Created byFuzzy Cloud

Supreme Court of India

GUJARAT URJA VIKAS NIGAM LIMITED & ORS.versusRENEW WIND ENERGY (RAJKOT) PRIVATE LIMITED & ORS

Citation
2023 INSC 366
Decided
13 April 2023
Disposal
Appeal(s) allowed

Holding

PPAs entered into before the amendment are not subject to its retrospective application, do not need prior State Commission approval, and the findings of coercion and tariff revision are untenable; therefore the appeals are allowed and the impugned orders set aside.

Summary

The Supreme Court examined a dispute between Gujarat Urja Vikas Nigam Ltd (the appellant) and wind power developers over a Power Purchase Agreement (PPA) executed on 29‑03‑2012 under the REC Regulations, 2010. The respondents sought to have the tariff in the PPA revised after the Central Electricity Regulatory Commission’s second amendment (July 2013) changed the wording from ‘price not exceeding pooled cost’ to ‘at the pooled cost’. The State Commission and APTEL had held the amendment applicable and also found the PPA entered under coercion. The Court held that the PPA did not require prior State Commission approval, that the amendment was prospective and could not alter contracts executed before it, and that the allegation of coercion was unsupported. Consequently, the findings of the State Commission and APTEL were set aside and the appeals were allowed.

Issues considered

  • Whether a Power Purchase Agreement for renewable energy requires prior approval of the State Electricity Regulatory Commission.
  • Whether the second amendment to the REC Regulations, 2010 mandatorily revises the tariff terms of PPAs executed before its commencement.
  • Whether the respondents were coerced or acted under duress in entering into the PPA.
  • Whether the State Commission and APTEL could validly vary the terms of an existing PPA under tariff‑determination powers.
  • Whether the amendment to the REC Regulations operates retrospectively or prospectively.

Legislation cited

Subjects

Power Purchase AgreementRenewable Energy CertificatesTariff determinationCoercionDuressRetrospective amendmentRegulatory commissionElectricity ActRenewable energy lawContract enforceability

Judgment

670                       [2023]
               SUPREME COURT     7 S.C.R. 670
                              REPORTS                     [2023] 7 S.C.R.


A           GUJARAT URJA VIKAS NIGAM LIMITED & ORS.
                                       v.
          RENEW WIND ENERGY (RAJKOT) PRIVATE LIMITED
                                & ORS.
B                (Civil Appeal Nos. 3480-3481 of 2020)
                                APRIL 13, 2023
           [SANJAY KISHAN KAUL, S. RAVINDRA BHAT AND
                           M.M. SUNDRESH, JJ.]
             Electricity Act, 2003 – Central Electricity Regulatory
C     Commission (Terms and Conditions for Recognition and issuance
      of Renewable Energy Certificate for Renewable Energy Generation)
      Regulations, 2010 – Power Purchase Agreement (PPA) in terms of
      the REC Regulations 2010 was entered into between the parties, on
      29.03.2012, within the control period stipulated in the tariff order
D     of 2010 – On 10.07.2013, Central Commission amended the REC
      Regulations 2010 (‘Second Amendment’), Explanation to Regulation
      5 was amended – The pre-existing clause that the power would be
      “at a price not exceeding pooled cost of the power purchase” was
      altered to “at the pooled cost of power purchase” – It was clarified
      that PPAs executed prior to this amendment at a tariff lower than
E     APCC would not be affected – Respondents filed petition before
      the State Commission arguing that the terms of the PPA had to be
      changed in view of the change in the REC Regulations – Allowed –
      Appellant filed appeal before APTEL, rejected – Review petition
      also dismissed – Held: There was never any provision which
F     mandated prior approval by the State Commission, of PPAs entered
      into by parties, in exercise of their free choice, in relation to
      renewable energy sources – Findings of APTEL requiring approval
      of the State Commission, unsustainable – Further, it is a matter of
      record, that for the period between 29.03.2012 and 10.07.2013
      and indeed, after the Second Amendment, no difficulty was
G     experienced in the pricing mechanism agreed by the parties under
      the PPA – It was on 10.12.2013 that the respondent wind power
      developer approached the State Commission for re-determination
      of tariff – This was an opportunistic attempt to derive advantage
      from the change, brought about by the Second Amendment, and
      seek to have it applied to an existing contract, which cannot be
H
                                      670
 GUJARAT URJA VIKAS NIGAM LIMITED v. RENEW WIND                         671
            ENERGY (RAJKOT) PVT. LTD.

countenanced – Thus, the reasoning of APTEL and the State               A
Commission cannot be upheld – PPAs entered into voluntarily by
the parties exercising equal bargaining power, before the Second
Amendment were not affected by its terms – Findings to the contrary
in the impugned order set aside – Furthermore, APTEL in the most
cavalier fashion virtually rubber stamped the State Commission’s
                                                                        B
findings on coercion, in regard to the entering into the PPA by the
parties – There was no evidence or any pleadings beyond a bare
allegation of coercion against the appellant – Findings regarding
coercion are wholly untenable and therefore, set aside – Gujarat
Electricity Regulatory Commission (Procurement of Energy from
Renewable Sources) Regulations, 2010 – Regulation 4(1), 9(1).           C
      Electricity Act, 2003– Central Electricity Regulatory
Commission (Terms and Conditions for Recognition and issuance
of Renewable Energy Certificate for Renewable Energy Generation)
Regulations, 2010 – Objective of – Discussed.
      Electricity Act, 2003 – s.64 – Tariff Orders u/s.64 – Held: Are   D
quasi-judicial in nature and ipso facto binding on the parties unless
amended or modified through law.
      Electricity – Power Purchase Agreements, if statutory contracts
– Held: Power Purchase Agreements are essentially not statutory
contract showever, certain terms contained in those contracts are       E
regulated by law, i.e. applicable regulations, under the Act – The
PPA between a generating company or, as in the instant case, a
wind generator, and a distribution licensee, such as the appellant,
is the outcome of a carefully considered decision, whereby the
parties after due deliberations and negotiations agree on terms         F
based on existing law and regulations.
      Pleadings – Standard of – Allegation of coercion/duress/fraud
– Findings on, not to be rendered casually by APTEL – Held: It is
incomprehensible how an allegation of coercion w.r.t entering into
the PPA by the parties could have been entertained and incorporated     G
as a finding, given that the respondents are established companies
who enter into negotiations and have the support of experts,
including legal advisers, when contracts are finalized – Casual
approach of APTEL in not reasoning how such findings could be
rendered cannot be countenanced – As a judicial tribunal, dealing
                                                                        H
672           SUPREME COURT REPORTS                      [2023] 7 S.C.R.


A     with contracts and bargains, which are entered into by parties with
      equal bargaining power, APTEL is not expected to casually render
      findings of coercion, or fraud, without proper pleadings or proof,
      or without probing into evidence – Electricity Act, 2003.
            Allowing the appeals, the Court
B          HELD: 1. Did the PPA in the present case, require prior
      approval of the state commission
            RWE and the other respondents urge that the PPA was
      unenforceable because it was not approved by the State
      Commission. The argument is unmerited and insubstantial. From
C     a reading of the State Commission’s regulations (Renewable
      Sources Regulations) relating to procurement of energy from
      Renewable Sources, it is evident that there was never any
      provision, which mandated prior approval by the state commission,
      of PPAs entered into, by parties, in exercise of their free choice,
D     in relation to renewable energy sources. As a matter of fact, in
      the case of renewable power, the state commission had approved
      a model PPA. Further, the tariff terms and conditions to the extent
      decided are by the Central Commission and not by the State
      Commission. These are incorporated in the model PPA. Neither
      the commission, nor the contesting respondents, during the
E     hearings in the present appeals, were able to point out any
      provision in the PPA in the present case, which conflicted with
      any provision of the model PPA, or any express regulation.
      Furthermore, it was not established how in the absence of any
      reference to the Multi Year Tariff Regulations, they were
F     applicable to PPAs relating to renewable energy sources. In the
      absence of specific norms prescribing prior approval of PPAs like
      in the case of provisions of Regulation 21 of the Maharashtra
      Electricity Regulatory Commission (Multi Year Tariff)
      Regulations, 2019; Regulation 45 of the Delhi Electricity
      Regulatory Commission Comprehensive (Conduct of Business)
G     Regulations 2001 and Regulation 36 of the Andhra Pradesh
      Electricity Regulatory Commission (Distribution Licensee)
      Regulations, 2013, the respondent’s arguments on this aspect
      cannot be accepted. In these circumstances, the findings of
      APTEL, not based on any stipulated obligations under provisions
H     of the state regulations, requiring approval of the state
 GUJARAT URJA VIKAS NIGAM LIMITED v. RENEW WIND                         673
            ENERGY (RAJKOT) PVT. LTD.

commission, for its operation, cannot be sustained. [Paras 45-          A
48][699-F-G; 700-B-F]
      2. Whether change in the REC Regulations obliged revision
of the PPA in this case
       Section 61 of the Act enacts the basis for tariff
determination. On the other hand, Section 62 is concerned with          B
the fixation of various other charges and tariffs. Section 64 lists
the manner and procedure for tariff determination by the
Commission. Section 86 lists the functions of the Commission
and reiterates the determination of tariffs to be a prominent task
of the commission. Tariff determination no doubt, comprehends           C
the exercise of regulatory function, including purchase, sourcing,
procurement of electricity from generators, by distribution and
other licensees, and their sales. This part involves generating
companies entering into PPA(s) with procuring entities or
licensees. Tariff fixation is a statutory function. Yet, by virtue of
Section 42, it is subject to open access determination of the price     D
of power, and subject to Section 63 wherever it involves open
bidding. In the facts of this case, the PPA incorporated a tariff
between the respondents and Gujarat Urja constituted the tariff
fixed by the State Regulatory Commission in the exercise of its
statutory powers. The issue and sale of RECs, constituted an            E
important part of that bargain, between the two parties, based on
the assessment of their commercial interest. The important
feature of the REC Mechanism is that in it, WPDs (i.e.
respondents) had to sell power to distribution licensees at a
mutually agreed price, not exceeding the Average Power Purchase
Cost (‘APPC’) of the DISCOMs, (such as Gujarat Urja). The               F
WPDs were entitled to the additional benefit of Renewable Energy
Certificates issued to it which could be traded in Power Exchange
for a price. The consideration payable to WPDs consisted of firstly,
a mutually agreed power Component and secondly a green
component through RECs traded in the Exchange. The                      G
alternative to the WPDs was to sell to licensees at a preferential
tariff, determined by the state commission. In the latter event,
WPDs were not entitled to the additional benefit of the green
component, which was the tradable RECs the sale of which would
have led to increased revenues. The respondent WPDs chose
                                                                        H
674            SUPREME COURT REPORTS                      [2023] 7 S.C.R.


A     the REC mechanism, while entering into PPAs in these cases,
      with Gujarat Urja. The PPAs entered by WPDs provided for the
      fixed tariff of 2.64/kWh for the entire term (25 years), as mutually
      agreed (Article 5.2 of PPA). WPDs were entitled to and were
      trading RECs in the power exchange, deriving extra monetary
      benefits: which, at the relevant period was         1.50/kWh (floor
B
      price at the time of signing of PPA). The Preferential Tariff
      determined by the state commission, for WPDs not opting for
      the REC Mechanism was             3.56/kWh. The WPDs were not
      entitled to any additional REC benefits, had they adopted the
      preferential tariff route. Regulation 9 of the REC Regulations
C     2010 prescribes the price determination mechanism for RECs in
      the power exchange. Proviso to Regulation 9 (1) of the REC
      Regulations 2010 empowers the central commission, in
      consultation with the Central Agency and the Forum of
      Regulators, to provide the floor price and forbearance price
      separately for solar and non-solar certificates. This provision is
D
      important because it enables regulatory intervention in the public
      interest: if the price went below a certain limit, the floor price
      was to be prescribed, to take care of the interests of generators-
      like the respondents; if the price went too high, a forbearance
      price could be fixed, to take care of the interests of the consumers
E     and distributors. By Regulation 9 (2) of the REC Regulations
      2010, the Central Commission, was to be guided, in determining
      the floor and forbearance price, by diverse factors, such as (a)
      variation in cost of generation of different renewable energy
      technologies falling under solar and non-solar category, across
      states in the country; (b) variation in the Pooled Cost of Purchase
F
      across States in the country; (c) Expected electricity generation
      for non-renewable energy sources [including (i) expected
      renewable energy capacity under preferential tariff (ii) expected
      renewable energy under mechanism of certificates] (d) Renewable
      purchase obligation targets set by various State Commissions.
G     By virtue of Explanation to Regulation 5 (1) of the REC
      Regulations, “the weighted average pooled price at which the
      distribution licensee has purchased the electricity including cost of
      self-generation, if any, in the previous year from all the energy
      suppliers long-term and short-term, but excluding those based on
      renewable energy sources, as the case may be.” An important factor
H
 GUJARAT URJA VIKAS NIGAM LIMITED v. RENEW WIND                             675
            ENERGY (RAJKOT) PVT. LTD.

which cannot be lost sight of is that all the respondent’s WPDs             A
were registered, under the REC Regulations, based on the state
commission’s tariff order, of 2010. It is undisputed, that to register
under the REC Regulations 2010, an entity (such as WPDs) had
to be (a) accredited, with a State Agency [(defined by Regulation
2 (n) of the REC Regulations as an agency “designated by the
                                                                            B
State Commission to act as the agency for accreditation and
recommending the renewable energy projects for registration”) and
an entity “not having any power purchase agreement for the
capacity related to such generation to sell electricity at a preferential
tariff determined by the Appropriate Commission]. Furthermore,
the state commission, in its tariff order, dated 30.01.2010 (which          C
was operative for three years, with the control period beginning
from 10.08.2009) while determining the preferential tariff, had
observed that it would apply for 25 years. In the present case,
the PPA was entered into by the parties on 29.03.2102, within the
control period stipulated in the tariff order of 2010. The change in
                                                                            D
the REC Regulations 2010, whereby the Explanation to
Regulation 5 was amended resulted in a change. The pre-existing
clause that the power would be “at a price not exceeding pooled
cost of the power purchase” was altered to “at the pooled cost of
power purchase”. This change, was through the Second
Amendment (to the REC Regulations), carried out on 10.07.2013.              E
It is a matter of record, that for the period between 29.03.2102
and 10.07.2013 - and indeed, after the Second Amendment, no
difficulty was experienced in the pricing mechanism agreed by
the parties, under the PPA. It was on 10.12.2013 that the
respondent WPD approached the state commission for re-
                                                                            F
determination of tariff. Clearly, this was an opportunistic attempt
to derive advantage from the change, brought about by the Second
Amendment, and seek to have it applied to an existing contract,
which cannot be countenanced. In view of these reasons, it is
held that the reasoning of APTEL, and the State Commission
cannot be upheld. [Paras 55-59][707-G; 708-A-H; 709-B-H; 710-               G
A-B, E-G]
      Transmission Corporation of Andhra Pradesh Ltd v Sai
      Renewable Power Private Limited (2010) 8 SCR 636;
      Gujarat Urja v. Solar Power Company India Pvt. Ltd.
      [2017] 14 SCR 115; Bangalore Electricity Supply Co.                   H
676            SUPREME COURT REPORTS                      [2023] 7 S.C.R.


