ESSCO FABS PVT. LTD. & ANR.versusSTATE OF HARYANA & ANR.
- Citation
- 2008 INSC 1273
- Decided
- 7 November 2008
- Disposal
- Disposed off
- Bench
- C K THAKKER
Holding
The Court held that the inquiry and hearing under Section 5A cannot be dispensed with in urgency cases unless the Government expressly declares under Section 17(4); the State’s failure to do so rendered the acquisition proceedings invalid.
Summary
The State of Haryana re‑issued a preliminary notification under the Land Acquisition Act, 1894 in 2001 for a link‑road and invoked the urgency clause of Section 17, dispensing with the inquiry and hearing of objections under Section 5A before issuing a final notification under Section 6. Essco Fabs Pvt. Ltd. and a teachers' cooperative society challenged the acquisition, arguing that no genuine urgency existed and that the statutory requirement of a Section 17(4) declaration to dispense with Section 5A was not complied with. The Supreme Court held that even where urgency or unforeseen emergency is claimed, the procedure of Section 5A must be followed unless the Government expressly invokes Section 17(4); the State had not done so. Consequently, the actions of dispensing with the inquiry and the final notification were ultra vires and were quashed. The appeals were allowed and the contempt petition was disposed.
Issues considered
- Whether the State could dispense with the inquiry and hearing of objections under Section 5A of the Land Acquisition Act by invoking the urgency clause of Section 17 without a declaration under Section 17(4).
- Whether the preliminary and final notifications issued in 2001 complied with the procedural requirements of the Act, including publication dates and compensation provisions.
- Whether the land acquisition was for a genuine public purpose and whether the claimed urgency was justified.
Legislation cited
- Constitution of Indias. Article 300A
- Land Acquisition Act, 1894s. 11, s. 16, s. 17(1), s. 17(2), s. 17(3A), s. 17(4), s. 4(1), s. 5A, s. 6(1), s. 9
- Land Acquisition (Amendment) Act, 1984
Subjects
Judgment
[2008] 15 S.C.R. 779
ESSCO FABS PVT. LTD. & ANR. A
v.
STATE OF HARYANA & ANR.
(Civil Appeal No. 6580-81 of 2008)
NOVEMBER 7, 2008
B
[C.K. THAKKER AND D.K. JAIN, JJ.]
Land Acquisition Act, 1894:
ss. 17(1),(2) and (4) rlw ss. 4(1) and 6(1) and s.5-A - c
Acquisition of land - State Government invoking urgency
clause u/s 17 and dispensing with inquiry and hearing of
objections uls 5A - HELD: Before exercise of power of
eminent domain, an opportunity of hearing must be afforded
to owner of property - Even in cases of ' urgency; or 0
'unforeseen emergency' within the meaning of sub-ss. (1)
and (2) of s. 17, enquiry contemplated by s. 5-A cannot ipso
facto be dispensed with - It is only when the Government
makes a declaration under sub-s.(4) of s.17 that it becomes
unnecessary to take recourse to procedure uls 5-A - On E
facts, no urgency clause could have been invoked nor could
inquiry and hearing of objections uls 5-A be dispensed with
- Resultantly, actions of the government dispensing with
inquiry and hearing of objections u/s. 5-A, and issuance of
final notification uls 6 quashed.
F
The respondent-State Government, on 15.12.1982
issued a notification u/s 4(1) of the Land Acquisition Act,
1984 in respect of the lands in question. However, as the
acquisition proceedings could not be completed, the
lands were released. Thereafter, a company engaged in G '
export business (the appellant in C.A. No. 6580 of 2008),
purchased some of the said lands for expansion of its
Export Orient Unit, and made an application on 6.6.1991
for change of user of the land. The said application was
779 H ;
780 SUPREME COURT REPORTS [2008] 15 S.C.R.
A rejected on the ground that the land was likely to be
required for public purp.ose. The case of the appellant in
,a
C.A. No. 6581 of 200Q w~s that it being Cooperative
Housing Society, the State Government released some of
the !ands in question in its favour- in 1985. The Society
B invested huge amount in developing the land. On 1.8.2001
the State Government again issued a notification u/s 4(1)
of the Act in respect of the lands in question for
development and construction of a link road. The State
c
Government, by applying urgency clause u/s.17 of the
Act, dispensed with the inquiry and hearing of objections
'
u/s.5·A of the Act and on the next day, i.e. on 2.8.2001,
issued the declaration u/s 6(1) of the Act. Both, the export
company as also the Housing Cooperative Society,
challenged the acquisition proceedings on the grounds
that they were denied their valuable right of filing
D
objections u/s 5·A, and that it was not a case for invoking
the provisions of s.17 of the Act. Since the writ i
petitioners' plea did not find favour with the High Court,
they filed the appeals. I-
E Allowing the appeals, the Court
HELD: 1.1. It is in exercise of power of eminent domain
that a sovereign may acquire property which does not
belong to him. As a general rule, before exercise of power
'f
F of eminent domain, law must provide an opportunity of
hearing against the proposed acquisition. Even without
a specific p_rovision to that effect, general law requires
raising of objections by and affording opportunity of
hearing to the owner of the property. Section SA of The
Land Acquisition Act, 1923 contains such a provision.
G
Afte~ ·issuance of preliminary notification u/s 4 and or
before 'final n~tification u/s 6 of the Act, the appropriate '
......
r
Goxernment is enjQined to hear person interested in the }-,
property before he is deprived of his ownership rights.
[Para 27] [798·C·E]
H
ESSCO FASS PVT. LTD. & ANR. v. STATE OF HARYANA 781
& ANR.
1.2. There may be cases of 'urgency' or 'unforeseen A
A emergency' which may brook no delay for acquisition of .
such property in larger public interest. The Legislature,
therefore, thought it appropriate to deal with such cases
of exceptional nature and in its wisdom enacted Section
17. Whereas sub-section (1) of Section 17 deals with B
cases of 'urgency', sub-section (2) of the said section
covers cases of 'sudden change in the channel of any
navigable river or other unforeseen emergency'. But even
in such cases of 'urgency' or 'unforeseen emergency',
enquiry contemplated by Section SA cannot ipso facto be c
dispensed with which is clear from sub-s.(4) of s.17. lfthe
Government intends to acquire land in cases of 'urgency'
or 'unforeseen emergency' falling under or covered by
sub-sections (1) and (2) of Section 17 of the Act, it is still
required to follow procedure u/s SA of the Act before D
issuance of final notification u/s 6 of the Act. It is only
when the Government also makes a declaration under
~
sub-s. (4) of s.17 that it becomes unnecessary to take
recourse to procedure u/s.SA of the Act. [Para 27-28 and
33] [798-F-H; 799-A; 801-A-B]
E
Nandeshwar Prasad & Anr. v. State of Uttar Pradesh &
Ors, (1964) 3 SCR 42S, relied on.
