M/S INTERSTATE CONSTRUCTIONversusNATIONAL PROJECTS CONSTRUCTION CORPORATION LTD.
- Citation
- 2025 INSC 699
- Decided
- 15 May 2025
- Disposal
- Appeal(s) allowed
- Bench
- ABHAY S OKA
Holding
The arbitral tribunal is authorized under Section 31(7) of the Arbitration and Conciliation Act, 1996 to award interest for the whole period between the cause of action and the award, which may be sub‑divided into pre‑reference and pendente‑lite periods, and to levy post‑award interest on the sum including such interest, thus the High Court’s setting aside of the pendente‑lite interest was erroneous.
Summary
The appellant, M/s Interstate Construction, executed work orders for a power project for the respondent, NPCC, and later disputed certain recoveries, leading to arbitration. The arbitral tribunal awarded the appellant principal sum plus interest, distinguishing pre‑reference, pendente‑lite and future interest periods. The respondent challenged the award under Section 34, and the High Court Division Bench set aside the pendente‑lite interest directions, holding that the tribunal could not carve out three separate interest periods under Section 31(7) of the Arbitration and Conciliation Act, 1996. On appeal, the Supreme Court examined the statutory scheme and held that the tribunal is permitted to subdivide the period between cause of action and award and to award different rates of interest, and that interest on the awarded sum may also attract post‑award interest. Consequently, the Court set aside the High Court’s judgment and allowed the appeal.
Issues considered
- Whether the arbitral tribunal can award interest for separate pre‑reference, pendente‑lite and post‑award periods under Section 31(7) of the Arbitration and Conciliation Act, 1996.
- Whether the inclusion of interest on interest (compound interest) in the award is permissible.
- Whether the High Court was correct in setting aside the pendente‑lite interest directions.
Legislation cited
- Arbitration Act, 1940
- Arbitration and Conciliation Act, 1996s. 31(7)(a), s. 31(7)(b), s. 34, s. 37
Headnote
Issue for Consideration Issue arose whether the Division Bench of High Court was justified setting aside the directions related to pendente lite interest, holding that it was not open for the arbitral tribunal to have carved out three periods for payment of interest: future. Headnotes† Arbitration and Conciliation Act, 1996 – s.37 – Arbitral award – Award of interest for pre-reference and pendente lite period – Respondent engaged services of the appellant for executing a contract relating to Power Project – Appellant
Subjects
Judgment
[2025] 5 S.C.R. 2106 : 2025 INSC 699
M/s Interstate Construction
v.
National Projects Construction Corporation Ltd.
(Civil Appeal No. 3461 of 2025)
15 May 2025
[Abhay S. Oka and Ujjal Bhuyan,* JJ.]
Issue for Consideration
Issue arose whether the Division Bench of High Court was justified
setting aside the directions related to pendente lite interest, holding
that it was not open for the arbitral tribunal to have carved out
three periods for payment of interest: pre-reference, pendente lite
and future.
Headnotes†
Arbitration and Conciliation Act, 1996 – s.37 – Arbitral award –
Award of interest for pre-reference and pendente lite period –
Respondent engaged services of the appellant for executing a
contract relating to Power Project – Appellant disputed certain
recoveries – Arbitration clause invoked – Arbitrator passed
an award, while arbitral tribunal allowed the claims of the
appellant under several heads, awarding pre-reference interest,
pendente lite interest and future interest – In petition u/s.34 by
the respondent for setting aside the award, the Single Judge
of the High Court set aside the award with regard to future
interest at a rate exceeding 9 percent pa from the date of the
award till the date of payment – However, the Division Bench
of High Court set aside the directions related to pendente lite
interest, holding that it was not open for the arbitral tribunal
to have carved out three periods for payment of interest-pre-
reference, pendente lite and future when the statute provides
for only two periods, period being the period between the date
on which the cause of action arose and the date on which the
award is made, and the period from the date of the award till
the date of payment – Sustainability:
Held: Not sustainable – Reasoning given by the Division Bench
is fallacious – Arbitral tribunal has the discretion to include in the
sum awarded, firstly, interest at such rate as it deems reasonable;
* Author
[2025] 5 S.C.R. 2107
M/s Interstate Construction v.
National Projects Construction Corporation Ltd.
and secondly, for the whole or any part of the period between the
date on which the cause of action arose and the date on which
the award is made – This would mean that the arbitral tribunal
can exclude a period from the date on which the cause of action
arose till the date on which the award is made for the purpose of
grant of interest as has been done in the instant case – It would
also mean that the arbitral tribunal can grant interest for the whole
or any part of the period between the date on which the cause of
action arose and the date on which the award is made – It can be
a composite period or the said period can be further sub-divided,
as done in the instant case i.e. from the date of cause of action to
filing of the claim and from the date of filing of the claim till the date
of the award excluding the period when the appellant was found
to be remiss – It would also mean that there can be one rate of
interest for the whole period or one or more rates of interest for the
sub-divided periods as has been done in the instant case – This
would be the correct approach to interpret s.31(7)(a), given the
scheme of the 1996 Act – Division Bench erred by holding that
the arbitral tribunal had no jurisdiction to award interest for two
periods-pre-reference and pendente lite when the statute provides
for only one period, from the date when the cause of action arose
till the date of the award – View expressed by the High Court
not the correct interpretation of s.37(1)(a) – Sum awarded in
s.31(7)(a) would mean principal amount plus the interest awarded
from the date of cause of action upto the date of the award – As
per s.31(7)(b) of the 1996 Act, the sum (principal amount + interest)
would carry further interest at the rate of 2 per cent higher than
the current rate of interest prevalent on the date of the award to
the date of payment – Impugned judgment and order passed by
the Division Bench of the High Court set aside. [Paras 26, 35,
36, 44, 45]
Case Law Cited
Sayeed Ahmed and Company v. State of Uttar Pradesh [2009]
10 SCR 841 : (2009) 12 SCC 26; Pam Developments Private
Limited v. State of West Bengal [2024] 8 SCR 615 : (2024) 10
SCC 715; North Delhi Municipal Corporation v. S.A. Builders Ltd.
