BHUSHAN POWER & STEEL LTDversusRAJESH VERMA & ORS.
- Citation
- 2014 INSC 308
- Decided
- 22 April 2014
- Disposal
- Disposed off
- Bench
- S S NIJJAR
Holding
The State Government is in contempt for failing to implement the Supreme Court's 14 March 2012 directions regarding the Keora area and must transmit the requisite recommendation to the Central Government within one month.
Summary
Bhushan Power & Steel Ltd. (BPSL) entered into a 2002 MOU with the Odisha State Government, which obliged the State to recommend iron‑ore mining leases for its steel plant. The Supreme Court, in a 2012 appeal, directed the State to act on the MOU for both the Thakurani and Keora areas. While the State complied for Thakurani, it failed to act on Keora, prompting BPSL to file a contempt petition. The State argued that statutory provisions (Section 11(4) of the MMDR Act) and overlapping applications made compliance impossible. The Court rejected this defence, holding that a final judgment cannot be evaded and the State is in contempt for not transmitting the required recommendation. It gave the State one month to send the recommendation to the Central Government, after which the contempt would be discharged; otherwise further contempt proceedings may follow. The Court also dismissed related writ petitions, stating that other claimants cannot invoke Article 32 for the same relief.
Issues considered
- The State Government's claim that Section 11(4) of the MMDR Act and overlapping mining applications excuse non‑implementation of the Supreme Court's directions.
- Whether the 2002 MOU between BPSL and the State remains subsisting and binding on the State.
- Whether failure to transmit the recommended mining lease constitutes contempt of court.
- Whether other petitioners can claim the same relief under Article 32 of the Constitution.
- Whether the court may reopen or modify the original judgment in contempt proceedings.
Legislation cited
- Mineral Concession Rules, 1960s. Rule 59(1), s. Rule 59(2)
- Mines and Minerals (Development and Regulation) Act, 1957s. 11(3), s. 11(4)
Subjects
Judgment
[2014] 5 S.C.R. 493
BHUSHAN POWER & STEEL LTD. A
v.
RAJESH VERMA & ORS.
(Contempt Petition (C) NO. 374 OF 2012)
IN
C. A. No. 2790 OF 2012 B
APRIL 22, 2014
[SURINDER SINGH NIJJAR AND A. K. SIKRI, JJ.]
Contempt of Court: c
Order of Supreme Court - Non-implementation of - In
terms of an MOU, State Government had committed to
recommend to Central Government for grant of iron ore mines
in favour of appellant for use in it~ proposed plant - Pursuant 0
thereto appellant set up the plant with huge investment -
Order of Supreme Caurt in appeal directing the State
Government to take steps in terms of MOU- No-compliance
of - Held: Respondents/contemners do not dispute that the
directions contained in the judgment have become final - E
However, State Government!Contemners have pleaded their
helplessness by narrating certairi circumstances ·and
developments as also the statutory mandate embodied in s. ·
11(4) of the MMDR Act - Held: Contemners cannot raise
such a plea to avoid implementation of directions issued by
Court - As far as the law- laid down in Sandur Manganese, F
that may be applied in application that are pending -
Respondents are in contempt of orders dated 14. 3. 2012
passed by the Court, in not complying with the directions in
respect of Keora area --:- However, they are given one final
opportunity to purge the contempt by transmitting requisite G
recommendations to the Central Government -:-- It. would be
for the Central Government to consider the said
recommendations on its own merits and in accordance with
law.
493 H
494 SUPREME COURT REPORTS [2014] 5 S.C.R ..
A Constitution of India, 1950:
Alt. 32 - Writ petition - Claiming simll~r relief with regard
to grant of mining lease as was directed in the case of
appellant in its appeal - Held: Petitioners cannot approach
8 the Coult directly under Alt. 32 of the Constitution by filing writ
petitions, as no fundamental right of th~ petitioners is violated
by non-granting of mining lease - However, petitioners are
at libelty to approach High Coult in the first instance and! or
any other forum which is available, as per law.
C In terms of MOU dated 15.5.2002 entered into
between the contempt-petitioner-appellant and the State
Government of Orissa, the latter recommended to the
Central Government grant of irpn ore mines ih favour of
the appellant for use of iron ore in proposed plant. For
D this purpose, Thakurani area with 96 million tonnes iron
ore reserve and Keora area with additional 128 million
tonnes of iron ore were earmarked for 50 years
requirement of the plant. The. plant was set up, but, due
to family dispute, which was subsequently resolved,
E there arose some difficulties in getting the grant of iron
ore lease. Meanwhile in 2006, the State Government took
a decision that mining lease over Thakurani area could
not be allowed in favour of the appellant, and made a
recommendation to Central Government to grant mining
F lease in favour of "NM(P) Ltd.". The appellant challenged
these orders before the High Court in a writ petition,
which was dismissed. However, the appeal of the
appellant (C.A. No. 279012012) was allowed by the
Supreme Court by its order dated 14.3.2012, with the
G direction to the State Government to take appropriate
steps to act in terms of MOU dated 15.5.2002 as also its
earlier commitments to recommend the case of the
appellants to the Central Government for grant of
adequate iron ore reserve to meet the requirement of the
H appellants' steel plant. The directions were implemented
BHUSHAN POWER & STEEL LTD. v."·' RAJ ESH 495
VERMA
with regard to Thakurani area, but the same were not A
implemente'd as regards Ke.ora area. Aggrieved, the
appellant filed the contempt petition. The State
Government filed I.A. No. 14 of 2013 giving details of
subsequent developments, whi(:h according to the State
Government made. it difficult to recommend the case of B
the appellant. It was also stated that the issue which was
dealt with by Supreme Court in Sandur Managenese, 1 was
not raised in the appellants' vyrit petition or in their appeal.
I.A. No. 2 in 1..A. No. 14 of 2013 was filed by another
company against the status quo order passed in the c
applications of the appellant. The petitioners in other
three writ petitions claimed that benefit granted to the
appe~nt by order 14.3.2012 in C.A. No. 2790/2012, be also
extended to them.
