CHIEF ADMINISTRATOR PUDA AND ANOTHERversusMRS. SHABNAM VIRK
- Citation
- 2006 INSC 167
- Decided
- 23 March 2006
- Disposal
- Appeal(s) allowed
- Bench
- ARIJIT PASAYAT
Holding
The respondent, having executed an affidavit undertaking to abide by all terms and conditions of the allotment letter, is liable to pay the revised price stipulated therein.
Summary
The Punjab Urban Development Authority (PUDA) advertised a housing scheme with a tentative flat price of Rs 6.3 lakh, stating that the price could be revised upward. Applicants, including the respondent, applied, signed a proforma undertaking to abide by all terms and to pay any higher cost due to material price fluctuations, and later received allotment letters showing a revised price of Rs 7.67 lakh (with floor‑wise slabs). The respondent paid 25% of the revised price, took possession, and subsequently claimed she was only liable to the originally advertised price. The District, State and National Consumer Disputes Redressal Forums held that only the advertised price was payable. On appeal, the Supreme Court held that the respondent’s affidavit expressly bound her to the terms of the allotment letter, and the clause in the advertisement did not limit price escalation to construction‑cost increases; therefore she must pay the revised amount. The Court allowed the appeal, overturning the National Commission’s decision.
Issues considered
- Whether the respondent is bound by the revised price indicated in the allotment letter despite the advertisement stating a tentative price.
- Whether the clause limiting price revision to construction‑cost escalation restricts the authority’s right to demand a higher price.
- Whether the respondent’s affidavit undertaking creates a contractual obligation to pay the revised price.
Legislation cited
Subjects
Judgment
CHIEF ADMINISTRATOR PUDA AND ANOTHER A
V.
MRS. SHABNAM VIRK
- MARCH 23, 2006
[ARIJIT PASA YAT AND TARUN CHATTERJEE, JJ.] B
Consumer Protection Act, 1986-Housing Scheme-Demand of increased
cost of flat-Advertisement inviting applications indicating tentative cost of
flat and that it was to be revisetf..-:AJ/otment letter demanding increased cost C
offlat-Affidavit of allottee accepting the allotment and undertaking to abide
by terms and conditions of the allotment letter-Allqttee, if liable to pay ·,
increased price stipulated in the letter-Held: Yes, si1Jce allottee had filed an
affidavit undertaking to abide by the terms and conditions of the letter-
Punjab Regional and Town Planning and Development Act, 1995.
D
Appellant-State Development Authority invited applications for
allotment of Oats fixing its costs at Rs. 6.3 lacs under the Scheme. The
price quoted was tentative, based on present cost of construction and was
likely to be revised on higher side on completion of houses. Respondent
and others applied for the flat undertaking to abide by the terms of the
Scheme. On completion of flats, draw was held for allotment of specific E
flat and allotment letters were issued indicating the base price of the flat
as Rs. 7.67 lacs. Respondent flied an affidavit undertaking to abide by the
terms and conditions of the allotment letter. Respondent deposited 25%
of the price stipulated and took possession of flat. Thereafter, he filed a
complaint that he was not liable to pay any aiMunt over and above the F
price advertised. District Forum held that there was a clear condition in
the advertisement that the price quoted was purely tentative and it was
likely to be revised on the higher side on completion of flats. However, it
directed the appellants to pay 12% interest on account of delay in handing
over the possession. State Commission directed the appellant to charge
only the price which was advertised while inviting the application and to G ·
pay 12% interest. National Commission held that there was no delay by
the appellant in handing over the possession. However, only the price
advertised while inviting application for allotment could be charged.
Hence, the present appeal.
221 H
222 SUPREME COURT REPORTS l2006 j 3 S. C.R.
A Allowing the appeals, the Court
HELD: Respondent herself had accepted in the undertaking filed
that she accepted the allotment of the house and undertook to abide by
all the terms and conditions of the allotment letter, the amount indicated
in the allotment letter was the revised amount on the higher side in respect
-
B of the allotment of the house. That being so the respondent was liable to
pay the amount as stipulated in the allotment letter. Nothing is found in
the quoted clause to show that the increase was possible only when there
was an increase in the cost of construction. The clause quoted does not
reflect any such intention of the parties. (226-B-DJ
c CIVIL APPELLATE JURISDICTION : Civil Appeal Nos. 3967-3968
of 2004.
