Created byFuzzy Cloud

Supreme Court of India

FOOD CORPORATION OF INDIAversusSURENDRA, DEVENDRA & MOHENDRA TRANSPORT CO.

Citation
1987 INSC 371
Decided
10 December 1987
Disposal
Disposed off

Holding

The arbitrator was not in error in adjudicating the demurrage and wharfage claim, but his award of pendente‑lite interest was an error of law and must be set aside.

Summary

The Food Corporation of India (appellant) hired Sureendra, Devendra & Mohendra Transport Co. (respondent) as a transport contractor under three written agreements. Disputes over demurrage, wharfage and shortage charges were referred to an arbitrator pursuant to an arbitration clause. The arbitrator reduced the appellant's claim for demurrage and wharfage to 25% of Rs 13,94,982.46 and awarded pendente‑lite interest at 6% per annum, which the appellant challenged under sections 30 and 33 of the Arbitration Act, 1940. The Calcutta High Court initially set aside the award, but the Division Bench reversed that decision and upheld the award. On special leave, the Supreme Court examined whether the manager’s decision under clause 9(a) was final and whether the arbitrator could award interest. The Court held that the arbitrator was within his jurisdiction to decide the demurrage and wharfage claim and that the manager’s decision was not conclusive for the whole dispute, but that the award of interest was not justified and amounted to an error of law. Consequently, the Court affirmed the High Court’s order except for the interest component, disposing of the appeal.

Issues considered

  • Whether the arbitrator could reduce the demurrage and wharfage claim despite clause 9(a) stating the manager's decision was final
  • Whether the award of pendente‑lite interest by the arbitrator was permissible under the Arbitration Act, 1940 and applicable law
  • Whether the award as a whole could be set aside under sections 30 and 33 of the Arbitration Act, 1940

Legislation cited

Subjects

ArbitrationArbitration Act 1940Section 30Section 33Pendente lite interestDemurrageWharfageContractual clauseManager's decisionSpecial leaveArticle 136

Judgment

                        FOOD CORPORATION OF INDIA                                    A
                                           v.
~   •    SURENDRA, DEVENDRA & MOHENDRA TRANSPORT CO.

                                DECEMBER 10, 1987

         ISABYASACHI MUKHARJI AND S. RANGANATHAN, JJ.J                               B

             Arbitration Act, 1940--Challenge to award of the arbitration
        under section 30, 33-0f.

               The respondent was appointed a transport and handling Con-
        tractor by the appellant subject to the terms and conditions mentioned       c
        in three successive written agreements entered into by both the parties.
        After disputes arose between the parties, an arbitrator was appointed
        as per the arbitration clause to adjudicate upon the disputes. The
        arbitrator made and published an award which was a speaking one. He
        did not allow the appellant's claim for demurrage and wharfage
        charges paid to the Railways amounting to Rs.15,63,863.02 by reason          D
        of the alleged wrongful conduct of the respondent but awarded only
         25% of the claim. The arbitrator also did not allo~ the appellant's claim
         for shortage in transit but reduced the claim by 40% and allowed only
         60% of it amounting to Rs.52,971.99. The arbitrator awarded to the
         respondent Rs.12,64,175.97 and pendente lite interest at 6% per
         annum.                                                                      E

             The appellant filed objections in the High Court under sections 30
        and 33 of the Arbitration Act, 1940 ('The Act') for setting aside the
        award. The High Court (Single Judge) set aside the award. The respon-
        dent filed an appeal to the Division Bench of the High Court which
        allowed the same, setting aside the judgment of the learned single judge     F
        and upholding the award. Being aggrieved by the dicision of the High
        Court, the appellant appealed to this Court for relief by special leave
        under Article 136 of the Constitution.

