  • Whether the third agreement dated 31 May 1980 stood automatically cancelled for non‑payment by the depositor.
  • Whether the second agreement of 4 May 1977 was automatically revived upon alleged cancellation of the third agreement.
  • Whether time was of the essence of the third agreement.
  • Whether the arbitrator exceeded his jurisdiction by framing and deciding issues not raised by the parties.
  • Whether the arbitrator committed grave misconduct warranting setting aside of the award under Sections 30/39 of the Arbitration Act, 1940.
  • Whether the award is ordinarily final and not subject to appellate jurisdiction under Section 30 of the Arbitration Act, 1940.

Legislation cited

Subjects

ArbitrationArbitrator jurisdictionSection 23 Arbitration ActSection 30 Arbitration ActSection 39 Arbitration ActTime of essenceContract interpretationAward finalityLegal misconductSupreme Court of India

Judgment

                                 [2009] 4 S.C.R. 725


                         M.P. HOUSING BOARD                                     A
                                   V.
                 PROGRESSIVE WRITERS & PUBLISHERS
                     Civil Appeal No. 1746 of 2009
                                 MARCH 20, 2009
                                                                                B
            (LOKESHWAR SINGH PANTA AND B. SUDERSHAN
                           REDDY, JJ)

              Arbitration Act, 1940:
               s.23 - Reference by court for arbitration - Power of             c
         arbitrator- HELD: Arbitrator in such matters has all the powes
         which the court itself would have in deciding the issues in the
         suit - Arbitrator was well within his jurisdiction to frame such
         additional issues as would be just and necessary for disposal
         of reference u/s 23.
                                                                                D
               s.30-Award by arbitrator- HELD: An award by arbitrator
         is ordinarily final and courts hearing application uls 30 would
         not exercise any appellate jurisdiction - Reappraisal of
         evidence of court is impermissible - Once it is found that view
         of arbitrator is plausible, court will refrain itself from interfering. E
              Arbitration - Interpretation of agreement - HELD: Is a
 •   ~   matter for arbitrator to determine - In order to determine scope
         of an agreement, intention of parties is to be gathered - In the
         instant case, arbitrator having considered the relevant
         agreements, and subsequent events and documents F
         including correspondence between parties, rightly arrived at
         the conclusion that cost of construction mentioned in Clause
         1 of agreement dated 30 5. 1980 was tentative, and though in
         Clause 4 thereof a date was mentioned for payment, but time
· ,. ~   was not the essence of contract.                                 G

              Arbitrator - Misconduct - HELD: Erroneous application
         of law constituting the very basis of award and improper and
         incorrect findings of fact, which without closer and intrinsic
                                         725                                    H
    726      SUPREME COURT REPORTS                  [2009] 4 S.C.R.


A scrutiny are demonstrable on the face of material on record
  are held as legal misconduct rendering the award as invalid -
  In the instant case, there is no erroneous application of law by
  arbitrator or any improper or incorrect finding demonstrable
  on the face of material on record - There is nothing in the
B award requiring interference by courts - Courts rightly refused
  to interfere with the award passed by arbitrator- It is not a fit
  case warranting interference in exercise of jurisdiction under
  Article 136 of the Constitution - Constitution of India, 1950 -     •
  Article 136.
C         The appellant-Housing Board and the respondent-
    depositor entered into an agreement on 18.2.1975
    stipulating that the Board would execute construction of
    Press Complex building for the respondent. The depositor
    made the initial payment towards the proposed cost, but
D   since it failed to deposit the balance amount, another
    agreement dated 4.5.1977 was entered into between the
    parties to the effect that the depositor would transfer the
    total area of the land and building to the Board, which in
    turn would re-transfer a part of the constructed portion to
E   the depositor. The parties entered into a third building
    agreement on 31.5.1980 which stated that the depositor
    would take the entire complex building on payment of the
    total amount of cost which was estimated at Rs.73.50
    lakhs. Under Clause 4 of the agreement, the depositor
F   agreed to pay the entire amount not later than 31.10.1980,
    failing which the agreement would be deemed to have
    been cancelled. The depositor could not comply with
    Clause 4 of the third agreement by 31.10.1980 and
    subsequently made certain representations to the Board
G   that they were willing to perform their part but were unable
    to do so for want of proper accounts and other details
    from the Board. The Board first filed a suit for permanent
    injunction and subsequently a comprehensive suit for
    declaration, specific performance of the contract and
    permanent injunction. The trial court referred both the
H
                   M.P HOUSING BOARD V.                      727
             PROGRESSIVE WRITERS & PUBLISHERS

      suits for arbitration. The arbitrator made the award A
      whereunder the Board was required to handover
      immediate possession to the depositor and the Board
      would be entitled to a sum of Rs.37,70,309.87. In case of
      any default, the Board was held to be entitled to interest
      at 18% per annum capitalized quarterly. The trial court B
      confirmed the award and the High Court dismissed
      Board's appeals.
            In the instant appeal filed by the Housing Board it
       was contended for the appellant that the arbitrator
     · committed grave misconduct as he disregarded the terms C
       of the contract and based the award on conjectures and
     · surmises. It was submitted that the arbitrator exceeded
       his jurisdiction by framing and deciding issues which
:1     were not referred to him by the parties. The questions for
       consideration before the Court were: (i) whether the third D
       agreement dated May 31, 1980 stood automatically
       cancelled on account of non- compliance of the terms
       there.under by the depositor and the second agreement
       dated May 4, 1977 stood automatically revived; and (ii)
       whether time was the essence of the third agreement E
       dated May 31, 1980.
           Dismissing the appeal, the Court
            HELD: 1.1 In order to determine the scope of an
      agreement, the intention of the parties is to be gathered. F
      The third agreement dated 31.5.1980, as is evident from
      the recitals, .was entered into mainly for the purpose of
      arriving at, terms for the paym~nt of construction cost and
      other fees payable by the depositor to the Board. The
      depositor agreed to pay to the Board the total amount of G
      'cost. of Complex' incurred by the Board for the
      construction pursuant to the first agreement dated
      February 18, 1975. The third agreement does not
      speak about any transfer of land. The nature and scope
      ofthe said agreement is entirely ~ifferent from that of the H
    728     SUPREME COURT REPORTS               (2009] 4 S.C.R


