BHARAT KARSONDAS THAKKARversusM/S. KIRAN CONSTRUCTION CO. AND ORS.
- Citation
- 2009 INSC 829
- Decided
- 15 May 2009
- Disposal
- Appeal(s) allowed
- Bench
- ALTAMAS KABIR
Holding
The Supreme Court vacated the interim injunction as Respondent No.1 had no privity of contract or established claim over the properties, making the continuation of the order inequitable.
Summary
The case arose from a long‑standing dispute over leasehold lands originally granted to Sowar Ramji Vaity. After a series of agreements, the respondent Kiran Construction Co. (Respondent No.1) sought to enforce a 1982 injunction restraining the Vaity family and others from dealing with the properties, despite having no direct contract with them. The Supreme Court examined whether the injunction could continue when Respondent No.1 lacked privity of contract and the underlying claim depended on Modern Development Corporation’s unestablished right to specific performance. It also considered whether the amendment of the plaint to challenge a consent decree was permissible. The Court held that the injunction was untenable because Respondent No.1 had no established title or contractual link, and the properties were already under the custody of a court‑appointed receiver. Consequently, the interim order was vacated and the appeals filed by the Official Receiver and the Vaitys were allowed.
Issues considered
- Whether an interim injunction restraining dealings with the suit properties can continue when the plaintiff lacks privity of contract and an established title.
- Whether the amendment of the plaint to include a challenge to a consent decree is permissible under Order 6, Rule 17 CPC.
- Whether the respondent’s claim for specific performance is viable given the termination of the agreement between the Vaitys and Modern Development Corporation.
- Whether the presence of a court‑appointed receiver (custodia legis) bars the grant of an injunction.
Legislation cited
- Code of Civil Procedure, 1908s. Order 6, Rule 17
- Indian Partnership Acts. 64
- Urban Land (Ceiling and Regulation) Act, 1976s. 6(1)
Subjects
Judgment
.. [2009] 9 S.C.R. 515
~:"\
BHARAT KARSONDAS THAKKAR A
• v.
M/S. KIRAN CONSTRUCTION CO. AND ORS.
(I.A. Nos. 4, 6, 7 & 8 in Civil Appeal No. 2573 of 200_8)
MAY 15, 2009
B
-"'! [ALTAMAS KABIR AND CYRIAC JOSEPH, JJ.]
,-l
Interim order: Restraint order - Interim order restraining
any dealings with the suit properties and for maintaining
status quo passed on an application of respondent 1 - c
Respondent 1 did not prove its title over the properties - Held:
Respondent 1 has no right to seek continuation of interim
order - Merely because the same was in force for a long time
would be no ground to allow same to continue.
""' D
y On 27.5.1949, the Collector recorded a grant of lease
of lands in favour of Sowar Ramji Vaity for 999 years.
Sowar died in 1965 leaving behind LRs (Vaitys) to
succeed to his estate. On 1.10.1973, t~e Vaitys agreed to
sell their rights in the lands to one Danani. Under the
E
agreement, Danani was required to obtain lease of suit
lands from the Collector in favour of Vaitys within 2 years.
-· During April..June 1974, Danani constituted a partnership
~ ....
i firm with K.V. Thakker and S.S. Thakker under the name
of Swas Construction Co. The appellant who was minor
was admitted to the benefits of partnership firm. The F
agreement recorded giving possession of suit land to
Swas Construction Company.
As the Urban Land (Ceiling and Regulation) Act,
- l 1976 came into force, Danani filed declaration under the G
Act. On 12.6.1979, the Government executed a lease in
favour of Vaitys for 60 years. Immediately thereafter on
18.6.1979 Vaitys entered into an agreement with Modern
Development Corporation giving development rights in
-. 515 H
516 SUPREME COURT REPORTS [2009] 9 S.C.R. -..
A respect of suit lands. On 24.8.1979, Modern Development
Corporation agreed to transfer its rights to respondent
no.1 and agreed to obtain confirmation from Thakker
Associates that there was no subsisting agreement for
sa1e in their favour in respect of property agreed to be
B sold.
On 18.2.1980, K.V. Thakker filed suits for declaration
-~
against Danani and S.S. Thakker praying for declaration
that there was a partnership between them and Danani
and S.S. Thakker had retired from Swas Construction
C Company.
