Created byFuzzy Cloud

Supreme Court of India

GR GREEN LIFE ENERGY PVT. LTD.versusLEITWIND SHRIRAM MANUFACTURING PVT. LTD.

Citation
2021 INSC 107
Decided
22 February 2021
Disposal
Disposed off

Holding

Parties may, by mutual agreement, modify their arbitration agreement and appoint a sole arbitrator, thereby superseding the contractual provision for a three‑member tribunal.

Summary

The appellant contractor and respondent entered a development agreement for a wind‑farm project that contained an arbitration clause providing for a three‑member tribunal, each party appointing one arbitrator who would then select a presiding arbitrator. A dispute arose over payments; the respondent invoked arbitration, nominated its arbitrator and sought the appointment of the appellant’s arbitrator under Section 11(6) of the Arbitration and Conciliation Act, 1996. The Madras High Court directed the appellant to nominate an arbitrator, thereby enabling the formation of the three‑member tribunal. The appellant also filed a claim under the Micro, Small and Medium Enterprises Development Act, 2006, but the court noted that the Act does not provide for counter‑claims. The appellant challenged the High Court order before the Supreme Court. During the Supreme Court proceedings the parties mutually agreed to have a sole arbitrator appointed by the court, superseding the original three‑member clause. The Supreme Court appointed a former High Court judge as sole arbitrator, closed the MSMED application, and disposed of the appeal.

Issues considered

  • Whether the High Court was justified in appointing an arbitrator for the appellant under Section 11(6) when the agreement stipulated a three‑member tribunal.
  • Whether the parties may, by mutual consent, replace the contractual three‑member arbitration panel with a sole arbitrator appointed by the court.
  • Whether the MSMED Act’s facilitation council can entertain counter‑claims against a contractor.

Legislation cited

Subjects

arbitrationappointment of arbitratorsole arbitratorSection 11MSMED Actfacilitation councilcontract disputewind farm project

Judgment

                         [2021] 1 S.C.R. 583                            583


              GR GREEN LIFE ENERGY PVT. LTD.                            A
                                 v.
     LEITWIND SHRIRAM MANUFACTURING PVT. LTD.
                   (Civil Appeal No.692 of 2021)
                         February 22, 2021                              B
       [INDU MALHOTRA AND AJAY RASTOGI, JJ.]
      Arbitration and Conciliation Act, 1996 – Appellant-contractor
and Respondent had entered into a agreement to set up a Wind
Farm Project – Agreement contained an arbitration clause (Clause
                                                                        C
20) – Disputes between the parties – Respondent invoked arbitration
under Clause 20 of the agreement, and nominated its arbitrator,
with request to Appellant to make nomination of its arbitrator –
Appellant failed to do so – Subsequently, Respondent filed petition
u/s.11(6) of the 1996 Act before the High Court, requesting the
Court to appoint an arbitrator on behalf of Appellant in terms of       D
Clause 20 of the agreement – High Court took the view that since
the parties had in their agreement agreed to refer all their disputes
under the 1996 Act, it was a fit case for appointment of arbitrator
and that the agreement provided for a three-member arbitral tribunal
– Respondent having already nominated its arbitrator, the Appellant
                                                                        E
was directed to appoint an arbitrator, and it was further directed
that on such nomination, the two arbitrators would appoint the
presiding arbitrator – Appeal before Supreme Court by Appellant-
Contractor – During proceedings before Supreme Court, the parties
agreed to have their disputes adjudicated under the Arbitration &
Conciliation Act, 1996 by a Court-appointed Sole Arbitrator –           F
Accordingly, the Supreme Court appointed a former Judge of the
Madras High Court, as the Sole Arbitrator.
      CIVIL APPELLATE JURISDICTION : Civil Appeal No. 692
of 2021.
      From the Judgment and Order dated 16.09.2020 of the High Court    G
of Judicature at Madras in Original Petition No. 300 of 2019.
     Ms. Shweta Sharma, Diggaj Pathak, Ravi Raghunath, Ms. Aakashi
Lodha, Sanyat Lodha, Advs. for the appearing parties.

                                                                        H
                                583
584            SUPREME COURT REPORTS                             [2021] 1 S.C.R.


A           The following Order of the Court was passed:
                                       ORDER
            Leave granted.
            1. The present Civil Appeal has been filed by the Appellant-
B     Contractor to challenge the Order dated 16.09.2020 passed on an
      Application filed under Section 11 of the Arbitration and Conciliation
      Act, 1996 by the Madras High Court in Original Petition No. 300 of
      2019.
            2.The Appellant and the Respondent had entered into a
C     Development Agreement dated 10.02.2014 to set up a Wind Farm Project
      in Sangli District in Maharashtra, which contained an arbitration clause.
            Clause 20 of the Agreement reads as :
            “20. Governing Law and Jurisdiction and Service of Process
            ….
D
            c) All disputes, differences and claims or any non-payment
            concerning the project work hereby created and / or touching this
            presents, arising out of or in relation to anything contained herein
            shall be referred to arbitration to be held at Chennai, under the
            provisions of Arbitration and Conciliation Act, 1996 (inforce from
E           time to time). The arbitration panel shall consist of three arbitrators,
            one arbitrator shall be appointed by each party and the arbitrators
            so appointed shall appoint the presiding arbitrator. The parties here
            to shall duly observe any interim award/s or direction/s of the
            arbitration tribunal and the award in pursuance to arbitration shall
F           be final and binding on the parties hereto. The arbitration
            proceedings shall be in English language.”
             3. Disputes arose between the parties with respect to claims raised
      by the Appellant-Contractor, which led to issuance of a legal notice dated
      21.04.2018 seeking payment of outstanding dues of Rs. 3,26,08,545/-.
G            4. The Respondent vide letter dated 21.01.2019 rejected the
      allegations in the notice, and contended that the Contractor had failed to
      provide services as agreed under the Development Agreement. It was
      further contended that the Appellant-Contractor was liable to refund an
      amount of Rs.10,26,00,000/- with Interest @ 15% p.a., and pay liquidated
H     damages of Rs. 1,54,00,000/- to the Respondent-Company.
      HGR GREEN LIFE ENERGY PVT. LTD. v. LEITWIND                           585
          SHRIRAM MANUFACTURING PVT. LTD.

