CHINTELS INDIA LTD.versusBHAYANA BUILDERS PVT. LTD.
- Citation
- 2021 INSC 76
- Decided
- 11 February 2021
- Disposal
- Appeal(s) allowed
- Bench
- R F NARIMAN
Holding
An order refusing to condone delay in filing a section 34 application is an appealable order under section 37(1)(c) of the Arbitration and Conciliation Act, 1996.
Summary
Chintels India Ltd. filed an application under section 34 of the Arbitration and Conciliation Act, 1996 to set aside an arbitral award, but the single judge of the Delhi High Court refused to condone the delay in filing the application and dismissed it. The appellant challenged that order by invoking section 37(1)(c) of the same Act, contending that a refusal to condone delay is an order "refusing to set aside" an award and therefore appealable. The Supreme Court examined the language of sections 34 and 37, held that the phrase "setting aside or refusing to set aside" must be read to include refusals based on the time‑bar under section 34(3), and noted that section 37(1)(c) is pari materia with section 39(1)(vi) of the 1940 Act. Relying on earlier decisions such as Essar Constructions, Chief Engineer of BPDP and Fuerst Day Lawson, the Court rejected the argument that the right of appeal is limited to merits. Consequently, the Court allowed the appeal, set aside the High Court’s order and remitted the matter to a Division Bench to decide the condonation issue.
Issues considered
- Whether an order refusing to condone delay in filing a section 34 application falls within the ambit of 'setting aside or refusing to set aside an arbitral award' under section 37(1)(c) of the Arbitration and Conciliation Act, 1996.
- Whether section 37(1)(c) of the 1996 Act is pari materia with section 39(1)(vi) of the Arbitration Act, 1940 and thus covers such orders.
- Whether the limited right of appeal under section 37 can be expanded to include orders dealing with procedural delay.
Legislation cited
- Arbitration Act, 1940s. 39(1)(vi)
- Arbitration and Conciliation Act, 1996s. 16, s. 17, s. 34, s. 37, s. 5
- Commercial Courts Act, 2015s. 13
- Limitation Act, 1963s. 5
Subjects
Judgment
[2021] 1 S.C.R. 829 829
CHINTELS INDIA LTD. A
v.
BHAYANA BUILDERS PVT. LTD.
(Civil Appeal No. 4028 of 2020)
FEBRUARY 11, 2021 B
[R.F. NARIMAN, NAVIN SINHA AND K.M. JOSEPH, JJ.]
Arbitration and Conciliation, 1996 – s. 37(1)(c) and s.34 –
Whether order of the Single Judge of the High Court refusing to
condone the Appellant’s delay in filing an application u/s. 34 of the
C
Arbitration and Conciliation Act, 1996 is an appealable order u/s.
37(1)(c) of the said Act – Held: An appeal u/s. 37(1)(c) of the
Arbitration Act, 1996 would be maintainable against an order
refusing to condone delay in filing an application u/s. 34 of the
Arbitration Act, 1996 to set aside an award.
D
Arbitration and Conciliation, 1996 – s. 37(1)(c) – Arbitration
Act, 1940 – s.39(1)(vi) – Held: s. 39(1)(vi) of the 1940 Act is in pari
materia to s. 37(1)(c) of the Arbitration Act, 1996 – This was held in
two of the judgments of the Supreme Court i.e. Chief Engineer of
BPDP/REO Ranchi v. Scoot Wilson Kirpatrick India (P.) Ltd. (2006)
13 SCC 622:[2006] 8 Suppl. SCR 836 and Fuerst Day Lawson Ltd. E
v. Jindal Exports Ltd. (2011) 8 SCC 333: [2011] 11 SCR 1.
Allowing the appeal, the Court
HELD: Whether order of the Single Judge of the High
Court refusing to condone the Appellant’s delay in filing an
application u/s. 34 of the Arbitration and Conciliation Act, 1996 F
is an appealable order u/s. 37(1)(c) of the said Act ?
1. A reading of section 34(1) of the Arbitration and
Conciliation Act, 1996 would make it clear that an application
made to set aside an award has to be in accordance with both
sub-sections (2) and (3). This would mean that such application G
would not only have to be within the limitation period prescribed
by sub-section (3), but would then have to set out grounds under
sub-sections (2) and/or (2A) for setting aside such award. What
H
829
830 SUPREME COURT REPORTS [2021] 1 S.C.R.
A follows from this is that the application itself must be within time,
and if not within a period of three months, must be accompanied
with an application for condonation of delay, provided it is within
a further period of 30 days, this Court having made it clear that
section 5 of the Limitation Act, 1963 does not apply and that any
delay beyond 120 days cannot be condoned – State of Himachal
B
Pradesh v. Himachal Techno Engineers and Anr. (2010) 12 SCC
210 at paragraph 5. [Para 8][839-G-H; 840-A-B]
2. Now coming to section 37(1)(c) of the 1996 Act. It is
important to note that the expression “setting aside or refusing
to set aside an arbitral award” does not stand by itself. The
C expression has to be read with the expression that follows -
“under section 34”. Section 34 is not limited to grounds being
made out under section 34(2). Obviously, therefore, a literal
reading of the provision would show that a refusal to set aside an
arbitral award as delay has not been condoned under sub-section
D (3) of section 34 would certainly fall within section 37(1)(c). The
aforesaid reasoning is strengthened by the fact that under section
37(2)(a), an appeal lies when a plea referred to in sub-section (2)
or (3) of section 16 is accepted. This would show that the
Legislature, when it wished to refer to part of a section, as
opposed to the entire section, did so. Contrasted with the
E language of section 37(1)(c), where the expression “under section
34” refers to the entire section and not to section 34(2) only, the
fact that an arbitral award can be refused to be set aside for refusal
to condone delay under section 34(3) gets further strengthened.
[Para 9][840-B-E]
F 3. In Essar Constructions, a judgment rendered under
section 39 of the Arbitration Act, 1940 this Court was faced with
the same question as is raised in this appeal. In Essar
Constructions it was held that “the order refusing to condone
the delay in filing the claim petition has the effect of finally
G disposing of the original petition. Such an order can, therefore,
be treated as an award and hence it is appealable”. [Paras 10 and
12][840-E-F; 841-G-H; 842-A]
4. It will be noticed that so far as the present question is
involved, section 39(1)(vi) of the 1940 Act is in pari materia to
H section 37(1)(c) of the Arbitration Act, 1996. This was held in
CHINTELS INDIA LTD. v. BHAYANA BUILDERS PVT. LTD. 831
two of the judgments of the Supreme Court i.e. Chief Engineer A
of BPDP/REO Ranchi v. Scoot Wilson Kirpatrick India (P.) Ltd.
and Fuerst Day Lawson Ltd. v. Jindal Exports Ltd. [Para 14]
[843-C-D]
5. The reasoning in Essar Constructions commends itself
to this Court, being on a pari materia provision to that contained B
in section 37(1)(c) of the Arbitration Act, 1996. This Court may
only add that the reasoning of the aforesaid judgment is further
strengthened by analysis of the additional words “under section
34” which occur in section 37(1)(c), and which are absent in section
39(1)(vi) [the pari materia provision to section 34 of the
Arbitration Act, 1996 being section 30 of the Arbitration Act, C
1940]. [Para 19][846-C-E]
6. The counsel for the respondent has relied on section 5
of the Arbitration Act, 1996. According to respondent, in
furtherance of this object, section 37 was enacted giving a limited
right of appeal. He argued that an appeal, being a creature of D
statute should not, therefore, be enlarged beyond what is
provided by the Legislature. This section does not take
respondent’s argument much further, as after the non-obstante
clause, the section states that no judicial authority shall intervene
“except where so provided in this Part”. What is “provided in E
this part” is section 37, which therefore brings us back to square
one. Undoubtedly, a limited right of appeal is given under section
37 of the Arbitration Act, 1996. But it is not the province or duty
of this Court to further limit such right by excluding appeals which
are in fact provided for, given the language of the provision as
interpreted by us hereinabove. Thus, this last argument also has F
no legs on which to stand. [Paras 35 and 36][856-G-H]
7. Consequently, the question of law is answered by stating
that an appeal under section 37(1)(c) of the Arbitration Act, 1996
would be maintainable against an order refusing to condone delay
in filing an application under section 34 of the Arbitration Act, G
1996 to set aside an award. [Para 37][857-B-D]
Essar Constructions v. N.P. Rama Krishna Reddy (2000)
6 SCC 94 : [2000] 3 SCR 923; Chief Engineer of
BPDP/REO Ranchi v. Scoot Wilson Kirpatrick India (P.)