               Disposing of the appeal, this Court,
                                                                                     G
              HELD: While issuing noiice on the application under Article 136
        of the Constitution, it was indicated that only three questions would be
        adjudicated upon in this appeal, viz, Rs.13,94,982.46 being the amonnt
        allowed on account of demurrage and wharfage charges mentioned in
        the award, secondly, the sum of Rs.2,35, 769.46 and lastly, the question
        of interest. l332G I                                                         H

                                            329
     330                   SUPREME COURT REPORTS            [1988] 2 S.C.R.

A         So far as the second question was concerned, counsel for the
    appellant did not make any submission before the Court. The Court also
    could not find any substance in this aspect. Therefore, it was not neces-
    sary to deal with this aspect of the matter. [332H; 333A)

         So far as the amount ofRs.13,94,982.46 on account ofdemurrage
B and wharfage was concerned, which was allowed, it appeared that the
  total demurrage and wharfage charges paid by the Corporation to the
  Railways in respect of the wagons cleared by the claimant firm, respon-
  dent herein, after obtaining such waiver as the Railways were per-
  suaded to make were Rs.15,63,863.21. There was no dispute about the           .J.
  actual payment of the charges. The appellant's case was that it was            '
C entitled to recover the entire amount it had to pay on account of the
  demurrage and wharfage charges from the respondent under clause
  9(a) of the agreement. [333B-C]

          Under clause 9(a) according to the appellant, the Agent was liable
   to make good any compeusatiou/demurrage/wharfage as per Railway
D rates in force during the period of contract and other charges or ex-
   penses that might be incurred hy the Corporation on account of delay in
   loading/unloading of trucks/carts and unloading/loading of wagons un·
   less the delay was for reasons beyond the Agent's control. It appeared
   lh11t the appellant had periodically served notices upon the respondent·
   firm calling upon it to pay demurrage and wharfage charges with liberty
E to prefer objections. Such objections·as the respondent-firm preferred
   were disposed of by the District Manager. This procedure continued till
   the end of November, 1975. Then the respondent-firm went to the Civil
   Court and obtained discontinuance of all proceedings for the recovery of
   demurrage and wharfage charges. The arbitrator noted that as a result
  of the hearings by the Corporation npto November, 1975, relief to the
F tune of Rs.1,21,884.55 was granted to the respondent-firm and the
  recovery of Rs.45,996.20 was made from the respondent-firm's bills.
  The Corporation, therefore, claimed before the arbitrator recovery of
  the remaining or the claim of Rs.13,94,982.46. Counsel for the appel-
  lant drew this Court's attention to clauses 9(a) and (b) of the agreement
  and submitted that the adjudication made by the Manager was final and
G there was no dispute thereafter. According to him, no further deduction
  was possible from what had been granted by the Manager for determi-
  nation on account of demurrage and .wharfage charges, nor was it arbi-
  trable because it was final. [334B-E]

        le appears on the facts as recorded by the arbitrator in his award
H that there was adjudication really by the Manager of the claims npto
                        FOOD CORPN. v. SURENDRA TPT. CO.                      331

      November, 1975. Thereafter, there could be no adjudication as a result A
      of injnnction obtained from the Court. Therefore, it appeared that
' ,   there was in fact no adjudication of all the disputes. The remaining
      points were arbitrable because of the amplitude of the arbitration
      clause. It was not brought to the notice of the Court that there was
      an adjudication by the Manager of the claim for the period
      beyond November, 1975, as mentioned hereinbefore. Therefore, the B
      arbitrator was not in error ·in proceeding in the manner he did. There
      was no other aspect of law on this aspect of the matter to which the
      attention of the Court was drawn. The submission on this aspect was,
      therefore, negatived and the challenge to the award on this aspect must
      fail. [337C-D; 338B]
                                                                                     c
            So far as the grant of interest pendente lite in the award was
      concerned, reliance was placed on various decisions of this Court. In
      deference to the latest pronouncement of this Court, which is a pro-
.'    nouncement of three learned Judges, in Executive Engineer Irrigation
      Galimala & Ors. v. Abaadute Jena, (J. T. 1987 4 S.C. 8), the Court held
      that the grant of pendente lite interest in this case was was not justified.   D
      Though the award in this case was a speaking award, it was not made
      clear on what basis the interest was awarded. The arbitrator was in
      error in granting the interest in the manner he did . It was true that in
      specific terms there was no denial on this right to grant interest, but
      there was denial as to get it in accordance with law. l338C·D; 340E-F]
                                                                                     E
            In awarding the interest the arbitrator committed an error of law.
      With this modification, the jndgment and order of the High Court were
      affirmed. [340F·G I

