Created byFuzzy Cloud

Supreme Court of India

GENERAL MANAGER NORTHERN RAILWAYS AND ANR.versusSARVESH CHOPRA

Citation
2002 INSC 114
Decided
1 March 2002
Disposal
Appeal(s) allowed

Holding

The four claims are excepted matters and cannot be referred to arbitration; the court must first assess arbitrability under Section 20.

Summary

The appellant, General Manager Northern Railways, entered into a construction contract with the respondent, Sarvesh Chopra, which contained both General and Special Conditions. Disputes arose and the respondent filed a petition under Section 20 of the Arbitration Act, 1940 seeking arbitration of six claims. The trial court referred only two claims to arbitration, deeming the remaining four as 'excepted matters' under Clause 63 of the General Conditions; the Division Bench reversed this view and ordered all six claims to be arbitrated. On appeal, the Supreme Court held that the four claims are indeed excepted matters, not arbitrable, and that a court must first determine whether a claim falls within the scope of the arbitration agreement before referring it to an arbitrator. The Court clarified that the existence of an in‑house remedy is not a prerequisite for a matter to be classified as excepted, and that the issue of arbitrability can be examined at any stage of the arbitration process. Consequently, the appeal was allowed, the Division Bench decision set aside, and the trial court's original order restored.

Issues considered

  • Whether the four claims raised by the respondent are 'excepted matters' under Clause 63 of the General Conditions of the Railway contract and thus non‑arbitrable.
  • Whether a court, while entertaining a petition under Section 20 of the Arbitration Act, 1940, must determine the arbitrability of the dispute before referring it to an arbitrator.

Legislation cited

Subjects

ArbitrationExcepted mattersSection 20ArbitrabilityConstruction contractRailway contractIn‑house remedyIndian Contract Act

Judgment

A         GENERAL MANAGER NORTHERN RAILWAYS AND ANR.
                              v.
                       SARVESH CHOPRA

                                  MARCH I, 2002

B                  [R.C. LAHOTI AND BRIJESH KUMAR, JJ.]


          Arbitration:

          Arbitration Act, 1940-Section 20-Excepted matters-Criteria of-
C Reference of excepted matters to arbitration-Held, the function of reference
    of matters to arbitration by Court is not a mechanical administrative function
    but a judicial function-Jn house remedy for settlement of a matter is not a
    prerequisite for treating the matter to be an excepted matter-On facts, the
    claims are excepted matters and hence cannot be referred for arbitration-
D   Contract Act, 1872-Sections 55 and 56.

           Respondent was granted a construction contract by appellant-               >-- _
    Railways. The contract is subject to the General Conditions and Special
    Conditions of the contract of Railways. Due to certain disputes, the respondent
    filed a petition before High Court under Section 20 of the Arbitration Act,               ;
E   1940 praying for filing of the arbitration agreement in the Court and for
    reference of the six claims set out in the application to arbitration for
    settlement The Single Judge directed only the first two claims for arbitration
    and treated the remaining four claims as 'excepted matters' being within
    clause 63 of the General Conditions of the contract and thereby not arbitrable.
F   In appeal by the respondent, Division Bench of the High Court held that the
    four claims are not 'excepted matters' and hence directed for arbitration.

          In appeal to the Court, the appellant contended that the four claims
    are covered by different clauses of the Special Conditions of the Contract and
    hence not arbitration as per clause 63 of the General Conditions of the
G   contract.

           The respondent contended that a matter cannot be treated as an
            \
    'excepted matter' if it is merely covered by any of the clauses in the Special
    Conditions of the contract and no in-house remedy is provided by way of
    decision of an authority of the Railways; and that on filing a petition under
H                                        156
                  GENERAL MANAGER NORTHERN RAILWAYS v. SAR VESH CHOPRA             l 57
       Section 20 of the Act, the Court should order the arbitration agreement to         A
       be filed and make an order of reference to the arbitrator and it is for the
       arbitrator to adjudicate whether a claim is entertainable or awardable being
       an 'excepted matter'.

