Supreme Court of India

M/S. P. MANOHAR REDDY & BROS.versusMAHARASHTRA KRISHNA VALLEY DEV. CORPN. & ORS.

Citation
2008 INSC 1482
Decided
18 December 2008
Disposal
Dismissed

Holding

The arbitration clause could not be invoked because the claim was not raised within the contractual time‑limits and the contract – and thus the arbitration agreement – had perished, rendering the trial court's appointment of an arbitrator erroneous.

Summary

The contractor, M/s P. Manohar Reddy & Bros., completed an excavation contract for the Maharashtra Krishna Valley Development Corporation, received full payment and accepted the final bill. Later it claimed extra work, but raised the claim after the contract had ended and beyond the 30‑day period prescribed in clauses 54 and 55 of the General Conditions of Contract. The respondent rejected the claim, stating the procedural deadline had expired, and refused to appoint an arbitrator. The contractor filed an application under Section 8 of the Arbitration Act, 1940; the trial court appointed a retired chief engineer as arbitrator, but the High Court set aside that appointment. The Supreme Court held that the arbitration clause could not be invoked because the claim was not raised within the contractual time‑limits and the contract – and thus the arbitration agreement – had perished. Consequently, the trial court was wrong to direct appointment of an arbitrator and the appeals were dismissed.

Issues considered

  • The claim for extra or additional work was raised after the contract had terminated and after acceptance of the final bill; does this bar invocation of the arbitration clause?
  • Did the contractor comply with the procedural requirements of clauses 54 and 55 of the General Conditions of Contract for raising a dispute?
  • Is an application under Section 8 of the Arbitration Act, 1940 maintainable where the arbitration agreement is no longer subsisting?
  • Can Section 37(4) of the Arbitration Act be invoked to extend the time‑limit for filing the arbitration application?

Legislation cited

Subjects

ArbitrationArbitration clauseContract terminationExtra work claimLimitation periodSection 8 Arbitration ActSection 37(4)Separability doctrineCivil court jurisdiction

Judgment

                         [2008] 17 S.C.R. 1217


                M/S. P. MANOHAR REDDY & BROS.                         A
                                   v.
       MAHARASHTRA KRISHNA VALLEY DEV. CORPN. &
                            ORS.
            (Civil Appeal No. 7408-7409 of 2008)
                        DECEMBER 18, 2008                             B

             [S.8. SINHA AND CYRIAC JOSEPH, JJ.]

          Arbitration Act, 1940- ss. 8, 20 and 37(4)-Appointment
     of arbitrator - Works contract - Claim for additional and extra C
     work - Rejection of claim as also appointment of arbitrator by
      Government - Trial court appointed arbitrator but High Court
     set aside the same - Correctness of - Held: Trial court not
     correct in directing appointment of arbitrator - Arbitration
     clause could not be invoked having regard to the limited
     application of clauses 37, 54, 55 of General Conditions of D
     Contract - Contractor did not raise claim for extra or additional
     work during the tenure of contract but after its completion and
     acceptance of final bill - He accepted the final bill without any
     demur - Contract came to an end and arbitration agreement
     which was part of it also perished - Jurisdiction of civil court E'
     could be invoked if disputes arising between parties was one
     to which arbitration agreement applied - More so, contractor
     did not seek extension of time uls. 37(4) and in any event no
     sufficient cause was made out.
          Respondent-government and the appellant- F
     contractor entered into a work contract. The General
"'   Conditions of Contract were specified. Clause 37
     imposed an obligation upon the contractor to furnish to
     j:xecutive Engineer a release of claims against
     Government arising out of the contract other than the
     claims_ specified, after completion of the work and prior G
     t-o payment thereof. The work was completed.
     Respondent paid the final bill prepared and the appellant
     accepted the same without any protest. As the appellant
     was asked to do extra items of work, it raised the claim
                                  1217                                H
                 1218    SUPREME COURT REPORTS             [2008] 17 S.C.R.

.··,, . ·
            "A   for the same but was rejected.Appellantissued notice·to
                 the Executive Engineer of respondent Corporation.
                 Respondent rejected the claim on the ground that the
               . stipulated period therefor expired and as such the matter
                 could not be considered for arbitration. Aggrieved,
            s appellant filed -appeal thereagainst before the
                 Superintending Engineer for arbitration but the same was
                 rejected as the contractor did not submit their claim
                 before expiry of 30 days after the defect liability period
                 nor the arbitrator was appointed.Thereafter, Chief
                 Engineer was issued notice for appointment of sole
            C arbitrator but was rejected. Appellant filed appHcation u/
                 s. 8 of the Arbitration Act, 1940 for appointment of .
                ·Arbitrator. Civil Judge appointed a retired Chief Engineer
              · ·as Arbitrator with regard to the additional and extra works
                 carried out by appellant. Respondent filed Revision
            D ··Application which was a.llowed. Review Petition
                 thereagainst was.· also dismissed. Hence the present
                 appeals.
                      Dismissing the appeals, the Court
                      HELD:1.1. As arbitration clause could not be invoked
            E having regard to the limited application of clauses 37, 54
                and 55 of the General Conditions of the Contract, the trial
                court was not correct in directing appointment of
                arbitrator. [Para 28] [1237-F]
                      1.2. The arbitration agreement is contained in a
            F commercial document. It must be interpreted having
                regard to the language used in it. A bare perusal of
                clauses 37, 54 and 55 of the General Conditions of
                Contract clearly shows that the arbitration agreement
                entered into by and between the parties is not of wide
            G amplitude. In a case where arbitration clause is of wide
               .amplitude, the same may cover also the claims arising
                during the tenure of contract or thereafter, provided the
                arbitration clause subsists. Clause 37 imposes an
                obligation upon the contractor to furnish to the Executive
            H Engineer a release of claims against the Government
                                                                               ->.
             P. MANOHAR REDDY & BROS. v. MAHARASHTRA 1219
                 KRISHNA VALLEY DEV. CORPN. & ORS.