            Wadsworth v. Smith, L.R. Vol. VI Q.B. 332; State of Orissa and
      Others, v. Construction India, J.T. 11987] 4 S.C. 588; Executive Engineer      F
      Irrigation Galimala & Ors. v. Abaadutalena, J.T. 1987 4 S.C. 8, Firm
      Madan lal Roshanlal Mahajan v. Hukumchand Mills Ltd., Indore,
      11987] 1 S.C.R. 105; State of Madhya Pradesh v. Mis. Saith & Skelton
      (P) Ltd., 11972] 3 S.C.R. 233; M/s. Ashok Construction Company v.

.'    Union of India, [1971] 3 S.C.C. 66 and Mis. Alopi Parshad & Sons
      Ltd. v. The Union of India, 11960] 2 S.C.R. 793, referred to.                  G

            CIVIL APPELLATE JURISDICTION: Civil Appeal No. 4096
      of 1987.

           From the Judgment and Order dated 2.6.1987 of the Calcutta
      High Court in Appeal No. 344of1980.                                            H
    332                    SUPREME COURT REPORTS            [1988] 2 S.C.R.

A         A.K. Sen, S.K. Gambhir and Vivek Gambhir for the Appellant.

          Dr. Shankar Ghosh and Rathin Das for the Respondent.

          The J udgment of the Court was delivered by

B         SABYASACHI MUKHARJI, J. Special leave granted.

          The respondent was appointed a transport and handling con-
    tractor by the appellant subject to the terms and conditions mentioned
    in three successive agreements in writing entered into by both the
    parties. After disputes arose between the parties, as per the terms of
C   arbitration clause an arbitrator was appointed to adjudicate upon the
    disputes. Both the respondent and the appellant filed their respective
    claims and counter-claims before the arbitrator. After considering the
    documents and evidence filed before the arbitrator, he made and
    published an award which was a speaking one. The arbitrator did not
    allow the appellant's claim for demurrage and wharfage charges paid
D   to Railways amounting to Rs.15,63,863.02 by reason of the alleged
    wrongful conduct of respondent but the arbitrator awarded only 25%
    of the claim. The arbitrator also did not allow the appellant's claim for
    shortage in transit but reduced the claim by 40% and allowed only
    60% of it amounting to Rs.52,971.99. By the award the arbitrator
    awarded to the respondent Rs.12,64, 175.97 and pendente lite interest
E   at 6% per annum. The appellant filed objections in the High Court of
    Calcutta under sections 30 and 33 of the Arbitration Act, 1940
    (hereinafter called 'the Act') for setting aside the award. on 18th
    September, 1980, the learned single judge of the High Court by his
    judgment and order set aside the award. There was an appeal to the
    Division Bench of the High Court. On 2nd June, 1987 the Division
F   Bench of the High Court allowed the respondent's appeal by its judg-
    ment and order and set aside the judgment of the learned single judge
    and upheld the award. Being aggrieved thereby the appellant has come
    up before this Court by special leave under Article 136 of the Constitu-
    tion. While issuing notice on the application under Article 136 of the
    Constitution it was indicated that only three questions will be adju-
G   dicated upon in this appeal viz. Rs.13,94,982.46 which was the amount
    allowed on account of demurrage and wharfage charges mentioned in
    the award and secondly, the sum of Rs.2,35,769.46 and lastly on the
    question of interest.