On 9.10.1980, High Court appointed a receiver of
properties. On 15.5.1981, Vaitys terminated agreement
with Modern Development Corporation. Modern
D Development Corporation could not go to the court as it ...
was unregistered firm. Respondent 1 filed suit against
Vaitys and Modern Development Corporation for specific
performance of 1979 agreement. On 1.7.1982, High Court
E
passed restraint order against Vaitys and partners of
Modern Development Corporation. All parties
compromised and a consent decree was passed. In 1999
respondent 38 applied for vacation of stay order of
..
1.7.1982. In August, 2000 respondent no.1 filed an ·-
application under order 6, Rule 17 CPC to join respondent
F 13 to 19 as defendants and to incorporate challenge to
the consent decree which was dismissed and the
restraint order was vacated. The three appeals were filed
and Division Bench of High Court allowed them. These
appeals were filed against the order of High Court
G allowing the amendment of the plaint and joining
respondent 13 to 19 as additional defendants. ~ --
Allowing the appeals, the Court
HELD: 1. Once the prayer for amendment of the plaint
H to include the challenge to the consent decree passed in
BHARAT KARSONDAS THAKKAR v. KIRAN 517
CONSTRUCTION CO.
a suit was disallowed by this Court, the question of A
restraining them from dealing with the suit properties over
which the Respondent No.1 has no established claim
would be completely unreasonable and merely because
the same had been in force for a long time, would be no
ground to allow the same to continue. [Para 23] [528-8- B
CJ
2. Admittedly, there is no privity of contract between
respondent 1 and the Vaitys, its claim is, therefore,
restricted to Modern Development Corporation alone and c I
is also dependent upon the right of Modern
Development Corporation to specific performance of its
agreement with the Vaitys. In other words, until and
unless Modern Development Corporation is able to
establish a right over the suit properties, respondent 1
can have no claim in respect thereof. Furthermore, since D
the Receiver continues to be in possession of the suit
properties and the properties continue to be in custodia
/egis, respondent 1 cannot ask for possession of the said
properties. The claim attempted to be set up by Kiran
Construction Company is highly tenuous and is entirely E
dependent upon the claim of Modern Development
Corporation which has so far not attempted to establish
- i such claim. In such circumstances it would be wholly
inequitable to allow the interim order to continue. The
same is accordingly vacated. [Paras 24 and 25] [528-0- F
G]
CIVIL AP PELLATE JURISDICTION : I.A. Nos. 4, 6, 7 & 8
in Civil Appeal No. 2573 of 2008.
- l
From the J!Jdgment & Order dated 16.11.2006 of the High G
Court of Judicature at Bombay in Appeal No. 745 of 2001 in
Chamber Summons No. 1203 of 2003 in Suit No. 1578 of
1981 and final Judgment & Order dated 17.11.2006 in Appeal
No. 748 of 2001 in notice of Motion No. 140 of 1999 in Suit
•• No. 1578 of 1981. H
518 SUPREME COURT REPORTS [2009] 9 S.C.R.
A WITH
C.A. Nos. 3618-3617 of 2009, 3618-3619 of 2009.
Mukul Rohtagi, Janardhan, E.C. Agrawala; Mahesh
Agarwal, Rishi Agrawala and Gaurav Goel for the Appellants.
B
Ranjeet Kumar, Rajesh Kumar, S.S. Khanduja
Respondent-in-person, Buddy A. Ranganadhan, Shiv Kumar
Suri, Dhruv Mehta and Tapesh Kumar Singh for the
Respondents.
c . The Judgment of the Court was delivered by
ALTAMAS KABIR, J. 1. Leave granted in Special Le1ave
Petition (Civil) Nos.28267-28268 of 2008 and 28270-28271 of
2008. All the Appeals were taken up together for disposal as
;.. \
D they arise out of the same set of facts and common questions
of law are involved. Five/ interlocutory applications, being
l.A.Nos.4,5,6, 7 and 8, filed in connection with the Special Leave
Petition, for clarification of the judgment dated 9th April, 2008, '
passed in Civil Appeal No.2573 of 2008 and for deletion of the if
l
E names of some of the parties and for filing additional
'
documents, were also taken up for disposal along with the
Appeals. While SLP(C)Nos.28267-28268 of 2008 have been ,...