Ltd. (2006) 13 SCC 622 : [2006] 8 Suppl. SCR 836; H
832 SUPREME COURT REPORTS [2021] 1 S.C.R.
A Fuerst Day Lawson Ltd. v. Jindal Exports Ltd. (2011) 8
SCC 333 : [2011] 11 SCR 1; Union of India v. Manager,
Jain and Associates (2001) 3 SCC 277 : [2001] 1 SCR
889; Amar Nath Om Prakash v. State of Punjab (1985)
1 SCC 345 : [1985] 2 SCR 72 – relied on.
B State of Maharashtra and Anr. v. M/s Ramdas
Construction Co. and Anr. 2006 (6) Mah. L.J. 678;
Union of India v. Radha Krishna Seth and Anr. 2005
SCC OnLine All 8400 – overruled.
BGS SGS Soma JV. v. NHPC Limited (2020) 4 SCC 234
C – distinguished.
Union of India v. Simplex Infrastructures Ltd. (2017)
14 SCC 225 – held inapplicable.
Harmanprit Singh Sidhu v. Arcadia Shares and Stock
Brokers Pvt. Ltd. 2016 SCC OnLine Del 5383; State
D of Himachal Pradesh v. Himachal Techno Engineers
and Anr. (2010) 12 SCC 210 – referred to.
Case Law Reference
[2000] 3 SCR 923 relied on Para 3
E [2006] 8 Suppl. SCR 836 relied on Para 3
[2011] 11 SCR 1 relied on Para 13
(2020) 4 SCC 234 distinguished Para 3
(2017) 14 SCC 225 held inapplicable Para 4
F (2010) 12 SCC 210 referred to Para 8
[2001] 1 SCR 889 relied on Para 15
[1985] 2 SCR 72 relied on Para 28
CIVIL APPELLATE JURISDICTION : Civil Appeal
G No. 4028 of 2020.
From the Judgment and Order dated 04.12.2020 of the High Court
of Delhi at New Delhi in FAO(OS)(Comm) No. 68 of 2020.
Mukul Rohtagi, Sr. Adv., Rajshekhar Rao, Arshdeep Singh, Kotla
Harshavardhan, Ms. Neeha Nagpal, Areeb Amanullah, Karthik Sundar,
H
CHINTELS INDIA LTD. v. BHAYANA BUILDERS PVT. LTD. 833
Ms. Mansi Sood, Ms. Vishakha Gupta, Shreedhar Kale, Udbhav Nanda, A
Malak Manish Bhatt, Saurabh Kirpal, Gaurav Mitra, Ms. Meghna Mishra,
Debmalya Banerjee, Ms. Manmeet Kaur, Rohan Sharma, Kartik
Bhatnagar, Yashvardhan Bandi, Ujjwal Singh, Vardaan Wanchoo, Ms.
Anjali Dwivedi for M/S. Karanjawala & Co., Advs. for the appearing
parties.
B
The Judgment of the Court was delivered by
R. F. NARIMAN, J.
1. This appeal arises out of a certificate issued under Article 133
read with Article 134A of the Constitution of India by the High Court of
Delhi in the impugned judgment dated 04.12.2020. The question raised C
in this appeal is whether a learned single Judge’s order refusing to
condone the Appellant’s delay in filing an application under section 34 of
the Arbitration and Conciliation Act, 1996 (“Arbitration Act, 1996”) is
an appealable order under section 37(1)(c) of the said Act. After
considering, in particular, two judgments of this Court, the High Court D
held:
“18. We have considered the rival contentions. Though, as observed
by us in the hearing on 5th November, 2020, in view of BGS SGS
Soma JV supra having referred to the grounds under Section 34
in entirety and not confined to Section 34(2) only, we were inclined E
to differentiate between a case of return of an application under
Section 34 on the ground of the Court to which it is presented not
having territorial jurisdiction, on the one hand and rejection of an
application under Section 34 on the ground of having not been
filed within the prescribed time, on the other hand, but in view of
the Supreme Court having been approached against Ramdas F
Construction Co. supra, expressly holding an appeal as the one
before us, to be not maintainable under Section 37, and having
dismissed the appeal with a speaking order, though not expressing
any opinion on the maintainability of the appeal, we consider
ourselves bound thereby and hold this appeal to be not G
maintainable.
19. We may however observe that Section 37(1)(b) also, while
providing for the appealable orders, refers to Section 34 in entirety
and not to Section 34(2); though BGS SGS Soma JV supra has
held that the order which is appealable thereunder is an order
H
834 SUPREME COURT REPORTS [2021] 1 S.C.R.
A testing the arbitral award on the grounds set out in Section 34 but
in our humble opinion if the intention of the legislature was to
confine the appeals only to grounds under Section 34(2), nothing
prevented them from, instead of referring to Section 34 generally
in Section 37(1)(c), referring only to Section 34(2). We are of the
view that sub-section (3) of Section 34, by use of the words ‘but
B
not thereafter’, as interpreted in Union of India Vs. Popular
Construction Co. (2001) 8 SCC 470, restricts the power otherwise
vested in Court to condone the delay beyond thirty days, the same
also creates a ground of time bar for refusing to set aside the
award and is part of the self-contained code for setting aside of
C the award; thus, refusal to set aside an award on the ground of
the said time bar, would be a refusal within the meaning of Section
37 and appealable under Section 37. There is also merit in the
contention of Mr. Rajshekhar Rao, Advocate for the appellant
that refusal to condone the delay also entails affirmation of the
underlying order. Mention in this regard may be made of Section
D
27 of the Limitation Act, 1963 which, though in the context of suit
for possession of any property, extinguishes the right to property
at the determination of the period prescribed for instituting the
suit for possession thereof. However we need not discuss further
since, as aforesaid, we are bound by the dicta in BGS SGS Soma
E JV and Ramdas Construction Co. supra.
20. We may also consider another aspect. By reading Section 37
as not permitting an appeal against refusal to condone the delay in
applying for setting aside of the award, the persons aggrieved by
the award are left with no remedy but to approach the Supreme
F Court by way of a petition under Article 136 of the Constitution of
India. The refusal to set aside the award may not necessarily be
by the Commercial Division of the High Court but may also be by
the Commercial Courts of the country. No other remedy would
be available to the persons aggrieved by the award, against the
decision of any Commercial Court in the country refusing to
G condone the delay in applying for setting aside of the award, leaving
such persons either with the option of accepting / remaining bound
by the award even if having excellent grounds for setting aside of
the same or of approaching the Supreme Court under Article 136
of the Constitution of India, thereby putting an avoidable burden
H on the Supreme Court which, as per the scheme of the Constitution
CHINTELS INDIA LTD. v. BHAYANA BUILDERS PVT. LTD. 835
[R.F. NARIMAN, J.]