         So far as the second question of the matter is concerned Sree
H A.K .. Sen, counsel appearing for the appellant has not made any sub-
        FOOD CORPN. v. SURENDRA TPT. CO. [MUKHARJI, J.]              333

mission before us. We also cannot find any substance in this aspect.
                                                                            A
Therefore, it is not necessary for us to deal with this aspect of the
matter.

      So far as the amount of Rs.13,94,982.46 on account of demur-
rage and wharfage is concerned, which was allowed, the award dealt
with the question as set out in the paper-book. It appears that the total   B
demurrage and wharfage charges paid by the Corporation to the Rail-
ways, in respect of the wagons cleared by the claimant firm, respon-
dent herein, after obtaining such waiver as the Railways were per-
suaded to make was for Rs.15,63,863.21. The charges were alleged to
have been paid under Credit Notes which were produced before the
arbitrator. There was no dispute about the actual payment of the
charges. The appellant's case was that it was entitled to recover the
                                                                            c
entire amount it had to pay on account of the demurrage and wharfage
charges from the respondent under clause 9( a) of the agreement.

      Clauses 9, 9(a) and 9(b) of the agreement are as follows:
                                                                            D
            9. The Agent shall commence to load and/or unload all the
            wagons and trucks as well as all streamers, flats, barges and
            boats or any other conveyance on the day of their arrival and
            shall carry out the orders and directions of the Manager
            with all possible despatch and shall be responsible for and
            make good all demurrage or other waiting charges and ex-        E
            penses that may accrue and all other charges that may in
            the opinion of the Manager be payable because of or
            through any reasonable detention or delay."

            "9(a) The Agent shall be responsible for unloading/load-
            ing the wagons within the free period allowed by the Rail-      F
            ways and also for loading/unloading for trucks/carts or any
            other transport vehicles expeditiously. The Agent shall be
            liable to make good any compensation/demurrage/whar-
            fage as per Railway rules in force during the period of
            contract other charges or expenses that may be incurred by
            the Corporation on account of delay in loading/unloading        G
            of truck/carts and unloading/loading of Wagons unless the
            delay is for reason beyond the Agents' control. The deci-
            sion of the manager in this respect shall be final and bind-
            ing on the Agent."

            "9(b) The Agent be present himself or send his duly             H
     334                   SUPREME COURT REPORTS            [1988] 2 S.C.R.

                authorised representative to be present at all weighments
A               with which the Agent is concerned under this Agreement
                and in case he fails or chooses not to do so, no claim what-
                soever shall lie against the Corporation in this regard."

         Under clause 9(a), according to the appellant, the Agent was
   liable to make good any compensation/demurrage/wharfage as per
B
   Railway rates in force during the period of contract, other charges or
  expenses that might be incurred by the Corporation on account of
  delay in loading/unloading of trucks/carts and unloading/loading or
  wagons unless the delay was for reasons beyond the Agent's control. It
  appears that the appellant and periodically served notices upon the
  respondent firm calling upon it to pay demurrage and wharfage
C charges with liberty to prefer objections. Such objections as the
  respondent-firm preferred were heard and disposed of by the District
  Manager. This procedure continued till the end of November, 1975.
  Then the respondent-firm went to the Civil Court and obtained discon-
  tinuance of all proceedings for recovery of demurrage and wharfage
  charges. The arbitrator noted that as a result of the hearings by the
D Corporation upto November, 1975 relief to the tune of Rs.1,21,884.55
  was granted to the respondent-firm and recovery of Rs.46,996.20 was
  made from the respondent-firm's bills. The Corporation, therefore,
  claimed before the arbitrator recovery of remaining of the claim of
  Rs. 13,94,982.46.
E        The respondent on the other hand claimed refund of the amount
   already deducted from the bills on the ground that it was not liable for
   any part of the demurrage and wharfage charges. The claim of the
   respondent was that the demurrage and wharfage charges accrued in-
  variably in circumstances beyond its control and accordingly under
   clause 9(a) of the agreement it could not be made liable for such
F charges. The arbitrator noted that the respondent-firm had impressive
  documentary evidence in support of its case. It had produced numer-
  ous letters in which it fully explained to the authorities concerned the
  difficulties it was experiencing in timely clearance of goods from rail-
  way wagons and sheds. It was claimed that it had produced month-wise
  report of its work accounting for nearly all cases of demurrage and
G wharfage. On 9th of October, 1975 the respondent had informed the
  Corporation by a letter Exhibit 128 which inadvertently was not
  marked exhibit that it was resuming work (there had been a break in
  his contract) on the condition that it would not be required to clear
  more than 10 c.c. or 4 box wagons, i.e. 200 m.t. approximately daily. This
H is a belated and rather grudging acceptance of this condition by the
  letter, Exhibit 44 dated 3rdof August, 1976.
              FOOD CORPN. v. SURENDRA TPT. CO. [MUKHARJI, J.]           335

