Created byFuzzy Cloud

Supreme Court of India

DELHI DEVELOPMENT AUTHORITYversusRAJAN SOOD & ORS.

Citation
2022 INSC 362
Decided
29 March 2022
Disposal
Appeal(s) allowed

Holding

The Supreme Court held that the acquisition proceedings have not lapsed under section 24(2) of the 2013 Act because possession was taken and the compensation, though deposited, was not paid, and the period of the stay order is excluded from the five‑year computation, thereby overturning the High Court's declaration of lapse.

Summary

The Delhi Development Authority (DDA) and the Government of NCT of Delhi appealed a Delhi High Court order that had declared the land acquisition proceedings under the Land Acquisition Act, 1894 as deemed to have lapsed under section 24(2) of the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013. The original writ petitioners, Rajan Sood and others, argued that they remained in possession of the land and had not received compensation, relying on the Pune Municipal Corporation decision. The DDA contended that possession had been taken on 23 September 1986, compensation of Rs.2 crore had been deposited, and that the Pune Municipal case had been overruled by the Indore Development Authority judgment. The Supreme Court examined the interpretation of section 24(2), the effect of a stay order, and the meaning of "possession" and "paid" under the 2013 Act, adopting the reasoning of the Indore Development Authority case. It held that the acquisition proceedings had not lapsed and set aside the High Court judgment. Consequently, the appeals were allowed and the order declaring lapse was quashed.

Issues considered

  • Whether the acquisition proceedings under the Land Acquisition Act, 1894 are deemed to have lapsed under section 24(2) of the 2013 Act when possession was taken but compensation was not paid.
  • Whether the High Court's reliance on the Pune Municipal Corporation decision is valid in view of its overruling by the Indore Development Authority judgment.
  • Whether the period of a court-ordered stay should be excluded from the five‑year period contemplated in section 24(2).
  • Interpretation of the terms "possession" and "paid" in section 24(2) of the 2013 Act.

Legislation cited

Subjects

Land acquisitionSection 24 lapseCompensationPossessionStay orderInterpretation of statutory provisionsOverruling precedentRight to Fair Compensation Act

Judgment

1060                     [2022] REPORTS
                SUPREME COURT   14 S.C.R. 1060              [2022] 14 S.C.R.


 A                  DELHI DEVELOPMENT AUTHORITY
                                         v.
                             RAJAN SOOD & ORS.
                          (Civil Appeal No. 1927 of 2022)
 B                               MARCH 29, 2022
                [M. R. SHAH AND B. V. NAGARATHNA, JJ.]
              Right to Fair Compensation and Transparency in Land
       Acquisition, Rehabilitation and Resettlement Act, 2013 – s.24(2) –
       Land Acquisition Act, 1894 – s.48 – High Court relying on the
 C
       decision in Pune Municipal Corporation case allowed the writ petition
       filed by Respondent No.1 and 2 original writ petitioners and declared
       that the acquisition proceedings initiated under the 1894 Act w.r.t
       the subject lands are deemed to have lapsed u/s.24(2) – On appeal,
       held: The decision in Pune Municipal Corporation case has been
 D     overruled by the decision of Constitution bench in Indore
       Development Authority case – Further, the High Court while passing
       the impugned judgment observed that the possession of the land in
       question continued with the original writ petitioners and that the
       compensation was neither paid nor even tendered – However, it
       was the specific case on behalf of the authority that the possession
 E
       of the land in question was already taken over on 23.09.1986 and
       even the compensation amount of Rs.2.00 crores was deposited with
       the land and building department – Considering the decision in
       case of Indore Development Authority it cannot be said that the land
       acquisition proceedings are deemed to have lapsed u/sub-section(2)
 F     of s.24 – Also, at the time when the Act, 2013 came into force there
       was a stay granted by the High Court vide order dated 09.11.2011
       in writ petition No.7714/2011 restraining the authority taking any
       coercive action in respect of the land in question – Thus, the
       impugned judgment passed by the High Court declaring that the
       land acquisition proceedings are deemed to have lapsed u/sub-
 G
       section (2) of s.24 of the 2013 Act, is unsustainable and is set aside.
             Indore Development Authority v. Manoharlal and Ors.
             (2020) 8 SCC 129 : [2020] 3 SCR 1 – followed.