             Allowing the appeal, the Court
                                                                                          B
             HELD: 1.1. While dealing with a petition under Section 20 of the
       Arbitration Act, 1940, the Court has to examine: (i) whether there is an
       arbitration agreement between the parties, (ii) whether the difference which
       has arisen is one to which the arbitration agreement applies, and (iii) whether
       there is a cause, shown to be sufficient to decline an order of reference to the   C
       arbitrator. The reference to an arbitration on a petition filed under section
       20 is not a function to be discharged mechanically or ministerially by the
       Court. It is a consequence of judicial determination, the Court having applied
       its mind to the requirements of Section 20 and formed an opinion, that the
       difference sought to be referred to arbitral adjudication is one to which the
       arbitration agreement applies. [163-F-G[                                           D
'°"·         1.2. The Court will look at the nature of the claim as preferred and
       decide whether it falls within the category of 'excepted matters'. If the claim
       preferred would be a difference to which the arbitration agreement does not
       apply, then the Court shall not refer the same to the arbitrator. On the           E
       pleading, 'the applicant may succeed in making out a case for reference, still
       the arbitration may, on the material produced before him, arrive at a finding
       that the claim was covered by 'excepted matters'. The claim shall have to be
       disallowed. If the arbitrator allows a claim covered by an excepted matter,
       the award would not be legal merely because the claim was referred by the
       Court to arbitration. The award would be liable to be set aside on the ground      F
       of error apparent on the face of the award or as vitiated by legal misconduct
       of the arbitrator. [166-G-H)

             Food Corporation of India v. Sreekanth Transport, (1999] 4 SCC 491;
       Union ofIndia v. Popular Builders, Calcutta. (2000] 8 SCC 1; Steel Authority of G
       India Ltd v. J.C. Budharaja, Government and Mining Contractor, (1999] 8 SCC
       122; Ch Ramlinga Reddy v. Superintending Engineer and Anr., (1994) 5 Scale
       12; Mis A/opi Parshad v. Union of India, (1960] 2 SCR 793; Mis Prabartak
       Commercial Corporation Ltd v. The ChiefAdministrator Dandakaranya Project
       and Anr.• (1991) 1 SCC 498 and Continental Construction Co. Ltd v. State of
       Madhya Pradesh, [1998) 3 sec 82, referred to.                                   H
         158                     SUPREME COURT REPORTS                    [2002] 2 S.C.R.

A             State ofA.P. v. Mis Associated Engineering Enterprises, Hyderabad, AIR
         (1990) A.P. 294, approved.

               Hudson's Building and Engineering Contracts 11th Edition; Chitty on
         Contracts 28th Edition, 1999 and Russel on Arbitration 21st Edition, 1997,
         referred fo. ·
B
                1.3. If it is a matter excepted from the arbitration agreement, the Court
         shall be justified in withholding the reference. To be an 'excepted matter' it
         is not necessary that a departmental or 'in-house' remedy (or settlement of
         claim must be provided by the contract Merely for the absence of provision
                                   ..
         for in-house settlement of the claim, the claim does not cease to be an excepted    ~-
C        matter. An issue of arbitrability of claim is available for determination at all
         the three stages-while making reference to arbitration, in the course of arbitral
         proceedings and whit~ inaking the award a rule of the Court [167-D]

               1.4. The statement of claims, as set out in the petition under section 20
D        of the Act, does not even prima facie suggest why such claims are to be taken
         out of the category of 'excepted matters' and referred to arbitration. It would
         be an exercise in futility to refer for adjudication by the arbitrator a claim
         though not arbitrable, and thereafter set aside the award if the arbitrator         ,Jo--
         chooses to allow such Claim. The High Court was not right in directing the
         said claims to be referred to arbitration. [167-F)      '
E
    <;
               2.1. A decision of this Court.is an authority for the proposition which it
         decides and not for what it has not decided or had no occasion to express·an
         opinion _on:.                                    ·.
                   .                                  ,.                     .·.
               Vishwanath Soodv. Union ofIndia and Anr., [1989) 1 SCC 657 and Food
                                                                                              ~



F        .Corporation·of India v. Sreekanth Transport, [1999) 4 sec 49~, distinguished.
                 CIVIL APPELLATE JURISDICTION : Civil Appeal No. 1791 of
         2002.

