Created byFuzzy Cloud

Supreme Court of India

G. RAMACHANDRA REDDY & CO.versusUNION OF INDIA & ANR.

Citation
2009 INSC 528
Decided
15 April 2009
Disposal
Disposed off

Holding

Interpretation of a contract is within the arbitrator’s jurisdiction and a court may set aside an award only on a ground of error apparent on the face of the award or a perverse award, not merely because it disagrees with the arbitrator’s view.

Summary

The appellant submitted a tender for a construction contract, claiming a 2.25% uplift on rates and a 40% labour component, which the respondent contested, leading to arbitration. The arbitrator held that the appellant’s covering letter formed part of the contract, upheld the 2.25% uplift, substituted the contractually stipulated 21% labour escalation with 40%, and awarded damages for illegal termination. Both parties appealed, arguing over the arbitrator’s jurisdiction to interpret the contract and whether the award contained errors apparent on its face. The Supreme Court reiterated that interpretation of a contract lies within the arbitrator’s domain and that courts may interfere only if the award is perverse or based on a wrong legal proposition. Applying this principle, the Court sustained the arbitrator’s award on all three claims and dismissed the Union of India’s appeal while allowing the appellant’s appeal.

Issues considered

  • The scope of judicial interference with an arbitral award, particularly where the award involves interpretation of contract terms
  • Whether the arbitrator erred in taking the appellant’s covering letter as part of the contract
  • Whether the award contains an error apparent on the face of the award or a perverse finding

Legislation cited

Subjects

ArbitrationArbitral awardCourt interferenceContract interpretationError apparent on the facePerverse awardLabour componentHigh rise buildingIllegal terminationDamages

Judgment

                                           [2009] 7 S.C.R. 917


                                 G. RAMACHANDRA REDDY & CO.                              A
    ,.                                              v.
                                       UNION OF INDIA & ANR.
                                    Civil Appeal No. 2479 of 2009
                                            APRIL 15, 2009
                                                                                         8
                             [S.B. SINHA AND CYRIAC JOSEPH, JJ.]
                          Arbitration -Award of arbitrator- Interference by court-
                    Scope - Held: The Court while dealing with an award would
                    not re-appreciate the evidence - Interpretation of a contract
                    may fall within the realm of the Arbitrator - Award containing       c
                    reasons also may not be interfered with unless they are found
                    to be perverse or based on a wrong proposition of law - If two
                    views are possible, -Court should refrain itself from interfering.
                          An advertisement was issued for the work of
                                                                                  D
                    construction. Appellant submitted its tender on 9/
                    17.7.1988. In its forwarding letter, appellant stated thatthe
                    total labour component involved in the work was 40% of
                    the scope of the contract. A post script was added thereto
                    stating that Item 1 of the schedule quoted percentage to
                    be read out over (+ 2.25% ) and the total value to be E
                    considered accordingly.
1                        Respondent by letter dated 19.7.1988, stated that the
                    tender should be considered with the reduction of
         ....
                    minimum 2.25% over quoted percentage for schedule 'A' F
                    Part I. Dispute arose between the parties and arbitration
                    clause was invoked. Before the Arbitrator, appellant put
                    forth claims regarding additional payment of 2.25% over
                    the quoted rates; dispute regarding percentage of labour
                    component in the work with reference to the escalation G
                    in labour rates and for consequential in labour rates and
          .... ~-   for consequential payments to the plaintiff; dispute
                    regarding escalation with reference to the extra payment
                    of labour involved in construction of high rise building;
                                                   917                                   H
        918      SUPREME COURT REPORTS                [2009] 7 S.C.R.


    A dispute regarding legality of the termination of the
      plaintiff's contract and for consequential damages.
             Arbitrator allowed some of the claim while rejecting
        others. Counter claim of the first respondent was rejected.
    B        First respondent filed an application under s.30 of
        Arbitration Act, 1940. Single Judge of High Court held that
        award did not warrant interference. The Division Bench
        of the High Court allowed the appeal in part in respect of
        three items of claim. Both the parties filed appeals.
    c        Dismissing the appeal of the Respondent Union of
        India and allowing the appeal of appellants, the Court
           HELD: 1.1. Interpretation of a contract may fall within
      the realm of the Arbitrator. The Court while dealing with
      an award would not re-appreciate the evidence. An award
-   D containing reasons also may not be interfered with unless
      they are found to be perverse or based on a wrong
      proposition of law. If two views are possible, the Court
      should refrain itself from interfering. [Para 18) [931-D-E]
    E        State of UP v. Allied Constructions (2003) 7 SCC 396;
        Pure Helium India (P) Ltd. v. Oil & Natural Gas Commission
        (2003) 8 SCC 593; K.R. Raveendranathan v. State of Kera/a
        (1998) 9 sec 41 o; H.P Seb v. R.J. Shah & co. (1999) 4 sec      r
        214; Rajasthan State Mines & Minerals Ltd. v. Eastern Engg.
    F   Enterprises (1999) 9 SCC 283; Food Corporation of India v.
        Surendra, Devendra & Mahendra Transport Co. (2003) 4 SCC
        80; Shyama Charan Agarwala & Sons v. Union of India (2002)
        6 sec 201 - relied on.
           1.2. Jurisdiction of the Court to interfere with an award
    G made by an Arbitrator is limited. One of the grounds
      therefor is the error apparent on the face of the award.
      [Para 19) [933-A-B]
            State of Rajasthan v. Pure Construction Co. Ltd. & Ors.
    H   (1994) 6 SCC 485; Trustees of the Port of Madras v.
                                    -
                         G. RAMACHANDRA REDDY & CO. V.               919
                              UNION OF INDIA & ANR.

