Created byFuzzy Cloud

Supreme Court of India

M/S RICKMERS VERWALTUNG GMB HversusTHE INDIAN OIL CORPORATION LTD.

Citation
1998 INSC 436
Decided
19 November 1998
Disposal
Dismissed

Holding

No binding contract or arbitration agreement existed between the parties, as the essential terms were not agreed, rendering the arbitration clause void.

Summary

The appellant, a shipowner, and the respondent, Indian Oil Corporation, negotiated a charter party for shipping pipes but never signed the agreement because they could not agree on the format of a standby letter of credit and a performance guarantee, which were treated as conditions precedent. The appellant later invoked the arbitration clause in the unsigned draft charter party, prompting the respondent to seek a declaration under Section 33 of the Arbitration Act, 1940 that no arbitration agreement existed. The Delhi High Court held that no enforceable contract had been concluded and restrained arbitration. On appeal, the Supreme Court affirmed that correspondence alone did not demonstrate a meeting of minds on the essential terms, that the standby letter of credit and performance guarantee were indeed conditions precedent, and therefore no binding contract or arbitration clause existed. The appeal was dismissed, leaving the respondent free from arbitration.

Issues considered

  • Whether a valid and subsisting contract existed between the parties despite the charter party being unsigned and essential terms pending.
  • Whether the arbitration clause in the unsigned draft charter party was enforceable.
  • Whether correspondence can be used to infer a binding agreement in the absence of a signed document.
  • Whether the standby letter of credit and performance guarantee constituted conditions precedent to contract formation.

Legislation cited

Subjects

arbitrationcontract formationunsigned agreementcondition precedentcharter partycorrespondencemeeting of mindsIndian Arbitration ActSection 33maritime shipping

Judgment

A                  MIS RICKMERS VERWALTUNG GMB H
                                         v.
                   THE INDIAN OIL CORPORATION LTD.

                             NOVEMBER 19, 1998

B           [DR. A.S. ANAND, CJ. AND K. VENKATASWAMI, J.)


         Arbitration Act, 1940 : Section 33

         Arbitration-Charter party agreement for shipping of pipes between
C appellant ad respondent-Agreement not signed by parties-Conditions for
    agreement-Execution of letter of credit and performance guarantee-
    Contents of these two documents to be mutually agreed between the parties-
    No agreement between parties as to contents of documents-Consequently
    cargo arrangements not made by appellant-Alternative arrangements by
D   respondent-Invocation of arbitration clause contained in the agreement by
    ap;,ellant-Claim that though no formal agreement was signed by parties yet
    a binding agreement had come into existence through correspondence-
    Held entire correspondence indicated no enforceable contract came into
    existence·-Consequently clause relating to arbitration had no existence.

E         Contract-Though not signed by parties-Can be spelled out from
    correspondence exchanged between the parties-But it must clearly emerge
    from correspondence that parties were ad idem to the terms.

           The respondent-Corporation entered into an agreement with a Mexico
    Company for purchase of pipes which were to be delivered at Tempico port
p   in Mexico. For the purpose of shipping of pipes negotiations were conducted
    with the appellant-vessel owners for entering into an agreement. Before
    execution of agreement the respondent-Corporation was to establish a
    stand-by letter of credit while the appellant was to furnish a performance
    bond. The format and contents of these two documents were to be mutually
    agreed upon by both the parties. A charter party agreement was drawn up
G   on November 11,1993 but it was not signed by the parties. However, no
    agreement was reached between the parties with regard to th~ contents of
    the s"tand-by letter of credit and performance guarantee. Therefore, the
    appellant did not make any shipping arrangements and the respondent-
    corporation had to make alternative arrangements. Thereafter, appellant
H   tiled an ap(•lication before Indian Council of Arbitration invoking clause 53
                                         42
                RICKMERS VER WAL TUNG GMB H v. 1.0.C. LTD.                      43
• of the Agreement of Affreightment relating to arbitration. This clause               A
  provided that all disputes under the charter party were to be settled in India
  in accordance with the provisions of the Indian Arbitration Act, 1940 read
  with Maritimes Arbitration Rules of Indian Council of Arbitration. The
  respondent-Corporation contested the application on the ground that the
  agreement between the parties had not been signed since no agreement could           B
  be reached at with regard to the contents of standby letter of credit and
  performance guarantee. Consequently reference of the dispute in question
  to Arbitration was unwarranted. However, the Indian Council of Arbitration
  appointed arbitrators and directed the respondent-Corporation to deposit
  expenses of arbitration.