filed by the Official Receiver against the order dated 17th
November, 2006, passed by the Division Bench of the Bombay
F High Court in Appeal No.748/2001 challenging the order dated
21st June, 2001, passed by the learned Single Judge and
restoring Notice of Motion No.140/99 for fresh hearing before
the learned Single Judge and SLP(C)Nos.28270-28271 of
2008 have been filed by the Vaitys against the same order in
G Appeal No.747/2001 in Notice of Motion No.2700/99, claiming
the self-same reliefs. As indicated hereinab..ove, three of the
interlocutory applications have been filed in Civil Appeal
No.2573/2008, for clarification of the Judgment dated 9th April,
2008, passed in Civil Appeal No.2573/2008, disposing of
H Appeal No.741 of 2001. Applications have also been filed by ....___
BHARAT KARSONDAS THAKKAR v. KIRAN 519
CONSTRUCTION CO. [ALTAMAS KABIR, J.]
... "'·
the petitioners in both the set of Special Leave Petitions (now A
appeals} for condonation of delay in filing the same on account
of the fact that the subject matter of the said Special Leave
Petitions was also the subject matter of SLP(C)No.232812007,
which was subse4uently renumbered as Civil Appeal No.25731
2008, but had remained undisposed of when the appeal 8
.... against the order dated 16th November, 2006, was finally
-' disposed of by the judgment and order dated 9th April, 2008.
There being substance in explanation given for condonation of
delay in filing the Special Leave Petition, such delay is
condoned. c·
2. On 27th May, 1949, the Collector of Thane recorded a
grant in favour of Mr. Sowar Ramji Vaity entitling him to lease
of lands relating to Survey Nos.83 to 91 in Village Mulund for a
.A
. term of 999 years. Mr. Sowar Ramji Vaity died in the year 1965,
leaving behind him surviving Jagannath, Babu, Vishnu and D
.lf
_, Bhaskar (hereinafter referred to as 'the Vaitys') as his legal
representatives to succeed to his estate. On 1st October, 1973, ·
the Vaitys entered into an agreement to sell their rights and
-I interests in the aforesaid lands to one Mr. K.L Danani (the
Respondent No.44 herein) for a total consideration of Rs.2 E
lakhs. Under the Agreem.ent, Mr. Danani was required to obtain
lease of the suit lands from the Collector in favour of the Vaitys
--'; within a period of two years. During the months of April and
June, 1974, Mr. Danani constituted a partnership firm with Mr.
K.V. Thakkar and Mr. S.S. Thakkar under the name of Mis Swas i=
Construction Company. The Appellant herein, who was then a
minor, was admitted to the benefits of the partnership firm. The
time for completion of the sale under the agreement dated 1st
October, 1973, was extended by two months till after the land
... ~ was converted to non-agricultural use or the Vaitys made a clear G
and marketable title to the suit land, whichever was later. It was
recorded that Mis Swas Construction Company had been put
in possession of the suit lands in part performance of the
agreement dated 1.10.1973.
H
,._
-~
•
520 SUPREME COURT REPORTS [2009] 9 S.C.R.
A 3. In the meantime, the Urban Land (Ceiling and
Regulation) Act, 1976, was enacted and Mr. K.L. Danani
claiming possession under the said Agreement filed a
statement with the Urban Land Ceiling Authorities in terms of
Section 6(1) of the Act. On 12th June, 1979, pursuant to a
B decision arrived at in April, 1978, the Government of
Maharashtra executed a lease in favour of the Vaitys for a
period of 60 years. Immediately thereafter, on 18th June, 1979,
the Vaitys entered into an Agreement with Mis Modern
Development Corporation, the Respondent No.24 herein,
c granting them development rights in respect of the suit lands.
On 24th August, 1979, Mis Modern Development Corporation
\'
is alleged to have entered into an· agreement with the ,.
Respondent No.1, Mis Kiran Construc~ion Company, to transfer
its beneficial interests in the suit lands, except for Serial No.91,
D in favour of the Respondent No.1. Clause 12 of the Agreement
specifically required Mis Modern DevEllopment Corporation to
obtain confirmation from Mis Thakkar & Associates that there
was no subsisting 29reement for sale in their favour in respect
---Of the property agreed to be sold. ·
E 4. On 18th February, 1980, the Appellant and Mr. K.V.