A   earlier agreements dated 18.02.1975 and 04.05.1977. [para
                                                                        y       ,
                                                                                    .
    13] [ 739-8-G]
         1.2 It is true that Clause 4 of the third agreement
    provides the depositor to make all the payments on or
    before October 31, 1980 on the pain of cancellation of
B   agreement. But it is to be seen as to what are those
    amounts that were required to be paid. The arbitrator in
    this regard upon consideration of the material available       •
    on record found that the depositor was under confusion,
    and rightly so, as to the amount of actual cost of
c   construction. The amount actually paid to the architect
    as his fees and the fees as the Board has included in the
    cost of construction were different. The duration of period
    of construction was also not clear from the records
    produced by the Board. Therefore, the depositor was not
    in a position to know the capitalized interest. The Board       ..
D
    had realised rents from the building which was not set off
    against the amount of Rs.73.50 lakhs shown in the
    agreement as cost of construction. The arbitrator after
    taking the sequence of events and correspondence
                                           1
    between the parties even after 31" October, 1980 into
E   consideration, arrived at a conclusion that the figure of
    Rs.73.50 lakhs as cost of construction mentioned in
    Clause 1was tentatively shown in the third agreement. The      l.       •
    Board did not raise any objection contending that the cost
    of construction was quantified at Rs.73.50 lakhs after
F   negotiation and verification of the accounts by the parities
    to their satisfaction. It was not the case of the Board that
    the quantified amounts towards cost of construction of
    complex was non-negotiable. Interpretation of the terms
    of the agreement concerning the quantification of cost of      ~        '           .
G   construction in the instant case, does not amount to
    rewriting the terms of the contract. [para 14, 15,21and31]
    [ 740-A-G; 743-C-E; 748-F]
        2.1 The arbitrator found that the Board had itself
    waived the time clause and was willing to accept money
H   from the depositor even after 31st October, 1980 as is
              M.P. HOUSING BOARD V.                        729
        PROGRESSIVE WRITERS & PUBLISHERS

evident from tlTe-'negotiations which continued between A
the parties till the year 1985-86. The arbitrator relied on
documentary evidence made available by the parties in
arriving at the conclusion that in the instant case the time
was not essence; that the agreement subsisted even after
31.10.1980 and the matter was kept open till 1990 for B
settlement of accounts. The finding cannot be said to be
perverse to give rise to legal misconduct deserving
intervention u/s 30 of the Act. [para 16, 20 and 31] [ 740-H;
741-A" 743-B · 748-E-F]
       '        '
     2.2 It is fairly well settled that the time is not normally C
essence of any agreement qua immovable properties and
even there was an express covenant of time being an
essence, the overall agreement has to ,be looked at to
determine whether the time was the essence. Whether the
time is the essence of the contract would, therefore, be a
question of fact to be determined in each case and mere D
expression of the stipulated time would not make time an
essence of the contract. The finding arrived at by the
arbitrator in this regard is not even challenged by the
Board in the proceedings initiated by it u/s 30 of the Act.
[para 17] [ 741-B-D]                 -                           E
     Sudarsan Trading Co. vs. Govt. of Kera/a (1989) 2 SCC
38 and State of UP vs. Allied Constructions (2003) 7 SCC
396 - referred to.
      2.3 The onus to plead and prove that time was of the
essence of the contract is on the person alleging it. In the F
instant case, the Board never took the plea before initiating
the legal proceedings that the time was of the essence of
the contract. The Board never took any stand during the
negotiations that the agreement stood cancelled nor did
it take any steps to terminate the same. [para 24 and 21] G
[ 744-G-H; 743-D-E]
                                       '
     2.4 In any event, even the time was the essence of
the agreement, the same was not insisted upon by the
parties. The materials available on record disclose that
even after October, 1980, parties continued negotiations H
    730     SUPREME COURT REPORTS                  [2009) 4 S.C.R.


A   as regards the actual amounts payable based on what                     y
    the construction cost would be on reconciliation of
    accounts and the same would indicate that the parties
    were still working out their rights and obligations under
    the agreement. [para 21] [ 743-C-D]
B        3.1 It is well settled that the award of an arbitrator is
    ordinarily final and the courts hearing applications u/s 30
    the Arbitration Act, 1940 do not exercise any appellate
    jurisdiction. Reappraisal of evidence by the court is              •
    impermissible. [para 18] [ 741-D-E]
c
         /spat Engineering & Foundry Works, B. S. City, Bokaro
    vs. Steel Authority of India, B. S. City, Bokaro (2001) 6 SCC
    347 - referred to.
          3.2 Interpretation of a contract, it is trite, is a matter
D   for the arbitrator to determine. Even in a case where the
    award contained reasons, interference therewith would
                                                                           ..
    still be not available within the jurisdiction of the court
    unless, of course, the reasons are totally perverse or
    award is based on wrong proposition of law. An error
E   apparent on the face of the records would not imply closed
    scrutiny of the merits of documents and materials on
    record. "Once it is found that the view of the arbitrator is a
    plausible one, the court will refrain itself from interfering."
    [para 19] [ 742-F-H]
                                                                       l        .   '

F        3.3 The courts below found conclusions drawn and
    findings arrived at by the arbitrator that non payment of
    amounts by the depositor by 31st October, 1980 as
    provided for did not result in automatic cancellation of
    the agreement were plausible and accordingly refused to
G   interfere in the matter. The courts below upheld the
                                                                       • . -·
    findings that the depositor continued to be the owner of
    the property. [para 22] [ 744-A-B]
        Swarnam Ramachandran and Anr. Vs. Aravacode
    Chakunga/ Jayapalan 2004 (8) SCC 689 - held inapplicable.
H
               M.P. HOUSING BOARD V.                    731 ·
         PROGRESSIVE WRITERS & PUBLISHERS