          arising out of the contract other than the claims A
          specifically identified, evaluated and expected from the
          operation of the release by the Contractor only after
          completion of the work and prior to payment thereof.
          [Paras 15 and 16] [1230-D-F]
               1.3. There is nothing on record to show that any claim B
          in relation to extra or additional work had been raised by
          the contractor prior to 27.2.1991 although final
          measurement had been recorded on 26.11.1990 and the
          bill was paid in full and final satisfaction on 4.12.1990.
          Clauses 54 and 55 of the arbitration agreement must be
          read together. The contract has been entered into for
                                                                        c
          works costing less than Rs. 50 lakhs and, thus, clause
          54 would be attracted in the instant case. In terms of the
          said provision, the contractor has to raise a demand with
          the Executive Engineer if any work is demanded from
          him, which he considers to be outside the requirements D
          of the contract. The word 'consider' is of some
          significance, it means "to think over; to regard as or deem
    )T    to be." [Paras 16 and 17] [1230-G-H; 1231-A-B]
               Advanced Law, Lexicon 3rd Edition 2005, referred to.
               1.4. If a work has to be carried out outside the terms E
          of the contract and is unacceptable, he is required to
          promptly approach the Executive Engineer in writing for
          obtaining his written instruction or decision in that behalf.
          The Executive Engineer is obligated to give his written
          instructions or decision within a period of 30 days of F
'         making such request. Once such instruction or decision
     ~   is received, the contractor is required to comply
         therewith. Only in a case where the Executive Engineer
         fails and/or neglects to give a decision or issue
         instruction, the contractor may within a period of 30 days
         thereafter prefer an appeal to the appellate authority. The G
         appellate authority is required to provide an opportunity
         of hearing to the contractor. It is only when the contractor
    ~    is dissatisfied with the decision of the appellate authority,
         he may indicate his intention to refer the dispute to
         Arbitration in terms of clause 55 within a period of 30 days H
    1220       SUPREME COURT REPORTS               [20_08] 17 S.C.R.


A    from the date of receipt of the said decision, failing which,
     the same would be final. The arbitration clause could be
     invoked only in a case where the decision has not                 \
                                                                       ',.-
     become final and conclusive as per clause 54. A plain                         -
     reading of the provisions clearly shows that clause 54
B    does not envisage raising of a claim in respect of extra
     or additional work after the completion of contract. [Paras
     18, 19 and 20] [1231-8-E-F]
          1.5. The jurisdiction of the civil court under s. 8 of the
    Act or under s. 20 thereof can be invoked if the disputes          -i.
    and differences arising between the parties was the one
c   to which the arbitration agreement applied. [Para 21]
     [1231-G]
         1.6. The contractual clause provides for a limitation
    for the purpose of raising a claim having regard to the
    provisions of Section 28 of the Contract Act. The period
D   of limitation as prescribed under Article 137 of the
    Limitation Act would be applicable, but a clause providing
    for limitation so as to enable a party to lodge his claim
    with the other side is not invalid. [Para 22] [1231-H; 1232-           i>...
    A]
E        1. 7. It is not a case ,where an application under
    Section 8 could not be filed within a period of 3 years. It
    is a case where a determination was necessary as
    regards invocation of the disputes settlement processes.
    For resolution of the dispute, a claim must be made in
F   terms of the provisions of the contract for the purpose
    of giving effect to the arbitration clause; the application                    ('


    thereof being limited in nature. [Para 23] [1233-H; 1234-          ~
    A]                                                    .
         1.8. An arbitration clause is a part of the contract. It
G   being a collateral term need not, in all situations, perish
    with coming to an end of the contract. It may survive. This
    concept of separability of the arbitration clause is now
    widely accepted. :J"he Indian law-The Arbitration and
    Conciliation Act, 1996, which is based on the UNCITRAL             1-
    Model Law, also explicitly adopts the doctrine of
H   separability in Article 16(1 ). [Para 26] [1235-0-E]
                      P. MANOHAR REDDY & BROS. v. MAHARASHTRA           1221
                          KRISHNA VALLEY DEV. CORPN. & ORS.

                      1.9. It is also not a case where sub-section (4) of A
                  Section 37 of the Act could be invoked. Appellant.did not
                  invoke Section 37(4) of the Act. No reason has been
                  assigned as to why the said discretion of the court should
                  be invoked particularly when the claim has been raised
                  only after completion of the work. [Para 31) [1238-F]      8
                      Mis Bharat Heavy Electricals Limited, Ranipur vs. Mis
                  Amar Nath Bhan Prakash (1982) 1 SCC 625, Held
                  inapplicable.
     ~
                        The Vulcan Insurance Co. Ltd. vs. Maharaj Singh and
                  Anr. AIR 1976 SC 287; Laminart Pvt. Ltd. v& A.P. Agencies, c
                  Salem AIR 1989 SC 1239; Damodar Valley Corporation vs.
                  K.K. Kar 1974 (1) SCC 141; S.C. Konda Reddy vs. Union of
                  India and Anr. AIR 1982 KARNATAKA 50; Bharat Coking
                  Coal Ltd. vs. Annapurna Construction (2003) 8 SCC 154;
                  Chairman and MD NTPC Ltd. vs. Reshmi Constructions D
                  Builders and Contractors (2004) 2 SCC 663; Wild Life
                  Institute of India, Dehradun vs. Vijay Kumar Garg (1997) 10
                  SCC 528 and Mis K. Ramaiah and Company vs. Chairman
                  and Managing Director, National Thermal Power Corpn. 1994
                  Supp. (3) SCC 126, referred to.
                                                                                E
                       Scott vs. Avery (1856) 25 LJ ex 308; Heyman v. Darwins
                  Ltd. (1942) 1 All ER 337; Buckeye Check Cashing Inc. v.
                  Cardegna 546 US 460; Prima Paint Corp. v. Flood and
                  Conklin Mfg. Co. 388 U. S. 395 and Southland Corp. v.