      The Respondent invoked arbitration under Clause 20 of the             A
Agreement, and nominated its arbitrator, with a request to the Appellant
herein to make nomination of its arbitrator.
       5. On 18.03.2019, the Respondent herein filed a Petition under
Section 11(6) of the 1996 Act before the High Court of Madras, wherein
it was prayed that the Court may appoint an arbitrator on behalf of the     B
Appellant in terms of Clause 20 of the Development Agreement, since
the Contractor had failed to do so.
      6. Subsequently, the Appellant-Contractor, registered itself under
the Micro, Small and Medium Enterprises Development Act, 2006
(“MSMED Act”), and filed an application for resolution of disputes before   C
the Facilitation Council, Pune established under the MSMED Act.
       7. In the meanwhile, the Petition under Section 11 was taken up
for hearing before the High Court, wherein it was observed that there is
no provision under the MSMED Act for reference of counter-claims to
the Facilitation Council, and adjudication thereof. Sections 15 to 18 of    D
the MSMED Act provide for reference of disputes with respect to claims
made by a supplier / contractor registered under the MSMED Act. Even
though Section 24 of the MSMED Act gives overriding effect to the
MSMED Act, it would not be applicable in this case, since there is no
provision under this Act to deal with counter-claims filed against the
supplier-contractor.                                                        E

       The High Court took the view that since there is no provision for
raising counter-claims under the MSMED Act, and the parties had in
the Development Agreement dated 10.02.2014 agreed to refer all their
disputes under the 1996 Act, it was a fit case for appointment of the
arbitrator. The arbitration agreement provided for a three-member           F
tribunal. The Applicant (Respondent herein) had already nominated its
arbitrator, the Contractor was directed to appoint an arbitrator. On such
nomination, the two arbitrators would appoint the presiding arbitrator.
      8. The Appellant-Contractor challenged the aforesaid Order dated
16.09.2020 before this Court vide Special Leave Petition (C) No. 16027      G
of 2020.
       During the course of the proceedings, the parties have agreed to
have their disputes adjudicated under the Arbitration & Conciliation Act,
1996 by a Court-appointed Sole Arbitrator.
                                                                            H
586             SUPREME COURT REPORTS                          [2021] 1 S.C.R.


A            In view of the statement made by the Counsel for both parties on
      instructions, Clause 20 of the Development Agreement dated 10.02.2014
      stands superseded to the extent that the arbitration will be conducted by
      a three-member tribunal.
             We appoint Justice K. Kannan, former Judge of the Madras High
B     Court, as the Sole Arbitrator to adjudicate on all the claims and counter
      claims made by the parties arising out of the Development Agreement
      dated 10.02.2014. The arbitration will be conducted in accordance with
      the Arbitration and Conciliation Act, 1996. The arbitral proceedings shall
      be conducted by the Madras High Court Arbitration Centre in accordance
      with its Rules.
C
            The appointment of the Sole Arbitrator is subject to the
      Declarations to be made under Section 12 of the Arbitration and
      Conciliation Act, 1996 with respect to independence and impartiality,
      and the ability to devote sufficient time to complete the arbitration. The
      Sole Arbitrator will be paid fees as per the Schedule of the Madras High
D     Court Arbitration Centre (Administrative Cost and Arbitrators’ Fees)
      Rules, 2017.
            A copy of this Order be despatched to the Madras High Court
      Arbitration Centre, and Justice K. Kannan (Retd.) at the following
      address:
E
                “Justice K. Kannan
                3/11, Lakshmi Colony,
                North Crescent, T. Nagar
                Chennai - 600017
F
                Mob: +91-9780008145"
             9. In view of the aforesaid directions, the Application filed by the
      Appellant-Contractor under the MSMED Act, registered as MSFEC
      Case No. MH/26/M/PNE/02000 on 22.10.2020, will stand closed by the
G     Facilitation Council, Pune.
            10. The Appeal is disposed of in the aforesaid terms. Pending
      applications, if any, stand disposed.


H     Bibhuti Bhushan Bose                                      Appeal disposed of.


Search Indian case law

Ask in plain English, not just keywords. 25,000 AI words free, no card.

Try "arbitration"Sign in to search

For a digitally signed copy suitable for filing, refer to the court's own website. Only the court can issue one.