1.3. The legislative scheme is amply clear which
merely enables the appropriate Government to issue the It
notification under sub-section (4) of Section 17 of the Act
dispensing with inquiry under Section SA if the
Government intends to exercise the said power. The use
of the expression 'may' in sub-section (4) of Section 17
leaves no room of doubt that it is discretionary power of
G
the Government to direct that the provisions of Section
SA would not apply to the cases covered by sub-section
• A,
(1) or (2) of Section 17 of the Act. It would not be correct
to say that once a case is covered by sub-section (1) or
(2) of Section 17 of the Act, sub-section (4) of Section 17
H
782 Sl)PREME COURT REPORTS [2008] 15 S.C.R.
A would necessarily apply and there is no question of
J.._
holding inquiry or hearing objections uls. 5A of the Act.
Such a view will make sub-section (4) of Section 17 totally
otiose, redundant and nugatory. [Para 44 and 45] [807-A-
D]
B
Union of India & Ors. v. Mukesh Hans, (2004) 8 SCC 14,
relied on.
Jai Narain & Ors. v. Union of India & Ors. 1995 Suppl. 5
c
SCR 769 = (1996) 1 SCC 9; Chameli Singh & Ors., v. State
of U.P. & Anr. 1995 Suppl. (6) SCR 827 =(1996) 2 SCC 549 '
and First Land Acquisition Collector & Ors. v. Nirodhi Prakash
Gangoli & Anr., 2002 ( 2 ) SCR 326 = (2002) 4 SCC 160,
referred to.
I
D 1.4. In the instant case, the facts are eloquent. Initial
action of acquisition of land was taken as early as in 1982
but the proceedings lapsed. In 1991, when the appellant
company made an application praying for change of user
of land, it was rejected on the ground that the land was
likely to be required for public purpose. Nothing,
E
however, was done for about a decade. It is only in 2001
that again a notification u/s 4 was issued and urgency
clause was applied. In the facts and circumstances of the
case, no urgency clause could have been invoked by the
respondents nor the inquiry and hearing of objections
F provided by Section 5A of the Act could have been y
dispensed with. Therefore, the action of the respondent-
authority of dispensing with inquiry u/s 5-A and issuance
of final notification uls 6 of the Act is quashed. It is,
however, open to the authorities to take appropriate
G action after following normal procedure laid down in the
Act. (Para 47 and 52] [807-H; 808-A, B; 809-E]
Union oflndia & Ors. v. Mukesh Hans, (2004) 8 SCC 14, ·>.
)...
relied on.
H s
ESSCO FASS PVT. LTD. & ANR. v. STATE OF HARYANA 783
& ANR.
•
Case Law Reference: /\
\A
(1964) 3 SCR 425 relied on para 31
(2004) a sec 14 relied on para 35
1995 (5) Suppl. SCR 769 referred to para 39
B
2002 (2) SCR 326 referred to para 42
CIVIL APPELLATE JURISDICTION : Civil Appeal No.
6580 of 2008.
From the final Judgment and Order dated 2.4.2004 of the c
High Court of Punjab and Haryana at Chandigarh in C.W.P. No.
1853 of 2003.
WITH
D
C.A. No. 6581 of 2008 & Contempt Petition (C) No. 30 of 2007
in C.A. No. 6580 of 2008.
J.L. Gupta and Ranjit Kumar, Sr. Advs., Ashok Mathur, Gian
Singh, Kusum Singh and Mahinder Singh Dahiya for the
Appellants. E
Manjit Singh, Addi. Adv. Gen., Annop G. Choudhary and
June Choudhary, Sr. Adv., Govind Goel and T.V. George for the
Respondents.
F
The Judgment of the Court was delivered by
C.K. THAKKER, J. 1. Leave granted.
2. Both these appeals are filed by the appellants being
aggrieved and dissatisfied with the judgment and order dated G
April 02, 2004, passed by the High Court of Punjab & Haryana
in Civil Writ Petition Nos. 1853 of 2003 and 2077 of 2002.
3. To appreciate the controversy raised in the present
appeals, relevant facts in nutshell may be noted.
H
· 784 · SUPREME COURT REPORTS [2Q08). 15 S._C.R.
A 4. According to the appellant Essco Fabs Pvt. Ltd.
('Essco' for short), the_ Government of Haryana intended to
acquire land for public purpose, viz., for utilization of land as
.residential, commercial· ?nd industrial area in Sector Nos. 11,
12 and 25 Part-II by Haryana Urban Development Authority
s ('HUDA' for short). Forth·e said ·purpose, 'the Government
issyed.a notification under sub-section (1) of Section 4 of the
Land Acquisition Act, 1894 (hereinafter referred to as 'the Act')
on December 15, 1982. The land mentioned in the said
notification situated in village Kheri Nangal was sought to be
C acquired. A final notification under Section 6 of the Act was
issued on June 20, 1984. However, the land acquisition
proceedings could not be completed within the stipulated
period and the notifications lapsed and the land stood released.
5. It was the case of Essco that it bought the land which
D was sought to be acquired earlier for expansion of its Export
Unit. According the appella.nt, it is engaged in manufacturing
and exporting rugs, cushions, bed-spreads, bath mats, fabrics,
kitchen towel, aprons, pot hqlders, .gloves,_ mitten, curtains,
napkins, carpets, etc. It is Export Oriented Unit and earns
E foreign exchange by export of goods manufactured in its unit.
In the year 1992, it exported materials over Rs.2 crores. The
appellant has stated that on June 6, 1991, it made an
application to the Director, Town & Country Planning, Haryana
for permission for change of user of land. All necessary
F documents were appended to the application. The Director, v
however, vide an order dated September 5, 1991, rejected the
permission on several grounds. One of the grounds weighed
with the Director for refusing the permission was that the land
in question was proposed to be acquired. The appellant has
· G produced a copy of the application as also an order of rejec;;tion
thereof in the present proceedings. But even thereafter,no
proceedings.for acquisition of land were initiated for many
. years.
6. On August 1, 2001 i.e. after about twenty years of the
H
.ESSCO FASS PVT. LTD. & ANR. v. STATE OF HARYANA 785
& ANR. [C.K. THAKKER, J.]
first notification of 1982 and nine years after rejection of prayer A
of the appellant for change of user, the Government of Haryana
again issued notification under sub-section ( 1) of Section 4 of
the Act for acquisition of land for the development and utilization
for construction of road connecting Sanauli Road with G.T. Road
for Sector 25 Part-II B, Urban Estate Panipat by HUDA. The B
land of the appellant situated in village Kheri Nangal was sought
to be included in the notification. Moreover, 'urgency clause'
under Section 17 of the Act was applied and a valuable right
of raising objections under Section 5-A of the Act was taken
away in an arbitrary manner. On the very next day i.e. on August c
2, 2001, final notification under Section 6 of the Act was issu~d
by the Government.
7. It is the case of the appellant that the preliminary
notification under sub-section (1) of Section 4 of the Act was
0
required to be published in the manner laid down in the Act.