A           Ltd. vs. Konark Power Projects Ltd. & Ors. (2016) 13
            SCC 515 – referred to.
            3. Applicability of the Second Amendment to pre-existing
      contracts- the general law
             In the present case, the PPAs were entered into in the
B     exercise of equal bargaining power, after due negotiation by the
      parties, and within the framework of existing regulations: both
      central and state. Therefore, unless any later amendment
      expressly overrides existing contracts, the terms of such
      agreements bind the parties. Thus, agreements such as the PPAs
C     in the present case, entered into, voluntarily by the parties, before
      the Second Amendment, were not affected, by its terms. The
      findings to the contrary in the impugned order, are set aside.
      [Paras 63, 66][714-C; 715-G; 716-A]
            PTC India Ltd. v. CERC [2010] 3 SCR 609 –
D           distinguished.
            Purbanchal Cables & Conductors (P) Ltd. v. Assam State
            Electricity Board & Ors. [2012] 6 SCR 905;
            Commissioner of Income Tax v Vatika Township (P) Ltd.
            [2014] 12 SCR 1037 – relied on.
E           4. Were the respondents coerced into entering into PPAs
            APTEL, in the most cavalier fashion, virtually rubber
      stamped the State Commission’s findings on coercion, in regard
      to the entering into the PPA by the parties. There was no shred
      of evidence, nor any particularity of pleadings, beyond a bare
F     allegation of coercion, alleged against Gujarat Urja. It is
      incomprehensible how such an allegation could have been
      entertained and incorporated as a finding, given that the
      respondents are established companies, who enter into
      negotiations and have the support of experts, including legal
      advisers, when contracts are finalized. The findings regarding
G
      coercion are, therefore, wholly untenable. The casual approach
      of APTEL, in not reasoning how such findings could be rendered,
      cannot be countenanced. As a judicial tribunal, dealing with
      contracts and bargains, which are entered into by parties with
      equal bargaining power, APTEL is not expected to casually render
H
 GUJARAT URJA VIKAS NIGAM LIMITED v. RENEW WIND                      677
            ENERGY (RAJKOT) PVT. LTD.

findings of coercion, or fraud, without proper pleadings or proof,   A
or without probing into evidence. The findings of coercion are
therefore, set aside. [Para 71][717-F-G; 718-A-B]
     Shanti Budhiya Vesta Patel &Ors. v. Nirmala
     Jayprakash Tiwari & Ors. [2010] 4 SCR 958;
     BishundeoNarain v. Seogeni Rai [1951] 1 SCR 548;                B
     New Indian Assurance Co. Ltd v. Genus Power
     Infrastructure Ltd [2014] 12 SCR 360 – relied on.
     Gujarat Urja Vikas Nigam Limited v. EMCO Limited
     [2016] 1 SCR 857; Gujarat Urja Vikas Nigam Limited
     v. ACME Solar Technologies (Gujarat) Pvt Ltd & Others           C
     [2017] 16 SCC 498; Central Bank of India v. Hartford
     Fire Insurance Co. Ltd AIR 1965 SC 1288; Her
     Highness Maharani Shantidevi P Gaikwad v. Savjibai
     Haribai Patel & Ors 2001 (5) SCC 101: [2001] 2 SCR
     590; Hindustan Zinc Ltd. v. Rajasthan Electricity
     Regulatory Commission [2015] 7 SCR 1104; Gujarat                D
     Urja Vikas Nigam Ltd. v. Tarini Infrastructure Ltd.
     [2016] 5 SCR 990; Union of India v. Indusind Bank
     Ltd. [2016] 11 SCR 700; Kerala State Electricity Board
     & Anr v. Principal Sir Syed Institute for Technical
     Studies [2020] 7 SCR 885; Gujarat Urja Vikas Nigam              E
     Limited v. Solar Semi-Conductors Power Limited
     Company (India) Private Limited [2017] 14 SCR 115 –
     referred to.
                      Case Law Reference
[2020] 7 SCR 885              referred to            para 4          F
[2017] 14 SCR 115             referred to            para 15
[2010] 8 SCR 636              referred to            para 23
[2016] 1 SCR 857              referred to            para 23
[2017] 16 SCC 498             referred to            para 23         G

[2001] 2 SCR 590              referred to            para 25
[2010] 3 SCR 609              distinguished          para 33
[2015] 7 SCR 1104             referred to            para 41
                                                                     H
678             SUPREME COURT REPORTS                         [2023] 7 S.C.R.


A     [2017] 14 SCR 115                    referred to          para 52
      [2016] 5 SCR 990                     referred to          para 52
      (2016) 13 SCC 515                    referred to          para 54
      [2012] 6 SCR 905                     relied on            para 64
B     [2014] 12 SCR 1037                   relied on            para 65
      [2016] 11 SCR 700                    referred to          para 65
      [2010] 4 SCR 958                     relied on            para 69
      [1951] 1 SCR 548                     relied on            para 69
C
      [2014] 12 SCR 360                    relied on            para 70
            CIVIL APPELLATE JURISDICTION : Civil Appeal Nos.3480-
      3481 of 2020.
             From the Judgment and Order dated 06.12.2018 in AN No.209 of
D     2015 and dated 24.07.2020 in RP No.3 of 2019 of the Appellate Tribunal
      for Electricity at New Delhi.
            C. A. Sundaram, M. G. Ramachandran, Sr. Advs., Ms. Hemantika
      Wahi, Anand Ganesan, Ms. Swapna Sesadri, Ms. Jesal Wahi, Ms. Srishti
      Khindaria, Advs. for the Appellants.
E           Shyam Divan, Basava P. Patil, Dhruv Mehta, Sr. Advs., Venkatesh,
      Ms. Kanika Chugh, Nitin Saluja, Siddharth Joshi, Suhael Buttan, Punyam
      Bhvtani, Ms. Nishtha Kumar, Apoorva Misra, Shri Venkatesh, Vishal
      Gupta, Ms. Suparna Srivastava, Tushar Mathur, Nikilesh Ramachandran,
      Advs. for the Respondents.
F            The Judgment of the Court was delivered by
             S. RAVINDRA BHAT, J.
            1. The current civil appeals,1 under Section 125 of the Electricity
      Act, 2003, (hereafter, “the Act”) challenge orders of the Appellate
      Tribunal for Electricity (hereafter, “APTEL”), dated 06.12.2018 (“first
G     impugned order”)2 and order dated 24.07.2020 (“second impugned
      order”)3. The APTEL had, by those orders, rejected the appeals preferred
      by the present appellant, and the review petition, as well. Resultantly,
      1
        Civil Appeals Nos. 3480 and 3481 of 2020
      2
        in Appeal No 209/2015
      3
H       in Review Petition No 03/2019
    GUJARAT URJA VIKAS NIGAM LIMITED v. RENEW WIND                                         679
     ENERGY (RAJKOT) PVT. LTD. [S. RAVINDRA BHAT, J.]

the order of the Gujarat Electricity Regulatory Commission (hereafter                      A
“the State Commission”), dated 01.07.20154 was affirmed.
       2. The first appellant – Gujarat Urja Vikas Nigam Limited
(hereafter “Gujarat Urja”) had approached this court previously
challenging the order of APTEL, which was disposed of by this court5
granting liberty to it, to seek review/rectification. Gujarat Urja then                    B
preferred a review petition, which was rejected by APTEL, by the second
impugned order. When this appeal was taken up for hearing, on
14.10.2020, this court had issued notice and stayed the impugned order
of APTEL.
       Background                                                                          C
       3. Gujarat Urja procures power in bulk on behalf of distribution
licensees in the state of Gujarat; it is an authorized licensee within the
meaning of the term under the Act. The second, third, fourth and fifth
appellants are distribution licensees in the State of Gujarat. The first
respondent, Renew Wind Energy (Rajkot) Pvt Ltd (hereafter “RWE”)                           D
is a wind generator which had set up 25.2 MW Wind Turbine Generators
at District Rajkot, Gujarat under the Renewable Energy Certification
scheme notified by the Central Electricity Regulatory Commission
(hereafter, “Central Commission”). The second respondent is the Wind
Independent Power Producers Association (hereafter “Association”).
The Respondent No 3, Gujarat Electricity Regulatory Commission                             E
(hereinafter “the State Commission”) is the regulatory commission under
the Act, for the State of Gujarat. The fourth respondent, Wish Wind
Infrastructure LLP (“Wish Wind” hereafter) is a wind generator.
      4. By Section 86 of the Act6 , State Commissions discharge several
functions- which include the determination of tariff “for generation,                      F
4
  in petition No 1363/2013
5
  Civil Appeal No 1253/2019 by order dated 15.02.2019
6
  The relevant extract of Section 86 is as follows:
      “86. Functions of State Commission.-(1) The State Commission shall discharge
the following functions, namely:-
      (a) determine the tariff for generation, supply, transmission and wheeling of        G
electricity, wholesale, bulk or retail, as the case may be, within the State:
      ……
     (b) regulate electricity purchase and procurement process of distribution licensees
including the price at which electricity shall be procured from the generating companies
or licensees or from other sources through agreements for purchase of power for
distribution and supply within the State;
                                                                                           H
680               SUPREME COURT REPORTS                                     [2023] 7 S.C.R.


A     supply, transmission and wheeling of electricity, wholesale, bulk or
      retail, as the case may be, within the State”. The tariff determination
      process should accord with Sections 62 and 64 of the Act. Section 62,
      requires “the Appropriate Commission” (in this case, the State
      Commission) to determine tariffs in accordance with the provisions of
      the Act for – among other purposes, retail supply of electricity. The
B
      State Commissions are also empowered to frame regulations, under
      Section 181 of the Act. That power includes the formulation of the “terms
      and conditions for determination of tariff Under Section
      61”.7Additionally, the tariff order can be modified or imposed with
      conditions under Section 64(3). The State Commission is guided by the
C     principles specified in Section 61 of the Act while formulation of the
      tariff regulations. This court has held that state commissions as expert
      bodies have to strike a balance between various competing concerns
      and interests while framing such regulations.8 The Gujarat State
      Commission, for a Multi-Year period (also called the “control period”),
      frames Regulations for determination of tariff. The state commission
D
      then determines the Multi-Year Tariff Order based on the data available.
      Furthermore, Section 64 (6) prescribes that tariff orders “shall continue
      to be in force for such period as may be specified in the Tariff
      Order unless amended or revoked”. If any party is aggrieved by any
           (c) facilitate intra-State transmission and wheeling of electricity;
E          …..
           (e) promote co-generation and generation of electricity from renewable sources of
      energy by providing suitable measures for connectivity with the grid and sale of electricity
      to any person, and also specify, for purchase of electricity from such sources, a percentage
      of the total consumption of electricity in the area of a distribution licensee;
       …. [..]”
      7
        Clause 181(2)(zd) of the Act.
F     8
        Kerala State Electricity Board & Anr v. Principal Sir Syed Institute for Technical
      Studies, 2020 7 SCR 885:
           7. [..] “While fixing tariff, the Commission cannot show undue preference to any
      consumer of electricity. The Commission, however, is vested with the power to prescribe
      differential rates according to the consumers’ load factor, power factor, voltage, total
      consumption of electricity during any specified period of time at which supply is required.
      So far as fixing different rates for these two categories of the educational institutions,
G     these factors did not come into play. The other permissible differentiating factors
      are geographical position of any area, the nature of supply and the purpose for which
      the supply is required. As regards this set of differentiating factors, the tariff advantage
      for government run and aided educational institutions do not appear to be based on
      geographical position or nature of supply. The Commission however has justified the
      classification of the aforesaid two sets of tariffs on the basis of purpose for which supply
H     is required by the consumers.”
 GUJARAT URJA VIKAS NIGAM LIMITED v. RENEW WIND                                681
  ENERGY (RAJKOT) PVT. LTD. [S. RAVINDRA BHAT, J.]

