COX & KINGS LTD.versusINDIAN RLY. CATERING & TOURISM CORPORATION LTD. & ANR.
- Citation
- 2012 INSC 270
- Decided
- 5 July 2012
- Disposal
- Dismissed
- Bench
- ALTAMAS KABIR
Holding
A party that is not a party to the lease cannot obtain a mandatory injunction under Section 9 of the Arbitration and Conciliation Act, 1996; its remedy is damages, and the interim receiver order is set aside.
Summary
Cox & Kings Ltd. entered into a joint‑venture with IRCTC to operate a luxury tourist train under a lease of the train to the joint‑venture company. IRCTC later terminated the lease, prompting Cox & Kings to invoke Section 9 of the Arbitration and Conciliation Act, 1996 seeking a stay of termination and the appointment of a receiver to keep the train running. The Delhi High Court Single Judge appointed a receiver as an interim measure, but the Division Bench set aside that order. The Supreme Court held that the petitioner, not a party to the lease, could not obtain a mandatory injunction to operate the train and that its proper remedy was an action for damages; the interim receiver order was therefore invalid. The Court dismissed the Special Leave Petitions, leaving the parties free to resolve their dispute through arbitration.
Issues considered
- Whether a party to a joint‑venture, but not a party to the lease, can obtain interim relief under Section 9 of the Arbitration and Conciliation Act, 1996 to restrain termination of the lease and compel operation of the train.
- Whether the joint‑venture agreement creates a partnership or confers enforceable rights on the petitioner to continue operating the train.
- Whether the appropriate remedy for the petitioner is an injunction or damages for breach of the lease and joint‑venture agreement.
- Whether the High Court had the jurisdiction to appoint a receiver as an interim measure in the circumstances.
Legislation cited
Subjects
Judgment
[2012] 7 S.C.R. 19
COX & KINGS LTD. A
V.
INDIAN RLY. CATERING & TOURISM CORPORATION
LTD.& ANR.
(Special Leave Petition (CIVIL) Nos. 965-967 of 2012)
JULY 5, 2012
B
[ALTAMAS KABIR AND J. CHELAMESWAR, JJ.]
Arbitration and Conciliation Act, 1996 - s. 9 - Grant of
interim measure - Permissibility - Luxury Tourist Train project C
- Expression of Interest floated by Respondent (IRCTC) for a
Joint Venture partner- to operate, manage and run the train -
Petitioner selected as Joint Venture shareholder - Petitioner
and Respondent became equal shareholders in a Joint
Venture Company in terms of a Memorandum of o
Understanding (MoU) - Luxury Tourist Train leased by
Respondent to the Joint Venture Company - Disputes
resulting in subsequent termination of the lease arrangement
by Respondent - Petitioner initiated proceedings u/s.9 for
staying the termination of the lease agreement and also to E
allow the arrangements to continue for sometime - Single
Judge of the High Court deemed it fit to appoint a Receiver,
as an interim measure, in the public interest, to prevent
discontinuation of the running of the train for which bookings
had already been made, and disposed of the s. 9 application,
F
inter alia, by directing the train to run under the supervision
of the Receiver for certain period - Division Bench, however,
set aside the arrangements made by the Single Judge and
allowed the appeal preferred by Respondent - On appeal,
held: Petitioner was not entitled to question termination of the G
lease agreement as by itself it had no existence as far as the
running of the train was concerned and it was not a party to
the proceedings - Petitioner attempted to either restore the
lease agreement, which had been terminated, or to create a
19 H
20 SUPREME COURT REPORTS [20121 7 S.C.R.
A fresh agreement to enable the Petitioner to operate the luxury
train indefinitely, till a decision was arrived at in s. 9 Application
- No doubt the Petitioner invested large sums of money in the
project, but that cannot entitle it to pray for and obtain a
mandatory order of injunction to operate the train once the
B lease agreement! arrangement had been terminated -
Petitioner's remedy, if any, would lie in an action for damages
against IRCTC for breach of any of the terms and conditions
of the Joint Venture Agreement and the MoU.
C The Ministry of Railways (Rail Mantralaya), Railway
Board, approved the proposal submitted by respondent
no.1-lndian Railway Catering & Tourism Corporation Ltd.
[IRCTC], for operating a Luxury Tourist Train on a Pan-
India route within India. Such proposal was made in
pursuance of an Expression of Interest floated by the
D respondent for a Joint Venture partner for the said
Luxury Transit Train Project, to operate, manage and run
the said train. The Petitioner came to be selected as the
Joint Venture shareholder for the operation of the Luxury
Tourist Train Project. In terms of a Memorandum of
E Understanding, the Petitioner and the Respondent
became equal shareholders in a Joint Venture Company.