      4.1 It cannot be said that no additional issue could A
have been framed by the arbitrator on his own for its
decision. In a reference made u/s 23, arbitrator's power to
determine the lis between the parties is much wider. The
arbitrator has all the powers which the court itself would
have in deciding the issues in the suit. In the light of the B
settled legal principle, the arbitrator was not bound to
adopt only the issues submitted by the parties but was
well within his jurisdiction to frame such other issue or
issues as may be just and necessary for the purpose of
disposal of the reference made u/s 23 of the Act. Therefore, C
it cannot be said that the arbitrator exceeded his
jurisdiction and committed grave legal misconduct in
framing said issue and determining the same. [para 26-
27] [ 745-E, G-H; 746-A]
     Jugal Kishore Prabhati/al Sharma and Ors. Vs. D
Vijayendra Prabhatilal Sharma and Anr. 1993 (1) SCC 114 -
referred to.
      4.2 It is true that the arbitrator took judicial note of
certain facts which were in the realm of conjectures and
s~rmises to conclude that the second agreement was E
entered into under political pressure, and depositor was
compelled to execute the said agreement under such
pressure. Even this surmise and conjecture is ignored
and not taken into consideration, the award of the
arbitrator continues to be valid and binding on the parties. F
The findings recorded by the arbitrator that the specific
performance of the second agreement was barred by
limitation; that the agreement was itself unconscionable;
that the agreement ceased to subsist after the 1980
agreement and was not revived are not based on the sole G
ground that the second agreement came to be executed
under political pressure. There is enough material
available on record to arrive at such conclusion as the
one arrived at by the arbitrator. [para 28] [ 746-8-E]
                                                            H
    732      SUPREME COURT REPORTS                 [2009] 4 S.C.R.


A        Gujarat Water Supply and Sewerage Board vs. Unique
    Erectors (Gujarat) (P) Ltd. and Anr. 1989 (1) SCC 532 and
    Food Corporation Vs. Joginder Pal 1989 (2) SCC 34 7 -
    referred to.
         5.1 The erroneous application of law constituting the
B   very basis of the award and improper and incorrect
    findings of fact, which without closer and intrinsic
    scrutiny, are demonstrable on the face of the materials
    on record, have been held as legal misconduct rendering
    the award as invalid but at the same time the court could
c   not reappraise the evidences intrinsically with a close
    scrutiny for finding out that the conclusion drawn from
    some facts, by the arbitrator is according to the
    understanding of the court, erroneous. Such exercise of
    power which can be exercised by an appellate court with
D   power to reverse the finding of fact, is alien to the scope
    and ambit of challenge of an award under the Arbitration
    Act. In the instant case there is no erroneous application
    of law by the arbitrator or any improper and incorrect
    finding which is demonstrable on the face of the material
E   on record. [para 30] [ 747-D-G]
          State of Rajasthan vs. Puri Construction Co. Ltd. and Anr
    1994 (6) sec 485 - referred to.
                                                                          •
          5.2 There is nothing in the award requiring
F   intervention by the courts. The courts below rightly
    refused to interfere with the award passed by the
    arbitrator. It is not a case which warrants interference in
    exercise of jurisdiction under Article 136 of the
    Constitution of India. [para 34] [ 749-E]
G                       Case Law Reference                            ~   .-
          (2001) 6 sec 347      referred to           para 18
          (1989) 2 sec 38       referred to           para 19
          (2003) 7 sec 396      referred to           para 19
H
                                  M.P. HOUSING BOARD V.                        733
                            PROGRESSIVE WRITERS & PUBLISHERS

-   'I                   2004 (B) sec 689      held inapplicable     para 23         A
                         1993 (1) sec 114      referred to           para 26

                         1989 (1) sec 532      referred to           para 28

                         1989 (2) sec 347      referred to           para 29
                                                                                     B
                          1994 (6) sec 485     referred to           para 30

                         CIVILAPPELLATE JURISDICTION: Civil Appeal No. 1746
         ~   -·-~

                    of 2009

                         From the Judgement and Order dated 27.07.2006 of the        c
                    Hon'ble of Madhya Pradesh, Judicature at Jabalpur in M.A. No.
                    705 of 2002 and MA No. 824 of 2002.

                         L.N. Rao, Vibha Datta Makhija, for the Appellants.

                         C.A. Sundaram, Sushi! Kumar Jain, Puneet Jain, Rohini       D
                    Musa, Abhishek Gupta, Zafar lnayat, Anand Kannan, Archana
                    Tiwari, Rajeev Mishra, for the Respondent.

                         The Judgement of the Court was delivered by

                         B.SUDERSHAN REDDY, J.
                                                                                     E
                            1. On February 18, 1975 the M.P. Housing Board (for short
                    'the Board') and Progressive Writers and Publishers, New Delhi
                    (hereinafter called as the 'depositor') entered into an agreement
                    whereunder the Board agreed to construct a building called the
                    'Hitavada Press Complex' on the land admeasuring 33932 sq. F
                    fl. situated at T.T.Nagar, Bhopal. The terms of agreement, inter-
                    alia, provided that the Board would execute the construction of
                    Hitavada Press Complex and charge 5% supervision charges
                    of the actual expenditure on the project. The cost of construction
                    was to be borne by the depositor. The depositor was required G
                    to place funds including supervision charges at the disposal of
                    the Board in advance as agreed upon. The work was expected
                    to be completed within 18-24 months. The possession of the
                    land was handed over to the Board for the purposes of
                    construction of building. In case of overrun of expenditure and H
    734       SUPREME COURT REPORTS                    [2009] 4 S.C.R.