conditions of a given Tariff Order, it can seek its amendment or revocation.   A
Orders are also appealable under Section 111 to APTEL, and thereafter
to this court under Section 125 of the Act. Tariff Orders under Section
64 of the Act are quasi-judicial in nature and ipso facto binding on the
parties unless amended or modified through law.
       5. On 29.01.2010, the Central Electricity Regulatory Commission         B
(Terms and Conditions for Recognition and issuance of Renewable
Energy Certificate for Renewable Energy Generation) Regulations, 2010
(hereafter “REC Regulations 2010”) were framed by the Central
Commission for the development of a power market for non-conventional
sources of energy by the issuance of tradable and saleable credit
certificates (hereafter “RECs”). Regulation 5 of the said REC                  C
Regulations 2010 provides for the required eligibility for the renewable
generators for participating in the RE Certificates:
      “5. Eligibility and Registration for Certificates:
      (1) A generating company engaged in generation of electricity            D
      from renewable energy sources shall be eligible to apply for
      registration for issuance of and dealing in Certificates if it
      fulfills the following conditions:
      a. it has obtained accreditation from the State Agency;
      b. it does not have any power purchase agreement for the                 E
      capacity related to such generation to sell electricity at a
      preferential tariff determined by the Appropriate Commission;
      and
      c. it sells the electricity generated either
                                                                               F
      (i) to the distribution licensee of the area in which the eligible
      entity is located, at a price not exceeding the pooled cost of
      power purchase of such distribution licensee, or
      (ii) to any other licensee or to an open access consumer at a
      mutually agreed price, or through power exchange at market
      determined price.                                                        G

      Explanation. - for the purpose of these regulations ‘Pooled
      Cost of Purchase’ means the weighted average pooled price
      at which the distribution licensee has purchased the electricity
      including cost of self generation, if any, in the previous year
                                                                               H
682                SUPREME COURT REPORTS                      [2023] 7 S.C.R.


A               from all the energy suppliers long-term and short-term, but
                excluding those based on renewable energy sources, as the
                case may be.”
              6. The objective of the REC Regulations 2010 was to separate
      the physical electrical component and the environmental (renewable)
B     component of the energy for issuance of RECs. This was an alternate
      mechanism developed for the sale of renewable energy at a preferential
      tariff to any licensee or directly to any consumer. The REC Regulations
      2010 aimed at selling the renewable component through the RE
      Certificates containing promotional benefits of renewable energy while
      the physical electrical component was sold as any other conventional
C     electricity. The REC Regulations 2010 also provided that generators
      based on the REC mechanism had the option to sell physical energy to
      the distribution licensee at a “price not exceeding the Average Pooled
      Power Purchase Cost” (hereinafter as “APPC”) of the distribution
      licensee9. This was to ensure that generators did not benefit twice over,
D     by selling RECs and also selling physical energy at higher promotional
      tariffs or taking concessional benefits from the concerned distribution
      licensee.
             7. Under the REC Regulations 2010, distribution licensees were
      not obliged to purchase the physical component of electricity from
E     renewable energy generators set up under the REC mechanism since
      such REC based generators had alternative options with regard to the
      physical component of electricity, namely, (i) sale of electricity power
      exchanges (ii) wheeling of power for sale to third parties at mutually
      agreed rates or (iii) wheeling of power for their own consumption. In the
      case of the sale of the physical component of electricity, the price for
F     the electrical component could not exceed average pooled cost of the
      distribution licensees. The regulations also provided that the generators
      (of renewable energy) were not eligible for any benefits including banking
      facilities, exemption from payment of cross subsidy surcharge etc.
      amongst other things. The stated promotional benefits were applicable
G     only in terms of trading and selling of the RE Certificates.
            8. The REC Regulations 2010 provided for floor price and
      forbearance price i.e. minimum price and maximum price respectively
      at which RECs could be traded in the power exchange. Those prices
      9
          Regulation 5(1)(c) of REC Regulations 2010.
H
     GUJARAT URJA VIKAS NIGAM LIMITED v. RENEW WIND                                          683
      ENERGY (RAJKOT) PVT. LTD. [S. RAVINDRA BHAT, J.]

i.e. floor price and the forbearance prices were to be determined by the                     A
central commission for the entire country.
       9. In the present case, the State Commission by its order 10
determined the tariff for procurement of power by distribution licensees
from wind energy generators and also ruled on other commercial issues
for wind energy generators set up under a preferential tariff mechanism.                     B
The order provided for a preferential levelized tariff of 3.56 per kWh
for the supply of energy to the distribution licensee for meeting it’s
Renewable Power Purchase Obligation (RPO). The “control period” of
the Order [dated 30.1.2010] was for the period 11.08.2009 to
10.08.2012 11. The order, inter alia, also provided the following
promotional benefits for wind generators set up for third party sale under                   C
a preferential mechanism:
        (a) Exemption from cross subsidy charges for the sale of wind
        energy to open access users in the State.
        (b) Payment for excess (over and above that set off against                          D
        monthly consumption in the 15 minutes time block) would be
        treated as a sale to the distribution licensee concerned at a rate of
        85% of the preferential tariff determined by commission for such
        renewable energy sources.
       10. On 17.04.2010, the State Commission notified Gujarat Electricity                  E
Regulatory Commission (Procurement of Energy from Renewable
Sources) Regulations, 2010 (hereafter “State Regulations”). The State
Regulations provided for the percentage of total consumption that
distribution licensees were to purchase from RPOs and further
recognized that RPO could be fulfilled by the purchase of such RECs.
Further, obligated entities could fulfil their renewable purchase obligation                 F
through two sources:

10
  Dated 30.01.2010 in Order No 1/2010
11
  The relevant provision of the Order reads as follows:
         “2.2 Control period The Commission had, vide its Order No.2 of 2006 dated
11th August,2006, determined the Wind Energy Tariff for a period of three years, i.e.
                                                                                             G
upto 10th August,2009. The draft for the present order was published on 17.05.2009
and it was proposed to be effective from 1st July, 2009.However, some of the objectors
suggested that the present order be made effective from the end of previous control
period. Since the previous control period expired on 10th August, 2009, the Commission
decides that the control period for this order will be 3 (three) years w.e.f. 11th August,
2009.”                                                                                       H
684               SUPREME COURT REPORTS                                     [2023] 7 S.C.R.


A             (a) Purchase of renewable energy directly (at preferential tariff
              determined by State Commission); and
              (b) Purchase of RECs at a market price between Floor Price and
              Forbearance price determined by Central Commission
              11. A Power Purchase Agreement (hereafter “PPA”) in terms of
B     the REC Regulations 2010, was entered into between the Gujarat Urja
      and the wind power developers (hereafter, “WPDs”) including respondent
      RWE on 29.03.2012. The agreement provided for a ceiling on tariff at
      2.64 per unit for 25 years. In addition to the tariff, WPDs were eligible
      for the issue of RECs for each unit of electricity generated and supplied
C     by them to the appellants. The alternate route available for the WPDs
      (such as RWE, Wish Wind etc.) at the time of entering into the PPA was
      to sell electricity at a promotional tariff of 3.56 per unit - as determined
      by the State Commission. By choosing the option, the WPDs were
      ensured tariff at 2.64 per unit plus tradable RECs whose price was
      determined on the basis of the “weighted average pooled price”12.
D     Distribution licensees were enabled to adjust such quantum of power
      purchased towards RPO specified under Section 86(1)(e) of the Act.
      Thus, the interests of both segments of the industry were taken care of.
             12. The State Commission by its order dated 08.08.2012 13
      determined the tariff at which the power could be procured by the
E     distribution licensees and others from wind power projects commissioned
      in the control period from 11.08.2012 to 31.03.2016.
            13. On 11.07.2013, Central Commission amended the REC
      Regulations 2010 (hereafter “Second Amendment”) and replaced “at a
      price not exceeding pooled cost of the power purchase “with” at
F     the pooled cost of power purchase”14 along with the relevant statement
      12
         See Explanation to Regulation 5 of the REC Regulations 2010 which defines average
      pooled price as follows:
       “the weighted average pooled price at which the distribution licensee has purchased
      the electricity including cost of self-generation, if any, in the previous year from all the
      energy suppliers long-term and short-term, but excluding those based on renewable
G
      energy sources, as the case may be.”
      13
         in Order No. 2/2012
      14
         The relevant amendment to Regulation 5 (c), reads as follows:
        “(2) In sub-clause (c) of clause (1) of Regulation 5 of the Principal Regulations, the
      words “at price not exceeding the pooled cost of the power purchase of such distribution
      licensee” shall be substituted with the words “at the pooled cost of power purchase of
H     such distribution licensee as determined by the Appropriate Commission”.”
     GUJARAT URJA VIKAS NIGAM LIMITED v. RENEW WIND                            685
      ENERGY (RAJKOT) PVT. LTD. [S. RAVINDRA BHAT, J.]

of reasons for the said amendment. It was clarified in the amendment           A
that PPAs already executed prior to this amendment at a tariff lower
than APCC would not be affected. The first two respondents were
aggrieved by the order of the Central Commission. They filed a petition15
before the State Commission arguing that the terms of the PPA had to
be changed in view of the change in the REC regulations. This petition
                                                                               B
was allowed by the State Commission directing that the order of the
Central Commission was general and was therefore applicable to all
similarly situated wind power generators. Aggrieved by the order of the
State Commission, Gujarat Urja had preferred an appeal16 before
APTEL. This appeal was rejected by APTEL by order dated 06.12.2018.
The appellants preferred review petition against APTEL’s order rejecting       C
their appeal against State Commission’s order; that too was dismissed
by APTEL vide order dated 24.07.2020.
        Arguments of the Appellant
        14. The learned senior counsel for the appellant, Mr. C.A.
Sundaram submitted that governing regulations for the PPAs in question         D
were the CERC Regulations 2010. Therefore, the State Commission
had no jurisdiction to decide the tariff contrary to the agreement. Further,
counsel argued that Central Commission itself has clarified by the Second
Amendment that in respect of PPAs entered into prior to 11.07.2013,
tariffs mutually agreed upon between the parties would be valid for the        E
entire duration of the PPA (i.e. 25 years) and they could not be substituted
or re-determined by the State Commission. It was further argued that
had the appellants known about the APPC on year-on-year basis at the
time of signing the agreement, they would not have adopted the REC
mechanism but instead would have availed a different method whereby
prices were fixed and appellants would have been entitled to RPO benefits      F
as well.
      15. Reliance was placed on this court’s judgment in Gujarat Urja
Vikas Nigam Limited v. Solar Semi-Conductors Power Limited
Company (India) Private Limited17 to argue that if the State Commission
re-determines the tariff amongst the parties, then the aggrieved party         G
cannot be compelled to continue the said agreement or enter into a new
agreement on such increased tariff.
15
   Petition No. 1363 of 2013
16
   Appeal No. 209/2015
17
   (2017) 14 SCR 115                                                           H
686              SUPREME COURT REPORTS                                  [2023] 7 S.C.R.


A            16. The appellants further submitted that State Commission had
      no jurisdiction to reopen the PPA as the same was entered into in terms
      of the REC Regulations 2010 that was framed by the Central Commission
      and was within its exclusive jurisdiction. Moreover, it was argued that
      the appellants would fail in their duty towards their consumers if they
      cannot negotiate for a lower tariff or if they agree to purchase power at
B
      a higher tariff despite the availability of power at a lower tariff. In such
      an event, the higher cost of procurement of power so imposed would be
      ultimately passed on to the consumers which would be contrary to a
      specified public interest, under the Act.
             17. The learned senior counsel argued that the definition of the
C     “APPC” cannot be relied upon in the present case18 and the PPA in
      question provided for a tariff. There was consequently no bar in any law
      or regulations for the parties to agree to such tariff and in fact, REC
      Regulations 2010 itself recognized that the PPA can be “at a price not
      exceeding the pooled purchase cost”. Likewise, for the sale of such
D     power to customers or the licensees, reference is made to “mutually
      agreed price” and therefore reference to “mutually agreed price”
      can mean that price can also be a fixed price and need not mean that it
      has to be dynamic and varying every year.
             18. It was argued that the interpretation placed by APTEL is not
E     founded on any express provision in the regulations, or anything arising
      out of necessary implication. The change in regulations, unless made
      specifically operable for a prior period, cannot be construed to be
      retrospective. Thus, contracts concluded prior to the entered into prior
      to the amendment [in 2013] cannot be governed by amended provisions.
      Doing so would not only be contrary to the express terms of the amended
F     regulations but would also be contrary to the terms of the PPA which do
      not accommodate or provide for such change in regulations.
            19. The appellants further urged that the PPA was consciously
      entered into by the respondents on 29.03.2012, which was before the

G     18
        APPC as clause 1.1 of the PPA is defined as:
                 “Average Power Purchase Cost” means the weighted average pooled price at
      which the distribution licensee has. Purchased the electricity including cost of self-
      generation, if any, in the previous year from all the energy suppliers long-term and
      short-term; but excluding those based on renewable energy sources, as the case may be.
      Further, for this agreement, Average Power Purchase Cost for the term of the agreement
      shall be as per Article No. 5.2
H
     GUJARAT URJA VIKAS NIGAM LIMITED v. RENEW WIND                                         687
      ENERGY (RAJKOT) PVT. LTD. [S. RAVINDRA BHAT, J.]