..   ~
         ""-~~·
                  Keating 465 U. S. 1, referred to.

                      AIR 1976 SC 287
                                      Case Law Reference:
                                                 Referred to.       Para 22
                                                                                F


                      (1856) 25 L-J Ex 308       Referred to.       Para 22
                      AIR 1989 SC 1239           Referred to.       Para 22
                      1974 (1) sec 141           Referred to.       Para 24     G
                      (1942) 1 All ER 337        Referred to.       Para 24
                      AIR 1982 KARNATAKA 50 Referred to.            Para 24
              i       546 us 460                 Referred to.       Para 26
                      388 U.S. 395               Referred to.       Para 26
                                                                                H
+                     465 U.S. 1                 Referred to.       Para 26
     1222       SUPREME COURT REPORTS                [200~] 17 S.C.R.



A     (1982) 1 sec 625        Referred to.   Para 26
      (2003) 8 sec 154        Referred to.   Para 26
                                                                          \.r>
      (2004) 2 sec 663        Referred to.   Para 27                             -
      (1997) 10 sec 528       Referred to.   Para 29
      1994 Supp. (3) sec 126  Referred to.   Para 30
B
      CIVIL APPELLATE JURISDICTION : Civil Appeal No.
  7408-7409 of 2008.
          From the final Judgment and Order dated 13.4.2004 and
     8.9.2004 of the High Court of Judicature of Bombay, Bench at
c    Aurangabad in C.R.A. No. 201 of 1998 and Review Petition
     No. 7232 of 2004 in C.R.A. No. 201 of 1998 respectively.
            R. Sundravaradan and G.N. Reddy for the Appellant.
         Aprajita Singh and Ravindra Keshavrao Adsure for the
     Respondents.
D          The Judgment of the Court was delivered by
           S.B. SINHA, J.1. Leave granted.
           2. Respondent herein invited tenders for the work of
     excavation in canal K.M. No. 126, Kukadi Left Bank Canal,             "'•
     Shrigonda in the District of Ahmednagar at an estimated costs
'E
     of Rs.23,26,424/- pursuant whereto appellant herein submitted
     its offer. for a sum of Rs.21, 10,233/-. The said offer being the
     lowest was accepted.·
            3. The parties hereto thereafter entered into a contact on
F
                 /

     9 .2 .1988; clauses 3 7, 54 and 55 whereof read as under:
            "37. After completion of work and prior to that payment,
            the contractor shall furnish to the Executive Engineer, a       ~
                                                                                 .
            release of claim_s against the Government arising out of
          . the contra.ct, other than claims specifically identified,                (
            evaiuated and expected from the operation of the release
G
            by the, 9ontractor."                                                     -.
      I
           54. Settlement of Dispute (For works costing less than Rs. ·
           50 lakhs).                                                        ~
          If the contractor considers any work demanded of him to
H         be outside the requirements of the contract, or considers


                                                                                     IF-
                                                                                     .Ii
              P. MANOHAR REDDY & BROS. v. MAHARASHTRA          1223
            KRISHNA VALLEY DEV. CORPN. & ORS. [S.8. SINHA, J.]
                any drawings, record or ruling of the Executive Engineer, A
                KIP Dn. No. VII, Shrigonda on any matter in connection with
                or arising out of the contract or the carrying out of work to
    -I          be outside the terms of contract and hence unacceptable
                he shall promptly ask the Executive Engineer, in writing,
                for written instructions or decision. Thereupon the 8
                Executive Engineer, shall give his written instructions or
                decision within a period of 30 days of such request.
                Upon receipt of the written instructions or decision the
                contractor shall promptly proceed without delay to comply
                with such instructions or decision.                             c
                If the Executive Engineer fails to give his decision in writing
                within a period of 30 days after being requested, or if the
                contractor is dissatisfied with the instructions or decision
                of the Executive Engineer, the contractor may within 30
                days after receiving the instructions or decision appeal to D
                upward authority who shall afford an opportunity to the
}
                contractor to be heard and to offer evidence in support of
                his appeal.
                If the contractor is dissatisfied with this decision, the
    """         contractor within a period of thirty days from receipt of the   E
                decision shall indicate his intention to refer the dispute to
                Arbitration as per clause 55 fqiling which the said decision
                shall be final and conclusive.
                55. Arbitration (For works costing less than Rs. 50 lakhs)
                All the disputes or differences in respect of which the         F
                decision has not been final and conclusive as per clause
     '.)_       54 above shall be referred for arbitration to a sole
                arbitrator appointed as follows.
                Within 30 days of receipt of notice from the contractor or
                his intention to refer the dispute to arbitration the Chief G
                Engineer (SP Irrigation Department}, Pune shall send to
                the contractor a list of three· officers of the rank of
                Superintending Engineers or higher, who have not been
    ~           connected with the work_ under this contract. The contractor
                shall within 15 days of-receipt of this list select and
                                                                             H
I
             P. MANOHAR REDDY & BROS. v. MAHARASHTRA          1225
           KRISHNA VALLEY DEV. CORPN. & ORS. [S.S. SINHA, J.]

