Created byFuzzy Cloud

Supreme Court of India

NATIONAL FERTILIZERSversusPURAN CHAND NANGIA

Citation
2000 INSC 485
Decided
17 October 2000
Disposal
Dismissed

Holding

The arbitrator acted within jurisdiction; the ±25% clause is to be applied to the aggregate of all variations, and the award of 50% of the extra claim is valid.

Summary

National Fertilizers Ltd. awarded a works contract to Puran Chand Nangia for 48% of a Rs. 3.39 crore project. The contract contained a clause that quoted rates would remain firm for variations up to ±25% of the contract price, beyond which market rates could apply. After the work was varied both upwards and downwards, the total variation exceeded 25%, and the contractor claimed higher rates. The arbitrator, appointed by consent, awarded the contractor 50% of the claimed escalation and rejected the appellant’s cross‑claim for delay. The trial court set aside the award on a technical ground, but the High Court restored it. On appeal, the Supreme Court held that the variation clause must be interpreted by aggregating all plus and minus variations, that the arbitrator’s construction was reasonable, and that awarding 50% of the extra claim did not exceed his jurisdiction. Consequently, the appeal was dismissed.

Issues considered

  • The proper interpretation of the ±25% variation clause – whether it applies to net increase after offsetting additions and deletions or to the aggregate of all variations.
  • Whether the arbitrator exceeded his jurisdiction by granting higher rates and by fixing a flat 50% of the escalation claim.
  • Whether a non‑speaking award can be examined for errors of law or jurisdiction.

Legislation cited

Subjects

ArbitrationWorks contractVariation clauseRate escalationJurisdiction of arbitratorNon‑speaking awardContract lawIndian Arbitration Act

Judgment

A                            NATIONAL FERTILIZERS
                                      v.
                             PURAN CHAND NANG IA

                                 OCTOBER 17, 2000

B         [M. JAGANNADHA RAO AND K.G. BALAKRISHNAN, JJ.)


           Arbitration :

           Works contract-Acceptance of tender-Applicability of quoted rates
C for a variation upto ± 25% of contract value and higher market rates beyond
    the variation-Claim for higher rates-Arbitrator awarding 50% of higher
    rates-Jurisdiction of arbitrator-Held, on facts, there is no error of law in
    the award of the arbitrator.

D         Works contract-Changes in terms of contract-Held, the terms of
    contract cannot be altered unilaterally to the detriment of opposite party.

            Appellant-company invited quotations for works amounting to Rs.
     3,39,88,000. The quotation of respondent-contractor was accepted and was
     given 48% of the work only. The work order issued by the appellant consisted
E    a clause stating that the quoted rates of the respondent is applicable for a
     variation upto ±. 25% of contract value beyond which higher market rates
     would be applicable. Original date of completion of work was extended by 4
     months. The respondent submitted a final bill at higher rates since the
     variations went above 25% of the contract value. The appellant, besides holding
     the respondent for delay in completion of work, rejected the bill stating that
F   the higher rates is justified only if the total contract value of the work has
    increased or decreased by 25% and not on account of any increase or decrease
    in the quantity of individual items. Further, the appellant made a cross-claim
    from the respondent for compensation of Rs. 7.64 lakhs on account of delay
    in completion since another contractor had to be appointed for completing
                                                                                       .•
G   the work. On reference of the disputes to arbitration, arbitrator gave a non-
    speaking award. The arbitrator awarded 50% of the.extra claim to the
    respondent and rejected the claim of the appellant for compensation. On appeal
    Trial Court set aside the award of the arbitrator on the ground that the
    reference was bad and gave alternative finding!'. High Court, allowing the
    appeal of the respondent, held that the reference was maintainable and directed
H                                          26
                 NA TI ON AL FERTILIZERS v. PU RAN CHAND NANG IA               27
 that the award be made a Rule of Court.                                             A
       In appeal to this Court, the appellant contended that tlie arbitrator acted
beyond his jurisdiction in granting higher rates for the work done upto the
extended date, which was contrary to the work order issued; that the higher
rates are applicable only if the net difference between the increases and
decreases works out to more than 25% of the contract value; that the variation       B
limit of±25% of the contract price was applicable on the total contract price
and not on individual quantities or items; and that the award by the arbitrator
at a flat rate of 50% of the extra claim is contrary to the terms and conditions
of the tender.

      The respondent contended that if the sum total of the variations, both         C
plus and minus, exceeded 25%, the market rates are applicable; and that the
Trial Court has found as a finding, that the sum total of the additions and
deletions in the work exceeded l 00%.