         '   Engineering Constructions CorporationLtd. (1995) 5 SCC 531;
             Food Corporation of India v. Joginderpal Mohinderpal & Anr
                                                                           A

             (1989) 2 SCC 34 7; Numaligarh Refinery Ltd. v. Daelim
             Industrial Company Ltd. JT 2007 (11) SC 73 - relied on.
                   2. A contract would warrant construction, if the terms
             thereof are vague and ambiguous. The letter exhibiting B
             the offer of the appellant refers to four different documents
             including the letter dated 9117.07.1988. Whether in the said
             letter, the appellant had asked for increase of 2.5% over
             the base value or deducted 2.5% therefrom is a matter of
             construction. The Arbitrator took the ultimate contract into c
             consideration. He did take the same into consideration.
             He, however, was of the opinion that the four letters which
             were said to be the sole repository of the contract formed
             part thereof. He, thus, took into consideration the relevant
             documents for arriving at a finding as to whether they
                                                                           D
             formed part of the contract. Offer of the appellant was
             accepted. [Paras 22, 23] [935-E-H; 936-A]
                     3.1. The first claim was in relation to disputes
             regarding additional payment of 2.25% over the quoted
             rates under item 1 of Schedule A with an overall effect of E
             4.5% over what had been paid to the plaintiff. The arbitrator
             came to the conclusipn that the letter dated 9/17.7.1988
             (Ex.C.2) does not make out whether the contractor
             intended to quote the price with +2.25% and therefore, he
             held that a concluded contract has taken place after taking
                                                                            F
             into consideration the sign (+) mentioned in the above
             letter. The contract would therefore still be enforced even
             if it is assumed that there was a mistake on the part of the
             respondent. The High Court held that it was apparent on
             the face of record that the contractor intended only to
             reduce 2.25%, which was seen from Ex.C.5, which was G
J. ..J
             final and concluded, claim no 1 fails for that reason. But
             as the Arbitrator held that the letter of the contractor dated
             9/17.7.1988 formed part of the contract, the claim cannot
             fail and therefore the award of the Arbitrator, in respect of
             claim No 1 must be sustained. [Para 24] [936-A-D]              H
    920      SUPREME COURT REPORTS               (2009] 7 S.C.R.


A      3.2. In relation to Claim No.2, the respondent relied
  on the fact that the claimant received payment only at the
  rate of 21% towards labour escalation in the several
  .R.A.Rs and therefore, it has to be presumed that the
  claimant is entitled to only 21 %. The Arbitrator opined that
B the receipt of money at 21% cannot absolve the claimant
  from claiming at 40% as per the contract, particularly,
  when it is clearly mentioned in Ex C.2 (R1) that 40% would
  be the labour component which forms part of the contract,
  Ex C.5. Keeping the same principle as applied in relation
c to Claim No.1, the Arbitrator held that as the covering letter
  (Ex.C.2) is part of the tender bid, and since the tender bid
  has been accepted without any modification, the Figure
  of 21% has to be substituted by 40%. Therefore, in respect
  of claim No.2, award of the Arbitrator is sustained. The
  matter might have been different had the respondents in
0
  categorical terms rejected the offer made by the appellant
  as amended by its letter dated 19.7.1988. It did not do it.
  Thus, the contract remained open for construction. [Paras
  25, 26] [936-E-H; 937-A-B]
E      3.3. So far as Claim No.3 is concerned, the claim
  towards higher minimum wages paid to the workmen is
  not in dispute. A high rise building cannot be divided into
  two parts. What would constitute a high rise building was
  defined. A portion of the building cannot be high rise and
F a portion would fall within the purview of the said
  definition. The Arbitrator rightly opined that the same
  workers may have to work for constructions of the entire
  building as it would be impossible for any contractor to
  employ any workmen to work exclusively for the high rise
G buiiding. Furthermore, the same workmen may have to
  work in different parts of the same building at different
  times. It would lead to an absurd situation if the workmen
  at one point of time are not paid the 20% of the excess
                                                                   -·
  amount and then paid the same and yet again denied the
H same benefit. Interpretation of the High Court, therefore,
                              G. RAMACHANDRA REDDY & CO. V.                921
                                   UNION OF !NOIA & ANR.
             '   that high rise building mean portion of the building,            A
                 keeping in view the beneficent nature of the provisions,
                 cannot be accepted. [Para 29] [937-D-G]
                        3.4. The question as to whether damages were payable
                 for illegal termination of contract cannot be a subject matter
                 of contract. The Arbitrator categorically held that not only     B
                 the termination of contract was illegal, the same was mala
                 fide. In any event, there is a delay of 411 days in filing the
            ,.   SLP of the respondent, for which no sufficient explanation
                 has been given. [Paras 30, 31] [938-A-C]
                                                                                  c
                                    Case Law Reference
                      (2003) 1 sec 396         relied on         Para 18
                      (2003) 8 sec 593         relied on         Para 18
                       (1998) 9 sec 410        relied on         Para 18          D
                      (1999) 4 sec 214         relied on         Para 18
                      (1999) 9 sec 283         relied on         Para 18
                       (2003) 4 sec 80       . relied on         Para 18
                                                                                  E
                       c2002) s sec 201        relied on         Para 18
                      (1989) 2 sec 38          relied on         Para 18
    I   ~             (1994) s sec 485         relied on         Para 19
                      (1995) 5 sec 531         relied on         Para 19          F