 H
                                        1060
             DELHI DEVELOPMENT AUTHORITY v.                                     1061
                    RAJAN SOOD & ORS.

      Pune Municipal Corporation and Anr. v. Harakchand                         A
      Misirimal Solanki and Ors. (2014) 3 SCC 183 : [2014]
      1 SCR 783 – referred to.
                         Case Law Reference
[2014] 1 SCR 783                 referred to             Para 2
                                                                                B
[2020] 3 SCR 1                   followed                Para 3.4
      CIVIL APPELLATE JURISDICTION: Civil Appeal No. 1927
of 2022.
      From the Judgment and Order dated 30.08.2016 of the High Court
of Delhi at New Delhi in WP (C) No. 1034 of 2015.                               C
      With
      Civil Appeal No. 1928 of 2022
      Ms. Pinky Anand, Sr. Adv., Anshay Dhatwalia, Ms. Kumud
Nijhawan, Ashwani Kumar, Ms. Saudamini Sharma, Ms. Asees Jasmine                D
Kaur, Love Kumar Gupta, Angad Sandhu, Ms. Astha Saxena, Ms. Amita
Singh Kalkal, Ms. Astha Tyagi, Siddharth Raj Agarwal, Ms. Ramandeep
Kaur, Advs. for the appearing parties.
      The Judgment of the Court was delivered by
      M. R. SHAH, J.                                                            E

       1. Feeling aggrieved and dissatisfied with the impugned judgment
and order dated 30.08.2016 passed by the High Court of Delhi at New
Delhi in Writ Petition (C) No. 1034/2015, by which the High Court has
allowed the said writ petition preferred by the private respondents herein
– original writ petitioners and has declared that the acquisition proceedings   F
initiated under the Land Acquisition Act, 1894 (hereinafter referred to
as the Act, 1894) in respect of the subject lands are deemed to have
lapsed under sub-section (2) of section 24 of the Right to Fair
Compensation and Transparency in Land Acquisition, Rehabilitation and
Resettlement Act, 2013 (hereinafter referred to as the Act, 2013), Delhi        G
Development Authority (DDA) and Government of NCT of Delhi have
preferred the present appeals.
        2. Private respondent No.1 and 2 herein - original writ petitioners
filed the writ petition before the High Court for a declaration that the
acquisition proceedings initiated under the Act, 1894 in respect of the
                                                                                H
1062            SUPREME COURT REPORTS                         [2022] 14 S.C.R.


 A     subject lands are deemed to have lapsed under sub-section (2) of section
       24 of the Act, 2013. It was the case on behalf of the original writ
       petitioners before the High Court that as the possession of the land in
       question is with them and no compensation has been paid, the land
       acquisition proceedings are deemed to have lapsed. Heavy reliance was
       placed on the decision of this Court in the case of Pune Municipal
 B
       Corporation and Anr. Vs. Harakchand Misirimal Solanki and Ors,
       (2014) 3 SCC 183.
              2.1 The petition was opposed by the appellants herein and others.
       It was the specific case on behalf of the DDA that as such the
       compensation was tendered to one Shiv Kumar S/o Devi Chand. Relying
 C     upon the decision of this Court in the case of Pune Municipal
       Corporation (supra), the High Court, by the impugned judgment and
       order has allowed the said writ petition and has declared that the
       acquisition proceedings initiated under the Act, 1894 in respect of the
       subject lands are deemed to have lapsed under sub-section (2) of section
 D     24 of the Act, 2013.
             2.2 Feeling aggrieved and dissatisfied with the impugned judgment
       and order passed by the High Court, DDA and Government of NCT of
       Delhi have preferred the present appeals.
             3. Learned counsel appearing on behalf of the DDA has vehemently
 E     submitted that in the facts and circumstances of the case the High Court
       has materially erred in declaring that the acquisition proceedings have
       lapsed under sub-section (2) of section 24 of the Act, 2013.
             3.1 It is submitted on behalf of the DDA that in the present case
       as such the possession was already taken over by the Authority on
 F     23.09.1986 after following the due procedure as required and even a
       punchnama was also drawn, which was the requirement while taking
       over possession.
             3.2 It is urged that even the compensation was tendered to the
       recorded owner - Shri Shiv Kumar through notice under section 12(2) of
 G     the Act, 1894 but recorded owner never came forward to accept the
       same. It is submitted that therefore, the original writ petitioners cannot
       be permitted to take the benefit under sub-section (2) of section 24 of
       the Act, 2013.
              3.3 It is further submitted that even the amount of compensation
 H     of Rs.2.00 crores was deposited by the DDA with the Land and Building
             DELHI DEVELOPMENT AUTHORITY v.                                     1063
             RAJAN SOOD & ORS. [M. R. SHAH, J.]