of India, was envisaged to hear limited number of matters entailing A
constitutional issues and not to hear matters of condonation of
delay. Though undoubtedly the scheme of expediency and limited
judicial intervention is ingrained in the Arbitration Act but at the
same time it cannot be forgotten that the Act nevertheless provides
remedies against the arbitral award and it is felt that to vest the
B
order, of any Commercial Court in the country refusing to condone
the delay in applying for setting aside of the award, and which
delay can be for varying reasons as diverse as the social,
geographical and economic conditions prevalent in this country,
and not even providing any opportunity to the High Courts to have
a look therein, would be a very harsh outcome. C
21. Thus, while dismissing the appeal as not maintainable, being
bound by the dicta of the Supreme Court in BGS SGS Soma JV
and in Ramdas Construction Co. supra, we grant certificate under
Article 133 read with Article 134A of the Constitution of India to
the appellant.” D
2. It may be noted that the learned single Judge of the High Court
dismissed the application for condonation of delay in an application filed
under section 34 of the Arbitration Act, 1996 to set aside an award
dated03.05.2019vide its judgment dated 04.06.2020, and consequently
dismissed the section 34 application itself. E
3. Shri Rajshekhar Rao, learned Advocate appearing on behalf of
the Appellant, has relied strongly upon the judgment of this Court in
Essar Constructions v. N.P. Rama Krishna Reddy (2000) 6 SCC
94, which was a judgment delivered under section 39 of the Arbitration
Act, 1940. His argument is that since section 39 of the 1940 Act is in F
parimateria with section 37 of the Arbitration Act, 1996, in that an appeal
lies where a single Judge refuses to condone delay, resulting in an order
refusing to set aside an arbitral award, the ratio ofEssar Constructions
(supra) would apply on all fours to the same provision contained in section
37. This being so, he argued that it is clear that refusal to condone delay
would result in a refusal to set aside an award, an appeal against such G
order being maintainable under section 37 of the Arbitration Act, 1996.
He also strongly relied upon the judgments of this Court in Chief
Engineer of BPDP/REO Ranchi v. Scoot Wilson Kirpatrick India
(P.) Ltd. (2006) 13 SCC 622 and Fuerst Day Lawson Ltd. v. Jindal
Exports Ltd. (2011) 8 SCC 333 to buttress his submission that section H
836 SUPREME COURT REPORTS [2021] 1 S.C.R.
A 39 of the 1940 Act was aparimateria provision to section 37 of the
Arbitration Act, 1996. He then relied upon judgmentsof the Madhya
Pradesh1, Bombay2, Karnataka3, Delhi4 and Calcutta5 High Courts to
argue that an order refusing to condone delay stands on a completely
different footing from an order which condones delay, as the latter order
cannot be said to impart any finality to the proceeding, as, when an order
B
condones delay, it cannot be said that the court has refused to set aside
an award as it may ultimately set aside the aforesaid award on the grounds
mentioned in section 34(2) of the Arbitration Act, 1996. He further argued
that the judgment of the Allahabad High Court in Union of India v.
Radha Krishna Seth and Anr., 2005 SCC OnLine All 8400 and that of
C the Bombay High Court in State of Maharashtra v. Ramdas
Construction Co. 2006 (6)Mah. L.J. 678 did not state the law correctly
and ought to be overruled by this Court. He argued that where a right of
appeal is granted by statute, a dismissal on a preliminary ground is
nevertheless a dismissal of the appeal, since it cannot be heard thereafter.
He also argued that a right of appeal, once granted, ought not to be
D
limited by statutory interpretation where the words used are capable of
a wider construction. In particular, referring to the language of section
37(1)(c) of the Arbitration Act, 1996, he argued that there must be refusal
to set aside an arbitral award “under section 34”, which includes section
34(3), under which a court may refuse to condone delay in filing an
E application under section 34. Coming to the two Supreme Court judgments
referred to in the impugnedjudgment, it was his contention that the focus
of thisCourt in BGS SGS Soma JV. v. NHPC Limited(2020) 4 SCC
234, was on a completely different question, namely, as to whether an
application to set aside an award under section 34 should be returned to
the proper court dependent upon where the seat of arbitration was located.
F
1
Bisleri International Pvt. Ltd. and Ors. v. Sun Petpack Jabalpur Pvt. Ltd. and Anr.
2009 (4) M.P.L.J. 514.
2
E-Square Leisure Pvt. Ltd., Pune v. K.K. Dani Consultants and Engineers Pvt. Ltd.
2013 (3) Mh.L.J. 24;
Jayshri Ginning & Spinning Pvt. Ltd. v. C.A. Galiakotwala & Company Pvt. Ltd. 2016
G SCC OnLine Bom 5067.
3
M/s Crompton Greaves Ltd. v. M/s Annapurna Electronics and Ors. ILR 2015 KAR
4199.
4
Harmanprit Singh Sidhu v. Arcadia Shares & Stock Brokers Pvt. Ltd. (2016) 234 DLT
30.
5
Damodar Valley Corporation v. Sanjay Singh Rathor 2018 SCC OnLine Cal 4014.
H
CHINTELS INDIA LTD. v. BHAYANA BUILDERS PVT. LTD. 837
[R.F. NARIMAN, J.]
It was only in the course of discussion relatable to this question that this A
Court approved certain observations made in the decision of the Delhi
High Court inHarmanprit Singh Sidhu v. Arcadia Shares and Stock
Brokers Pvt. Ltd. 2016 SCC OnLine Del 5383, in which a learned
single Judge of the Delhi High Court allowed an application for
condonation of delay,a Division Bench then holding that an appeal against
B
such an order was not maintainable under section 37 of the Arbitration
Act, 1996. He contended that it is only in this context that paragraph 17
of BGS SGS Soma (supra) approved of the observations made
inHarmanprit Singh Sidhu (supra), inasmuch as it cannot be said that
the Court has refused to set aside the award under section 34, as it may
yet do so if any of the grounds contained in section 34(2) are made out. C
So far as this Court’s order dated 12.04.2017 in State of Maharashtra
and Anr. v. M/s Ramdas Construction Co. and Anr. [C.A. Nos.
5247-5248 of 2007]is concerned, he argued that this Court did not go
into the maintainability aspect at all, but ultimately dismissed the Civil
Appeals on the ground that the District Judge, Nagpur had held that the
D
period of delay being beyond four months, the court had no jurisdiction
to entertain the application for condonation of delay or the application on
merits under section 34 of the Arbitration Act, 1996.
4. Shri Mukul Rohatgi, learned Senior Advocate appearing on
behalf of the Respondent, strongly refuted the fact that section 37 of the
Arbitration Act, 1996 is in parimateria with section 39 of the 1940 Act. E
According to him,section 39 of the 1940 Act is materially different, and
concerns itself with grounds that were made out under section 30 of the
said Act, which grounds were completely different from the grounds
that could be made out under section 34(2) and (2A) of the 1996 Act.
Therefore, Shri Rohatgi argued that section 37 needs to be interpreted F
on its own terms, and that consequently, this Court’s judgment in Essar
Constructions (supra) would not be applicable. He relied strongly upon
section 5 of the Arbitration Act, 1996, by which it was statutorily made
clear that judicial intervention is to be minimal in the arbitration process.For
this purpose he also relied upon the Statement ofObjects and Reasons
for enacting the Arbitration Act, 1996. He then went on to state that G
section 37 of the Arbitration Act, 1996 in fact carries out this object.He
stressed that this object was reinforced first, by the non-obstante clause
contained in section 37(1); andsecond, by the fact that the grounds of
appeal contained in section 37 are exhaustive, and makes explicit that an
appeal shall lie only from the following orders “and from no others”. He H
838 SUPREME COURT REPORTS [2021] 1 S.C.R.
A also stressed the fact that the word “namely” makes it clear that it is
only from the orders set out in section 37 that an appeal can be filed. He
went on to argue that an appeal, being a creature of statute, has to be
read as the statute provides without expanding any of the words
used.According to him, section 37(1)(c) is clear and without any
ambiguity – the expression “under Section 34” has to be read with the
B
preceding words “setting aside or refusing to set aside an arbitral award”,
and when so read, it is clear that the refusal to set aside the award can
only be on merits and not on some preliminary ground which would then
lead to a refusal to set aside the award. He relied strongly upon the fact
that this Court in BGSSGS Soma (supra) had approved of Harmanprit
C Singh Sidhu (supra), and stated exactly this in paragraph 17 thereof.He
then strongly relied upon the judgment in Union of India v. Simplex
Infrastructures Ltd. (2017) 14 SCC 225 for the proposition that whether
delay is or is not condoned, the same result ensues – it cannot be said
that by condoning or refusing to condone delay, an arbitral award either
gets or does not get set aside. He ended by saying that in point of fact
D
the Bombay High Court Division Bench judgment in Ramdas
Construction Co. (supra) was the correct enunciation of the law, and
that we should accept this enunciation and overrule the judgments of the
other High Courts.