Disposing of the matters, the Court D
HELD: 1.1. The appellant, by means of the contempt
petition, is seeking the ~nforcement of the directions
contained in its favour in the judgment dated 14.3.2012
passed in C.A. NO. 2790 of 2012. The State Government E
has exhibited helplessness in carrying out the directions
contained in the judgment dated 14.3.2012 even qua the
beneficiary of the said judgment namely, the appellant. In
the MOU entered into between the parties, the State
Government had committed to recommend to the Central F
Government, for grant of iron ore mines to the appellant
for use in its proposed plant. Pursuant to the grant of
permissions by various authorities enabling the appellant
to get the land, electricity, permission for installation of a
Captive Power Plant etc. etc., it set up the plant with an G
investment of Rs. 25,000 crores. It is further mentioned
that for running of this steel plant, uninterrupted supply
of iron ore is essential. This plant was set up in a
1. Sandur Manganese and Iron Ors. v. State of Kamataka 2010 (11) SCR
~~ H
496 SUPREME COURT REPORTS [2014] 5 S.C.R.
A backward area of Orissa persuant to the scheme of ttie
State Government. The Court held that MOU dated
15.5.2002 still subsisted in favour of the appellant and
also that State Government was under obligation to make
recommendations as per the said MOU. [Para 13-16] [506·
B F, G-H; 507-D, G-H; 508-A, F, G]
1.2. In so far as reserve of 96 million tonnes of iron ore
in Thakurani mines is concerned, the State Government
had made the recommendation to the Central
C Government, which also approved the same in favour of
the appellant. As regards a reserve of 128 million tonnes
in Keora mines, the respondents/ contemners do not
dispute (and in fact there is no scope for any dispute) that
the directions contained in the judgment have become
final. One would, therefore, command for obeying these
D directions. However, the State Government/contemners
have pleaded their helplessness by narrating certain
circumstances and developments as also the statutory
mandate embodied in s. 11 (4) of the MMDR Act, 1957
which, are stated to have come in the way of the
E respondent State in implementing the final order and
judgment dated 14.3.2012 in so far it relates to the Keora
area. [Paras 17 -19] [510-A-C; 512-8-C]
1.3. The respondents cannot raise a plea to avoid
F implementation of the directions contained in the
judgment. It is significant to note that there is a judgment,
inter partes, which has become final. Even when the civil
appeal was being heard, certain other parties claiming
their interest in these very lands had moved intervention
G applications which were dismissed. At that time also it
was mentioned that there are 195 applicants. However,
notwithstanding the same, this Court issued firm
directions to the State Government to recommend the
case of the petitior:iers for mining lease in both the areas.
H In view of such categorical and unambiguous directions
BHUSHAN POWER & STEEL LTD. v. RAJ ESH 497
VERMA
-giv~!'.I in the judgment which has attained finality, merely A
because another judgment has been delivered by this
Court in Sandur Manganese case, cannot be a ground to
undo the_ directions contained in the judgment dated
14.3.2012. [Para 20 and 24] [512-B-C; 515-C-E]
B
T.R. Dhananjaya vs J. Vasudevan 1995 (3) Suppl. SCR
=
64 (1995) 5 SCC EM~; Prithawi Nath Ram v. State of
Jharkhand and Others; 2004 (3) Suppl. SCR 740 = (2004)
7 SCC 261; Bihar Finance Service H. C. Coop. Soc. Ltd. v.
Gautam Goswami and Ors.; (2008) 5 sec 339 - relied on.
c
Sandur Manganese and Iron Ore vs State of Karnataka
2010 (11) SCR 240 = (2010) 13 SCC 1 - referred to,
1.4. In so far as law laid down in Sandur Manganese
is concerned, that may be applied and followed by the D
State Government in respect of other applications which
are still pending. However, that cannot be pressed into
service qua the appellant whose rights have been
crystallised by the judgment rendered in its favour. It
cannot be 're-opened, that too at the stage of E
implementation of the said judgment. [Para 24] [515-E-F]
1.5. Once the respondents are bound to implement
the direction contained in judgment dated 14.3.2012, in so
far as the State Government is concerned, it is obliged to
comply therewith and such matters, alongwith other F
relevant considerations, can be left to the wisdom ,of the
Central Government while taking a decision on the
recommendation of the State Government. [Para 25] [516-
B-C]
G
1.6. This Court, therefore, holds that the respondents/
contemners are in contempt of orders dated 14.3.2012
passed by this Court, in not complying with the directions
in respect of Keora area. However, they are given one final ·
opportunity to purge the contempt by transmitting H
498 SUPREME COURT REPORTS (2014) 5 S.C.R.
A requisite recommendations to the Central Government. It
would be for the Central Government to consider the said
recommendations on its own merits and in accordance
with law. In case the recommendation is sent within one
month, the respondents/ contemners shall stand
B discharged from the contempt petition and no further
action will be taken. However, in case the respondents
do not purge in the manner suggested, it would be open
to the petitioners to point out the same to this Court by
moving appropriate application and in that event the
c contemners shall be proceeded against. [Para 27] [517-
8-E]
2. In so far as three writ petitions are concerned, they
claim on the basis of parity with the appellant. However,
on the basis of such a plea, the petitioners in the said
D petitions cannot approach this Court directly under Art.
32 of the Constitution by filing writ petitions, as no
fundamental right of the petitioners is violated by non-
granting of mining lease. However, the petitioners are at
liberty to approach the High Court in the first instance
E and/ or any other forum which is available, as per law.
[Paras 29 and 30] [517-F, G-H; 518-A, C-0]
Monnet !spat & Energy Ltd. V. U.0.1 & Ors. 2012 (7)
SCR 644 = (2012) 11 SCC 1; State of Assam v. Om Prakash
F Mehta 1973 (3) SCR 169 = (1973) 1 SCC 584 - relied on.
Supreme Court Bar Association v. Union of India & Anr.
1998 (2) SCR 795 = (1998) 4 SCC 409 - referred to.
