COMMISSIONER, M.P. HOUSING BOARD AND OTHERSversusM/S. MOHANLAL AND COMPANY
- Citation
- 2016 INSC 1187
- Decided
- 19 July 2016
- Disposal
- Appeal(s) allowed
- Bench
- DIPAK MISRA
Holding
Section 14 of the Limitation Act does not apply because the earlier Section 11 proceeding does not relate to the same matter in issue, and the respondent lacked the requisite diligence and good faith; consequently, the Section 34(2) objection filed beyond the prescribed period cannot be condoned.
Summary
The parties entered into a construction contract containing an arbitration clause, and an award was rendered on 11 November 2010. The respondent later filed a Section 11 application in the High Court seeking appointment of an arbitrator, claiming the clause was invalid; the application was dismissed. Subsequently, on 26 September 2011, the respondent filed a Section 34(2) objection to the award, well beyond the three‑month period prescribed by the Arbitration and Conciliation Act, 1996, and also sought exclusion of the time spent in the earlier Section 11 proceeding under Section 14 of the Limitation Act, 1963. The High Court held that Section 14 applied and condoned the delay. On appeal, the Supreme Court examined whether the earlier proceeding related to the same matter in issue and whether the respondent acted with diligence and good faith. It concluded that the Section 11 application was a distinct proceeding, the respondent participated in the arbitration and was aware of the award, and therefore the delay could not be excluded. The objection was filed out of time and could not be entertained. The appeal was allowed, setting aside the High Court’s order.
Issues considered
- Whether Section 14 of the Limitation Act, 1963 can be invoked to exclude the period spent in a Section 11 application when computing the limitation period for filing a Section 34(2) objection under the Arbitration and Conciliation Act, 1996.
- Whether the earlier proceeding under Section 11 relates to the same matter in issue as the later objection under Section 34(2).
- Whether the respondent exercised due diligence and acted in good faith in pursuing the earlier remedy.
Legislation cited
- Arbitration and Conciliation Act, 1996s. 11, s. 34(2), s. 34(3)
- Code of Civil Procedure, 1908s. 11
- Limitation Act, 1963s. 14
Subjects
Judgment
[2016] 3 S.C.R. 357.
COMMISSIONER, M.P. HOUSING BOARD AND OTHERS A
v.
M/S. MOHANLAL AND COMPANY
(Civil Appeal No. 6573of2016)
JULY 19,2016 B
[DIPAK MISRA AND ROHINTON f'ALI NARIMAN, JJ.j
Arbitration and Conciliation Act. 1996: s.34(2) - Delay in
filing objection 11/s.34(2) il'hether c1111donable in aid of s.14 of
Limitation Act - In the instant case. arbitral award passed on
11.11.2010 - Respondent filed s.11 application for seeking
c
appointment of arbitrator on the ground that there was 110 ctrbitration
clause in the contract - High Court dismissed the application which
order remained unchallenged and a/fained finality - Thereqfte1;
respondent filed an o~jection u/s.34(2) on 26.9.2011 to challenge
the award - Respondent also filed application u/s.14 seeking D
exclusion of time consumed in the proceedings u/s.11 asserting that
he was bonqfidely prosecuting the case in the court having no
jurisdictio11 - Whether s. ]./ would be applicable - Held: Not
applicable -- s.14{1) of the limitmion Act lays down that the
proceedings must relate to the same matter in issue - Filing of an
E
application u/s.11 for un appointment of arbitrator is totalzy different
from an objection filed u/s.34 - It cannot be said that the
proceedings related to "same matter in issue·· - Respondent had
duly participated in the arbitral proceeding - There was thus
absence of diligence a11d good faith on part of respondent - Time
consumed for pursuing remedy u/s. JJ not excludible for filing f.
objection - Limitation Act, 1963 - s.14.
Allowing the a11peal, the Court
HELD: The ob,iection was filed beyond the JICriod
prescribed under the 1996 Act. However, the a1>pellants sought
exclusion of the time spent in the proceedings in court as G
envisaged under Section 14 of the Act. It is settled in law that
Section 14 of' the Act applies to Section 34(3) of the 1996 Act.