       Dismissing the appeal, the Court
                                                                                     D
        HELD: 1.1. The concept of variation of the question of work is a common
  feature of works contracts. This is because in contracts relating to major
  works, the estimates of work at the time of inviting the tenders can only be
  approximate. But the power of the employer to vary the terms relating to the
  quantum of work cannot be unlimited. Under the general law of Contracts,           E
. once the contract is entered into, any clause giving absolute power to one
  party to override or modify the terms of the contract at his sweet will or to
  cancel the contract - even if the opposite party is not in breach - will amount
  to interfering with the integrity of the contract. f35-E; 36-BJ

       1.2. The variation clause was understood by the arbitrator in a               F
 reasonable manner as being applicable to a case where the value of the sum
total of the additions and deletions exceeded 25% of the contract price. That
construction cannot be said to be vitiated by any serious error of law. When
a contractor bids in a contract, he has to offer reasonable rates for the works
which are both difficult to perform and others works, which are not difficult        G
to perform. Every contractor tries to balance his rates in such a manner that
the employer may consider his offer reasonable. In that process the contractor
tries to get a reasonable margin of profit by balancing the more difficult and
less profitable items and the less difficult and more profitable items. His bid
is, normally, a package. If the employer is permitted in law to make variations
upwards and downwards - even if it be upto a limit beyom' which market rates         H
    28                       SUPREME COURT REPORTS [2000) SUPP. 4 S.C.R.

A   become payable - then th~ interpretation of the clause must be one which
    balances the rights of both parties. If the plus and minus variations go beyond
    25% and are made in a manner increasing the less profitable items and
    decreasing the more profitable items, and if the net l'esult of the contract is
    to be the basis, then it may work out that the contractor could be made to
    J}erform a substantially new contract on the same contracted r;ltes. lfthe said
B   reasoning of the appellant is accepted and if, in a given case, the value of the
    increases in unprofitable items is 50% of the contracfvalue and the value of
    the reductions of the remaining more profitable items is 50o/o of the contract
    value, it could still be contended for the appellant that the net variation was
    nil, even though that was a situation where the contract had been substantially
C   mOdified and was almost a different contract from the one stipulated. Such an
    unreasonable construction is to be avoided and was rightly avoided by the
    aroitrator. (37-H; 38-H-El

          1.3. The additions and decreases in work are both independent for the
    purpose of finding out the plus/minus 25% variation and have to be pooled
D   together. The arbitrator was right in thinking that the case fell within the
    exception. In the result, the interpretation put on the clause by the arbitrator
    is quite reasonable and very plausible and it cannot therefore be said that the
    award is vitiated by any error of law affecting his jurisdiction. 138-Fl

          Union of India v. Maddali Thathiah, 1196413 SCR 61 =AIR (1966) SC
E   1724;. Central Bank of India v. H.F. Insurance Co., AIR (1965) SC 1288; S.
    Harcharan Singh v. Union of India, (19901 4 SCC 647; Himachal Pradesh
    State Electricity Board v. .R.J. Shah & Co., (1999( 4 SCC 214; Hindustan
    Construction Co. ltd. v. State of J&K, 119921 4 SCC 217 and K.R.
    Ravendranathan v. State of Kera/a, 1199819 SCC 410, referred to.
F         Maddal/i Thathiah v. Union of India, AIR (1957) Mad. 82, referred to.

          Naylor, Benson & Co. v. Krarinische Industries Gessellschatt, (1918) 1
    KB 331; Parkinson (Sir Lindsay) & Co. ltd v. Commissfoners of Works and
    Public Buildings, (1949) 2 KB 632 and Bush v. Whitehaven Town & Harbour
G   Trustees, 1 (1988) 52 J.P. 392, referred to.                       ·

          Hudson's Building and Engineering Contracts, 8th Edition Pages 294-
    296; Mulla's Contract Act 10th Edition Pages 371-372 and Gajaria's law
    Relating to Building and Engineering Contracts in India 3rd Edition·Pages
    410-412, referred to~