state commission’s tariff order dated 08.08.2012. The PPAs were                             A
signed by the respondents before 11.07.2013, (when the amendment
was made to the REC regulations) voluntarily without any reservation.
The terms of the PPA were binding and enforceable, unaffected by the
Second Amendment, which applied prospectively. Learned counsel relied
on the clarification by the CERC in the Statement of Reasons published
                                                                                            B
in this regard.19
      20. It is argued that the National Action Plan on Climate Change
and the Union Ministry of Power resolution dated 28-01-2016 and Tariff
Policy underline the necessity of the co-generation of renewable sources
of energy, progressively, so that it reaches a greater proportion. The
policy aims at increasing investment, and ensuring that viable units                        C
generating renewable energy are set up.
       21. It was argued that the PPA was a commercial transaction,
freely entered into between the parties. Neither the appellants nor the
first Respondent was obliged to enter into the PPA nor agree to any
specific terms or conditions. In case the terms were not acceptable,                        D
both parties had the freedom to reject the transaction and seek to sell or
buy power through other alternative available options as provided under
the REC Regulations 2010. Further at the time of signing the PPA, and
even thereafter till the filing of the Petition before the State Commission
in the month of December 2013 (i.e. more than one and half years after                      E
the execution of the PPA), the first respondent did not raise any objections
or protest on being allegedly coerced or placed under duress to agree to
the terms and conditions of the PPA. The terms of the PPA were fully in
compliance with the provisions of the REC Regulations 2010 as the
restriction in those regulations was for the price not to exceed the Pooled
Power Purchase Cost. The price agreed to between the appellant and                          F
Respondent No. 1 was 2.64/- per unit or Pooled Power Purchase
Cost of the subsequent year, whichever was lower.
19
  Dated 10.07.2013, which inter alia, stated that
 “Some of the stakeholders have suggested to clarify as to whether the PPAs executed at
price lower than APPC would become ineligible under REC Mechanism. It is felt that the      G
tariff for electricity component lower or higher than APPC may lead to avoidable loss or
profit to RE generator. The Commission would like to clarify that the intention is not to
debar the projects that have executed PPA at tariff lower than APPC. This amendment
will apply prospectively and as such will not affect the” already executed PPAs at lower
than APPC.”
                                                                                            H
688               SUPREME COURT REPORTS                                      [2023] 7 S.C.R.


A             22. The appellants argue that till 11.07.2013 none of the WPDs/
      respondents raised any issue on the tariff of 2.64/kWh for the entire
      duration of the PPA. It was only on 10.12.2013, the first two respondents
      filed Petition No.1363/ 2013 before the State Commission claiming that
      the tariff should be the APPC cost year-on-year basis instead of a fixed
         2.64/kWh. This was contrary to the decision by CERC on the
B
      application of Second Amendment only prospectively -which is, for PPAs
      entered on or after 11.07.2013. The state commission by its order (dated
      01.07.2015) allowed the respondent’s petition and further directed that
      the order is generic in nature and applicable to all similarly placed WPDs-
      which was affirmed by the first impugned order. The appellants argue
C     that the governing Regulations for PPAs adopting the REC Mechanism
      are 2010 REC Regulations and the state commission cannot decide on
      tariff contrary to the same. When the Central Commission clarified that
      for PPAs entered into prior to 11.07.2013, the tariff mutually agreed is
      valid for the entire duration of the PPA (25 years), the state commission
      and APTEL fell into error in substituting a new tariff at the instance of
D
      the WPDs/Respondents. It is pointed out that Rule 820 of the Electricity
      Rules, 2005, notified by the Central Government, is binding, and
      specifically provides that tariff determined by the Central Commission
      (CERC) shall not be subject to re-determination by the GERC/State
      Commission.
E           23. Learned senior counsel argued that if at the time of signing
      the PPAs WPDs-Respondents had sought for tariff at APPC on year-
      on-year basis, the appellants would not have entered into PPAs under
      the REC mechanism route and would have only adopted the alternate
      route where the price was fixed and in addition, the appellants would
F     have been entitled to RPO benefits. This is also clear as the appellants
      did not sign any PPAs after the Second Amendment for procuring power
      under the REC mechanism. The appellants urge that the Impugned Order
      is contrary to the decision of this court in Gujarat Urja Vikas Nigam
      20
        Rule 8 reads as follows:
       “8. Tariffs of generating companies under section 79. –The tariff determined by the
G     Central Commission for generating companies under clause (a) or (b) of subsection (1)
      of section 79 of the Act shall not be subject to redetermination by the State Commission
      in exercise of functions under clauses (a) or (b) of sub section (1) of section 86 of the Act
      and subject to the above the State Commission may determine whether a Distribution
      Licensee in the State should enter into Power Purchase Agreement or procurement
      process with such generating companies based ,on the tariff determined by the Central
H     Commission.”
     GUJARAT URJA VIKAS NIGAM LIMITED v. RENEW WIND                           689
      ENERGY (RAJKOT) PVT. LTD. [S. RAVINDRA BHAT, J.]

Limited v Solar Semi-Conductors Power Company (Pvt) Ltd (Supra)               A
holding that if the state commission re-determines the tariff, it cannot
force the appellants to continue the PPAs or enter into a contract based
on such increased tariff. Furthermore, it is argued that the principle that
WPDs having validly executed the PPAs cannot seek a modification to
the tariff terms and conditions contained in the PPAs under a prevalent
                                                                              B
dispensation for an increase in the tariff or for any other terms and
conditions: counsel referred to Transmission Corporation of Andhra
Pradesh Ltd v Sai Renewable Power Private Limited (hereafter
“Transmission Corporation of Andhra Pradesh Ltd”)21; Gujarat Urja
Vikas Nigam Limited v EMCO Limited (hereafter “Emco Ltd”)22;
and Gujarat Urja Vikas Nigam Limited v ACME Solar Technologies                C
(Gujarat) Pvt Ltd & Others23 in support of the above contention.
        24. Mr. Sundaram argued – for the appellants that the plea of
coercion or duress or unequal bargaining etc, raised by the WPDs was
patently erroneous for the following reasons: (a) the petition before the
state commission was filed only by the first two Respondents; therefore,      D
it cannot be a ground for alleging coercion against all WPDs; (b) the
allegations by the said two Respondents were vague and unsubstantiated,
and an afterthought as no such plea was raised till December 2013, i.e.,
till after the amended CERC Regulations; and (c) as held by this Court
such plea of coercion had to be specifically pleaded and proved. In this
regard, reliance was placed on Transmission Corporation of Andhra             E
Pradesh Ltd (Supra).
       25. It is further argued that there is no Regulation of the state or
central commissions prohibiting a term being incorporated in PPA which
permits an option to either party to switch from REC mechanism to
Preferential Tariff Mechanism. The impugned order had not considered          F
judgments referred to by the appellants on clauses granting power to
one party to cancel the contract. In this regard, reliance is placed on
Central Bank of India v Hartford Fire Insurance Co. Ltd24; and Her
Highness Maharani Shantidevi P Gaikwad v Savjibai Haribai Patel
& Ors25.                                                                      G
21
   (2010) 8 SCR 636
22
   (2016) 1 SCR 857
23
   (2017) 16 SCC 498
24
   AIR 1965 SC 1288
25
   2001 (5) SCC 101
                                                                              H
690             SUPREME COURT REPORTS                            [2023] 7 S.C.R.


A           Respondents’ Submissions
             26. Mr. Shyam Divan and Mr. Dhruv Mehta, learned senior
      counsels appearing for the first two respondents urged that State
      Commission had jurisdiction in the present case. Reliance was placed
      on the definitional clause of the PPA (Article 1.1) to submit that
B     commission meant ‘State Commission’. It was urged that in terms of
      the extant regulatory framework, (which provided for regulatory oversight
      by the appropriate commission), PPAs executed by generating companies
      and distribution licensees necessarily required approval by the appropriate
      commission. Firstly, Section 86(1)(b) of the Act specifically vests the
      State Commission with the power to regulate the electricity purchase
C     and procurement process of distribution licensees including the price at
      which electricity shall be procured from the generating companies. This
      provision empowers the state commission to modify, alter or vary the
      terms of PPAs, to ensure their compliance in accordance with the
      regulatory framework. Secondly, under the Multi Year Tariff Regulations,
D     2011 (hereafter “GERC (Multi Year Tariff) Regulations”) notified by
      the State Commission, , PPAs are to be mandatorily approved in order
      for them to be considered effective and enforceable. Learned counsel
      relied on provisions of the Maharashtra Electricity Regulatory
      Commission (Multi Year Tariff) Regulations, 2019, (Regulation 21); Delhi
      Electricity Regulatory Commission Comprehensive (Conduct of
E     Business) Regulations 2001 (Regulation 45) and Andhra Pradesh
      Electricity Regulatory Commission (Distribution Licensee) Regulations,
      2013 (Regulation 36) to support the contention that prior filing and approval
      of PPAs is necessary and was not undertaken in this case, which
      undermines its legal efficacy.
F            27. It was submitted that pooled purchased cost of power to be
      taken into consideration under the REC mechanism has to be the APPC
      of the previous financial year- which has to be modified / increased on a
      regular basis. When pooled purchase cost increases, the floor price of
      REC will decrease as the floor price and forbearance price of RECs are
G     subject to fluctuation, at the end of each control period. Thus, wind power
      projects under the REC mechanism will be viable, only when the
      realization from the power component increases to compensate for the
      reduction in prices of RECs. It was submitted that if the APPC computed
      is lower than what has been taken by the CERC for the determination of
      the REC price band, there could be a viability gap problem for RE
H
 GUJARAT URJA VIKAS NIGAM LIMITED v. RENEW WIND                              691
  ENERGY (RAJKOT) PVT. LTD. [S. RAVINDRA BHAT, J.]

generators under the REC mechanism, especially in cases where the            A
price discovered in the power exchange is closer to the floor price.
       28. It was further submitted that the Second Amendment to REC
regulations specifically replaced the words “at a price not exceeding” to
“at the pooled cost”, which meant that the cost of electricity purchased
could neither be lower nor higher than the power purchase cost. Counsel      B
further placed reliance on Statement of Reasons dated 10.07.2013 issued
by the Central Commission regarding the Second Amendment to contend
that REC contracts cannot be fixed price contracts as they would affect
the viability of REC projects as the price band (floor price / forbearance
price) are subject to periodic revision. Relevant extracts of the said
statement of reasons are reproduced below:                                   C

      “4.3 Analysis and decision
      Some of the stakeholders have suggested to clarify as to
      whether the PPAs executed at price lower than APPC would
      become ineligible under REC Mechanism. It is felt that the             D
      tariff for electricity component lower or higher than APPC
      may lead to avoidable loss or profit to RE generator. The
      Commission would like to clarify that the intention is not to
      debar the projects that have executed PPA at tariff lower than
      APPC. This amendment will apply prospectively and as such
      will not affect the already executed PPAs at lower than APPC.          E

      Regarding suggestion received that PPA of electricity
      component should be a fixed price long term contract (without
      escalation) since Commission has assumed fixed price while
      determining REC price bands in its methodology, it is clarified
      that the price band is subject to periodic revision; hence fixed       F
      APPC or long-term contract without escalation might affect
      viability of RE Projects. In any case proposed amendment
      provides that APPC would be determined by the Appropriate
      Commission”
       29. Counsel appearing for the association submitted that in terms     G
of the regulatory framework, PPAs executed by generating companies
and distribution licensees have to be approved by the appropriate
commission; and that the PPA in question was never approved by State
Commission nor did the appellants approach the State Commission for
such approval. It was further submitted that floor price and forbearance
                                                                             H
692            SUPREME COURT REPORTS                          [2023] 7 S.C.R.


A     price are to be determined guided by various principles, inter alia,
      variations in APPC across the states, (which is revised on an annual
      basis). Hence, the APPC cannot be a static concept else variation in
      floor price or forbearance price would lead to under recovery to
      generators.
B             30. It was further contended that APPC along with REC pricing,
      together, are the tariff determined and approved for the supply of power.
      That is to say that APPC and REC pricing are two halves of the same
      whole which constitutes the overall tariff which a generating company
      registered under the REC mechanism is entitled to receive. APPC along
      with REC pricing is what was intended to be incorporated as part of the
C     tariff clause in the PPA. If either of the components is pegged or capped
      artificially, and without the approval of the State Commission, it would
      lead to a skewed application of the REC mechanism to the detriment of
      generating company, leading to under-recovery and unviability of the
      RE generator.
D             31. It was argued that Regulation 9(2) of REC Regulations 2010
      provides for the determination of the floor price (minimum price) and
      the forbearance price (maximum price) within which the RECs can be
      traded in power exchanges. The floor price and the forbearance are to
      be determined by CERC for the entire country guided by various
      principles, inter alia, variations in APPC across the States, which is
E     revised on an annual basis. Therefore, if APPC is made static then
      variation in Floor Price/ Forbearance price would lead to under recovery
      to generators.
              32. The APPC to be taken into consideration under the REC
      mechanism must be dynamic and must be revised on a regular basis.
F     When APPC is increased, the floor price of REC comes down and vice
      versa and the same is subject to change every year. The APPC along
      with REC pricing, together, are the tariff determined and approved for
      the supply of power. In other words, the APPC and REC pricing are
      two halves of the same whole, which constitute the overall tariff which
      a generating company registered under the REC mechanism is entitled
G
      to receive. APPC along with REC pricing is what was intended to be
      incorporated as part of the tariff clause in the PPA. If either
      component is pegged or capped artificially, and that too without approval
      from GERC, the same would lead to a skewed application of the REC
      mechanism to the detriment of the generating company, leading to under-
H     recovery and unviability of the RE Generator.
     GUJARAT URJA VIKAS NIGAM LIMITED v. RENEW WIND                           693
      ENERGY (RAJKOT) PVT. LTD. [S. RAVINDRA BHAT, J.]