But it had not been published before issuance of final
notification under Section 6 of the Act. The final notification was,
therefore, illegal and the appellant could not be deprived of h.is
property in a manner not known to law. The right of the appellant
. to own, possess and enjoy the property is not merely a E
Common Law right but also constitutional right under Article
300A of the Constitution which has a 'flavour of fundamental
right'. The acquisition proceedings, being not in consonance
with law were vitiated and liable to be quashed.
F
8. The appellant, hence, filed Civil Writ Petition No. 1853
of 2003 in the High Court of Punjab & Haryana by invoking
Article 226 of the Constitution praying therein for quashing and
setting aside acquisition proceedings. The High Court
entertained the petition and granted status quo with regard to G
possession of the land in question. Finally, however, by the
impugned judgment it dismissed the petition. The said order
is challenged by the appellant in this Court.
9. The other appeal is filed by the Panipat Teachers
H
786 SUPREME COURT REPORTS [2008] 15 S.C.R.
A (Recognized Schools)· Housing Co-operative Society Ltd.
)...
('society' for short) challenging the acquisition proceedings. It
was the case of the society that pursuant to the representation
made by the society, the State Government released 53 kanals
and 8 marlas of land by executing an agreement dated October
B 19, 1985 and by granting land in favour of the society on
conditions mentioned in the agreement. Possession of land
was handed over to the society. The land was demarcated and
was carved out into plots reserving requisite space for school,
parks, temple, overhead water tank, roads, green belt etc. The \.
c society got the site plan designed strictly in accordance with
HUDA Rules. The society invested huge amount, approximately
Rs.26 lakhs, for developing the land laying down sewer pipe
lines, RCC Water pipe lines, construction of roads and
boundary walls etc. The site plan, however, has not been cleared
by the office of the Director, Town & Country Planning, Haryana
D
despite numerous attempts by the appellant-society. It is
alleged by the society that the matter was kept pending for ...,,
oblique and ulterior purposes on lame and untenable excuses.
It is also stated by the society that HUDA published public
notice in 'Daily Bhaskar' dated November 10, 2000 demanding
E development charges thereby acknowledging that the society's
land has been rightly developed for teachers' colony. The public
notice informed and instructed those land/plot owners who were
in arrears to pay all the balance development charges and
outstanding dues. No dues were shown as against the
F appellant-society. Thus, there is nothing due and payable to
HUDA by the appellant.
10. Ignoring all these material facts and with a view to
cause serious prejudice to the appellant-society, a notification
G under sub-section (1) of Section 4 of the Act had been issued
by the State for acquisition of land.
11. We have already stated facts relating to the issuance
of preliminary notification, application of urgency clause under
Section 17 and issuance of final notification under Section 6
H
ESSCO FASS PVT. LTD. & ANR. v. STATE OF HARYANA 787
& ANR. [C.K. THAKKER, J.]
of the Act while narrating the facts in the first case of Essco. It A
,...
is, therefore, not necessary to repeat all those facts in the
second matter.
12. The appellant-society, in the circumstances,
approached the High Court by filing Civil Writ Petition No. 2077
B
of 2002 which was also decided along with the petition of
Essco and the petition of the appellant-society also came to
be dismissed.
~
-I
13. Third writ petition (Civil Writ Petition No. 3324 of 2003)
was filed by M/s Lord Shiva Exports, Panipat which also met c
with the same fate. Lord Shiv Exports, however, has not
approached this Court.
14. Notices were issued by this Court and interim relief
was granted. Respondents thereafter appeared, affidavits and D
further affidavits were filed and the matters were ordered to be
'I posted for final hearing. That is how the matters are before us.
15. We have heard learned counsel for the parties.
16. The learned counsel for the appellants Essco and E
Teachers' society have challenged the acquisition on several
grounds. It was contended that the land was not needed for
public purpose as set out in the notification of 2001 and, hence,
the acquisition is not legal or lawful. Moreover, initially an action
... was taken for acquisition of land before more than a quarter F
century in the year 1982. Final notification was also issued after
more than one and half year of preliminary notification, but even
thereafter, nothing was done by the State and the proceedings
lapsed. Again, in 1991, when Essco applied for change of user
of land, the prayer was turned down, inter alia, on the ground G
that the land in question was proposed to be acquired for public
purpose. Nothing was done by the State for about a decade.
Only in August, 2001, notification under Section 4 was issued.
It was strongly urged by the learned counsel for the appellants
that preliminary notification was issued on August 1, 2001 and
H
.788 SUPREME COURT REPORTS [2008] 15 S. C.R.
A urgency clause was applied though there was no urgency at all.
The notification was published in the official gazette thereafter
and in two daily newspapers on August 10 and 12, 2001. Final
notification under Section 6, however, was issued immediately
on the next day i.e. on August 2, 2001, of the issuance of
B preliminary notification under sub-section ( 1) of Section 4. It
was contended that on the facts of the case, no urgency clause
could have been invoked. Even otherwise, the action was bad
and de hors the Act since the conditions laid down in sub-
section (4) of Section 17 of the Act have not been complied
~
c with inasmuch as there was neither grave urgency nor
unforeseen emergency. It was submitted that there was lethargy
on the part of officers of the Government in not taking steps for
more than twenty years. The State cannot take undue
advantage of its negligence or inaction and deprive the owners
of their right to property in purported exercise of power of
D
eminent domain. The Act is an expropriatory legislation which
deprives a person of his property without his consent. The
provisions of the Act, hence, have to be construed strictly. It was 7'
submitted that Section 5A confers a valuable right on the
owners of land of submitting objections against proposed
E acquisition and such right cannot be taken away or curtailed
by the State. On the facts of the case, invocation of urgency
clause was not only uncalled for being contrary to law but
otherwise arbitrary and unreasonable and on that ground also,
the proceedings are liable to be quashed. It was urged that the
F expression 'the date of publication' has been defined in sub-
section (1) of Section 4 of the Act. While construing the said
connotation under Section 17, same meaning as contemplated
under Section 4(1) has to be given. Since the final notification
under Section 6 had not been published as required by the Act
G after 'the last date of publication' of notification under Section
4(1 ), the action is unlaWful and is.liable to be set aside. It was
asserted that no notice as required by Section 9 of the Act had
been issued nor payment of 80 percent of the compensation
).._
as required by sub-section (3A) of Section 17 h_ad been paid.
H There was also total non-application of mind on the part of the
ESSCO FASS PVT. LTD. & ANR. v. STATE OF HARYANA 789
& ANR. [C.K. THAKKER, J.]
State Government in not considering the Government policy of A
granting exemption to functional units dealing with handloom
and other industries. On that count also, the proceedings are
liable, to be dropped.