                                                                                      ...
A   funds, the revised estimates were to be submitted and the                 r   -
    administrative approval of the depositor was required to be
    obtained. In the event of any dispute, the matter was required to
    be referred to the Secretary, Government of Madhya Pradesh
    for decision.
B           2. The cost of construction of the building was estimated
    at Rs. 28 lakhs out of which the depositor was required to
    deposit an amount of Rs. 14 lakhs at the outset and the balance
                                                                          •
    thereafter. The initial amount of Rs.14 lakhs was accordingly
  . deposited by the depositor with the Board. However, the
C depositor failed to deposit the balance amount. In the
    meanwhile, the Board had paid the amounts from its own funds
    in order to complete the construction of the building. The
    depositor expressed its desire to retain only that portion of the
    building where the printing press was located including
D mezzanine floor along with two adjacent halls on the first floor
    and accordingly made a representation to the Board. The Board
    in its turn agreed to the suggestion and thereafter parties entered
    into the second building agreement dated May 4, 1977; under
    which it was expressly agreed between the parties that the
E depositor would transfer the total area of the land and building
    which was 33932 sq. ft. and the Board would in turn re-transfer
    7437 sq.ft. of land along with hall having Press portion
    constructed thereon for which the depositor would pay Rs. 3.50
                                                                          • •
    lakhs to the Board in 15 equal yearly installments. The Board
F agreed to grant a loan of Rs. 3.50 lakhs repayable with interest
    against an equitable mortgage of the Press building and the
    portion of the land thereon. Out of the said amount, Rs. 50,000/
    - was to be paid by the Board to Punjab and Sind Bank as per
    the instructions of the depositor. It was also agreed between
G the parties that the Board in order to acquire full ownership of        •
    the entire complex shall return the amount of Rs. 14 lakhs and
    for that purpose the original documents pledged by the depositor
    with the Punjab and Sind Bank were to be redeemed by the
    Board upon payment of Rs.13.50 lakhs to the Bank. Upon
                                                                                  -
    fulfillment of the said conditions, the Board was entitled to
H
          M.P. HOUSING BOARD V. PROGRESSIVE WRITERS & 735
                PUBLISHERS [B.SUDERSHAN REDDY, J.]

        complete the construction of the building in its possession and A·
        enjoy the same as the full owner.

               3. The Board in terms of the second building agreement
        had paid the agreed sum to the Bank and obtained the original
        title deeds of the part of the plot admeasuring 19319 sq. ft only. B
        However, the title deeds of the residual area were not handed
        over to the Board. The construction was completed by the Board.

               4. For whatever be the reasons, the parties have entered
        into third building agreement on May 31, 1980. The recitals in
        the agreement disclose that certain complications and disputes c
        arose between the parties after execution of the earlier two
        agreements resulting in litigation between the parties which were
        pending as on the date of third building agreement. In the third
        building agreement it is inter-alia stated that "on the request of
        the depositor vide their letter of May 1, 1980, expressing their  o
        desire to take the entire Complex building on the following terms
        and conditions and to end all litigation for all time to come, to
        which the Board agrees ...... " Under the said agreement, the
        depositor agreed to pay to the Board the total amount of cost
        incurred by the Board for construction of Complex undertaken E
        by it under the first agreement of February 18, 1975, estimated
        at Rs. 73.50 lakhs including architectural fee, capitalised interest
        and supervision charges. The depositor was required to pay
        interest on the principal amount at the rate of 15% per annum
        from the date of completion of construction of the building (i.e. F
        01.01.1979) upto the date of payment. The depositor also
        agreed to repay the entire loan amount of Rs. 3.50 lakhs paid
        to it under the second agreement dated May 4, 1977 with
        interest at the rate of 1OYi % till the date of repayment.
r   •
              5. The dispute centers around the interpretation of Clause G
        4 of the agreement and it may be just and necessary to notice
        the same in its entirety.
             " Clause 4: That the depositor agrees to pay the entire
             aforesaid amount of cost, loan and interest on execution
    736      SUPREME COURT REPORTS                   [2009] 4 S.C.R.


A         of this agreement not later than 31st October, 1980, failing
          which this agreement shall be deemed to be cancelled."
          The agreement further provides that as soon as the
    aforesaid amounts are paid in full, the parties were required to
    take follow up action and withdraw all suits and appeals filed by
B   the parties that were pending in courts and as well as before
    Property Administrator, M.P. Housing Board. The Board was
    required to hand over possession and the title deeds by duly
    declaring the depositor as the owner of the Complex. It was          •
    expressly provided that all such provisions of the previous two
c   agreements which were inconsistent with the third agreement
    shall be deemed to be ineffective.
          6. It is an admitted fact that the depositor did not comply
    with Clause 4 of the third agreement which required the
                                    51
    payments to be made by 31 October, 1980. It is equally an
D
    admitted fact that the depositor made certain representations
    to the Board that they were willing to perform their part but were
    unable to do so for want of proper accounts and other details
    from the Board and thus required further time for payments of
    the amounts under the third agreement. Exchange of
E   correspondence in that regard between the parties went on till
    1986.
          7. Since the parties failed in arriving at any agreed
    settlement. the Board filed Suit No.2A/87 before the court of
F   llnd Additional Judge, Bhopal for permanent injunction seeking
    a restraint against the depositor from disturbing their possession
    of the land and building and also sought a further restraint order
    restraining the depositor from demolishing sheds .constructed
    by the Board. The court granted a temporary injunction. The
    depositor filed Misc. First Appeal in the High Court challenging     • '
G
    the order of temporary injunction granted by the trial court. The
    High Court vacated the temporary injunction order. The Board
    thereafter filed a comprehensive Civil Suit bearing RCS No.8A/
    90 in the court of llnd Additional District Judge, Bhopal for
    declaration, Specific Performance of the Contract and
H
        M.P. HOUSING BOARD V. PROGRESSIVE WRITERS & 737                        ·
              PUBLISHERS [B.SUDERSHAN REDDY, J.]

