DURGA CHARAN RAUTRAYversusSTATE OF ORISSA & ANR.
- Citation
- 2011 INSC 779
- Decided
- 1 November 2011
- Disposal
- Appeal(s) allowed
- Bench
- RAJENDRA MAL LODHA
Holding
A contractual arbitration clause remains enforceable and a party may seek arbitration even after receiving payment on the final bill without objection.
Summary
Durga Charan Rautray, a contractor, completed a dam construction project for the State of Orissa but later claimed additional payments for price escalation, material supply, royalty refund and interest. The parties' contract contained an arbitration clause (clause 23) and the disputes were referred to an arbitral tribunal, which awarded the contractor in his favour. The State challenged the award by filing a Miscellaneous Case under Sections 30 and 33 of the Arbitration Act, 1940, but the Civil Judge dismissed it on limitation grounds and made the award "rule of court". The State appealed, and the High Court held that because the contractor had received payment on the final bill without objection, he could not invoke arbitration, thereby denying him the award. On further appeal, the Supreme Court held that the arbitration clause allowed the contractor to seek arbitration irrespective of receipt of payment, that the High Court’s view was contradictory, and that the award should stand. Consequently, the Supreme Court set aside the High Court judgment, upheld the Civil Judge’s order and allowed the appeal, directing the State to pay the awarded amount.
Issues considered
- Whether receipt of payment on preparation of the final bill, without raising objections, bars a contractor from invoking the arbitration clause in the contract.
- Whether the High Court erred in concluding that the contractor could not initiate arbitral proceedings after such payment.
- Whether the limitation defence raised by the contractor bars the State's Miscellaneous Case under Sections 30 and 33 of the Arbitration Act, 1940.
Legislation cited
- Arbitration Act, 1940s. 30, s. 33, s. 39
Subjects
Judgment
[2011] 13 (ADDL.) S.C.R. 16
A DURGA CHARAN RAUTRAY
v.
STATE OF ORISSA & ANR.
(Civil Appeal No. 1735 of 2006)
NOVEMBER 1, 2011
B
[R. M. LODHA AND JAGDISH SINGH KHEHAR, JJ.]
Arbitration Act, 1940 - Contractual agreement -
Disputes/claims raised by contractor-appellant - After receipt
C of payment on preparation of the final bill, without raising
objection - Redressal by way of arbitration - High Court
holding that the appellant having received payment after
preparation of final bill without raising objections, could not
have initiated arbitral proceedings - On appeal, held:
o Appellant despite having received payment after preparation
of final bill without raising objections, could seek redressal of
his disputes by way of arbitration in terms of the contractual
agreement - He could still raise his unsatisfied claims before
an arbitrator - Order referring the dispute raised by the
E appellant to the arbitral tribunal, having attained finality, the
respondents were precluded from asserting that the claims
raised by the appellant could not be adjudicated upon by way
of arbitration - Order passed by the High Court was
contradictory in terms - Once the High Court concluded that
F the Miscellaneous Case filed by the respondents raising
objections was barred by limitation, it was not open to the High
Court to consider one of the objections raised by the
respondents and to uphold the same, so as to disentitle the
appellant from reaping the fruits of the arbitral award - Thus,
order passed by the High Court is set aside and that of the
G civil judge making arbitral award rule of the court, is upheld.
Appellant was entrusted with a construction work by
respondent-State. Dispute arose between the parties and
were referred to an arbitral tribunal. The arbitral tribunal
H 16
DURGA CHARAN RAUTRAY v. STATE OF ORISSA & 17
ANR.