Case Law Reference:
G
2010 (11) SCR 240 referred to para 5
1995 (3) Suppl. SCR 64 relied on para 21
2004 (3) Suppl. SCR 740 relied on para 22
H 2008 (3) SCR-1.t37 reUed on para 23
BHUSHAN POWER & STEEL LTD. v. RAJESH 499
VERMA
1998 (2) SCR 795 referred to para 26 A
2012 (7) SCR 644 relied on para 29
1973 (3) SCR 169 relied on para 29
CIVIL APPELLATE JURISDICTION: Contempt Petition (C) B
No. 374 of 2012.
In
.
Civil Appeal No. 27~0 of 2012.
.
From the Judgment & Order dated 14.12.2007 passed by
c
the Hgih Court of Orissa at Cuttack in W.P.(C) No. 6646 of
2006.
WITH
D
W.P.(C) Nos. 60, 194, 837 of 2013.
{A. No. 14 &I.A. No. 2 in I.A. No. 14 in C.A. No. 2790 of 2012.
L. Nageswara Rao, ASG, Mukul Rohatgi, Dr. A.M. Singhvi,
.R.F. Nariman, K.K. Venugopal, Pinaki Mishra, K. E
Radhakrishnan, Shibashish Misra, Abhinav Rao, Mahesh
Agarwal, Rishi Agrawala, E.C. Agarwala, Radhika Gautam,
Devika Mohan, Ranjeeta Rohtagi, Sunil Fernandes, Ranjana
Roy Gawai, Raghav Chadha, Astha Sharma, Sanjeev Kumar,
Rohit Bhatt, Rajat Jariwal, Aakash Bajaj (for Khaitan & Co.), F
Suresh Chandra Tripathy, Sanjay Jain, Sunil Kumar Jain, Sachin
Sharma, Satya Mitra Garg, Manjula Gupta, Mohan Prasad
Gupta, D.S. Mahra for the following parties.
The Judgment of the Courtwas delivE3red by. G
A.K SIKRI, J. 1. All the aforesaid matters wer.e heard
analogously as they are inter-connected. In fact, it is the
judgment dated 14.3.2012 passed in C.A. No. 2790 of 2012
which has become the trigger point of all other cases. C.A. No.
2790 of 2012 was filed by M/s. Bhushan Power and Steel Ltd. H
500 SUPREME COURT REPORTS [2014] 5 S.C.R.
A (formerly known as Bhushan Limited) (hereinafter referred to
as 'BPSL'). That was an appeal against the judgment passed
by High Court of Orissa whereby the High Court had dismissed
the writ petition of the BPSL. Before proceeding further, we
would like to narrate the nature of different cases and the
B background in which they came to be filed.
CCP No. 374 of 2012
2. The erstwhile Bhushan Limited had proposed setting up
of plant in some identified villages in the District of Sambalpur,
C Orissa. For this purpose it had made a request for acquisition
of land, measuring 1250 acres, which was acquired for Bhushan
Limited. It had also applied for grant of lease of mining of iron
ore for use in the proposed plant. These applications were
favourably considered by the State Government which agreed
D to accord due priority to Bhushan Limited for grant of suitable
iron qre areas and also agreed to recommend the proposal to
the Government of India for grant of a Coal Block. Even a MOU
was entered into between the State Government and Bhushan
Limited containing the commitment of the State Government to
·E recommend to the Central Government, grant of iron ore mines
for its use in the proposed plant. For this purpose area
earmarked for recommendation were Thakurani area with 96
million tonnes iron ore reserves and Keora Area, District
Sundargarh for additional 128 million tonnes of iron ore; both
F for 50 years requirement of the plant. Though various statutory
and other permissions required for setting up of the plant were
granted and the plant was also set up, but due to some in-fight
between the family members who owned Bhushan Limited, it
faced difficulties in getting the grant of iron ore lease.
G 3. In so far as granting of mining lease of iron ore reserves
in the aforesaid areas is concerned, it fell into rough weather.
It resulted into show cause notice dated 18.1 .. 2006 by the State
Government which led to the decision that mining lease over
the Thakurani area could not be allowed on various grounds
H and the application made by Bhushan Limited was premature.
BHUSHAN POWER & STEEL LTD. v. RAJ ESH 501
VERMA [A.K. SIKRI, J.]
Thereafter, the Government of Orissa made a recommendation A
to the Central Government on 9.2.2006 to grant mining lease
in favour of one M/s Neepaz Metallics (P} Ltd. in relaxation· of
Rule 59(1) of the Mining Rules, for a period of 30 years.
Challenging these orders, Bhushan Limited filed the writ petition
in the High Court on 8.5.2006. This Writ Petition was dismissed B
by the High Court on 14.12.2007 and challenging this decision
Special Leave Petition was filed which was granted converting
the SLP into C.A. No. 2790/2012. This appeal was allowed by
this Court vide judgment dated 14.3.2012 with the following
directions: c
"Accordingly, we allow the appeal and set aside the
judgment and order of the High Court of Orissa and also
the decision of the State Government dated 9.2.2006,
rejecting the Appellant's claim for grant of mining lease.
During the course of hearing, we have been informed that D
Thakurani Block A has large reserves of iron ore, in which
the Appellants can also be accommodated. We,
accordingly, direct the State of Orissa to take appropriate
steps to act in terms of the MOU dated 15.5.2002, as also
its earlier commitments to recommend the case of the E
Appellants to the Central Government for grant of adequate
·iron ore reserves to meet the requirements of the
Appellants in their steel plant at Lapanga".
4. It would be pertinent to mention that State of Orissa had F
filed Review Petition seeking review of this judgment but the
same was rejected. Pursuant to the aforesaid directions, though
the BPSL has been given Thakurani Block A, the order has not
been implemented qua Keora, District Sundargarh. That is
precisely the cause for filing Contempt Petition (Civil) No. 374 G
of 2012 by BPSL.