The Luxury Tourist Train was leased by the Respondent
to the Joint Venture Company for a period of 15 years,
which could be extended by another period of 10 years
F on conditions to be mutually agreed between the
Petitioner and the Respondent. Whilst the Joint Venture
operations were being conducted, certain disputes arose
between the shareholders regarding the working of the
Joint Venture Agreement and the Memorandum of
G Understanding, which ultimately resulted in the
termination of the lease arrangement by the Respondent,
IRCTC. On account of such termination of the lease
agreement, the Petitioner initiated proceedings under
Section 9 of the Arbitration and Conciliation Act, 1996 for
H staying the termination of the lease agreement and also
COX & KINGS LTD. v. INDIAN RLY. CATERING & 21
TOURISM CORPORATION LTD.
to allow the arrangements to continue for a specified A
period, subject to such terms and conditions as may be
imposed by the Court.
The Single Judge of the High Court deemed it fit to
appoint a Receiver, as an interim measure, in the public
B
interest;- to prevent discontinuation of the running of the
train for which bookings had already been made, and
disposed of the Section 9 application, inter alia, by
directing that the train would continue to be run under
the supervision of the Receiver for certain period. The C
Division Bench, however, set aside the arrangements
made by the Single Judge and allowed the appeal
preferred by the Respondent. The order was challenged
before this Court.
Dismissing the Special Leave Petitions as also the D
connected Contempt Petitions, the Court
HELD: 1. It is evident from the submissions made on
behalf of the respective parties that the arrangement
between Respondent No.1, IRCTC, was with the E
Petitioner Company and, although, it was the intention of
the parties by virtue of the Joint Venture Agreement that
the luxury train, belonging to the Respondent No.1, was
to be operated by the Joint Venture Company, at least for
a minimum period of 15 years, what ultimately transpired F
was the termination of the Agreement by Respondent,
No.1 in favour of the Joint Venture Company. As pointed
out by the Division Bench of the High Court, the Petitioner
was not entitled to question such termination as by itself
it had no existence as far as the running of the train was G
concerned and it was not a party to the proceedings. In
fact, what the Petitioner attempted to do in these
proceedings was to either restore the Lease Agreement,
which had been terminated, or to create a fresh
Agreement to enable the Petitioner to operate the luxury H
22 SUPREME COURT REPORTS [2012] 7 S.C.R.
A train indefinitely, till a decision was arrived at in Section
9 Application. [Para 22] [31-F ·H; 32-A]
2. It is no doubt true that the Petitioner has invested
large sums of money in the project, but that cannot entitle
it to pray for and obtain a mandatory order of injunction
8
to operate the train once the lease agreement/
arrangement had been terminated. It cannot be said that
the Joint Venture Agreement was akin to a partnership.
Such submission had been rightly rejected by the
Division Bench. As rightly pointed out by the Division
C Bench of the High Court, the Petitioner's remedy, if any,
would lie in an action for damages against IRCTC for
breach of any of the terms and conditions of the Joint
Venture Agreement and the Memorandum of
Understanding. [Para 23] [32-B-D]
D
3. Taking into consideration the totality of the
circumstances, this Court is inclined to agree with the
suggestions made by IRCTC before the Division Bench
of the High Court regarding the operation of the train by
E IRCTC, with liberty to the parties to appoint an Arbitral
Tribunal to settle their disputes. It is made clear that if an
Arbitral Tribunal is appointed, the aforesaid arrangement
will be subject to the decision of the Arbitral Tribunal.
[Para 24] [32-E-F]
F CIVIL APPELLATE JURISDICTION : SLP (Civil) No. 965-
967 of 2012 etc.
From the Judgment & Order dated 06.01.2012 of the High
Court of Delhi at New Delhi in FAO (OS) No. 433-435 of 2011.
G WITH
Conmt. Pet.(C) No. 41-43 of 2012 in SLP (C) No. : 965-967
of 2012.
Mukul Rohatgi, Nikhil Rohatgi, Misha Rohatgi, Peter Lobo,
H Mahesh Agrawala, Akshay Runge, E.C. Agrawala for the
COX & KINGS LTD. v. INDIAN RLY. CATERING & 23
TOURISM CORPORATION LTD.