                 From the Judgment and Order dated 28.2.2000 of the Delhi High
G, Court in F.A.O. No. 31 of·19.89.

            · Mukul Rohtagi; Additional Solicitor General, A.D.N. Rao and Anil
         Katiyar for the Appellants.

                 K.R. Gupta, Ms. Neena Gupta, S. Chakraborty and Sudhir Kumar
H . Gupta for the Respondents.                                .
  GENERAL MANAGER NORTHERN RAILWAYS v. SARVESH CHOPRA [R.C. LAHOTl,J.) 159


     The Judgment of the Court was delivered by                                    A
       R.C. LAHOTI, J. The respondent was granted by the appellants work
of construction on bored piles 500 mm dia by cast in Situ method for widening
anc! raising of Pul Mithai (S). A contract was entered into between the parties
on 27.4.1985. The contract is subject to the General conditions of the contract
of Railways read with Special Conditions, Disputes arose between the parties B ·
and the respondent moved a petition under Section 20 of the Arbitration Act,
 1940 praying for the arbitration agreement being filed in the Court and six
claims set out in the petition being referred to the Arbitraior. for settlement. .
The learned Single Judge of the High Court of Delhi (Original Side) directed
two claims to be referred but as to claims numbers 3 to 6 for.med an opinion C
that t\le claims being 'excepted matters' within the meaning of Clause 63 of
General Conditions of Contract were not .liable to be referred to arbitration.
An intra-Court Appeal preferred by respondent has been allowed and the four
claims have also been directed to be referred by the Division Bench to arbitrator ·
on for.ming an opinion that they were not covered by 'excepted matters'. The
appellants have filed this petition seeking special leave to appeal against the D
decision of Division Bench.

      Leave granted.

      Clause 63 of the General Conditions of the Contract ifrovides as under:-.
                                                                                   E
       ·"Matters finally determined by the Railway - All disputes and
        differences of any kind whatsoever arising out of or in connection
        with the contract, whether during the progress of the work or after its
        completion and whether before or after the determination of the
        co~tract, shall be referred by the contractor to the Railway and the       F
        Railway shall within a reasonable time after receipt of the Contractor's
        representation make and notify decisions on all matters referred to by
        the contractor in writing provided that matters for which provision
        has been made in clauses 18, 22(5), 39, 45(a), 55, 55-A(5), 61(2) and
        62(1) (XIl)(B)(eXb) of the General conditions of Contract or in any
        clauses of the special conditions of the contract shall be deemed as       0
        excepted matters and decisions thereon shall be final and binding on
        the contractor provided further that excepted matters shall stand
        specifically excluded from the purview of the· arbitration clause and
        not be referred to arbitration."

      Clauses 9.2., 11.3 and 21.5 of Special Conditions of contract are as         H
    160                    SUPREME COURT REPORTS                   [2002] 2 S.C.R.

A under:-
            "9.2. No material price variation or wages escalation on any account,
            whatsoever and compensation for "Force Majeure" etc. shall be
            payable under this contract.

B           ll .3. No claim whatsoever will be entertained by the Railway on al
            c of any delay or hold up of the works arising out of delay in supply
            of drawings, changes, modifications, alterations, additions, omissions,
            omissions in the site layout plans or detailed drawings or designs and
            or late supply of such materials as are required to be arranged by the
            Railway or due to any other factor on Railway Accounts.                   ~..

c
            21.5. No claim for idle labour and/or idle machinery etc. on any
            account will be entertained. Similarly no claim shall be entertained
            for business loss or any such loss."

          Claims numbers 3 to 6 whereon reference is sought for by the respondent
D to the Arbitrator are as under:-
          3.   There occurred tremendous increase in cost of building materials.
               52 Nos. of piles were bored after the expiry of stipulated
               completion period and particularly when the prices were too high.
               Additional cost incurred @ Rs. 250 for these 42 Nos. of piles
E              may please be paid. This has also been verified by your staff at
               site, Rs. 250 x 42 Rs. I 0500.
          4.   Piling rig with diesel driven wench, mixture, machine, driving
               pipe, wheel barrows, hoppers and other tools and plants remained
               idle at site for 24 months, i.e. for 75 days. The entire machinery
F              was procured from the market on hire charges. Rent was paid
               @Rs.1070 per day for this machinery. Hire charges amounting to
               Rs. 80,250 (l070x75) may please be reimbursed.