I.A. No. 14 of 2013
5. The State of Orissa and its officials who are impleaded
as Contemners in the CCP have filed their replies to the CCP H
502 SUPREME COURT REPORTS [2014] 5 S.C.R.
A expressing certain difficulties because of which they claim that
the directions given in the judgment are incapable of
enforcement. Simultaneously, Respondent No. 1/ State of
Orissa has filed instant I.A. No. 14 of 2013 as well, in which
certain subsequent developments which have taken place after
B the passing of the judgment dated 12.3.2012 are traversed. It
is highlighted that there are certain other and legal proceedings
filed by them are pending at various stages in the High Court
or in this Court and the area claimed bY. them in those legal
proceedings overlap with the area which is the subject matter
c of grant to BPSL. A reference is also made to subsequent
judgment in the case of Sandur Manganese & Iron Ore v. State
of Karnataka; (2010) 13 SCC 1 which has changed the legal
position thereby making it difficult for the State to recommend
the case of the petitioner. It is also stated that the issue which
is dealt with by this Court in Sandur Manganese (Supra) was
0
not raised in the Writ proceedings/ Civil Appeal of the BPSL.
On the basis of the aforesaid averment prayer made in the I.A.
reads as under:-
"Pass appropriate directions with regard to implementation
E of the directions contained in final order and judgment
dated 14.3.2012 passed by this Hon'ble Court in Civil
Appeal No. 2790 of 2012 in so far as it relates to the
mining lease applications of the petitioner for an additional
128 million tonnes of iron ore over lands in Keora area of
F Sundergarh District".
I.A. NO. 2 OF 2013 IN I.A. NO. 14 OF 2013
6. In I.A. No. 14 of 2013, this I.A. is preferred by M/s. Shri
Mahavir Ferro Alloys Pvt. Ltd. The grievance of this applicant
G is against the status quo order dated 21.4.2008 passed in the
applications filed by the BPSL. It is alleged that the applicant
has filed 9 applications for grant of Iron Ore Mining Lease of
different areas, notified as well as non-notified, including the
Thakurani area. However, because of the status quo order the
H applications of the applicant not being considered by the State
BHUSHAN POWER & STEEL LTD. v. RAJ ESH 503
VERMA [A.K. SIKRI, J.]
Government which is adversely affecting the interest of the A
applicant.
WRIT PETITION (CIVIL) NO. 60 OF 2013
7. While narrating the facts of C.A. No. 2790 of 2012 in
brief, we had mentioned about the inter se disputes between B
the family members of erstwhile Bhushan Limited because of
which BPSL faced difficulties in getting the grant of iron ore
lease. It so happened that during the pendency of the aforesaid
appeal, the family members resolved their disputes. On
28.2.2006, Bhushan Limited altered its name to BPSL. Other C
group got incorporated a company named as M/s. Bhushan
Steel Limited (BSL). BSL is the petitioner in the instant petition.
This significant development was taken note of in the judgment
dated 14.3.2012 in the following manner:-
D
"As indicated hereinbefore, on 21st April, 2008, this Court
passed an interim order in the Special Leave Petition filed
by Bhushan Limited directing the parties to maintain status
quo with regard to the lands indicated in the application
filed by the appellants for grant of mining lease. However,
one of the most significant developments that subsequently
E I
took place was that on 25th NovemQer, 2011, Shri B.B.
Singhal and Shri Neeraj Singhal, Vice-Chairman and
Managing Director of Bhushan Steel and Strips Ltd. filed
affidavits withdrawing all their claims and rights in the MOU
dated 15th May, 2002, executed between the State F
Government and Bhushan Limited and declaring that the
said MOU was and had always been in favour of Bhushan
power & Steel Ltd. The above named persons also prayed
for deletion of their names from the array of parties.'.'
G
xxxxxxx
The mutual settlement of the disputes between the
members of the Bhushan Group has altered the situation
considerably, since BSSL has withdrawn its claim under H
504 SUPREME COURT REPORTS [2014] 5 S.C.R.
A the MOU dated 15th May, 2002 and has declared that the
said MOU was and had always been executed by the
State Government in favour of Bhushan Power & Steel
Ltd., which had set up its steel plant at Lapanga. As
indicated hereinbefore, although, the MOU was entered
B into by the State Government with the Bhushan Group for
setting up a steel plant at Lapanga, at a later stage, BSSL
also laid claim under the MOU for setting up a separate
steel plant at Mehramandali and a suggestion was also
made for execution of a fresh MOU between the State
Government and BSSL to this effect."
c
8. It is the case of the SSL in the present Writ Petition that
BSL was a part of the then Bhushan Group. It executed a MOU
dated 15.5.2002 with the State of Orissa. Consequent to a
family settlement, Mis. Bhushan Steel and Strips Ltd. (BSSL)
D executed a separate MOA dated 3.11.2005 in which the State
of Orissa had identical duties and obligations as those
contained in 2002 MOU. On 12.4.2007, BSSL was re-named
as BSL herein. It is thus claimed that SSL is identically situated
as BPSL and, therefore, the benefit given to BPSL vide
E judgment dated 14.3.2012 needs to be extended to the SSL
as well. The direction in the nature of mandamus is sought to
implement the decision of 12th llAC Meeting dated 27.8.2003
and terms of MOA dated 3.11.2005 against the State
Government by making appropriate recommendation to the
F Central Government for allotment of the remaining portion in
Thakurani RF Block A, District Keonjhar i.e. 601.500 hectares
applied while ML Application No. 882 and the areas applied
vide ML Application No. 1079 i.e. 722.30 hectares
approximately in village Kadalia, Kuriyakudar, Mithirda etc.
G uhder Bonai sub-division, District Sundegarh to meet the
captive requirements of SSL plants.
9. In essence, the petitioner wants same treatment as is
given to BPSL and, therefore, has prayed for the extension of
the benefit of judgment dated 12.3.2012 to SSL as well.
H
BHUSHAN POWER & STEEL LTD. v. RAJ ESH 505
VERMA [AK. SIKRI, J.]
WRIT PETITION (C) NO. 194 OF 2013 A
10. This Writ Petition is filed by Jindal Steel and Power
Limited (hereinafter referred to as 'Jindal Steel'). It had entered
into MOU with the State of Orissa on 8.5.2002. It is stated in
the writ petition that this petitioner became an intervenor in C.A. 8
No. 2790 of 2012 to protect its interest which has been duly
·taken note of in the judgment dated 14.3.2012 in the following
manner:-
"Appearing for the Intervener, M/s. Jindal Steels Ltd., Mr.