17. On behalf of Teachers'- Society, the learned counsel B
adopted all the contentions raised on behalf of Essco. The
learned counsel, however, further submitted that the society
prayed for allotment of land and the prayer was granted. An
" agreement was entered into between the Authority and the
society, possession of land was handed over to the society,
c
which has spent substantiai amount of several lakhs for ·
development. Necessary permission was sought so that
construction can be made which was also granted by the
Authorities, requisite charges which were to be paid had
already been paid and no dues had been shown so far as the .
appellant- society is concerned and yet the impugned action D
has been taken mala fide and with ulterior motive though the
' land is not required for public purpose. It was also submitted
that even according to the authorities, lhe land of the appellant-
society does not come in 'road line'. It is situate at about 24
meters away (23.94 meters) from road line. It was, therefore, E
submitted that the proceedings should be declared against the
provisions of law and may be quashed.
18. Learned counsel for the respondents, on the other
" hand, submitted that the action of the authorities is legal, lawful
and in consonance with law. It was urged that the land was
F
required for public purpose, viz., for construction of road. For
acquisition of land, therefore, a notification was issued. It was
submitted that there is no element of mala fide or colourable
exercise of power which is clear form the fact that even in early
G
eighties, the land was sought to be acquired. Since the
proceedings could not be completed within the stipulated
.... period, they lapsed. That, however, does not mean that the land
was not needed for public purpose or that the public purpose
disappeared or vanished. The counsel submitted that it was
H
790 SUPREME COURT REPORTS [2008) 15 S.C.R.
A further clear when the prayer of Essco for change of user of
land in 1991 was rejected. The applicant was told at that time
also that the land was required for public purpose. According
to the counsel, Government machinery took some time but it
cannot be concluded that the land was not required by the State
B and only with a view to deprive the appellants of their ownership
rights acquisition proceedings had been initiated.
19. Regarding notification of August 1, 2001 and August
2, 2001 under Sections 4 and 6 of the Act respectively, it was ..... ...,-
submitted that both the notifications were in consonance with r
c law. A preliminary notification under sub-section {1) of Section
4 of the Act was issued showing the intention of the State for
acquisition of land for public purpose. Since the acquisition was
for construction of road, it was covered by Section 17 of the
Act and urgency clause was rightly invoked and in exercise cf
D power under sub-section (4) of Section 17, inquiry
contemplated by Section 5A of the Act had been dispensed ,
with. The action was in consonance with law and no grievance
can be made contending that the inquiry as contemplated by
Section 5A and hearing of objections were illegally dispensed
E with by the authorities. All actions were consistent with the
provisions of the Act and .the appellants have no right to make
complaint against tho,se actions. It was, therefore, submitted
that the High Court was wholly right in dismissing the writ
petitions and the appeals have no substance.
-;.-
F
20. Before we deal with the matter on merits, it would be
appropriate if we notice the relevant provisions of the Act. As
the Preamble shows, the Act has been enacted with a view "to
amend the law for the acquisition of land for public purposes
(and for Companies)". Section 3 is a 'definition clause' of
G
various expressions used in the Act. Clause (f) defines 'public
purpose' and the definition is 'inclusive' in nature. Purposes
mentioned in Clauses (i) to (viii) are in the nature of 'public
l..
purpose' and the land can be acquired for any such purpose.
Part II (Sections 4 to 17) deals with 'Acquisition'. Section 4
H
_{
ESSCO FASS PVT. LTD. & ANR. v. STATE OF HARYANA 791
"' & ANR. [C.K. THAKKER, J.]
'
enables the appropriate Government to issue preliminary A
>..
notification for acquisition of land needed or likely to be needed
for public purposes. The said section is relevant and reads thus;
Section 4 - Publication of preliminary notification and
powers of officers thereupon- (1) Whenever it appears
B
to the appropriate Government that land in any locality is
needed or is likely to be needed for any public purpose
..... or for a company a notification to that effect shall b~
~ ~ published in the Official Gazette 1[and in two daily
newspapers circulating in that locality of which at least one
shall be in the regional language and the Collector shall
c
cause public notice of the substance of such notification
to be given at convenient places in the said locality 1[the
last of the dates of such publication and the giving of such
public notice, being hereinafter referred to as the date of
publication of the notification. D
' (2) Thereupon it shall be lawful for any officer, either,
generally or specially authorised by such Government in
this behalf, and for his servants and workmen,--
E
to enter upon and survey and take levels of any land in such
locality;
-4, to dig or bore in the sub-soil;
F
~ to do all other acts necessary to ascertain whether the land F
is adapted for such purpose;
. to set out the boundaries of the land proposed to be taken
and. the intended line of the work (if any) proposed to be
made thereon;
~ G
to mark such levels, boundaries and line by placing marks
and cutting trenches,
~
and, where otherwise the survey cannot be completed and
the levels taken and the boundaries and line marked, to H
r-
792 SUPREME COURT REPORTS [2008] 15 S.C.R.
"'''
A cut down and clear away any part of any standing crop, ).._
fence o~ jungle:
Provided that no person shall enter into any building or upon
r
any enclosed court or garden attached to a dwelling-house
(unless with the 'consent of the occupier thereof) without
B
previously giving such occupier at least seven days' notice
iri writing of his intention to do sci.
21. Section 5A is a salutary provision and enables any 'lo t
person interested in the land which is notified under sub-section
c ( 1) of Section 4 as being needed or iikely to be needed for a
public purpose to lodge objections against the proposed
acquisition. It is equally important provision and may be ·-'
reproduced'
D Section SA - Objections : Hearing of objections-(1) Any
person interested in any land which has been notified
. under . section 4, Sub-section (1), as being needed or likely ..,,
to be needed for a public purpose or for a company may,
within thirty days from the date of the publication of the
notification, object to the acquisition of the land or of any
E
· land in the locality, as the case may be.
(2) Every objection under sub-section (1) shall be made l
to the Collector in writing, and the Collector shall give the r-
objector an 9pportunity of being heard in person or by any
..,,--:.
r-
F person authorised by him in this behalf or by pleader and L
shall, after hearing all such objections and after making
such further inquiry, if any, as he thinks necessary, either
make a report in respect of the land which has been
~
notified under section 4, sub-section (1 ), or make different
G reports in respect of different parcels of such land, to the r
·1 ~
appropriate Government, containing his recommendations .,__
on the objections, together with the record of the
proceedings held by him, for the decision of that >
Government. The decisioh of the Appropriate Governrnent
H tne
ori objections shall be final.· · · ·
ESSCO FASS PVT. LTD. & ANR. v. STATE OF 793
HARYANA & ANR. [C.K. THAKKER, J.]
(3) For the purposes of this section, a person shall be A
deemed to be interested in land who would be entitled to
claim an interest in compensation if the land were acquired
under this Act.