            The Arbitrator noted that from the letters and reports it
                                                                               A
      appeared that timely clearance was hampered, and often made impos-
      sible by arrival of too many wagons at a time, congestion at the sidings
      and at the weighbridges with consequent detention of lorries, labour
      unrest and chronic want of space in the Corporation's godowns and by
      others. The arbitrator noted that there was insistent complaint about
      this want of space in the Corporation's godown, which led to the goods B
      being left in railways sheds for days together incurring unusually heavy
      wharfage charges. The Corporation sometimes prepared over ambiti-
      ous programmes of work for the contractors, as if unaware. of the
      existing situation. The arbitrator noted that the appellant had
      examined several witnesses from the sidings. But they did not accord-
      ing to the Arbitrator, prove anything beyond the procedure of work
      generally adopted at the sidings. The arbitrator further noted about c
      the foregoing explanations that the very often the objection of the
      railway shed staff to the claimant regarding not clearing of the wagons
      timely from the railway shed because of non-space there owing to
      heavy stock kept therein remaining uncleared, and further that the
      claimant under the direction and order of the respondent being given D
      limited programme because of non-space in the receiving depots/
      god owns were causes of delay. The arbitrator noted that it would be
      fair to make the claimant firm liable for only 25% of the demurrage
      and wharfage charges sought to be recovered by the Corporation,
      leaving the remaining 75% to be borne by the Corporation itself.
       Therefore, out of Rs.13,94,982.46 the Corporation, according to the E
       arbitrator, could recover only Rs.3,48, 745.61. The appellant felt
       aggrieved thereby and challenges this grant of 25%. So far as respon-
!     dent's claim for refund of Rs.46,996.20 already recovered, the arbi-



,     trator felt that there was no ground for interference. The arbitrator
      noted that after hearing the claimant firm's objections the deductions
      had been made. The claimant firm had been granted relief in respect of F
       Rs.1,21,884.55. The arbitrator had not been able to ascertain precisely
       the total claim of the appellant till the end of November, 1975 but he
       noted that the sum of Rs.46,996.20 represented not much more than
       25% of the total claim. Therefore, the arbitrator noted that the claim-
       ant, namely, the respondent was not entitled to any refund and that
• •    the appellant could recover only Rs.3,48,745.61 on account of demur- G
       rage and wharfage charges. As mentioned hereinbefore that is the
       main contention in this challenge before this Court. The appellant
       claimed that it should have been entitled to the benefit of
       Rs.13,94,982.46 and not to 25% of the same.

            Sree Sen, counsel for the appellant drew out attention to clauses   H
     336                    SUPREME COURT REPORTS           (1988] 2 S.C.R.