Section 14 would be applicable in cases of mistaken remedy or
selection of a wrong forum. In the case at hand, the respondent
appeared before the arbitrator and after the award was passed, H
357
.,
358 SUPREME COURT REPORTS [2016] 3 S.C.R.
A chose not to file any objection to the award immediately. On the
contrary, the respondent filed an application under Section 11 of
1996 Act before the High Court for appointment of an arbitrator.
Section 14(1) of the Act lays down that the proceedings must
relate to the same matter in issue. It emphasises on due diligence
and good faith. Filing of an application under Section 11 of the
B
1996 Act for an appointment of arbitrator is totally different from
an objection to award filed under Section 34 of the 1996 Act. To
put it differently, one is at the stage of initiation, and the other at
the stage of culmination. By no stretch of imagination, it can be
said that the proceedings relate to "same matter in issue".
c Additionally, the respondent had participated in the arbitral
proceeding and was aware of passing of the award. He, may be,
by design, invoked the jurisdiction of the High Court for
appointment of an arbitrator. Liberal interpretation should be
placed on Section 14 of the Act, but if the fact situation exposits
absence of good faith of great magnitude, law should not come to
D
the rescue of such a litigant. This is so because the respondent
instead of participating in the arbitration proceedings, could have
immediately taken steps for appointment of arbitrator as he
thought appropriate or he could have filed his ob.icctions under
Section 34(2) of the Act within permissible parameters but he
E chose a way, :m innovative path, possibly harbouring the thought
that he could contrive the way where he could alone rule. This is
neither diligence nor good faith. On the contrary, it is absence of
both. The High Court has fallen into grave error by concurring
with the opinion expressed by the Additional District Judge and,
therefore, both the orders deserve to be lancinated. [Paras 14,
F
17, 18, 19] [364-D-E; 365-G; 366-B, E-H; 367-A-C)
State of Goa v. Western Builders (2006) 6 SCC 239:
2006 (3) Suppl. SCR 288; Consolidated Engineering
Enterprises v. Principal Secretary, Irrigation
lJepar/ment and ot/Jcrii (2008) 7 sec 169: 2008 (5)
G SCR 1108; Ranwdhar Shril'as v. Bhagll'andas (2005)
13 SCC 1: 2005 (4) Suppl. SCR 808; Union of India
v. Popular Construction Co. (2001) 8 SCC 470:2001
(3) Suppl. SCR 619 - relied on.
MP. Housing Board and Another v. Sohanlal Chourasia
H and Another (2008) 2 M.P.L.J. 103 - referred to.
COMMISSIONER, M.P. HOUSING BOARD AND OTHERS v. 359
MIS. MOHANLAL AND COMPANY
Case Law Reference A
(2008) 2 M.P.L.J. 103 referred to Paras
2001 (3) Suppl. SCR 619 relied on Para 13
2006 (3) Suppl. SCR 288 relied on Para 14
2008 (5) SCR 1108 relied on Para 14
2005 (4) Suppl. SCR 808 relied on Para 17
CIVIL APPELLATE JURISDICTION : Civil Appeal No. 6573
of2016.
From the Judgment and Order dated 12.08.2013 of the High Court
of Madhya Pradesh, Principal Seat at Jabalpur in Civil Revision No. 332
c
of2012.
Sushi! Dutt Salwan, Pramod Dayal, Nikunj Dayal, Ms. Paya!
Dayal, Siddharth Vikram, Advs. for the Appellants.
Shekhar Sharma, Ms. Rashmi Singh, Adarsh Upadhyay, Advs.
for the Respondent. D
The Judgment of the Court was delivered by
DIPAK MISRA, J. 1. Leave granted.