--(
22. Then comes Section 6 which ~authorizes the
B
appropriate Government to issue final notification as to
declaration that the land is required for public purpose. The said
section is also material and reads as under;
.., 6. Declaration that land is required for a public purpose.-
( 1) Subject to the provisions of Part VI I of this Act, when c
the Appropriate Government is satisfied after considering
. the report, if any, made under section 5A, sub-section (2),
that any particular land is needed for a public purpose, or
for a company, a declaration shall be made to that effect
under the signature of a Secretary to such Government or D
of some officer duly authorised to certify its orders an
different declarations may be made from time to time in
respect of different parcels of any land covered by the
same notification under section 4, sub-section (!),
irrespective of whether one report or different reports has E
or have been made (wherever required) under section 5-
A, sub-section (2):
Provided that no declaration in respect of any particular
land covered by a notification under section 4, sub-section
F
(1),--
~
(i) published after the commencement of the Land
Acquisition (Amendment and Validation) Ordinance, 1967
but before the commencement of the Land Acquisition
1 (Amendment) Act, 1984 shall be made after the expiry of G
three years from 'the date of the publication of the
notification; or
'\
.(
(ii) published after the commencement of the Land
Acquisition (Amendment) Act, 1984, shC!ll be made ~fter
H
794 SUPREME COURT REPORTS (2008] 15 S.C.R.
r- I
'
A the expiry of one year from the date of the publication of
)._
the notification:
·Provided further that no such declaration shall be made
unless the compensation to be awarded for such property
\"
.._
is to be paid by a company, or wholly or partly out of public
B
revenues or some fund controlled or managed by a local
authority.
Explanation 1.-ln computing any of the periods referred to ,.
....
~
in the first proviso, the period during which any action or
c proceeding to be taken in pursuance of the notification
issued under Section 4, sub-section (1 ), is stayed by an
order of a Court shall be excluded.
Explanation 2.-Where the compensation to be awarded for
D such property is to be paid out of the funds of a corporation
owned or controlled by the State, such compensation shall
be deemed to be compensation paid out of public v
revenues. l
\I
(2) Every declaration shall be published in the Official
E Gazette, and in two daily newspapers circulating in the
locality in which the land is situate of which at least one
shall be in the regional language, and the Collector shall
cause public notice of the substance of such declaration
to be given at convenient places in the said locality (the
F last of the date of such publication and the giving of such 'f'
public notice, being hereinafter referred to as the date of
{'r-
publication of the declaration), and such declaration shall
state] the district or other territorial division in which the
G
land is situate, the purpose for which it is needed, its
approximate area, and where a plan shall have been r
made of the land, the place where such plan may be
inspected. ,
i
(3) The said declaration shall be conclusive evidence that >
the land is needed for a public purpose or for a Company,
H
-;
-
ESSCO FASS PVT. LTD. & ANR. v. STATE OF HARYANA 795
----(
& ANR. [C.K. THAKKER, J.]
as the case may be; and, after making such declaration A
A the Appropriate Government may acquire the land in
manner hereinafter appearing.
23. Section 9 requires issuance of notice to persons
interested. Section 11 requires enquiry to be made and award
B
to be passed by Collector. Section 16 authorises the Collector
to take possession of the land acquired under the Act.
Thereupon, the land vests absolutely in the Government free
from all encumbrances.
I
24. Section 17 is an exception to the normal rule of c
acquisition of land and deals with cases of urgency and
emergency. The provision is of extreme importance and may
(
be quoted in extenso.
17. Special powers in cases of urgency.-(1) In cases of
D
urgency, whenever the Appropriate Government so directs,
the Collector, though no such award has been made, may,
'¥
on the expiration of fifteen days from the publication of the
notice mentioned in section 9, sub-section (1 ), take
possession of any waste or arable land needed for a public
E
purpose]. Such land shall thereupon vest absolutely in the
Government, free from all encumbrances.
(2) Whenever, owing to any sudden change in the channel
of any navigable river or other unforeseen emergency, it
) becomes necessary for any Railway administration to F
acquire the immediate possession of any land for the
maintenance of their traffic or for the purpose of making
thereon a river-side or ghat station, or of providing
convenient connection with or access to any such station,
or the appropriate Government considers it necessary to G
acquire the immediate possession of any land for the
purpose of maintaining any structure or system pertaining
to irrigation, water supply, drainage, road communication
or electricity,] the Collector may, immediately after the
"' publication of the notice mentioned in sub-section (1) and H,,
~
796 SUPREME COURT REPORTS [2008) 15 S.C.R.
A with fhe previous s~nctio~· the appropriate Government,
cit
enter upon and take possessio'n "of such land, which shall
thereupon vest absolutely in the Government free from all
encumbrances.
f?rovided that the Collector shall not take possession of any
B buildi~g or part of a building under this sub-sec~ion without
giving to the occupier thereof at least forty-eight hours'
notice of his intention so to do, or such longer notice as
may be reasonably sufficient to enable such occupier to
remove his movable property from such building without
c unnecessary inconvenience.
(3) In every case under either of the preceding sub-
sections the Collector shall at the time of taking possession
offer to the persons interested, compensation for the
D standing crops and trees (if any) on such land and for any
other damage sustained by them caused by such sudden
dispossession and not excepted in section 24; and, in case y
such offer is not accepted, the value of such crops and
trees and the amount of such other damage shall be
allowed for in awarding compensation for the land under
E
the provisions herein contained.
(3A) Before taking possession of any land under sub-
sGction.(1) or sub-section (2), the Collector shall, without
· prejudice to the provisions of sub-section (3),-
F
( a) tende.r payment of eighty per centum of the
compensation for such land as estimated by him to the
persons interested entitled thereto, and
(b) pay it to them, unless prevented by some one or more
G
of the contingencies mentioned in section 31, sub-section
(~).and where the Collector is so prevented, the provisions
of section 31, sub-section (2), (except the second proviso
thereto), shall apply as they apply to the payment of
compensation under that section.
H
ESSCO FABS PVT. LTD. & ANR. v. STATE OF HARYANA 797
& ANR. [C.K. THAKKER, J.]
(3-B) The amount paid or deposited under sub-section A
(3A), shall be taken into account for determining the
amount of compensation required to be tendered under
section 31, and where the amount so paid or deposited
exceeds the compensation awarded by the Collector
under section 11, the excess may, unless refunded within B
three months from the date of the Collector's award, be
recovered as an arrear of land revenue.
(4) In the case of any land to which, in the opinion of the
appropriate Government, the provisions of sub-section (1) C
or sub-section (2) are applicable, the appropriate
Government may direct that the provisions of section SA
shall not apply, and, if it does not so direct, a declaration
may be made under section 6 in respect of the land at any
time after the date of the publication of the notification
under section 4, sub-section (1 ). D
25. Whereas Part Ill relates to 'Reference to Court and
procedure thereon', Parts IV and V deal with 'Apportionment
of compensation' and 'Payment', respectively.