• •   Permanent Injunction. The learned trial court referred the disputes A
      arising out of RCS No. 8A/90 (New No.63-A/94) and Regular.
      Civil Suit No.2A/87 (New No. 16A/94) to the sole arbitrator Shri
      Justice K.K. Dubey (Retired) for determination of disputes. The
      said cases were registered before the arbitrator as Reference
      Case No.1 /95 and Reference Case No.2/95. The arbitrator by B
      his award dated September 23, 1998 granted the following
      reliefs:
           "1.   The board shall give immeuiate possession of the
                 building to the society. This should be done within a
                 week of the award being made the rule of the Court. C
           2.    The board shall be entitled to a sum of Rs.37,70,309-
                 87. Half of this amount shall be paid by the society
                 as soon as the award is declared the rule of the
                 court.-The rest of the amount shall be paid in monthly D
                 installments of Rs.2.4 lakhs from the monthly rental
                 income of the building. If there is any shortfall in the
                 realization of the rent, it shall be made good by the
                 society. This amount shall be receivable by the board
                 by the end of the month. In case of any default, the
                 board shall be entitled @ 18% per annum capitc.:;Led E
                 quarterly.
           3.    There shall be no interest payable to the board for
                 the interim period, that is, after passing of this award
                 and the decree of the court making this award the F
                 rule of the court.
           4.    As regards unrealized rent, the parties shall enter
                 into an agreement to the effect assigning the rental
                 debt to the board.
                                                                           G
           5.    Both the parties shall take steps to withdraw all cases
                 against each other before the court and before other
                 authorities.
           6.    The relief of specific performance of the third
                 agreement dated 31-5-80 as prayed by the society H
    738      SUPREME COURT REPORTS                     [2009] 4 S.C.R


A              has been allowed subject to the relief under this                        •       ~




               award."
          8. Being aggrieved by the award passed by the arbitrator,
    the Board initiated appropriate proceedings for setting aside
    the award passed by the arbitrator. The trial court confirmed the
B   award passed by the arbitrator against which the Board
    preferred appeals under Section 39 of the Arbitration Act, 1940
    (for short 'the Act'). The High Court dismissed the appeals
    preferred by the Board. Hence the present Special Leave
    Petition.
c         9. Leave granted.
         10. The present appeal is directed against the common
    judgment and order dated July 27, 2006 passed by the High
    Court of Madhya Pradesh judicature at Jabalpur whereby the
D   High Court dismissed the appeals of the appellant filed under                lo,.


    Section 39 of the Act.
          11. Shri L.N. Rao, learned senior counsel forthe appellant
    submitted that the award of the arbitrator is vitiated and required
    to be set aside. The courts below have committed a grave error
E   in confirming the award passed by the arbitrator. The arbitrator
    has committed gross misconduct which is apparent from the
    face of the record. The arbitrator disregarded the terms of the         ._
                                                                                            "
    contract and passed his award on events and circumstances
    which were irrelevant for interpreting the terms of the contract.
F   The award is based on conjectures and surmises. It was also
    submitted that the arbitrator has exceeded his jurisdiction by
    framing and deciding issues which were not referred to him by
    either of the parties which reflects the predetermined mind of
    the arbitrator.
G                                                                           •           '
          12. Shri C.A. Sundaram, learned senior counsel appearing
    for the respondent submitted that the award does not suffer from
    any infirmities whatsoever requiring the interference of this Court
    in exercise of its jurisdiction under Article 136 of the Constitution
    of India. Learned senior counsel submitted that both the courts
H
  M.P. HOUSING BOARD V. PROGRESSIVE WRITERS & 739
        PUBLISHERS [B.SUDERSHAN REDDY, J.]

below concurrently found that the award passed by the arbitrator A
is just and reasonable and is not vitiated by any act of
misconduct on the part of the arbitrator. The findings so recorded
by the courts below by no stretch of imagination could be
characterised as perverse and that being the position, there is
no scope for any interference with the award.                      B

      13. Shorn of all the details and embellishments, the crucial
question that arises for our consideration is whether the third
building agreement dated May 31, 1980 stood automatically
cancelled on account of non-compliance of the terms thereunder
by the depositor and whether the second agreement dated May C
4, 1977 stood automatically revived? In order to resolve the
controversy it is just and necessary to make a detailed analysis
of terms and conditions incorporated in the third building
agreement dated May 31, 1980. The intention of the parties is
to be gathered for determining the scope of the agreement. The D
third agreement as is evident from the recitals was entered into
mainly for the purpose of arriving at terms for the payment of
construction cost and other fees payable by the depositor to
the Board. The depositor agreed to pay to the Board the total
amount of 'cost of Complex' incurred by the Board for the E
construction pursuant to the first agreement dated February 18,
1975. The amount was quantified at Rs. 73.50 lakhs which
included the architectural fees, capitalised interest and
supervision charges etc. The said agreement does not speak
about any transfer of land. There is no doubt that the depositor F
agreed to pay the entire amount of cost of construction, loan
and interest payable to the Board on or before October 31, 1980.
The question is whether non payment results in automatic
cancellation of the third agreement? The nature and scope of
the said agreement is entirely different from that of the earlier G
agreements of 18.02.1975 and 04.05.1977 executed by and
between parties.

    14. Whether time is the essence of the agreement dated
May 31, 1980:
                                                                  H
    740      SUPREME COURT REPORTS                    [2009] 4 S.C.R.      I




                                                                                     1
A        It is true that Clause 4 of the third agreement provides that
    the depositor to make all the payments on or before October
    31, 1980 on the pain of cancellation of agreement. But the
    question is what are those amounts that were required to be
    paid?
B         15. The arbitrator in this regard upon consideration of the
    material available on record found that the depositor was under
    confusion and rightly so as to the amount of actual cost of
    construction. It was also found that the amount actually paid to
    the architect as his fees and the fees as the Board has included
c   in the cost of construction was different. The duration of period
    of construction was also not clear from the records produced
    by the Board. Therefore, the depositor was not in a position to
    know the capitalised interest. It is an admitted fact that the Board
    had been realising rents from the lessees of the building. The
D   same has not been taken into account and it is under those
    circumstances the depositor went on requesting the Board to
    provide the detailed accounts as regards the actual cost and
    also details as to the rent collected by the Board in order to
    enable them to pay the exact amount to the Board. The arbitrator
E   found that despite such request'the account books were not
    shown to them and in fact the account books were not maintained
    in terms of the first agreement. The arbitrator found that the             ._            ""
    Board always assured the depositor that it would provide the
    details as required after complete verification as regards the
F   amounts of cost incurred by the Board for construction of the
    building. The arbitrator found that the Board has realised rents
    from the building which had not been set off against the amount
    of Rs.73.50 lakhs shown in the agreement as cost of
    construction. The arbitrator after taking the sequence of events
                                                               1
    and correspondence between the parties even after 31 ' October,            ,,.
G                                                                                        '
    1980 into consideration arrived at a conclusion that the figure
    of Rs.73.50 lakhs as cost of construction was tentatively shown
    in the agreement.
          16. The arbitrator found that the Board had itself waived
H   the time clause and was willing to accept money from the
                     M.P. HOUSING BOARD V. PROGRESSIVE WRITERS & 741
                           F'.UBLISHERS [B.SUDERSHAN REDDY, J]