                      (1989) 2 sec 347         relied on         Para 20
                      JT 2007 (11) SC 73       relied on         Para 21
                      CIVILAPPELLATE JURISDICTION: Civil Appeal No. 2479 G
                 of 2009
        ~   ..
/
    ~

                      From the Judgment and Order dated 04.10.2004 of the
                 High Court of Judicature at Madras in O.S.A. No. 172 of 2000
                                             WITH                                 H
    922         SUPREME COURT REPORTS                   [2009) 7 S.C.R


A          Civil Appeal No. 2536 of 2009
          Gurukrishna Kumar, R. Murari, S.R. Setia, B.B. Singh,
    Mukesh Verma , Anil Katiyar, B.K. Prasad, for the Appearing                  :
    Parties(s).

B          The Judgment of the Court was delivered by

           S.B. SINHA, J.
          · 1. Leave granted.

        2. Jurisdiction of a court to interfere with an arbitral award
C involving interpretation of a contract is involved in these appeals
  which arise out of a judgment and order dated 4.10.2004 passed
  by a Division Bench of the High Court of judicature at Madras
  allowing an appeal from a judgment and order dated 14.1.2000
  passed by a learned Single of the said court making the award
D made by Respondent No.2 herein a rule of Court.
          3. For the work of construction of "Married accommodation
    for MCPOs/CPOs/POs and Junior Sailors at Naval Air Station,
    Arakkonam" by the Union of India, an advertisement was issued;
    pursuant whereto appellant submitted its tender on or about 9/
E   17. 7.1988 marked as Exhibit C-2. In its forwarding letter, it was
    stated:
           "We have kept ready all the men and material for early
           commencement of the work. The technical personnel
F          engaged by the firm have the vast experience in the
           execution of major building projects. The total labour
           component involved in this work is forty per cent of the
           scope of the contract. We can deploy the huge skilled and
           unskilled labour force already on our rolls for all the works
           along with the machinery for successful completion of the
G
           work positively as per targeted time schedules of the
           Department. The latest ITCC and partnership deed are            ...
           enclosed as required."
           A post script added thereto reads as under :
H
                   G. RAMACHANOR/'I REDDY & CO. V.                 923
                UNION OF !NOIA & ANR. [S.B. SINHA, J.)

.,        "When our tender opened and Rates Read out, Please               A
          Read out over (+) 2.25% under item 1 of the schedule
          quoted percentage and total value considered
          accordingly."
          4. Respondent, by a letter dated 19.7 .1988 (marked as
     Exhibit C-3) replied thereto, stating :                               B
          "On scrutiny of your forwarding letter the following
          comments are made :-
          (a)   The Labour component in the work is 20 as included
                under Special Condition No.17 on Serial Page 94 of C
                the tender and not 40 as referred to by you.
          (b)   In case of acceptance of your tender mobilization
                advance of Rs.35.00 lakhs will be paid against BGBs
                as per conditions of the tender.
                                                                           D
          (c)   It is seen that the way the revision has been made in
                the quoted percentage for Schedule 'A' Part I does
                not go well with the status of your firm. However, your
                tender is being considered with the reduction of
                minimum 2.25% over quoted percentage for                   E
                Schedule 'A' Part I as also read out at the time of
                opening of tenders wherein your representative was
                also present."
          Yet again on 5.8.1988, appellant in reply thereto, inter alia,
     stated:                                                               F
          "1. We hereby clarify that our rates are worked out and
          quoted taking total labour component involved in the scope
          of work as 40%. As such the department may please
          evaluate our tenders on the same basis and consider G
          accordingly.
          xxx                      xxx                    xxx
          After ascertaining this just before dropping the tender in
          the tender box, our Managing Partner had to include an           H
     924        SUPREME COURT REPORTS                 [2009) 7 S.C.R.