       The respondent-Corporation filled a petition under Section 33 of the
                                                                                       c
 Arbitration Act, 1940 seeking a declaration to the effect that reference of
 dispute to the Arbitrator was not maintainable as there existed no concluded
 agreement between the parties. A single Judge of the Delhi High Court held
 that no concluded, enforceable and binding contract came into existence
 between the parties and as such clause 53 of the charter party agreement              D
 relating to arbitration had no existence in the eye of law. Accordingly the
 Single Judge restrained the appellant from proceeding with the arbitration.
        In appeal to this Court it was contended on behalf of the appellant that
  (1) a binding agreement had come into existence through correspondence
  and therefore non-signing of the charter party agreement was of no                   E
  consequence; and (2) even in the absence of an agreement about the format
  of letter of credit and of the performance guarantee, clause 48 of the
  agreement was attracted and recourse to arbitration was justified.

        Dismissing the appeal, the Court
                                                                                       F
        HELD : I. The Single Judge of the High Court was perfectly justified
  in holding that clause 53 of the Charter party relating to arbitration had no
  existence in the eye of law, because no concluded and binding contract ever
  came into existence between the parties. The finding recorded by him is
  based on a proper appreciation of evidence on the record and a correct
  application of the legal principles. [48-C)                                          G
        2. Clause 48 of the Charter Party by itself does not show whether the
  condition of establishing a standby irrevocable letter of credit or the furnishing
  of performance guarantee were conditions precedent to the conclusion of
  contract but there is enough material on the record to show that they were
  meant to be condition precedent. The correspondence between the parties              H
    44                        SUPREME COURT REPORTS [1998] SUPP. 3 S.C.R.

A   unmistakably shows that at no point of time, till the Charter Party agreement
    was drafted did the parties agree to proceed further without agreeing upon
    the format of the letter of credit and performance guarantee. From the
    record it is evident that the stand of the appellant was categorical that
    without any agreement on the terms of the letter of credit, it was not ready
    to nominate the vessel to carry the cargo. The appellant was, thus, for all
B   intent and purposes treating the furnishing of the letter of credit as a
    condition precedent for carrying the cargo. At no point of time did the
    appellant accept the terms of the letter of credit furnished by the respondent.
                                                                 [50-B; 52-A; D-EJ

C          3. An agreement, even if not signed by the parties, can be spelt out
    from correspondence exchanged between the parties. However, in this
    connection the cardinal principle to remember is that it is the duty of the
    court to construe correspondence with a view to arrive at a conclusion
    whether there was any meeting of mind between the parties, which could
    create a binding contract between them but the Court is not empowered to
D   create :a contract for the parties by going outside the clear language used
    in the correspondence, except insofar as their are some appropriate
    implications of law to be drawn. Unless from the correspondence it can
    unequivocally and clearly emerge that the parties were ad idem to the terms,
    it ca!lnot be said that an agreement had come into existence between them
E   through correspondence. The Court is required to review what the parties
    wrote and how they acted and from that material to infer whether the intention
    as expressed in the correspondence was to bring into existence a mutually
    binding contract. The intention of the parties is to be gathered only from the
    expressions used in the correspondence and the meaning it conveys and in
    case it shows that there had been meeting of mind between the parties had
F   they had actually reached an agreement, upon all material terms then alone
    can it be said that a binding contract was capable of being spelt out from the
    correspondence. [52-F; G-H; 53-A-BI

           4. From a careful perusal of the entire correspondence on the record
G   it is evident that no concluded bargain had been reached between the parties
    as the terms of the standby letter of credit and performance guarantee were
    not accepted by the respective parties. In the absence of acceptance of the
    standby letter of credit and performance guarantee by the parties, no
    enforceable agreement could be said to have come into existence. The
    correspondence exchanged between the parties shows that there is nothing
H   expressly agreed between them and no concluded enforceable and binding
        RICKMERSVERWALTUNGGMBH v.1.0.C. LTD. [DR.A.S. ANAND, CJ.]            45
• agreement came into existence between them. Apart form the correspondence,       A
  the fax messages exchanged between the parties go to show that the parties
  were only 11egotiating and had not arrived at any agreement. There is a vast
  difference between negotiating a bargain and entering into a binding contract.
  After negotiation of bargain in the present case, th~ stage never reached
  when the negotiations were completed giving rise to a binding contract.          B
                                                                        (53-C-E)

       CIVIL APPELLA rE JURISDICTION : Civil Appeal No. 5810 of 1998.