5. Having heard learned counsel for the parties, it is important to
E first set out section 37 of the Arbitration Act, 1996 which is as
follows:
“37. Appealable orders.—(1) Notwithstanding anything
contained in any other law for the time being in force, an appeal
shall lie from the following orders (and from no others) to the
F Court authorised by law to hear appeals from original decrees of
the Court passing the order, namely:—
(a) refusing to refer the parties to arbitration under section 8;
(b) granting or refusing to grant any measure under section 9;
G (c) setting aside or refusing to set aside an arbitral award under
section 34.
(2) Appeal shall also lie to a court from an order of the arbitral
tribunal—
H
CHINTELS INDIA LTD. v. BHAYANA BUILDERS PVT. LTD. 839
[R.F. NARIMAN, J.]
(a) accepting the plea referred to in sub-section (2) or sub-section A
(3) of section 16; or
(b) granting or refusing to grant an interim measure under section
17.
(3) No second appeal shall lie from an order passed in appeal B
under this section, but nothing in this section shall affect or
takeaway any right to appeal to the Supreme Court.”
6. Since we are directly concerned with section37(1)(c), it is
important to advert to the language of section 34 as well. Section 34(1)
reads as follows: C
“34. Application for setting aside arbitral award.— (1)
Recourse to a Court against an arbitral award may be made only
by an application for setting aside such award in accordance with
sub-section (2) and sub-section (3).”
7. Section 34(2) and (2A) then sets out the grounds on which an D
arbitral award may be set aside. Section 34(3), which again is material
for decision of the question raised in this appeal, reads as follows:
“(3) An application for setting aside may not be made after three
months have elapsed from the date on which the party making
that application had received the arbitral award or, if a request E
had been made under section 33, from the date on which that
request had been disposed of by the arbitral tribunal:
Provided that if the Court is satisfied that the applicant was
prevented by sufficient cause from making the application within
the said period of three months it may entertain the application F
within a further period of thirty days, but not thereafter.”
8. A reading of section 34(1) would make it clear that an application
made to set aside an award has to be in accordance with both sub-
sections (2) and (3). This would mean that such application would not
only have to be within the limitation period prescribed by sub-section(3), G
but would then have to set out grounds under sub-sections (2) and/or
(2A) for setting aside such award. What follows from this is that the
application itself must be within time, and if not within a period of three
months, must be accompanied with an application for condonation of
H
840 SUPREME COURT REPORTS [2021] 1 S.C.R.
A delay, provided it is within a further period of 30 days, this Court having
made it clear that section 5 of the Limitation Act, 1963 does not apply
and that any delay beyond 120 days cannot be condoned – see State of
Himachal Pradesh v. Himachal Techno Engineers and Anr. (2010)
12 SCC 210 at paragraph 5.
B 9. We now come to section 37(1)(c). It is important to note that
the expression “setting aside or refusing to set aside an arbitral award”
does not stand by itself. The expression has to be read with the expression
that follows -”under section 34". Section 34 is not limited to grounds
being made out under section 34(2). Obviously, therefore, a literal reading
of the provision would show that a refusal to set aside an arbitral award
C as delay has not been condoned under sub-section (3) ofsection 34 would
certainly fall within section 37(1)(c).The aforesaid reasoning is
strengthened by the fact that under section 37(2)(a), an appeal lies when
a plea referred to in sub-section (2) or (3) of section 16 is accepted. This
would show that the Legislature, when it wished to refer to part of
D asection, as opposed to the entire section, did so. Contrasted with the
language of section 37(1)(c), where the expression “under section 34”
refers to the entire section and not to section 34(2) only, the fact that an
arbitral award can be refused to be set aside for refusal to condone
delay under section 34(3) gets further strengthened.
E 10. In Essar Constructions (supra), a judgment rendered under
section 39 of the 1940 Act, this Court was faced with the same question
as is raised in the appeal before us. In order to appreciate the ratio of
this judgment, it is necessary to first set out section 39 of 1940 Act,
which reads as under:
F “39. Appealable orders:- (1) An appeal shall lie from the
following orders passed under this Act (and from no others) to
the Court authorised by law to hear appeals from original decrees
of the Court passing the order:
An order –
G (i) superseding an arbitration;
(ii) on an award stated in the form of a special case;
(iii) modifying or correcting an award;
(iv) filing or refusing to file an arbitration agreement;
H
CHINTELS INDIA LTD. v. BHAYANA BUILDERS PVT. LTD. 841
[R.F. NARIMAN, J.]
(v) staying or refusing to stay legal proceedings where there is an A
arbitration agreement;
(vi) setting aside or refusing to set aside an award;
Provided that the provisions of this section shall not apply to any
order passed by a Small Cause Court.
B
(2) No second appeal shall lie from an order passed in appeal
under this section, but nothing in this section shall affect or take
away any right to appeal to the Supreme Court.”
11. The question which the Court was required to answer was set
out as follows: C
“5. But was the Civil Judge’s order dismissing the respondent’s
application under Section 5 at all revisable under Section 115 of
the Code or did an appeal lie from it under Section 39 of the
Arbitration Act, 1940? The answer is of moment as the powers
of an appellate court are wider than those available under Section D
115. Section 39(1)(vi) of the Arbitration Act, 1940 says that an
appeal shall lie inter alia from an order “refusing to set aside an
award”.
6. To arrive at a conclusion as to whether the order passed by the
Senior Civil Judge, Kakinada was an order “refusing to set aside
E
the award”, we have to consider the facts.”
12. After setting out the order of the Senior Civil Judge, who
refused to condone delay in filing an application for setting aside the
award, the Court then held:
“11. The outcome of the order in effect wasthat the prayer for F
setting aside the award was refused on the ground of delay.
12. The “effect test” was applied by the High Court of Andhra
Pradesh in Babumiyan&Mastan v. K. Seethayamma [AIR 1985
AP 135] which said:
“In the light of the rulings in G. Gopalaswami v. G. G
Navalgaria [AIR 1967 Mad 403] and the decision of the Bench
in CMA No. 612 of 1977 dated 3-4-1978, the legal position may
be enunciated as follows: The order refusing to condone the delay
in filing the claim petition has the effect of finally disposing of the
H
842 SUPREME COURT REPORTS [2021] 1 S.C.R.
A original petition. Such an order can, therefore, be treated as an
award and hence it is appealable.”
13. Again a Division Bench of the Assam High Court
in MafizuddinBhuyan v. AlimuddinBhuyan [AIR 1950 Ass 191]
has said:
B “Whether objections to an award are dismissed on the merits or
they are dismissed on the ground that they are filed beyond time,
the Court by dismissing them in effect refuses to set aside the
award, and an order refusing to set aside an award is clearly
appealable under Section 39.”
C 14. In some High Courts, no separate application is filed under
Section 5 of the Limitation Act and the prayer for condonation of delay
is included along with the prayers made for substantive relief. Courts
have entertained appeals from an order dismissing an application on
the ground of limitation. Thus, in State of W.B. v. A. Mondal [AIR
D 1985 Cal 12 (DB)] where an application under Section 30 of the
Arbitration Act was dismissed on the ground of limitation, an appeal
was entertained.(See also Damodaran v. Bhaskaran [(1988) 2 KLT
753].)