          5.   The site was not made available for one month. Changes took
               place and decisions were delayed. The Work which was required
G              to be completed within 3 Yi months but dragged on for additional
               period of 6 months. Establishment period of 6 months at a cost
               of Rs. I 0,000 per month. These losses may please be paid. (Rs.
               10,000 x 6 Rs. 60,000).
          6.   The work of Rs. 5,95,000 was required to be completed within
H              3 Yi months meaning thereby, monthly progress would not be less
  GENERAL MANAGER NORTHERN RAILWAYS v. SARVESH CHOPRA [R.C. LAHOTI, J.)        161

             than Rs. 1,75,000. As against the entire work could be completed          A·
             within a period of 9V. months i.e. Rs. 75,000 per month. The
             losses sustained for less output may be compensated and this
             comes to Rs. 40,000."
      According to the appellants, claims numbers 3, 4 and 5 are covered
respectively by Clauses 9.2, 21.5 and 11.3. Claim No. 6 is covered by Clause           B
11.3 of Special Conditions. On this there does not appear to be any serious
controversy. The core issue is the interpretation of Clause 63 of the General
Conditions and Section 20 of the Arbitration Act, 1940.
        A bare reading of Clause 63 shows that it consists of three parts. Firstly,
 it is an Arbitration Agreement requiring all disputes and differences of any          C
 kind whatsoever arising out of or in connection with the contract to be referred
 for adjudication by arbitration, by the Railways, on a demand being made by
 the contractor through a representation in that regard. Secondly, this agreement
 is qualified by a proviso which deals with 'excepted matters'. 'Excepted
  matters' are divided into two categories: (i) matters for which provision has
  been made in specified clauses of the General Conditions, and (ii) matters           D
 covered by any clauses of the Special Conditions of the Contract. Thirdly, the
 third part of the clause is a further proviso, having an overriding effect on the
 earlier parts of the clause, that all 'excepted matters' shall stand specifically
  excluded from the purview of the Arbitration Clause and hence shall not be
 referred to arbitration. The source of controversy is the expression - "matters       E
  for which provision has been made ...... .in any clauses of the Special Conditions
  of the contract shall be deemed as 'excepted matters' and decisions thereon
  shall be final and binding on the contractor." It is submitted by the learned
  counsel for the respondent that to qualify as 'excepted matters' not only the
  relevant clause must find mention in that part of the contract which deals
  with special conditions but should also provide for a decision by an authority       F
  of the Railways by way of an 'in-house remedy' which decision shall be final
  and binding on the contractor. In other words, if a matter is covered by any
  of the clauses in the Special Conditions of the contract but no remedy is
  provided by way of decision by an authority of the Railways then that matter
  shall not be an 'excepted matter'. The learned counsel supported his submission      G
   by reading out a few clauses of General Conditions and Special Conditions.
   For example, vide Clause 18 of General Conditions any question or dispute
  as to the commission of any offence or compensation payable to the Railway
  shall be settled by the General Manager of the Railway in such manner as he
· shall consider fit and sufficient and his decision shall be final and conclusive.
  Vi de Clause 2.4.2.(b) of Special Conditions a claim for compensation arising        H
     162                    SUPREME COURT REPORTS                   [2002] 2 S.C.R.

,A   on account of dissolution of contractor's firm is to be decided by Chief ·
     Engineer (Construction) of the Railway and his decision in the matter shall
     be final and binding on the contractor. Vide clause 12.1.2. of Special
     Conditions a dispute whether the cement stored in the godown of the contractor
     is fit for the work is to be decided by the Engineer of Railways and his
B    decision shall be final and binding on the contractor. The learned counsel
     submitted that so long as the remedy of decision by.some one though he may
     be an authority of the Railways is not provided for, the contractor's claim
     cannot be left in lurch by including the same in 'excepted matters'. We find
     it difficult to agree.

