JAI DAYAL AND ORS.versusKRISHAN LAL GARG AND ANR.
- Citation
- 1996 INSC 1298
- Decided
- 6 November 1996
- Disposal
- Appeal(s) allowed
Holding
Execution proceedings under Order 21 Rule 32 CPC are proper to enforce a final perpetual injunction, and Section 22 of the Easement Act does not preclude such execution; a fresh suit is barred by Section 49 CPC.
Summary
Jai Dayal sued Krishan Lal Garg for a perpetual and mandatory injunction to keep a 5‑ft passage between their houses free from obstruction. The trial court granted the injunction in 1964, which was confirmed on appeal. After the obstruction was initially removed, Garg later built a shop that completely blocked the passage, prompting Dayal to seek execution of the decree under Order 21 Rule 32 of the CPC. The High Court set aside the execution, holding that Section 22 of the Easement Act required a fresh adjudication of the easement right. The Supreme Court held that once an injunction decree is final, execution proceedings may be used to enforce it; Section 22 applies only when the right is first determined, and a fresh suit is barred by Section 49 of the CPC. Consequently, the appeal was allowed, the High Court order was reversed, and the lower courts' decisions were restored.
Issues considered
- Whether execution under Order 21 Rule 32 of the CPC can be employed to enforce a final perpetual and mandatory injunction despite the provisions of Section 22 of the Easement Act.
- Whether Section 22 of the Easement Act is applicable when the easement right has already been adjudicated and a decree is in force.
- Whether a fresh suit is barred under Section 49 of the CPC after a decree for injunction has become final.
Legislation cited
- Code of Civil Procedure, 1908s. Order 21 Rule 32, s. Section 49
- Easement Act, 1882s. Section 22
Subjects
Judgment
A JAi DAY AL AND ORS.
v.
KRISHAN LAL GARG AND ANR.
NOVEMBER 6, I 996
B [K. RAMASWAMY AND G.B PATTANAIK, JJ.]
Code of Civil Procedure, 1908/Easement Act, 1882 :
S.49, Order 21, R.32/s.22-Execution of decree-Plaintiff-
C Appellant's suit for perpetual injunction and mandatory injunction
restraining defendant from blocking passage to appellant's house decreed-
Later, the judgment-debtor constructed a shop blocking the passage-Court
issued orders of attachment ofproperty and detention ofjudgment-debtor
in case obstruction is not removed-High Court holding that matter to be
adjudicated uls 22 of Easement Act-Held, since attachment was made for
D enforcement ofperpetual injunction, the decree is required to be complied
with-Jn the circumstances, s. 22 of Easement Act cannot be resorted to--
If a judgment-debtor has suffered the "decree, no attempt to circumvent the
perpetual injunction can be permitted-Non-compliance is a continuing
disobedience entailing penal consequences_:A fresh suit is barred u/s 49,
CPC.
E
CIVIL APPELLATE JURISDICTION: Civil Appeal No. 2583 of
I 980.
From the Judgment and Order dated 9.4.1980 of the Allahabad High
F Court in Execution Second Appeal No. 789 of 1969.
·Rani Chhabra, (N.P.) for the Appellant No. 2-5. D. Goburdhan for
the Appellant No. I.
R.K. Maheshewari for the Respondent.
G
The following Order of the Court was delivered :
This appeal by special leave arises from the judgment of the learned
single Judge of the Allahabad High Court, made on 9.4.1980 in Execution
H Second Appeal No. 789 of 1969.
538
JAi DAYAL v. KL. GARG 539
The admitted facts are that the appellant had filed Suit No. 1023/61 A
against the respondent for perpetual injunction and also for mandatory
injunction restraining him from blocking passage of 5 ft. between the
house of the appellant and that of respondents and for removal of the
obstruction. It was decreed by the Trial Court on March 30, 1964 which
was confirmed by the appellate Court on December 10, 1964. Thus, the
decree of mandatory injunction to remove the obstruction and perpetual B
injunction restraining the respondent from blocking the passage of the
appellants through the "QOADEMLP area" of the land shown in the decree
of the trial Court. When the appellants had filed an application for execution
under Order 21, Rule 32, CPC in Execution Case No. 2903/65, the
respondent had removed the obstruction and consequently, the execution
case was struck out on February 25, 1966 on the finding that the passage C
had been cleared and obstruction was removed. That was also upheld by
the appellate Court by dismissing CA No. 65166 on March 6, 1967.