15. The procedure appears to have been approved by the Supreme
E Court in the case of Union of India v. Union Builders [AIR
1985 Cal 337 (DB)] where on an appeal to the Supreme Court
from an order dismissing an application under Section 30 on the
ground of delay, the appeal was remanded to the High Court to be
disposed of.
F 16. The position should be no different in courts where a separate
application under Section 5 of the Limitation Act is required to be
filed. If the various High Courts’ decisions noted earlier are correct,
then the application under Section 5 being dismissed, the application
under Section 30 would consequently also have to be dismissed
although this might be a mere formality. The end result would be
G the same.
xxx xxx xxx
21. Section 39(1)(vi) of the Arbitration Act, 1940 does not indicate
the grounds on which the court may refuse to set aside the award.
There is nothing in its language to exclude a refusal to set aside
H
CHINTELS INDIA LTD. v. BHAYANA BUILDERS PVT. LTD. 843
[R.F. NARIMAN, J.]
the award because the application to set aside the award is barred A
by limitation. By dismissing the application albeit under Section 5,
the assailability of the award is concluded as far as the court
rejecting the application is concerned. Ultimately therefore, it is
an order passed under Section 30 of the Arbitration Act though by
applying the provisions of the Limitation Act.”
B
13. The Court ultimately concluded:
“25. Reading Section 39(1)(vi) and Section 17 together, it would
therefore follow that an application to set aside an award which is
rejected on the ground that it is delayed and that no sufficient
cause has been made out under Section 5 of the Limitation Act C
would be an appealable order.”
14. It will be noticed that so far as the present question is involved,
section 39(1)(vi) of the 1940 Act is inparimateria to section 37(1)(c) of
the Arbitration Act, 1996. This was in fact held in two of the judgments
of this Court. In Chief Engineer of BPDP/REO Ranchi (supra), this D
Court when considering a similar question held as follows:
“5. Section 37(1)(b) of the Act is in parimateria with Section
39(1)(vi) of the Arbitration Act, 1940 (in short “the old Act”). The
provisions in the Acts read as follows:
1996 Act E
“37. (1) An appeal shall lie from the following orders (and from
no others) to the court authorised by law to hear appeals from
original decrees of the court passing the order, namely—
***
F
(b) setting aside or refusing to set aside an arbitral award under
Section 34.”
1940 Act
“39. Appealable orders.—(1) An appeal shall lie from the
following orders passed under this Act (and from no others) to G
the court authorised by law to hear appeals from original decrees
of the court passing the order:
An order—
***
H
844 SUPREME COURT REPORTS [2021] 1 S.C.R.
A (vi) setting aside or refusing to set aside an award:”
15. Having so held, this Court then referred to and followed the
judgment in Essar Constructions (supra) and the judgment contained
in Union of India v.Manager, Jain and Associates(2001) 3 SCC
277, ultimately holding:
B “8. The decision in Popular Construction case [(2001) 8 SCC
470] did not deal with specific issues in this case. In that decision
it was held that in respect of “sufficient cause cases” the provisions
of Section 34(3) of the Act which are special provisions relating
to condonation of delay override the general provisions of Section
C 5 of the Limitation Act, 1963 (in short “the Limitation Act”). The
position was reiterated in the Western Builders case [(2006) 6
SCC 239] and also in Fairgrowth Investments
Ltd. v. Custodian [(2004) 11 SCC 472] . There can be no quarrel
with the proposition that Section 5 of the Limitation Act providing
for condonation of delay is excluded by Section 34(3) of the Act.
D
9. But the question in the instant case is not about the applicability
of Section 5 of the Limitation Act, and the question really is
whether the appeal was maintainable. The High Court did not
consider this aspect. The appeal is clearly maintainable. Therefore,
the order of the High Court is set aside. The High Court shall deal
E with the matter and examine the respective stand on merits treating
the appeal to be maintainable.”
16. Likewise, in Fuerst Day Lawson Ltd. (supra)this Court held:
“37. These general principles are culled out from the decisions of
F this Court rendered under Section 104 CPC and various other
Acts, as noted above. But there is another set of decisions of this
Court on the question under consideration rendered in the context
of Section 39 of the 1940 Act. Section 39 of the erstwhile Act
contained the provision of appeal and provided as follows:
“39.Appealable orders.—(1) An appeal shall lie from the following
G
orders passed under this Act (and from no others) to the court
authorised by law to hear appeals from original decree of the
court passing the orders:
An order—
H
CHINTELS INDIA LTD. v. BHAYANA BUILDERS PVT. LTD. 845
[R.F. NARIMAN, J.]
(i) superseding an arbitration; A
(ii) on an award stated in the form of a special case;
(iii) modifying or correcting an award;
(iv) filing or refusing to file an arbitration agreement;
(v) staying or refusing to stay legal proceedings where there B
isan arbitration agreement;
(vi) setting aside or refusing to set aside an award:
Provided that the provisions of this section shall not apply to any
order passed by a Small Cause Court.
C
(2) No second appeal shall lie from an order passed in appeal
under this section, but nothing in this section shall affect or take
away any right to appeal to the Supreme Court.”
(Insofar as relevant for the present, Section 37 of the 1996 Act, is
very similar to Section 39 of the previous Act as quoted above.)” D
17. It then referred to an argument of counsel that there would be
no material difference between the provisions of section 39 of Arbitration
Act, 1940 and section 37 of the Arbitration Act, 1996 vis-à-vis section
50 of the 1996 Act, as follows:
“43. Mr Dave, in reply submitted that the words “(and from no E
others)” occurring in Section 39 of the 1940 Act and Section 37
of the 1996 Act were actually superfluous and seen, thus, there
would be no material difference between the provisions of Section
39 of the 1940 Act or Section 37 of the 1996 Act and Section 50
of the 1996 Act and all the decisions rendered on Section 39 of F
the 1940 Act will apply with full force to cases arising under Section
50 of the 1996 Act.”
18. So far as section 37 of the Arbitration Act, 1996 and section
39 of the Arbitration Act, 1940 were concerned, this Court agreed with
counsel’s argument, but disagreed with the submission insofar as section G
50 of the 1996 Act was concerned, as follows:
“52. Having regard to the grammatical use of brackets or
parentheses, if the words “(and from no others)” occurring in
Section 39 of the 1940 Act or Section 37 of the 1996 Act are
viewed as “an explanation or afterthought” or extra information
H
846 SUPREME COURT REPORTS [2021] 1 S.C.R.
A separate from the main context, then, there may be some substance
in Mr Dave’s submission that the words in parenthesis are
surplusage and in essence the provisions of Section 39 of the
1940 Act or Section 37 of the 1996 Act are the same as Section
50 of the 1996 Act. Section 39 of the 1940 Act says no more and
no less than what is stipulated in Section 50 of the 1996 Act. But
B
there may be a different reason to contend that Section 39 of the
1940 Act or its equivalent Section 37 of the 1996 Act are
fundamentally different from Section 50 of the 1996 Act and hence,
the decisions rendered under Section 39 of the 1940 Act may not
have any application to the facts arising under Section 50 of the
C 1996 Act. But for that we need to take a look at the basic scheme
of the 1996 Act and its relevant provisions.”
19. The reasoning in Essar Constructions (supra) commends
itself to us, being on a parimateria provision to that contained in section
37(1)(c) of the Arbitration Act, 1996. We may only add that the reasoning
D of the aforesaid judgment is further strengthened by our analysis of the
additional words “under section 34” which occur in section 37(1)(c),
and which are absent in section 39(1)(vi) [the pari858
materia provision to section 34 of the Arbitration Act, 1996 being
section 30 of the Arbitration Act, 1940].