Thakkar filed Suit No.252 of 1980 in the Bombay High Court
against Mr. K.L. Danani (the Respondent No.44) and Mr. S.S.
Thakkar, ·inter alia, praying for a declaration that a partnership
had existed between them and that Mr. K.L. Danani and Mr.
F S;S. Thakkar had retired from Mis Swas Construction
Company.
5. It appears that in February, 1980, in Notice of Motion
No.283 of 1980 filed in the said Suit, Mr. K.L. Danani undertook
G not to part with possession of the suit lands pending disposal
of the Notice of Motion, which was disposed of on 9th October,
1980, by the Bombay High Court by appointing the Court
1
Receiver over the properties.
6. On 15th May, 1981, the Vaitys terminated the
H Agreement dated 18th June, 1979, entered into with Mis
BHARAT KARSONDAS THAKKAR v. KIRAN 521
CONSTRUCTION CO. [ALTAMAS KABIR, J.]
-- ,,
Modern Development Corporation (the Respondent No.24). A
This prompted the Respondent No.1 to file Suit No.1578 of
1981 against the Vaitys and the partners of Mis Modern
Development Corporation on 7th September, 1981, for specific
performance of the purported Agreements dated 18th June,
1979 and 24th August, 1979. On 1st July, 1982, the Bombay B
High Court passed an order restraining the Vaitys and the
• ,J
partners of the Respondent No.4 from selling, transferring,
~ encumbering, alienating or further parting with possession of
the suit lands pending disposal of Suit No.1578 of 1981. After
the death of Mr. Babu Vaity on 1st May, 1994, all the parties c
to Suit No.252 of 1980, entered into a comprehensive
settlement with the Vaitys, Mr. K.L. Danani (the Respondent
No.44) and one Mulchand G. Mehta (the Respondent No.47)
and in order to give effect to the settlement, the Vaitys and the
Respondent No.47 were joined as defendants in Suit No.252
- ~
of 1980. On the very same day, the Bombay High Court
decreed the suit on consent terms. Pursuant to the terms and
D
conditions arrived at between the parties, the Respondent
No.48 took out Notice of Motion No.140 of 1999 in Suit
No.1578of1981, praying that the order dated 1st July, 1982,
E
be vacated. The Vaitys also took out Notice of Motion No.2700
of 1999 in the said Suit, praying for the same order. In August,
2000, Mis Kiran Construction Company took out Chamber_
Summons No.1203 of 2000 in Suit No, 1578 of 1981, seeking
~
to amend the plaint so as to join the Respondent Nos.13 to 19
as defendants and also to incorporate a challenge to the F
decree dated 6.5.1998 passed by the Bombay High Court in
Suit No.252 of 1980. The said Chamber Summons was
dismissed by the learned ~ingle Judge of the Bombay High
Court on 21st June, 2001, and the injunction granted on 1st July,
1982, was vacated. The said order of injunction was also G
~ ~
vacated by a common order of even date passed in Notices
of Motion No.140 and No.2700 of 1999.
7. Three Appeals were filed by the Respondent No.1
~ herein before the Division Bench of the Bombay High Court, H
BHARAT KARSONDAS THAKKAR v. KIRAN 523
CONSTRUCTION CO. [ALTAMAS KABIR, J.]
property, and if they failed to make out a marketable title, all A
the monies paid to Kiran Construction Company would be
returned to it with interest at the rate of 12% per annum. As
indicated hereinbefore, the agreement which was entered into
between the Vaitys and Modern Development Corporation on
18th June, 1979, was terminated by the Vaitys on 15th May, B
, "' 1981, prompting Kiran Construction Company to file Suit
+ No.1578of1981 in the Bombay High Court in which an interim
order was passed by the Bombay High Court restraining the
Vaitys and the partners of Modem Development Corporation
from selling, transferring or further parting with possession of c
the suit lands.