E
26. It is vehemently contended on behalf of the appellants
that on the facts and in the circumstances of the case, the
respondents could not have invoked 'urgency clause' by
scuttling enquiry and dispensing with hearing of objections
under Section 5A of the Act It was submitted that no action
F
could have been taken in view of the circumstances mentioned
earlier. As early as in 1982 proceedings were initiated for
acquisition of land but they were allowed to be lapsed in spite
of final notification under Section 6 of the Act by not taking
appropriate actions in time. Again, in 1991, when Essco Fabs
applied for change of user of land, request was turned down G
on the ground that the land was likely to be needed for public
purpose. It was, therefore, submitted that when preliminary
notification under Section 4 was issued in 2001, there was no
urgent need or compelling necessity nor it was a matter of
urgency or emergency under Section 17 of the Act which could H
I-
798 SUPREME COURT REPORTS [2008] 15 S.C.R.
A justify the action and the proceedings are liable to be quashed.
,.!.
27. We find considerable force in the above argument of
the learned counsel for the appellants. The scheme of the Act
is clear which provides for issuance of preliminary notification
B under sub-section ( 1) of Section 4 of the Act empowering the
appropriate Government to issue such notification for
acquisition of land needed or likely to be needed for any public
purpose. Since the property belongs to a private individual,
unless there is a 'public purpose' as defined in clause (f) of 'o; ~
Section 3 of the Act, no acquisition of land can be made. It is
c in exercise of power of eminent domain that a sovereign may
acquire property which does not belong to him. In the
circumstances, as a general rule, before exercise of power of
eminent domain, law must provide an opportunity of hearing '
against the proposed acquisition. Even without a specific
D provision to that effect, general law requires raising of
objections by and affording opportunity of hearing to the owner
y
of the property. The Lan~ Acquisition (Amendment) Act, 1923
(Act 38 of 1923), however, expressly made such provision by
inserting Section 5A in the Act. It is, therefore, clear that after
E issuance of preliminary notification under Section 4 before and
final notification under Section 6 of the Act, the appropriate
Government is enjoined to hear persons interested in the
property before he is ·deprived of his ownership rights. But then
there may be cases of 'urgency' or 'unforeseen emergency'
F which may brooke no delay for acquisition of such property in 'f
larger public interest. The Legislature, therefore, thought it
appropriate to deal with such cases of exceptional nature and
in its wisdom enacted Section 17.
28. Whereas sub-section (1) of Section 17 deals with
G
cases of 'urgency', sub-section (2) of the said section covers
cases of 'sudden change in the channel of any navigable river
or other unforeseen emergency'. But even in such cases i.e.
cases of 'urgency' or 'unforeseen emergency', enquiry >
contemplated by Section 5A cannot ipso facto be dispensed
H
ESSCO FABS PVT. LTD. & ANR. v. STATE OF HARYANA 799
& ANR. [C.K. THAKKER, J.]
with which is clear from sub-section (4) of Section 17 of the Act. A
29. Sub-section (4) of Section 17 is an enabling provision
and it declares that if in the opinion of the appropriate
Government, the provisions of sub-section (1) or (2) are
applicable, it may direct that the provisions of Section 5A would B
not apply. It is, therefore, clear that the Legislature has
contemplated that there may be 'urgencies' or 'unforeseen
emergencies' and in such cases, private properties may be
acquired. But, it was also of the view that normally even in such
cases, i.e. cases of urgencies or unforeseen emergencies, the
owner of property should not be deprived of his right to property
c
and possession thereof without following proper procedure of
law as contem_plated by Section 5A of the Act unless the
urgency or emergency is of such a nature that the Government
is convinced that holding of enquiry or hearing of objections
may be detrimental to public interest. D
... 30. In this connection, both the parties invited our attention
to several decisions. We will deal with some of the important
decisions.
E
31. In Nandeshwar Prasad & Anr. V. State of Uttar
Pradesh & Ors, (1964) 3 SCR 425, the land was acquired by
the Government for public purpose, viz. the Kanpur
Development Board under the Kanpur Urban Area
Development Act, 1945. The Court considered the scheme of
the Act that after issuance of preliminary notification under
F
Section 4 of the Act, objections are to be heard under Section
5A of the persons interested in the property and thereafter final
notification under Section 6 can be issued. The Court, however,
noted that to that procedure, there is an exception under Section
17 which enables the Government to apply urgency clause. G
Where an action is taken under sub-section (4) of Section 17
.. of the Act, it is not necessary to follow procedure luid down in
' Section 5A and notification under Section 6 can be issued
,I..
without report from the Collector as envisaged by Section 5A.
H
ESSCO FABS PVT. LTD. & ANR. v. STATE OF HARYANA 801
& ANR. [C.K. THAKKER, J.]
33. From the above observations, it is clear that even in A
cases falling under or covered by sub-sections (1) and (2) of
Section 17 of the Act and the Government intends to acquire
land in cases of 'urgency' or 'unforeseen emergency', it is still
required to follow procedure under Section 5A of the Act before
issuance of final notification under Section 6 of the Act. It is only B
when the Government also makes a declaration under sub-
section (4) of Section 17 that it becomes unnecessary to take
recourse to procedure under Section 5A of the Act.
·"
34. Nandeshwar Prasad was decided by a three Judge
Bench.
c
35. Recently, in Union of India & Ors. v. Mukesh Hans,
(2004) 8 sec 14, a similar question came up for consideration
before a three Judge Bench. There land was sought to be
acquired at Mehrauli by the appropriate Government for D
organizing Anjuman-Saire-e-Gul-Faroshan. Proceedings were
~
initiated under the Act and urgency clause was applied. The
notification mentioned the public purpose as 'Planned
Development of Delhi'. It was also stated that Lt. Governor was
of the opinion that Section 17(1) of the Act was applicable to E
the acquisition and he d~rected to dispense with inquiry under
Section SA of the Act. Simultaneously, a declaration under
Section 6 was issued. Interested parties approached the High
Court of Delhi, inter alia, on the ground that decision to dispense
'\ with inquiry contemplated by Section 5A of the Act was vitiated F
by non-application of mind. The High Court upheld the
contention and quashed the proceeding. The aggrieved Union
approached this Court.
36. It was contended on behalf of the Union that in case
of urgency, it was open to the appropriate Government to G
dispense with inquiry under Section 5A by invoking sub-section
(4) of Section 17 of the Act. It was alsQ contended that the
urgency contemplated by sub-sections (1) or (2) of Section 17
of the Act was 'by itself sufficient to invoke sub-section (4) of
H
\
~
802 SUPREME COURT REPORTS [2008) 15 S.C.R.
A Section 17.
37. Negativing the contention and referring to Nandeshwar
Prasad and other judgments, the Court held;
"A careful perusal of the above Section shows that Sub-
B section ( 1) of Section 17 contemplates taking possession
of the land in, the case of an urgency without making an
award but after the publication of Section 9( 1) notice and
after the expiration of 15 days of publication of Section 9( 1) '>;-
notice. Th'erefore it is seen that if the appropriate
c Government decides that there is an urgency to invoke
Section;17(1) in the normal course Section 4(1) notice will
have J6 be published, Section 6 declaration will have to
be ..Jllade and after completing the procedure
contemplated under Sections 7 and 8, 9(1) notice will have
D to be given and on expiration of 15 days from the date of
such notice the authorities can take possession of the land
y
even before passing of an award.