H        2.1. The contention of the appellant that the arbitrator has awarded at a
    NATIONAL FERTILIZERS''· PURAN CHAND NANG IA [M.JAGANNADHA RAO, J.)        29

flat rate of 50% of the extra claim is not accepted both on law and on facts.       A
The arbitrator cannot be said to have acted illegally on facts for he has not in
fact granted at the full market rate claimed by the contractor but has only
granted at 50% of the claim. In the case of non-speaking award, it is not
permissible for the Court to probe into the mental process of the arbitrator
when he rejected 50% of the claim in favour of the appellant and accepted
50% of the claim in favour of the contractor. Therefore, the award cannot be        B
said to be bad merely because the increase was at a flat rate. The arbitrator
was appointed by consent and he was a former General Manager in the
Railways and was also associated with the appellant corporation. There is no
error apparent on the face of the record in the award of50% of the escalation
claimed and in the claim upto the extended date. 139-E-HI                           C
     Hindustan Steel Works v. Rajeswar Rao, 119871 4 SCC 93; P. M Paul v.
Union of India, 119891Suppl.1 SCC 358 and Himachal Pradesh Nagar Vikas
Pradhikaran v. Mis. Aggarwal & Co., AIR (1997) SC 1027, relied on.

      CIVIL APPELLATE JURISDICTION: Civil Appeal No. 1329of1995.                    D
     From the Judgment and Order dated 18. l 0.1994 of the Madhya Pradesh
High Court in C.M. (First) A. No. 211 of 199 l.

      Bhasker P. Gupta, Pinaki, S. Saxena and G. Joshi for the Appellant.

      S. Ganesh, Vijay Kumar and Ms. Sangeeta Kumar for the Respondent.             E
      The Judgment of the Court was delivered by

       M. JAGANNADHA RAO, J. This appeal, which arises out of an award
passed under the Indian Arbitration Act, I 940 concerns the interpretation of
a 'variation' clause in the contract which allows the appellant, the National       F
Fertilizers Ltd., to issue directions to the contractor varying the extent of the
contract work, both upwards and downwards upto 25%. Question is whether
(as contended by the appellant) the said 25% is to be arrived at by taking
into account the net overall increase in the work i.e. by adding up the
increases in work and deducting therefrom the decre~es in work or whether
(as contended for the respondent-contractor) the 25% was to be computed             G
by adding up the total variations, both involving the increase in the work and
the decrease in the work. The importance of the point is that if the variations
exceed 25% of the contract price, the contractor is not confined to the
contract rates but can claim market rates.
      The disputes were referred to arbitration and the arbitrator gave a non-      H
     30                      SUPREME COURT REPORTS [2000) SUPP. 4 S.C.R.

A   speaking award. The arbitrator's award was set aside by the learned District
    Judge on the ground that the reference was bad. He, however, gave alternative
    findings accepting the conclusions in the award. As the learned District
    Judge held the reference was bad, he set aside the award. The contractor
    appealed to the High Court which by its judgment in Civil Misc. (First) Appeal
    No. 211 of 1991 dated 18. I 0.94 held the reference was valid and allowed the
B   appeal and directed the award be made Rule of Court. It is against the said
    judgment that this appeal is prefefred.

           The facts of the case are as follows. Quotations were called by the
    appellant for works amounting to Rs. 3,39,88,000. It appears that the
C   respondent submitted his quotation which was opened on 12.9.1984. His
    tender was accepted. But, instead of giving him the entire contract, the
    appellant awarded only 48% of the work of Rs. 3,39,88,000 amounting to Rs.
    1,52,94,235, by letter dated 5.11.1984. Part I of the work was upto Rs.
    94,34,323 and Part II was upto Rs. 94,34,323 .. Subsequently, letter of intent was
    issued on 5/6.11.1984 and then a work order was issued on 22.1.1985. The said
D   letter dated 22.1.1985 of the appellant contained the ± 25% clause which
    permitted rates higher than the contract rates to be paid, as an exception.
    It stated as follows:

            "The contract price has been arrived at on the basis of your quoted
            rates in your tender and the enclosed schedule of quantities, your
E           quoted rates shall hold good for a variation of 25% (plus/minus
            twenty five perc~nt) of the contract price stated in this work order,
            beyond which your quoted rates will be suitably revised subject to
            mutual agreement."

F          It appears the site was not made available on time and there were lot
    of disputes between the parties. There was corresp~ndence between the
    appellant and respondent. The appellant varied the works both upwards and
    downwards. As, according to the contractor, the sum total of variations went
    above 25% of the contract value, the contractor asked for higher rates in his
    letters dated 20.11.1986, 8.12.1986 and 9.12.1986. The final bill was submitted
G   by the contractor on 9.12.1986 for Rs. 85,98,705 as detailed in the Annexure
    A thereto. This plea for extra rates was rejected on 31.12.1986 by the appellant
    stating that the ± 25% clause applied to the overall net increase. The letter
    stated :

            " ...... no enhancement is justified unless the total contract value of
H          the work has increased or decreased by 25%. Enhancement of rates
,-




              NATIONAL FERTILIZERS"· PURAN CHAND NANGIA [M.JAGANNADHA RAO,J.]              3l

                  is therefore not on account of any increase or decrease in the quantity        A
                  of individual items ....... on completion of the enti[e work, it is expected
                  that there will not be any variation in the contract value within the
                  limits of± 25%."