 A   9( a) and (b) as set out hereinbefore and submitted that the respondent
     was only entitled to the amount as determined by the Manager which
     was described as final. Sree Sen submitted that according to clause
     9(a) aforesaid the adjudication made by the manager was final and          ' "·
     there was no dispute thereafter and therefore, there could be no
     determination beyond 25%. He drew our attention to that part of the
 B clause 9(a) to the following effect "the decision of the manager in this
    respect shall be final and binding on the Agent." So according to Sree
    Sen apart from what had been granted by the Manager for determina-
    tion on account of demurrage and wharfage charges, no further deduc-
    tion was possible nor was it arbitrable because it was final. He drew
    our attention to certain observation in Wadsworth v. Smith, L.R. Vol.
    VI Q.B. 332. There by a written agreement the plaintiff therein had
c agreed     to build four houses on land of defendant and the defendant to
    grant plaintiff a lease when the houses were completed; the architects
    of the defendant for the time being were to certify as to the progress of
    the work, and if there should be any unnecessary delay or unsatis-
    factory conduct on the part of the plaintiff with regard to the erection
D of the buildings, on any matter or thing connected therewith "the fact
   of such delay or unsatisfactory conduct to be ascertained and decided
    in writing by the architects, against whose decision there shall be no
    appeal", then it should be lawful for defendant to employ other
   persons to execute the works, and to sell the buildings and lease the
   land to other persons. On an application to make the agreement a rule
E of court under section 17 of the Common Law Procedure Act, 1854 of
   England, it was held by Cockburn, C.J., Blackburn and Mellor, JJ.
   that assuming the agreement to be "an agreement or submission to
   arbitration" within the section, the clause that there was to be no
   appeal against the decision of the architects amounted to "words
   purporting that the parties intended that it should not be made a rule
F  of   court." The question was raised whether the agreement was not a
   submission to arbitration. Cockburn, C.J. observed that this clause
   was certainly more like a submission to arbitration' it was on the
   confines of the two classes' but on the whole it seems to His Lordship
   to savour more of a mere architect's certificate than of a judicial pro-
   ceeding. Moreover, even if this were a submission within section 17,
G the Chief Justice thought that it could not be made a rule of court,          • •
   because it was clear that the parties intended that the matter should be
   left to the decision of the architects without appeal; but to make it a
   rule of court would be to submit the decision to the jurisdiction of the
   Court. Blackburn, J. agreed. His Lordship observed that where by an
   agreement the right of one of the parties to have or to do a particular
H thing was made to depend on the determination of a third person, that
            FOOD CORPN. v. SURENDRA TPT. CO. [MUKHARJI, J.)                337

    was not a submission to arbitration, nor was the determination an A
    award; but where there was an agreement that any dispute about a
•   particular thing shall be enquired into and determined by a person
    named, that might amount to a submission to arbitration, and the
    determination though in the form of a certificate, be an award. Han-
    nen, J. was of the view that this is not an agreement or submission to
    arbitration; the clause in question appeared to be no more than an B
    extension of the ordinary clause in building contracts, that the certifi-
    cate of the architect should be conclusive as to work done and the
    mode of doing it.

           If we proceed on this basis then the logical conclusion of this
    would be that where there is a decision by the manager as in the instant
    case that would be final. Where a dispute has been adjudicated by the
                                                                                   c
    manager in this aspect there was nothing for the arbitrator to decide. It
    appears to us on the facts as recorded by the arbitrator in his award
    that there was adjudication really by the Manager of the claims upto
    November, 1975. Thereafter there could be no adjudication as a result
    of injunction obtained from the court. Therefore, it appears to us that        D
    there was really, in fact, no adjudication of all the djsputes. The re-
    maining points were arbitrable because of the amplitude of the arbitra-
    tion clause. The relevant arbitration clause in this case contained, inter
    alia, as follows:

                "In the event of any question or dispute arising under this        E
                Agreement regarding the construction thereof or any
                clause herein or in respect of any act, matter or thing relat-
                ing to this agreement the same shall be referred to the Sole
                Arbitration of any person appointed by the Managing
                Director of the Food Corporation of India .......... .
                 . . . . . . . . The Award of such Arbitrator shall be final and   F
                binding on the parties to this Agreement ............... "

          The point there having been decision before the Manager, that
    disallowance of the claim beyond 25% was beyond the jurisdiction of
    arbitration was not agitated before the High Court. Prabir Kumar
    Majumdar, J. speaking for the Division Bench of the High Court of              G
    Calcutta observed at page 24 of the paper book as follows:

                "It has not been brought to our notice whether there has
                been any such decision by the Manager. Further, taking all
                the relevant materials into consideration, the learned
                arbitrator has made a finding in respect of the appellant's        H
    338                    SUPREME COURT REPORTS             [ 1988] 2 S.C.R.
                                                                                 )<.._,
A               claim and respondent's counter-claim in respect of demur-
                rage and wharfage charges."