(2024) SCC Online SC 3768; State of Haryana v. S.L. Arora
[2010] 2 SCR 297 : (2010) 3 SCC 690; Hyder Consulting (UK)
Ltd. v. Governor, State of Orissa [2014] 14 SCR 1029 : (2015) 2
SCC 189; UHL Power Company Ltd. v. State of Himachal Pradesh
2108 [2025] 5 S.C.R.
Supreme Court Reports
[2022] 1 SCR 1 : (2022) 4 SCC 116; Delhi Airport Metro Express
Private Ltd. v. Delhi Metro Rail Corporation [2022] 3 SCR 716 :
(2022) 9 SCC 286; Morgan Securities and Credits Private Ltd. v.
Videocon Industries Limited [2022] 9 SCR 819 : (2023) 1 SCC
602 – referred to.
List of Acts
Arbitration and Conciliation Act, 1996; Arbitration Act, 1940.
List of Keywords
Pendente lite interest; Pre-reference interest; Future interest;
Contractual dues; Recoveries; Payment of interest; Cause of action;
Principal amount plus the interest; Past period; Date on which the
award is made; Date on which the cause of action arose.
Case Arising From
CIVIL APPELLATE JURISDICTION: Civil Appeal No. 3461 of 2025
From the Judgment and Order dated 01.08.2023 of the High Court
of Delhi at New Delhi in FAO (OS) (COMM) No. 175 of 2021
Appearances for Parties
Advs. for the Appellant:
Mrs. S. Janani, Sr. Adv., Ms. Madhu Moolchandani, Ms. Sharika Rai.
Advs. for the Respondent:
Dhruv Mehta, Sr.Adv., Rajat Arora, Ms. Mariya Shahab, Ms. Nishi
Sangtani.
Judgment / Order of the Supreme Court
Judgment
Ujjal Bhuyan, J.
This appeal by special leave is directed against the judgment and
order dated 01.08.2023 passed by the Division Bench of the High
Court of Delhi in FAO (OS) (Comm) No.175 of 2021.
2. It may be mentioned that by the aforesaid judgment and order
dated 01.08.2023 (impugned judgment), Division Bench of the
[2025] 5 S.C.R. 2109
M/s Interstate Construction v.
National Projects Construction Corporation Ltd.
High Court of Delhi (High Court) allowed the appeal of National
Projects Construction Corporation Limited, (NPCC) or the respondent
hereinafter, filed under Section 37 of the Arbitration and Conciliation
Act, 1996 (briefly ‘the 1996 Act’ hereinafter) setting aside that part
of the judgment and order dated 02.08.2021 passed by a learned
Single Judge of the High Court under Section 34 of the 1996 Act
upholding the directions contained in paragraph 58(b) of the award
dated 28.10.2020 as well as setting aside the directions of the arbitral
tribunal as contained in paragraph 58(b) of the said award.
3. Relevant facts may be briefly noted.
4. Respondent had engaged the services of the appellant for executing
a contract relating to Ramagundam Super Thermal Power Project,
Ramagundam, District Karimnagar in the then composite State of
Andhra Pradesh. In this regard, two separate work orders were issued:
(i) Work order No.917344/838 dated 19.06.1984 in respect of the
work excavation of foundation package work-II 3 X 500 MW
of National Thermal Power Corporation Limited, Ramagundam
Super Thermal Power Project;
(ii) Work Order No. 917344/2382 in respect of the work foundation
package work, stage-II, at Ramagundam Super Thermal Power
Project;
5. Thereafter, contract agreement was entered into between the parties.
As per clause 4 of the conditions of contract read with clause 15 of
the special conditions attached to the work orders, all the disputes
and differences between the parties were to be settled by way of
arbitration.
6. It is stated that appellant had completed the contract work in the
year 1987. Respondent had paid the appellant the contractual dues
after withholding certain sums on account of recoveries. Appellant
disputed such recoveries. Additionally, appellant also raised certain
claims which were not accepted by the respondent.
7. In view of such disputes and differences, appellant invoked the
arbitration clause by issuing notice dated 17.05.1993.
8. Respondent did not take immediate steps for appointment of
an arbitrator. After considerable delay, by communication dated
07.10.1997, respondent appointed Shri Shivamoy Ghosh, Additional
2110 [2025] 5 S.C.R.
Supreme Court Reports
General Manager, NPCC, Madras Sector, Chennai as the sole
arbitrator to arbitrate on the subject dispute.
9. Appellant filed statement of claims before the learned arbitrator on
20.01.1998 claiming an aggregate amount of Rs.4,46,29,404.00
along with pendente lite and future interest at the rate of 24 percent
per annum till final realization of the amount.
10. Appellant sought for a direction from the learned arbitrator to the
respondent to supply various documents related to the dispute.