      From the Judgment and Order dated 17.10.96 of the Delhi High Court
 in O.M.P. No. 18 of 1995.
                                                                                   c
      R.F. Nariman, Mahesh Agrawal, Ms. Rina Barua, Dr. Jose Verghese and
 E.C. Agrawala for the Appellant.

       V.N. Koura and Manoj Wad for the Respondent.

       The Judgment of the Court was delivered by                                  D
       DR. A.S. ANAND, C.J. Leave granted.

       This appeal by special leave calls in question the judgment and order
 of the Delhi High Court dated Oct. 17, 1996 and arises in the following
 circumstances.                                                                    E
       The respondent, Indian Oil Corporation Ltd., entered into an agreement
 with Mis Tubacero of Mexico for purchase of pipes for its Kandla-Bhatinda
 Pipeline project on September 16, 1993. According to the terms of the
 agreement, Mis Tubacero were to deliver the pipes to the respondent at
 Tampico Port in Mexico. In order to bring the pipes to India, the respondent,     F
 a Government Corporation, was required to go through Mis Transchart, a
 department of the Ministry of Surface Transport, which brokers charter party
 arrangements with various vessel owners, for the purposes of shipping of
 pipes from Tampico Port. Mis. Transchart invited offers from various ship
 owners and the appellant was one of the ship owners who made an offer. In         G
 order to execute a contract between the parties, respondent No. 1 was to
 establish a standby letter of credit as per the format to be mutually agreed
 upon by the parties while the appellant was to furnish a performance bond
 also in a format to be mutually agreed upon by both the parties. Respondent
 No. I conveyed to the appellant on Nov. 17, 1993 that loading of pipes at
 Tampico port should commence on December 14, 1993 and be completed by             H
    46                        SUPREME COURT REPORTS (1998) SUPP. 3 S.C.R.