                The letter also blamed the contractor for delay in the work.
                                                                                                 B
                It is.not denied that the original date of completion was 30.6.1986 and
          was extended upto 30. I 0.1986. The total value of work done upto 30. l 0.1986,
          according to the appellant, was Rs. 1,01,84,968.58. According to the appellant,
          the Contractor abandoned the work in November, 1986. According to the
          contractor, the appellant committed breach. Another contractor was appointed
          by the appellant for the balance work and in fact, a cross claim for compensation      C
          for Rs. 7.64 lakhs was raised against the respondent.

                On 26.12.1986, the respondent claimed reference to arbitration. By
          consent, the District Court appointed Sri Dharwadkar, Ex. General Manager,
          Northern Railway, as sole arbitrator. It was stated that he was also connected         D
          with the appellant. He entered on the reference on 22.1.1988. The arbitrator
          in his award accepted the plea of the contractor for higher rates upto the
          extended date. On the disputed claim No. 4 he held as follows:

           Payment of final bill, including extra rates   50% of the revised amount
           for increase & decrease in the quantities      awarded. Balance escalation on         E
           at Rs. 80,08,000(approx.) Revised on           the original rate. only may be
     ..    17.6.1986 as Rs.70,98,852.67                   allowed upto 30.10.1986

                In other words, the arbitrator awarded 50% ofRs.70,98,852.67 towards
          increase in rates. So far as the cross claim by the appellant for compensation         F
          for delay, the arbitrator negatived the same. That would mean that the breach
          was not by the contractor.

                 The appellant filed an appeal before the District Court for setting aside
          the award. (No appeal was preferred so far as the rejection of the cross-claim)
          The District Court, as already stated, set aside the award on the ground that          G
          the reference itself was bad. But, it gave alternative findings on merits. It held
          that, as the award was not a reasoned award, but was one made on
          consideration of all documents, the NIT, the tender papers, the offer, the
          acceptance and correspondence, it was not permissible to probe into the mind
          of the arbitrator. The District Court referred to Madan Lal v. Hukum Chand,
          [I 967] I SCR I 06; Hindustan Steel Works v. Rajeswar Rao, [1987] 4 SCC 93             H
                                                                                            .,



     32                       SUPREME COURT REPORTS [2000) SUPP. 4 S.C.R.

A and held that the award was not liable to be set aside on meri.ts. The District
     Court also found (para 38) that the value of variations in the work, both
     upwards and downwards exceeded 25% and was in fact more than 100%. It
     ~:                                                                                 ~

             "Because of modifications in quantities of items of work, which the
B            respondent required the applicant to execute, the deviation difference
             was more than 100%, what to talk about 25%. Therefore, the arbitrator
             has not misconducted in awarding 50% of the claimed amount."

           It is necessary to explain what the Arbitrator meant by 'Balance of
C escalation'. As pointed by the respondent in his counter filed in this Court,
    it appears that 75% of the escalation was released by the appellant and the
    balance 25% was not paid on the ground that the appellant slowed down.
    While the matter was pending before the arbitrator, the appellant prepared a
    final bill and the balance 25% was also allowed but only upto 30.11.1985. The
    balance escalation was not allowed upto 30.10.1986, on the ground that the
D   delay was attributable to the contractor. It was this balance that was allowed
    upto 50% by the arbitrator. (These facts are clear from the reply of the
    appellant on 18.3.1988 filed before the arbitrator).

          The High Court, as already stated, held that the reference was
    maintainable and it set aside the judgment of the learned District Judge and
E   directed the award be made a Rule of Court.

           In this appeal, it was contended by the learned senior counsel for the
     appellant Sri Bhaskar P. Gupta that the arbitrator acted without jurisdiction in
                                                                                        •
     granting extra amount or higher rates for the work done upto the extended
     date 30. I 0.1986. This was prohibited by several clauses of the NIT, Special          ~-

F    and general conditions and under annexure R attached to the work order
     dated 22.1.1985. The variation limit of plus/minus 25% of the contract price
    was applicable on the 'total contract price' and not on any individual
    quantities or items. Any revision of rates would be permissible only after the
    total contract price stood increased or decreased beyond 25% on actual
G   execution and completion of the contract project. In any event, the arbitrator
    could not have allowed a uniform increase of 50% for all items.