However, learned arbitrator only permitted the appellant an opportunity
to inspect the documents and did not issue any direction to the
respondent for supply of copies.
11. Aggrieved thereby, appellant filed a petition under Section 14 of the
1996 Act before the High Court seeking termination of the mandate
of the learned arbitrator and for appointment of a new arbitrator in his
place. This petition was registered as OMP No. 214/2002. By order
dated 11.10.2004, learned Single Judge terminated the mandate
of Shri Shivamoy Ghosh and appointed Shri A.S. Chandhiok, Sr.
Advocate, as the sole arbitrator.
12. Respondent challenged the said order of the learned Single Judge
dated 11.10.2004 before the Division Bench of the High Court in
FAO (OS) No.241/2004. By order dated 02.02.2005, Division Bench
appointed Shri L.R. Gupta, retired Director General of CPWD as the
sole arbitrator.
13. Before Shri L.R. Gupta, the learned arbitrator, respondent while
filing its reply to the statement of claims filed by the appellant, also
challenged the authority of one Shri Jagdish Raj Yadav to file the
claim on behalf of the appellant. In this regard an application dated
23.02.2007 was filed before the learned arbitrator. Learned arbitrator
dismissed the said application vide the order dated 03.08.2007.
14. The said order dated 03.08.2007 was challenged by the respondent
before the learned Single Judge of the High Court by filing a petition
under Section 34 of the 1996 Act, being OMP No.537/2007.
15. It may be mentioned that Shri L.R. Gupta resigned as the sole
arbitrator on 23.06.2008.
16. Vide order dated 30.01.2007, learned Single Judge disposed of
the petition filed under Section 34 of the 1996 Act bearing OMP
No.537/2007.
[2025] 5 S.C.R. 2111
M/s Interstate Construction v.
National Projects Construction Corporation Ltd.
17. Appellant filed a petition under Section 15 of the 1996 Act before the
High Court being OMP (T) (Comm) No. 30/2018 seeking appointment
of an arbitrator in place of Shri L.R. Gupta who had resigned. The
said petition was disposed of by the learned Single Judge of the
High Court vide order dated 31.05.2018 reconstituting the arbitral
tribunal by appointing Mr. Justice R.C. Jain, a former Judge of the
High Court, as the sole arbitrator to arbitrate on the disputes between
the parties.
18. New arbitrator held the first hearing on 03.05.2019 and finally
pronounced the award on 28.10.2020. While the arbitral tribunal
allowed the claims of the appellant under several heads, we are
concerned with the contentious part of the award relating to payment
of interest (claim No. 7) contained in paragraph 58 of the award.
Relevant portion contained in paragraph 58 of the award reads as
under:
58. *** *** *** ***
In a nutshell the claimant is held entitled to interest as
under:
a) Pre-reference / past period interest:
@ 18% per annum on a sum of Rs.34,43,490.61 w.e.f.
July 1987 up-till 19.01.1998.
b) Pendente lite interest:
i) @ 12% per annum w.e.f. 20.01.1998 uptill 31.12.2008
on the total amount (i.e. principal amount + the amount
of interest on the pre-reference/past period).
ii) @ 12% per annum w.e.f. 01.01.2017 till the date of
award on the total amount (i.e. principal amount + the
amount of interest for the pre-reference period and for
the period from 20.01.1998 till 31.12.2008).
c) Future interest:
@ 18% per annum from the date of the award till the date
of payment on the total amount (i.e. principal amount +
amount of interest on the pre-reference/past period+
amount of interest pendente lite).
2112 [2025] 5 S.C.R.
Supreme Court Reports
19. Respondent filed a petition under Section 34 of the 1996 Act before
the Single Bench of the High Court for setting aside the award dated
28.10.2020. The same was registered as OMP (Comm) No. 78/2021.
By the judgment and order dated 02.08.2021, learned Single Judge
partly allowed the petition by setting aside the award with regard to
future interest at the rate exceeding 9 percent per annum from the
date of the award till the date of payment.
20. Aggrieved by the judgment and order dated 02.08.2021 passed by
the learned Single Judge, respondent preferred an appeal under
Section 37 of the 1996 Act before the Division Bench of the High
Court which was registered as FAO (OS) (Comm) No. 175/2021. In
the appeal, learned senior counsel for the respondent (which was
the appellant before the Division Bench) clarified that the challenge
would be restricted to the directions issued by the arbitral tribunal
insofar the issue of interest was concerned. This was further clarified
by submitting that the challenge was not with respect to the rate
of interest or award of interest for the pre-reference/past period.
Grievance highlighted was against the directions contained in sub-
paragraph (b)(i) of paragraph 58 to the extent of the arbitral tribunal
stipulating that interest for the period mentioned therein would be
leviable not merely on the principal amount as awarded but upon
the said amount inclusive of the amount of interest relating to the
pre-reference/past period. Likewise, arbitral tribunal awarded interest
on identical terms in sub-paragraph (b)(ii) of paragraph 58 which was
objected to. Division Bench of the High Court vide the judgment and
order dated 01.08.2023 (impugned judgment) allowed the appeal by
setting aside the directions contained in paragraph 58(b).
21. Aggrieved thereby, appellant filed the related SLP (C) No.23235/2023
before this Court. By order dated 19.10.2023, this Court issued notice.
In the hearing held on 25.02.2025, leave was granted.