10. Mr. Rohtagi submitted that in view of the said order of
injunction, on 10th November, 1981, Babu Vaity filed an
4 affidavit in Notice of Motion No.1271 of 1981 indicating that on
.- 15th May, 1981, the Vaitys had terminated the agreement D
dated 18th June, 1979, with Modern Development Corporation
and that a separate agreement had been executed in favour
of one Mr. Ashok Kumar Goyal and Mr. Gosalia granting them
development rights in respect of the suit lands. Despite the
above, on 1st July, 1982, the Bombay High Court passed an E
order in Notice of Motion No.12671 of 1981 in the suit filed by .
the Respondent No.1 and restrained the Vaitys and the partners
" of Modern Development Corporation from selling, transferring,
encumbering, alienating or from further parting with possession
of the suit lands, pending disposal of the suit filed by the F
Respondent No.1 herein. Mr. Rohtagi submitted that on 27th
March, 1984, the Respondent No.1 was informed by a letter
written on behalf of the appellants regarding the claims of the
appellants herein, the filing of Suit No.252 of 1980 and the
.., ~ appointment of the Court Receiver who had taken over G
possession of the s~it properties.
11. As indicated hereinbefore, on the death of Babu Vaity,
all the parties to Suit No.252 of 1980 arrived at a
comprehensive settlement with the Vaitys, the Respondent
H
524 SUPREME COURT REPORTS (2009] 9 S.C.R.
A No.44 and one Mulchand G. Mehta, the Respondent No.47. On
the same day, the Bombay High Court passed a decree on the
consent terms arrived at between the parties in Suit No.252 of
1980. Mr. Rohtagi submitted that the High Court vide order
dated 21st June, 2001, dismissed the Chamber Summons
B taken out by the Respondent No.1 and also vacated the
injunction granted in Suit No.1578 of 1981 on 1st July, 1982.
Mr. ~ohtagi submitted that the order of the learned Single Judge -+
was challenged in Appeal and was ultimately set aside and the
prayer for amendment of the plaint made by the Respondent
c No.1 was allowed.
12. Mr. Rohtagi submitted .that Kiran Construction
Company did not have any privity of contract with the Vaitys.
Furthermore, the Vaitys had terminated their agreement with
Modern Development Corporation with whom Kiran
D Construction Company had entered into an agreement and
such termination had not been challenged by Modern
Development Corporation, particularly since it is an
unregistered firm arid, therefore, could not sue or be sued under
the provisions of Section 64 cf the Partnership Act. Mr. Rohtagi
E submitted that when Modern Development Corporation was
unable to compel the Vaitys to perform their part of the contract,
Kiran Construction Company, whose claim, if any, to the suit
properties_, was through Modern Development Corporation,
could not compel the Vaitys to specifically enforce the contract
F between the Vaitys and Modern Development Corporation.
Accordingly, the entire exercise undertaken by the Respondent
No.1 was but an exercise in futility and the Division Bench while _
allowing the prayer for impleadment made on behalf of Kiran
Construction Company erred in injuncting the Vaitys and also
G the Thakkars from taking steps to develop the property.
13. Mr. Rohtagi urged that even the fact that a Receiver
had been appointed over the suit properties and the properties
were, therefore, in custodia legis had been suppressed, and,
in any event, since the properties were in custodia legis, the
H order of injunction could not have been passed. Mr. Rohtagi
BHARAT KARSONDAS THAKKAR v. KIRAN 525
----\ CONSTRUCTION CO. [ALTAMAS KABIR, J.]
submitted that since Kiran Construction Company had no privity A
of contract with the Vaitys and Modern Development
Corporation being an unregistered partnership, there was no
possibility whatsoever of the suit filed by Kiran Construction
Company ever being decreed. For such reason also, the order
of injunction passed by the Division Bench was liable to be B
' .Jo vacated.
-i
14. Mr. Rohtagi submitted that from the orders passed by
the Division Bench of the Bombay High Court on 17th
November, 2006, disposing of Appeal Nos. 747 and 748 of
2001 arising out of the orders passed by the learned Single c
Judge in Notices of Motion No.2700 and 140 of 1999, it would
be evident that the said appeals were allowed merely as a
consequence of the order passed earlier on 16th November,
..,;. 2006, in Appeal No.745/2001 in connection with the Chamber
D
. : Summons No.1203/2000 taken out by Kiran Construction
Company., Mr. Rohtagi submitted that no reasons, other than
what has been indicated hereinabove, were given for allowing
the said appeals and accordingly, while Civil Appeal No.2573/
2008 was disposed of, consequential orders were passed
whereby the other appeals were also disposed of. E
15. Mr. Rohtagi submitted that since this Court had earlier
· on 9th April, 2008, affirmed the order of the learned Single
....
