Created byFuzzy Cloud

Supreme Court of India

KISHORSINH RATANSINH JADEJAversusMARUTI CORP. & ORS.

Citation
2009 INSC 457
Decided
6 April 2009
Disposal
Disposed off

Holding

The Supreme Court held that the High Court's interim orders restraining alienation and construction were invalid as they failed to satisfy the mandatory principles for injunctions, and the earlier order based on Section 52 of the Transfer of Property Act should stand.

Summary

The appellants, owners of agricultural land, entered into an agreement in 1980 for a cooperative housing project that later failed, leading the respondent Maruti Corp. to sue for specific performance in 1999. While the Gujarat High Court admitted the appeal and initially ordered that any dealing with the property would be subject to the appeal's outcome, it later issued two interim injunctions on 22 April 2008 and 7 May 2008 restraining alienation of the land and prohibiting construction, despite 280 plots having already been sold and construction commenced. The Supreme Court examined whether the High Court had applied the three mandatory principles for granting injunctions under Order XXXIX Rules 1‑2 CPC, considered the effect of Section 52 of the Transfer of Property Act (lis pendens), the conduct of the parties, and the rights of third‑party transferees. It held that the later injunctions were unsustainable because the High Court failed to assess prima facie case, balance of convenience, irreparable loss, and the parties’ conduct, and that the earlier order based on lis pendens should remain. Consequently, the Court set aside the 22 April and 7 May orders and upheld the 29 February order, disposing of the appeals in favour of the appellants.

Issues considered

  • The appropriateness of granting interim injunctions under Order XXXIX Rules 1‑2 CPC without applying the required principles of prima facie case, balance of convenience, and irreparable loss.
  • Whether Section 52 of the Transfer of Property Act (lis pendens) bars alienation of the disputed land during pendency of the appeal.
  • The impact of the respondent's 19‑year delay in instituting suit on its entitlement to injunctive relief.
  • The validity of an injunction affecting third‑party transferees who were not parties to the proceedings.

Legislation cited

Subjects

interim injunctionlis pendensspecific performancethird‑party rightsbalance of convenienceirreparable lossequityTransfer of Property ActCivil Procedure Code

Judgment

                            (2009] 5 S.C.R. 527


                   KISHORSINH RATANSINH JADEJA                             A
                                      v.
                         MARUTI CORP. & ORS.
                 (Civil Appeal Nos. 2186-2187 of 2009)

 !                            APRIL 6, 2009
                                                                           B
            [ALTAMAS KABIR AND CYRIAC JOSEPH, JJ.]

           CODE OF CIVIL PROCEDURE, 1908:

            Or.39 rr 1 and 2 - Interim injunction - Grant of -             c
       Principles to be considered - High Court in an appeal arising
       out of a suit for specific performance of contract directing that
       any alienation of property would be subject to decision of
       appeal - By subsequent interim orders staying sale of plots
;.
       and restraining the purchasers from raising any construction        D
       on the suit land - Held: The earlier order having been passed
     . on principle of /is pendens, as enshrined in s.52 of Transfer
       of Property Act, and transferees having obtained plots when
       there was no injunction against owners, the subsequent orders
       are not sustainable - The subsequent cryptic orders were
                                                                           E
       passed in great haste without giving the owners an opportunity
       of hearing and without giving any reason for passing the same
       - Orders were passed ignoring the basic principles required
       to be considered while passing an order under Or.39 rr. 1 and
I      2 - Besides, High Court did not take into consideration that
       the suit was filed after a long silence of 19 years - The           F
       subsequent interim orders in question passed by High Court
       set aside - High Court would decide the appeal expeditiously
       - Transfer of Property Act, 1882 - s.52 - Equity.

           In the instant appeals, it was contended for the G
      appellant and other joint owners of the suit land, as also
'     for the transferees that in the first appeal, the High Court-
      having passed an interim order dated 29.2.2008 to the
      effect that if the properties in question were dealt with in
                                     527                                   H
    528        SUPREME COURT REPORTS            [2009] 5 S.C.R.


A any way, the same would be subject to the decision in
  the appeal, there was no bar to alienation of the property;
  that in the circumstances, 280 plots were sold and the
  purchasers started constructions on their respective
  plots; that the High Court, therefore, erred in passing the
B subsequent orders, namely, order dated 22.4.2008 and
  7.5.2008 and restraining the owners from selling the land
  as also stalling the constructions, without giving an
  opportunity of hearing.