22. Though there is no challenge by either parties to the award on merit,
challenge of the respondent being confined only to the interest part,
nonetheless, to have a complete picture, it would be appropriate to
mention the claims of the appellant and the corresponding amounts
awarded by the arbitral tribunal. The following statement in tabular
form will throw light on the amounts claimed by the appellant and
the amounts awarded by the arbitral tribunal under sixteen heads
of claim. The tabular statement is as under:
[2025] 5 S.C.R. 2113
M/s Interstate Construction v.
National Projects Construction Corporation Ltd.
Claim Particulars Amount Claimed Amount Awarded
No.
(a) Escalation at 10% for work Rs.20,71,322.00 Rs.20,71,322.00
order 48/4
(b) Escalation at 10% for work Rs.1,84,418. 77 Rs.1,84,418.77
order 47/11
(c) Refund of panel recovery
of steel taking 5% of scrap
wastage in place of 3%
wastage: -
I) Steel difference Rs.1,75, 132.00
II) M.S. Found Steel Rs. 1,806.42
III) 12 Dia M.S. Rs. 68,750.00
IV) Structural Steel Rs. 2,513.28
V) Steel Plates Rs. 2,649.84
VI) Scrap made in Rs.12,000.00
labour rates
Total Rs.2,62,850.70 Rs.1,82,463. 70
d) Unreasonable recoveries:-
i) Cribes Rs. 3,747.75
ii) Shutter plates Rs. 38,322.65
iii) B.F.P. Hire charges Rs. 15,776.31
for shutter plates
iv) B.F.P. Hire charges Rs. 64,521.00
for shutter plates
v) Refund of 28% Rs. 60,833.00
overhead supply for
metal
vi) Dozer recovery for Rs. 10,676.00
work order No. 48/4
vii) Cubes failure (never Rs. 34,701.92
given in writing of
any cube failure of
any member)
viii) Chain pulley block Rs. 8,000.00
(not with us)
ix) Clamps (already Rs. 14,990.00
returned)
2114 [2025] 5 S.C.R.
Supreme Court Reports
x) Pipes (already Rs. 89,353.00
returned)
Total Rs.3,40,921.63 Rs.60,833.00
e) Work order by other Rs.84,447.00 Rs.84,447.00
agencies but not in our
scope like plastering etc.
f) Held amounts:-
i) Amount held on Rs.3,95,000.00
account of grouting
T.G.
ii) Amount held on Rs.20,000.00
account of grouting
C.E.P.
iii) Staging held amount Rs.3,09,203.14
of T.G.
iv) Work order No. 48/4 Rs.43,000.00
withheld amount
v) Work Order No. Rs.51,803.00
47/11 withheld
amount
vi) Work Order No. 48/4 Rs.23,000.00
shutter plates held
vii) Curing held amount Rs.3,000.00
48/4
viii) Work order No.48/4 Rs.10,000.00
E.S.P. rectification
held amount
ix) Work order No.48/4 Rs.5,000.00
T.G. held amount for
final shape.
Total Rs.8,60,004.14 Rs.8,60,004.14
g) Balance payable in bills
i) Payable in bills 47/11 Rs.64,376.76
ii) S.D. 47/11 total Rs.2,02,870.00
balance
iii) Work order No. 48/4 Rs.84,000.00
money payable in
bills
Total Rs.3,51,246.76
[2025] 5 S.C.R. 2115
M/s Interstate Construction v.
National Projects Construction Corporation Ltd.
h) Difference in excavation Rs.1,31,464.00
i) Booking of C.E.P. in Rs.17,690.00
package-IV as agreed by
E.D.S.R. differences
j) Claims of not allotting quarry Rs.2,66,000.00
as agreed by E.D.S.R.
k) 1200 M3 of stone aggregate Rs.13,40,000.00
from Karim Nagar for rate
differences of Rs. 70/- M3
extra and the claim was
agreed by EDSR referred
to our letter ISC/ Claims/1
Dt.14.10.89 para III.
l) Idle labour charges refer Rs.4,81,000.00
our letter ISC/Claims/1 dt.
14.10.89, para IV
m) 2% interest rate difference Rs.50,000.00
on mobilization advance.
n) Interest on delayed release Rs.2,40,000.00
of S.D. refer para 9 of
our letter ISC/Claims/1 dt.
14.10.89.
o) Mental anguishes, torture Rs.60,00,000.00
and loss of social status
suffered refer Letter No.
ISC/ Claims/1 dt. 14.10.89
para II.
p) Addl. 24% interest for 10.5 Rs.3,19,57,039.0
years w.e.f. July 1987 upto
Dec. 1997.
Total Rs.4,46,38,404.00 Rs.34,43,490.61
23. We have already extracted the nature of interest payment provided in
the award dated 28.10.2020. However, for ready reference, interest
awarded to the appellant by the arbitral tribunal may once again be
noted which is as under:
(a) Pre-reference/past period interest at the rate of
18% per annum on the sum of Rs. 34,43,490.61 with
effect from July 1987 uptill 19.01.1998.
2116 [2025] 5 S.C.R.
Supreme Court Reports
(b) Pendente lite interest at the rate of 12% per
annum with effect from 20.01.1998 uptill 31.12.2008
on the total amount (that is, principal amount plus the
amount of interest for the pre- reference/past period).
(c) Pendente lite interest at the rate of 12% per annum
with effect from 01.01.2017 till the date of the award
on the total amount (that is, principal amount plus
the amount of interest on the pre- reference period
and for the period from 20.01.1998 till 31.12.2008).