Judge and had rejected the Chamber Summons for
impleadment, consequential orders were required to be passed 'F
for setting aside the order dated 17th November, 2006, passed
by the Division Bench of the Bombay High Court in Appeal '
Nos.747 and 748 of 2001 and also to vacate the interim order
dated 1st July, 1982, passed in Suit No.1578 of 1981 filed by
the Respondent No.1 herein .
./ ~ G
16. While adopting Mr. Rohtagi's submissions, Mr. Ranjit
Kumar, learned Senior Advocate appearing for Respondent
Nos.2A to 2E, 3 to 16, 18, 19 and 31 in IA No.6 of 2008, prayed
for clarification of the judgment and order passed by this Court
on 9th April, 2008, in Civil Appeal No.2573 of 2008 to the extent H
526 SUPREME COURT REPORTS [2009) 9 S.C.R.
r--
A that as a consequence of the order dated 16th November,
2006, passed in Appeal no.745 of 2001 being set aside, the
order dated 17th November, 2006, passed by the Division
Bench in Appeal No.747 of 2001 and Appeal no.748 of 2001
were also set aside.
B
17. Mr. Ranjit Kumar submitted that after· the prayer for
amendment of the plaint was disallowed by this Court, it was ~ ,..,
1 only through inadvertence that consequential orders were not +
recorded as far as the two appeals are concerned and that
when the Vaitys were not before the Court in the suit filed by it,
c the Respondent No.1 could have no justification for submitting
that the interim order passed by the Division. Bench of the High
Court should be allowed to remain. He also reiterated Mr.
Rohtagi;s submissions that when there was no privity of
contract between the Respondent No.1, Kiran Construction
D Company, and the Vaitys and its suit was for relief only against /..
Modern Development Corporation, the agreement entered into ~
between Modern Development Corporation and the Vaitys
could not be specifically enforced by the said Respondent and
the Division Bench of the High Court had committed an error
E in allowing the interim order of injunction to continue against the
appeals.
18. On the other hand, Mr. Buddy A. Ranganadhan, ~
learned Advocate appearing for Kiran Construction Company, t
urged that the rejection of the prayer made on behalf of the
F
Respondent No.1 for leave to amend the plaint did not mean
that the orders prayed for in these appeals would follow as a
matter of consequence. It was urged that thejudgment delivered
by this Court on 9th April, 2008, was only concerned with the
challenge to the amendment and that the scope of the appeal
G was limited to the amendment of the plaint. According to learned
~ "
counsel, the prayer for injunction was made on account of the
decision of the Respondent No.1 to file a separate suit and it
was in that context that the prayer for injunction to continue till
the hearing of the new suit could be taken up. Mr. Ranganadhan
H submitted that, in any event, at no point of time was any
BHARAT KARSONDAS THAKKAR v. KIRAN 527
__." CONSTRUCTION CO. [AlTAMAS KABIR, J.]
indication given that any argument was to be advanced on the A
question of remand to the Division Bench.
19. Mr. Ranganadhan also urged that the prayer for
vacating the interim order that had lasted for 16 years should
not have been entertained. He submitted that the appeals were
~ . I misconceived and were liable to be dismissed .
B
~
-+ 20. From the submissions made on behalf of the
respective parties and the materials on record, it is quite
apparent that the Chamber Summons No.1203 of 2000 taken
out by Kiran Construction Company for leave to amend its suit c
to incorporate a challenge to the consent decree passed in Suit
No.252 of 1980 and also to implead the appellants herein, Mr.
... ·' K.L. Danani and Mr. Mulchand G. Mehta as defendants in the
suit, was heard along with and Notice of Motion No.140 of
... 1999 filed by the Receiver and Notice of Motion No.2700 of D
. 1999 filed by Vaitys for vacating the order of injunction dated
1st July, 1982, were taken up for hearing together. While
Chamber Summons filed by Kiran Construction Company was
dismissed, the Notices of Motion filed by the Receiver and the
Vaitys were allowed and the order of injunction dated 1st July, E
1982, was vacated.