          Disposing of the appeals, the Court
c
       HELD:1.1. It is well established, that while passing an
  interim order of injunction under Or. 39 rr. 1 and 2 CPC,
  the Court is required to consider three basic principles,
  namely, (i) prima facie case; (ii) balance of convenience
D and inconvenience; and (iii) irreparable loss and injury.
  None of these principles have been considered by the
  High Court while passing the second and third interim
  orders dated 22nd April, 2008 and 7th May, 2008, nor has
  the High Court taken into account the long silence on the
E part of respondent No.1-Corporation in filing a suit after
  19 years. [Para 22] [541-B-E]

       1.2. Having passed an order on 29th February, 2008,
  based on the principle of lis pendens as enshrined in s.52
  of the Transfer of Property Act, 1882, the Division Bench
F of the High Court in its order dated 22nd April, 2008,
  observed that when the first appeal was admitted and the
  matterin dispute as regards the property in question was
  sub-judice, the properties in question should not be sold
  and passed an order which was contrary to the initial
G order dated 29.2.2008. [Para 21] [540-H; 541-A-B]

         1.3. Again the order dated 7th May, 2008, directing      '
    that no construction be raised on the lands in dispute,
    which has bearing on the 280 transferees who were in
                  KISHORSINH RATANSINH JADEJA v. MARUTI CORP. &          529
                                     ORS.

                 the process of raising their constructions having              A
       ~
       !
                 obtained the plots at a point of time when no injunction
       '         against land owners was in force, was passed in great
                 haste without even giving the owners of the lands an
                 opportunity of contesting the application. In fact, the
       .)        application was disposed of by a cryptic order which           B
                 does not even contain any reason for passing the same.
                 The order was passed without even taking into
                 consideration that the transferees would be adversely
                 affected by such an order. [Para 18 and 19] [540-B-F]

                     Manda/i Ranganna & others vs. T. Ramachandra (2008)
                                                                                c
                 11 sec 1, referred to.

                     1.4. While passing the interim order dated 7th May,
                 2008, the High Court ought to have considered the effect
           .,,   which its order would have on the 280 transferees to           D
                 whom some portions of the land had already been sold
                 and who had commenced construction thereupon,
                 particularly when they were not even parties in the
                 appeal, nor were they heard before they were injuncted
                 from continuing with the construction work. Such an            E
                 order affecting third party rights in their absence, as they
                 were not parties to the proceedings, cannot be sustained
                 having further regard to the manner in which the said
                 order was passed. [Para 23] [541-E-G]
           J
                                                                                F
                      2.1. As far as the lands which the appellant and the
"""              other joint owners have been restrained from alienating
                 by the second order dated 22nd April, 2008, are
                 concerned, in the event the order of 22nd April, 2008, is
  ·~
                 set aside, respondent No.1 can be compensated in terms
                 of money and no irreparable loss and injury will be            G
                 caused to it on account thereof. On the other hand, if the
                 owners of the property remain restrained from
                 developing the same, it is they, who will suffer severe
                 prejudice, as they will be deprived of the benefit of the
                                                                                H
    530       SUPREME COURT REPORTS             (2009] 5 S.C.R.


A user of their land during the said period. The balance of
  convenience and inconvenience is against grant of such               f'
  injunction. The success of the suit for specific                     '
  performance filed by respondent No.1 depends to a large
  extent on tenuous proof of genuineness of the agreement
B sought to be enforced after 19 years, despite the finding        i   •
  of the trial court that the suit was not barred by limitation.
  [Para 24) [542-C-F]

       2.2. The question of conduct of respondent No.1 also
  becomes relevant, inasmuch as, having slept over its
C rights for more than 19 years, it will be inequitable on its
  prayer to restrain the owners of the property from dealing
  with the same, having particular regard to the fact that a
  large portion of the land has already been conveyed to
  as many as 280 purchasers who are in the process of
D erecting constructions thereupon. [Para 25) (542-G-H;
  543-A]

         3. An application for an order which would have far
    and wide reaching consequences was sought to be
E   disposed of by the Division Bench on the very next day
    without giving an opportunity of controverting the
    allegations made therein even to those who were parties
    in the suit, though it had been brought to the notice of
    the Bench that conveyances had been executed in favour
F   of 280 purchasers. This is not a case where the appellant
    and the other co-owners had violated any restraint order
    passed by the High Court in transferring the plots in
    question to the said 280 transferees. The said transfers
    were effected at a point of time when there was no
G   injunction or restraint order against the appellant and the
    other owners of the property and as far as the said
    transfers are concerned, the only order that could have
    been passed on the said application is the order which
    was passed at the first instance on 29th January, 2008,
H   based on the principles of s.52 of the Transfer of Property
                        KISHORSINH RATANSINH JADEJA v. MARUTI CORP. & 531
                                           ORS.