(d) Future interest at the rate of 18% per annum from
the date of the award till the date of payment on the
total amount (that is, principal amount added to the
amount of interest for the pre-reference/past period
and interest pendente lite).
23.1. While holding that appellant was entitled to award of interest
for the pre-reference period i.e. from the date on which the
cause of action arose till filing of the claim before the arbitral
tribunal as well as for the pendente lite period and also for the
future period, arbitral tribunal agreed with the respondent that
no interest should be awarded to the appellant for the period
when there was absolute laches on the part of the appellant.
Arbitral tribunal held that for the period from 01.01.2009 till
31.12.2016, that is for a period of about eight years, there was
complete laches on the part of the appellant. Therefore, the
arbitral tribunal declared that appellant would not be entitled
to any interest for the aforesaid period.
24. Respondent filed a petition under Section 34 of the 1996 Act before the
High Court impugning the arbitral award dated 28.10.2020. Vide the
judgment and order dated 02.08.2021, learned Single Judge upheld
the claims awarded by the arbitral tribunal. On the question of interest,
learned Single Judge framed the question as to whether interest
awarded by the arbitral tribunal was exorbitant and unsustainable.
Learned Single Judge held that arbitral tribunal’s decision to award
pre-reference interest at the rate of 18 percent per annum did not
warrant any interference. As regards pendente lite interest, learned
Single Judge while noting that arbitral tribunal had awarded 12 percent
interest per annum for the period from 20.01.1998 till 31.12.2008 and
again from 01.01.2017 till 28.10.2020, justified the decision of the
[2025] 5 S.C.R. 2117
M/s Interstate Construction v.
National Projects Construction Corporation Ltd.
arbitral tribunal not to award interest for the period from 01.01.2009
to 31.12.2016 as during this period the appellant was remiss and
did not pursue its claim before the arbitral tribunal diligently. On the
rate of interest, learned Single Judge held that interest at the rate of
12 percent per annum could not by any stretch be considered to be
exorbitant or unreasonable but held that 18 percent future interest
from the date of the award till the date of payment granted by the
arbitral tribunal was ex facie erroneous as according to learned Single
Judge the interest rate should have been 2 percent higher than the
current rate of interest prevalent on the date of the award. Therefore,
this portion of the award was set aside by the learned Single Judge;
instead learned Single Judge awarded future interest holding that it
could not have been in excess of 9 percent per annum. Therefore,
learned Single Judge partly allowed the petition under Section 34 of
the 1996 Act to the extent of setting aside the award of future interest
at a rate exceeding 9 percent per annum from the date of the award
till the date of payment.
25. This brings us to the impugned judgment and order dated 01.08.2023.
We have already noted about the limited nature of challenge made
by the respondent during the hearing of the appeal filed under
Section 37 of the 1996 Act. Learned senior counsel appearing
for the respondent clarified that the challenge to the award stood
restricted to the directions issued by the arbitral tribunal insofar the
issue of interest was concerned. He clarified that the challenge was
not with respect to either the rate at which interest was awarded or
the grant of interest for the pre-reference/past period. The grievance
was confined to the directions contained in paragraph 58(b)(i) of
the award and the similar nature of interest in paragraph 58(b)(ii)
inasmuch as the arbitral tribunal proceeded to award interest on
identical terms: on the principal amount plus the amount of interest
for the pre-reference/past period. Division Bench referred to Section
31(7)(a) and (b) of the 1996 Act as well as placed reliance on the
decision of this Court in Sayeed Ahmed and Company Vs. State of
Uttar Pradesh1 and came to the following two conclusions:
i) Section 31(7) recognizes only two periods for which
interest may be awarded. The two periods are, firstly from
1 (2009) 12 SCC 26
2118 [2025] 5 S.C.R.
Supreme Court Reports
the date on which the cause of action arose till passing
of the award and secondly from the date of the award till
actual payment. Therefore, the distinction between pre-
reference/past period and pendente lite period no longer
existed. The period from the date of cause of action i.e.
July, 1987 till the date of the award dated 28.10.2020
would constitute the period contemplated under Section
31(7)(a) of the 1996 Act. The period commencing from
the date of award till payment would be the second period
within the meaning of Section 31(7)(b) of the 1996 Act.
Therefore, the arbitral tribunal committed an illegality in
awarding interest for three periods: pre-reference/past
periods, pendente lite and for the future period.
ii) Arbitral tribunal committed further illegality in forging
the principal amount with interest as would be evident
from paragraph 58(b) of the award. Interest awarded for
the pre-reference period as well as for the pendente lite
period have been subjected to further levy of interest
for the said periods by adding the interest amount with
the principal amount awarded. This amounted to levying
compound interest which is impermissible. Accordingly, the
directions contained in paragraph 58(b) were set aside by
the Division Bench.
26. In our considered view, the reasonings given by the Division Bench
are fallacious. We say so for the reasons mentioned hereunder.
27. Section 31 of the 1996 Act is the relevant provision. It deals with the
form and contents of arbitral award. Section 31 has eight sub-sections.
Sub-section (7) is central to the debate and after the amendment
with retrospective effect from 23.10.2015 read as under:
31. Form and contents of arbitral award -
* * * * *
(7)(a) Unless otherwise agreed by the parties, where
and in so far as an arbitral award is for the payment
of money, the arbitral tribunal may include in the sum
for which the award is made interest, at such rate
as it deems reasonable, on the whole or any part of
the money, for the whole or any part of the period
[2025] 5 S.C.R. 2119
M/s Interstate Construction v.