       33. It was submitted that the tariff in the PPA was in violation of    A
the principal regulation, which does not contemplate a fixed long-term
price/ tariff. It is, therefore, illegal and had to be aligned with the
regulation. The APTEL correctly aligned the tariff to the regulation. The
regulation has not been challenged and it has the force of statute and it
mandates that PPAs should be aligned to the regulations. Reliance is
                                                                              B
placed on PTC India Ltd. v. CERC (hereafter “PTC India”)26.
       34. Counsel for the third respondent argued that there could not
be a tariff between a generating company and a distribution licensee in
a PPA which was not in line with the CERC Regulations and tariff
orders issued by the State Commission. It was further contended that
the court cannot enforce a contract where unequal bargaining power            C
exists amongst the parties. It was further submitted that State Commission
has rightly observed that the fixed tariff of 2.64/unit for a period of 25
years by the parties violates not only the provisions of the Act but also
the National Electricity Policy and tariff policy as notified under Section
3 of the Act which promotes renewable energy sources through                  D
preferential pricing.
       35. Counsel for Wish Wind submitted that it cannot be bound by
the onerous terms of the PPA as it was never approved by the State
Commission and thus not in consonance with the statutory procedure
prescribed under the Act. Learned counsel also submitted that present         E
proceedings are not a case where a contract has been interdicted by the
State Commission but rather where a contract has been aligned with the
relevant regulatory regime in the exercise of the regulatory power vested
by the Act. In response to Gujarat Urja’s argument that State Commission
has no jurisdiction to reopen the PPA, it was submitted that Section
86(1)(b) of the Act places an obligation upon distribution licensees to get   F
PPAs (executed by them) approved by the State Commission and in the
present case, state commission never had the opportunity to verify/
regulate such PPAs in accordance with the law.
       36. It was also submitted that Section 86(1)(b) of the Act empowers
the state commission to modify, alter or vary the terms of the agreement      G
of PPAs, to ensure their compliance in accordance with the regulatory
framework established under the Act. It was further submitted that taking
into consideration the definition of APPC, it is evident that floor price
26
     (2010) 3 S.C.R. 609
                                                                              H
694              SUPREME COURT REPORTS                                    [2023] 7 S.C.R.


A     and forbearance price are dynamic in nature and APPC being associated
      with the floor price and the forbearance price is also required to be
      determined on a year-to-year basis so that the guaranteed return to the
      generators is not affected.
              Analysis and Findings
B            37. The crisis arising out of, and the enormous environmental cost
      involved in the continued use of fossil fuels has led governments, world
      over, to promote alternative and renewable sources of energy. The rapid
      growth of renewable energy over the decade and a half has witnessed
      that solar and wind power are now the cheapest sources of energy in
C     many countries in the world. Once green energy was an expensive
      alternative, however, it is now helping to reduce energy bills.
             38. The rapidly changing economics of such sources has led, the
      Union government to realize that solar and other renewables can
      potentially transform the energy landscape, increase access and help
D     India meet its climate change objectives. Grid transmission capacity has
      been a barrier; however, distributed and off-grid solar solutions provide
      a viable solution for increasing energy access. Being dependent primarily
      on cheap coal-based power generation, traditional thinking on energy
      has been that increase in renewable energy’s share of electricity
      generation would further impair local distribution companies’ poor
E     financial situation. Over the years, India has established a comprehensive
      policy and regulatory frameworks to encourage renewable energy
      development. India began its development of wind power in the 1990s
      and has significantly increased its capacity over the last few years.
      Compared to established countries with wind energy capacities like the
F     USA or Denmark, India is a latecomer. Yet, its support for wind power,
      through its policies has resulted in India becoming the producer with the
      fourth largest installed wind power capacity, in the world; wind power
      accounts for 10% of India’s total installed power capacity. As of February
      2023, the installed capacity of wind power in India was 42,015 megawatts
      (MW). 27
G
          39. Section 86 of the Act enumerates the functions of state
      commissions; Section 86 (1)(e) reads as follows:
      27
        Physical Progress (Achievements) Ministry of New and Renewable Energy, Govt. of
      India. https://mnre.gov.in/the-ministry/physical-progress, visited on 06.04.2023 at 20:30
      hours.
H
 GUJARAT URJA VIKAS NIGAM LIMITED v. RENEW WIND                                 695
  ENERGY (RAJKOT) PVT. LTD. [S. RAVINDRA BHAT, J.]

      “Section 86(1): The State Commission shall discharge the                  A
      following functions, namely:
      ******************                    *****************
      (e) promote cogeneration and generation of electricity from
      renewable sources of energy by providing suitable measures
      for connectivity with the grid and sale of electricity to any             B
      person, and also specify, for purchase of electricity from such
      sources, a percentage of the total consumption of electricity
      in the area of a distribution licensee;”
       40. State Commissions have placed significant emphasis on the
last part of this important clause while developing regulations for             C
Distribution Licensees under their jurisdiction. The National Tariff Policy,
issued by the Central Government in terms of Section 3 of the Act states
as follows:
      “Clause 6.4: Non-conventional sources of energy generation
      including co-generation:                                                  D
      (1) Pursuant to provisions of section 86(1)(e) of the Act, the
      Appropriate Commission shall fix a minimum percentage for
      purchase of energy from such sources taking into account
      availability of such resources in the region and its impact on
      retail tariffs. Such percentage for purchase of energy should             E
      be made applicable for the tariffs to be determined by the
      SERCs latest by April 1, 2006.”
       By virtue of Regulation 4 (1) of the REC Regulations 2010, there
are two categories of RECs: solar and non-solar. Regulation 4 (2)
mandates that “non-solar certificate shall be sold to the obligated             F
entities to enable them to meet their obligation for purchase from
renewable energy sources other than solar.” Regulation 5 (1) of the
REC regulations (extracted earlier) spells out the eligibility conditions
for renewable energy generating companies to apply and seek registration
for certificates; these are that the company should have: (a) obtained
accreditation from the State Agency; (b) it does not have any power             G
purchase agreement for the capacity related to such generation to sell
electricity at a preferential tariff determined by the Appropriate
Commission; and (c) it sells the electricity generated either-(i) to the
distribution licensee of the area in which the eligible entity is located, at
a price not exceeding the pooled cost of power purchase of such                 H
696                SUPREME COURT REPORTS                       [2023] 7 S.C.R.


A     distribution licensee, or (ii) to any other licensee or to an open access
      consumer at a mutually agreed price, or through power exchange at
      market determined price. What is meant by “pooled cost or purchase” is
      elaborated in the Explanation (to Regulation 5) to mean “the weighted
      average pooled price at which the distribution licensee has
      purchased the electricity including cost of self-generation, if any,
B
      in the previous ·year from all the energy suppliers long-term and
      short-term, but excluding those based on renewable energy sources.
      as the case may be.”
             41. The objectives of the REC Regulations 2010 were described
      in the judgment of this court, reported as Hindustan Zinc
C     Ltd. v. Rajasthan Electricity Regulatory Commission,28
                “44. [..] Regulations have been enacted in order to effectuate
                the object of promotion of generation of electricity
                from renewable sources of energy as against the polluting
                sources of energy which principle is enshrined in the Act, the
D               National Electricity Policy of 2005 and the Tariff Policy of
                2006. The provisions requiring purchase of minimum
                percentage of energy from renewable sources of energy have
                been framed with an object of fulfilling the constitutional
                mandate with a view to protect environment and prevent
E               pollution in the area by utilising renewable energy sources as
                much as possible in larger public interest.[..]”
             42. The approach of this court, therefore, has to consider the
      objective of the policy of promoting non-renewable sources of energy,
      the purpose of introducing RECs, and the progressive obligations placed
F     upon licensees, to ensure that they purchase energy from such “green”
      or “clean” sources, in a viable manner. In the present case, the obligation
      to procure renewable energy, is located in the Gujarat Electricity
      Regulatory Commission (Procurement of Energy from Renewable
      Sources) Regulations, 2010 (hereafter the “Renewable Sources
      Regulations”). Regulation 4 (1) of the said Renewable sources Regulations
G     reads as follows:
                “4. Quantum of Renewable Purchase Obligation (RPO)
                4.1 Each distribution licensee shall purchase electricity (in
                kWh) from renewable energy sources, at a defined minimum
      28
H          (2015) 7 S.C.R. 1104
     GUJARAT URJA VIKAS NIGAM LIMITED v. RENEW WIND                                           697
      ENERGY (RAJKOT) PVT. LTD. [S. RAVINDRA BHAT, J.]

        percentage of the total consumption of its consumers including                        A
        T&D losses during a year. Similarly, Captive and Open Access
        user(s) / consumer(s) shall purchase electricity (in kWh) from
        renewable energy sources, at a defined minimum percentage
        of his/her total consumption during a year.
        The defined minimum percentages are given below in the Table                          B
        1.




                                                                                              C




        If the above-mentioned minimum quantum of power purchase
        from solar and other renewable energy sources is not available                        D
        in a particular year, then in such cases, additional wind or
        other energy, over and above that shown in column 3 and 5,
        shall be utilized for fulfillment of the RPO in accordance with
        column 2.
        Provided further that such obligation to purchase renewable                           E
        energy shall be inclusive of the purchases, if any, from
        renewable energy sources already being made by the obligated
        entity concerned:
        Provided also that the power purchases under the power
        purchase agreements for the purchase of renewable energy                              F
        sources already entered into by the distribution licensees shall
        continue to be made till their present validity, even if the total
        purchases under such agreements exceed the percentage as
        specified hereinabove.”
       43. In terms of Regulation 9 (1) of the Renewable Sources                              G
Regulations, if an obligated entity29 (such as the present appellant) does
not fulfil the renewable purchase obligation as provided in the regulations
29
  An “obligated entity” is defined in Regulation 2 (k) as “the entity mandated under
clause (e) of subsection (1) of section 86 of the (Electricity) Act to fulfil the renewable
purchase obligation and identified under clause 3 of these Regulations.                       H
698             SUPREME COURT REPORTS                           [2023] 7 S.C.R.


A     during any year and also does not purchase the certificates, the State
      Commission may direct the obligated entity to deposit into a separate
      fund, to be created and maintained by such obligated entity, such amount
      as the State Commission may determine. Thus, obligated entities,
      (distribution licences included) had to take steps to progressively increase
      the purchase of power from renewable energy sources. To incentivize
B
      this, flexibility was granted; the power generators could either have the
      tariff fixed, according to the State Commission’s Tariff determination
      order, or adopt another mechanism, i.e., the one contemplated in the
      REC Regulations.
             44. The relevant conditions and stipulations set out in the PPA in
C     this case, are extracted below:
            “RATES AND CHARGES
            5.1 Monthly energy charges: the GUVNL shall pay for the
            delivered energy as certified by the SEA of Gujarat SLDC,
D           for the term of this agreement from the commercial operation
            date of signing of power purchase agreement whichever is
            later, to the power producer every month. The tariff payable
            by GUVNL for energy purchased shall be as per clause 5.2
            herein.

E           5.2. GUVNL shall pay a fixed rate of Rs. 2.64 per KWh
            (average power purchase cost for previous FY i.e. 2010-11)
            during the term of this agreement for delivered energy certified
            by Gujarat SLDC in the monthly State energy Account (SEA):
            a) In case in any subsequent FY the APPC goes below the
F           APPC goes below the APPC of FY 2010-11, the applicable
            tariff for ensuring. FY shall be such lower APPC of the
            previous year.
            b) Power producer and power procurer both have option to
            switch over from REC mechanism to preferential tariff after
            10 years from commissioning of the 23.10 MW WTGS. In case
G
            either party exercises the option, the tariff shall be Rs. 3.56
            per KWh (as determined by GERC through order no. 1 of
            2010 dated 30.1.2010) for balance term of the agreement.
            Further, power producer shall submit documentary evidence
            to GUVNL for de-registration of wind project from REC
H
 GUJARAT URJA VIKAS NIGAM LIMITED v. RENEW WIND                             699
  ENERGY (RAJKOT) PVT. LTD. [S. RAVINDRA BHAT, J.]

      mechanism in case either party ·exercise. Option to switch            A
      over from REC to preferential tariff.
      5.3 For each KVRAH drawn from the grid, the Company shall
      pay at the rate of as determined by the Commission to GETCO
      from time to time for each KARH drawn.
      5.4 Till the intra-State ABT is implemented, the certificate issued   B
      by GEDA for generation share of wind turbine shall be
      acceptable for monthly energy bill. The other provisions of
      intrastate ABT and Open access regulations appearing in this
      agreement shall also be applicable only after the intra-State
      ABT is implemented.                                                   C
      ************************              ****************
      ARTICLE 9
      TERM, TERMINATION AND DEFAULT
      9.1 Term of the agreement: This agreement shall become                D
      effective upon the executive and delivery thereof by the parties
      hereto and unless terminated pursuant to other provisions of
      the agreement, shall continue to be in force for such time
      until the completion of a period of 25 (twenty five) years from
      the commercial operation date.”
                                                                            E
      ………………………..
       Did the PPA in the present case, require prior approval of the
state commission
      45. RWE and the other respondents urge that the PPA was
unenforceable because it was not approved by the State Commission.          F
This court is of the considered view that the argument is unmerited and
insubstantial.
      46. The State Commission’s regulations (Renewable Sources
Regulations) relating to procurement of energy from Renewable Sources,
provides, inter alia, pertinently, as follows:                              G

      “3. Applicability of Renewable Purchase Obligation: These
      Regulations shall apply to: (1) Distribution licensee (2) Any
      other person consuming electricity

                                                                            H
700            SUPREME COURT REPORTS                          [2023] 7 S.C.R.