          On the other hand, Sri S. Ganesh, learned counsel for the respondent-
    contractor contended that the question was not one of increase or decrease
    in total contract value. If the sum total of the variations i.e. both plus and
H   minus exceeded 25%, the contract rates were no longer binding and market
    NATIONAL FERTILIZERS 1>. PURAN CldAND NANG IA [M.JAGANNADHA RAO, J.]     33

rates had to be paid. The learned District Judge had found, as a fact, that the    A
sum total of the addition!:i and deletions in the work exceeded 100%. A tabular
statement in this behalf was also filed before us to show that the total
variation, both upward and downwards in the work was of a value of more
than 25% of the contract price, and in fact it was more than I 00%.

      On the above contentions, the following points arise for consideration.      B
      ( 1) Whether, in view of the various clauses in the NIT, special and
general conditions, schedules and Annexure P., the arbitrator acted without
jurisdiction in revising the rates and in ignoring the contract rates which were
to be "firm" upto date of extension of the contract?
                                                                                   c
      (2) Whether, the case fell within the exception of escalation of "±25%
of contract price". If so what was the meaning of that clause? Did it mean
the overall net increase in contract price after deducting the value of the
reduction in work from the value of the additional items of work (as contended
by the appellant) or did it mean that the plus and minus variations had to be      D
added or pooled together (as contended by the contractor) to find out if they
were together above 25% of the contract price?

     (3) Was the arbitrator wrong in granting 50% out of the escalation
claimed by the respondent?
                                                                                   E
Points I and 2:

      It is true that there are various conditions in the NIT, the Tender Form
and the Special and General Conditions that no extra amount or higher rates
will be allowed under any circumstances whatsoever. These have.been strongly       F
relied upon by the appellant. We shall refer to them.

      The Notice inviting tender (NIT) is dated 24. 7 .1984. The instructions
to the tenderer require 4 envelopes to be submitted. Envelope 1 related to
earnest money deposit, envelope 2 to contain tenderer's conditions, envelope
3 to contain tender documents as filed. After envelopes 1 to 3 were opened         G
and discussions were over, envelope 4 which contained papers relating to
resultant modification, were opened. The Tender Form contained an
undertaking to be signed by the contractor that he had seen the NIT, the
instructions and the special conditions, the particular specifications and the
general conditions of contract Schedules A, B and E and the drawings.
Schedule A contained the rates of work fixed by the appellant and Schedule         H
     34                       SUPREME COURT REPORTS (2000] SUPP. 4 S.C.R.

A    E contained the time stipulations. It also stated in para 11 which referred to
     deviations/variations as follows:

          "Para I I: Maximum limit         ±(plus/minus) 25 (twenty five) percent
          of deviation/variation           of the contract value"

B    That meant that the appellant's officers could entrust work upto the said
     variations and the contractor would have to execute the same without any
     extra payment or higher rate.

           In the Special conditions, it was stated in para 1.4 that the rates quoted
    would remain ''firm" throughout the pendency of contract; including the
C   extended period and "shall not be subject to any sort of escalation" even if
    labour costs, material or petroleum oil and lu.bricant (P.O.L.) prices increased.
    The rates were to be quoted by the tenderer to the approximate Bill of
    quantity. Para 4 dealt with 'additional works and states that', if required, the
    contractor was to execute works to the extent of an extra 25%. No adjustment
D   of rates shall be made for the additional work ordered upto this limit. Terms
    and conditions of the contract remain unaltered.

           The General Conditions of the contract defined 'contract value' in
    clause 3(e) to mean, in the case of item rate contracts, the cost of works
    arrived at after executio_n of the quantities shown in the schedule of quantities
E   of the items rates quoted by the tenderer for variations. Para 11 of the general
    condition also required additional work to be carried and it permitted
    "alterations, omissions, additions" to the work, at the same price as agreed.
    Schedule A to the general conditions stated in para 1.00.02 that                    ...
            "The total quantities of work may vary upto ± 20% (later amended as
p           25%) on either side and nothing extra will be paid on this account."

         Para 1.00.05 also stated that the quantities in the schedule were
    approximate and nothing extra would be paid above the quoted rates if there
    was any increase or decrease in quantities.