2. The present appeal, by special leave, is directed against the
order dated 12th August, 2013, passed by the High Court of Madhya E
Pradesh, Principal Seat at Jabalpur, in Civil Revision No.332 of2012,
whereby the High Court has affirmed the view expressed by the learned
Additional District Judge, Bhopal, that the objection preferred by the
respondent under Section 34(2) of the Arbitration & Conciliation Act,
1996 (for short, 'the 1996 Act') was condonable in aid of Section 14 of
the Limitation Act, 1963 (for brevity, 'the Act'). F
3. The present litigation has a history. The respondent had entered
into a contract for construction of a commercial complex at Bittan Market,
E-5, Arera Colony, Bhopal on 29th June, 2009. During the subsistence
of the contract, certain disputes arose between the p~rties and the matter
was arbitrated upon. Clause 29 of the contract, on the basis of which G
the matter was referred to arbitration, reads as follows:
"29 - Except as otherwise provided in this contract all
questions and disputes relating to the meaning of the
specifications, designs, drawings and instructions, herein
before mentioned and as to thing whatsoever, in any way, H
360 SUPREME COURT REPORTS [2016] 3 S.C.R.
A arising out of or relating to the contracts, designs. drawings,
specifications, estimates, concerning the work, or the
execution or failure to execute the same, whether arising
during the progress of the work or after the completion or
abandonment thereof, shall be referred to the Dy. Housing
Commissioner in writing for his decision within a period of
B
thirty days of such occurrence. Thereupon, the Dy.
Housing shall give his written instructions and/or decision
within a period of sixty days of such written request. This
period can be extended by mutual consent of the parties.
If decided amount is more than Rs.25,000/- the same shall
c be. referred to the Housing Commissioner for his perusal.
Upon receipt of written instructions, or decision, the parties
shall promptly proceed without delay to comply such
decision or instructions. If the Dy. Housing Commissioner
fails to give his instructions or decision in writing within a
D period of sixty days or mutually agreed time after being
requested, ifthe parties are aggrieved against the decision
of the Dy. Housing Commissioner the patties may within
thirty days prefer such dispute/disputes for arbitration to
the Addi. Housing Commissioner subject to the jurisdiction
and limitations in accordance with the provisions of
E Madhyastham Adhikaran Adhiniyam, 1995. In case the
dispute is within the jurisdiction of Addi. Housing
Commissioner he shall then act as sole arbitrator, and he
shall pass an award after hearing both the parties, strictly
in accordance with the provisions of the Arbitration Act,
F 1940 and the rules made thereunder for the time being in
force.
If the contractor does not make any demand for arbitration
in respect of claim(s) in writing within ninety days on
receiving information from the Executive Engineer that the
G final bill is ready for payment, the claim of the contractor
shall be deemed to have been waived and shall be absolutely
barred and the Board shall be discharged or released of all
the liabi Ii ties. under the contract in respect of such claim( s).
A reference to the Arbitration shall be no ground for not
continuing the work on the part of the contractor and
H
COMMISSIONER, M.P. HOUSING BOARD AND OTHERS v. 361
MIS. MOHANLAL AND COMPANY [DIPAK MISRA, J.]
payment as per terms and conditions of the agreement shall A
be continued by the Board."
4. Relying on the said clause, the matter was referred to the
Additional Housing Commissioner, the sole arbitrator, who passed an
award on 11th November, 2010. Be it stated, both the parties appeared
before the learned arbitrator and on the basis of the materials brought on B
record, the learned arbitrator passed the award. As is manifest from
record, the arbitrator did not find any justification to allow any of the
claims of the respondent-contractor.