          It has not been brought to our notice that there was any adjudi-
                                                                                 . "'
    cation by the Manager beyond the claim for the period of November,
     1975 as mentioned hereinbefore. Therefore, in our opinion, the
B   arbitrator was not in error in proceeding in the manner as he did.




                                                                                 J
    There was no other aspect of Jaw on this aspect of the matter to which
    our attention was drawn. The submission on this aspect is, therefore,
    negatived. The challenge to the award on this aspect must, therefore,
    fail.

          So far as the grant of interest pendente lite in the award is con-
c   cerned, reliance was placed on various decisions of this Court. Reliance      --f
    was placed on State of Orissa and others v. Construction India, (J.T.
    1987 4 S.C. 588) where the award of interest from the commencement
    of the proceedings before the Arbitrator to the date of the award was
                                                                                 .     ~



    disallowed in consonance with the views expressed by this Court in the
D   case of Executive Engineer Irrigation Galimala & Ors. v. Abaaduta
    Jena,) J.T. 1987 4 S.C. 8).

           Our attention was drawn by Dr. Ghosh counsel for the respon-
    dent firstly, to the decision in the case of Firm Madan/al Roshanlal
    Mahajan v. Hukumchand Mills Ltd., Indore, [1967] 1 S.C.R. 105.
E   There the respondent had filed a suit against the appellant claiming
    two sums as losses in respect of two items and interest on the same.
    The disputes were referred to an arbitrator, before whom the respon-         ,.,

                                                                                 ,
    dent did not press for interest prior to the institution of the suit, but      \
    pressed its claim for the two sums and interests from the date of the
    institution of the suit till recovery. Bachawat, J. speaking for the three
F   learned Judges of this Court held that though in terms, section 34 of
    the Code of Civil Procedure did not apply to arbitrations, it was an
    implied term of the reference in the suit that the arbitrator would
    decide the dispute according to law and would give such relief with
    regard to pendente lite interest as the Court could give if it decided the
    dispute. This power of the arbitrator, it was held, was not fettered
G   either by the arbitration agreement or by the Arbitration Act, 1940.

          Our attention was also drawn to the decision in the case of State
                                                                                 ~
    of Madhya Pradesh v. Mis. Saith & Skelton (P) Ltd., [1972] 3 S.C.R.
    233. There disputes had arisen between the appellant and the respon-
    dent with reference to the performance of a contract which provided
H   for arbitration. Steps were taken to appoint arbitrators and an umpire.
           FOOD CORPN. v. SURENDRA TPT. CO. IMUKHARJI, J.I            .l39



r~The   appellant filed a petition in the District Judge's Court, having
   jurisdiction over the matter for setting aside the nominations. When
   the matter came up to this Court in appeal, this Court appointed a sole
                                                                           A


   arbitrator with consent of the parties. Thereafter in the presence of
   counsel for both the parties, this Court gave directions in the appeal
   that the arbitration records be sent to the sole arbitrator and later
   extended the time for making the award and gave directions regarding B
   the venue. The arbitrator gave his award, directing the payment of a
   certain sum by the appellant to the respondent with simple interest at
   9% from the date anterior to the reference and filed the award in the
"·Court the next day. One of the questions that arose before this Court
   was whether the arbitrator had any jurisdiction to award the interest
   from a date anterior to the date of award or rcfernee. This Court held
- that the claim for the payment of interest had been referred to the
                                                                             c
   arbitrator. The contract did not provide that no interest was payable
 , on the amount that might be found due. Therefore, the respondent
   was entitled under section 61(2) of the Sale of Goods Act, 1930, to
   claim interest from the date on which the price became due and pay-
   able. The arbitrator had found that the price had become payable from f)
   a date anterior to the date of the award. Therefore, the award of
   interest from the anterior date was justified. The Court further held
   that the award of interest at 9% was also not exorbitant because the
   parties themselves claimed interest at 12 % .