Department towards compensation. Therefore, the original writ petitioners       A
are not entitled to the benefit of deemed lapse.
       3.4 It is further contended by learned counsel appearing on behalf
of the DDA and the Government of NCT of Delhi that as such the
original writ petitioners were not having any locus to file the writ petition
as their title to the property is shrouded with fraud and investigation is      B
pending with the Anti-Corruption Branch. It is submitted that as the
possession of the land in question was already taken over as far as back
on 23.09.1986 and even compensation of Rs.2.00 crores was deposited
with the Land and Building Department, in view of the subsequent decision
in the case of Indore Development Authority Vs. Manoharlal and
Ors., (2020) 8 SCC 129, it cannot be said the acquisition proceedings           C
have lapsed under sub-section (2) of section 24 of the Act, 2013.
      3.5 It is further submitted on behalf of the appellants that while
passing the impugned judgment and order, the High Court has relied on
the decision of this Court in the case of Pune Municipal Corporation
(supra). That, the said decision has been subsequently overruled by the         D
Constitution bench of this Court in the case of Indore Development
Authority (supra).
       3.6 In the alternative, it is submitted by the learned counsel
appearing on behalf of the respective appellants that assuming, without
admitting that the possession of the land in question remain with the           E
original writ petitioners, in that case also, as there was an order of stay
granted by the High Court in the year 2011, in the writ petition filed by
the original writ petitioners and the High Court granted the interim order
of taking no coercive action/order qua the land, therefore, in view of the
decision of this Court in the case of Indore Development Authority              F
(supra), the period under which the stay was operative is to be excluded.
Reliance is placed on para 366.8 of the decision of this Court in the case
of Indore Development Authority (supra).
      3.7 Making the above submission and relying upon the aforesaid
decision, it is prayed to allow the present appeals.                            G
       4. Both these appeals are vehemently opposed by Ms. Pinky
Anand, learned Senior Advocate appearing on behalf of the original writ
petitioners. Counter affidavits have been filed on behalf of private
respondent No.1 and 2 – original writ petitioners opposing the present
appeals.
                                                                                H
1064             SUPREME COURT REPORTS                           [2022] 14 S.C.R.