A           (i) generated from conventional Captive Generating Plant
            having capacity of 5 MW and above for his own use and / or
            (ii) procured from conventional generation through open
            access and third party sale.”
             47. From a reading of the above provision, it is evident that there
B     was never any provision, which mandated prior approval by the state
      commission, of PPAs entered into, by parties, in exercise of their free
      choice, in relation to renewable energy sources. As a matter of fact, in
      the case of renewable power, the state commission had approved a
      model PPA. Further, the tariff terms and conditions to the extent decided
C     are by the Central Commission and not by the State Commission. These
      are incorporated in the model PPA. Neither the commission, nor the
      contesting respondents, during the hearings in the present appeals, were
      able to point out any provision in the PPA in the present case, which
      conflicted with any provision of the model PPA, or any express regulation.
      Furthermore, it was not established how in the absence of any reference
D     to the Multi Year Tariff Regulations, they were applicable to PPAs
      relating to renewable energy sources.
             48. This court is also of the considered view, that in the absence
      of specific norms prescribing prior approval of PPAs like in the case of
      provisions of Regulation 21 of the Maharashtra Electricity Regulatory
E     Commission (Multi Year Tariff) Regulations, 2019; Regulation 45 of the
      Delhi Electricity Regulatory Commission Comprehensive (Conduct of
      Business) Regulations 2001 and Regulation 36 of the Andhra Pradesh
      Electricity Regulatory Commission (Distribution Licensee) Regulations,
      2013, the respondent’s arguments on this aspect cannot be accepted. In
F     these circumstances, the findings of APTEL, not based on any stipulated
      obligations under provisions of the state regulations, requiring approval
      of the state commission, for its operation, cannot be sustained.
            Whether change in the REC Regulations obliged revision of
      the PPA in this case
G             49. In Emco Ltd (supra), the parties had entered into a PPA on
      09.12.2010 for the sale and purchase of solar power. The PPA was
      modified on 07.05.2011 in view of certain difficulties in the location of
      the unit. When the PPA was entered into, the tariff order was applicable.
      The PPA was thus entered into during the control period of the first
      tariff order. The second tariff order came into force on 27.01.2012. It
H
 GUJARAT URJA VIKAS NIGAM LIMITED v. RENEW WIND                               701
  ENERGY (RAJKOT) PVT. LTD. [S. RAVINDRA BHAT, J.]

granted certain concessions to purchase and availing of the benefit of        A
accelerated depreciation under the income tax and did not grant such
benefits to purchasers and tariff payable to power purchasers which did
not avail of the benefit of accelerated depreciation. The respondent Emco
had not availed accelerated depreciation. Despite that, it approached
the Gujarat State Commission, seeking a determination of the tariff afresh,
                                                                              B
contending that the position had changed. This court noticed that the
power purchaser had contended that notwithstanding that it entered into
a PPA during the control period, it was not obliged to sell power to the
distributor for a price specified in the PPA and was legally entitled to
seek fixation of separate tariff. The Court rejected the contention after
noticing the arguments. The relevant extracts of the judgment (In Emco        C
Ltd.) are as below:
       “11. The case of the first respondent is that notwithstanding
      the fact that it entered into a PPA during the “control period”
      specified in the First Tariff Order, it is not obliged to sell power
      to the appellant for the price specified in Article5.2 of the           D
      PPA and is legally entitled to seek (from the second
      respondent) fixation of a separate tariff. It is the further case
      of the first respondent that under the PPA, the appellant is
      under an obligation to procure the power from the first
      respondent for a period of 25 years if the first respondent
      commences the generation of power within the “control                   E
      period” and is also obliged to pay for the power procured by
      it at the rates specified in Article 5.2 of the PPA. But the
      obligation of the first respondent to sell power generated by
      it to the appellant at the rates specified in Article 5.2 of the
      PPA comes into existence only on the happening of the two               F
      contingencies i.e. the first respondent (i) commencing the
      generation of power within the “control period” stipulated
      under the First Tariff Order; and (ii) choosing to avail the
      “benefit of accelerated depreciation” under the Income Tax
      Act. According to the first respondent, the stipulation under
      the First Tariff Order that the tariff fixed there under is not         G
      applicable to those Projects which “do not get such benefit,
      the Commission would on a petition in that respect determine
      a separate tariff taking into account all the relevant facts
      from not” would only imply that tariff fixed under the First
      Tariff Order is not applicable to those Projects/power                  H
702            SUPREME COURT REPORTS                         [2023] 7 S.C.R.


A           producers which do not avail the “benefit of accelerated
            depreciation” under the Income Tax Act.
            xxxxxx                     xxxxxx                   xxxxxx
            13. We have already noticed that the first respondent did not
            commence generation of power within the “control period”
B           stipulated under the First Tariff Order and also did not avail
            the “benefit of the accelerated depreciation” under the Income
            Tax Act. It is admitted on all hands that the “benefit of
            accelerated depreciation” mentioned in the First Tariff Order
            and the PPA is the stipulation contained in Section 32(1)(i) of
C           the Income Tax Act read with Rule 5(1-A) of the Income Tax
            Rules. They provide for the method and manner in which
            depreciation of the assets of an assessee is to be calculated.
            xxxxxx                     xxxxxx                   xxxxxx
            26. Apart from that, the conclusion of the Tribunal in the instant
D           case is wrong. First of all the PPA does not give any option to
            the respondent to opt out of the terms of the PPA. It only
            visualises a possibility of the producer not commissioning its
            Project within the “control period” stipulated under the First
            Tariff Order and provides that in such an eventuality what
            should be the tariff applicable to the sale of power by the
E           first respondent. Secondly, the PPA does not “entitle” the first
            respondent to the “tariff as determined by the” second
            respondent by the Second Tariff Order. On the other hand,
            the PPA clearly stipulates that in such an eventuality:
            “Above tariff shall apply for solar projects commissioned on
F           or before 31-12-2011. In case, commissioning of solar power
            project is delayed beyond 31-12-2011, GUVNL shall pay the
            tariff as determined by the Hon’ble GERC for solar projects
            effective on the date of commissioning of solar power project
            or abovementioned tariff, whichever is lower.”
G                                                     (emphasis supplied)”
             50. In Transmission Corporation of Andhra Pradesh Ltd
      (Supra), the state commission had, by an order dated 20.06.2001 directed
      generators of non-conventional energy to supply power exclusively to
      the A.P. Transmission Corporation. Energy developers were not permitted
H     to sell power to third parties. The Commission also approved the rate
 GUJARAT URJA VIKAS NIGAM LIMITED v. RENEW WIND                             703
  ENERGY (RAJKOT) PVT. LTD. [S. RAVINDRA BHAT, J.]

prevailing earlier for supply @ 2.25/- per unit with a 5% escalation per    A
annum from 1994-1995 being the base year. The parties entered into
PPA after the passing of the Regulatory Commission’s order. The PPA
embodied or reflected the tariff @ 2.25/- per unit with escalation @
5% per annum having 1994 as the base year to be revised annually upto
2003-04. After that, the purchase price was to be decided by the state
                                                                            B
commission. The stipulation also provided that further review of the
purchase price on the completion of 10 years from the commissioning of
the project would be made.
       51. The A.P. Transmission Corporation’s functions devolved upon
discoms by operation of law. In this background, the state commission
exercised suo motu powers to revise non-conventional energy purchase        C
tariffs. The APTEL rejected the appeal of the A.P. Transmission
Corporation. This court held that once agreements were signed and were
enforceable in law, such enforceable obligations could not be frustrated.
The court also negatived the arguments on behalf of the power generator
that they had been subjected to coercion or duress. The observations of     D
this court in this regard are pertinent in this regard and are extracted
below:
      “39. [..] In the present case the order dated 20-6-2001 was
      fully accepted by the parties without any reservation. After
      the lapse of more than reasonable time of their own accord            E
      they voluntarily signed the PPA which contained a specific
      stipulation prohibiting sale of generated power by them to
      third parties. The agreement also had a renewal clause
      empowering TRANSCO/ APTRANSCO/Board to revise the
      tariff. Thus, the documents executed by these parties and their
      conduct of acting upon such agreements over a long period,            F
      in our view, bind them to the rights and obligations stated in
      the contract. The parties can hardly deny the facts as they
      existed at the relevant time, just because it may not be
      convenient now to adhere to those terms. Conditions of a
      contract cannot be altered/avoided on presumptions or                 G
      assumptions or the parties having a second thought that a
      term of contract may not be beneficial to them at a subsequent
      stage. They would have to abide by the existing facts,
      correctness of which, they can hardly deny. Such conduct,
      would be hit by allegans contraria non est audiendus.”
                                                                            H
704                SUPREME COURT REPORTS                      [2023] 7 S.C.R.


A             ----------------------------
              42. Now, we will proceed to examine the merits or otherwise
              of the findings recorded by the Tribunal that the PPAs executed
              by the parties were result of some duress and thus, it will not
              vest the authorities with the power to review the tariff and
B             other granted incentives. PPAs were executed prior and
              subsequent to the issuance of the order dated 20-6 2001.
              Different persons executed the contracts at different times in
              full awareness of the terms and conditions of such PPAS. To
              frustrate a contract on the ground of duress or coercion, there
              have to be definite pleadings which have to be substantiated
C             normally by leading cogent and proper evidence. However,
              in the case where summary procedure is adopted like the
              present one, at least some documentary evidence or affidavit
              ought to have been filed raising this plea of duress specifically.
              43. [..] From the record before us, nothing was brought to
D             our notice to state the plea of duress and to prove the alleged
              facts which constituted duress, so as to vitiate and/or even
              partially reduce the effect of the PPAs. On the one hand, the
              Tribunal appears to have doubted the binding nature of the
              contracts stating that they contained unilateral conditions
              introduced by virtue of order and approval of the Regulatory
E             Commission, while on the other hand, in para 53 of the order,
              it proceeded on the presumption that PPAS are final and
              binding and still drew the conclusion that the Regulatory
              Commission could not revise the tariff. Even in the order, no
              facts have been pointed out which, in the opinion of the
F             Tribunal, constituted duress within the meaning of the Contract
              Act so as to render the contract voidable.”
              52. In Gujarat Urja v. Solar Power Company India Pvt.
           30
      Ltd. (hereafter “Solar Power Company India Pvt. Ltd”), the issue
      involved was whether the State Commission could extend the control
      period. One of the arguments made was that having regard to the terms
G
      of the PPA, the exercise of such power to extend the control period was
      not available under the statute. The Court (per Kurian Joseph, J) referred
      to Gujarat Urja Vikas Nigam Ltd. v. Tarini Infrastructure Ltd.31
      wherein it was held that:
      30
           (2017) 14 S.C.R. 115
H     31
           (2016) 5 S.C.R. 990
 GUJARAT URJA VIKAS NIGAM LIMITED v. RENEW WIND                         705
  ENERGY (RAJKOT) PVT. LTD. [S. RAVINDRA BHAT, J.]

     “10. While Section 61 of the Act lays down the principles for      A
     determination of tariff, Section 62 of the Act deals with
     different kinds of tariffs/charges to be fixed. Section 64
     enumerates the manner in which determination of tariff is
     required to be made by the Commission. On the other hand,
     Section 86 which deals with the functions of the Commission
                                                                        B
     reiterates determination of tariff to be one of the primary
     functions of the Commission which determination includes,
     as noticed above, a regulatory power with regard to purchase
     and procurement of electricity from generating companies by
     entering into PPA(s). The power of tariff determination/fixation
     undoubtedly is statutory and that has been the view of this        C
     Court expressed in paras 36 and 64 of A.P. TRANSCO v. Sai
     Renewable Power (P) Ltd. This, of course, is subject to
     determination of price of power in open access (Section 42)
     or in the case of open bidding (Section 63). In the present
     case, admittedly, the tariff incorporated in PPA between the
                                                                        D
     generating company and the distribution licensee is the tariff
     fixed by the State Regulatory Commission in exercise of its
     statutory powers. In such a situation it is not possible to hold
     that the tariff agreed by and between the parties, though finds
     mention in a contractual context, is the result of an act of
     volition of the parties which can, in no case, be altered except   E
     by mutual consent. Rather, it is a determination made in the
     exercise of statutory powers which got incorporated in a
     mutual agreement between the two parties involved.
     **********                                         ***********
      This Court in Solar Power Company India Pvt. Ltd (Supra)          F
further observed that:
     35. This Court should be specially careful in dealing with
     matters of exercise of inherent powers when the interest of
     consumers is at stake. The interest of consumers, as an
     objective, can be clearly ascertained from the Act. The            G
     Preamble of the Act mentions “protecting interest of
     consumers” andSection61 (d) requires that the interests of
     the consumers are to be safeguarded when the appropriate
     Commission specifies the terms and conditions for
     determination of tariff. Under Section 64 read with Section
                                                                        H
706              SUPREME COURT REPORTS                        [2023] 7 S.C.R.