A          extra at 2.25% towards Turnover Sales Tax liability and
           the vertical line in the sign (+) has been hurriedly put as




B
           shown here once again (+).
           Thus, our quoted rates for item 1 of the schedule is 18.5%
           i.e. 16.25% quoted by us in the schedule and plus 2.25%
                                                                                  -
           quotd in the covering letter along with our tender against
           item 1 of the schedule. We regret for the misunderstanding
           led in this regard."
         Offer of the appellant was accepted by the respondents in
c   terms of its letter dated 11.8.1988, the relevant portion whereof
    reads as under :
           "Reference your letter No.Nil dated 9/17.7.1988 forwarding
           the tender for the above mentioned work.
           2. On behalf of the President of India, I hereby accept
D
           your tender for the work mentioned above for the Lump
           Sum of Rs.7,54,03,216.00 (Rupees Seven Crores Fifty
           four lakhs three thousand two hundred and sixteen only).
           3. This contract is allotted the number "CA No.CEMZ/
E          ARK/4of1988-89" which will be quoted by you in all future
           correspondence in connection with this contract.
           4. The tender enquiry, your tender, the letter referred to
           above and this letter shall be the sole repository of the
           contract."
F
        With the said letter, the details of amended Lump-sum was
    appended which reads as under :
           "DETAILES OF AMENDED LUMP SUM

G i)       Lump sum amount originally         Rs. 7,67,22,728.00
           quoted
    ii)    Deducted for reduction of (-)      Rs. 13,91,512.00           ,_ ...
           2.25% offered on Schedule '/:>.:
           Part I vide your letter No. NIL
H          dated 9/17 July, 88 while
             G. RAMACHANDRA REDDY & CO. V.                   925
           UNION OF INDIA & ANR. [S.B. SINHA, J.)

     forwarding the tender (i.e.                                    A
     2.25% on Rs.6,18,45,000/-)
     Note : Consequent on SI (ii)
     above the Representing
     percentage on Schedule 'A'
     Part I stands amended to "+ 14%"                               B

     Amended Lump Sum                   Rs. 7,54,03,216.00
     (Rupees Seven crores fifty four lakhs three thousand two
     hundred and sixteen only)"
                                                                    c
     6. Indisputably, whereas the main letter dated 11.8.1988
was signed by one L.D. Sharma, Brig. Chief Engineer as
accepting officer for and on behalf of the President of India, the
appendix was signed by some other person for 'Accepting
Officer'. Indisputably, the representative of the appellant also D
signed the said letter.
     The said contract, however was terminated on or about
10.7.1991
      7. Disputes and differences having arisen between the
parties, the arbitration agreement which formed part of the         E
general condition of the contract as also special condition of
contract was resorted to. Respondent No.2 was appointed as
the Arbitrator.
     Before the learned Arbitrator, appellant put forth eight       F
claims, being :
     "(a) Dispute regarding additional payment of 2.25% over
          the quoted rates under item 1 of Schedule A with an
          overall effect of 4.5% over what has been paid to the
          plaintiff.                                            G
     (b)   Dispute regarding percentage of labour component
           in the work with reference to the escalation in labour
           rates and for consequential in labour rates and for
           consequential payments to the plaintiff.
                                                                    H
    926         SUPREME COURT REPORTS                 [2009] 7 S.C.R.


A         (c)   Dispute regarding escalation with reference to the
                extra payment of labour involved in construction of
                high rise building.
          (d)   Dispute regarding legality of the termination of the
                plaintiff's contract and for consequential damages.
B
          (e)   Dispute regarding release of the plaintiff's plant and
                equipment, together with damages for the use of the
                equipment by the defendant and in default payment
                of the market value of the plant and equipment as on
                the date of termination, together with the damages
c               as aforesaid.
          (f)   Dispute regarding balance payment for the work
                done and material supplied by the plaintiff.
          (g)   Interest at 24% p.a. on all amounts due to plaintiff
D               and awarded by the arbitrator from the date when
                the cause of action for the claim arose, till the date
                of payment to the plaintiff."
         8. Respondent repudiated the said claims of the appellant.
    Respondent No.2 made and published an award on 17.9.1996.
E   While claims Nos.1 and 5 were allowed in part, claims No.2
    and 4 were allowed in toto. Claim No.3 was allowed for the
    amount to which the appellant itself had restricted its claim to.
          Counter claim of the first respondent was rejected.

F         9. First respondent filed an application under Section 30
    of the Arbitration Act, 1940 (hereinafter called and referred to
    for the sake of brevity as 'the Act').
       A learned Single Judge of the High Court rejected the said
  objection, opining that the award did not warrant any interference.
G The learned Single Judge noticed that claim Nos. 5 and 6 had
  not been disputed by the first respondent and counter claim No.4
  was not pressed. It was, therefore, directed payment of a sum          '   ..
  of Rs.2, 78, 17 ,530.01 p. with further interest @ 6% per annum
  from the date of decree till the date of realization. The counter
H claim was also dismissed.
                                  G. RAMACHANDRA REDDY & CO. V.                     927
                                UNION OF INDIA & ANR. [S.B. SINHA, J.]