From the Final Order dated 26.8.2003 of the National Consumer Disputes
Redressal Commission, New Delhi in Revision Petition No. 1206-1207 of
D 2002 and Order dated 17.3.2004 in Review Petition No. 31/2004.
Altaf Ahmed, Mrs. Rachana Joshi Jssar for the Appellants.
Manoj Swarup. Neeraj Sharma, Naresh Kaushal, Dinesh Verma, Ms.
Suresh Kumari, A.P. Mohanty, G.K. Bansal (N.P.), R.K. Talwar. S.S. Virk,
E Amit Talwar and S.L. Aneja for the Respondent.
The Judgment of the Court was delivered by
ARIJIT PASA YAT, J. Challenge in these appeals is to the order passed
by the National Consumer Redressal Commission, New Delhi (in short the
F 'Commission'). The Commission held that as delay in handing over the
possession was clearly established and the reasons in price escalation of the
house was not proved or established, the respondent was entitled to get the
house at Rs.6.3 lacs instead of Rs.7.44 lacs as demanded by the appellants.
Background facts in a nutshell, as projected by the appellants are as
G follows:
On 15.8.1995 the appellants floated a scheme for allotment of784 four
story MIG (SUPER) flats on hire purchase basis at SAS Nagar,(Mohali). The
scheme opened on 15.8.1995 and was to close on 14.9.1995. As per the
advertisement inviting applications for allotment under the said scheme, the
H tentative cost of the flat was fixed at Rs.6.3 lacs. However, condition (2)
CHIEF ADMINISTRATOR PUDA v. SHABNAM VIRK [PASAYAT, J.]223
therein clearly specified that the price quoted is purely tentative and based on A
the present cost of construction and that it was likely to be revised on the
higher side by the time houses are completed. The said clause reads as under:
"The price quoted is purely tentative and is based on the present cost
of construction. It is likely to be revised on the higher side by the
time houses are completed." B
The advertisement further stated that the allotment shall be governed
by PUDA under rules and regulations framed/amended from time to time.
On 27.3.1996 pursuant to the aforesaid advertisement, a large number·
of applicants (including the respondent) applied for a MIG Super Category C
flat under the scheme in the prescribed Proforma Clause 12(ii), (iii) & (iv)
of the said Proforma read as under:
"(ii) I have carefully gone through and understood the terms and
conditions of the scheme applied and do hereby undertake to abide
by the same. D
(iii) I also undertake to pay higher cost due to fluctuations in the
prices of building material or due to any other reason.
(iv) I shall abide by the terms and conditions of the allotment made
by the PUDA as amended from time to time and shall enter into such E
agreement in any manner and at any time, as stipulated by PUDA."
Prior to the construction of the flats, the first draw for allocation of
flats, was held on 7.12.1995. On the basis of this draw held prior to the
construction of flats, allocation letters (including allocation letter dated
27.3. I 996 issued to respondent) were issued. In the said allocation letters, the F
tentative cost of each flat was stated to be Rs.6.30 lacs. The said figure was
purely provisional, as was made explicit by Note (i), (ii) & (iii) contained in
the said allocation letter, which read as under:
"(ii) The aforesaid price is purely tentative. The actual price shall be
determined on completion of House/Flat and you shall be liable to G
make payment of the revised .price of thbe Houses/Flats, if any, at
the time of allotment.
(iii) Earnest Money already deposited with the Board will be adjusted
with the instalments required to be deposited before taking over
H
224 SUPREME COURT REPORTS [2006] 3 S.C.R.
A possession."
Note (i) contained in said al_location letters gave the tentative date when
the flats were expected to be completed. The said note stated:
"Houses/Flats are likely to be completed by April 1997. This date is
B however tentative and may change."
The applicants accepting the allocation were required to submit affidavits
to the effect that they would abide by the terms and conditions of allocation
and the respondent submitted the required affidavit dated 15.4.1996. 784
MIG (Super) flats were completed in the years 1998 and second draw was
C held for allotment of specific flat numbers to applicants successful in the first
draw, including the respondent and allotment letters dated 21.8.1998 were
issued to the applicants including the respondent.
On 16.10. I998 the respondent accepted the terms and conditions of the
allotment letter by tendering an affidavit dated 16.10.1998 to abide by the
D terms and conditions of the allotment letter as well as of the provisions of the
Punjab Regional and Town Planning and Development Act, 1995 (in short
'the Act') and rules framed thereunder.