Sub-section (2) of Section 17 contemplates a
different type of urgency inasmuch as it should be an
E
unforeseen emergency. Under this Section if the
appropriate Government is satisfied that there is such
unforeseen emergency the authorities can take
possession of the land even without waiting fort 15 days r-
period contemplated under Section 9(1 ). Therefore, in
F -I
cases, where Government is satisfied that mere is an
unforeseen emergency it will have to in the normal course,
issue a Section 4(1) notification, hold 5A inquiry, make
Section 6 declaration, and issue Section 9(1) notice and
possession can be taken immediately thereafter without l
G waiting for the period of 15 days prescribed under Section ;
9( 1) of the Act.
Section 17 (4) as noticed above provides that in
cases where the appropriate Government has come to the
H conclusion that there exists an urgency or unforeseen
)
~
ESSCO FABS PVT. LTD. & ANR. v. STATE OF HARYANA 803
& ANR. [C.K. THAKKER, J.]
emergency as required under Sub-sections (1) or (2) of A
Section 17 it may direct that the provisions of Section 5A
shall not apply and if such direction is given then 5A inquiry
can be dispensed with and a declaration may be made
under Section 6 on publication of 4( 1) notification
possession can be made". B
38. The Court, therefore, proceeded to state;
"A careful perusal of this provision which is an exception
!'
to the normal mode of acquisition contemplated under the
Act shows mere existence of urgency or unforeseen c
emergency though is a condition precedent for invoking
Section 17(4) that by itself is not sufficient to direct the
dispensation of 5A inquiry. It requires an opinion to be
formed by the concerned government that along with the
existence of such urgency or unforeseen emergency there D
is also a need for dispensing with 5A inquiry which
"f indicates that the Legislature intended that the appropriate
government to apply its mind before dispensing with 5A
inquiry. It also indicates the mere existence of an urgency
under Section 17(1) or unforeseen emergency under E
Section 17(2) would not by themselves be sufficient for
dispensing with 5A inquiry. If that. was not the intention of
the Legislature then the latter part of Sub-section (4) of
Section 17 would not have been necessary and the
\ Legislature in Section 17(1) and (2) itself could have F
incorporated that in such situation of existence of urgency
or unforeseen emergency automatically 5A inquiry will be
dispensed with. But then that is not language of the Section
which in our opinion requires the appropriate Government
to further consider the need for dispensing with 5A inquiry
G
in spite of the existence of unforeseen emergency. This
understanding of ours as to the requirement of an
application of mind by the appropriate Government while
dispensing with 5A inquiry does not mean mat in and every
case when there is an urgency contemplated under Section
H
804 SUPREME COURT REPORTS. [2008] 15 S.C.R.
A 17(1) and unforeseen emergency contemplated under
Section 17(2) exists that by itself would not contain the
need for dispensing with SA inquiry. It is ppssible in a given
case the urgency noticed by the appropriate Government
under Section 17(1) or the unforeseen emergency under
B Section 17(2) itself may be of such degree that it could
require the appropriate Government on that very basis to
dispense with the inquiry under Section SA but then there
is a need for application of mind by the appropriate
·"\;
Government that such an urgency for dispensation of the
c SA inquiry is inherent in the two types of urgencies
contemplated under Section 17(1) and (2) of the Act".
39. The learned counsel for the respondent authorities,
however, strongly relied upon a two Judge Bench decision of
this Court in Jai Narain & Ors. v. Union of India & Ors., (1996)
D 1 SCC 9. In Jai Narain, the Court held that the question of
'urgency' or 'unforeseen emergency' is the matter which is y
entirely based on 'subjective satisfaction of the Government'
and the Courts do not interfere unless the reasons given are
wholly irrelevant and there is non-application of mind. If the
E public purpose, on the face of it shows that the land is needed
urgently, that by itself is relevant circumstance for justifying the
action under Section 17(4) of the Act.
40. Again, a similar view was taken by a two Judge Bench
F in Chameli Singh & Ors., v. State of U.P. ·& Anr., (1996) 2 SCC t
S49. In Chameli Singh, land was acquired for public purpose,
namely, construction of houses for dalits. Urgency clause under
Section 17 was applied which was challenged by the land-
owners. Holding that the urgency clause was rightly applied and
inquiry under Section SA of the Act has been correctly
G
dispensed with, the Court observed that acquisition of land for
providing houses to dalits, tribes and poor would be sufficient
to invoke Section 17 of the Act and the land-owners cannot
>
challenge the validity of such acquisition on the ground that
inquiry under Section SA cannot be dispensed with.
H
ESSCO FASS PVT. LTD. & ANR. v. STATE OF 805
HARYANA & ANR. [C.K. THAKKER, J.]
41. The Court stated; A-
"It would thus be seen that this Court emphasised the
holding of an inquiry on the facts peculiar to that case. Very
· often the officials, due to apathy in implementation of the
policy and programmes of the Government, themselves 8
adopt dilatory tactics to create cause for the owner of the
land to challenge the validity or legality of the exercise of
the power to defeat the urgency existing on the date of
taking decision under Section 17(4) to dispense with
Section 5-A inquiry.
c
It is true that there was pre- notification and post-
notification delay on the part of the officers to finalise and
publish the notification. But those facts were present
before the Government when it invoked urgency clause
and dispensed with inquiry under Section 5A. As held by D
this Court, the delay by itself accelerates the urgency:
Larger the delay, greater be the urgency. So long as the
unhygienic conditions and deplorable housing needs of
Dalits, Tribes and the poor are not solved or fulfilled, the
urgency continues to subsist When the Government on the E
basis of the material, constitutional and international
obligation, formed its opinion of urgency, the Court, not
being an appellate forum, would not disturb the finding
unless the court conclusively finds the exercise of the power
male fide. Providing house sites to the Dalits, Tribes and F
the poor itself is a national problem, and a constitutional
obligation. So long as the problem is not solved and the
need is not fulfilled, the urgency continues to subsist. The
State is expending money to relieve the deplorable
housing condition in which they live by providing decent G
housing accommodation with better sanitary conditions.
The lethargy on the part of the officers for pre and post-
notification' delay would not render the exercise of the
power to invoke urgency clause invalid on that account".
42. In First Land Acquisition Collector & Ors., v. Nirodhi H
806 SUPREME COURT REPORTS [2008] 15 S.C.R.
A Prakash Gangoli & Anr., (2002) 4 SCC 160, a two Judge
Bench again observed that case of existence of urgency under
Section 17. of the Act is a matter of subjective satisfaction of
appropriate Government and a decision of Government to
dispense with inquiry under Section SA by invoking urgency
B provision can be challenged only on the ground of non-
application of mind or mala fide exercise of power by the
Government. Burden is always on the person alleging mala fide
to prove it on the basis of specific materials. So long as the
purpose of acquisition continues to exist, exercise of power
c under Section 17 cannot be held to be mala fide. Mere delay
of the Government subsequent to its decision to dispense with
inquiry under Section SA by exercising power under Section
17 would not invalidate the decision.