                        10. First respondent preferred an intra court appeal A
                  thereagainst in terms of clause 15 of the Letters Patent of the
                  High Court read with Section 39 of the Act. The Division Bench
      /
                  of the High Court allowed the said appeal iri part in respect of
                  three items of claim. The objection in relation to fourth item was
                  also dismissed.                                                    B
      ~
                       11. Both parties are here before us aggrieved by and
          •       dissatisfied with the said judgment.
                       12. The three heads of claim which were allowed by the
                  respondent No.2 in favour of the appellant are as under :                c
                       (i)      Claim of 2.25% over and above the base price as
                                specified in Item No.1 of Schedule A;
~   .,                 (ii)     claim of escalation towards labour component
                                whether 40% or 21 %; and
                                                                                           D
              )        (iii)    claim towards higher minimum wages paid to the
j                               workmen in terms of a Government of India
                                notification dated 14.10.1986.
::)
                       The fourth claim which was allowed related to loss of profit
                  allegedly suffered by the petitioner for illegal termination of the
                                                                                           E
                  contract.
                      13. Mr. Gurukrishna Kumar, learned counsel appearing on
                  behalf of the appellant, would submit :
                       (1)       That the Division Bench of the High Court committed F
                                 a serious error in so far as it failed to take into
                                 consideration the distinction between an excess of
                               . jurisdiction and an error apparent on the face of the
                                 award and as the respondent's objection was not in
                                 relation to the exercise of excess jurisdiction by the G
                                 arbitrator, a strict scrutiny test should have been
                                 applied.
                       (2)      The Division Bench of the High Court committed a
                                serious error of law in so far as it failed to take into   H
    928         SUPREME COURT REPORTS                  [2009] 7 S. C.R.


A               consideration that an error apparent on the face of
                the award would not entitle it to enter into the merit
                of the matter as the same is confined to the award
                itself or any note appended thereto.
          (3)   Interpretation of an agreement admittedly being
B               within the realm of the jurisdiction of the Arbitrator,
                interference therewith is not permissible even if the
                court takes a different view.
          14. Mr. B.B. Singh, learned counsel appearing on behalf
c   of the respondent, on the other hand, would urge:
          1)    As the jurisdiction of the Arbitrator emanates from
                the contract, he must exercise the same within the
                four corners thereof.
          2)    Interpretation of a contract although fell within the
D
                jurisdiction of the Arbitrator but in construing the
                same, he could not have ignored any material
                document, namely, the final contract entered into by
                and between the parties on 11.8.1988 and based
                his interpretation only on the basis of letter of the
E               contractor d;:3ted 9/17. 7.1988 and, thus, he must be
                held to have misconducted himself and the
                proceedings.
       15. Before adverting to the rival contentions, as noticed
F hereinbefore, we may briefly notice the reasonings adopted by
  respondent No.2 in making the award.
          The learned Arbitrator proceeded on the basis that :
          (1)   The letter of the contractor dated 9/17. 7.1988 formed
G
                part of the contract.
          (2)   The intent of the parties must be ascertained from
                four documents which formed part of the contract
                and not de hors the same.
                                                                          ."
          (3)   Appendix to the letter dated 11.8.1988 having been
H
                       G. RAMACHANDRA REDDY & CO. V.                   929
                     UNION OF !NOIA & ANR. [S B. SINHA, J]

                     signed by a person other than the Accepting Officer     A
                     who was authorized therefor, the same was not
                     binding on the appellant.
               (4)   Although the appellant had signed the work order,
                     the same by itself would not lead to the conclusion
                     that it was estopped and precluded from questioning     8
                     the quantum of amount mentioned in the said letter
                     dated 11.8.1988.
               16. In respect of claim No.1, the learned Arbitrator held :
               "On a consideration of the letters and the Exhibits           C
               mentioned above, we have to state that a concluded
               contract has taken place taking into consideration the sign
               (+) mentioned in the covering letter. Even assuming that
               there was a mistake on the part of the respondent reading
               the covering letter, the contract would remain unaffected.    D
               The contention of the respondent that when once the
               claimant has accepted for the reduction, as is found in
               Ex.R.7, which is the contractor's work order sheet, and
               which is signed by the contractor on 14.9.1988., it has to
               be concluded that there is an acceptance for the reduction. E


-              This argument of the learned Counsel for the respondent
               is not well founded. An acceptance of the contract will
               have to be considered under the terms of Ex.C.5 dated
               11.8.88. In the instance case it is common ground that
               there is a concluded contract between the parties and F
               what remains is the interpretation of the contract, Ex.C.5
               it is not the case of the respondent that Ex. C .5 is a counter
               offer which was accepted by the claimant. On the other
               hand, it is agreed by the respondent that acceptance of
               the contract is solely based on Ex.C.5. The documents G
               filed before me in this case clearly establish the sigh (+)
    > ......   which is more particularly referred to in Ex.C.5 as the sole
               repository of the contract. (underlining is mine) In such a
               case, it has to be ~oncluded that Ex.R.1 is the clear
               acceptance of the contract. It has to be further noted chat H
    930       SUPREME COURT REPORTS                     [2009] 7 S.C.R.


A         as per the terms of Section 7(2) of the Contract Act, if the
          proposer does not insist that his proposal should be
          accepted in the prescribed manner, he in fact accept the
          acceptance."
          In respect of claim No.2, the relevant condition of contract,
B namely, clause (17) although specified that for the purpose of
    escalation of the labour component, the value of contract should
    be taken as 21 % but as the appellant claimed 40% in its offer,
    the same would prevail over the contract, stating :