A December 21, 1993. The appellant, however, did not proceed in the matter
  because the format and the language of the standby letter of credit in the form
  issued by its ban'k.ers was not approved by the first respondent. The draft
  letter of credit proposed by the first respondent was also not approved by
  the appellant and fresh proposals were exchanged between the parties. As a
  consequence, the appellant did not carry the pipes, as according to it, the
B formats of standby letter of credit and performance guarantee were not settled
  betwef:n the parties. The first respondent was, therefore, compelled to arrange
  for the carriage of first consignment of pipes received from Mis Tubacero at
  Mexico. Transchart by it telex dated December 24, 1993 apprised the appellant
  about the failure to carry out its obligation, despit.e repeated requests which
C had resulted in the Charterers to finalise alternative shipping arrangements.
  While the matter stood thus, the appellant filed a request for arbitration with
  the Indian Council of Arbitration on 11.6.1994. On June 28, 1994 the first
  respondent received a notice from the Indian Council of Arbitration intimating
  it that the appellant had filed an application dated June 16, 1994 invoking
  Clause .53 of the Agreement of Affreightment (AOA) relating to arbitration
D and that it had laid a claim of 1,031 ;668.77 US dollars. The first respondent
  was dirf:cted to deposit a sum of Rs. 83,200 towards costs of the arbitration
  on or before Iuly 28, 1994. On receipt of the communication from the Indian
  Council of Arbitration, the first respondent informed the Indian Council of
  Arbitration (second respondent) that there did not exist any binding contract
E between the first respondent and the appellant, much less any binding
  agreement of refer any dispute between the parties to arbitration according
  to the Rules of the Arbitration of the Indian Council of Arbitration. It was
  asserted that the agreement dated Nov. 11, 1993 relied upon by the appellant
   in its statement of claim, as constituting the contract between the parties had
  not been signed by the first respondent and the document was nothing more
F than a mi::re proposal made by the appellant, which was subject to the parties
   agreeing on the format and language of the standby letter of credit to be
   provided by the first respondent for the benefit of the appellant and was
   subject to the parties also agreeing to the format and language of performance
   guarantee to be established by the appellant in favour of the first respondent.
G It was maintained that since no agreement could be reached with regard to
   the contents of the aforesaid two documents, which were fundamental to
   arrive at a working relationship between the parties, the claim of the appellant
   regarding !he conclusion of the contract between them was not maintainable.
   The first respondent also questioned the jurisdiction of the Indian Council of
   Arbitration to decide whether or not an arbitration agreement exists between
H the parties and asserted that in case the appellant considered that they had
      RICKMERS VERWALTUNGGMBH v.1.0.C.LTD. [DR.A.S.ANAND,C.J.]                47
entered into a binding agreement between the parties, they could take steps         A
to obtain a reference through a competent court. Notwithstanding the stand
of the first respondent, the Indian Council of Arbitration on January 3, 1995,
intimated to the parties that it had appointed Mr. M.K. Chawla a retired Judge
of the Delhi High Court as an Arbitrator. It was also stated in the communication
that appellant had nominated Rear Admiral (Dr.) O.P.Sharma as their nominee         B
as arbitrator. The first respondent was requested to file its statement of
defence by January 15, 1995, which date was subsequently extended. The
direction to deposit a sum of Rs. 83,000 towards cost of expenses of the
arbitration was reiterated. The first respondent, aggrieved by the communication
from the Indian Council of Arbitration dated January 3, 1995, filed a petition
under Section 33 of the Indian Arbitration Act, 1940, seeking a declaration         C
from the court that there did not exist any concluded arbitration agreement
between the parties and the reference of the dispute in question to the
Arbitration by the appellant was unwarranted and not maintainable. The
application was resisted by the appellant, who maintained that a valid and
subsisting agreement between the parties had come into existence and that
the claim of the appellant was required to be adjudicated by the arbitrators        D
in terms of Clause 53 of the "agreement". On the pleadings of the parties, a
 learned single Judge of the Delhi High Court framed the following issues :

         "I.Whether there is a valid and subsisting agreement between the
        parties ?
                                                                                    E
        2. Relief."

       During the pendency of the application the learned single Judge stayed
further proceedings before the Arbitrator appointed by the Indian Council of
Arbitration. Parties were directed to file evidence by way of affidavits in the
court. Documentary evidence and affidavit were consequently filed in the            F
court.

       The case put up before the learned single Judge on behalf of tJ:ie
appellant was that though no agreement (as drawn up on 11.11.1993) was
formally signed between the parties, yet the contemporaneous correspondence         G
exchanged between them went to show that a binding contract did come into
existence between the parties and since Clause 53 of the "agreement" dated
 11.11.1993 provided that all disputes under the Charter Party were to be
settled in India in accordance with the provisions of the Indian Arbitration
Act, 1940 read with the Maritime Arbitration Rules of the Indian Council of
 Arbitratio_n, their plea to get the dispute settled by arbitration was well        H
    48                        SUPREME COURT REPORTS [1998) SUPP. 3 S.C.R.

A   found1~d. According to respondent No. I, Indian Oil corporation Ltd., on the
    other hand, no arbitration agreement had been executed between the parties
    and that the contemporaneous correspondence exchanged between the parties
    had also not brought about any enforceable contract between them because
    the fundamental conditions of the terms of the bargain were neither agreed
B   upon nor fulfilled by the parties.

           After referring to various documents and correspondence exchanged
    between the parties, the learned single Judge on October 17,1996, vide the
    order impugned herein, held that no concluded, enforceable and binding
    contra1;t came into existence between the parties and as such Clause 53 of
C   the Charter Party "agreement" relating to arbitration had no existence in the
    eye oflaw. Issue No. I was, accordingly, decided in favour of respondent No.
     I and the petition filed under Section 33 of the Arbitration Act by respondent
    No.I was allowed on October 17,1996. The learned single Judge restrained the
    appelfa1nt from proceeding with the arbitration. Hence this appeal.