43. On the basis of above decisions, it was submitted that
D once a decision has been taken by the State Government to
apply urgency clause, the decision of the Government cannot
be interfered with by a Court exercising writ jurisdiction.
44. In our judgment, from the above case law, it is clear
E that normal rule for acquisition of land under the Act is issuance
of notification under sub-section (1) of Section 4, hearing of
objections under Section SA and issuance of final nctification
under Section 6 of the Act. Award will be made by the Collector,
notice has to be issued to the land-owners or the person
F interested and thereafter possession can be taken. Section 17,
no doubt, deals with special situations and exceptional
circumstances covering cases of 'urgency' and 'unforeseen
emergency'. In case of 'urgency' falling under sub-section (1)
of Section 17 or of 'unforeseen emergency' covered by sub-
G section (2) of Section 17, special powers may be exercised
by appropriate Government but as held by a three Judge Bench
decisions before more than four decades in Nandeshwar
Prasad and reiterated by a three Judge Bench decision in
Mukesh Hans, even in such cases, inquiry and hearing of )
H objections under Section SA cannot ipso facto be dispensed
ESSCO FABS PVT. LTD. & ANR. v. STATE OF HARYANA 807
& ANR. [C.K. THAKKER, J.]
with unless a notification under sub-section (4) of Section 17 A
.- ).
of the Act is issued. The legislative scheme is amply clear
which merely enables the appropriate Government to issue
such notification under sub-section (4) of Section 17 of the Act
dispensing with inquiry under Section SA if the Government
intends to exercise the said power. The use of the expression B
'may' in sub-section (4) of Section 17 leaves no room of doubt
that it is discretionary power of the Government to direct that
the provisions of Section 5A would not apply to such cases
I
covered by sub-section ( 1) or (2) of Section 17 of the Act.
45. In our opinion, therefore, the contention of learned
c
counsel for the respondent authorities is not well founded and
cannot be upheld that once a case is covered by sub-section
(1) or (2) of Section 17 of the Act, sub-section (4) of Section
17 would necessarily apply and there is no question of holding
inquiry or hearing objections under Section SA of the Act. p
Acceptance of such contention or upholding of this argument
"( will make sub-section (4) of Section 17 totally otiose, redundant
and nugatory.
46. It is true that in Chameli Singh and Jai Narain, a two E
Judge Bench has observed that acquisition of land for housing
accommodation or for construction of residential quarters for
dalits and tribals can be said to be of an urgent nature falling
under Section 17(1) of the Act. But as already held in
~ .... Nandeshwar Prasad and Mukesh Hans, even in such cases, F
procedure required to be followed under Section 5A cannot be
dispensed with unless notification under sub-section (4) of
Section 17 is issued. In Mukesh Hans, the Court also held that
the provision cannot be pressed in service by officers who were
negligent and due to their lethargy, proceedings could not be
G
initiated for a quite long time.
47. In the instant case, the facts are eloquent. Initial action
... of acquisition of land was taken as early as in 1982 but the
'"' proceedings lapsed. In 1991, when Essco made an application
praying for change of user of land, it was rejected on the ground H
808 SUPREME COURT REPORTS [2008] 15 S.C.R.
A that the land was likely to be required for public purpose.
I..
Nothing, however, was done for about a decade. It is only in ..(
2001 that·again Notification under Section 4 was issued and
urgency clause was applied. We are, therefore, satisfied that
the ratio lad down in Mukesh Hans squarely applies to the facts
B of the case. No urgency clause could have been invoked by the
respondents and inquiry and hearing of objections provided by
Section 5A of the Act could not have been dispensed with. The
actions of issuance of urgency clause under sub-section (4) of :.
Section 17, dispensing with inquiry under Section 5A and
\
c issuance of final notification under sub-section (1) of Section
6 are required to be quashed and they are accordingly
quashed.
48. The learned counsel for the appellant also contended
that even if it is held that the respondent could have issued final
D notification without holding inquiry and hearing of objections
under Section ·5A of the Act, the notification under Section 6
of the Act is illegal and unlawful in view of the fact that the said ..,,,..
notification has not been issued after the last of the dates of
the publication and giving of public notice referred to as "the
E date of publication of the notification" under sub-section (1) of
Section 4 of the Act.
49. It was submitted that even the said point is concluded
by a decision of this Court in State of Uttar Pradesh & Ors. v.
Radhey Shyam Nigam & Ors, (1989) 1 SCC 591.
F ,.
'
50. The learned counsel for the respondents, on the other
hand, relying on State of Haryana & Anr. v. Raghubir Dayal,
(1995) 1 SCC 133 and Mohan Singh & Ors. v. International
Airport Authority of India & Ors., (1997) 9 SCC 132 submitted
G that if urgency clause under Section 17(4) is applied by the
appropriate Government, final notification under Section 6 of
the Act can be issued on the next day of the issuance of
preliminary notification under Section 4 of the Act. In the case ,,
on hand,· the said procedure is followed. Notification. under >-
H Section 4_ was issued on August 1, 2001. Urgency clause was
ESSCO FASS PVT. LTD. & ANR. v. STATE OF HARYANA 809
& ANR. [C.K. THAKKER, J.]
~
applied and the case was covered by Section 17(4) oft~e Act. A
A
On the very next day i.e. on August 2, 2001, final notification
under Section 6 was issued. Therefore, the procedure required
by law has been strictly followed as held by this Court in
Raghubir Dayal and Mohan Singh.
51. We would have entered into the said question had it
8
been absolutely necessary for us ~o decide it in the case on
hand. But as observed hereinabove, we are of the view that the
appellants are entitled to succeed on the first ground that on
I the facts and in the circumstances of the case, the appropriate
Government was not justified in invoking urgency clause under c
sub-section (4) of Section 17 of the Act by dispensing with
inquiry and hearing of objections under Section SA of the Act
and the final notification issued under Section 6 of the Act
deserves to be set aside on that ground alone, we express no
opinion one way or the other on the interpretation of the D
expression "the date of publication of the notification" used in
)
sub-section (1) of Section 4, sub-section (4) of Section 17 and
'"' Section 6 of the Act.
52. For the foregoing reasons, both the appeals are
E
allowed. The action of the respondent authority of dispensing
with the inquiry and hearing of objections under Section SA and
issuance of final notification under Section 6 of the Act is hereby
quashed and set aside. It is, however, open to the authorities
to take appropriate action after following normal procedure laid
~
down in the Act. F
'
53. Appeals are accordingly allowed with costs.
CONTEMPT PETITION NO. 30 OF 2007
IN C.A.NO. 6580 OF 2008 @ S.L.P. (C}NO. 15449 OF
G
2004
54. In the light of judgment in the above appeals, the
-...;: contempt petition stands disposed of.
~
RP. Appeals allowed.