passed an award in favour of the appellant. The appellant A
filed an application to make the arbitral award, rule of the
court. The respondents filed objections under Sections
30 and 33 of the Arbitration Act, 1940 by filing
Miscellaneous Case. The Civil Judge dismissed the
Miscellaneous Case on the ground of limitation. The B
award was made rule of the court. Aggrieved, the
respondents filed an appeal before the High Court under
Section 39 of the Arbitration Act, 1940. The High Court
upheld the order of the Civil Judge on the issue of
limitation, however, held that the appellant could not c
obtain the benefits of the award rendered by the Arbitral
Tribunal in his favour since the appellant had received
payments on the preparation of final bill without raising
objections. Therefore, the appellant filed the instant
appeal. D
Allowing the appeal, the Court
HELD: 1.1 A perusal of clause 23 of the contractual
agreement leaves no room for any doubt that the
appellant could claim arbitration on account of disputes E
arising from the contract "except where otherwise
provided". Clause 23 includes within the purview of
arbitration, disputes whether arising during the progress
of the work or after the completion or abandonment
thereof. There is no restraint whatsoever expressed in F
clause 23, which would deprive the appellant from
seeking redressal by way of arbitration, merely because
he had received payments after the preparation of the
final bill, without raising any objections. Accordingly,
even after the receipt of payment on the preparation of G
the final bill, it was open to the appellant to seek redressal
of his disputes.by way of arbitration, even though he had
not raised any objections. [Para 8] [23-G-H; 24-A-C]
Bharat Coking Goa Ltd. v. Annapurna Construction
H
18 SUPREME COURT REPORTS [2011] 13 (ADDL.) S.C.R.
A (2003) 8 sec 154: 2003 (3) Suppl. SCR 122 - relied on.
1.2 Despite receipt of payment on the preparation of
the final bill, it was still open to the appellant to raise his
unsatisfied claims before an arbitrator, under the contract
B agreement. It was no longer open to the respondents to
contest the claim of the appellant on the instant issue
after the appellant had obtained the court order dated
15.05.1981 which referred the disputes raised by the
appellant to an arbitral tribunal. The court order dated
c 15.05.1981 referring the disputes raised by the appellant
to arbitration, attained finality inasmuch as the same
remained uncontested at the hands of the respondents.
The respondents were, thereafter precluded from
asserting that the claims raised by the appellant could not
0 be adjudicated upon by way of arbitration. Once the
disputes raised by the appellant were referred for
arbitration and the rival parties submitted to the arbitration
proceedings without any objection, it is no longer open
to either of them to contend that arbitral proceedings
E were not maintainable. Further, the order passed by the
High Court is contradictory in terms. Once the High Court
had concluded, that the Miscellaneous Case filed by the
respondents raising objections was barred by limitation,
it was not open to the High Court to consider one of the
objections raised by the respondents and to uphold the
F same, so as to disentitle the appellant from reaping the
fruits of the arbitral award. Once the plea of limitation had
been upheld, the objection(s) filed by the respondents,
irrespective of the merit{s) thereof were liable to be
rejected. [Para 8] [24-E-H; 25-A-D]
G
1.3 The High Court erred in concluding that the
appellant having received payment after preparation of
the final bill, without having raised any objection, could
not have initiated arbitral proceedings. The judgment
H
DURGA CHARAN RAUTRAY v. STATE OF ORISSA & 19
ANR.
rendered by the High Court is set aside. The order passed A
by the Civil Judge, Senior Division is upheld. [Para 9] [25-
E-F]
Case Law Reference:
2003 (3) Suppl. SCR 122 relied on Para 8 B
CIVIL APPELLATE JURISDICTION : Civil Appeal No.
1735 of 2006.
From the Judgment & Order dated 22.12.2003 of the High
Court of Orissa at Cuttack in ARBA No. 14 of 2003. C
Ginny J. Rautray, Praveena Gautam for the Appellant.
Shibashish Misra for the Respondents.