E 20. In point of fact, the “effect doctrine” referred to in Essar
Constructions (supra) is statutorily inbuilt in section 37 of the Arbitration
Act, 1996 itself.For this purpose, it is necessary to refer to sections
37(1)(a) and 37(2)(a).So far as section 37(1)(a) is concerned, where a
party is referred to arbitration under section 8, no appeal lies. This is for
F the reason that the effect of such order is that the parties must go to
arbitration, it being left to the learned Arbitrator to decide preliminary
points under section 16 of the Act, which then become the subject matter
of appeal under section 37(2)(a) or the subject matter of grounds to set
aside under section 34 an arbitral award ultimately made, depending
upon whether the preliminary points are accepted or rejected by the
G arbitrator. It is also important to note that an order refusing to refer
parties to arbitration under section 8 may be made on a prima facie
finding that no valid arbitration agreement exists, or on the ground that
the original arbitration agreement, or a duly certified copy thereof is not
annexed to the application under section 8. In either case,i.e. whether
H the preliminary ground for moving the court under section 8 is not made
CHINTELS INDIA LTD. v. BHAYANA BUILDERS PVT. LTD. 847
[R.F. NARIMAN, J.]
out either by not annexing the original arbitration agreement, or a duly A
certified copy, or on merits – the court finding that prima facie no valid
agreement exists – an appeal lies under section 37(1)(a).
21. Likewise, under section 37(2)(a), where a preliminary ground
of the arbitrator not having the jurisdiction to continue with the
proceedings is made out, an appeal lies under thesaid provision, as such B
determination is final in nature as it brings the arbitral proceedings to an
end. However, if the converse is held by the learned arbitrator, then as
the proceedings before the arbitrator are then to carry on, and the
aforesaid decision on the preliminary ground is amenable to challenge
under section 34 after the award is made, no appeal is provided. This is
made clear by section 16(5) and (6) of the Arbitration Act, 1996 which C
read as follows:
“16. Competence of arbitral tribunal to rule on its
jurisdiction.—
xxx xxx xxx D
(5) The arbitral tribunal shall decide on a plea referred to in sub-
section (2) or sub-section (3) and, where the arbitral tribunal takes
a decision rejecting the plea, continue with the arbitral proceedings
and make an arbitral award.
(6) A party aggrieved by such an arbitral award may make an E
application for setting aside such an arbitral award in accordance
with section 34.”
22. Given the fact that the “effect doctrine” is part and parcel of
the statutory provision for appeal under section 37, and the express
language of section 37(1)(c), it is difficult to accede to the argument of F
Shri Rohatgi.
23. We now come to the judgment inSimplex Infrastructures
Ltd. (supra). In this judgment, what was argued before thisCourt is set
out with reference to the Division Bench judgment under appeal as follows:
“11. The Division Bench of the High Court, however, made a G
fine distinction by holding that the judgment of the learned Single
Judge of condoning delay in filing of the petition under Section 34
of the Act was without jurisdiction and not in terms of the provisions
of the Act. It is not possible to countenance this approach. The
Division Bench, in our opinion, was not right in observing that the H
848 SUPREME COURT REPORTS [2021] 1 S.C.R.
A decision in Tanusree Art Printers [Tanusree Art
Printers v. Rabindra Nath Pal, 2000 SCC OnLine Cal 217] being
of a Special Bench of three Judges of the same court, was binding,
in spite of having noticed the decision of this Court in Fuerst Day
Lawson Ltd. [Fuerst Day Lawson Ltd. v. Jindal Exports Ltd.,
(2011) 8 SCC 333] — which is directly on the point and was
B
pressed into service by the appellant. Neither the Division Bench
of the High Court of Calcutta which dealt with Modi Korea
Telecommunication Ltd. [Modi Korea Telecommunication
Ltd. v. Appcon Consultants (P) Ltd., 1999 SCC OnLine Cal 19]
nor the three-Judge Bench which decided Tanusree Art Printers,
C had the benefit of the judgment of this Court in Fuerst Day
Lawson Ltd., which is later in time.”
24. In stating that the Division Bench was wrong, as a judgment
of a single Judge condoning delay in the filing of a petition under section
34 cannot be said to be without jurisdiction, the Court then held:
D “12… On a bare reading of this provision, it is noticed that the
remedy of the appeal has been provided only against an order of
setting aside or refusing to set aside an arbitral award under Section
34. No appeal is provided against an order passed by the court of
competent jurisdiction condoning the delay in filing the petition
E under Section 34 of the Act as such. The Division Bench in the
impugned judgment, therefore, rightly noted that remedy of appeal
against the impugned order of the learned Single Judge was not
otherwise available under Section 37 of the Act.
13. In our opinion, the issue is squarely answered against the
F respondent by the decision of this Court in Fuerst Day Lawson
Ltd. [Fuerst Day Lawson Ltd. v. Jindal Exports Ltd., (2011) 8
SCC 333] In that, the judgment of the learned Single Judge dated
27-4-2016 [Union of India v. Simplex Infrastructures Ltd., 2016
SCC OnLine Cal 12045], was passed on an application purported
to be under Section 34(3) of the Act, for condoning delay in filing
G of the petition for setting aside the arbitral award. Hence, the
remedy of letters patent appeal against that decision is unavailable.
The question as to whether the learned Single Judge had rightly
exercised the discretion or otherwise, could be assailed by the
respondent before this Court by way of special leave petition.
H But, certainly not by way of a letters patent appeal under
CHINTELS INDIA LTD. v. BHAYANA BUILDERS PVT. LTD. 849
[R.F. NARIMAN, J.]
Clause 15. For, even if the learned Single Judge may have A
committed manifest error or wrongly decided the application for
condonation of delay, that judgment is ascribable to exercise of
jurisdiction under Section 34(3) of the Act. In other words, whether
the prayer for condonation of delay can be accepted or whether
the application deserves to be rejected, is a matter well within the
B
jurisdiction of that court.”
25. This judgment does not in any manner militate against what
has been held by us. In answer to the question as to whether a single
Judge’s judgment condoning delay in filing an application under section
34 was without jurisdiction, this Court correctly held that such an order
is in exercise of jurisdiction conferred by the statute.This judgment C
therefore cannot be said to be an authority for the proposition that, as
the converse position to the facts contained in the present appeal before
us has been held to be not appealable, it must follow that even where
delay is not condoned, the same position obtains. This would fly in the
face of the reasoning contained in this judgment, as well as the reasoning D
contained in Essar Constructions (supra), which has commended itself
to us.
26. We now come to this Court’s judgment in BGS SGS Soma
(supra).As correctly pointed out by Shri Rao, the question before this
Court in BGS SGS Soma (supra) was a completely different one, being E
set out in paragraph 1 of the judgment as follows:
“1. Leave granted. Three appeals before us raise questions as to
maintainability of appeals under Section 37 of the Arbitration and
Conciliation Act, 1996 (hereinafter referred to as “the Arbitration
Act, 1996”), and, given the arbitration clause in these proceedings, F
whether the “seat” of the arbitration proceedings is New Delhi or
Faridabad, consequent upon which a petition under Section 34 of
the Arbitration Act, 1996 may be filed dependent on where the
seat of arbitration is located.”
27. In answering this question, the Court first went into the interplay G
between section 37 of the Arbitration Act, 1996 and section 13 of the
Commercial Courts Act, 2015, holding that section 37 of the Arbitration
Act alone provides grounds for appeal, section 13(1) of the Commercial
Courts Act providing the procedure thereof. In the course of discussion,
this Court then referred to a judgment of the Delhi High Court as follows:
H
850 SUPREME COURT REPORTS [2021] 1 S.C.R.
A “16. Shri Chowdhury also referred to another Delhi High Court
judgment reported as Harmanprit Singh Sidhu v. Arcadia
Shares & Stock Brokers (P) Ltd. [(2016) 234 DLT 30], in which
a learned Single Judge of the Delhi High Court allowed an
application for condonation of delay in filing a Section 34 petition.