Petitioner. A
R.F. Nariman, S.G.I., Shyam Diwan, Saurav Agrawal,
Abhijeet Sinha, Ashish Tiwari, Titash Sen, Vipul Sharda,
Kamlendra Mishra, Siddharth Singla for the Respondents.
The Judgment of the Court was delivered by B
~LTAMAS KABIR, J. 1. In June/July 2007, The Ministry
of Railways (Rail Mantralaya), Railway Board, approved the
proposal submitted by the Indian Railway Catering & Tourism
Corporation Ltd., hereinafter referred to as "IRCTC", for c
operating a Luxury Tourist Train on a Pan-India route within
India. Such proposal was made in pursuance of an Expression
of Interest floated by the Respondent for a Joint Venture partner
for the said Luxury Transit Train Project, to operate, manage
and run the said train. The proposal was approved subject to D
certain broad principles for running the said train, set out by the
Indian Railways in its letter dated 29th November, 2007,
addressed to the Respondent, namely,
"(a) The Respondent will own the rake;
E
(b) The Respondent will pay to the Indian Railways the
cost of maintenance and periodical overhaul of the
rake;
(c) Railways be entitled to recover the haulage cost;
F
(d) The Respondent with their associate agencies will
manage on board/off board services, marketing,
booking, pricing, etc."
2. The Petitioner came to be selected as the Joint Venture G
shareholder for the operation of the Luxury Tourist Train Project.
On 11th January, 2008, the Respondent forwarded the draft
Memorandum of Understanding, which was proposed to be
executed between the Petitioner and the Respondent, to the
Indian Railways. In terms of the said Memorandum of H
24 SUPREME COURT REPORTS (20121 7 S.C.R.
A Understanding, the Petitioner and the Respondent would be
equal shareholders of the Joint Venture Company and the
project cost was estimated at Rs.37.5 crores, out of which an
amount of Rs. 7.5 was to be contributed by the Ministry of
Tourism as a grant and an amount of Rs.15 crores was to be
B contributed as advance lease rental by the Petitioner as its
share. In addition to the above, the Petitioner was to bring in
the funding for the project and the Luxury Tourist Train was to
be leased by the Respondent to the Joint Venture Company
for a period of 15 years, which could be extended by another
c period of 10 years on conditions to be mutually agreed between
the Petitioner and the Respondent. The Joint Venture Company
was incorporated under the name and style of "Royale India Rail
Tours Ltd.".
3. Upon receiving the approval of the Indian Railways, the
0 Respondent executed a Memorandum of Understanding with
the Petitioner dated 10th July, 2008, wherein it was stated that
the Ministry of Railways had given the permission to the
Respondent to own and operate the Luxury Tourist Train for the
exclusive use of the Joint Venture Company for a period of 15
E years, which was renewable for a further period of 10 years.
The said Memorandum of Understanding also contained the
various terms and conditions on which the train was to be
operated. In terms of the Joint Venture Agreement and the
Memorandum of Understanding, a Service Agreement dated
F 5th March, 2010, was executed between the Joint Venture
Company and the Ninth Dimension Hotel and Resorts Pvt. Ltd.,
hereinafter referred to as "MAPPLE Hotels", for providing
hospitality services on board and their respective roles and
responsibilities were set out in the said agreement.
G
4. The Maharaja Express commenced operations on 20th
March, 2010, and completed 4 journeys in the inaugural runs
till 31st March, 2010, and 30 journeys between April, 2010, till
April, 2011.
H 5. Whilst the Joint Venture operations were being
COX & KINGS LTD. v. INDIAN RLY. CATERING & 25
TOURISM CORPORATION LTD. [ALTAMAS KABIR, J.]
conducted, certain disputes arose between the shareholders A
regarding the working of the Joint Venture Agreement and the
Memorandum of Understanding, which ultimately resulted in the
termination of the lease arrangement by the Respondent,
IRCTC, by its letter dated 12th August, 2011, on the grounds
indicated therein. B
6. On account of such termination of the lease agreement,
the Petitioner initiated a proceeding under Section 9 of the
Arbitration and Conciliation Act, 1996, under the Arbitration
Agreement contained in Article 30 of the Joint Venture C
Agreement, for staying the termination of the lease agreement
and also to allow the arrangements to continue till the month of
April, 2012, subject to such terms and conditions as may be
imposed by the Court.
7. As has been submitted by Mr. Mukul Rohatgi, learned D
Senior Advocate, appearing for the Petitioner, what was of
utmost importance and concern to the Petitioner was not only
the huge investment made by the Petitioner in the project, but
the loss of goodwill and reputation in the eyes of its clients, who
were mainly from foreign countries. Discontinuance of operation E
would also besmirch the reputation of the Indian Government.