        Our attention was also drawn to Mis. Ashok Construction Com-
  pany v. Union of India, [1971) 3 S.C.C. 66 where a bench of three
Wlearned Judges at page 68 of the report held that the terms of the
r arbitration agreement did not exclude the jurisdiction of the arbitrator
• to entertain a claim for interest, on the amount due under the contract
r and on this ground this Court upheld the grant of interest.
                                                                             F
         Our attention was drawn by Dr. Ghosh to the observations in the
  case of Mis. Alopi Parshad & Sons, Ltd. v. The Union of India, [1960)
  2 S.C.R. 793. This Court reiterated the well-settled principle that an
  award was liable to be set aside because of an error apparent on the
 .face of the award. An arbitration award may be set aside on the
  ground of an error on the face of it when the reasons given for the        G
~decision, either in the award or in any document incorporated with it,
   are based upon any legal proposition which is erroneous.

           In a recent decision, Chinnappa Reddy, J. speaking for a bench
    of three learned Judges in Executive Engineer Irrigation Galimala' s
    case (supra) at paragraph 15 of the judgment considered the q ues-       II
    340                    SUPREME COURT REPORTS           [1988] 2 S.C.R.
                                                                               l
A  tion of award of interest by an arbitrator. The learned Judge noted the     ·~
   decisions in Hrm Madan/al Roshanlal Mahajan v. Hukamchand Hills             1
  Ltd. (supra) Ashok Construction Company v. Union of India, (supra)
  and the State of Madhya Pradesh v. Mis. Saith & Skelton Private
  Limited, (supra) and expressed the view that these were cases in which
B the references to arbitration were made by the court or in court pro-
  ceedings of the disputes in the suit. It was held that the arbitrator must
  be assumed in these cases to have the same power to award interest as
  the court. Therefore, the grant of pendente lite interest on the analogy
  of section 34 of the Civil Procedure Code was permissible. In regard to j
  interest prior to the suit, it was held in most of these cases that since
  the Interest Act, 1839 was not applicable, interest could be awarded if
C there was an agreement to pay interest or a usage of trade having.the
  force of law. This Court held in the last mentioned case that they are
  not entitled to claim interest for the period prior to the commence-
  ment of the arbitration proceedings for the reason that the Interest Act •
  did not apply to their case and there was no agreement to pay interest
D or any usage of trade. It was further held that the claimants were not
  entitled to claim pendente lite interest as the arbitrator was not a court
  nor were the references to arbitration made in suits.

        In deference to the latest pronouncement of this Court which is a
  pronouncement of three learned Judges, we must hold that the grant _
E of pendente /ite interest in this case was not justified. Though the
  award in this case is a speaking award, it was not made clear on what
  basis the interest was awarded. We are of the opinion that the ar-
  bitrator was in error in granting the interest in the manner he did. It is 4·
  true that in specific term there was no denial of this right to grant
  interest but there was denial as to get it in accordance with law.         ·

F         In the aforesaid view of the matter so far as the interest of the
    award is concerned we are of the opinion that in awarding the interest
    the arbitrator committed an error of law. With this modification the
    judgment and order of the Higb Court are confirmed. The appeal is
    disposed of in these terms without any order as to costs.
G S.L.                                                 Appeal disposed of.
                                                                              -4


Search Indian case law

Ask in plain English, not just keywords. 25,000 AI words free, no card.

Try "Arbitration"Sign in to search

For a digitally signed copy suitable for filing, refer to the court's own website. Only the court can issue one.