                      Act, 1882. The restraint order on the transferees must,               A
     .,               therefore, be held to be bad and liable to be set aside .
     1                [Para 23) (541-G-H; 542-A-B]

                          4. The orders dated 22nd April, 2008 and 7th May,
                      2008, passed by the Division Bench of the High Court in
                  )                                                                         B
                      F.A.No.853 of 2008 and C.A. Nos.2405 and 5618 of 2008
                      are set aside and the initial order dated 29th February,
                      2008 is maintained. The High Court would dispose of the
                      appeals pending before it at an early date. [Para 27] (543-
                      B-C]
                                                                                            c
                                             Case Law Reference:

                           (2000) 11 sec 1             referred to            Para 12

                          CIVIL APPELLATE JURISDICTION : Civil Appeal No.
              t       2186-2187 of 2009.                                                    D

                          From the Judgment & Order dated 22.04.2008 of the High
                      Court of Gujarat at Ahemdabad in Civil Application No.181 of
                      1982.

                          Mukul Rohtgi, T. Mahipal, Kavin Gulati, Rashmi Singh,             E
                      Avnish Pandey and Vimal M. Patel for the Appellant.

                          Arun Jaitley, Soli J. Sorabjee, Ranjit Kumar, Huzefa
                      Ahmadi, Rajesh Dave, Ejaz Maqbool, Tauna Singh,
 '        j           Oardhuman Gohil, Manik Karanjawala, Ruby Singh Ahuja, M.R.            F
-r                    Shamshad, Mukesh Verma and Yash Pal Dhingra for the
                      Respondents.

                           The Judgment of the Court was delivered by

                           ALTAMAS KABIR, J. 1. Leave granted.                              G

                          2. The appellant and the Respondent Nos.2 to 7 are
                      owners of agricultural land in Survey No.36 measuring 32 acres
                      and 38 gunthas situated in Village Nanamauva, Taluka & District
                      Rajkot (hereinafter referred to as the 'suit land'). On 19th March,   H
    532        SUPREME COURT REPORTS                [2009] 5 S.C.R.


A 1980, the appellant and the other joint owners of the suit land
  entered into an Agreement with Tirupati Cooperative Housing           ,..
  Society - a proposed Cooperative Housing society - for
  development of the said land upon obtaining necessary
  permission under Section 20 of the Urban Land (Ceiling &
                                                                        '
B Regulation) Act, 1976 (hereinafter referred to as the 'Land
  Ceiling Act, 1976') for exemption and for construction of houses
  for the weaker sections. The application made by the proposed
  Society on 29th April, 1988, under Section 20 of the Land
  Ceiling Act, 1976, was rejected and according to the appellant
C and other joint owners, on the failure of the proposed Society
  to get such permission, the Agreement could not be performed
  and, therefore, by Public Notice dated 24th April, 1988, the
  Agreement was declared to have been cancelled.

        3. A legal notice was received from one Sharad N.
D Acharya, Advocate, denying that the Agreement had been
  cancelled, as indicated in the Public Notice. Despite
  cancellation of the Agreement, the Respondent No. 1 called
  upon the appellant to give effect to the Agreement dated 19th
  March, 1980, executed with the said respondent for
E development of the said land. The Respondent No.1 thereupon
  filed Special Civil Suit No.299 of 1999 on 29th November,
  1999, before the Civil Court at Rajkot against the appellant,
  inter a/ia, praying for a declaration that the Respondent No.1
  was in possession of the suit land and for a decree for specific
F performance of the said Agreement. In the alternative, for a
  decree for refund of the earnest money of Rs.1,81,000/- and
  for damages amounting to Rs.16,30,670/-with interest@12%
  per annum. The Respondent No.1 also filed an application for
  interim injunction to restrain the appellant from entering into the
G said land and disturbing the possession of the Respondent
  No.1 and to further restrain the appellant from alienating the
  land to any third party. The Civil Court at Rajkot dismissed the
  said application by its order dated 29th April, 2002, against
  which the Respondent No.1 filed appeal from Order No.372/
H
        }
             KISHORSINH RATANSINH JADEJA v. MARUTI CORP. & 533
                        ORS. [ALTAMAS KABIR, J.]