5. When the matter stood thus. as it appears. wisdom dawned
upon the respondent and he thought that he could take a somersault. c
And that propelled him to file an application under Section 11 of the 1996
Act before the High Court of Madhya Pradesh, which formed the subject
matter of Arbitration Case No.135of2010, for seeking appointment of
an arbitrator to adjudicate the disputes. It was contended before the
High Court that clause 29 of the contract could not be treated as an
arbitration clause and, therefore, the court should appoint an arbitrator. D
To bolster the said stand, reliance was placed on M.P. Housing Board
mu/ Another vs. Solw11/al C/1011,.asia anti A11other1•
6. The learned Single Judge reproduced the relevant passages
from the said judgment and came to hold as follows:
E
"From the aforesaid clause, it is seen that if any dispute
arises between the parties, the matter has to be resolved
by reference to the Dy. Housing Commissioner and,
thereafter, to the Addi. Housing Commissioner. The
provisions of Arbitration Clause clearly indicates that the
Arbitrator appointed under the agreement is a named_ F
arbitration namely the Addi. Housing Commissioner and he
has to exercise, powers available under the Arbitration Act
of 1940. Available on record is an award passed by the
Arbitrator i.e. the Addi. Housing Commissioner vide
Annexure PS and once in terms of clause 29 of the G
Agreement, the arbitrator i.e. the Addi. Housing
Commissioner has adjudicated the dispute and has passed
an award, no further action is to be taken in these
proceedings against u/s 11, as the sole arbitrator in
I (2008) 2 M.l'.L.J. 103
H
362 SUPREME COURT REPORTS [2016] 3 S.C.R.
A accordance with Arbitration Agreement has already
adjudicated the dispute between the parties. If the petitioner
is aggrieved by the adjudication of the dispute, he can now
challenge the award of the Arbitration in accordance with
law.
B In the light of the resolution of the dispute by the sole
Arbitator in accordance with clause 29 of the agreement,
this court does not find any ground to interfere into the
matter. The judgment relied upon by Sh. Shashank Shekhar
is clearly distinguishable. In that case the question and the
power is exercised by the Addi. Housing Commissioner u/
c s 29 of the agreement in question. In the said case, it is
only held that a Dy. Housing Commissioner deciding the
claim under clause 29 is not an Arbitrator."
7. We must immediately state that the said order was not assailed
and, has been allowed to attain finality.
D
8. After facing non-success before the High Court in his effort to
get an arbitrator appointed, the respondent thought it appropriate to file
an objection under Section 34(2) of the 1996 Act to challenge the award.
The said application was filed on 26th September, 2011. It is apt to note
here that the award was passed on 11th November, 20 I 0.
E 9. The respondent, along with his objection, filed an application
under Section 14 of the Act seeking exclusion of the time consumed in
the proceedings asse11ing that he was bonafidely prosecuting the case in
the court having no jurisdiction. The learned Additional District Judge,
upon hearing the learned counsel for tlie parties, a II owed the application
F on the foundation that the respondent was entitled to exclusion of time
under Section I 4 of the Act.
I 0. Being grieved by the aforesaid order, the appellant preferred
civi I revision before the High Court and, as has been stated earlier, the
High Cou11 did not find any infirmity in the order passed by the learned
G Additional District Judge and, accordingly, gave the stamp of approval
to the same.
I I. We have heard Mr. Sushi I Dutt Salwan, learned counsel for
the appellants and Mr. Shekhar Sharma, learned counsel for the
respondent.
H 12. The singular issue that emerges for consideration is whether
COMMISSIONER, M.P. HOUSING BOARD AND OTHERS v. 363
MIS. MOHANLAL AND COMPANY [DIPAK MISRA, J.)
in the obtaining factual scenario, Section 14 of the Act would be A
applicable. To appreciate the controversy, it is necessary to refer to
Section 34(3) of the 1996 Act. It reads as follows:
"34(3) An application for setting aside may not be made
after three months have elapsed from the date on which
the party making that application had received the arbitral .B
award or, if a request had been made under Section 33,
from the date on which that request had been disposed of
by the arbitral tribunal:
Provided that ifthe Court is satisfied that the applicant was
prevented by sufficient cause from making the application c
within the said period of three months it may ente11ain the
application within a further period of thirty days, but not
thereafter."