           Final bill prepared and paid by the respondent was accepted           A
           by the appellant without any demur.
   -~          5. Inter alia, on the premise that appellant was asked to
           do extra items of work, it raised its claims by a letter dated
           27.2.1991, which was rejected.
                Details of the purported extra work done by appellant, B
           however, were not mentioned in the said letter dated 27.2.1991.
           It submitted another claim giving details thereof by a letter
           dated 10.6.1991.
      J.
                6. Appellant by a letter dated 26.9.1991 purporting to
           invoke clause 54 of the General Conditions of Contract, issued        c
           notice to the Executive Engineer of respondent, stating:
                "Whereas a number of claims were referred to you from
                time to time and in respect of many of them you have failed
                to give the decision. And whereas the work under contract
                was kept in progress·by us in good faith and with a belief D
                that on completion of the work you will reconsider our total
                case and settle our accounts with all the claims:
.......
                      And whereas the work has been duly completed by
                us, we are now in a petition (sic) of finally work out in full
                the sum of money due and payable to us by the department         E
                including all the claims.
                      Now therefore, we hereby call upon you and give you
               notice finally under clause 54 of the General conditions of
               contract with a request to settle our accounts and give your
               decisions in respect of our following claims and disputes         F
               within a period of thirty days from the date of receipt of this
  ->           notice by reconsidering your earlier decision in respect of
               claim on which you had indicated your decision earlier."
           He specified 16 claims thereunder.
                                                                                 G,
                7. Respondent rejected the said claim by its letter dated
           5.10.1991 alleging that the stipulated period therefor expired
           in May, 1991. The Executive Engineer of the respondent by his
-'i        letter dated 29.10.1991 opined tnat the matter cannot be
           considered f6r arbitration, stating:
                                                                                 H
    1226       SUPREME COURT REPORTS                    [2008]-17 S.C.R.


A        "Please refer your letter under reference which was
                                                                                         r-
       . received by this office in the 1st week of October 1991.
         The claims raised were already denied by this Office vide
         letter No. 448 dtd. 29.4.91. As you have referred the matter
         under the provisions of clause 54 of the L.C.B. No. 18 for
B        87, 88, The decisions of this office are again sent herewith.
         It is further clarified that the matter is brought for arbitration
         process after expiry of 30 days from end of defect liability
         period. The work was completed in November-90 and the
         defect liability period of six months is over in May 1991,           J..
         hence the matter cannot be considered for arbitration."
c
         However,. its earlier decision of rejecting the claim was
         repeated.
         8. Treating the same to be an order rejecting his claim,
    appellant herein preferred an appeal thereagainst before the
0   Superintending Engineer in terms of its letter dated 26.11.1991;
    pursuant whereto a meeting was held between the
    representatives. of the parties; the minutes whereof read as
    under:
        "Since· the contractors have not submitted their claims
E       under clause 54 of the General conditions of the contract
        along with documentary evidences within the stipulated
        period i.e. before the expiry of 30 days after defect liability
        period and as per clause 55 which states 'Neither party is
        entitled to bring a claim to arbitrator if the arbitrator has
        not been appointed before the expiration of 30 days after
F       defect liability period.'
              Defect liability period of this contract expired on 31st
        May 1991 and the stipulated period of 30 days expired on
        30th June 1991.
             Hence the contractor's appeal for arbitration is
G
        hereby rejected"
         9. A copy of the said minutes of the meeting was sent by
    the Superintending Engineer along with his letter dated                         ~-
    30 .12 .1991 .
H       A notice, on the premise that disputes and differences
       P. MANOHAR REDDY & BROS. v. MAHARASHTRA          1227
     KRISHNA VALLEY DEV. CORPN. & ORS. [S.S. SINHA, J.]
     arose between the parties within the meaning of clause 55 of A
     the General Conditions of Contract, was served upon the Chief
     Engineer asking him to furnish the names of its three officers
     for appointment of sole arbitrator within 30 days from the receipt
     thereof. The said request was rejected by the Chief Engineer
     in terms of his letter dated 26.2.1992, stating:                       B
          "You have given notice under clause 54 on 26/11/91 to refer
          the dispute to arbitration. Thus the notice under clause 54
          is given after the expiry of 30 days of defect liability period .
.[
                 Thus you have not submitted the claims within the
          stipulated time and followed the procedure as per the             c
          clause 54 of general condition for settlement of dispute.
          This has already been informed to you by the
          Superintending Engineer Kukadi canal circle, Pune-6
          under his letter no. KCC/PB-1/KM 126/Claims/4129 dt. 30/
          12/91.                                                     D
                 Hence the question of appointing arbitrator by this
          office does not arise."
          10. Appellant thereafter sent a list of arbitrators on 9.3.1992
     followed by a notice through a lawyer.
         Indisputably, the said request for referring the disputes to       E
     an arbitrator was rejected by respondent.
          11. Appellant filed an application under Section 8 of the
     Arbitration Act, 1940 (for short, "the Act") in the Court of Civil
     Judge (Senior Division), Ahmednagar at Ahmednagar for
     appointment of Arbitrator.                                             F
-)         By reason of a judgment and order dated 9.12.1997, the
     Civil Judge Senior Division, Ahmednagar opining that the said
     application having been filed within the period as specified in
     Article 137 of the Limitation Act, 1963 and the cause of action
     therefor having arisen on 29.10.1991 on which date the G
     appellant's claim was rejected, appointed one Shri V.M. Bedse,
     a retired Chief Engineer as Arbitrator with regard to the
     additional and extra works allegedly carried out by appellant.
         The learned judge held:
                                                                            H
    1228     SUPREME COURT REPORTS                  (2008] 17 S.C.R.