K.V. Vishwanathan, learned Senior Advocate, submitted C
that so long as any allotment made in favour of the
Appellants did not impinge on the allotment made in favour
of M/s. Jindal Steels Ltd;, it could have no grievance
against a separate allotment being made in favour of the
Appellants." D
11. It is pleaded that the case of Jindal Steel is even on a
better footing for grant of mining lease, application for which
purpose are pending with the State of Orissa. It had also signed
the MOU for setting up an integrated Steel Plant wherein similar E
promise was made by the State Government for grant of a
mining lease. Additionally, Jindal Steel had the advantage of
being an earlier applicant for the mining lease in regard to
Thakurani RF Block A area which was also a part of an MOU
by BPSL. It is further mentioned that 16 mining lease
F
applications were received in respect of the said area and the
Director of Mines vide his report dated 8.11.2002 rejected all
other applications except that of Jindal Steel herein, BPSL and
three other applicants. In the case of Jindal Steel,
recommendation was for 264 hectares in Thakurani RF Block
A as against 383 Hectare in respect of BPSL. It is also stated G
that even when recommendation in respect of BPSL in
Thakurani area is made by the State Government and
approved by the Union of India, recommendation of Jindal Steel
is still pending with the State Government. It is thus, pleaded
that the case of the petitioner, Jindal Steel, is squarely covered H
506 SUPREME COURT REPORTS [2014] 5 S.C.R.
A by judgment dated 14.3.2012 passed in C.A. NO. 2790 of
2012 and benefit thereof be extended to this petitioner as well.
WRIT PETITION (C) NO. 837 OF 2013
12. This Wi"it Petition is filed by Shri Mahavir Ferro Alloys
B Pvt. Ltd. It has also proposed to set up a 0.35 MTPA Captive
Integrated Steel Plant with additional facilities and 60 MW
Captive Power Plant in Sundargarh district had an overall
investment of Rs. 435 crores. This petitioner claims that
pursuant to MOU entered into with the State Government for
C grant of mining leases, it had submitted its application in this
behalf. However, more than 10 years have elapsed but the
State Government has not recommended its case, primarily
because of status quo orders passed by this Court in C.A. NO.
2790 of 2012. It is pointed out that for this reason this petitioner
D has already filed I.A. No. 2 in I.A. NO. 14 of 2013 in C.A. NO.
290 of 2012. Case of this petitioner, again, is that it is equally
circumscribed and placed as BPSL as well as Jindal Steel and,
therefore, entitled to the grant of mining lease as done in favour
of BPSL by this Court vide judgment dated 14.3.2012.
E
13. We have reproduced, hereinabove gist of the cases
filed by different parties to get the favour of the proceedings. It
becomes obvious and can be readily understood that in so far
as BPSL is concerned, by means of Contempt Petition, it is
F seeking the enforcement of the directions contained in its favour
in the judgment dated 14.3.2012 passed in C.A. NO. 2790 of
2012. Three other parties namely BSL, Jindal Steel and
Mahavir Ferro Alloys (P) Ltd. have filed Writ Petitions claiming
same relief as given to the BPSL vide judgment dated
14.3.2012 on the ground that they are placed in the similar or
G even better position than BPSL and, therefore, entitled to same
treatment. Further, as already pointed out above, the State
Government has ventured to exhibit its helplessness in carrying
out the directions contained in the judgment dated 14.3.2012
even qua the beneficiary of the said judgment namely BPSL.
H In so far as other three writ petitioners are concerned, not only
BHUSHAN POWER & STEEL LTD. v. RAJ ESH 507
VERMA [A.K. SIKRI, J.]
same difficulties are sought to be projected, ,it is also mentioned A
that are precluded from· seeking same relief as given to BPSL
for various reasons. That apart, even the maintainability of the
writ petitions under Article 32 of the Constitution filed by these
petitioners i.s questioned. In such a scenario it i.s apposite to
first de;al with the GCP filed. by BPSL. B
'
CONTEMPT PETITION (Cl NO. 374 OF 2012 In
C.A. No. 2790 OF 2012
· 14. We have already narrated the gist Of factual c
background in which BPSL approached the High Court and
thereafter this Court for grant of mining leases of iron.ore. As
already mentioned, in the MOU entered into between the
· parties, the State Government had committed to recommend
to the Central Government, for grant of iron ore mines to the D
BPSL for its use·in the plant to be set up at Lapanga. In this
behalf it was agreed to make the following recommendations
to the Central Government:-
(a) For grant of 96 million tonnes iron ore reserves in
.Joda Barbi! Sector of Keonjhar (Thakurani area) E
· for 50 years requirement of the plant.
(b) For additional 128 million tonnes of iron ore
reserves in Keora, District Sundergarh, to meet a
requirement of 1.6. million tonnes for 50 years. F
15. It is not necessary to set out the detailed facts which
have been noted in judgment dated 14.3.2012, pertaining to
the grant of permissions by various authorities enabling BPSL
to get the land, electricity, permission for installation of a G
Captive Power Plant etc. etc. Armed with those permission, the
BPSL set up the plant in Lapanga in the district of Sambalpur,
Orissa. BPSL claims that is has invested Rs. 25,000 crores in
this project. It is further mentioned that for running of this steel
plant, uninterrupted supply of iron ore is essential. This plant
was set up in a backward area of Orissa persuant to the H
508 SUPREME COURT REPORTS [2014] 5 S.C.R.
A scheme of the State Government. It is for this reason that the
State Government agreed to grant mining rights of iron ore
reserves, keeping in view a total requirement of 200 million
tonnes over a period of 50 years for the smooth running of the
said plant. For this reason MOU dated 15.5.2002 was entered
B into. Since the grant of mining lease is by the Central
Government under the Mining Act, State Government which is
a recommendatory authority had agreed to recommend the
case of the BPSL. There was deadlock for some period
because of infight within Bhushan family. However, this impasse
c came to be resolved. Taking note of these developments the
Court was of the opinion that there were two issues which arose
for considerations namely:
(a) Whether the Memorandum of Understanding
dated 15th May, 2002 continues to subsist in
D favour of the appellants?