c         "I state that special condition to the contract that is clause
          17 at Page 4 specifies that for the purpose of escalation
          the labour component for the value of work will be taken
          as 20% which was later changed as 21%. Similarly, fuel
          component which was shown as 1.5% in the agreement
          was changed as 2% and the material component which
D
          was shown in the agreement on page 90 as 60% was
          changed into 58%. In other words, the total component             "
          towards labour, material and fuel comes to 81%. The
          claimant has not claimed anything in excess of 81%, for,
          the escalation clause in the agreement provides, the
E                                                                                   ~
          escalation for an amount not exceeding 81 % of the value
          of the work done. All that he has claimed is, towards fuel
          2%, towards material 39% and towards labour 40%. This
          change in labour component at 40% is based on Ex.C.22
          (R1) dated 9/17.07.88 which has become part of the tender
F         bid: This part of the offer that is tender bid, has been
          accepted by the respondent, that is to say, that this 21%
          mentioned in the contract has been substituted as 40%.
          The claimant has made this fact clear in all his subsequent
          letters. In other words, the contention of the claimant is
G         that the covering letter Ex.C.2 (R1) is part of the tender
          bid, and since the tender bid has been accepted without
          any modification, the figure 21% in the condition, has,          ,. ...
          therefore, to be substituted by 40%. It is on this basis the
          claimant claims that the labour component should be paid
H         at the rate of 40%, while material component would
                             G. RAMACHANDRA REDDY & CO. V.                     931
                           UNION OF INDIA & ANR [S.B. SINHA, J.]

          '         consequently come at 39% and the fuel component will               A
                    remain at 2%."
                     In respect of claim No.3, it was held that in view of the
               notification issued by the Central Government dated
               14.10.1980, the minimum wages payable to the workmen being
               over and above 20% the general wages, the same would be                 B
               payable to all the workmen and not those employed in high rise
·t             portions of the building.
                    17. The Division Bench, however, set aside in part the
               award in respect of the aforementioned claims stating as under :        c
                    "However, we find some substance with regard to the
                    claim No.4, loss of profit, there was an admitted delay in
                    handling over the. site and supply of materials. We confirm
'                   both the award of the Arbitrator and the order of the learned
                    Single Judge with regard to Claim No.4, loss of profit."           D
          ;
                     18. We may, at the outset, notic~ the legal principles
               governing the dispute between the parties. Interpretation of a
               contract may fall within the realm of the Arbitrator. The Court
               while dealing with an award would not reappreciate the evidence.
               An award containing reasons also may not be interfered with             E
               unless they are found to be perverse or based on a wrong
               Proposition of law. If two views are possible, it is trite, the Court
               will refrain itself from interfering. {See State of U.P v. Allied
               Constructions [(2003) 7 SCC 396]}.
                                                                                       F
                    In Pure Helium India (P) Ltd. v. Oil & Natural Gas
               Commission [(2003) 8 SCC 593], this court, upon referring to
               the decisions in Allied Constructions (supra), K.R.
               Raveendranathan v. State of Kera/a [(1998) 9 SCC 410], H.P
               Seb v. R.J. Shah & Co. [(1999) 4 SCC 214], Rajasthan State
                                                                             G
               Mines & Minerals Ltd. v. Eastern Engg. Enterprises [(1999) 9
               SCC 283], Food Corporation of India v. Surendra, Devendra
.
\         ~.

               & Mahendra Transport Co. [(2003) 4 SCC 80] and Shyama
               Charan Agarwala & Sons v. Union of India [(2002) 6 SCG 201 ],
               opined as under :
                                                                             H



     .J
    932       SUPREME COURT REPORTS                    [2009] 7 S.C.R


A          '41. The principles of law laid down in the aforementionE~d
          decisions leave no manner of doubt that the jurisdiction of
          the court in interfering with a non-speaking award is limited.
          42. The upshot of the above decisions is that if the claim
          of the claimant is not arbitrable having regard to the bar/
B         prohibition created under the contract, the court can set
          aside the award but unless such a prohibition/bar is found
          out, the court cannot exercise its jurisdiction under Section
          30 of the Act. The High Court, therefore, misdirected itself
          in law in posing a wrong question. It is true that where such
c         prohibition exists, the court will not hesitate to set aside
          the award."
         In Sudarshan Trading Company v. Government of Kera/a
    & Anr. [(1989) 2 SCC 38], the law was laid down in the following               ,
    terms:
D
          "28. It was submitted before us that the High Court had          '
          exceeded its jurisdiction in acting in the manner it did on
          these aforesaid aspects. The first question, therefore, that
          arises for consideration in this case is, whether the award
E         in question was a speaking award or not. In our opinion,
          the award was not a speaking award. An award can also
          be set aside if the arbitrator had misconducted himself or
          the proceedings or had proceeded beyond his jurisdiction.
          These are separate and distinct grounds for challenging
F         an award. Where there are errors apparent on the face of
          the award it can only be set aside if in the award there is
          any proposition of law which is apparent on the face of the
          award, namely, in the award itself or any document
          incorporated in the award."
G         It was furthermore observed :
          "29. The next question on this aspect which requires             .   ~


          consideration is that only in a speaking award the court
          can look into the reasoning of the award. It is not open to
          the court to probe the mental process of the arbitrator and
H
                         G. RAMACHANDRA REDDY & CO. V.                   933
                       UNION OF INDIA & ANR [S.B .. SINHA, J]