G         lt will be noticed that the above clauses permitted increase or decrease
    in the work upto 25% of the contract price. As to what should happen if the
    value of the variations exceeded 25% of the contract price was stated in
    Annexure R attached to the letter of the appellant dated 22.1.1985 by which.
    the general and special conditions were modified. T~is clause in Annexure R
    has already been extracted and it permitted higher rates to be paid if the
H   "variation is ± 25% (plus/minus, twenty five percent) of the contract price".
          NATIONAL FERTILIZERS l'. PURAN CHAND NANGIA [M.JAGANNADHA RAO, J.]        35
            The question therefore is as to what is the meaning of this clause. The       A·
      arbitrator, as already stated, granted 50% of the extra rates obviously on the
      basis that the case fell within the above exception. The District Court found
      that the total variations - both plus and minus - exceeded I 00%.

            The contention of the appellant is that the above exception is applicable
_,    only to the net difference between the increases and decreases and if it works      B
      out to more than 25% of the contract value, then rates can be revised. For
      example if the contract value is Rs. 50 lakhs, the increases are of a value of
      Rs. 15 lakhs and the reductions are of a value of Rs. I 0 lakhs, the net
      difference according to the appellant, in the overall contract value is only
      Rs. 5 lakhs and being I 0% of Rs. 50 lakhs, there can be no escalation in rates.    C
            On the other hand, the respondent contends that one has to add up the
      total variations both plus and minus and hence, in the above example, the
      value of total variation, both plus and minus amounts to Rs. 25 lakhs which
      works out to more than 25% (in fact 50%) of the contract price and the
      enhanced rates will be applicable.                                                  D
             In our opinion, the construction put on this escalation clause by the
       learned counsel for the respondents, Sri S. Ganesh is the proper one. On that
      basis, this case would come within the exception and there was no error of
      jurisdiction on the part of the arbitrator.
                                                                                          E
            The point raises certain important issues concerning integrity of the
      contract. The concept of variation of the question of work is no doubt a
      common feature of works contracts. This is because in contracts relating to
      major works, the estimates of work at the time the tenders are invited can only
      be approximate. But, it was also realised that the power of the employer to         F
      vary the terms relating to the quantum of work cannot be unlimited. In
      Hudson's Building and Engineering Contracts (8th Ed.) (pp.294-296) it has
      been pointed out that this power

 ·-           "although unlimited, is in fact limited to ordering extras upto a certain
              value."
                                                                                          G
           McCardie, J. in Naylor, Benson & Co. v. Krarinische Industries
      Gessellschaft, (1918) I KB 331] said that the words "even though general,
      must be limited to circumstances within the contemplation of the parties". In
      Parkinson (Sir Lindsay) & Co. Ltd v. Commissioners of Works and Public
      Buildings, (1949) 2 KB 632, Asquith, LJ. stated (at p.682) that the words           H
     36                       SUPREME COURT REPORTS (2000] SUPP. 4 S.C.R.

A enabling the employer to add extra work, though wide, have to be limited for
    otherwise it would amount.to 'placing one party so completely at the mercy
    of the other'. Singleton, LJ. observed (p.673) that, to confer an unbridled
    power on the employer to vary the quantities of work would lead "to manifest
    absurdity and injustice as stated by Mathew, J. in Bush v. Whitehaven .Town
B   & Harbour Trustees, (I) (1888) 52 J.P. 392.

          We may also state that under the general law of C0ntracts, unce the
    contract is entered into, any clause giving absolute power to one party to
    override or modify the terms of the contract at his sweet will or to cancel the
    contract -even ifthe opposite party is not in breach, - will amount to interfering
C   with the integrity of the contract (Per Rajamanner, CJ. in Maddali Thathiah
    v. Union of India, AIR (1957) Mad. 82). On appeal to this Court, in that case,
    in Union of India v. Maddali Thathiah, [I 964] 3 SCR 61 =AIR 1966 SC 1724
    the conclusion was upheld on other grounds. The said judgment of the
    Madras High Court was considered again in Central Bank of India v. H.F.
    Insurance Co., AIR ( 1965) SC 1288 but the principle enunciated by Rajamanner
D   CJ was not differed from. (See the discussion on this aspect in Mulla's
    Contract Act, (10th Ed.) PP.371-372, under Section 31 ofthe Indian Contract
    Act,)
                                                                                         _/

          There is thus good reason as to why, in modern works contract, a
    limitation upto 20% (now 25%) has been put on this power of alteration, both
E   plus and minus. (See Gajaria's Law Relating to Building and Engineering
    Contracts in India, 3rd Ed.,· pp.410-412). Such a limitation upto 200/o or 25%
    is now imposed under clause 12A of the Standard Terms ofCPWD Contracts.