National Projects Construction Corporation Ltd.
between the date on which the cause of action arose
and the date on which the award is made.
(b) A sum directed to be paid by an arbitral award
shall, unless the award otherwise directs, carry
interest at the rate of two per cent higher than the
current rate of interest prevalent on the date of award,
from the date of award to the date of payment.
27.1. Before substitution and prior to 23.10.2015, clause (b) of sub-
section (7) of Section 31 stood thus:
(b) A sum directed to be paid by an arbitral award
shall, unless the award otherwise directs, carry
interest at the rate of eighteen per centum per annum
from the date of the award to the date of payment.
28. We now come to the analysis of Section 31(7), both clauses (a)
and (b). For the time being we concentrate on clause (a) insofar it
deals with the period for which interest may be awarded. A reading
of clause (a) reveals that interest may be for the whole or any part
of the period between the date on which the cause of action arose
and the date on which the award is made. In real terms it means the
period from the date on which the cause of action arose till filing of
the claim petition by the claimant and from the date of filing of the
claim petition till the date of the award. Division Bench of the High
Court relied upon Sayeed Ahmed and Company (supra) wherein this
Court analyzed Section 31(7) of the 1996 Act and opined that the
difference between pre-reference period and pendente lite period has
disappeared insofar award of interest by the arbitrator is concerned.
The said section now recognizes only two periods and makes the
following provision:
i) In regard to the period between the date on which the
cause of action arose and the date on which the award is
made (pre-reference period + pendente lite), the arbitral
tribunal may award interest at such rate as it deems
reasonable for the whole or any part of the period unless
otherwise agreed by the party;
ii) For the period from the date of award to the date of
payment, interest at the rate of 18 percent per annum
(this is in reference to the pre 23.10.2015 position) if no
2120 [2025] 5 S.C.R.
Supreme Court Reports
specific order is made in regard to interest; however, the
arbitrator may award interest at a different rate for the
period between the date of award and the date of payment.
29. Based on the aforesaid decision, the Division Bench held that it was
not open for the arbitral tribunal to have carved out three periods for
payment of interest: pre-reference, pendente lite and future when the
statute provides for only two periods: first period being the period
between the date on which the cause of action arose and the date
on which the award is made and the second period is from the date
of the award till the date of payment.
30. We are unable to agree with the view expressed by the Division
Bench. Even in Sayeed Ahmed and Company (supra) relied upon by
the Division Bench, the Bench held that Section 31(7) had carved out
two periods, the first period being from the date on which the cause
of action arose till the date on which the award is made and the
second period being from the date of award till the date of payment.
As regards the first period, the Bench clarified that it includes the
pre-reference period plus pendente lite period. Though the arbitral
tribunal had granted interest for three periods: pre-reference period,
pendente lite and post award period, the first two period basically
comprises of the period contemplated under clause (a) of sub-section
(7) of Section 31. It is another matter that the arbitral tribunal awarded
varying degrees of interest for the two sub-periods: 18 percent per
annum for the pre-reference period and 12 percent as pendente lite,
excluding from the said period, the period of eight years when the
appellant was found to be remiss in pursuing its claims before the
arbitral tribunal. This is also permissible as we shall explain.
31. Therefore, Sayeed Ahmed and Company (supra) does not exclude or
does not say that interest should not be granted for the pre-reference
period. All that it explains is that Section 31(7)(a) has joined the two
periods of interest: pre-reference and pendente lite.
32. This position has been clarified by a recent decision of this Court
in Pam Developments Private Limited Vs. State of West Bengal2.
After extracting Section 31(7) of the 1996 Act, this Court held that
power of the arbitrator to grant pre-reference interest, pendente lite
2 (2024) 10 SCC 715
[2025] 5 S.C.R. 2121
M/s Interstate Construction v.
National Projects Construction Corporation Ltd.
interest and post award interest under Section 31(7) of the 1996 is
now fairly well settled. The Bench, thereafter, culled out the following
legal propositions in this regard highlighting the difference in the
position of law qua the Arbitration Act, 1940 vis-à-vis the 1996 Act:
23. The power of the arbitrator to grant pre-reference
interest, pendente lite interest, and post-award interest
under Section 31(7) of the Act is fairly well-settled. The
judicial determinations also highlight the difference in
the position of law under the Arbitration Act, 1940. The
following propositions can be summarised from a survey
of these cases:
23.1. Under the Arbitration Act, 1940, there was no
specific provision that empowered an arbitrator to grant
interest. However, through judicial pronouncements,
this Court has affirmed the power of the arbitrator to
grant pre-reference, pendente lite, and post-award
interest on the rationale that a person who has
been deprived of the use of money to which he is
legitimately entitled has a right to be compensated
for the same. When the agreement does not prohibit
the grant of interest and a party claims interest, it
is presumed that interest is an implied term of the
agreement, and, therefore, the arbitrator has the
power to decide the same.
23.2. Under the 1940 Act, this Court has adopted a
strict construction of contractual clauses that prohibit
the grant of interest and has held that the arbitrator
has the power to award interest unless there is
an express, specific provision that excludes the
jurisdiction of the arbitrator from awarding interest
for the dispute in question.