The Division Bench, in holding that an appeal against such an
B
order would not be maintainable under Section 37 of the Arbitration
Act, 1996, read with the Commercial Courts Act, 2015 held:
“10. Coming to Section 37(1), it is evident that an appeal can lie
from only the orders specified in clauses (a), (b) or (c). In other
words, an appeal under Section 37 would only be maintainable
C against (a) an order refusing to refer the parties to arbitration
under Section 8 of the A&C Act; (b) an order granting or refusing
to grant any measure under Section 9 of the A&C Act; or (c) an
order setting aside or refusing to set aside an arbitral award under
Section 34 of the A&C Act. The impugned order [Arcadia Shares
D & Stock Brokers (P) Ltd. v. Harmanprit Singh Sidhu, 2016 SCC
OnLine Del 6625] is clearly not relatable to Section 8 or 9 of the
A&C Act. It was sought to be contended by the learned counsel
for the appellant that the present appeal would fall within Section
37(1)(c) which relates to an order “setting aside” or “refusing to
set aside” an arbitral award under Section 34. We are unable to
E accept this proposition. By virtue of the impugned order, the arbitral
award dated 10-9-2013 has not been set aside. Nor has the court,
at this stage, refused to set aside the said arbitral award under
Section 34 of the A&C Act. In fact, the appellant in whose favour
the award has been made, would only be aggrieved if the award
F were to have been set aside in whole or in part. That has not
happened. What the learned single Judge has done is to have
condoned the delay in re-filing of the petition under Section 34.
This has not, in any way, impacted the award.”
17. The reasoning in this judgment in Harmanprit Singh
G Sidhu commends itself to us, as a distinction is made between
judgments which either set aside, or refuse to set aside, an arbitral
award after the court applies its mind to Section 34 of the
Arbitration Act, 1996, as against preliminary orders of condonation
of delay, which do not in any way impact the arbitral award that
has been assailed.”
H
CHINTELS INDIA LTD. v. BHAYANA BUILDERS PVT. LTD. 851
[R.F. NARIMAN, J.]
28. It is well settled that judgments are not to be construed like A
Euclid’s theorems (see Amar Nath Om Prakash v. State of Punjab
(1985) 1 SCC 345), but all observations made therein must relate to the
context in which they were made. In that case, the Court put it thus:
“10. There is one other significant sentence in Sreenivasa
General Traders v. State of A.P [(1983) 4 SCC 353] with which B
we must express our agreement, it was said:
“With utmost respect, these observations of the learned Judge
are not to be read as Euclid’s theorems, nor as provisions of a
statute. These observations must be read in the context in which
they appear.” C
We consider it proper to say, as we have already said in other
cases, that judgments of courts are not to be construed as statutes.
To interpret words, phrases and provisions of a statute, it may
become necessary for Judges to embark into lengthy discussions
but the discussion is meant to explain and not to define. Judges D
interpret statutes, they do not interpret judgments. They interpret
words of statutes; their words are not to be interpreted as statutes.
In London Graving Dock Co. Ltd. v. Horton [1951 AC 737,
761] Lord MacDermott observed:
“The matter cannot, of course, be settled merely by treating E
the ipsissima verba of Willes, J., as though they were part of an
Act of Parliament and applying the rules of interpretation
appropriate thereto. This is not to detract from the great weight to
be given to the language actually used by that most distinguished
Judge.... F
In Home Office v. Dorset Yacht Co. Ltd. [(1970) 2 All ER 294]
Lord Reid said:
“Lord Atkin’s speech [Donoghue v. Stevension, 1932 All ER Rep
1, 11] ... is not to be treated as if it was a statutory definition. It
will require qualification in new circumstances.” G
Megarry, J. in (1971) 1 WLR 1062 observed:
“One must not, of course, construe even a reserved judgment of
even Russell, L.J. as if it were an Act of Parliament.”
H
852 SUPREME COURT REPORTS [2021] 1 S.C.R.
A And, in Herrington v. British Railways Board [1972 AC 877
(HL)] Lord Morris said:
“There is always peril in treating the words of a speech or a
judgment as though they were words in a legislative enactment,
and it is to be remembered that judicial utterances are made in the
B setting of the facts of a particular case.”
11. There are a few other observations in Kewal Krishan Puri
case [(1980) 1 SCC 416] to which apply with the same force all
that we have said above. It is needless to repeat the oft-quoted
truism of Lord Halsbury that a case is only an authority for what
C it actually decides and not for what may seem to follow logically
from it.”
29. The context in which paragraph 17 of BGS SGS Soma (supra)
was made, was a context in which an application under section 34 would
have to be returned to the Court which had jurisdiction to decide a section
D 34 application, dependent upon where the seat of the arbitral tribunal
was located. In this context, it was held that a mere preliminary step,
which did not lead to the application being rejected finally, cannot be
characterised as an order which would result in the application’s fate
being sealed once and for all. The Court’s focus was not on the language
of section 37(1)(c), nor were any arguments addressed as to its correct
E interpretation. As a matter of fact, Harmanprit Singh Sidhu (supra)
itself went on to hold:
“13. In sum, the impugned order does not fall within the category
of appealable orders specified in Section 37(1) of the A&C Act.
Therefore, even if the provisions of Section 37(1) are read with
F Section 13 of the Commercial Courts Act, the present appeal is
not maintainable. This, however, does not mean that the appellant
cannot take up the ground that is sought to be urged before us if
the decision in OMP 294/2014 (under Section 34 of the A&C
Act) goes against him. In other words, if the arbitral award is set
G aside in part or in whole and the appellant is aggrieved thereby, he
may prefer an appeal under Section 37 of the A&C Act on merits
as also on the ground that the delay in re-filing ought not to have
been condoned. This is in line with the scheme of the A&C Act of
not, in any way, stalling the proceedings thereunder. For example,
under Section 13(4) of the A&C Act, if a challenge to an arbitrator
H
CHINTELS INDIA LTD. v. BHAYANA BUILDERS PVT. LTD. 853
[R.F. NARIMAN, J.]
is not successful, the arbitral tribunal is required to continue the A
arbitral proceedings and make an arbitral award and, in such an
instance, as provided in Section 13(5) of the A&C Act, the party
challenging the arbitrator may make an application for setting aside
such an arbitral award in accordance with Section 34. In other
words, recourse to a remedy for an unsuccessful challenge to an
B
arbitrator is deferred till the stage of the making of the award.
Similarly, under Section 16, an arbitral tribunal may rule on its
jurisdiction. In a case where the arbitral tribunal rejects a plea
with regard to its jurisdiction, it is enjoined by Section 16(5) of the
A&C Act to continue with the arbitral proceedings and to make
the arbitral award. Section 16(6) stipulates that a party aggrieved C
by such an arbitral award may make an application for setting
aside the award in accordance with Section 34. Here, too, the
unsuccessful party, who challenges the jurisdiction of an arbitral
tribunal, is asked to wait till the award is made. The remedy of
questioning the decision of the arbitral tribunal with regard to the
D
arbitrator’s jurisdiction in such a case is not extinguished but is
merely deferred till the making of the arbitral award. In similar
vein, in the present case, the remedy of challenging the decision
of condoning the delay in re-filing is not extinguished but is deferred
till the final decision of the court on the pending Section 34 petition.”
30. Obviously therefore, an observation of this Court torn out of E
its context cannot be said to conclude the issue that is now before us.