           These aspects were discussed in detail in S. Harcharan Singh v. Union

F
    of India, [ 1990] 4 SCC 64 7 by a three Judge Bench of this Court. That
    judgment is very much relevant to the present case both on principle and on
    facts. It was held by S.C. Aggarwal, J. speaking for the Court that the
    arbitrator could award higher rates on the analogy of clause 12 A of CPWD
                                                                                          -
    contracts for excess variations beyond 20%. The contract rate was Rs. 129
    per thousand cft plus 2% but the contractor claimed at Rs. 200 per cubic ft          --
G   in respect of the excess over 20% extras. The arbitrator upheld part of the
    enhancement claimed and that was upheld by this Court.

          Clause 12A of the CPWD contract'which permits variations upto 20%
    again come up for consideration recently in Himachal Pradesh State Electricity
    Boardv. R.J. Shah & Co., [1999] 4 SCC 214. In that case, the arbitrator gave
H   a non-speaking award on disputes I, 2 and 4. Dispute I related to revision
                   NATIONAL FERTILIZERS v. PU RAN CHAND NANG IA [M.JAGANNADHA RAO, J.]       37

               of rates. Dispute 2 was whether the quantities were payable at the deviated         A
               rates, where quantities of individual items exceeded the deviation limit. Dispute
               4 was as to whether the quantities to be considered for the purpose of
-"'            deviation limit. Under clause 3(2)(e) (ii) deviations upto 20% were liable to be
               carried without any extra. The contention of the department was that the
               contract was an items. rate contract and that it was only those items which
               crossed the deviation limit that were to be paid at revised rates. The rate for
                                                                                                   B
               work in excess of the deviation limit was to be fixed only as per clause 12A.
               It was contended for the Board that the arbitrators acted beyond their
               jurisdiction and could not have revised the rates of items merely because the
               overall value of the contract which was executed exceeded 20%. On the other
               hand, it was contended for the contractor that the claim as to revised rates        c
               must be deemed to have been specifically referred to the arbitrator, the
               arbitration clause being wide, and that the construction put on the 20% clause
               by the arbitrator could not be held to be vitiated by any error apparent on
               the face of the word. Kirpal, J. after referring to a number of judgments dealing
               with the power of the arbitrator to interpret the terms of the contract, -
          ,.   including Hindustan Construction Co. ltd. v. State ofJ&K, [1992] 4 SCC 217,
                                                                                                   D
               K. R. Ravendranathan v. State of Kera/a, [ 1998] 9 SCC 410 held that the grant
..   _
               by the arbitrator at a rate higher than the contract rate could not be treated
               as outside his jurisdiction. It was observed:

                       "The construction placed on the contract by the contractor cannot be        E
                       said to be an implausib.le one. Eve~ if the arbitrators considered the
                       terms of the contract incorrectly, it cannot be said that the award was
                       in excess of jurisdiction."


r                    It was, however, contended before us for the appellant that by a wrong
               construction of the clause permitting revised rates as stated in Annexure R,
                                                                                                   F
               the arbitrator could not have clutched at jurisdiction he did not have. The
               question then is whether the arbitrator clutched at jurisdiction he did not
     "•        have, by an unreasonable construction of the clause "± (25%)" for purposes
          I
               of escalation.
                                                                                                   G
                     We are of the view that the abovesaid clause "±25%" was understood
               by the arbitrator in a reasonable manner as being applicable to a case where
               the value of the sum total of the additions and deletions exceeded 25% of the
               contract price. That construction, in our view, cannot be said to be vitiated
               by any serious error of law. The following are our reasons.
                                                                                                   H
     38                       SUPREME COURT REPORTS (2000] SUPP. 4 s.c:R.

A           When a contractor bids in a contract, he has to offer reasonable rates
      for the works which are both difficult to perform and other works which are
      not that difficult to perform. Every contractor tries to balance his rates in such
     a manner that the employer may consider his offer reasonable. In that process
     the contractor tries to get a reasonable margin of profit by balancing the more
B    difficult.(and less profitable items) and the less difficult (and more profitable
     items). His bid is, normally, a package. If the employer is permitted in law to
     make variations upwards and down-~ards - even if it be upto a limit beyond
     which market rates become payable - then the interpretation of the clause
                                                                                             -
     must be one which balances the rights of both parties. For example, if the plus
     and minus variations go beyond 25% and are made in a manner increasing
C    the less profitable items and decreasing the more profitable items, and if the
     net result of the contract is to be the basis, as contended by the appellant,
     then it may work out that the contractor could be made to perform a
     substantially new contract on the same contracted rates. In fact, if the said
     reasoning of the appellant is accepted and if, in a given case, the value of
D   the increases in unprofitable items is 50% of the contract value and the value
    of the reductions of the remaining more profitable items is 50% of the contract        ......
    value, it could still be contended for the appellant that the net variation was
    nil, even though that was a situation where the contract had been substantially
    modified and was ·almost a different contract from the one stipulated. Such
    an unreasonable construction is to be avoided and was rightly avoided by
E   the arbitrator.