13. This Court iii Union of India vs. Popular Construction
1
Co. interpreting the said provision has held that:- -D
" As far as the language of Section 34 of the 1996 Act is
concerned, the crucial words are "but not thereafter" used
in the proviso to sub-section (3). In ouropinion, this phrase
would amount to an express exclusion within the meaning
of Section 29(2) of the Limitation Act, and would therefore
E
bar the application of Section 5 of that Act. Par! iament did
not need to go further. To hold that the cout1 could entertain
an application to set aside the award beyond the extended
period under the proviso, would render the phrase "but not
thereafter" wholly otiose. No principle of interpretation
would justify such a result". F
Andagain:-
"Furthermore, Section 34(1) itself provides that recourse
· to a court against an arbitral award may be made only by
an application for setting aside such award "iii accordance
with" sub-section (2) and sub-section (3). Sub-section (2) G
relates to grounds for setting aside an award and is not
relevant for our purposes. But an application filed beyond
the period mentioned in Section 34, sub-section (3) would
not be an application"in accordance with" that sub-section.
'(200I) s sec 470 H
364 SUPREME COURT REPORTS [2016] 3 S.C.R.
A Consequently by virtue of Section 34( I), recourse to the
court against an arbitral award cannot be made beyond the
period prescribed. The importance of the period fixed under
Section 34 is emphasised by the provisions of Section 36
which provide that
B "where the time for making an application to set aside the
arbitral award under Section 34 has expired ... the award
shall be enforced under the Code of Civil Procedure, 1908
in the ·same manner as if it were a decree of the court".
This is a significant depaiture from the provisions of the
c Arbitration Act, 1940".
14. The aforesaid authority makes it absolutely clear that that the
scheme oflimitation provided under the 1996 Act is different than 1940
Act; and, therefore, an application filed beyond the period of limitation
under Section 34(3) of 1996 Act would not be an application in
D accordance with the said provision. As.is evident from factual narration,
the.application was filed beyond the period prescribed in the said
provision. Therefore, it could not have been entertained under the 1996
· · Act.· However, the appellants sought exclusion of the time spent in the
··.·proceedings . in court as envisaged under Section 14 of the Act. It is
settled in law that Section 14 of the Act applies to Section 34(3) of the
E 1996 Act. It has been so held in State of Goa vs. Western Builders ..
and Consolidated Engineering Enterprises vs. Principal Secretary,
lrrigatio11 Departme11t a11d others4•
l5. Having stated thus, we are obliged to scrutinise under what
situations Section 14 of the Act gets attracted. Section 14( I) of the
F Act, which is relevant for the present purpose, reads as follows:
"14. Exclusion of time of proceeding bona fide in court
without jurisdiction.-( I) In computing the period oflimitation
for any suit the time during which the plaintiff has been
prosecuting with due diligence another civil proceeding,
G whether in a court of first instance or of appeal or revision,
against the defendant shall be excluded, where the
proceeding relates to the same matter in issue and is
prosecuted in good faith in a court which .. from defect of .
, (2006) 6 sec 239
1-1 • (2008) 1 sec 169
COMMISSIONER, M.P. HOUSING BOARD AND OTHERS v. 365
MIS. MOHANLAL AND COMPANY [DIPAK MISRA, J.]
jurisdiction or other cause of a like nature, is unable to A
entertain it."
16. In Consolidated Enl(ineerinK Enterprises (supra), the Court,
while dealing with the conditions in which Section 14 will be applicable,
enumerated five conditions which are as follows:-
;'(1) Both the prior and subsequent proceedings are civil B
proceedings prosecuted by the same party;
(2) The prior proceeding had been prosecuted with due
diligence and in good faith;
(3) The failure of the prior proceeding was due to defect
of jurisdiction or other cause ofl ike nature; c
(4) The earlier proceeding and the latter proceeding must
relate to the same matter in issue and;
(5) Doth the proceedings are in a court."
In the said case, it has also been stated that:- D
'' ... While considering the provisions of Section 14 of the
Limitation Act, proper approach will have to be adopted
and the provisions will have to be interpreted so as to advance
the cause of justice rather than nbort the proceedings. It
will be well to bear in mind that an element of mistake is
inherent in the invocation of Section 14. In fact, the section E
is intended to provide reliefagainst the bar of Iimitation in
cases of mis taken remedy or selection of a wrong forum.