                   depositor even after 31st October, 1980 as is evident from the A
-      1-
                   negotiations which continued between the parties till the year
                   1985-86. The arbitrator relied on documentary evidence made
                   available by the parties in arriving at the conclusion that in the
                   present case the time is not essence of the agreement
                         17. It is fairly well settled that the time is not normally an B
                   essence of any agreement qua immovable properties and even
                   there was an express covenant of time being an essence, the
            ·;     overall agreement have to be looked at to determine whether
                   the time was the essence. Whether the time is the essence of
                   the contract would, therefore, be a question of fact to be c
                   determined in each case and merely expression of the stipulated
                   time would not make time an essence of the contract. The finding
                   arrived at by the arbitrator in this regard is not even challenged
                   by the Board in the proceedings initiated by it under Section 30
                   of the Act.                                                        D
                         18. It is fairly well settled and needs no restatement that
                   the award of the arbitrator is ordinarily final and the courts
                   hearing applications under Section 30 the Act do not exercise
                   any appellate jurisdiction. Reappraisal of evidence by the court
                   is impermissible. In lspat Engineering & Foundry Works, B. S. E
                   City, Bokaro vs. Steel Authority of India, B. S. City, Bokaro
_.;.
                   [(2001) 6 sec 347], it is held:
             ...
                        " 4. Needless to record that there exists a long catena of
                        cases through which the law seems to be rather well settled F
                        that the reappraisal of evidence by the court is not
                        permissible. This Court in one of its latest decisions
                        [Arosan Enterprises Ltd. v. Union of India (1999) 9 SCC
                        449] upon consideration of decisions in Champsey Bhara
                        & Co. v. Jivraj Ba/loo Spg. & Wvg. Co. Ltd. [AIR 1923 PC
    .. "                66], Union of India v. Bungo Steel Furniture (P) Ltd.[(1967
                                                                                    G
                        1 SCR 324], N. Chellappan v. Secy., Kera/a SEB {(1975)
                        1 SCC 289], Sudarsan Trading Co. v. Govt. of Kera/a
                        {(1989) 2 SCC 38], State of Rajasthan v. Puri Construction
                        Co. Ltd. [(1994) 6 SCC 485] as also in Olympus
                                                                                    H
    742       SUPREME COURT REPORTS                      (2009] 4 S.C.R.


A         Superstructures (P) Ltd. v. Meena Vijay Khetan [(1999)
                                                                                 r
          5 sec  651] has stated that reappraisal of evidence by                          *

          the court is not permissible and as a matter of fact, exercise
          of power to reappraise the evidence is unknown to a
          proceeding under Section 30 of the Arbitration Act. This
B         Court in Arosan Enterprises categorically stated that in
          the event of there being no reason in the award, question
          of interference of the court would not arise at all. In the
          event, however, there are reasons, interference would still
          be not available unless of course, there exist a total
c         perversity in the award or the judgment is based on a
          wrong proposition of law. This Court went on to record that
          in the event, however, two views are possible on a question
          of law, the court would not be justified in interfering with the
          award of the arbitrator if the view taken recourse to is a
D         possible view. The observations of Lord Dunedin in
          Champsey Bhara stand accepted and adopted by this
          Court in Bungo Steel Furniture to the effect that the court
          had no jurisdiction to investigate into the merits of the
          case or to examine the documentary and oral evidence in
E         the record for the purposes of finding out whether or not
          the arbitrator has committed an error of law. The court as
          a matter of fact, cannot substitute its own evaluation and
          come to the conclusion that the arbitrator had acted               . "
          contrary to the bargain between the parties."
F
        19. Interpretation of a contract, it is trite, is a matter for the
  arbitrator to determine. Even in, a case where the award
  contained reasons, the interference therewith would still be not
  available within the jurisdiction of the court unless, of course,
  the reasons are totally perverse or award is based on wrong
G
  proposition of law. An error apparent on the face of the records           •       'f



  would not imply closed scrutiny of the merits of documents and
  materials on record. "Once it is found that the view of the
  arbitrator is a plausible one, the court will refrain itself from
  interfering." (see Sudr>rsan Trading Co. vs. Govt. of Kera/a
H
                M.P. HOUSING BOARD V. PROGRESSIVE WRITERS & 743
                      PUBLISHERS [B.SUDERSHAN REDDY, J.]

              (1989) 2 SCC 38 and State of UP vs. Allied Constructions A
              (2003) 7 sec 396].
                    20. In the present case, on the material available and upon
              appreciating the same the arbitrator arrived at the finding that
              the time was not of the essence and the agreement subsisted
              even after 31st October, 1980. The finding cannot be said to be B
              perverse to give rise to legal misconduct deserving intervention
              under Section 30 of the Act.