D         We have heard learned counsel for the parties and perused the record.

           It is an admitted case of the parties that a Charter Party Agreement was
    drawn up on November 11, 1993. It is, however, not disputed that the said
    agreement was not signed by the parties. Mr. R.F. Nariman, learned senior
E   advocate appearing for the appellant submitted that even though the agreement
    dated November 11, 1993 had not been signed by the parties but the parties
    had acted upon it treating it to be a binding contract. Argued Mr. Nariman
    that the agreement was operative and binding even without the parties having
    agreed to the format and terms of the standby letter of credit and the
    perfom1ance guarantee, because the appellant had after receipt of the letter
F   of credit 'rrom respondent No. I sent to him a communication dated December
    6, 1993 intimating that the draft of letter of credit was basically acceptable
    except :for some minor details. Similarly, it had been conveyed that the draft
    perfonnance bank guarantee received by it from respondent No. I had beea
    forwarded to the bankers for their acceptance. Learned counsel pointed out
G   that on December 16,1993, Transchart had fixed a fresh draft of standby letter
    of credit to the appellant and in the communication attached thereto, it was
    indicated that the draft letter of credit would be acted upon by respondent
    No. I. On this basis, Mr. Nariman submitted that a binding agreement had
    come into existence, through correspondence, and the non-signing of the
    charter party agreement dated November 11, 1993 by respondent No. I was of
H   no consequence. Mr. Nariman asserted that Clause 48 of the agreement did
      RlCKMERSVERWALTUNGGMBHv.1.0.C.LTD.[DR.A.S.ANAND,C.J.]                  49
not speak of any agreement regarding the terms of letter of credit to be           A
forwarded by State Bank of India or regarding the format and language of the
performance guarantee to be established by the appellant in favour of the fi:st
respondent, and therefore, even in the absence of an agreement about the
format of the letter of credit and of the performance guarantee, Clause 48 of
the agreement was attracted and recourse to arbitration was justified.
                                                                                   B
       Learned counsel for the respondent in reply submitted that perusal of
the correspondence exchanged between the parties established that there was
no meeting of mind between the parties and no agreement could also be spelt
out from the correspondence exchanged between the parties. Learned counsel
submitted, by reference to the documents on the record, that the                   C
correspondence exchanged between the parties, including various fax
messages, exposed that the appellant was not ready to nominate the vessel
to carry the cargo, without agreeing on the terms of the letter of credit and
the performance guarantee and that there was no letter or fax exchanged
between the parties which could in any manner indicate that any agreement
had been arrived at between the parties with regard to the terms of the            D
standby letter of credit and the performance guarantee. Since, the appellant
itself attached primary importance to the furnishing of letter of credit by the
first respondent before it could carry the cargo, submitted the learned counsel,
the "draft" Charter Party agreement dated November 11,1993 even if it had in
fact been executed between the parties, could not become enforceable because       E
the terms of letter of credit and performance guarantee had not been agreed
to between the parties.

       It would at this ~tage be relevant to extract sub-clause (a) of Clause
48 to the Charter Party. It reads thus:-
                                                                                   F
        "48(a) Freight is payable :-

        IOC will open a standby irrevocable Letter of Credit for freight amount
        of each shipment for the cargo in transit. Standby Letter of Credit will
        be issued by SBI India on SBI Germany. Freight payment will be made
        through Bank Transfer at Hamburg Germany under which 50 percent            G
        less 3.75 percent commission is payable within 7 working days against
        presentation of copy Bill of Lading and owners invoice in triplicate.
        40 percent within 7 working days of saft arrival of vessel at disport
        and on presentation of owners invoice in triplicate and I 0 percent
        within 30 days of completion of discharge and on presentation of
        owners invoice in triplicate".                                             H
    so                         SUPREME COURT REPORTS [1998] SUPP. 3 S.C.R.