On reading Section 14 of the Act it becomes c!ear that the
legislature has enacted the said section to exempt a certain
period covered by a bona fide litigious activity.... " F
17. From the aforesaid passage, it is clear ?S noon day that
there has to be a liberal interpretation to advance the cause of justice.
However, it has also been laid down that it woulcfbe applicable in cases
of mistaken remedy or selection ofa wrong forum. As per the conditions
enumerated, the earlier proceeding and the latter proceeding must relate G
to the same matter in issue. It is worthy to mention here that the words
"matter in issue" are used under Section 11 of.the Code of Civil
Procedure, 1908.' As has been held in Rammllwr Shrivas vs.
Blwgwandas·' the said expression connotes the matter which is directly
'(200SJ 13 sec 1 .._.H
366 SUPREME COURT REPORTS [2016] 3 S.C.R.
A and substantially in issue. We have only referred to the said authority to
highlight that despite liberal interpretation placed under Section 14 of the
Act, the matter in issue in the earlier proceeding and the latter proceeding
has to be conferred requisite importance. That apart, the prosecution of
the prior proceeding should also show due diligence and good faith.
B 18. In the case at hand, the respondent appeared before the
learned arbitrator and after the award was passed, chose not to file any
objection to the award immediately. On the contrary, the respondent
filed an application under Section 11 of 1996 Act before the High Court
for appointment of an arbitrator. As has been stated earlier, the learned
c Single Judge of the High Court distinguished the decision in the case of
Solzanlal Clzourasia and Another (supra) and came to hold that the
application was not maintainable. However, he granted liberty to the
respondent to file an objection in accordance with law. The words "in
accordance with law" gain significance. It allows an argument to be
canvassed by the respondent that the time spent in earlier proceeding
D deserved exclusion while computing the period of limitation. But, an
ominous one for the respondent, whether Section 14 is at al I attracted?
Had the learned Single Judge stated that the period consumed for pursuing
the remedy under Section 11 of the 1996 Act, would be excluded for
filing objection, possibly the matter would have been different. In any
case, we do not intend to dilate further on that aspect. It is quite clear
E
that the quoted portion herein-above does not so indicate. It only grants
liberty to the respondent to file an objection in accordance with law.
Sectioo 14( I) of the Act which we have reproduced, lays down that the
proceedings must relate to the same matter in issue. It emphasises on
due diligence and good faith. Filing of an application under Section 11 of
F the 1996 Act for an appointment of arbitrator is totally different than an
objection to award filed under Section 34 of the 1996 Act. To put it
differently, one is at the stage of initiation, and the other at the stage of
culmination. By no stretch of imagination, it can be said that the
proceedings relate to "same matter in issue". Additionally, the respondent
had participated in the arbitral proceeding and was aware of passing of
G
the award. He, may be, by design, invoked the jurisdiction of the High
Court for appointment of an arbitrator. We are absolutely conscious
that liberal interpretation should be placed on Section 14 of the Act, but
ifthe fact situation exposits absence of good faith of great magnitude,
law should not come to the rescue of such a litigant. We say so because
H the respondent instead of participating in the arbitration proceedings,
COMMISSIONER, M.P. HOUSING BOARD AND OTHERS v. 367
MIS. MOHANLAL AND COMPANY [DIPAK MISRA, J.]
could have immediately taken steps for appointment of arbitrator as he A
thought appropriate or he could have filed his objections under
Section34(2) of the Act within permissible parameters but he chose a
way, which we are disposed to think, an innovative path, possibly
harbouring the thought that he could contrive the way where he could
alone rule. Frankly speaking, this is neither diligence nor good faith. On
B
the contrary, it is absence of both.
19. In view of the aforesaid analysis, we find that the High
Court has fallen into grave error by concurring with the opinion expressed
by the learned Additional District Judge and, therefore, both the orders
deserve to be lancinatcd and, accordingly, we so direct. c
20. The appeal is, accordingly, allowed. There shall be no order
as to costs.
D~vika Gujral Appeal allowed.
Search Indian case law
Ask in plain English, not just keywords. 25,000 AI words free, no card.