It is now an admitted position that subsequently a shop was
constructed which is an obstruction to the passage in question and it had
completely blocked the passage. The appellant, therefore, filed again an D
execution application under Order XX!, Rule 32 in E.C.No. 42/1967. The
executing Court had directed, over-ruling the objections of the respondents,
to remove the obstruction completely and issued injunction not to. disobey
the mandatory injunction. It was issued by way of attachment of the property
and detention of the respondents in civil prison if only the obstruction is
not removed. On appeal, the Additional District Judge by his judgment E
dated March 10, 1969 confirmed the same. In the execution second appeal,
the learned Single Judge reversed the decree and remitted the matter on
the finding that under Section 22 of the Easement's Act, it is required to
be seen whether the obstruction has caused enjoyment of easementary
right. Since. that was not done, the courts below have committed error of
law in directing removal of the obstruction and also the attachment of the F
properties and direction to keep the respondents in civil prison.
The question is: whether the view taken by the High Court is correct
in law? One of the defences taken by the respondent was that he had sold
the property to third parties who had constructed the shop and thus it is G
not he who caused obstruction. That evidence was not accepted and it was
found that the respondent had constructed the shop in the disputed area.
Thereafter, it is recorded as a fact as under:
"The next question for decision in this appeal is whether the
disputed construction has blocked the passage. In support of H
540 SUPREME COURT REPORTS [l 996] SUPP. 8 S.C.R.
A his contention on this point the decree holder has examined
himself and has stated on oath that by disputed construction
the passage at QOAOEMLP shown in the decree has been
completely blocked. The statement of the decree holder is
corroborated by the report of the commission dated
13.5.1967. The report and map of the commission filed in
B the execution case show that the said passage has been
completely blocked by the disputed construction and the place
of dirty water of plaintiffs house has been stopped. The
judgment debtors Babu Lal Garg has also admitted in cross-
examination that by the disputed construction the said passage
has been completely blocked."
c
The appellate Court, thereafter, found that though the decree on the
earlier occasion was satisfied, since by his conduct he had constructed
shop obstruction the free flow of passage, an application for execution
under Order XX!, Rule 32, CPC could be laid to enforce the injunction
granted in the suit in respect of the aforesaid area.
D
It is contended that the High Court has proceeded on the premise
that the rights of parties are required to be adjudicated under Section 22 of
the Easement Act. The view of the High Court is clearly in error. It is seen
that once the decree of perpetual injunction and mandatory injunction has
E become final, the judgment-debtor is required to obey the decree. In
whatever form he obstructs, it is liable to removal for violation and the
natural consequence is the execution proceedings under Order XX!, Rule
32, CPC which reads as under:
"(3) Where any attachment under sub-rule (!) or sub-rule
F (2) has remained in force for six months if the judgment-
debtor has not obeyed the decree, if the decree-holder has
applied to have the attached property sold, such property
may be sold; out of the proceeds the Court may award to the
decree-holder such compensation as it thinks fit, and shall
pay the balance, if any, to the judgment-debtor on his
G
application. Where the judgment -debtor has obeyed the
decree and paid all costs of executing the same which he is
bound to pay, or where, at the end of six months from the
date of the attachment, no application to have the property
sold has been made, or if made has been refused, the
H attachment shall cease."
JAi DAYAL v. KL GARG 541
In this case, since the attachment was made for enforcement of the A
perpetual injunction and mandatory injunction, the decree is required to
be complied with. In case he did not obey the injunction under Clause (1)
of Order 32, the judgment-debtor is liable to detention in the civil prison
and also to proceed against the property under attachment.
The question of Section 22 of Easement Act would arise only if the B
question arises for the first time. However having allowed the perpetual
injunction and mandatory injunction granted by the trial Court to become
final, it would be no defence for the respondent to plead that he has not
obstructed the passage etc. or that, as found by the High Court, a part of
the property in which the present shop was constructed was not part of the
property in the original suit. In other words, if a judgment-debtor has C
suffered the decree, no attempt to circumvent the perpetual injunction and
mandatory injunction, can be permitted. If the decree-holder makes any
construction clubbing the other adjacent property, property which is part
of the subject matter in the earlier suit, a party cannot and should not, by
his action, be permitted to drive tl:e decree for another round ofadjudication
-of the rights in the second suit to be settled afresh. In other words, giving D
such a liberty will amount to encouraging persons to take the law into
their own hands and drive the decree-holder to another suit. It can never
be facilitated to circumvent the Jaw and relegate the party for tardy process
of the civil action. What is needed is an opportunity to obey the injunction.
Non~compliance is a continuing disobedience entailing penal consequences.
A separate fresh suit is barred under Section 49 of the CPC. Under these E
circumstances, the view of the High Court is clearly in error and appeal is
accordingly allowed. The judgment and order of the High Court stand set
aside and that of the trial Court and the appellate Court stand restored. No
costs.
F
R.P. Appeal Allowed.
Search Indian case law
Ask in plain English, not just keywords. 25,000 AI words free, no card.