A       "The petitioner along with Exh. 19 has produced various
        documents and correspondence ensued with the
        respondents. It is crystal clear from this correspondence
        that the petitioner had demanded release of claim on 27/
        2/91 under clause No. 37 of the contract agreement. This
B       claim letter was received by the respondents and further
        query in respect of proof of claim was called for..by the
        respondents by their letter dated 29/4/91. Accordingly, the
        proof was submitted by letter dated 10/6/91 and details
        of claim were given on 26/9/91. The petitioner also                J.
        apprised about 'settlement of dispute' as contemplated in
c       clause No. 54 of the contract agreement. Therefore
        practically there is compliance by the petitioner as
        contemplated under clause No. 54 of the contract
        agreement. The record also reveals that the respondents
        on 5/10/91 i.e. after lapse of three months replied the
D       notice of petitioner dated 10/6/91 and first time it was
       agitated that the petitioner has not taken steps under
       clause No. 55 under defect liability and before expiration
       of 30 days. The clause No. 19(a) of the contract agreement
       is in respect of material and workmanship and it defines
E      the defect liability in respect of workmanship and materials
       and so also the defect liability period is to be counted from
       the certified date of completion certificate. Under clause
       No. 26 of the contract agreement, it is the respondents who
       are required to issue such certificate to the petitioner. The
       notices were issued by the petitioner under clause Nos.
F      54 and 55 of the contract but it appears from the record
       that the respondents did not take any steps to choose their
       arbitrator. On the contrary, on 9/3/92 the list of three officers
       was demanded and out of them sole arbitrator was chosen
       but the respondents have not replied the same. In this
G      manner, the petitioner and respondents could not concur
       for appointment of arbitrator and the petitioner had
       therefore no alternative but to resort to provisions of
       Section 8 of the Arbitration Act. The correspondence ·
       produced on record in support of claim under Section 8
H      of the Arbitration Act by the petitioner is sufficient to come
       P. MANOHAR REDDY & BROS. v. MAHARASHTRA          1229
     KRISHNA VALLEY DEV. CORPN. & ORS. [S.B. SINHA, J.]

         to the conclusion that there was dispute between petitioner A
         and the respondents in respect of additional work and no
         such steps have been taken by the respondents as
         provided under the Contract."
          12. A Civil Revision Application No. 201 of 1998 was
     preferred thereagainst by the respondent before the High Court,     B
     which by reason of the impugned judgment and order dated
     13.4.2004 has been allowed. A Review Petition filed by
     appellant thereagainst has been dismissed.
         13. Mr. Sundaravaradan, learned Senior Counsel
     appearing on behalf of appellant raised the following               c
     contentions in support of the appeal.
          i.     The High Court committed a serious error of law in
                 passing the impugned judgment insofar as it failed
                 to take into consideration that limitation for raising
                 a claim as envisaged under clause 54 is not 0
                 applicable in the instant case.
          ii.    In view of the fact that the claim was rejected only
                 on 26.2.1992 by the appellate authority, the period
                 of 30 days should be counted therefrom.
          iii.   While exercising its jurisdiction under Section 8 of .E
                 the Act, the court was concerned only with the
                 question as to whether there was a triable issue.
          iv.    Once a triable issue is found to have been raised,
                 which was required to be referred to the arbitration,
                 the merit of the claim cannot be gone into.             F
         14. Ms. Aprajita Singh, learned counsel appearing on
-)
     behalf of the respondent, on the other hand, would urge:
          i.     Clause 54 of the General Conditions of the
                 Contract must be invoked by the contractor during
                                                                    G
                 the tenure thereof and not after completion of the
                 contract and acceptance of the final bill.
          ii.    The final bill having been accepted without any
                 demur, the contract came to an end, wherewith the
                 arbitration agreement which was a part thereof also
                                                                         H
    1230           SUPREME COURT REPORTS               [2008] 17 S.C.R.


A                   perished.
            iii.    Appellant having not sought for extension of time in
                    terms of sub-Section (4) of Section 37 of the Act
                    and in any event no sufficient cause having been
                    made out therefor, even no extension of time could
B                   be granted.
           15. Indisputably, the parties are governed by the Act.
         'Arbitration Agreement' has been defined in Section 2(a)
    of the Act to mean a written agreement to submit present or
    future differences to arbitration, whether an arbitrator is named
C   therein or not.             '
        An arbitration is a private dispute resolution mechanism
  agreed upon by the parties. The arbitration agreement is
  contained in a commercial document; it must be interpreted
  having regard to the language used in it. A bare perusal of
D clauses 37, 54 and 55 of the General Conditions of Contract
  clearly shows that the arbitration agreement entered into by and
  between the parties is not of wide amplitude. In a case where
  arbitration clause is of wide amplitude, the same may cover also         -A...
  the claims arising during the tenure of contract or thereafter,
E provided the arbitration clause subsists.
          16. Clause 37 imposes an obligation upon the contractor
    to furnish to the Executive Engineer a release of claims against
    the Government arising out of the contract other than the claims
    specifically identified, evaluated and expected from the
F   operation of the release by the Contractor only after completion
    of the work and prior to payment thereof.
       There is nothing on record to show that any claim in relation
  to extra or additional work had been raised by the contractor
  prior to 27.2.1991 although final measurement had been
G recorded' on 26.11.1990 and the bill has been paid in full and
  final satisfaction on 4.12.1990. Clauses 54 and 55 of the
  arbitration agreement must be read together.
       17. Indisputably, the contract has been entered into for
  works costing less than Rs. 50 lakhs and, thus, clause 54 wo~ld
H be attracted in the instant case. In terms of the said provision,
                 P. MANOHAR REDDY & BROS. v. MAHARASHTRA          1231
               KRISHNA VALLEY DEV. CORPN. & ORS. [S.B. SINHA, J.]