31. We now come to the sheet anchor of Shri Rohatgi’s case,
namely, Ramdas Construction Co. (supra). In this judgment, a Division
Bench of the Bombay High Court held:
F
“9. Sub-section (3) of section 34 of the Act provides that an
application for setting aside may be made after three months have
elapsed from the date on which the party making such application
had received the arbitral award or, if a request had been made
under section 33, from the date on which that request had been
disposed of by the arbitral tribunal, provided that if the Court is G
satisfied that the applicant was prevented by sufficient cause from
making the application within the said period of three months, it
may entertain the application within a further period of thirty days,
but not thereafter. This provision of law expressly reveals that the
legislature has provided a specific period of limitation for filing an H
854 SUPREME COURT REPORTS [2021] 1 S.C.R.
A application for setting aside of the award and simultaneously the
Court has been given discretion to extend such period only by
thirty days, and not beyond the said period of thirty days. The
provision is very clear in that regard. However, the scope of enquiry
under sub-section (3) is restricted to the cause for delay in filing
the application but it does not relate to the merits of the application
B
for setting aside of the award. Being so, an order which is to be
passed in exercise of powers under sub-section (3) of section 34
of the Act cannot extend to the subject matter of the application
for setting aside of the award but has to restrict to the aspect of
delay in filing such application only. Such an order is not
C contemplated to be an appealable order within the meaning of the
said expression under section 37 of the Act. It is very clear from
the fact that section 37 refers to the orders dealing with the aspect
of setting aside or refusing to set aside an arbitral award. It does
not refer to the proceedings preceding the enquiry in relation to
the issue of setting aside or refusing to set aside an arbitral award.
D
The subject-matter of delay in filing an application and the
condonation thereof relates to the proceedings preceding the
enquiry for setting aside or refusing to set aside an arbitral award.
Once it is clear that section 37(1)(b) does not contemplate any
order passed in such proceeding relating to the matter preceding
E the enquiry in relation to setting aside or refusing to set aside an
arbitral award, such an order cannot be considered as an appealable
order within the meaning of the said expression under section 37
of the Act.
10. Undoubtedly the impugned order while rejecting the application
F for condonation of delay, clearly observes:
“Consequently, application under section 34 of the Arbitration and
Conciliation Act, 1996 for setting aside the award is also rejected
being barred by time.”
In other words, the Court has not dealt with the application for
G setting aside of the award on merits and the same has been disposed
of solely as a consequence of rejection of the application for
condonation of delay and there has been no enquiry as regards
the rights of the parties on the issue of setting aside of the award.
The appealable order which is contemplated for the purpose of
H exercise of appellate jurisdiction is the one which deals with the
CHINTELS INDIA LTD. v. BHAYANA BUILDERS PVT. LTD. 855
[R.F. NARIMAN, J.]
merits of the case in relation to the claim for setting aside or A
refusing to set aside an arbitral award. As already stated above,
the appellate powers under section 37 are not in relation to the
proceedings which precedes the enquiry regarding setting aside
or refusing to set aside an arbitral award. Being so, the
consequence of the order of dismissal of the application for
B
condonation of delay cannot itself amount to an appealable order
under section 34(1) for the purpose of appeal under section 37(1)
of the Act.”
32. This judgment cannot be said to state the law correctly as it
does not advert to the decision of this Court in Essar Constructions
(supra), and is against the interpretation of section 37(1)(c) of the C
Arbitration Act, 1996 given by us above. We may also add that this
Court, in dismissing the Civil Appeal against the aforesaid judgment,
held:
“1. The appellants before this Court, in the first instance, impugned
the award rendered by the Chief Engineer on 30.06.2005, by D
preferring an appeal before the District Judge, Nagpur. The District
Judge, Nagpur, declined to entertain the appeal on merits, as he
found the same barred by limitation, and as such, the application
for condonation of delay was dismissed. The District Judge, Nagpur
in his order dated 23.12.2005 recorded as under: E
“17. In nut-shell, what emerges from the material placed on the
record is that the applicants or in other words, party making
application under Section 34 duly received the award on 4.7.2005,
but approached this Court on 18.11.2005. Time in between 4.7.2005
and 18.11.2005 was consumed in taking administrative decision. F
Beyond statutory period of limitation of three months, further period
of thirty days can be condoned, but not thereafter. On 4.11.2005,
entire period of four months elapsed. In this view of the matter,
this Court has no jurisdiction to entertain the application for
condonation of delay and for that matter, application under Section
34 of the Act.” G
2. The order dated 23.12.2005 was assailed by the appellants
before the High Court. Having remained unsuccessful, the
appellants have approached this Court. The primary issue, that
emerges for consideration is, whether the dismissal of the
H
856 SUPREME COURT REPORTS [2021] 1 S.C.R.
A application filed by the appellants under Section 34 of the
Arbitration and Conciliation Act, 1996 (hereinafter referred to as
the ‘Arbitration Act’), by the District Judge, Nagpur, was justified
in law.
3. So far as the issue in hand is concerned, having heard learned
B counsel for the rival parties, we are satisfied that on an earlier
occasion, the same proposition came up for consideration before
this Court, and stands declared by this Court in State of Himachal
Pradesh vs. Himachal Techno Engineers (2010) 12 SCC 210. In
view of the legal position declared by this Court, on the subject of
limitation under Section 34 of the Arbitration Act, we are of the
C view, that the order passed by the District Judge, Nagpur, calls
for no interference.”
33. The order of this Court does not in any manner touch upon the
reasoning of the Bombay High Court. On the contrary, this court refers
to the judgment of this Court in Himachal Pradesh Techno Engineers
D (supra), which as has been held by us hereinabove, makes it clear that
Section 5 of the Limitation Act is excluded by section 34(3) of the
Arbitration Act, 1996 and that no condonation of delay can take place
beyond the period of 120 days. It is on this ground, citing the learned
District Judge’s order, that this Court did not interfere. Consequently, it
E cannot be said that this Court approved of the judgment of the Division
Bench of the Bombay High Court. Likewise, the reasoning contained in
Radha Krishna Seth (supra), does not commend itself to us.Both these
judgments therefore do not state the law correctly and stand overruled.
34. Shri Rohatgi referred to the Statement of Objects and Reasons
F of the Arbitration Act, 1996and in particular clause 4(v), which reads as
follows:
“4. Main objects of the Bill are as under:
xxx xxx xxx
(v) to minimise the supervisory role of courts in the arbitral
G
process;”
35. Shri Rohatgi then read section 5 of the Arbitration Act, 1996
to us. According to him, in furtherance of this object,section 37 was
enacted giving a limited right of appeal. He argued that an appeal, being
a creature of statute should not, therefore, be enlarged beyond what is
H
CHINTELS INDIA LTD. v. BHAYANA BUILDERS PVT. LTD. 857
[R.F. NARIMAN, J.]
provided by the Legislature. Section 5 of the Arbitration and Conciliation A
Act reads as follows:
“5. Extent of judicial intervention.—Notwithstanding anything
contained in any other law for the time being in force, in matters
governed by this Part, no judicial authority shall intervene except
where so provided in this Part.” B
36. This section does not take Shri Rohatgi’s argument much
further, as after the non-obstante clause, the section states that no
judicial authority shall intervene “except where so provided in this Part”.
What is “provided in this part” is section 37, which therefore brings us
back to square one. Undoubtedly, a limited right of appeal is given under C
section 37 of the Arbitration Act, 1996. But it is not the province or duty
of this Court to further limit such right by excluding appeals which are in
fact provided for, given the language of the provision as interpreted by
us hereinabove. Thus, this last argument also has no legs on which to
stand.
D
37. Consequently, the question of law is answered by stating that
an appeal under section 37(1)(c) of the Arbitration Act, 1996 would be
maintainable against an order refusing to condone delay in filing an
application under section 34 of the Arbitration Act, 1996 to set aside an
award.
E
38. The appeal is accordingly allowed. The impugned judgment
of the Division Bench under appeal is set aside, and the matter is remitted
to a Division Bench of the High Court of Delhito decide whether the
Single Judge’s refusal to condone delay is or is not correct.
39. The appeal is allowed in the aforesaid terms. All pending F
applications are disposed of.
Ankit Gyan Appeal allowed.
G
H
Search Indian case law
Ask in plain English, not just keywords. 25,000 AI words free, no card.