8. One of the other concerns of the Petitioner was that it
had been looking after the marketing and the bookings
internationally and within India and such bookings had been F
made much in advance. It was the case of the Petitioner that
the Joint Venture Company had received and was holding
approximately 400 bookings up to December, 2011 and such
bookings had been made by various international travel
companies.
G
9. The prayer for interim directions was contested by the
Respondent on several grounds. One of the grounds taken was
that by making relief on the basis of the Joint Venture
Agreement, the Petitioner was trying to get a lease in favour
of the Joint Venture Company, which was neither a party to the H
26 SUPREME COURT REPORTS [2012] 7 S.C.R.
A proceedings nor to the Agreement. It was further contended that,
in fact, the lease was never executed in favour of the Joint
Venture Company and the rights of the Petitioner could not go
beyond what had been laid down in the Articles of Association
of the Joint Venture Company. It was also urged that since the
B relationship between the Joint Venture Company and the
Respondent had been terminated, the Petitioner was trying to
create a right in its favour for operating the train, which was
never in its individual possession. It was urged that such a
prayer was not maintainable and it was not open to the
c Petitioner to claim any relief in relation to the train, which was
the subject matter of the termination letters issued by the
Respondent to the Joint Venture Company, in its capacity as
owner of the train. Noting the interest of the parties and keeping
in mind the fact that advance bookings had been made, the
learned Single Judge of the Delhi High Court, who heard the
0
Application under Section 9 of the Arbitration and Conciliation
Act, 1996, came to the conclusion that, although, in terms of
the Joint Venture Agreement in which there was a separate
provision for arbitration, the arbitral dispute: would have to be
E confined to the disputes between the parties to the Agreement,
under the wider connotation of the Agreement between the
Respondent and the Joint Venture Company, certain interim
orders were required to be made. More so, when the main
grievance of the Respondent against the Petitioner and the
Joint Venture Company was in respect of inflated bills raised
F by the Petitioner and non-payment of the amounts payable in
terms of the Agreement. In such circumstances, the learned
Single Judge found it fit to appoint a Receiver, as an interim
measure, in the public interest, to prevent discontinuation of the
running of the train for which bookings had already been made.
G The learned Judge appointed one Shri Sudhir Nandrajog, a
Senior Advocate of the Delhi High Court, as Receiver, and
disposed of the Section 9 application, inter alia, by directing
that the train would continue to be run under the supervision of
the learned Receiver for the period commencing from 14th
H September, 2011, uptil 31st December, 2011, which was the
COX & KINGS LTD. v. INDIAN RLY. CATERING & 27
TOURISM CORPORATION LTD. [ALTAMAS KABIR, J.]
major period for which the bookings had been effected, as per A
the arrangement which was continuing during the earlier
season. Various other directions were given to enable the
learned Receiver to operate the Maharaja Express and for
maintenance of accounts. The parties were also granted leave
to approach the Court or Arbitrator (if appointed) for B
modification of the order in case such need arose.
10. In addition to the above, the parties were also given
liberty to take necessary steps to have their disputes resolved
by the appointment of an Arbitral Tribunal which would be at C
liberty to decide the disputes without being influenced by the
order passed on the application under Section 9 of the 1996
Act. The rights and contentions of both sides were also kept
open for submission before the Arbitral Tribunal, if appointed.
11. The order of the learned Single Judge was challenged D
by IRCTC Ltd. by way of FAO(OS)Nos.433-35 of 2011.
12. The submissions made before the learned Single
Judge were reiterated on behalf of both the parties before the
Division Bench, but a new dimension was attempted to be E
added to the submissions advanced on behalf of the Petitioner,
Mis Cox & Kings India Ltd. An attempt was made to make out
a case that the Joint Venture Company was akin to a
partnership and the train in question was partnership property.
The Division Bench took note of the fact that the total cost of
the train was Rs.49.5 crores, which had been borne by IRCTC
F
and was even recorded in Article 6 of the Agreement. Apart
from the above, not only the shell train, but even the cost of the
interior, fittings and furnishing was borne by IRCTC. The
Division Bench also noted that if the train was to be regarded
as a Joint Venture property, there was no reason to provide G
for leasing of the train by IRCTC to the Joint Venture Company.