               the contractor has to raise a demand with the Executive A
               Engineer if any work is demanded from him, which he
...........;   considers to be outside the requirements of the contract. The
               word 'consider' is of some significa.nce, it means "to think over;
               to regard as or deem to be." (See Advanced Law Lexicon.3rd
               Edition, 2005).                                                     B
                     18. If a work has to be carried out outside the terms of the
               contract and is unacceptable, he is required to promptly
               approach the Executive Engineer in writing for obtaining his
               written instruction or decision in that behalf. The Executive
               Engineer is obligated to give his written instructions or decision C
               within a period of 30 days of making such request. Once such
               instruction or decision is received, the contractor is required
               to comply therewith. Only in a case where the Executive
               Engineer fails and/or neglects to give a decision or Issue
               instruction, the contractor may within a period of 30 days
               thereafter prefer an appeal to the appellate authority. The D
               appellate authority is required to provide an opportunity of
               hearing to the contractor. It is only when the contractor is
.,,),          dissatisfied with the decision of the appellate authority, he may
               indicate his intention to refer the dispute to Arbitration in terms
               of clause 55 within a period of 30 days from the date of receipt E
               of the said decision, failing which, the same would be final.
                     19. The arbitration clause, thus, could be invoked only in
               a case where the decision has not become final and conclusive
               as per clause 54.
                    20. A plain reading of the aforementioned provisions           F
               clearly shows that clause 54 does not envisage raising of a
               claim in respect of extra or additional work after the completion
               of contract.   /
                    21. The jurisdiction of the civil court under Section 8 of the
               Act or under Section 20 thereof can be invoked if the disputes G
               and differences arising between the parties was the one to
               which the arbitration agreement applied.
    J               22. The contractual clause provides for a limitation for the
               purpose of raising a claim having regard to the provisions of
               Section 28 of the Indian Contract Act. It is no doubt true that H
        1232      SUPREME COURT REPORTS                      [2008] 17 S.C.R.
0

    A the period of limitation as prescribed under Article 137 of the
      Limitation Act would be applicable, but it is well settled that a
      clause providing for limitation so as to enable a party to lodge
      his claim with the other side is not invalid.
           In The Vulcan Insurance Co. Ltd. vs. Maharaj Singh and
    B anr. reported in AIR 1976 SC 287, the arbitration clause read
      as under:
            "18. If any difference arises as to the amount of any loss
            or damage such difference shall independently of all other
            questions be referred to the decision of an Arbitrator, to
    c       be appointed in writing by the parties in difference, or, if
            they cannot agree upon a single Arbitrator to· the decision
            of two disinterested persons as Arbitrators .................. .
            .... . .. ..... ...... .... And it is hereby expressly stipulated and
            declared that it shall be a condition precedent to any right
            of action or suit upon this policy that the award by such
    D
            arbitrptor, arbitrators or Umpire of the amount of the loss
            or damage if disputed shall be first obtained.
            19. In no case whatever shall the company be liable for any
            loss or damage after the expiration of twelve months from
            the happening of the loss or damage unless the claim is
    E
            the subject of pending action or arbitration."
            Referring to the well known decision of Scott vs. Avery,
                               =
        (1856) 25 LJ Ex 308 5 HLC 811, and noticing different views
        expressed by different courts, it was held:
    F       "22. The two lines of cases clearly bear out the two distinct
            situations in law. A clause like the one in Scott v. Avery
            bars any action or suit if commenced for determination of
            a dispute covered by the arbitration clause. But if on the
            other hand a dispute cropped up at the very outset which
            cannot be referred to arbitration as being not covered by
    G
            the clause, then the Scott v. Avery clause is rendered
            inoperative and cannot be pleaded as a bar to the
            maintainability of the legal action or suit for determination
            of the dispute which was outside the arbitration clause."
            Whether such a clause comes within the purview of the
    H
       P. MANOHAR REDDY & BROS. v. MAHARASHTRA          1233
     KRISHNA VALLEY DEV. CORPN. & ORS. [S.B. SINHA, J.]

     arbitration clause, vis-a-vis Article 137 of the Limitation Act, it A
     was held:
          "... It has been repeatedly held that such a clause is not hit
          by Section 28 of the Contract Act and is valid; vide-The
          Baroda Spinning and Weaving Co. Ltd. v. The Satyar
          narayan Marine and Fire Insurance Co. Ltd. ILR 38 Born B
          344: AIR 1914 Born 225 (2); Dawood TarMahomed Bros . .
          v. Queensland Insurance Co. Ltd. AIR 1949 Cal 390 and
          The Ruby General Insurance Co. Ltd. v. The Bharat Bank
          Ltd. AIR 1950 (East) Punj 352. Clause 19 has not
          prescribed a period of 12 months for the filing of an C
          application under Section 20 of the Act. There was no
          limitation prescribed for the filing of such an application  1