The Judgment of the Court was delivered by D
JAGDISH SINGH KHEHAR, J. 1. The appellant was
entrusted with the construction of balance work of earth dam
in connection with the Kharkhai Irrigation Project upto RL
316.50 on 31.12.1975. The estimated cost of the said balance E
work was Rs.13,78,810/-. As per the contract agreement, the
work was to commence on 1.1.1976 and was to be completed
on or before 31.7.1976. For some reasons including change
in design, the work could not be completed within the
prescribed time. The appellant eventually completed the F
assigned work in July, 1978. This deiay in completion of work,
according to the appellant, resulted in financial loss to the
appellant. In addition to the aforesaid, the appellant had some
other grievances as well. Illustratively, the appellant sought
payment towards some additional work e~ecuted by him, and G
also, refund of royalty deducted on account of the supply of
"morum". All these disputes were raised by the appellant, with
the concerned respondent(s). The respondent(s) chose not to
entertain the claims raised by the appellant. In fact, all
communications addressed by the appellant to the respondents
H
20 SUPREME COURT REPORTS [2011] 13 (ADDL.) S.C.R.
A remained unanswered. The appellant then sought reference of
his claims for adjudication before an arbitrator. This request of
the appellant was also not heeded to. The appellant thereafter
obtained a Court order dated 15.5.1981, whereby the disputes
raised by the appellant were referred to an arbitral tribunal. The
B arbitral tribunal examined nine items of claim raised by the
appellant.
2. The award rendered by the arbitral tribunal dated
15.9.1998, adjudicated claim item nos. 4, 5, 6 and 9, in favour
C of the appellant. In so far as claim item no.4 is concerned, the
appellant had demanded an additional amount of Rs.2 lakhs
on account of price escalation. This claim was based on the
fact, that after the work was assigned to him, the State
Government had revised minimum wages of labour, and
increased the same by 16%. The appellant, accordingly,
D claimed extra payment of 16% over the gross amount paid in
the final bill. The arbitral tribunal neld the appellant entitled to
Rs.24,380/- towards price escalation. In claim item no.5, the
appellant claimed Rs.5,51, 173/- towards cost of "morum"
supplied, but for which no payment had been released. In this
E behalf, the appellant claimed carriage of 47,106 cubic meters
with 15 kilometers lead, at the rate of Rs.21.35 per cubic meter.
While adjudicating the instant claim, the arbitral tribunal found
the appellant entitled to the difference between the cost of
supply of "morum", as against the cost of supply of "earth". In
F respect of claim item no.5, the appellant was held entitled to a
sum of Rs.78,667/-. In claim item no.6, the appellant demanded
a refund of Rs.20,727/- deducted towards royalty from his bills.
The aforesaid royalty was allegedly charged on the "morum"
supplied by the appellant. The appellant was held entitled to
G refund of the entire sum of Rs.20,727/- deducted from his bills
towards royalty. In so far as claim item no.9 is concerned, the
appellant claimed interest at the rate of 18% per annum on the
principal claim amount, from the due date till the date of final
payment. The arbitral tribunal held the appellant entitled to
H interest at the rate of 10% per annum on the principal awarded
DURGA CHARAN RAUTRAY v. STATE OF ORISSA & 21
ANR. [JAGDISH SINGH KHEHAR, J.]
amount of Rs.1,23,724/-, with effect from 19.8.1981 (i.e., the A
date with effect from which the Interest Act, 1978 came into
force) till 5.4.1992. Calculated in the aforesaid terms, the
arbitral tribunal awarded interest of Rs.1,31,544/- to the
appellant.
8
3. Notice to make the arbitral award dated 15.9.1998 "rule
of the court" was issued on 22.2.1999. In March, 1999, the
respondents were served with the said notice. On 21.12.1999,
the Government Pleader entered appearance on behalf of the
respondents, and sought time to file objections. Objections on C
behalf of the respondents were filed before the Civil Judge,
Senior Division, Bhubaneswar on 6.3.2000. To contest the
arbitral award dated 15.9.1998, the respondents filed
objections under sections 30 and 33 of the Arbitration Act, 1940
by filing a "Miscellaneous Case". It would be relevant to mention
that section 30 aforesaid, postulates the grounds for setting D
aside an award, whereas, section 33 lays down the course to
be adopted for challenging, inter alia, the validity of an arbitral
award.