C ,         In our opinion those claims which are covered by several clauses of the
     Special Conditions of the Contract can be categorized into two. One category·
     is of such claims which are just not Ieviable or entertainable. Clauses 9.2.,.
     11.3 and 21.5 of Special Conditions are illustrative of such claims. Each of
     these clauses provides for such claims being not capable of being raised or
     adjudged by employing such phraseology as !'shall not be payable.", "no
D    claim whatsoever will be entertained by the Railway", or "no claim. will/shall
     be entertained". These are 'no claim', 'no damage', or 'no liability' clauses.
     The other category of claims is where the dispute or difference has to be
     determined by an authority of Railways as provided in the relevant clause. In
     such other category fall such claims as were read out by the learned counsel
E    for the respondent by way of illustration from several clauses of the contract
     such as General Conditions Clause 18 and Special Conditions Clause 2.4.2.(b)
     and 12. l.2. The first category is an 'excepted matter' because the claim .as
     per terms and conditions of the contract is simply not entertainable; the
     second category of claims falls within 'excepted matters' because the claim
     is liable to be adjudicated upon by an authority of the Railways whose decision
F    the parties have, under the contract, &greed to. treat as final and binding and
     hence not arbitrable. The expression "and decision thereon shall be final and
     binding on the contractor"· as occurring in Clause 63 refers to th~ second
     category of 'excepted matters'.

G      . The learned counsel for the respondent placed reliance on Vishwanath
     Sood v. Union of India and Anr., [1989] 1 SCC 657, and Food Corporation
     of India v. Sreekanth Transport, [ 1999] 4 SCC 491 to strengthen his submission
     that an 'excepted matter' should be one covered by a clause which provides
     for a departmental remedy and is not arbitrable f<?r that reason. We have
     carefully perused both the decisions. Vishwanath Sood's case is one wherein
H    Clause 2 of the contract envisaged determination of the amount of
       GENERAL MANAGER NORTHERN RA1LWAYS t•. SARVESHCHOPRA [R.C. LAHOit, J.}     163

     compensation for the delay in the execution of work only by the Superintending    A
     Engineer whose decision in writing shall be final. In Food Corporation of
     India's case also the relevant clause provided for the decision of Senior
     Officer being final and binding between the parties. Both were considered to
     be 'excepted matters'. A decision of this Court is an authority for the
     proposition which it decides and not for what it has not decided or had no        B
     occasion to express an opinion on. The two decisions relied on by the learned
     counsel for the respondent hold a Clause providing a departmental or in-
     house remedy and attaching finality to decision therein to be an 'excepted
     matter' because such were the Clauses in the contracts which came up for the
     consideration of this Court. Those decisions cannot be read as holding nor
     can be relied on as an authority for the proposition by reading them in a         C
     negative way that if a departmental remedy for settlement of claim was not
     provided then the claim would cease to be an 'excepted matter' and such
     should be read as the decision of this Court.

            It was next submitted by the learned counsel for the respondent that if
     this Court was not inclined to agree with the submission of the learned D
     counsel for the respondent and the interpretation sought to be placed by him
,~   on the meaning of 'excepted matter' then whether or not the claim raised by
     the contractor is an 'excepted matter' should be left to be determined by the
     arbitrator. It was submitted by him that while dealing with a petition under
     Section 20 of the Arbitration Act, 1940 the Court should order the agreement E
     to be filed and make an order of reforence to the arbitrator appointed by the
     parties leaving it open for the arbitrator to adjudicate whether a claim should
      be held to be not entertainable or awardable being an 'excepted matter'. With
     this submission too we find it difficult to agree. While dealing with a petition
      under Section 20, the Court has to examine: (i) whether there is an arbitration
      agreement between the parties, (ii) whether the difference which has arisen F
      is one to which the arbitration agreement applies, and (iii) whether there is
      a cause, shown to be sufficient, to decline an order of reference to the arbitrator.
      The word 'agreement' finding place in the expression 'where a difference has
      arisen to which an agieement applies', in sub-section(!) of Section 20 mea.lS
      'arbitration agreement'. The reference to arbitrator on a petition filed under G
     Section 20 is not a function to be discharged mechanically or ministerially by
     the Court; it is a consequence of judicial determination, the Court having
     applied its mind to the requirements of Section 20 and formed an opinion,
      that the difference sought to be referred to arbitral adjudication is one to
      which the arbitration agreement applies. In the case of Food Corporation of
      India (supra), relied on by the learned counsel for the respondent, it has been H
      164                     SUPREME COURT REPORTS                    [2002) 2 S.C.R.