          under the Indian limitation Act, 1908 or the limitation Act,
          1963. Article 181 of the former did not govern such an
          application. The period of three years prescribed in Article
          137 of the Act of 1963 may be applicable to an applicatiori D
          under Section 20."
          Whether the difference which arose between the parties
     was the one to which the arbitration clause applied and whether
     the application under Section 20 of the Act could be dismissed,
     this Court opined:                                              E
           "24. But in this case on a careful consideration of the
           matter we have come to the definite conclusion that the
           difference which arose between the parties on the
           company's repudiation of the claim made by respondent
..         No. 1 was not one to which the arbitration clause applied F
           and hence t~e arbitration agreement could not be filed and
           no arbitrator could be appointed under Section 20 of the
           Act. Respondent No. 1 was ill-advised to commence an
           action under Section 20 instead of instituting a suit within
         · three months of the date of repudiation to establish the .G
           company's liability."
         (See also A.B.C. Laminart Pvt. Ltd. vs. A.P. Agencies,
     Salem [AIR 1989 SC 1239)
          23. It is not a case where an application under Section 8
     could not be filed within a period of 3 years. It is a case where H
    1234       SUPREME COURT REPORTS                 [2008] 17 S.C.R.


A a determination was necessary as regards invocation of the
  disputes settlement processes. For resolution of the dispute,
  a claim must be made in terms of the provisions of the contract         -1---
  for the purpose of giving effect to the arbitration clause; the
  application thereof being limited in nature.
B         24. Mr. Sundaravaradan has taken us through a large
    number of decisions to contend that the purported 'accord and
    satisfaction' on the part of the contractor might not itself be a
    sufficient ground to reject a prayer for making a reference under
    the Arbitration Act.                                                  J,,
c       Such a question came up for consideration before this
    Court in Damodar Valley Corporation vs. K.K. Kar [(1974) 1
    SCC 141), wherein this Court noticing the decision of Heyman
    v. Darwins Ltd. (1942) 1 All ER 337, stated the law thus:
       "Again, an admittedly binding contract containing a general
D      arbitration clause may stipulate that in certain events the
       contract shall come to an end. If a question arises whether
       the contract has for any such reason come to an end I can
       see no reason why the arbitrator should not decide that                         »
                                                                           ->'-...,
       question. It is clear, too, that the parties to a contract may
       agree to bring it to an end to all intents and purposes and
E
       to treat it as if it had never existed. In such a case, if there
       be an arbitration clause in the contract, it perishes with the
       contract. If the parties substitute a new contract for the
       contract which they have abrogated the arbitration clause
       in the abrogated contract cannot be invoked for the
F      determination of questions under the new agreement. All
       this is more or less elementary."
                                                                                      .
                                                                           ....t-·
  It was furthermore held:
       "Similarly the question whether there has been a settlement
       of all the claims arising in connection with the contract also
G
       postulates the existence of the contract. The principle laid
       down by Sarkar. J., in Kishorilal Gupta Bros's case [1960)
       1 S.C.R. 493 that accord and satisfaction does not put an
                                                                              ~-
       end to the arbitration clause was not dissented to by the
       majority. On the other hand proposition (6)seems to lend
H                                                                                     ..{
             P. MANOHAR REDDY & BROS. v. MAHARASHTRA          1235
           KRISHNA VALLEY DEV. CORPN. & ORS. [S.B. SINHA, J.]

                weight to the views of Sarkar, J. In these circumstances,         A
                the question whether the termination was valid or not and
                whether damages are recoverable for such wrongful
     ~-+
                termination does not affect the arbitration clause, or the
                right of the respondent to invoke it for appointment of an
                arbitrator."
                                                                                  B
               {See also S. C. Konda Reddy vs. Union of India & ·anr.
           [AIR 1982 KARNATAKA 50)}
                25. We are, however, in this case faced with a different
      J.   situation. The contention of respondent is not that there has
           been a breach of contract and the contract still subsists. Its         c
           contention is that in terms of the contract the claim for extra work
           or additional work should have been raised during the tenure
           of the contract itself and not after it came to an end and
           payment received in full and final satisfaction.
                26. An arbitration clause, as is well known, is a part of the . D
           contract. It being a collateral term need not, in all situations,
           perish with coming to an end of the contract. It may survive. This
           concept of separability of the arbitration clause is now widely
           accepted. In line with this thinking, the UNCITRAL Model Law
           on International Commercial Arbitration incorporates the
           doctrine of separability in Article 16(1). The Indian law - The E
           Arbitration and Conciliation Act, 1996, which is based on the
           UNCITRAL Model Law, also explicitly adopts this approach in
           Article 16(1)(b), which reads as under:-
                "16. Competence of arbitral tribunal to rule on its
                                                                                  F
..             jurisdictional. - (1) The arbitral tribunal may rule on its own
               jurisdiction, including ruling on any objections with respect
      -)
               to the existence or validity of the arbitration agreement, and
               for that purpose, -
               (a) An arbitration clause which forms part of a contract
               shall be treated as an agreement independent of the other G
               terms of the contract; and
               (b) A decision by the arbitral tribunal that the contract is
      j        null and void shall not entail ipso jure the invalidity of the
               arbitration clause."
                                                     (Emphasis supplied).         H
     1236      SUPREME COURT REPORTS                [2008] 17 S.C.R.