(b) Whether the State Government is obliged to make
recommendations. for the grant of iron ore mines
in terms of the stipulations contained in the
E aforesaidMOU dated 15th May, 2002 andwhether
in respect of the areas which had notbeen notified
under Rule 59(1 ), the StateGovernment can make
a recommendation forrelaxation of Rule 59(1)
under Rule 59(2).
F 16. The Court deliberated at length on these issues and
decided in favour of BPSL holding that MOU dated 15.5.2002
still subsisted in favour of the BPSL and also that State
Government was under obligation to make recommendations
as per the said MOU. The most relevant part of discussion, in
G this behalf, reads as under:
"Pursuant to the MOU with Bhushan Limited, the State
Government had not only allotted land for the setting up of
the steel plant at Lapanga, it had even extended all help
H for the commissioning of the plant, which, in fact, had
BHUSHAN POWER & STEEL LTD. v. RAJ ESH 509
VERMA [A.K. SIKRI, J.] ·
already started functioning. However, it is the claim made A
by BSSL under the MOU executed on 15th May, 2002, that
had created obstructions in the setting up of the steel plant
at Lapanga. Despite having allotted land and granted
sanction to Bhushan Limited to take steps for construction
of the said plant, it was subsequently contended that the B
application filed by Bhushan Limited was premature and
could not, therefore, be acted upon. Specific instances
have been mentioned hereinabove of the steps taken by
the various departments in extending cooperation to
Bhushan Limited to set up its steel plant at Lapanga. To c
now turn around and take a stand that the application made. ·
by Bhushan Limited was premature, is not only
unreasonable, but completely unfair to Bhushan Limited,
who have already invested large sums of money in setting
up the plant. The State Government had, on its own D
entered into the MOU with Bhushan Limited on 15th May,
2002, and had even agreed to request the Central
Government to allot mining areas and coal blocks for
operating the steel p·lant. Whatever differences that may
have resulted on account of the dispute within the Bhushan E
Group, which could have led to the rethinking on the part
of the State Government, have now been laid to rest by
virtue of the settlement arrived at between the Bhushan
Limited ~now BPSL) and BSSL. The State Government
has also accepted the said position. In addition to the
above, the action taken by the State Government appears F
to us to be high,ly unreasonable and arbitrary and also
attracts the doctrine of legitimate expectation. There is no
denying the fact that the Appellants have altered their
position to their detriment in accordance with the MOU
dated 15th May, 2002. whatever may have been the G
arrangement subsequently arrived at between the State
Government and BSSL, the original MOU dated 15th May,
2002, continued to be in existence and remained
operative".
H
510 SUPREME COURT REPORTS [2014] 5 S.C.R.
A 17. In so far as reserve of 96 million tonnes of iron ore in
Thakurani mines are concerned, the State Government had
made the recommendation to the Central Government, which
has also approved the same in favour of the BPSL. The dispute
now relates to Keora mines for a reserve ofJ28 million tonnes.
B
18. Respondents/ Contemners do not dispute (and in fact
there is no scope for any dispute) that the aforesaid directions
contained in the judgment have become final. Review Petition
was filed by the State Government but unsuccessfully. One
C would, therefore, command for obeying these directions.
However, the State Government/ Contemners have pleaded
their helplessness by narrating certain circumstances which are
captured herein below.
"(a) These areas fall almost entirely within the areas notified
D on 23.8.1991 under Rule 59(1) of the Mineral Concession
Rules, 1960. The validity of the notification dated
23.8.19S1 is an issue in SLP(c)No. 31593 of 2010 and
connected cases .which are now listed for hearing on
17.01.2013 before another Division Bench of this Hon'ble
E Court.
(b) Further, it is seen that the applied area is overlapping
with the applied area of several other applicants, including
Mis. Larsen & Toubro Limited and M/s. Tata Iron and Steel
Co. Limited.
F
(c) It is also po.inted out that earlier on 21.10.1997 an are~
of 998.93 hectares overlapping with appliedarea of the
BPSL, was recommended in favour of M/s Larsen &
Toubro Ltd. in puruance with the said company. However,
G this recommendation was withdrawn for certain reasons.
Thereafter, even revised MU PL application of M/s. Larsen
and Toubro Ltd. Were rejected. The said company
challenged the order of rejection before the Revisional
Authority i.e. Central Government which passed orders
H dated 10.7.2003 wherein direction is given to consider
BHUSHAN POWER & STEEL LTD: v. RAJ ESH
VERMA [A.K. SIKRI, J.]
application of M/s. Lar:s.efl ~ ifoubro Ltd. Alongwith about A
196 app]ica.ti&ns" for grant of mining lease and after
granting- an opportunity of hearing to all the applicants.
However, BPSL is outside the 196 applications that were
to be considered afresh.
B
(d) M/s. Larsen and Toubro Ltd has challenged the
aforesaid orders of the Central Government by filing Writ
Petition in the High Court which was dismissed by the
Single Judge of Delhi High Court. Appeal thereagainst was
dismissed by the Division Bench on 3. 7 .2012. Order of the C
Division Bench of the High Court is challenged by filing
SLP (C) NO. 33812 of 2012 in which notice has been
issued and as the matter is sub-judice in those
proceedi11gs it is difficult to pass any orders qua B P S L
at this stage.
D
(e) It is further pointed out that in the case of Sandur
Mangnese (Supra) this Court has considered the
provisions of Section 11 (4) of the MMDR Act and ha$
concluded that all applications filed over areas notified
under Rule 59(1) of the Mineral Concession Rules, 1960 E
deserve simultaneous consideration. As per the mandate
of Section 11 (4) of the MMDR Act, the State Government
may grant a mining lease over a notified area to such one .
of the simultaneous applicants after considering the
matters specified in sub-section (3) of Section 11. The F
process of simultaneous consideration of the applications
filed over ·Khajhurdihi R.F. In Sundergarh and Rakma,
Marsuanand Tiriba of Keonjhar district had rem a i n e d
stalled due to the various stay orders passed in litigations
concerning such area. Subject to the orders, if any, passed G
by this Hon'ble Court in this application, the process of
simultaneous consideration of applications will take
considerable time in view of the large number of
overlapping applications over the areas in question. Each
of these applicants is required to be given an opportunity H
512 SUPREME COURT REPORTS [2014] 5 S.C.R.
A of personal hearing and credentials of these applicants are
required to be evaluated for assessment of relative merits
in terms of Section 11 (3) of the MMDR Act."