23.3. Under the 1996 Act, the power of the arbitrator
to grant interest is governed by the statutory provision
in Section 31(7). This provision has two parts. Under
clause (a), the arbitrator can award interest for the
period between the date of cause of action to the
date of the award, unless otherwise agreed by the
parties. Clause (b) provides that unless the award
2122 [2025] 5 S.C.R.
Supreme Court Reports
directs otherwise, the sum directed to be paid by
an arbitral award shall carry interest @ 2% higher
than the current rate of interest, from the date of the
award to the date of payment (referring to the post
23.10.2015 position).
23.4. The wording of Section 31(7)(a) marks a
departure from the Arbitration Act, 1940 in two ways :
first, it does not make an explicit distinction between
pre-reference and pendente lite interest as both of
them are provided for under this sub-section; second,
it sanctifies party autonomy and restricts the power
to grant pre-reference and pendente lite interest the
moment the agreement bars payment of interest,
even if it is not a specific bar against the arbitrator.
23.5. The power of the arbitrator to award pre-
reference and pendente lite interest is not restricted
when the agreement is silent on whether interest can
be awarded or does not contain a specific term that
prohibits the same.
23.6. While pendente lite interest is a matter of
procedural law, pre-reference interest is governed by
substantive law. Therefore, the grant of pre-reference
interest cannot be sourced solely in Section 31(7)(a)
(which is a procedural law), but must be based on an
agreement between the parties (express or implied),
statutory provision (such as Section 3 of the Interest
Act, 1978), or proof of mercantile usage.
24. In view of the above, the High Court had no reason
to interfere with the arbitral award with respect to grant
of pre-reference interest, since the contract between the
parties does not prohibit the same.
33. This position has been further explained by a recent decision of
this Bench in North Delhi Municipal Corporation Vs. S.A. Builders
Ltd.3. After adverting to Section 31(7) of the 1996 Act, this Court
explained as under:
3 (2024) SCC Online SC 3768
[2025] 5 S.C.R. 2123
M/s Interstate Construction v.
National Projects Construction Corporation Ltd.
36.1. From a minute reading of sub-section (7), it is
seen that it has got two parts: the first part i.e. clause
(a) deals with passing of award which would include
interest up to the date on which the award is made.
The second part i.e. clause (b) deals with grant of
interest on the ‘sum’ awarded by the arbitral tribunal.
33.1. Thereafter the Bench observed that under Section 31(7) of
the 1996 Act, an arbitral tribunal has the power to grant –
(i) pre-award (ii) pendente lite (iii) post-award interest. The
Bench explained the reason for award of such interest in the
following manner:
39. Generally, going by the provisions contained in
Section 31(7) of the 1996 Act, it is evident that an
arbitral tribunal has the power to grant (i) pre-award
(ii) pendente lite (iii) post-award interest. Intention
behind awarding pre-award interest is primarily to
compensate the claimant for the pecuniary loss
suffered from the time the cause of action arose till
passing of the arbitral award. Further, this is also to
ensure that the arbitral proceeding is concluded within
a reasonable period to minimise the impact of the
pre-award interest as well as interest pendente lite;
thereby promoting efficiency in the arbitration process.
Similarly, grant of post-award interest also serves a
salutary purpose. It primarily acts as a disincentive to
the award debtor not to delay payment of the arbitral
amount to the award holder.
34. Thus, what Section 31(7)(a) has done is that there is now a statutory
recognition of the power of the arbitral tribunal to grant pre-reference
interest from the date on which the cause of action arose till the date
on which the award is made. There was a vacuum in the Arbitration
Act, 1940 as there was no such provision for granting pre-reference
interest. It was through judicial pronouncements that such power
of the arbitrator to grant pre-reference interest was conferred. Now
under Section 31(7)(a) of the 1996 Act, such power is statutorily
recognized.
35. Let us revert back to clause (a) of sub-section (7) of Section 31
of the 1996 Act. A careful and minute reading of this provision will
2124 [2025] 5 S.C.R.
Supreme Court Reports
make it clear that the arbitral tribunal has the discretion to include
in the sum awarded interest at such rate as it deems reasonable on
the whole or any part of the money awarded for the whole or any
part of the period from the date on which the cause of action arose
till the date on which the award is made. We may exclude that part
of the sentence ‘on the whole or any part of the money’ from our
analysis since this is not relevant to the controversy. If we exclude
this portion, what then becomes discernible is that the arbitral tribunal
has the discretion to include in the sum awarded : firstly, interest
at such rate as it deems reasonable; and secondly, for the whole
or any part of the period between the date on which the cause of
action arose and the date on which the award is made. This would
mean that the arbitral tribunal can exclude a period from the date on
which the cause of action arose till the date on which the award is
made for the purpose of grant of interest, as has been done in the
present case. It would also mean that the arbitral tribunal can grant
interest for the whole or any part of the period between the date on
which the cause of action arose and the date on which the award is
made. It can be a composite period or the said period can be further
sub-divided, as done in the present case i.e. from the date of cause
of action to filing of the claim and from the date of filing of the claim
till the date of the award excluding the period when the appellant
was found to be remiss. It would also mean that there can be one
rate of interest for the whole period or one or more rates of interest
for the sub-divided periods as has been done in the instant case. In
our opinion, this would be the correct approach to interpret Section
31(7)(a), given the scheme of the 1996 Act.