 A            4.1 It is vehemently submitted by Ms. Anand, learned Senior
       Advocate appearing on behalf of the original writ petitioners that as
       such there are specific findings recorded by the High Court that the
       original writ petitioners continue to be in physical possession and therefore,
       as neither the actual possession of land in question was taken over nor
       any compensation was paid and/or even tendered to the original writ
 B
       petitioners. It is rightly held that acquisition proceedings have lapsed.
               4.2 It is urged that in fact in the earlier order passed by the High
       Court on 09.11.2011 in writ petition No.7714/2011, the Division Bench
       directed the authority to consider their application under section 48 of
       the Act, 1894 and to decide it on merits. That as per section 48 of the
 C     Act, 1894 only in a case where possession of the land is not taken over
       by the acquiring authority, then only, the application under section 48 of
       the Act, 1894 would be maintainable. It is submitted therefore, when the
       Division Bench directed the authority to consider the application of the
       petitioners under section 48 of the Act, 1894 on merits, it is to be presumed
 D     that only original writ petitioners continue to remain possession. It is
       contended that the authority might have taken ex-parte possession on
       paper as alleged on 23.09.1986, however, the original writ petitioners
       remained in possession actually. It is further submitted by learned Senior
       Advocate appearing on behalf of the original writ petitioners that there
       is also a specific finding recorded by the High Court that the authorities
 E     have failed to prove that any amount of compensation was paid and/or
       tendered to the original writ petitioners or even deposited with the treasury.
       It is submitted that when the original writ petitioners remain in possession
       and neither the compensation was tendered nor it was paid, the twin
       conditions to declare the acquisition proceedings as having lapsed under
 F     sub-section (2) of section 24 of the Act, 2013 have been satisfied. It is
       therefore submitted that the High Court has not committed any error in
       declaring that the acquisition proceedings in respect of the subject lands
       are deemed to have lapsed under sub-section (2) of section 24 of the
       Act, 2013
 G           5. We have heard learned counsel appearing on behalf of the
       respective parties at length.
              6. By the impugned judgment and order the High Court has held
       and declared that the land acquisition proceedings in respect of the land
       in question are deemed to have lapsed under sub-section (2) of section
 H     24 of the Act, 2013. While holding and declaring so the High Court has
             DELHI DEVELOPMENT AUTHORITY v.                                  1065
             RAJAN SOOD & ORS. [M. R. SHAH, J.]

relied upon decision of this Court in the case of Pune Municipal             A
Corporation (supra). However, the said decision of this Court has been
subsequently overruled by the decision of this Court in the case of Indore
Development Authority (supra). In paragraph 365 to 366, this Court
in the case of Indore Development Authority (supra) has observed
and held as under: -
                                                                             B
      “365. Resultantly, the decision rendered in Pune Municipal
      Corpn. [Pune Municipal Corpn. v. Harakchand Misirimal
      Solanki, (2014) 3 SCC 183 : (2014) 2 SCC (Civ) 274] is hereby
      overruled and all other decisions in which Pune Municipal
      Corpn. [Pune Municipal Corpn. v. Harakchand Misirimal
      Solanki, (2014) 3 SCC 183 : (2014) 2 SCC (Civ) 274] has been           C
      followed, are also overruled. The decision in Sree Balaji Nagar
      Residential Assn. [Sree Balaji Nagar Residential Assn. v. State
      of T.N., (2015) 3 SCC 353 : (2015) 2 SCC (Civ) 298] cannot be
      said to be laying down good law, is overruled and other decisions
      following the same are also overruled. In Indore Development           D
      Authority v. Shailendra [Indore Development Authority v.
      Shailendra, (2018) 3 SCC 412 : (2018) 2 SCC (Civ) 426], the
      aspect with respect to the proviso to Section 24(2) and whether
      “or” has to be read as “nor” or as “and” was not placed for
      consideration. Therefore, that decision too cannot prevail, in the
      light of the discussion in the present judgment.                       E

      366. In view of the aforesaid discussion, we answer the questions
      as under:
      366.1. Under the provisions of Section 24(1)(a) in case the award
      is not made as on 1-1-2014, the date of commencement of the            F
      2013 Act, there is no lapse of proceedings. Compensation has to
      be determined under the provisions of the 2013 Act.
      366.2. In case the award has been passed within the window
      period of five years excluding the period covered by an interim
      order of the court, then proceedings shall continue as provided        G
      under Section 24(1)(b) of the 2013 Act under the 1894 Act as if it
      has not been repealed.
      366.3. The word “or” used in Section 24(2) between possession
      and compensation has to be read as “nor” or as “and”. The deemed
      lapse of land acquisition proceedings under Section 24(2) of the
                                                                             H
1066      SUPREME COURT REPORTS                          [2022] 14 S.C.R.