 A held as the consistent view of this Court that in the event of the claims arising
      within the ambit .of 'excepted matters', the question of assumption oC·
      jurisdiction by any arbitrator either with or without the intervention of the
      Court would not arise. In Union of India v. Popular Builders, Calcutta,
      [2000] 8 SCC l, and Steel Authority of India Ltd. v. J.C. Budharaja,
      Government and Mining Contractor, [1999] 8 SCC 122, Ch. Ramlinga Reddy
 B    v. Superintending Engineer & Anr., (1994) 5 Scale 12 (pr.18), Mis Alopi
      Parshad v. Union of India, [1960] 2 SCR 793 at page 804 this Court has
      unequivocally expressed that an award by an arbitrator over a claim which
      was not arbitrable as per the terms of contract entered into between the
      parties would be liable to be set aside. In Mis. Prabartak Commercial
 C    Corporation Ltd. v. The Chief Administrator Dandakaranya Project & Anr.,
      [ 1991] l SCC 498, a claim covered by 'excepted matter' was referred to
      arbitrator in spite of such refer:ence having been objected to and the arbitrator
      gave an award. This court held that the arbitrator had no jurisdiction in the
      matter and that the reference of the dispute to the arbitrator was invalid and
      the entire proceedings before the arbitrator including the awards made by
·.o   him wete null and void. In Continental Construction Co. Ltd. v. State of
      Madhya Pradesh, [ 1988] 3 SCC 82, the contract provided for the work being
      completed by the contractor in spite of rise in prices of material and labour
      charges at the rates stipulated in the contract. It was held that on the contractor
      having completed the work, it was not open to him to claim extra cost
 E    towards rise in prices of material and labour. An award given by the arbitrator
      for extra claim given by the contractor was held to be vitiated on the ground
      of misconduct of arbitrator. There were specific clauses in the agreement
      which barred consideration of extra claims in the event of price escalation.

             In Ch. Ramalinga Reddy v. Superintending Engineer and Anr., (1994)
 F     5 Scale 67, claim was allowed by arbitrator for "payment of extra rates for
       work done beyond agreement time at schedule of rate prevailing at the time
      of execution". Clause 59 of A.P. Standard Specifications, which applied to
       the contract between the parties, stated that no claim for compensation on
      account of delays or hindrances to the work from any cause would lie ex(;ept
 G    .as therein defined. The claim was found to be outside the defined exceptions.
      When extensions of time were granted to the appellant to complete the work
      the respondents made it clear that no claim for compensation would lie. For
      both these reasons, this Court held that it was impennissible to award such
      claim because the arbitrator was required to decide the claims referred to him ..
      having regard to the contract between the parties and, therefore, his jurisdiction
H     was limited by the terms of the contract
       GENERAL MANAGER NORT~-tERN RAILWAYS v. SARVESH CHOPRA (R.C. LAHOTI, J.] 165

           A Division Bench decision of High Court of Andhra Pradesh in State            A
     of A.P. v. Mis. Associated Engineering Enterprises, Hyderabad, AIR (1990)
     A.P. 294, is of relevance. Jeevan Reddy, J. (as His Lordship then was),
     speaking for the Division Bench, held that where clause 59 of the standard
     terms and conditions of the contract provided that neither party to the contract
     shall claim compensation "on account of delays or hindrances of work from           B
     any cause whatever", an award given by an arbitrator ignoring such express
     tem1s of the contract was bad. We find ourselves in agreement with the view
     so taken.