19. It is thus, argued that the developments narrated above
and the statutory mandate embodied in Section 11 (4) of the
8
MMDR Act, 1957 have come in the way of the Respondent
·state in implementing the final order and judgment dated
14.3.2012 in so far it relates to the Keora area of Sundergarh
district. It is_ also sought to be argued that the question of
entitlement of the petitioner to the recommendation of mines
C in the Keora area, which are almost entirely covered under
notification issued under Rule 59(1) of MC Rules, 1960 with
specific reference to Sections 11 (4) and 11 (3) of the MMDR
Act was not raised in the Writ Proceedings/ Civil Appeal. During
the course of the implementation of the order of this Hon'ble
D Court dated 14.3.2012 passed in Civil Appeal No. 2790 of
2012, the Respondent No. 1 is faced with the difficulties with
regard to the Keora area as enumerated above. Hence, this
application for appropriate directions.
E 20. The question is as to whether such a plea can be
raised to avoid implementation of the directions contained in
the judgment? Our answer is in the negative, having regard to
the categorical and authoritative principle of law enunciated by
various judgments of this Court. From the reading of these
F judgments one can comfortably get a complete answer to the
so-called difficulties feigned by the State Government/
Contemners:
21. First judgment which needs to be noticed is in the case
of_T.R. Dhananjaya v. J. Vasudevan; (1995) 5 SCC 619. The
G following discussion contained in the said judgment squarely
applies here:-
"10. When this order was passed, what remained for the
respondent was only implementation of the order passed
H by this Court in furtherance of the action taken thereunder
BHUSHAN POWER & STEEL LTD. v. RAJ ESH 513
VERMA [A.K. SIKRI, J.]
by the Corporation. It is now clear that instead of A
implementing the order, an attempt has been made to
circumvent the same and deny the benefits to the petitioner.
As stated earlier, the petitioner is a Corporation employee
and the stand of the Government appears to be to give
benefit to their employees. So, an attempt has now been B
made to get into the rule position and to find whether the
petitioner is eligible to be considered for promotion to the
post of Executive Engineer, Superintending Engineer and
Chief Engineer. It is now stated that according to the rules
the petitioner would be eligible only as superintending c
engineer and not as Chief Engineer. When direction was
given in LA. 3 of 1993, Government was a party to the
proceedings and it was never brought to our notice that the
petitioner was not eligible. On the other hand, the Division
Bench of Karnataka High Court upheld the right of the
0
petitioner which became final.
11. Question is whether it is open to the respondent to take
at this stage this volte-face step. It is seen that all through
Government was a part)L, when the direction was given in
LA. No. 3 filed by the petitioner, it was not brought to out E
notice that the petitioner was not eligible for promotion, in
contradiction with Dasegowda, or any other. When t11e
claim inter se had been adjudicated and the claim of the
petitioner had become final and that of Dasegowda was
negatived, it is no longer open to the Government to go F
behind the order and truncate the effect of the orders
passed by this Court by hovering over the rules to get
round the result, to legitimise legal alibi to circumvent the
orders passed by this Court. Thus, it is clear that the
concerned officers have deliberately made concerted effort G
to disobey the orders passed by this court to deny the
benefits to the petitioner. So, we are left with no option but
to hold that the respondent has deliberately and wilfully,
with an intention to defeat the orders of this Court, passed
the impugned order." H
514 SUPREME COURT REPORTS [2014] 5 S.C.R.
A 22. Another judgment cited at the bar is Prithawi Nath Ram
v. State of Jharkhand and Others; (2004) 7 SCC 261. Para 8
of the said judgment makes the following reading:
"8. If any party concerned is aggrieved by the order which
B in its opinion is wrong or against rules or its
implementation is neither practicable nor feasible, it ~hould
always either approach the court that passed the order or
invoke jurisdiction of the appellate court. Rightness or
wrongness of the order cannot be urged in contempt
proceedings. Right or wrong, the order has to be
c obeyed. Flouting an order of the court would render
the party liable for contempt. While dealing with an
application for contempt the court cannot traverse
beyond the order, non-compliance with which is
alleged. In other words, it cannot say what should not have
D been done or what should have been done. In cannot
traverse beyond the order. It cannot test correctness or
otherwise of the order or give additional direction or delete
any direction. That would be exercising review jurisdiction
while dealing with an application for initiation of contempt
E proceedings. The same would be impermissible and
indefensible. In that view of the matter, the order of the High
Court is set aside and the matter is remitted for fresh
consideration. It shall deal with the application in its proper
perspective in accordance with law afresh. We make it
F clear that we have not expressed any opinion regarding
acceptability or otherwise of the application for initiation
o( contempt proceedings". ·
23. This very principle has been reiterated by in Bihar
G Finance Service H. C. Coop. Soc. Ltd. v. Gautam Goswami
and Ors.; (2008) 5 SCC 339 in the following words:
"32. While exercising the said jurisdiction this Court does
not intend to re-open the issues which could have been
raised in the original proceeding nor shall it embark upon
H other questions including the plea of equities which could
BHUSHAN POWER & STEEL LTD. v. RAJ ESH 515
VERMA [A.K. SIKRI, J.]
fall for consideration only in the original proceedings. The. A
Court is not concerned with as to whether the original order
was right or wrong. The court must not take a different view
or traverse beyoncl the same. It cannot ordinarily give an
additional direction or delete a direction issued. In short,
it will not do anything which would amount to exercise of B
its review jurisdiction".