A          A bare reading of Clause 48 (supra) shows that respondent No. I was
    to open a standby irrevocable letter of credit for freight amount of each
    shipment of the cargo in transit. The standby letter of credit was required to
    be is!:ued by the State Bank of India on the State Bank of Gennany. Indeed
    this clause by itself does not show '.vhether the condition of establishing a
B   standby irrevocable letter of credit or the furnishing of perfonnance guarantee
    were conditions precedent to the conclusion of contract but there is enough
    material on the record to show that they were meant to be condition precedent,.
    In this connection a reference may be made to the fax communication dated
    4.11.1993 from the appellant (much before the alleged agreement of November
    11, 1993) which reads thus :-
c          "frt-payment : I 00 pct secured by bank gtee in favour of Lina account
           at hamburg under which 50 pct less 3.75 pct commission is payable
           within seven working days against presentation of original bladings
           and Linas invoice in triplicate. 40 pct within 35 days of date of bill of
           lading I 0 pct within 60 days of date of bill of lading.
                          /
D
            (in order to avoid any dispute and documents to be furnished we have
            to relate to one finn document which is bill of lading and one finn date
            which is date of bill of lading).

            Lina to provide charters with perfonnance gtee equivalent to 5 pct of
E           freight based on appr. I 0,000 mt per shipment equivalent to usd 50,000
            finn valid till 40 pct payment is released.

            Format of bank gtee and performance bond gtee to mutually agreed.
            Specification of cargo noted however quantity now abt. 50,000 mt
            only. In case of 7 shipments quantity per shipment 7,000 mt only.
p           Kdly. advise as cargo quantity major factor for freight calculation. Pis
            Advise urgently till office opening tom. Morning here. Will reply on
            c/p-terms tom. Afternoon."

            and the fax message sent by respondent No.I. on I0.11.1993:

            "tradex new delhi I 0.11.1993 attn: mr wersich line pipes-tampico/kandla
G           received following from chrts:

            l. period - to be changed to dee 1993 to july 1994 (however everything
            else reg qtty I lots remains same)

            2. in place of bank gtee -"ioc will open a standby irrevocable lie for
H           freight amount of one shipment for the cargo in transit. Standby l/c
RICKMERSVERWALTUNGGMBH v.1.0.C.LTD. [DR.A.S.ANAND,C.J.]                 51
 will be issued by sbi India on sbi germany. Freight payment will be           A
 made through bank transfer at hamburg germany under which 50%
 less 3.75 pct commission is payable within 7 working days against
 presentation of b/l and owners invoice in triplicate. 40 pct within 7
 working days of safe arrival of vsl at disport and I 0 pct within 30 days
 of completion of discharge.
                                                                               B
 3. the ship name/details should be intimated immediately. End plse
 confirm your acceptance to above per return."

The return fax message from the appellant dated 10.11.1993 reads:

 "ref yr msg of just now:                                                      c
  I. accepted

 2. ioc will open a standby irrevocable 1/c in regard to the freight
 amount for the shipments. Funds under lie for each lot to be available
 by latest 15th of each month before nomination of the vessel by Jina.         D
 Standby lie will be issued by sbi India on sbi germany, sbi Germany
 to be authorised to reimburse themselves. In case any freight amount
 is not being received by Jina as per c/p and mentioned below, the
 amount shall be released on first written demand under standby lie
 freight payment will be made through bank transfer at hamburg
 germany:                                                                      E
  a.   50% less 3.75% commission is payable within 7 days on prersaa,
       29,90: 2 nos. copy bill of lading Lina's invoice in triplicate

  b.   40% is payable within 7 days on presentation of: arrival notice
       from master (telegram/telex/telefex)                                    p
  c.   10% is payable within 30 days on presentation of : discharge
       notice from master (telegram/telex/telefex)

  3. require urgently all detls of Ist lot (see Y' days telex) before, we
  cannot nominate the vessel. Entd comments:
                                                                               G
  in case point 2 not clear, kdly call in order to discuss the possibilities
  over phone. Tks.

  Lifting extended to 12.30 hrs german time tomorrow.

  Looking forward to hearing from you."                                        H
    52                          SUPREME COURT REPORTS [1998] SUPP. 3 S.C.R.

A   This '~orrespondence unmistakably shows that at no point of time, till the
    chartf:r party agreement was drafted on I Ith Nov. 1993 did the parties agree
    ~o proceed further without agreeing upon the format of the letter of credit and
    performance guarantee.