--           In Hudson's Building and Engineering Contracts (I Ith Edition, pp.1098-
     9) there is reference to 'no damage' clauses, an American expression, used          C
     for describing a type of clause which classically grants extensions of time for
     completion, for variously defined 'delays' including some for which, as
     breaches of contract on his part, the owner would prima facie be contractually
     responsible, but then proceeds to provide that the extension of time so granted
     is to be the only right or remedy of the contractor and, whether expressly or
     by implication,. that damages or compensation are not to be recoverable             D
     therefor. These 'no damage' clauses appear to have been primarily designed
     to protect the owner from late start or co-ordination claims due to other
     contractor delays which would otherwise arise. Such clauses originated in
     Federal Government contracts but are now adopted by private owners and
     expanded to cover wider categories of breaches of contract by the owners in         E
     situations which it would be difficult to regard as other than oppressive and
     unreasonable. American jurisprudence developed so as to avoid the effect of
      such clauses and permitted the contractor to claim in four situations, namely"
      (i) where the delay is of a different kind from that contemplated by the
      clause, including extreme delay, (ii) where the delay amounts to abandonment,
      (iii) where the delay is a result of positive acts of interference by the owner,   F
      and (iv) bad faith. The first of the said four exceptions has received
      considerable support from judicial pronouncements in England and
      Commonwealth. Not dissimilar principles have enabled some commonwealth
      courts to avoid the effect of 'no damage' clauses. [See Hudson, ibid].
                                                                                         G
            In our country question of delay in performance of contract is governed
     by Sections 55 and 56 of the Indian Contract Act, 1872. If there is an abnormal
     rise in prices of material and labour, it may frustrate the contract and then the
     innocent party need not perform the contract. So also, if time is of the essence
     of the contract, failure of the employer Lo perform a mutual obligation would
     enable the contractor to avoid the contract as the contract becomes voidable        H
      166                      SUPREME COURT REPORTS                    [2002) 2 S.C.R.

  A at his option. Wh~re time is "of the essence" of an obligation, ChittY on ·"'
      Contracts (Twenty-Eighth Edition, 1999, at p.1106, para 22-015) states "a
      failure to perform by the stipulated time will entitle the innocent party to (a)
      terminate performance of the contract and thereby put an end to all the
      primary obligations of both parties remaining unperformed; and (b) claim
                                                                                            ...
. B damages from the contract-breaker on the basis that he has committed a
      fundamental !;>reach ofthe cc.mtract ("a breach going to the root of the contract")
      depriving the innocent party of tpe benefit of the contract ("damages for loss
      of the whole transaction").'' If, instead of avoiding the contract, the contractor
      accepts the belated performance of reciprocal obligation on the. part of the
     _employer, the innocent party, i.e. the contractor, canµot claim compensation
  C for any loss occasioned by the non-performance of the reciprocal promise by
      the employer at the time agreed, "unless, at the time of such acceptance, he
      gives notice to the promisor of his intention to do so". Thus, it appears that
      under the Indian law, in spite of there being a contract between the parties
      whereunder the contractor has undertaken not to make any claim for delay
  D in performance of the contract occasioned by an act of the employer, still a
    . claim would be entertainable in one of the following situations: (i) if the
      contractor repudiates the contract exer<:ising his right to do so under Section
      5.5 of the Contract Act; (ii) the employer gives an extension of time either by
   , entering fato supplemental agteement or by making it clear that escalation of
      rates or compemation for delay would be permissible, (iii) if the contractor
  E makes it clear that escalation of rates or compensation for delay shall have
      to be made by the employer and the employer accepts performance by the
      contractor in. spite of delay and such notice by the contractor putting the
      employer on terms.
            Thus, if may be open to prefer a claim touching an apparently excepted
 F matter subject to a clear case having been made out for excepting or excluding
      the claim from within the four corners of "excepted matters". While dealing
      with a petition under Section 20 of the Arbitration Act, the Court will look
      at the nature of the claim as preferred and decide whether it falls within the
      category of"excepted matters". If so, the claim preferred would be a difference
 G    to which the arbitration agreement does not apply, and therefore, the Court
      shall not tefer the same to the arbitrator. On the pleading, .the applicant may
      succeed in making out a case for reference, still the arbitrator may, on the
      material produced before him, arrive at a finding that the claim was covered ·
      by "excepted matters". The claim shall have to be disallowed. If the arbitrator
      allows a claim covered by an excepted matter, the award would not be legal
 H    merely because the claim was referred by the Court to arbitration. The award
        GENERAL MANAGER NORTHERN RAILWAYS v. SARVESH CHOPRA [R.C. LAHOTI, J.) 167