36. That being the position, we are of the view that the Division Bench had
fallen in error by holding that the arbitral tribunal had no jurisdiction
to award interest for two periods i.e. pre-reference and pendente
lite when the statute provides for only one period viz. from the date
when the cause of action arose till the date of the award. The view
expressed by the High Court is not the correct interpretation of
Section 37(1)(a) of the 1996 Act as explained by us supra as well
as in Pam Developments Private Limited (supra) and S.A. Builders
Ltd. (supra).
37. This brings us to the second issue on which the High Court set aside
the directions of the arbitral tribunal contained in paragraph 58(b) of
the award. According to the Division Bench, the arbitral tribunal had
[2025] 5 S.C.R. 2125
M/s Interstate Construction v.
National Projects Construction Corporation Ltd.
committed an illegality in forging the principal amount with interest
while computing the awarded amount on which future interest is to
be paid. Interest awarded for the past period could not have been
subjected to further levy of interest during the pendente lite or post
award period on merger with the principal amount as this would
amount to levy of compound interest.
38. This aspect of the matter is no longer res integra.
39. In State of Haryana Vs. S.L. Arora4, a two-Judge Bench of this
Court observed that as regards pre-award period, interest has to
be awarded as specified in the contract and in the absence of any
contract, as per the discretion of the arbitral tribunal. However, with
regard to the post-award period, the interest is payable as per the
discretion of the arbitral tribunal and in the absence of exercise of
such discretion, at the mandatory statutory rate of 18 percent per
annum. Award of interest like award of cost are ancillary matters.
Therefore, the expressions sum for which the award is made and the
sum directed to be paid by an arbitral award contextually refers to the
award on the substantive claims and not ancillary or consequential
directions relating to interest or cost. It was held that arbitral tribunals
did not have the power to award interest upon interest or compound
interest either for the pre-award period or for the post-award period.
40. A three-Judge Bench of this Court in Hyder Consulting (UK) Ltd. Vs.
Governor, State of Orissa5, opined that it was not possible to agree
with the conclusion in S.L. Arora (supra) that Section 31(7) of the
1996 Act does not require that interest which accrues till the date
of the award be included in the sum from the date of the award for
calculating the post-award interest. Justice Bobde (as His Lordship
then was) authoring the majority opinion was of the view that the
conclusion reached in S.L. Arora (supra) did not seem to be in
consonance with the clear language of Section 31(7) of the 1996
Act. Hyder Consulting (UK) Ltd. (supra) declared that S.L. Arora
(supra) was wrongly decided in that it held that a sum directed to
be paid by an arbitral tribunal and the reference to the award on the
substantive claim did not refer to interest pendente lite awarded on
the sum directed to be paid upon award and that in the absence of
4 (2010) 3 SCC 690
5 (2015) 2 SCC 189
2126 [2025] 5 S.C.R.
Supreme Court Reports
any provision of interest upon interest in the contract, the arbitral
tribunal did not have the power to award interest upon interest or
compound interest either for the pre-award period or for the post-
award period. It has been clarified that the ‘sum’ includes the principal
as adjudged together with the interest granted.
41. A three-Judge Bench of this Court in UHL Power Company Ltd. Vs.
State of Himachal Pradesh6 declared that the judgment in S.L. Arora
(supra) has since been overruled by a three-Judge Bench of this
Court in Hyder Consulting (UK) Ltd. (supra). The majority view in
Hyder Consulting (UK) Ltd. (supra) is that post-award interest can
be granted by an arbitrator on the interest amount awarded.
42. This view was reiterated by this Court in subsequent decisions
(please see Delhi Airport Metro Express Private Ltd. Vs. Delhi Metro
Rail Corporation7 and Morgan Securities and Credits Private Ltd. Vs.
Videocon Industries Limited 8).
43. Finally, in S.A. Builders (supra), this Bench after a thorough analysis
of Section 31(7)(a) and Section 31(7)(b) of the 1996 Act came to
the following conclusion:
38. Natural corollary to the above analysis would be that the
‘sum’ so awarded by the arbitral tribunal which may include
interest from the date when the cause of action arose to
the date of the award, would carry further interest of 18
percent from the date of the award to the date of payment
unless the arbitral award otherwise directs (referring to the
pre 23.10.2015 position). Thus, the legislative intent is that
the awarded sum whether inclusive of interest or not, in
case included, then from the date of cause of action to
the date of award, would carry further interest from the
date of the award to the date of payment.
44. It has been held that the sum awarded would mean the principal
amount plus the interest awarded from the date of cause of action
upto the date of the award. The sum awarded in Section 31(7)(a)
would mean principal amount plus the interest awarded. Thereafter,
6 (2022) 4 SCC 116
7 (2022) 9 SCC 286
8 (2023) 1 SCC 602
[2025] 5 S.C.R. 2127
M/s Interstate Construction v.
National Projects Construction Corporation Ltd.
as per Section 31(7)(b) of the 1996 Act, the sum (principal amount +
interest) would carry further interest at the rate of 2 per cent higher
than the current rate of interest prevalent on the date of the award
to the date of payment.
45. Therefore, in view of the clear legal position delineated as above,
impugned judgment of the Division Bench dated 01.08.2023 cannot
be sustained.
46. Thus, having regard to the discussions made above, impugned
judgment and order dated 01.08.2023 passed by the Division Bench
of the High Court is hereby set aside. Civil appeal is accordingly
allowed. However, there shall be no order as to cost.
Result of the case: Appeal allowed.
†
Headnotes prepared by: Nidhi Jain
Search Indian case law
Ask in plain English, not just keywords. 25,000 AI words free, no card.