On August, 1998 at the time of issue of the allotment letter the base
E price of the flats in question was calculated to be Rs.7,67,000/-. Further a
slab system was fixed for different floors which is as follows :
Ground Floor Rs. 8,05,400 (5% extra on the base price)
First Floor Rs. 7,67,000 (the base price) Second Floor -
Rs.7,51,600 (2% less than the base price)
F
Third Floor Rs. 7,44,000 (3% less than the base price)
Upon receipt of the respective allotment letters, the applicants, including
the respondent who opted to accept the allotments, furnished affidavits clearly
G stating that they would abide by all the terms and conditions of the allotment
and by the provisions of the Act and the rules framed thereunder from time
to time.
On 21.10 .1998 u"pon depositing 25% of the price of the flat as stipulated
in the allotment letter, the respondent took possession of the flat. On 12.5.1999
H the respondent filed complaint No. 486 of 1999 dated 12.5. 1999 before the
CHIEF ADMINISTRATOR PUDA v. SHABNAM VIRK [PASAYAT, J.]225
District Consumer Disputes Redressal Forum, Chandigarh (in short 'the District A
Forum') claiming, inter alia, that he was not liable to pay any amount over
and above the price which was advertised while inviting applications for
allotment much prior to the construction of the houses. The District Forum
by order dated 17 .10.200 I held that the price quoted was purely tentative and
it was likely to be revised on the higher side by the time the houses are
completed as there was clear condition to that effect in the advertisement. B
However, it directed the appellants to pay interest at the rate of 12% on the
amount of Rs.1,03,000/- for a period of I year and 4 months on the ground
that houses were likely to be completed by April, 1997 but the possession
was handed over in August, 1998. Both the appellants and respondent preferred
separate appeals before the State Commission, Chandigarh. The said C
Commission dismissed the appeal filed by the appellants and allowed the
other appeal. The State Commission directed the appellant No. I Authority to
charge only the price which was advertised while inviting the application for
allotment and to pay interest at the rate of 12%. A revision petition was filed
before the National Commission under Section 2 l(b) of the Consumer
Protection Act, 1986 (in short the 'Consumer Act'). The Commission held D
that there was no delay on the part of the appellant No. I Authority in handing
over the possession. However it held that only the price which was advertised
while inviting application for allotment could be charged. The Review
Application filed was dismissed.
E
In support of the appeals, learned counsel for the appellant submitted
that the complaint was thoroughly misconceived as the allotment was made
on 21.8.1998 and the price indicate.d was Rs.7.44 lacs. Same was accepted
by letter dated 16. l 0.1998 and the terms of acceptance were contained in the
accompanying affidavit. It was clearly stated in the affidavit dated 16. l 0.1998
that the allotment of the MIG (Super) house was accepted and the deponent F
undertook to abide by all the terms and conditions of the allotment letter.
With reference to the undertakings learned counsel for the appellants submitted
that the order of the National Commission is clearly erroneous. The clause
which has been used to fasten liability on the appellants clearly stipulates that
the price quoted is purely tentative and is based on the present cost of G
construction and likely to be revised by the time the house was completed.
It was, therefore, submitted that the demand raised by the appellants was
justified and the National Commission did not appreciate the position correctly
and held that the respondent was liable to pay at the earlier rate.
Learned counsel for the respondent on the other hand submitted that H
t
226 SUPREME COURT REPORTS (2006] 3 S.C.R.
A price quoted could be changed only if there was escalation in the cost of
construction. As the details filed would go to show, there was no increase in
the cost of construction, rather there was decrease.
It is to be noted that the respondent herself had accepted in the
undertaking that she accepted the allotment of the house and undertook to
B abide by all the terms and conditions of the allotment letter. It is not in
dispute that in the allotment letter the figure as demanded has been reflected.
That being so the respondent was liable to pay the amount as stipulated in
the allotment letter.
As there is no dispute that the respondent had in fact filecj an affidavit
C clearly indicating that she undertook to abide by all the terms and conditions
of the allotment letter, the amount indicated in the allotment letter was the
amount in respect of the allotment of the house. We find nothing in the
quoted clause to show that the increase was possible only when there was an
increase in the cost of construction. The clause quoted above does not reflect
D any such intention of the parties.
Above being the position the National Commission was clearly in error
granting relief to the respondent. The appeals are allowed. No costs.
N.J. Appeals Allowed.
Search Indian case law
Ask in plain English, not just keywords. 25,000 AI words free, no card.