          The additions and decreases in work are, in our opinion, therefore both
    independent for the purpose of finding out the ± 25% variation and have to
    be pooled together. The arbitrator was right in thinking that the case fell
F   within the exception. Obviously, he must have felt that the plus and minus
    variations are more than 25% and that the contract rates are no longer
    binding. His construction of the clause appears to be rational and just and
    cannot be said to be unreasonable.

           In the result, the interpretation put on the clause by the arbitrator
G   appears to. us to be quite reasonable and very plausible and it cannot therefore
    be said that the award is vitiated by any error of law affecting his jurisdiction.
    In fact, the learned District Judge found that the total variation - both upwards
    and downwards was more than I 00% of the contract price. For the aforesaid
    reasons, we are of the view that Points I and 2 should be answered in favour
H   of the respondent-contractor.
                NATIONAL FERTILIZERS v. PU RAN CHAND NANGIA [M.JAGANNADHA RAO, J.)          39

                  Point 3:                                                                       A
                   This concerns the question whether the arbitrator could have awarded
            at a flat rate of 50% of the extra claim or at 50% of the difference between
            the market prices and the contract rates. Both on law and on facts, the case
            of the appellant cannot be accepted.
                                                                                                 B
                  There is material on record that the appellant had, during the pendency

--          of the arbitration proceedings, not seriously disputed that market rates were
            payable because the plus and minus variations exceeded 25% of the contract
            price. As pointed out in the respondent's counter filed in this Court, the
            appellant had, in a reply dated 18.3.1988 filed before the arbitrator conceded       C
            having paid 75% of the additional work at the revised rates though not upto
            the extended date. Now the award by the arbitrator was for the 'balance' and
            upto 30.10.1986. That is also an indication that, on facts, the arbitrator's
            construction of the "± 25%" clause was correct.

                   In the appellant's defence to the respondent's claim before the arbitrator,
                                                                                                 D
            there was no specific denial of the contractor's right to the market rates. The
      ...   appellant was relying more on its general plea that the ±i's% clause was not
            attracted at all as the contract value as a whole or the net increase was to
-'-         be taken into consideration. In fact, there were favourable recommendations
            of the departme.,ntal officers for payment at higher rates. In S. Harcharan          E
            Singh 's case to which we have referred earlier, there were similar
            recommendations of the officers. The arbitrator cannot, therefore, be said to
            have acted illegally on facts for he has not in fact granted at the full market
            rate claimed by the contractor but has. only granted at 50% of t,he claim.
                                                                                                 F
                   In law also, the appellant has no case. In the case of a non-speaking
            award, it is not permissible for the Court to probe into the mental process of
            the arbitrator [See Hindustan Steel Works v. Rajeswar Rao, [1987] 4 SCC 93
            when he rejected 50% of the claim in favour of the appellant and accepted

 ..   I'
            50% of the claim in favour of the contractor. In two decided cases of non-
            speaking awards when a flat increase of 20% or 25% for permissible items of G
            additional work was granted by the arbitrator, this Court accepted the same
            as not being illegal. See P.M Paul v. Union of India, [ 1989] Suppl. 1 SCC 368
            and Himachal ·Pradesh Nagar Vikas Pradhikaran v. Mis Aggarwal & Co.,
            AIR (1997) SC 1027. Therefore, merely because the increase was at a flat rate,
            we cannot find fault with the award. The arbitrator was appointed by consent H
    40                     SUPREME COURT REPORTS (2000] SUPP. 4 S.C.R.

A and he was a.former General Manager in the Railways and was also associated
    with the appellant corporation. We do not therefore find any error apparent
    on the face of the record in the award of 50% of the escalation claimed and
    in the claim upto the extended date, 30. l 0.1986.

B        For the aforesaid reasons, the appeal is dismissed. The interim orders
    passed by this Court stand vacated. No costs.

    B.S.
                                                                                  -
                                                            Appeal dismissed.




                                                                                  J.


Search Indian case law

Ask in plain English, not just keywords. 25,000 AI words free, no card.

Try "Arbitration"Sign in to search

For a digitally signed copy suitable for filing, refer to the court's own website. Only the court can issue one.