13. The Division Bench, however, was disinclined to
continue the arrangement, as directed by the learned Single
Judge, and accepted the submissions made on behalf of the H
28 SUPREME COURT REPORTS [2012) 7 S.C.R.
A IRCTC that the mandatory injunction which had been passed,
would have the effect of creating an Agreement between the
Joint Venture Company and IRCTC in relation to the train, which
would be influenced even though the Joint Venture Company
was not a party to the proceedings. However, keeping in mind
B the prestige of the country in regard to the running of the
Maharaja Express which had earned worldwide fame, the
Division Bench felt that since the Court was not in a position
to restore the terminated arrangement and direct the train to
be managed and run by M/s. Cox & Kings under the supervision
c of the Receiver, the public interest could be subserved if the
Maharaja Express continued to be operated even by the
IRCTC. Also taking into account the factor relating to the
bookings which had already been made in advance, the
Division Bench accepted the suggestions made by IRCTC to
honour the bookings, without prejudice to the rights and
0
contentions of the parties, as extracted hereinbelow :
"a) The train has to be run by the owner/respondent. All
the facility material including crockery, furnish-ings
etc. which are in custody of the petitioner should be
E handed over to respondent for executing this facility
arrangement.
b) All revenues arising therefrom without any
deductions earned either by the petitioner or
F respondent may be deposited in the separate
account from which expenditure will be funded.
c) All the bookings may be allowed to be transferred
to the respondents for honouring.
G d) All the on board or off board expenses and railway
payments may be allowed to be charged to this
account. In this way, the amount will be sufficient to
cover the expenses and there will be no need for
further loans.
H
COX & KINGS LTD. v. INDIAN RLY. CATERING & 29
TOURISM CORPORATION LTD. [ALTAMAS KABIR, J.]
e) The existing service providers may be retained." A
14. The Division Bench also directed that while running the
train, the IRCTC would remain bound by the aforesaid
suggestions. Whatever bookings had been made till then could
be transferred by M/s. Cox & Kings to IRCTC. The Division
8
Bench accordingly set aside the auangements made by the
learned Single and allowed the appeal preferred by the
Respondent herein.
15. It is against the said judgment and order passed by
the Division Bench of the Delhi High Court on 6th January, 2012 C
in FAO(OS)Nos.433-35 of 2011, that the present Special Leave
Petitions have been filed by M/s. Cox & Kings India Ltd.
16. Appearing for the Petitioner Company, Mr. Mukul
Rohatgi, learned Senior Advocate, submitted that the primary
reason for filing of the writ petition was to protect and save the D
image ;md goodwill of the Petitioner Company in the field of
global tourism. Mr. Rohtagi submitted. that it is in that context
that a prayer had been made on behalf of the Petitioner
Company for stay of operation of the termination of the Lease
Arrangement by the Respondent IRCTC by its letter dated 12th E
August, 2012. Mr. Rohatgi submitted that almost the entire
expenses for commencing operations in respect of the
Maharaja Express had been borne by the Petitioner Company
in different forms, and in view of the promises contained in the
Memorandum of Understanding and the Agreement executed F
between the Petitioner Company and the Joint Venture
Company, the termination of the Lease Arrangement was not
warranted.
17. Mr. Rohatgi urged that it had been agreed by both the G
parties in the said Memorandum of Understanding and the Joint
Venture Agreement and other supporting documents that the
lease of the train by IRCTC to the Joint Venture Company was
for a minimum period of 15 years from the date of the first
commercial run of the train and in lieu whereof 50% cost of the
H
30 SUPREME COURT REPORTS [2012] 7 S.C.R.
A train had been paid by way of advance lease charges which
were to be adjusted over a period of 15 years from the date of
the first commercial run of the train. Mr. Rohatgi urged that the
said amount had been paid by the Petitioner to the IRCTC
through the Joint Venture Company. It was on account of the
B termination letters dated 12th August, 2011, issued by IRCTC
that the Petitioner Company was compelled to initiate
proceedings before the High Court under Section 9 of the
Arbitration and Conciliation Act, 1996. Mr. Rohatgi submitted
that the relief claimed in the said application was that the
c Maharaja Express should be operated only through the Joint
Venture Company and that the Respondent IRCTC should be
restrained from using the train for any purpose other than for
the exclusive use of the Joint Venture Company. Mr. Rohatgi
also reiterated the fact that in order to safeguard the interest
0 of the parties concerned, the learned Single Judge had
appointed a Receiver to oversee the function and operations
of the train and granted injunction to preserve the existing
status-quo till the final hearing of the dispute.