~ 21. Since the three appeals before the High Court were
-· i filed by Kiran Construction Company against the orders passed
by the learned Single judge on the Chamber Summons and the
two Notices of Motion, the Division Bench of the High Court, F
while considering the said appeals, allowed the prayer for
amendment of the plaint and as a consequence reversed the
learned Single Judge's order on the two Notices of Motion and
remanded the Notice of Motion for fresh hearing.
/ } G
22. In the Civil Appeal filed by the appellants herein against
..... (
the three orders passed by the Division Bench, ?.lthough, by
order dated 9th April, 2008, the Appeal was allowed and the
order of the Division Bench allowing the amendment prayed for
by the Respondent No.1 was set aside, through inadvertence,
H
528 SUPREME COURT REPORTS [2009] 9 S.C.R.
r-....
A no orders were passed in respect of the appeals against the
orders passed on the two Notices of Motion for vacating the
interim order dated 1st July, 1982. It is for clarification of the
said order that the interim applications have been filed which
are under consideration.
B .:I '
23. Once the prayer for amendment of the plaint to include
'
the challenge to the consent decree passed in Suit No.252 of
1980 was disallowed by this Court, the question of restraining
+
them from dealing with the suit properties over which the
Respondent No.1 has no established claim would be
c completely unreasonable and merely because the same had
been in force for a long time, would be no ground to allow the
same to continue.
24. Admittedly, as pointed out by Mr. Mukul Rohtagi and
;..
D Mr. Ranjit Kumar, learned Senior Advocates, there is no privity
of contract between Kiran Construction Company and the i
Vaitys, its claim is, therefore, restricted to Modern Development
Corporation alone and is also dependent upon the right of
Modern Development Corporation to specific performance of
E its agreement with the Vaitys. In other words, until and unless
Modern Development Corporation is able to establish a right
over the suit properties, Kiran Construction Company can have
no claim in respect thereof. Furthermore, since the Receiver 'y
continues to be in possession of the suit properties and the .....
properties continue to be in custodia legis, Kiran Construction
F
Company cannot ask for possession of the said properties.
25. In our view, the claim attempted to be set up by Kiran
Construction Company is highly tenuous and is entirely
dependent upon the claim of Modern Development Corporation
~
--...
......
G which has so far not attempted to establish such claim. In such
circumstances it would be wholly inequitable to allow the interim
order to continue. The same is accordingly vacated. r
26. Accordingly, the appeals filed by the Official Receiver
and the Vaitys must succeed and are allowed. Simultaneously, ,..
H
BHARAT KARSONDAS THAKKAR v. KIRAN 529
CONSTRUCTION CO. [ALTAMAS KABIR, J.]
Interlocutory Application Nos.4, 6 and 7 for clarification of the A
judgment and order dated 9th April, 2008, passed in Civil
Appeal No.2573/2008 and Interlocutory Application No.8 for
filing additional dC?cuments are also disposed of by virtue of this
judgment. Further more, the following clerical mistakes have
- been pointed out in paragraph 7 of the I.A.No. 4 with regard to
the judgment dated 9.4.2008 passed in Civil Appeal No. 2573
of 2008:
B
a. "In paragraph 2, page 1, line 3, the wor~ "Serial"
ought to be "Survey".
c
b. The reference to "K.B. Thakkar" in paragraph 2,
paragraph 4 and paragraph 11 ought to be
"K.V .Thakkar";
c. The submission at paragraph 21 was in fact the
submission made on behalf of the Petitioner and D.
not on behalf of Respondent No.1.; and
d. In paragraph 16, page 15, line 1 the word
"respondent" is to be read as "Respondent No.1."
E
Let a Corrigendum be issued with regard to the errors
indicated above. As far as Interlocutory Application No.5 for
deletion of the names of the Respondent Nos.17, 20, 22, 25(a),
25(b), 25(c), 25(d) and 27, is concerned, the same is allowed .
at the risk of the appellant.
F
27. Inasmuch as, these appeals have been taken from
interlocutory orders and the suit of the Respondent No.1 is still
pending, we make it clear that the observations made in this
order are only for the purpose of disposal of the applications
for vacating the interim orders and such observations should G
not influence the learned Trial Court from disposing of the
pending suits, in accordance with law.
28. There will, however, be no order as to costs.
D.G. Appeals allowed. H
Search Indian case law
Ask in plain English, not just keywords. 25,000 AI words free, no card.