                 speculate, where no reasons are given by the arbitrator,       A
                 as to what impelled the arbitrator to arrive at his
                 conclusion."
                 19. Jurisdiction of the Court to interfere with an award
            made by an Arbitrator is limited. One of the grounds therefor is
            the error apparent on the face of the award. We have noticed        B
            hereinbefore some precedents operating in the field.
                 What is an error apparent on the face of an award and
            legal misconduct is stated in State of Rajasthan v. Pure
            Construction Co. Ltd. & Ors. [(1994) 6 SCC 485], in the following   c
            terms:
                 "As reference to arbitration of disputes in commercial and
                 other transactions involving substantial amount has
                 increased in recent times, the courts were impelled to
                 have fresh look on the ambit of challenge to an award by D
      ,          the arbitrator so that the award does not get undesirable
i                immunity. In recent times, error in.law and fact in basing an
                 award has not been given the wide immunity as -enjoyed
                 earlier, by expanding the import and implication of "legal
                 misconduct" of an arbitrator so that award by the arbitrator E
                 does not perpetrate gross miscarriage of justice and the
                 same is not reduced to mockery of a fair decision of the
                 lis between the parties to arbitration: Precisely for the
                 aforesaid reasons, the erroneou$ application of law


-                constituting the very basis of the award and improper and F
                 incorrect findings of fact, which without closer and intrinsic
                 scrutiny, are demonstrable on the face of the materials on
                 record, have been held, very rightly, as legal misconduct
                 rendering the award as invalid."
                 It was furthermore stated :                                    G

    /> .J
                 "Error apparent on the face of the record does not mean
                 that on closer scrutiny of the import of documents and
                 materials on record, the finding ·made by the arbitrator
                 may be held to be erroneous. Judicial decisions over the
                                                                                H
    934        SUPREME COURT REPORTS                   [2009] 7 S.C.R.


A         decades have indicated that an error of law or fact
          committed by an arbitrator by itself does not constitute
          misconduct warranting interference with the award."

         In Trustees of the Port of Madras v. Engineering
    Constructions Corporation Ltd. [(1995) 5 SCC 531], This Court
B   opined:

          "14.... A note of clarification may be appended, viz., where
          the parties choose to refer a question of law as a separate
          and distinct matter, then the Court cannot interfere with the
c         award even if the award lays down a wrong proposition of
          law or decides the question of law referred to it in an
          erroneous fashion. Otherwise, the well-settled position is
          that an arbitrator "cannot ignore the law or misapply it in
          order to do what he thinks is just and reasonable". [See
          Thawardas Pherumal v. Union of India]
D
          It was clarified :
          20. The proposition that emerges from the above decisions
          is this: in the case of a reasoned award, the court can
          interfere if the award is based upon a proposition of law
E         which ls unsound in law. The erroneous proposition of law
          must be established to have vitiated the decision. The
          error of law must appear from the award itself or from any
          document or note incorporated in it or appended to it. It is
          not permissible to travel beyond and consider material
F         not incorporated in or appended to the award."
        20. We may, however, notice that in Food Corporation of
  India v. Joginderpal Mohinderpal & Anr. [(1989) 2 SCC 347],
  referring to a large number of decisions, a Division Bench of
G this Court held :
          " ... It has to be borne in mind, however, that wrong.
          statement or conclusion of law, assuming even that it was
          a wrong statement of law, was not wrong statement of the
          proposition of law which was the basis for decision in this
H         award. Error of law as such is not to be presumed; ifthere
                      G. RAMACHANDRA REDDY & CO. V.                     935
                    UNION OF INDIA & ANR. [S.B. SINHA, J]

             is legal proposition which is the basis of the award and A
             which is erroneous as observed in Champsey Bhara &
             Co., then only the award can be set aside."
               21. Almost to the similar effect is the decision of another
        Division Bench of this Court in Numaligarh Refinery Ltd. v.
        Da§lim Industrial Company Ltd. [JT 2007 (11) SC 73], wherein           B
        it is stated :
             "17. We have considered the rival submissions of the
    .        parties. So far as the legal proposition as enunciated by
             this Court in various decisions mentioned above, it is            c
             correct that courts shall not ordinarily substitute their
             interpretation for that of the arbitrator. It is also true that if
             the parties with their eyes wide open have consented to
             refer the matter to the arbitration, then normally the finding
             of the arbitrator should be accepfed without demur. There
                                                                                D
             is no quarrel with this legal proposition. But in a case
             where it is found that the arbitrator has acted without
             jurisdiction and has put an interpretation on the clause of
             the agreement which is wholly contrary to law then in that
             case there is no prohibition for the courts to set things
             right."                                                            E

              22. A contract would warrant construction if the terms thereof
        are vague and ambiguous. The letter exhibiting the offer of the
        appellant refers to four different documents including the letter
        dated 9/17.07.1988 which was marked as Exhibit C-2. Whether            F
        in the said letter, the appellant had asked for increase of 2.5%
        over the base value or deducted 2.5% therefrom is a matter of
        construction.
              23. The learned Arbitrator, it is not correct to contend, has
        not taken into consideration the ultimate contract. He did take        G
        the same into consideration. He, however, was of the opinion
,   ~
        that the aforementioned four letters which were said to be the
        sole repository of the contract formed part thereof.
             He, thus, took into consideration the relevant documents
                                                                               H
    936       SUPREME COURT REPORTS                  [2009] 7 S.C.R.