4. The "Miscellaneous Case", filed by the respondents was E
contested by the appellant inter alia by raising a preliminary
objection. It was sought to be asserted, that the "Miscellaneous
Case" was barred by limitation. The "Miscellaneous Case" filed
by the respondents was rejected by the Civil Judge, Senior
Division, Bhubaneshwar by accepting the plea of limitation F
raised by the appellant. The suit filed by the appellant was
decreed on 30.4.2002. The award of the arbitral tribunal dated
15.9.1998 was made "rule of the court". The respondents were
directed to pay the awarded amount to the appellant, failing
which, the appellant was granted liberty to recover the same
through Court. G
5. Dissatisfied with the order passed by the Civil Judge
Senior Division, Bhubaneshwar, the respondents preferred a~
app:al ?efore the High Court of Orissa under section 39 of the
Arb1trat1on Act, 1940. In the said appeal, the respondents H
22 SUPREME COURT REPORTS [2011] 13 (ADDL.) S.C.R.
A raised two contentions. Firstly ii was sought to be asserted, that
the objections filed by the respondents through the
"Miscellaneous Case" filed under sections 30 and 33 of the
Arbitration Act, 1940, were wrongly rejected by the Civil Judge,
Senior Division, Bhubaneshwar, on the ground of limitation.
s Secondly it was asserted, that the controversy raised by the
appellant could not have been referred for adjudication by way
of arbitration, after the appellant had received the final bill
without raising any objection.
6. The determination by the Civil Judge, Senior Division,
C Bhubaneshwar, on the issue of limitation was upheld by the High
Court. Yet the contention advanced at the hands of the
respondents, that ii was not open to the appellant to have sought
adjudication of his claims, by way of arbitration, after the
appellant had received payments on the preparation of the final
D bill without raising any objections, was accepted. In sum and
substance, therefore, by its order dated 22.12.2003 it was
concluded by the High Court, that the appellant could not reap
the benefits of the award rendered by the arbitral tribunal in his
favour on 15.9.1998.
E
7. Dissatisfied with the judgment rendered by the High
Court dated 22.12.2003, the appellant filed a petition for special
leave to appeal bearing no.12183 of 2004. Leave was granted
on 20.3.2006. Consequently, the matter came to be
F renumbered as civil appeal no.1735 of 2006.
8. Since the plea of limitation had been decided in favour
of the appellant and against the respondents, the only question
to be adjudicated upon, in the present appeal filed by the
appellant, is, whether the disputes/claims raised by the
G appellant could have been referred for arbitration, after the
appellant had received payment after the preparation of the final
bill, without raising any objections. The answer to the instant
query must necessarily flow from the relevant clause of the
agreement which entitled the appellant to seek redressal of
H disputes through arbitration, as it is the arbitration clause alone
DURGA CHARAN RAUTRAY v. STATE OF ORISSA & 23
ANR. [JAGDISH SINGH KHEHAR, J.)
which defines the parameters of the disputes which rival parties A
can raise for adjudication before an arbitrator (or arbitral
tribunal). In so far as the instant aspect of the matter is
concerned, clause 23 of the agreement dated 31.12.1975 is
relevant. The same is being extracted hereinbelow:
B
"Clause 23 - Except where otherwise provided in the
contract all questions and disputes relating to the meaning
of the specifications, designs, drawings and instructions
hereinbefore mentioned and as to the quality of
workmanship of materials used on the work, or as to any
other questions, claim, right matter, or thing whatsoever, C
if any way arising out of, or relating to the contract, designs,
drawings, specifications, estimates instructions, orders or
these conditions, or otherwise concerning the work or the
execution, or failure to execute the same, whether arising
during the progress of the work, or after the completion or D
abandonment thereof shall be referred to the sole
arbitration of a Superintending Engineer of the State Public
Works Department unconnected with the work at any stage
nominated by the concerned Chief Engineer. If there be
no such Superintending Engineer, it should be referred to E
the sole arbitration of the Chief Engineer concerned. It will
be no objection to any such appointment that the arbitrator
so appointed is a Government Servant. The award of the
Arbitrator so appointed shall be final, conclusive and
binding on all parties to these contract." F
A perusal of clause 23 of the contractual agreement extracted
above, leaves no room for any doubt that the appellant could
claim arbitration on account of disputes arising from the contract
"except where otherwise provided". It is not the case of the G
respondents, that the appellant was precluded by any clause
in the contractual agreement from seeking settlement of claims
raised by the appellant (which have been allowed in favour of
the appellant by the arbitral tribunal). Clause 23 includes within
the purview of arbitration, disputes whether arising during the
H
24 SUPREME COURT REPORTS [2011] 13 (ADDL.) S.C.R.
A progress of the work or after the completion or abandonment
thereof. There is no restraint whatsoever expressed in clause
23, which would deprive the appellant from seeking redressal
by way of arbitration, merely because he had received
payments after the preparation of the final bill, without raising
8 any objections. Accordingly, we are of the view, that even after
the receipt of payment on the preparation of the final bill, it was
open to the appellant to seek redressal of his disputes by way
of arbitration, even though he had not raised any objections.
Secondly, in so far as the instant aspect of the matter is
c concerned, the issue in hand stands concluded by this Court
in Bharat Coking Coal Ltd. v. Annapurna Construction (2003)
8 sec 154 wherein it has been held as under:
"Only because the respondent has accepted the final bill,
the same would not mean that it was not entitled to raise
D any claim. It is not the case of the appellant that while
accepting the final bill, the respondent had unequivocally
stated that he would not raise any further claim. In absence
of such a declaration, the respondent cannot be held to be
estopped or precluded from raising any claim ... ".
E
In the instant case also the appellant, while accepting payment
on the preparation of the final bill, did not undertake that he
would not raise any further claims. As such, we are satisfied
that the judgment rendered in Bharat Coking Coal Ltd., case
F (supra) leads to the irresistible conclusion, that despite receipt
of payment on the preparation of the final bill, it was still open
to the appellant to raise his unsatisfied claims before an
arbitrator, under the contract agreement. Thirdly, it was no
longer open to the respondents to contest the claim of the
G appellant on the instant issue after the appellant had obtained
the court order dated 15.5.1981 which referred the disputes
raised by the appellant to an arbitral tribunal. The Court order
dated 15.5.1981 referring the disputes raised by the appellant
to arbitration, attained finality inasmuch as the same remained
H uncontested at the hands of the respondents. The respondents
DURGA CHARAN RAUTRAY v. STATE OF ORISSA & 25
ANR. [JAGDISH SINGH KHEHAR, J.]
were, thereafter precluded from asserting that the claims raised A
by the appellant could not be adjudicated upon by way of
arbitration. Once the disputes raised by the appellant were
referred for arbitrat:on and the rival part:es submitted to the
arbitration proceedings without any objection, it is no longer
open to either of them to contend that arbitral proceedings were B
not maintainable. And fourthly, the order passed by the High
Court is contradictory in terms. Once the High Court had
concluded, that the Miscellaneous Case filed by the
respondents raising objections was barred by limitation, it was
not open to the High Court to consider one of the objections c
raised by the respondents and to uphold the same, so as to
disentitle the appellant from reaping the fruits of the arbitral
award. In other words, once the plea of limitation had been
upheld, the objection(s) filed by the respondents, irrespective
of the merit(s) thereof were liable to be rejected. 0
9. For the reasons recorded hereinabove, we are of the
view that the High Court erred in concluding that the appellant
having received payment after preparation of the final bill,
without having raised any objection, could not have initiated
arbitral proceedings. The judgment rendered by the High Court E
dated 22.12.2003 is, accordingly, set aside. The order passed
by the Civil Judge, Senior Division, Bhubaneshwar dated
30.4.2002 is upheld. The instant appeal is accordingly allowed.
The respondents are directed to pay the appellant the awarded
amount, failing which, the appellant shall be at liberty to recover F
the same through Court.
10. There will be no order as to costs.
N.J. Appeal allowed.
Search Indian case law
Ask in plain English, not just keywords. 25,000 AI words free, no card.