                    21. In any event, even the time was the essence of the
              agreement, the same was not insisted upon by the parties in        c
              the present case. The material available on record disclose that
              even after October, 1980, parties continued negotiations as
              regards the actual amounts payable based on what the
              construction cost would be on reconciliation of accounts and
              the same would indicate that the parties were still working out D
              their rights and obligations under the agreement. The parties
              would not have acted in such a manner had the agreement had
              come to an end. Be it noted that the Board never took any stand
              during the negotiations that the agreement stood cancelled or
              took any steps to terminate the same. It did not raise any
;             objection contending that the cost of construction was quantified E
              at Rs.73.50 lakhs after negotiation and verification of the
              accounts by the parities to their satisfaction. It was not the case
              of the Board that the quantified amounts towards cost of
              construction of complex was non negotiable. It is under those
              circumstances the arbitrator accepted the case set out by the F
              depositor that the Board was always assuring them to furnish
              the correct figure and the accounts of cost incurred by them but
              refused to do so. The arbitrator took into consideration variety
              of circumstances in arriving at the conclusion that the figure of
    'I'   •   Rs.73.50 lakhs stipulated in the agreement was tentative and G
              not a final figure. The arbitrator has fully discussed the issue as
              to how the non-payment of the amounts was on account of the
              Board's action in not furnishing the accounts even at the stage
              of arbitration and, therefore, held that the Board could not seek
              to wriggle out of 1980 agreement.                                   H
    744           SUPREME COURT REPORTS                 [2009] 4 S.C.R.


A         22. The courts below found conclusions drawn and findings
    arrived at by the arbitrator that non payment of amounts by the
                     1
    depositor by 31 ' October, 1980 as provided for did not result in
    automatic cancellation of the agreement were plausible and
    accordingly refused to interfere in the matter. The courts below
B   upheld the findings that the depositor continued to be the owner
    of the property.

         23. The decision in Swamam Ramachandran and Anr.
    Vs. Aravacode Chakungal Jayapalan, [2004 (8) SCC 689],
    upon which reliance has been placed by the learned senior
C   counsel, in our considered opinion, in no manner, supports the
    contention advanced before us. In the said decision the Court
    took the view that the time is presumed not to be of the essence
    of the contract relating to immovable property, but it is of the
    essence in contracts of reconveyance or renewal of lease. It is
D   further held that whether time is of the essence is a question of
    fact and the real test is the intention of the parties. It depends
    upon the facts and circumstances of each case. In cases where
    notice is given making time of the essence, it is the duty of the
    court to examine the real intention of the party giving such notice
E   by looking at the facts and circumstances of each case. The
    intention can be ascertained from:

          (i)      the express words used in the contract;
                                                                            .
          (ii)     the nature of the property which forms the subject
F                  matter of the contract;

          (iii)    The nature of the contract itself; and
          (iv)     The surrounding circumstances.


G
          24. The onus to plead and prove that time was of the
    essence of the contract is on the person alleging it. In the present
    case, the Board never took the plea before initiating the legal
                                                                            .   ..,

    proceedings that the time was of the essence of the contract.
    The arbitrator after taking all the relevant facts into consideration
    in the present c:se found that there was no justification in
H   claiming to treat time as of the essence of the contract.
  M.P. HOUSING BOARD V. PROGRESSIVE WRITERS & 745
        PUBLISHERS [B.SUDERSHAN REDDY, J]

      25. Mr. Nageshwar Rao, learned senior counsel for the A
appellant submitted that amongst the issues submitted by the
parties to the arbitrator there was no issue regarding the non-
execution of the contract or with regard to whether the non-
performance of the third agreement was due to non-supply of
accounts by the Board. The contention was that the arbitrator B
himself framed a specific issue, being issue No. 13 to the effect
whether the Board thwarted the fulfillment of the condition of the
payment within the period of time by not supplying the proper
accounts of the costs of the building, thus, denying the depositor
the opportunity to deposit the amount. The submission was that    c
the arbitrator exceeded his jurisdiction in framing such an issue
and thus committed grave legal misconduct. It was submitted
that in the present case both the parties acted in accordance
with the terms of the 1980 agreement and upon admitted failure
of the depositor to pay the stipulated amounts within the agreed
                                                                   0
period, the contract stood automatically terminated and the 1977
contract automatically revived.

       26. We cannot accept the contention of the Board that no
additional issue could have been framed by the arbitrator on
his own for its decision. In a reference made under Section 23, E
arbitrator's power to determine the lis between the parties is
much wider. The arbitrator has all the powers which the court
itself would have in deciding the issues in the suit. The court's
power to frame an additional issue if its is just and necessary
for deciding the matter in dispute cannot be denied and so also F
of the arbitrator where disputes between the parties pending
adjudication on suits have been referred to arbitrator for
determination [See: Jugal Kishore Prabhatilal Sharma and Ors.
Vs. Vijayendra Prabhatilal Sharma and Anr. [1993(1) SCC
114)].                                                            G
      27. In the light of the settled legal principle, we are of the
opinion that the arbitrator was not bound to adopt only the issues
submitted by the parties but was well within his jurisdiction to
frame such other issue or issues as may be just and necessary
for the purpose of disposal of the reference made under Section H
    746      SUPREME COURT REPORTS                     [2009] 4 S.C.R


A   23 of the Act. We accordingly find no merit in the submissions
    made by the learned senior counsel that the arbitrator exceeded
    his jurisdiction and committed grave legal misconduct in framing
    said issue and determining the same.

          28. It is true that the arbitrator took judicial note of certain
B   facts which were in the realm and conjectures and surmises to
    conclude that the second agreement 1977 was entered into
    under political pressure and depositor was compelled to execute
    the said agreement under such pressure. But the question is
    what is the effect of the same. In our considered opinion even
c   this surmise and conjecture is ignored and not taken into
    consideration, the award of the arbitrator continues to be valid
    and binding on the parties. The findings recorded by the
    arbitrator that the specific performance of the second agreement
    is barred by limitation; that the agreement is itself
D   unconscionable; that the agreement ceases to subsist after the           ...
    1980 agreement and was not revived are not based on the sole
    ground that the second agreement came to be executed under
    political pressure. There is enough material available on record
    to arrive at such conclusion as the one arrived at by the arbitrator.
E   All the said conclusions were not arrived solely on the basis of
    conjectures and surmises. In Gujarat Water Supply and
    Sewerage Board vs. Unique Erectors (Gujarat) (P) Ltd. and
    Anr. [1989 (1) sec 532], this Court held that "an award of an                  :ii

    arbitrator should be read reasonably as a whole to find out the
F   implication and the meaning thereof. Even in a case where the
    arbitrator has to state reasons, the sufficiency of the.reasons
    depends upon the facts and circumstances of the case. The
    Court, however, does not sit in appeal over the award and review
    the reasons. The court can set aside the award only if it is
    apparent from the award that there is no evidence to support
G                                                                                  y

    the conclusion or if the award is based upon any legal proposition
    which is erroneous." The award under challenge is not the one
    which is based on no evidence.