 A     2013 Act takes place where due to inaction of authorities for five
       years or more prior to commencement of the said Act, the
       possession of land has not been taken nor compensation has been
       paid. In other words, in case possession has been taken,
       compensation has not been paid then there is no lapse. Similarly,
       if compensation has been paid, possession has not been taken
 B
       then there is no lapse.
       366.4. The expression “paid” in the main part of Section 24(2) of
       the 2013 Act does not include a deposit of compensation in court.
       The consequence of non-deposit is provided in the proviso to
       Section 24(2) in case it has not been deposited with respect to
 C     majority of landholdings then all beneficiaries (landowners) as on
       the date of notification for land acquisition under Section 4 of the
       1894 Act shall be entitled to compensation in accordance with the
       provisions of the 2013 Act. In case the obligation under Section
       31 of the Land Acquisition Act, 1894 has not been fulfilled, interest
 D     under Section 34 of the said Act can be granted. Non-deposit of
       compensation (in court) does not result in the lapse of land
       acquisition proceedings. In case of non-deposit with respect to
       the majority of holdings for five years or more, compensation under
       the 2013 Act has to be paid to the “landowners” as on the date of
       notification for land acquisition under Section 4 of the 1894 Act.
 E
       366.5. In case a person has been tendered the compensation as
       provided under Section 31(1) of the 1894 Act, it is not open to him
       to claim that acquisition has lapsed under Section 24(2) due to
       non-payment or non-deposit of compensation in court. The
       obligation to pay is complete by tendering the amount under Section
 F     31(1). The landowners who had refused to accept compensation
       or who sought reference for higher compensation, cannot claim
       that the acquisition proceedings had lapsed under Section 24(2)
       of the 2013 Act.
       366.6. The proviso to Section 24(2) of the 2013 Act is to be treated
 G     as part of Section 24(2), not part of Section 24(1)(b).
       366.7. The mode of taking possession under the 1894 Act and as
       contemplated under Section 24(2) is by drawing of inquest report/
       memorandum. Once award has been passed on taking possession
       under Section 16 of the 1894 Act, the land vests in State there is
 H
             DELHI DEVELOPMENT AUTHORITY v.                                    1067
             RAJAN SOOD & ORS. [M. R. SHAH, J.]

      no divesting provided under Section 24(2) of the 2013 Act, as            A
      once possession has been taken there is no lapse under Section
      24(2).
      366.8. The provisions of Section 24(2) providing for a deemed
      lapse of proceedings are applicable in case authorities have failed
      due to their inaction to take possession and pay compensation for        B
      five years or more before the 2013 Act came into force, in a
      proceeding for land acquisition pending with the authority concerned
      as on 1-1-2014. The period of subsistence of interim orders passed
      by court has to be excluded in the computation of five years.
      366.9. Section 24(2) of the 2013 Act does not give rise to new           C
      cause of action to question the legality of concluded proceedings
      of land acquisition. Section 24 applies to a proceeding pending on
      the date of enforcement of the 2013 Act i.e. 1-1-2014. It does not
      revive stale and time-barred claims and does not reopen concluded
      proceedings nor allow landowners to question the legality of mode
      of taking possession to reopen proceedings or mode of deposit of         D
      compensation in the treasury instead of court to invalidate
      acquisition.”
       7. The High Court while passing the impugned judgment and order
has observed that the possession of the land in question continued with
the original writ petitioners and that the compensation was neither paid       E
nor even tendered to the original writ petitioners. However, by holding
that the original writ petitioners have continued to remain in possession,
the High Court has relied upon the earlier order dated 09.11.2011 passed
in writ petition No.7714/2011, by which the High Court directed the
authority to consider their application under section 48 of the Act, 1894      F
on merits. However, it was the specific case on behalf of the authority
before the learned Single Judge that the possession of the land in question
was already taken over on 23.09.1986 and even the compensation amount
of Rs.2.00 crores was deposited with the land and building department.
       7.1 It is the case on behalf of the original writ petitioners that a    G
purported letter dated 23.09.1986 allegedly taking symbolic possession
was never disclosed by appellants in the proceedings conducted before
the High Court on two separate occasions and the same has been filed
for the first time in the present proceedings. The aforesaid is not correct.
Even in the impugned order itself in paragraph 2, the High Court has
                                                                               H
1068             SUPREME COURT REPORTS                           [2022] 14 S.C.R.