A          Modem laws on arbitration confirm the concept. The United
    States Supreme Court in the recent judgment in Buckeye
    Check Cashing, Inc. v. Cardegna (546 US 460)
    acknowledged that the separability rule permits a court "to
    enforce an arbitration agreement in a contract that the arbitrator
    later finds to be void." The Court, referring to its earlier
  8
·   judgments in Prima Paint Corp. v. Flood & Conklin Mfg. Co.,
    (388 U. S. 395), and Southland Corp. v. Keating, (465 U. S.
     1), inter alia, held :-
         "Prima Paint and Southland answer the question
         presented here by establishing three propositions. First,
c        as a matter of substantive federal arbitration law, an
         arbitration provision is severable from the remainder of the
         contract."
          But this must be distinguished from the situ~tion where the
     claim itself was to be raised during the subsistence of a
 0
     contract so as to invoke the arbitration agreement would not
     apply.
        Mis Bharat Heavy Electricals Limited, Ranipur vs. Mis
  Amar Nath Bhan Prakash (1982) 1 SCC 625, whereupon
E reliance has been placed by Mr. Sundaravaradan is not
  applicable as it was held therein that the question whether there
  was discharge of the contract by accord and satisfaction or not,
  is itself arbitrable.
      The said question need not detain us having been
F considered by this Court in Bharat Coking Coal Ltd. vs.
  Annapurna Construction [(2003) 8 SCC 154] holding:
         "14. The question is as to whether the claim of the
         contractor is de hors the rules or not was a matter which
         fell for consideration before the arbitrator. He was bound
         to consider the same. The jurisdiction of the arbitrator in
G
         such a matter must be held to be confined to the four-
         corners of the contract. He could not have ignored an
         important clause in the agreement; although it may be open
         to the arbitrator to arrive at a finding on the materials on
         records that the claimant's claim for additional work was
H
               P. MANOHAR REDDY & BROS. v. MAHARASHTRA          1237
             KRISHNA VALLEY DEV. CORPN. & ORS. [S.B. SINHA, J.]

                  otherwise justified."                                               A
     ~           27. In Chairman and MD, NTPC Ltd. vs. Reshmi
             Constructions, Builders & Contractors [(2004) 2 SCC 663), this
             Court held:
                   "18. Normally, an accord and satisfaction by itself would
                   not affect the arbitration clause but if the dispute is that the   B
                   contract itself does not subsist, the question of invoking the
,,                 arbitration clause may not arise. But in the event it be held
      :;)_         that the contract survives, recourse to the arbitration clause
                   may be taken. [See Union of India v. Kishorilal Gupta (AIR
                   1959 SC 1362) and Naihati Jute Mills Ltd. v. Khya/iram             c
                 . Jagannath (AIR 1968 SC 522)."
             It was furthermore opined
                  "28. Further, necessitas non habet legem is an age-old
                  maxim which means necessity knows no law. A person .
                  may sometimes have to succumb to the pressure of the D
                  other party to the bargain who is in a stronger position.
     ,.>--        29. We may, however, hasten to add that such a case has
                  to be made out and proved before the Arbitrator for
                  obtaining an award.
                                                                                      E
                  30. At this stage, the Court, however, will only be concerned
                  with the question whether trial issues have been raised
                  which are required to be determined by the Arbitrators."
                  28. We, however, as noticed hereinbefore, are concerned
             with a different fact situation. As arbitration clause could not be
             invoked having regard to the limited application of clauses 37,,
                                                                                 F
      -~     54 and 55 of the General Conditions of the Contract, we are
             of the opinion that the trial court was not correct in directing
             appointment of an arbitrator.
                  29. We may notice that in Wild Life Institute of India,
             Dehradun vs. Vijay Kumar Garg [(1997) 10 SCC 528), a                     G
             Division Bench of this Court held as under:
                 "It is also necessary to refer to the arbitration clause under
                 the contract which clearly provides that if the contractor
                 does not make any demand for arbitration in respect of
                                                                                      H
     1238        SUPREME COURT REPORTS                  [2008] 17 S.C.R.


A           any claim in writing within 90 days of receiving the
            intimation from the appellants that the bill is ready for
                                                                             ~
            payment, the claim of the contractor will be deemed to have
            been waived and absolutely barred and the appellants
            shall be discharged and released of all liabilities under the
            contract in respect of these claims. The liability, therefore,
B
            of the appellants cease if no claim of the contractor is
            received within 90 days of receipt by the contractor of an
            intimation that the bill is ready for payment. This clause
            operates to discharge the liability of the appellants on         .,l
            expiry of 90 days as set out therein and is not merely a
c           clause providing a period of limitation. In the present case,
            the contractor has not made any claim within 90 days of
            even receipt of the amount under the final bill. The dispute
            has been raised for the first time by the contractor 10
            months after the receipt of the amount under the final bill."
D      30. The High Court has relied upon a decision of this Court
  in Mis K. Ramaiah and Company Vs. Chairman & Managing
  Director, National Thermal Power Corpn. [1994 Supp. (3) SCC
  126]. We need not deal therewith in details as the effect thereof
  has been considered by us in Bharat Coking Coal Ltd. vs.
E Annapurna Construction (supra).                                                  ;,

       31. It is also not a case where sub-section {4) of Section
  37 of the Act could be invoked. Appellant did not invoke
  Section 37(4) of the Act. No reason has been assigned as to
  why the said discretion of the court should be invoked
F particularly when the claim has been raised only after
  completion of the work.                                                    +-
       32. For the reasons aforementioned, we, albeit for different
  reasons, affirm the judgment of the High Court. The appeals
  are, accordingly, dismissed. In the facts and circumstances of
G the case there shall be no order as to costs.
         We may clarify that nothing stated herein shall affect the
     merit of the appellant's claim to invoke the jurisdiction before
     any other forum for enforcing the same.
     N.J.                                          Appeals dismissed.
32                                                                                 J


Search Indian case law

Ask in plain English, not just keywords. 25,000 AI words free, no card.

Try "Arbitration"Sign in to search

For a digitally signed copy suitable for filing, refer to the court's own website. Only the court can issue one.