    · would be liable to be set aside on the ground of error apparent on the face A
      of the award or as vitiated by legal misconduct of the .arbitrator. Russell on
      Arbitration (Twenty-First Edition, 1997) states vide para 1.027 (at p.15)
      "Arbitrability. The issue of arbitrability can arise at three stages in an
      arbitration; first, on an application to stay the arbitration, when the opposing
•     party claims that the tribunal lacks the authority to determine a dispute because B
      it is not arbitrable, second, in the course of the arbitral proceedings on the
      hearing of an objection that the tribunal lacks substantive jurisdiction and
      third, on an application to challenge the award or to oppose its enforcement.
      The New York Convention, for example, refers to non-arbitrability as a ground
      for a court refusing to recognize and enforce an award." To sum up, our
      conclusion are: (i) while deciding a petition under Section 20 of the Arbitration C
      Act, 1940, the Court is obliged to examine whether a difference which is
      sought to be referred to arbitration is one to which the arbitration agreement
      applies. If it is a matter excepted from the arbitration agreement, the Court
      shall be justified in withholding the reference, (ii) to be an excepted matter
     ._it is not necessary that a departmental or 'in-house' remedy for settlement of


-     claim must be provided by the contract Merely for the absence of provision D
      for in-house settlement of the claim, the claim does not cease to be an excepted·
      matter, (iii) an issue as to arbitrability of claim is available for determination
      at all the three stages - while making reference to arbitration, in the course
      of arbitral proceedings and while making the award a rule of the Court.
                                                                                           E
             In the case before us, the claims in question as preferred are clearly
      covered by "excepted matters". The statement of claims, as set out in the
      petition under Section 20 of the Arbitration Act, does not even prima facie
      suggest why such claims are to be taken out of the category of "excepted
      matters" and referred to arbitration. It would be an exercise in futility to refer
      for adjudication by the arbitrator a claim though not arbitrable, and thereafter,    F
      set aside the award if the arbitrator chooses to allow such claim. The High
      Court was, in our opinion, not right in directing the said four claims to be
      referred to arbitration.

              After the hearing was concluded the learned counsel for the respondent       G
       cited a few decisions by making a mention, wherein the view taken is. that
       'interpretation of contract' is a matter for arbitrator to decide and the Court
    .. cannot substitute its own decision in place of the decision of the arbitrator.
       We do not think that the cited cases have any relevance for deciding the
       question arising for consideration in this appeal. None of the cases is an
       authority for the proposition that the question whether a claim is an 'excepted     H
                                                                                        .·,




    168                     SUPREME COURT REPORTS                    [2002] 2 S.C.R.

A matter' or not must be left to be decided by the arbitrator only and not
    adjudicated upqn by the Court while disposing of a petition under Section 20
    of the Arbitration Act, 1940. We cannot subscribe to the view that interpretation
    of arbitration clause itself can be or should be left to be determined by
    arbitrator and such determination cannot be done by Court at any stage.
                                                                                        .
B         For the foregoing reasons we are of the opinion that the view of the
    'excepted matters' taken by the Division Bench of the High Court cannot be
    sustained. The appeal is allowed, the impugned decision of the Division
    Bench of the High Court is set aside and that of the learned Single Judge is
    restored .. No order as to the costs.
c ·B.S.                                                            Appeal allowed.


Search Indian case law

Ask in plain English, not just keywords. 25,000 AI words free, no card.

Try "Arbitration"Sign in to search

For a digitally signed copy suitable for filing, refer to the court's own website. Only the court can issue one.