A             62, determination of tariff is to be made only after considering
              all suggestions and objections received from the public. Hence,
              the generic tariff once determined under the statute with notice
              to the public can be amended only by following the same
              procedure. Therefore, the approach of this Court ought to be
              cautious and guarded when the decision has its bearing on
B
              the consumers.
              36. Regulation 85 provides for extension of time. It may be
              seen that the same is available only in two specified situations
              - (i) for extension of time prescribed by the Regulations, and
              (ii) extension of time prescribed by the Commission in its order
C             for doing any act. The control period is not something
              prescribed by the Commission under the Conduct of Business
              Regulations. The control period is also not an order by the
              Commission for doing any act. Commissioning of a project is
              the act to be performed in terms of the obligation under the
D             PPA and that is between the producer and the purchaser viz.
              Respondent 1 and appellant. Hence, the Commission cannot
              extend the time stipulated under the PPA for doing any act
              contemplated under the agreement in exercise of its powers
              under Regulation 85. Therefore, there cannot be an extension
              of the control period under the inherent powers of the
E             Commission.
              37. The Commission being a creature of statute cannot assume
              to itself any powers which are not otherwise conferred on it.
              In other words, under the guise of exercising its inherent power,
              as we have already noticed above, the Commission cannot
F             take recourse to exercise of a power, procedure for which is
              otherwise specifically provided under the Act.”
              53. The concurring view expressed by Banumathi J, crucially held
      that:

G             “Sanctity of power purchase agreement
              22. It is contended that Section 86(1)(b) of the Act empowers
              the State Commission to regulate the price of sale and purchase
              of electricity between the generating companies and
              distribution licensees and the terms and conditions of the PPA
              cannot be set to be inviolable. Merely because in PPA, tariff
H
     GUJARAT URJA VIKAS NIGAM LIMITED v. RENEW WIND                          707
      ENERGY (RAJKOT) PVT. LTD. [S. RAVINDRA BHAT, J.]

         rate as per Tariff Order, 2010 is incorporated that does not        A
         empower the Commission to vary the terms of the contract to
         the disadvantage of the consumers whose interest the
         Commission is bound to safeguard. Sanctity of PPA entered
         into between the parties by mutual consent cannot be allowed
         to be breached by a decision of the State Commission to extend
                                                                             B
         the earlier control period beyond its expiry date, to the
         advantage of the generating company, Respondent 1 and
         disadvantage of the appellant. Terms of PPA are binding on
         both the parties equally.
         66. In Gujarat Urja Vikas Nigam Ltd. v. EMCO Ltd., facts
         were similar and the question of law raised was whether by          C
         passing the terms and conditions of PPA, the respondent can
         assail the sanctity of PPA. This Court held that power producer
         cannot go against the terms of the PPA and that as per the
         terms of the PPA, in case, the first respondent is not able to
         commence the generation of electricity within the “control          D
         period” the first respondent will be entitled only for lower of
         the tariffs.”
     54. Similarly, in Bangalore Electricity Supply Co. Ltd. vs.
Konark Power Projects Ltd. & Ors32 this court held as follows:
         “13. The contention that Under Regulations 5.2, 5.3, 5.4 of         E
         the 2004 Regulations as well as Sections 61 and 62 of the
         Electricity Act, power is vested with the Commission to vary
         the tariff is concerned, such power specifically provided for
         in the said Regulations will only operate prior to fixing of the
         tariff once the concerned Power Purchase Agreements are             F
         ultimately concluded and the terms are agreed between the
         parties under the Power Purchase Agreements, thereafter, in
         our considered opinion, Regulation 5.1 of the 2004
         Regulations alone would apply in the case of the parties before
         us. Consequently, there was no scope for the Commission to
         vary the tariff agreed between the parties under the approved       G
         Power Purchase Agreement.”
      55. Section 61 of the Act enacts the basis for tariff determination.
On the other hand, Section 62 is concerned with the fixation of various
32
     (2016) 13 SCC 515                                                       H
708             SUPREME COURT REPORTS                           [2023] 7 S.C.R.


A     other charges and tariffs. Section 64 lists the manner and procedure for
      tariff determination by the Commission. Section 86 lists the functions of
      the Commission and reiterates the determination of tariffs to be a
      prominent task of the commission. Tariff determination no doubt,
      comprehends the exercise of regulatory function, including purchase,
      sourcing, procurement of electricity from generators, by distribution and
B
      other licensees, and their sales. This part involves generating companies
      entering into PPA(s) with procuring entities or licensees. Tariff fixation
      is a statutory function. Yet, by virtue of Section 42, it is subject to open
      access determination of the price of power, and subject to Section 63
      wherever it involves open bidding. In the facts of this case, the PPA
C     incorporated a tariff between the respondents and Gujarat Urja
      constituted the tariff fixed by the State Regulatory Commission in the
      exercise of its statutory powers. The issue and sale of RECs, constituted
      an important part of that bargain, between the two parties, based on the
      assessment of their commercial interest.
D             56. The important feature of the REC Mechanism is that in it,
      WPDs (i.e. respondents) had to sell power to distribution licensees at a
      mutually agreed price, not exceeding the Average Power Purchase Cost
      (‘APPC’) of the DISCOMs, (such as Gujarat Urja). The WPDs were
      entitled to the additional benefit of Renewable Energy Certificates issued
      to it which could be traded in Power Exchange for a price. The
E     consideration payable to WPDs consisted of firstly, a mutually agreed
      power Component and secondly a green component through RECs
      traded in the Exchange. The alternative to the WPDs was to sell to
      licensees at a preferential tariff, determined by the state commission.
      In the latter event, WPDs were not entitled to the additional benefit of
F     the green component, which was the tradable RECs the sale of which
      would have led to increased revenues. The respondent WPDs chose
      the REC mechanism, while entering into PPAs in these cases, with Gujarat
      Urja. The PPAs entered by WPDs provided for the fixed tariff of
      2.64/kWh for the entire term (25 years), as mutually agreed (Article 5.2
      of PPA). WPDs were entitled to and were trading RECs in the power
G     exchange, deriving extra monetary benefits: which, at the relevant period
      was 1.50/kWh (floor price at the time of signing of PPA). The
      Preferential Tariff determined by the state commission, for WPDs not
      opting for the REC Mechanism was 3.56/kWh. The WPDs were not
      entitled to any additional REC benefits, had they adopted the preferential
H     tariff route.
 GUJARAT URJA VIKAS NIGAM LIMITED v. RENEW WIND                                 709
  ENERGY (RAJKOT) PVT. LTD. [S. RAVINDRA BHAT, J.]

        57. The respondents successfully complained before the State            A
Commission, and APTEL, that the PPA, which they had entered into
with Gujarat Urja, whereby the tariff was fixed at 2.64/kWh (with the
price of RECs sold by them) was, in the long run, less beneficial than
3.56/kWh. During the hearing, it was sought to be urged that the cost of
RECs in the exchange, had been decreasing, whereas the preferential
                                                                                B
tariffs had risen. On this aspect, Regulation 9 of the REC Regulations
2010 prescribes the price determination mechanism for RECs in the
power exchange. Proviso to Regulation 9 (1) of the REC Regulations
2010 empowers the central commission, in consultation with the Central
Agency and the Forum of Regulators, to provide the floor price and
forbearance price separately for solar and non-solar certificates. This         C
provision is important because it enables regulatory intervention in the
public interest: if the price went below a certain limit, the floor price was
to be prescribed, to take care of the interests of generators- like the
respondents; if the price went too high, a forbearance price could be
fixed, to take care of the interests of the consumers and distributors. By
                                                                                D
Regulation 9 (2) of the REC Regulations 2010, the Central Commission,
was to be guided, in determining the floor and forbearance price, by
diverse factors, such as (a) variation in cost of generation of different
renewable energy technologies falling under solar and non-solar category,
across states in the country; (b) variation in the Pooled Cost of Purchase
across States in the country; (c) Expected electricity generation for non-      E
renewable energy sources [including (i) expected renewable energy
capacity under preferential tariff (ii) expected renewable energy under
mechanism of certificates] (d) Renewable purchase obligation targets
set by various State Commissions. By virtue of Explanation to Regulation
5 (1) of the REC Regulations, “the weighted average pooled price at
                                                                                F
which the distribution licensee has purchased the electricity
including cost of self-generation, if any, in the previous year from
all the energy suppliers long-term and short-term, but excluding
those based on renewable energy sources, as the case may be.” An
important factor which cannot be lost sight of is that all the respondent’s
WPDs were registered, under the REC Regulations, based on the state             G
commission’s tariff order, of 2010. It is undisputed, that to register under
the REC Regulations 2010, an entity (such as WPDs) had to be (a)
accredited, with a State Agency [(defined by Regulation 2 (n) of the
REC Regulations as an agency “designated by the State Commission
to act as the agency for accreditation and recommending the
                                                                                H
710             SUPREME COURT REPORTS                            [2023] 7 S.C.R.


A     renewable energy projects for registration”) and an entity “not having
      any power purchase agreement for the capacity related to such
      generation to sell electricity at a preferential tariff determined by
      the Appropriate Commission].
            58. Furthermore, the state commission, in its tariff order, dated
B     30.01.2010 (which was operative for three years, with the control period
      beginning from 10.08.2009) while determining the preferential tariff, had
      observed that it would apply for 25 years:
            “The Commission, therefore, determines the tariff for
            generation of electricity from wind energy projects at Rs.3.56
C           (constant) for its entire project life of 25 years i.e. from the
            first year to the twenty fifth year. This tariff shall be applicable
            for purchase of wind energy by Distribution Licensees/ other
            entities for complying with the renewable power purchase
            obligations specified in the regulation by commission from
            time to time. This tariff is applicable to wind energy projects
D           which commission brand new wind energy plants and
            equipments on 11th August, 2009 onwards.”
              59. In the present case, the PPA was entered into by the parties
      on 29.03.2102, within the control period stipulated in the tariff order of
      2010. The change in the REC Regulations 2010, whereby the Explanation
E     to Regulation 5 was amended resulted in a change. The pre-existing
      clause that the power would be “at a price not exceeding pooled cost
      of the power purchase”was altered to “at the pooled cost of power
      purchase”. This change, was through the Second Amendment (to the
      REC Regulations), carried out on 10.07.2013. It is a matter of record,
F     that for the period between 29.03.2102 and 10.07.2013 - and indeed,
      after the Second Amendment, no difficulty was experienced in the pricing
      mechanism agreed by the parties, under the PPA. It was on 10.12.2013
      that the respondent WPD approached the state commission for re-
      determination of tariff. Clearly, this was an opportunistic attempt to derive
      advantage from the change, brought about by the Second Amendment,
G     and seek to have it applied to an existing contract, which cannot be
      countenanced. In view of these reasons, it is held that the reasoning of
      APTEL, and the State Commission cannot be upheld.
            Applicability of the Second Amendment to pre-existing
      contracts- the general law
H
 GUJARAT URJA VIKAS NIGAM LIMITED v. RENEW WIND                                711
  ENERGY (RAJKOT) PVT. LTD. [S. RAVINDRA BHAT, J.]

        60. Power Purchase Agreements are essentially not statutory            A
contracts; however, certain terms contained in those contracts, are
regulated by law, i.e. applicable regulations, under the Act. The PPA
between a generating company or, as in this case, a wind generator, and
a distribution licensee, such as Gujarat Urja, is the outcome of a carefully
considered decision, whereby the parties, after due deliberations and
                                                                               B
negotiations, agree on terms, which are based on existing law and
regulations. Aside from contending that the PPA had to be approved,
(which this court has rejected in a previous part of this judgment) but
was not, the respondents also urge, independently, that the Second
Amendment had necessitated re-visiting of the terms of the PPA, relating
to the payment of average pooled power purchase cost, given that the           C
amendment mandated that the power would be at the pooled power
purchase cost, as opposed to the previous provision, which stated that
the cost would not exceed the pooled power purchase cost.
       61. Regulation 1 (2) of the Second Amendment clearly provides
that the amendments were to come into force from the date of their             D
publication in the Official Gazette, which is 10th July, 2013. Furthermore,
the Statement of Reasons, accompanying the Second Amendment,
clarified that existing PPAs were not affected:
      “Some of the stakeholders have suggested to clarify as to
      whether the PPAs executed at price lower than APPC would                 E
      become ineligible under REC Mechanism. It is felt that the
      tariff for electricity component lower or higher than APPC
      may lead to avoidable loss or profit to RE generator. The
      Commission would like to clarify that the intention is not to
      debar the projects that have executed PPA at tariff lower than
      APPC. This amendment will apply prospectively and as such                F
      will not affect the already executed PPAs at lower than APPC.”
      62. The Constitution Bench of this Court, in PTC India (supra)
had indicated that state commissions possess the power to vary existing
contracts, especially PPAs:
                                                                               G
      “40. [..] To regulate is an exercise which is different from
      making of the regulations. However, making of a regulation
      under Section 178 is not a precondition to the Central
      Commission taking any steps/measures under Section 79(1).
      As stated, if there is a regulation, then the measure under
                                                                               H
712     SUPREME COURT REPORTS                        [2023] 7 S.C.R.