18. The major thrust of Mr. Rohatgi's submissions was
E towards the aforesaid end and was indicative of the fact that
the running of the train was of primary importance and should
be allowed to continue as per the earlier undertaking, without
any disturbance, while the disputes before the learned
Arbitrator were finally disposed of.
F
19. On the other hand·, on behalf of the Respondent No.1
it was contended by the Learned Solicitor General that the
Special Leave Petitions had been filed by Mis. Cox & Kings.
Ltd. in respect of the train, which was owned by the Respondent
No.1, IRCTC. The said train had been converted into a luxury
G train and was being operated on a seasonal basis between the
months of September to April by the Joint Venture Company.
However, the IRCTC had no· option but to terminate the
arrangement made with the Joint Venture Company to operate
the luxury train on account of various reasons and, in particular,
H on account of non-payment of the dues of IRCTC. The learned
COX & KINGS LTD. v. INDIAN RLY. CATERING & 31
TOURISM CORPORATION LTD. [ALTAMAS KABIR, J.]
Solicitor General submitted that the letter terminating the Joint A
Venture Agreement was the subject matter of the Section 9
Application before the learned Single Judge of the High Court,
who, by his order dated 6th September, 2011, allowed the
prayers made therein in part and issued a mandatory injunction
and also appointed a Receiver for operation of train between B
the months of September to December, 2011. However, the
train was never operated under the Receiver on account of the
interim orders passed in the appeal on 9th September, 2011.
20. The learned Solicitor General reiterated the fact that
on 6th January, 2012, the Division Bench set aside the order C
passed by the learned Single Judge which was, in any event,
to operate only till 31st December, 2011.
21. The learned Solicitor General urged that there was no
ambiguity regarding the ownership of the train and it had been D
clearly understood by all concerned that it was IRCTC which
was to be the owner of the train and that the Joint Venture
Company was to be formed for management and operation of
the train. It had also been made clear that IRCTC's association
with other agencies was for the purpose of management of the E
train only.
22. It is evident from the submissions made on behalf of
the respective parties that the arrangement between the
Respondent No.1, IRCTC, was with the Petitioner Company
and, although, it was the intention of the parties by virtue of the F
Joint Venture Agreement that the luxury train, belonging to the
Respondent No.1, was to be operated by the Joint Venture
Company, at least for a minimum period of 15 years, what
ultimately transpired was the termination of the Agreement by
the Respondent No.1 in favour of the Joint Venture Company. G
As pointed out by the Division Bench of the High Court, the
Petitioner was not entitled to question such termination as by
itself it had no existence as far as the running of the train was
concerned and it was not a party to the proceedings. In fact,
what the Petitioner has attempted to do in these proceedings H
32 SUPREME COURT REPORTS [2012] 7 S.C.R.
A is to either restore the Lease Agreement, which had been
terminated, or to create a fresh Agreement to enable the
Petitioner to operate the luxury train indefinitely, till a decision
was arrived at in Section 9 Application.
23. It is no doubt true that the Petitioner has invested large
B sums of money in the project, but that cannot entitle it to pray
for and obtain a mandatory order of injunction to operate the
train once the lease agreement/arrangement had been
terminated. We are also unable to accept Mr. Rohatgi's
submission that the Joint Venture Agreement was akin to a
C partnership. Such submission had been rightly rejected by the
Division Bench. As rightly pointed out by the Division Bench of
the High Court, the Petitioner's remedy, if any, would lie in an
action for damages against IRCTC for breach of any of the
terms and conditions of the Joint Venture Agreement and the
D Memorandum of Understanding.
24. Taking into consideration the totality of the
circumstances, we are inclined to agree with the suggestions
which had been made by IRCTC before the Division Bench of
E the High Court regarding the operation of the train by IRCTC,
with liberty to the parties to appoint an Arbitral Tribunal to settle
their disputes. We, therefore, dismiss the Special Leave
Petitions, but make it clear that if an Arbitral Tribunal is
appointed, the aforesaid arrangement will be subject to the
decision of the Arbitral Tribunal. We also make it clear that the
F observations made by the learned Single Judge, the Division
Bench of the High Court and by us, shall not, in any way,
influence the outcome of the arbitral proceedings, if resorted
to by the parties.
G 25. Having regard to the nature of the facts of the case,
the parties shall bear their own costs. ·
26. In view of the above, no order is required to be passed
on the Contempt Petitions and the same are also dismissed.
H B.B.B. SLP & Contempt Petitions dismissed.
Search Indian case law
Ask in plain English, not just keywords. 25,000 AI words free, no card.