         29. In Food Corporation Vs. Joginder Pal [ 1989 (2) SCC
H   347] this Court reiterated the principle that an award of an
          MP. HOUSING BOARD V. PROGRESSIVE WRITERS & 747
               PUBLISHERS [B.SUDERSHAN REDDY, J]

        arbitrator can only be interfered with or set aside or modified A
        within four corners of the procedure provided by the Act. It is not
        misconduct on the part of an arbitrator to come to an erroneous
        decision, whether error is one of the fact or law, and whether or
        not his findings of fact are supported by evidence. In case of
        errors apparent on the face of the award it can only be set aside B
        if in the award there is any proposition of law which is apparent
        on the face of the award, namely, in the award itself or any
        document incorporated in the award. Errors of law as such are
        not to be presumed.

                30. Learned senior counsel for the appellant further C
        contended that the arbitrator in the instant case has committed
        grave error in going beyond the terms of the contract admittedly
        entered into by and between the parties. The question is what
        is the legal misconduct committed by the arbitrator in the instant
        case? Whether the award by the arbitrator perpetrates gross D
        miscarriage of justice? Is it reduced to mockery of a fair decision
        of the lis between the parties to the arbitration? The . erroneous
        application of law constituting the very basis of the award and
        improper and incorrect findings of fact, which without closer and
        intrinsic scrutiny, are demonstrable on the face of the :materials E
        on record, have been held as legal misconduct rendering the
        award as invalid but at the same time the court could not
        reappraise the evidences intrinsically with a close scrutiny for
        finding out that the conclusion drawn from some facts, by the
        arbitrator is according to the understanding of the court, F
        erroneous. Such exercise of power which can be exercised by
        an Appellate Court with power to reverse the finding of fact, is
        alien to the scope and ambit of challenge of an award under the
        Arbitration Act. [See: .State of Rajasthan vs. Puri Construction
        Co. Ltd. and Anr. [1994 (6) SCC 485]. In the present case there G
y   ,
        is no erroneous application of law by the arbitrator or any
        improper and incorrect finding which is demonstrable on the
        face of the material on record.
              31. ltwas submitted that when there has been quantification
        of the costs of the construction of the building and incorporation H
    748      SUPREME COURT REPORTS                   [2009] 4 S.C.R.


A   of the same in the third agreement the same could not be re-
    determined by the arbitrator by rewriting the terms of the
    agreement entered into between the parties. We find no merit
    in the submission. There is no dispute with the proposition that
    the intention of the parties is to be gathered from the words
B   used in the agreement. If the words are clear, there is very little
    that the Court can do about it. In the present case, the parties
    entered into three agreements one after the another. The
    arbitrator while interpreting clause I of the third building
    agreement whereunder the figure of Rs.73.50 lakhs being the
c   amount of cost of complex arrived at the conclusion that the
    figure has been given by the Board. The arbitrator upon
    appreciation of the material available on record found that the
    depositor repeatedly requested the Board to provide the details
    of accounts of the cost as also the rent realization in order to
    enable them to pay the exact amount to the Board. The arbitrator
D
    after taking all the relevant facts and circumstances into
    consideration found that determination as to the actual cost of
    the construction was absolutely imperative to determine the
    exact amount payable and found that the figure of 73.50 lakhs
    as stated in clause 1 of the third agreement was only indicative.
E   The arbitrator derived support from the numerous documents
    filed before him which revealed that the cost of construction was
    stipulated in clause 1 of the agreement was tentative, the matter
    was kept open till 1990 for settlement of accounts. Interpretation
    of the terms of the agreement concerning the quantification of
F   cost of construction in the present case, in our considered
    opinion, does not amount to rewriting the terms of the contract.
          32. The arbitrator having considered the overall situation
    and having arrived at a conclusion that the second building
    agreement was not enforceable held that the property would
G
    continue to vest with the depositor. But the arbitrator did not
    ignore the legitimate right of the Board to realize the amounts
    spent by it for putting up the construction. The arbitrator
    considered the matter and worked out a reasonable, just and
    fair solution and accordingly held that the depositor was bound
H
            M.P. HOUSING BOARD V. PROGRESSIVE WRITERS & 749 '
                  PUBLISHERS [B.SUDERSHAN REDDY, J.]

,_   >-   to pay the amounts spent by the Board for construction whether A
          or not they wanted such a construction to have come up or
          whether or not the Board could have expended monies to pay
          for the construction without the consent of the depositor as
          provided in the 1975 agreement.

                 33. The arbitrator accordingly passed the award declaring B
          that the Board shall be entitled to a sum of Rs.37,70,309.85
          and directed the depositor to pay half of the amount as soon as
          award is declared a Rule of the Court. The rest of the amount to
          be paid in monthly installments of 2.4 lakhs from the monthly
          rental income of the building. In case of any default the Board C
          shall be entitled to interest @ 18% per annum capitalized
          quarterly. Relief granted by the arbitrator, in our considered view
          is fair and equitable one. The arbitrator awarded the amounts
          towards cost of construction plus supervision and other charges
          payable to the Board together with a hefty interest @ 15% D
          compound from the date of expenditure by the Board till the
          date of payment.
                34. In our considered opinion, there is nothing in the award
          requiring intervention by the courts. The courts below rightly
          refused to interfere with the award passed by the arbitrator. It is E
          not a case which warrants our interference in exercise of


-         jurisdiction under Article 136 of the Constitution of India.
                35. Appeal fails and is accordingly dismissed with no order
          as to costs.                                                      F

          R.P.                                         Appeal dismissed.




,


Search Indian case law

Ask in plain English, not just keywords. 25,000 AI words free, no card.

Try "Arbitration"Sign in to search

For a digitally signed copy suitable for filing, refer to the court's own website. Only the court can issue one.