A   for arriving at a finding as to whether they formed part of the
    contract. Offer of the appellant was accepted.

        24. The first claim was in relation to disputes regarding
  additional payment of 2.25% over the quoted rates under item
  1 of Schedule A with an overall effect of 4.5% over what had
8 been paid to the plaintiff. The arbitrator came to the conclusion
  that the letter dated 9/17.7.1988 (Ex.C.2) does not make out
  whether the contractor intended to quote the price with +2.25%
  and therefore, he held that a concluded contract has taken place
  after taking into consideration the sign (+) mentioned in the
C above letter. The contract will therefore still be enforced even if
  it is assumed that there was a mistake on the part of the
  respondent. The High Court held that it was apparent on the
  face of record that the contractor intended only to reduce 2.25%,
  which was seen from Ex.C.5, which was final and concluded,
D claim no 1 fails for that reason. But as the Arbitrator held that
  the letter of the contractor dated 9/17. 7 .1988 formed part of the
  contract, the claim cannot fail and therefore the award of the
  Learned Arbitrator, in respect of claim No 1 must be sustained.
        25. In relation to Claim No.2, the respondent relied on the
E fact that the claimant received payment only at the rate of 21 %
  towards labour escalation in the several RA.Rs and therefore,
  it has to be presumed that the claimant is entitled to only 21%.
  The Arbitrator opined that the receipt of money at 21 % cannot
  absolve the claimant from claiming at 40% as per the contract,
F particularly, when it is clearly mentioned in Ex C.2 (R1) that 40%
  will be the labour component which forms part of the contract,
  Ex C.5. The High Court held that as the Department themselves
  gave 21 % to the contractor, and only 21 % of escalation, which
  was in consonance with the special conditions, which was
G apparent on the face of the record, the second claim of
  escalation of 40% was to be set aside. But, keeping the same
  principle as applied in relation to Claim No.1, the Arbitrator held
  that as the covering letter (Ex.C.2) is part of the tender bid, and
  since the tender bid has been accepted without any modification,
H the Figure of 21 % has to be substituted by 40%. Therefore, in
 .:                       G. RAMACHANDRA REDDY & CO V.                      937
                        UNION OF !NOIA & ANR. [S.S. SINHA, J.]

            respect of claim No.2, the impugned judgment of the High Court A
            cannot be upheld and the award of the Arbitrator is sustained.
~.               26. The matter might have been different had the
;,,         respondents in categorical terms rejected the offer made by
            the appellant as amended by its letter dated 19.7.1988. It did
            not do it. Thus, the contract remained open for construction.          B

                  27. We have not been able to persuade ourselves to agree
            with the reasonings of the Division Bench of the High Court.
       s    The award of the learned Arbitrator in respect of claim No.1,
            therefore, must be sustained.                                         c
                 28. Keeping in view the fact that the same principle would
            apply in respect of claim No.2 also, the impugned judgment of
            the High Court cannot be upheld.
                  29. So far as Claim No.3 is concerned, the claim towards
                                                                             D
            higher minimum wages paid to the workmen is not in dispute. A
            high rise building is a high rise building, it cannot be divided
            into two parts.
                   What would constitute a high rise building was defined. A
            portion of the building cannot be high rise and a portion would E
 )          fall within the purview of the said definition. The learned Arbitrator,
            in our opinion, had rightly opined that the same workers may
            have to work for constructions of the entire building as it will be
            impossible for any contractor to employ any workmen to work
            exclusively for the high rise building. Furthermore, the same F
            workmen may have to work in different parts of the same building
            at different times. It would lead to an absurd situation if the
            workmen at one point of time are not paid the 20% of the excess
            amount and then paid the same and yet again denied the same
            benefit. Interpretation of the High Court, therefore, that high rise
                                                                                    G
            building mean portion of the building, in our opinion, keeping in
      ' ~   view the beneficent nature of the provisions, cannot be accepted.
                 30. The award of the Arbitrator in respect of claim No.4
            has been accepted by t!1e Division Bench. Mr. B.B. Singh has
            drawn our attention to clause 11 (c) of the general conditions of      H
    938       SUPREME COURT REPORTS                  [2009] 7 S.C.R.


A   contract to contend that in terms thereof, no damages were
    payable.
          The question as to whether damages were payable for
    illegal termination of contract cannot be a subject matter of
    contract. The learned Arbitrator has categorically held that not
B   only the termination of contract was illegal, the same was mala
    fide. Furthermore, the contention raised before us by Mr. Singh
    has not been raised before the High Court.

         31. In any event, there is a delay of 411 days in filing the
c   SLP of the respondent, for which no sufficient explanation has
    been given.
        32. For the reasons aforementioned, the appeal filed by
                                                                                -
  Union of India is dismissed and that of the appellant is allowed.
  In the facts and circumstances of the case, however, there would
D be no order as to costs.

    D.G.                                      Appeals disposed of.




                                                                        >   '


Search Indian case law

Ask in plain English, not just keywords. 25,000 AI words free, no card.

Try "Arbitration"Sign in to search

For a digitally signed copy suitable for filing, refer to the court's own website. Only the court can issue one.