           Reference here may also be made to the fax message dated December
B   16, 1993, by which a fresh draft of standby letter of credit was sent by
    Transchart to the appellant. In that fax message it was indicated that the draft
    letter of credit would be acted upon by the appellant. The response of the
    appellant's agent, Lina International of the same date, however, shows that
    it was categorically asserted by it that the draft letter of credit was not
C   workable and therefore, was not acceptable,. Lina International had faxed
    draft of a fresh standby letter of credit. Subsequently, another draft of standby
    letter of credit was also faxed by Lina International but since there was no
    agreement regarding the acceptance of the draft, the appellant did not nominate
    any vessel for carrying the cargo which was required to be loaded from
    December 14, 1993 to December 21, 1993. Lina International had consistently
D   maintained in their various fax messages, that the offer made by the appellant
    was subject, inter alia, to the acceptance of the draft letter of credit. The stand
    of the appellant was thus categorical that without any agreement on the terms
    of the letter of credit, it was not ready to nominate the vessel to carry the
    cargo. The appellant was, thus, for all intent and purposes treating the
E   furnishing of the letter of credit as a condition precedent for carrying .the
    cargo. At no point of time did the appellant accept the terms of the letter of
    credit furnished by respondent No. I.

           The submission of Mr. Nariman that an agreement, even if not signed
    by the· parties, can be spelt out from correspondence exchanged between the
F   parties admits of no doubt. In fact, various judgments cited by him at the bar
    unmistakably support this assertion. The question, however, is can any
    agreement be spelt out from the correspondence between the parties in the
    instant case ?

G          In this connection the cardinal principle to remember is that it is the
    duty of the court to construe correspondence with a view to arrive at a               -4.•
    conclusion whether there was any meeting of mind between the parties, which
    could create a binding contract between them but the Court is not empowered
    to create a contract for the parties by going outside the clear language used
    in the correspondence, except insofar as there are some appropriate implications
H   of law to be drawn. Unless from the correspondence it can unequivocally and
            RICKMERS VERWALTUNGGMB H v. I.O.C. LTD. [DR. A.S.ANAND,C.J.]          53
      clearly emerge that the parties were ad idem to the terms, it cannot be said      A
      that an agreement had come into existence between them through
      correspondence. The Court is required what the parties wrote and how they
      acted and from that material to infer whether the intention as expressed in the
...   correspondence was to bring into existence a mutually binding contract. The
      intention of the parties is to be gathered only from the expressions used in      B
      the corresponde11ce and the meaning it conveys and in case it shows that
      there had been meeting of mind between the parties and they had actually
      reached an agreement, upon all material terms, then and then alone can it be
      said that a binding contract was capable of being spelt out from the
      correspondence.

              From a careful perusal of the entire correspondence on the record, we
                                                                                        c
      are of the opinion that no concluded bargain had been reached between the
      parties as the terms of the standby letter of credit and performance guarantee
      were not accepted by the respective parties. In the absence of acceptance of
      the standby letter of credit and performance guarantee by the parties, no
      enforceable agreement could be said to have come into existence. The              D
      correspondence exchanged between the parties shows that there is nothing
      expressly agreed between the parties shows that there is nothing expressly
      agreed between them and no concluded enforceable and binding agreement
      come into existence between them. Apart from the correspondence relied
      upon by the learned single Judge of the High Court, the tax messages              E
      exchanged between the parties, referred to above, go to show that the parties
      were only negotiating and had not arrived at any agreement. There is a vast
      difference between negotiating a bargain and entering into a binding contract.
      After negoti~tion of bargain in the present case, the stage never reached
      when the negotiations were completed giving rise to a binding contract. The
      learned single Judge of the High Court was, therefore, perfectly justified in     F
      holding that Clause 53 of the Charter Party relating to Arbitration had no
      existence in the eye of law, because no concluded and binding contract ever
      came into existence between the parties. The finding rec~rded by the learned
      single Judge is based on a proper appreciation of evidence on the record and
      a correct application of the legal principles. We find no merit in this appeal.   G
       It fails and is dismissed with costs.

      T.N.A.                                                      Appeal dismissed.


Search Indian case law

Ask in plain English, not just keywords. 25,000 AI words free, no card.

Try "arbitration"Sign in to search

For a digitally signed copy suitable for filing, refer to the court's own website. Only the court can issue one.