 A     noted the submissions on behalf of the appellants to the effect that the
       possession was taken over on 23.09.1986. Therefore, it cannot be said
       such a plea is taken for the first time before this Court. It is the case on
       behalf of the original writ petitioners, relying upon the earlier order passed
       by the High Court dated 09.11.2011 in writ petition No.7714/2011 that,
       the original writ petitioners continue to be in possession and the actual
 B
       possession has never been taken over. However, it is required to be
       noted that even in the order dated 09.11.2011, there was no specific
       finding given by the High Court that the original writ petitioners are in
       possession of the land in question. On the contrary, it is observed that
       the authority to consider the application under section 48 of the Act,
 C     1894 on merits on the assumption of the possession being with the original
       writ petitioners. Therefore, while passing the order dated 09.11.2011
       also, the High Court assumed the original writ petitioners are in possession
       hence as such no specific finding was given to the effect that the original
       writ petitioners are in possession.
 D            7.2 It is next contented on behalf of the original writ petitioners
       that the alleged possession on 23.09.1986 is illegal and it was a paper
       possession. However, it is submitted on behalf of the appellants that
       possession of land in question was taken over by drawing the punchnama
       which can be said to be sufficient compliance of the requirement while
       taking possession. The High Court has also doubted the compensation
 E     being tendered as contended on behalf of the appellant.
               7.3 Be that as it may. Assuming for the sake of argument that the
       original writ petitioners are found to be in possession and the compensation
       was not tendered, in that case also as can be seen from the order passed
       by the High Court on 09.11.2011 in writ petition No.7714/2011, the
 F     authority was restrained from taking any coercive action in respect of
       the land in question. Therefore, in view of the subsequent decision of
       this Court in the case of Indore Development Authority (supra -
       paragraph 366.8), the period, during which the interim order is/was
       operative, has to be excluded in the computation of five years’ period. In
 G     the present case even, it is the contention on behalf of the original writ
       petitioners that the order of no coercive action was directed to be
       continued till the application under section 48 of the Act, 1894 was decided.
       It is the specific case on behalf of the original writ petitioners before this
       Court and even so stated in the written submissions that till date no
       decision is taken on the application under section 48 of the Act, 1894.
 H
              DELHI DEVELOPMENT AUTHORITY v.                                  1069
              RAJAN SOOD & ORS. [M. R. SHAH, J.]

Meaning thereby the direction/stay granted by the High Court while            A
passing the order dated 09.11.2011 in writ petition No.7714/2011
continued when the Act, 2013 came into force.
       7.4 In that view of the matter and considering the decision of this
Court in case of Indore Development Authority (supra), it cannot be
said that the land acquisition proceedings are deemed to have lapsed          B
under sub-section (2) of section 24 of the Act, 2013.
      8. Applying the law laid down by this Court in the case of Indore
Development Authority (supra), more particularly, paragraph 366, it
cannot be said that the land acquisition proceedings are deemed to have
lapsed.                                                                       C
       9. In view of the above and for the reasons stated above and on
the aforesaid ground alone that at the time when the Act, 2013 came
into force there was a stay granted by the High Court vide order dated
09.11.2011 in writ petition No.7714/2011 restraining the authority taking
any coercive action in respect of the land in question, the impugned          D
judgment and order passed by the High Court declaring that the land
acquisition proceedings are deemed to have lapsed under sub-section
(2) of section 24 of the Act, 2013, is unsustainable.
       10. In view of the above and for the reasons stated above, the
present appeals are allowed. The impugned judgment and order passed           E
by the High Court in Writ Petition (C) No.1043/2015 declaring that the
land acquisition proceedings under the Act, 1894 with respect to the land
in question are deemed to have lapsed under sub-section (2) of section
24 of the Act, 2013, is hereby quashed and set aside. The present appeals
are allowed to the aforesaid extent, accordingly. There shall be no order
as to costs.                                                                  F


Divya Pandey                                               Appeals allowed.
(Assisted by : Neha Sharma, LCRA)


                                                                              G




                                                                              H


Search Indian case law

Ask in plain English, not just keywords. 25,000 AI words free, no card.

Try "Land acquisition"Sign in to search

For a digitally signed copy suitable for filing, refer to the court's own website. Only the court can issue one.

DELHI DEVELOPMENT AUTHORITY versus RAJAN SOOD & ORS. — 2022 INSC 362 - Legal Desk AI