A     Section 79(1) has to be in conformity with such regulation
      under Section 178. This principle flows from various judgments
      of this Court, which we have discussed hereinafter. For
      example, under Section 79(1)(g), the Central Commission is
      required to levy fees for the purpose of the 2003 Act. An order
      imposing regulatory fees could be passed even in the absence
B
      of a regulation under Section 178. If the levy is unreasonable,
      it could be the subject-matter of challenge before the appellate
      authority under Section 111 as the levy is imposed by an order/
      decision-making process. Making of a regulation under
      Section 178 is not a precondition to passing of an order
C     levying a regulatory fee under Section 79(1)(g). However, if
      there is a regulation under Section 178 in that regard then
      the order levying fees under Section 79(1)(g) has to be in
      consonance with such regulation.
      *********
D     40. [..] One must keep in mind the dichotomy between the
      power to make a regulation under Section 178 on the one
      hand and the various enumerated areas in Section 79(1) in
      which the Central Commission is mandated to take such
      measures as it deems fit to fulfil the objects of the 2003 Act.
E     Applying this test to the present controversy, it becomes clear
      that one such area enumerated in Section 79(1) refers to
      fixation of trading margin. Making of a regulation in that
      regard is not a precondition to the Central Commission
      exercising its powers to fix a trading margin under Section
      79(1)(j), however, if the Central Commission in an appropriate
F     case, as is the case herein, makes a regulation fixing a cap
      on the trading margin under Section 178 then whatever
      measures the Central Commission takes under Section 79(1)(j)
      have to be in conformity with Section 178. One must
      understand the reason why a regulation has been made in
G     the matter of capping the trading margin under Section 178
      of the Act. Instead of fixing a trading margin (including
      capping) on a case-to-case basis, the Central Commission
      thought it fit to make a regulation which has a general
      application to the entire trading activity which has been
      recognised, for the first time, under the 2003 Act. Further, it
H
  GUJARAT URJA VIKAS NIGAM LIMITED v. RENEW WIND                                 713
   ENERGY (RAJKOT) PVT. LTD. [S. RAVINDRA BHAT, J.]

       is important to bear in mind that making of a regulation under            A
       Section 178 became necessary because a regulation made
       under Section 178 has the effect of interfering and overriding
       the existing contractual relationship between the regulated
       entities. A regulation under Section 178 is in the nature of a
       subordinate legislation. Such subordinate legislation can even
                                                                                 B
       override the existing contracts including power purchase
       agreements which have got to be aligned with the regulations
       under Section 178 and which could not have been done
       across the board by an order of the Central Commission under
       Section 79(1)(j).
       *********                                                                 C

       43. [..] While deciding the nature of an order (decision) vis-
       à-vis a regulation under the Act, one needs to apply the test
       of general application. On the making of the impugned 2006
       Regulations, even the existing power purchase agreements
       (PPA) had to be modified and aligned with the said                        D
       Regulations. In other words, the impugned Regulations make
       an inroad into even the existing contracts. This itself indicates
       the width of the power conferred on CERC under Section
       178 of the 2003 Act. All contracts coming into existence after
       making of the impugned 2006 Regulations have also to factor               E
       in the capping of the trading margin. This itself indicates that
       the impugned Regulations are in the nature of subordinate
       legislation.     Such     regulatory     intervention        into
       the existing contracts across the board could have been done
       only by making regulations under Section 178 and not
       bypassing an order under Section 79(1)(j) of the 2003 Act.                F
       Therefore, in our view, if we keep the above discussion in
       mind, it becomes clear that the word “order” in Section 111
       of the 2003 Act cannot include the impugned 2006 Regulations
       made under Section 178 of the 2003 Act.”
       63. Whilst there cannot be any doubt that regulations framed under        G
the Act can be made applicable to existing contracts, what is discernible
from PTC India (supra) is that in that case, the applicability of the Trading
Margin Regulations which for the first time, compelled persons engaged
in trading of electricity, in terms of Section 2 (17) of the Act, to register,
obtain licenses, and operate within the margin limits indicated in the           H
714                SUPREME COURT REPORTS                          [2023] 7 S.C.R.


A     regulations. These provisions introduced a new regime, regulating an
      area, or activity which had hitherto been unregulated. The entire edifice
      of prescribing general standards for application to all those operating
      within its sweep, is to ensure that they are universal and constitute a
      code. The observations in PTC India (supra), therefore, are to be seen
      in this context. Being regulations of general application, dealing with a
B
      range of commercial activity, there could have been no question of existing
      contracts, operating in isolation, through separate silos, outside of their
      framework. In the present case, however, the PPAs were entered into
      in the exercise of equal bargaining power, after due negotiation by the
      parties, and within the framework of existing regulations: both central
C     and state. Therefore, unless any later amendment expressly overrides
      existing contracts, the terms of such agreements bind the parties.
            64. That amendments to laws, or regulations, unless expressly
      retrospective, are always prospective, is a settled proposition. In
      Purbanchal Cables & Conductors (P) Ltd. v. Assam State Electricity
D     Board & Ors.33, the position was articulated in this manner:
                “39. [..] This Court, time and again, has observed that any
                substantive law shall operate prospectively unless retrospective
                operation is clearly made out in the language of the statute.
                Only a procedural or declaratory law operates retrospectively
E               as there is no vested right in procedure.
                40. In the absence of any express legislative intendment of
                the retrospective application of the Act, and by virtue of the
                fact that the Act creates a new liability of a high rate of interest
                against the buyer, the Act cannot be construed to have
F               retrospective effect. Since the Act envisages that the supplier
                has an accrued right to claim a higher rate of interest in terms
                of the Act, the same can only be said to accrue for sale
                agreements after the date of commencement of the Act i.e. 23-
                9-1992 and not any time prior.”

G             65. In Commissioner of Income Tax v Vatika Township (P)
      Ltd.34, this court observed, in this context, that:
                “31. Of the various rules guiding how a legislation has to be
                interpreted, one established rule is that unless a contrary
      33
           (2012) 6 S.C.R. 905
      34
H          (2014) 12 S.C.R. 1037
     GUJARAT URJA VIKAS NIGAM LIMITED v. RENEW WIND                      715
      ENERGY (RAJKOT) PVT. LTD. [S. RAVINDRA BHAT, J.]

      intention appears, a legislation is presumed not to be intended    A
      to have a retrospective operation. The idea behind the rule is
      that a current law should govern current activities. Law passed
      today cannot apply to the events of the past. If we do something
      today, we do it keeping in view the law of today and in force
      and not tomorrow’s backward adjustment of it. Our belief in
      the nature of the law is founded on the bedrock that every         B
      human being is entitled to arrange his affairs by relying on
      the existing law and should not find that his plans have been
      retrospectively upset. This principle of law is known as lex
      prospicit non respicit : law looks forward not backward. As
      was observed in Phillips v. Eyre [Phillips v. Eyre, (1870) LR
                                                                         C
      6 QB 1], a retrospective legislation is contrary to the general
      principle that legislation by which the conduct of mankind is
      to be regulated when introduced for the first time to deal with
      future acts ought not to change the character of past
      transactions carried on upon the faith of the then existing
      law.                                                               D
      32. The obvious basis of the principle against retrospectivity
      is the principle of “fairness”, which must be the basis of every
      legal rule as was observed in [L’Office Cherifien des
      Phosphates v. Yamashita-Shinnihon Steamship Co. Ltd., (1994)
      1 All ER 20 (HL)] Thus, legislations which modified accrued
      rights or which impose obligations or impose new duties or         E
      attach a new disability have to be treated as prospective unless
      the legislative intent is clearly to give the enactment a
      retrospective effect; unless the legislation is for purpose of
      supplying an obvious omission in a former legislation or to
      explain a former legislation. We need not note the cornucopia
                                                                         F
      of case law available on the subject because aforesaid legal
      position clearly emerges from the various decisions and this
      legal position was conceded by the counsel for the parties.
      In any case, we shall refer to few judgments containing this
      dicta, a little later.”
      This proposition was again explained and applied in Union of       G
India v. Indusind Bank Ltd 35.
      66. In view of the above discussion, it is held that agreements,
such as the PPAs in the present case, entered into, voluntarily by the
35
     (2016) 11 S.C.R. 700
                                                                         H
716            SUPREME COURT REPORTS                          [2023] 7 S.C.R.


A     parties, before the Second Amendment, were not affected, by its terms.
      The findings to the contrary in the impugned order, are set aside.
             Were the respondents coerced into entering into PPAs
             67. The State Commission had concluded that the PPAs were
      also unenforceable, to the extent of being in non-conformity with the
B     pre-amended Rule 5, of the REC Regulations, as the contracts were
      entered into by parties with unequal bargaining power. This aspect was
      noted by APTEL, which held as follows:
             “9.19 [..] The State Commission after careful consideration
             of the submissions made by both the parties and after due
C            analysis of the available material on record has recorded its
             findings in the impugned order that the conditions envisaged
             in the PPA relating to the tariff and other associated conditions
             appeared to be one sided in favour of the Appellant and
             accordingly concluded the case of coercion or duress and
             unequal bargaining power between the parties being
D            responsible for executing an Agreement full of unjustness and
             perversity. In view of these facts, we hold that the State
             Commission has analysed this issue rightly in accordance with
             law and passed the order assigning cogent reasoning. Thus,
             we do not find any material case or ground for our
E            interference in the matter.
             10. SUMMARY OF OUR FINDINGS:
             Having regard to the careful consideration and critical
             analysis of the facts and submissions of the learned counsel
             for the Appellants as well as the Respondents, we hold that
             the findings of the State Commission are just and right in
F
             accordance with law.”
             68. In Transmission Corporation of Andhra Pradesh Ltd
      (supra), this court observed, in the context of a contention of coercion,
      as follows:
             “42. [..] To frustrate a contract on the ground of duress or
G
             coercion, there have to be definite pleadings which have to
             be substantiated normally by leading cogent and proper
             evidence. However, in the case where summary procedure is
             adopted like the present one, at least some documentary
             evidence or affidavit ought to have been filed raising this
H            plea of duress specifically.[..]”
     GUJARAT URJA VIKAS NIGAM LIMITED v. RENEW WIND                           717
      ENERGY (RAJKOT) PVT. LTD. [S. RAVINDRA BHAT, J.]

        69. In Shanti Budhiya Vesta Patel & Ors. v. Nirmala Jayprakash        A
Tiwari& Ors.36 , this court held that to establish fraud or coercion, there
should be”(a) an express allegation of coercion or fraud, and (b)
all the material facts in support of such allegations must be laid out
in full and with a high degree of precision. In other words, if coercion
or fraud is alleged, it must be set out with full particulars.” The
                                                                              B
court had cited and applied the principle enunciated in Bishundeo
Narain v. Seogeni Rai37where it was held that:
        “ […] Now if there is one rule which is better established
        than any other, it is that in cases of fraud, undue influence
        and coercion, the parties pleading it must set forth full
        particulars and the case can only be decided on the particulars       C
        as laid. There can be no departure from them in evidence.
        General allegations are insufficient even to amount to an
        averment of fraud of which any court ought to take notice,
        however strong the language in which they are couched may
        be, and the same applies to undue influence and coercion.             D
        [See Order 6 Rule 4 of the Civil Procedure Code.]”
        70. In New Indian Assurance Co. Ltd v Genus Power
Infrastructure Ltd38 this court dealt with the standard of pleadings and
evidence, needed in cases, where coercion or duress is alleged:
        “8. It is therefore clear that a bald plea of fraud, coercion,        E
        duress or undue influence is not enough and the party who
        sets up a plea, must prime facie establish the same by placing
        material before the Chief Justice/his designate.”
       71. In the present case, this salutary rule was thrown to the wind,
by the State Commission. In this court’s opinion, APTEL, in the most
cavalier fashion, virtually rubber stamped the State Commission’s findings    F
on coercion, in regard to the entering into the PPA by the parties. There
was no shred of evidence, nor any particularity of pleadings, beyond a
bare allegation of coercion, alleged against Gujarat Urja. It is
incomprehensible how such an allegation could have been entertained
and incorporated as a finding, given that the respondents are established     G
companies, who enter into negotiations and have the support of experts,
including legal advisers, when contracts are finalized. The findings
36
   (2010) 4 S.C.R. 958
37
   (1951) 1 SCR 548
38
   2014 (12) SCR 360                                                          H
718              SUPREME COURT REPORTS                           [2023] 7 S.C.R.


A     regarding coercion are, therefore, wholly untenable. This court is also of
      the opinion that the casual approach of APTEL, in not reasoning how
      such findings could be rendered, cannot be countenanced. As a judicial
      tribunal, dealing with contracts and bargains, which are entered into by
      parties with equal bargaining power, APTEL is not expected to casually
      render findings of coercion, or fraud, without proper pleadings or proof,
B
      or without probing into evidence. The findings of coercion are therefore,
      set aside.
             Conclusions
             72. In view of the foregoing discussion, it is held that the concurrent
C     findings and orders of the State Commission and APTEL cannot be
      sustained. They are accordingly set aside. The appeals are allowed,
      with costs payable to the appellants.

      Divya Pandey                                                   Appeals allowed.
      (Assisted by : Shevali Monga, LCRA)
D




E




F




G




H


Search Indian case law

Ask in plain English, not just keywords. 25,000 AI words free, no card.

Try "Power Purchase Agreement"Sign in to search

For a digitally signed copy suitable for filing, refer to the court's own website. Only the court can issue one.