24. We cannot lose sight of the fact that there is a
judgment, inter parties, which has become final. Even when the
Civil Appeal was being heard, certain other parties claiming C
their interest in these very lands had moved intervention
applications which were dismissed. At that time also it was
mentioned that there are 195 applicants. However,
notwithstanding the same, this Court issued firm directions to
the State Government to recommend the case of the petitioners
for mining lease in both the areas. In view of such categorical D
and unambiguous directions given in the judgment which has
attained finality, merely because another judgment has been
delivered by this Court in Sandur Manganese case, cannot be
a ground to undo the directions contained in the judgment dated
14.3.2012. In so far as law.laid down in Sandur Manganese E
(Supra) is concerned, that may be applied and followed by the
State Government in respect of other applications which are
still pending. However, that cannot be pressed into service qua
the petitioner whose rights have been crystallised by the
judgment rendered in its favour. It cannot be re-opened, that too F
at the stage of implementation of the said judgment.
. .
25. We would like to place on record the arguments of
learned Senior Counsel for the petitioner that the total area
under notification is 731.67 sq. kms. and out of this 406 sq. G
km. is yet to be allotted. The area which comes to the share of
the petitioner under MOU is 13.91 sq. km. which is barely 3
percent of 406 sq. km and, therefore recommendation by the
State Government in favour of the petitioner cannot be stalled
or put to naught only on the basis of inchoate applications, fate H
516 SUPREME COURT REPORTS [2014] 5 S.C.R.
A whereof is yet to be decided. It is also pointed out that in so
far as the petitioners in other writ petitions are concerned area
claimed by them is not overlapping with the petitioner's area.
However, it may not even be necessary to go into these
contentions in detail. Once we hold that the respondents are
B bound to implement the direction contained in judgment dated
14.3.2012, in so far as the State Government is concerned, it
is obliged to comply therewith and such matters, alongwith other
relevant considerations, can be left to the wisdom of the Central
Government while taking a decision on the recommendation of
c the State Government.
26. In so far as intervention applications by Talas and LNT
are concerned these are dismissed as non maintainable, in
view of law laid down in by this Court in Supreme Court Bar
Association v. Union of India & Anr.; (1998) 4 SCC 409;
D
"42. The contempt of court is a special jurisdiction to be
exercised sparingly and with caution whenever an act
.adversely affects the administration of jµstice or which
tends to impede its course or tends to shake public
E confidence in the judicial institutions. This jurisdiction may
also be exercised when the act complained of adversely
affects the majesty of law or dignity of the courts. The
purpose of contempt jurisdiction is to uphold the majesty
and dignity of the courts of law. It is an unusual type of
F jurisdiction combining "the jury, the judge and the
hangman" and it is so because the court is not adjudicating
upon any claim between litigating parties. This jurisdiction
is not exercised to protect the dignity of an individual judge
but to protect the administration of justice from being
maligned. In the general interest of the community it is
G
imperative that the authority of courts should not be
imperilled and there should be no unjustifiable interference
in the administration of justice. It is a matter between the
court and the contemner and third parties cannot intervene.
It is exercised in a summary manner in aid of the
H
BHUSHAN POWER & STEEL LTD. v. RAJ ESH 517
VERMA [A.K. SIKRI, J.]
administration of justice, the majesty of law and the dignity A
of the courts. No such act can be permitted which may
have the tendency to shake the public confidence in the
fairness and impartiality of the administration of justice"..
27. As a consequence, we hold th.at the Respondents/ 8
Contemners are in contempt of orders dated 14.3.2012
passed by this Court in not complying with the directions in
respect of Keora area. However, we are giving one final
opportunity to them to purge the contempt by transmitting
requisite recommendations to the Central Government. It would C
be for the Central Government to consider the said
recommendations on its own merits and in accordance with
law. In case the recommendation is sent within one month from
the date of copy of receipt of this order, we propose not to take
any further action and the respondents/ contemners shall stand
discharged from this Contempt Petition. However, in case the D
respondents do not purge in the manner mentioned above, it
would be open to the petitioners to point out the same to this
Court by moving appropriate application and in that event the
Contemners shall be proceeded against.
E
28. With this, I.A No. 14 in C.A. NO. 2790 of 2012 and
I.A. No. 2 in I.A. NO. 14 in C.A. NO. 2790 of 2012 also stand
disposed of.
Writ Petitions
F
29. In so far as three writ petitions .are concerned we need
not go into the detailed arguments advanced by Counsel for
the petitioners in those petitions. As already noted above, for
their own reasons all the three petitioners pray that the same
directions as given in favour of BPSL in judgment dated G
14.3.2012, be passed in their cases as well. This they claim
on the basis of parity with BPSL. However, we are constrained
·to hold that, on the basis of such an argument, they cannot
approach this court directly under Article '32 of the Constitution
by filing writ petitions. It has already been authoritatively H
518 SUPREME COURT REPORTS [2014] 5 S.C.R.
A determined that no fundamental right of the petitioners is
violated. No fundamental right is violated by non-granting of
mining lease. (See (2012) 11 SCC 1 and (1973) 1 SCC 584).
30. That apart, there are few other aspects, aptly pointed
8 out by Mr. L. Nageswara Rao, learned ASG, which come in the
way of maintainability of the· instant petitions. He, inter alia,
submitted that atleast in respect of applications which are still
pending and yet to be decided, judgment in Sandur
Manganese (Supra) shall have to be applied as it does not
C remain virgin area, which was the position when the case of
BPSL was decided. He had made various other submissions
on merit as well. Without going into all these issues, we dismiss
these petitions giving liberty to the petitioners to approach the
High Court in the first instance and/ or any other forum which
is available, as per law. We make it clear that in so far as these
D petitions are concerned we have not dealt with the issues on
merits. Wherever the petitions are filed, it would be open to the
said forum to deal with the question as to whether the
petitioners would be entitled to the benefit of judgment dated
14.3.2012 passed in the case of BPSL or not. All other issues
E are also kept open .to be agitated in those proceedings. Writ
petitions are dismissed with liberty as aforesaid.
Rajendra Prasad Matter disposed of.
Search Indian case law
Ask in plain English, not just keywords. 25,000 AI words free, no card.