    .       2000 before the Gujarat High Court, which was ultimately            A
            withdrawn with a direction for expeditious disposal of the suit
    •       within a period of 10 months. The suit was thereafter taken up
            for trial by the Civil Court at Rajkot, and by judgment and order
            dated 23rd November, 2007, while rejecting the prayer for
            specific performance, the Trial Court directed refund of the        B
            earnest money.

                  4. The Respondent No.1, thereafter, filed an appeal on
            15th February, 2008, being First Appeal No.853/2008, along
            with an application, being Civil Application No.2405/2008, inter
            alia, to restrain the respondents therein from transferring or
                                                                                 c
            alienating the land in question to any third party till the disposal
            of the appeal. Since the appellant was on caveat before the
            High Court, after hearing the parties, the Division Bench of the
    {
            Gujarat High Court admitted the appeal but did not grant any
            stay, as prayed for, and only directed that if the property in D
            question was dealt with in any way, that would be subject to the
            decision of the appeal.

                  5. Although, the Respondent No.1 failed to obtain any
            order of injunction in the appeal, he issued a Public Notice        E
            through his learned Advocate on 7th March, 2008, asking the
            public not to deal with the property. In response thereto, the
            appellant also caused a Public Notice to be published on 10th
    J       March, 2008, clarifying that no injunction order had been
~           passed by the Gujarat High Court. The said fact was brought         F
            to the notice of the Gujarat High Court by the Respondent No.1
            by way of an additional affidavit on the basis whereof, the High
            Court passed an order on 22nd April, 2008, directing that the
            property in question should not be sold. Thereafter, on 6th May,
            2008, a further application for injunction No.5618/2008 was         G
            filed in the pending First appeal by the Respondent No.1 herein
            indicating that constructions were being raised on the land in
            question. On the basis of the above, the Division Bench of the
            Gujarat High Court, on 7th May, 2008, passed the following
            order impugned in these appeals :
                                                                                H
    534         SUPREME COURT REPORTS                  [2009] 5 S.C.R.


A         "By this application, learned counsel for the applicant           ,
          submits that inspite of the directions of this court issued
          vide orders dated 29.02.2008 and 22.04.2008, the
          constructions are being raised in the disputed land.
                                                                            '
          Learned counsel Mr. Pahwa, the respondent No.2 submits
B
          that the constructions were raised about 6 months back,
          and part of the property was already sold.

          To avoid further complications and multiplicity of litigations,
          we order that no construction be raised on the disputed
c         land. In spite of our direction, if further construction is
          raised, the applicant will be at liberty to approach the
          concerned police authority, and the concerned police
          authority is also directed to take immediate steps to stop
          the construction on the disputed land.
D
          Civil application stands disposed of."

          6. Appearing for the appellants, Mr. Mukul Rohtagi,
    submitted that the Respondent No.1, Maruti Corporation
    (plaintiff in the suit), came to be registered as a partnership firm
E   on 21st June, 1989, but has sought specific performance of an
    agreement alleged to have been entered into with the appellant
    on 19th March, 1980, executed on a Non-judicial stamp paper
    dated 17th March, 1990. Mr. Rohtagi urged that it was obvious
    that the claim of the Respondent No.1 in the plaint had no valid,
F   legal and/or factual foundation, on the basis of which the interim          r
    orders could have been passed by the High Court. He
    submitted that none of the three orders impugned in the appeal
    were speaking or reasoned orders. As the orders would
    themselves reveal, they were simply reactions to new facts
G   brought to the notice of the Court from time to time and orders
    were passed on the basis thereof without even giving the
    appellant herein or other interested parties a proper opportunity
    of meeting the allegations or questioning the same. Mr. Rohtagi
    submitted that the several interim orders passed by the Division
H   Bench were devoid of any reason and were liable to be set
                          KISHORSINH RATANSINH JADEJA v. MARUTI CORP. &                 535
                     f               ORS. [ALTAMAS KABIR, J.]


       -
       ...
                         aside.

                               7. Mr. Ranjit Kumar, learned senior counsel, who appeared
                         for the Respondent Nos.2 to 7, who were the joint owners of
                                                                                               A



                         the property with the appellant, while adopting Mr. Rohtagi's
                 ;       submissions, supplemented the same by contending that the
                                                                                               B
                         original agreement with Tirupati Cooperative Housing Society
                         stipulated that the said proposed Housing Society would have
                         to apply to the authorities of the Land Ceiling Act, 1976, under
                         Section 20 thereof, for exemption and leave to construct on the
                         vacant land. Learned counsel submitted that such application
                         had been made by Tirupati Cooperative Housing Society, but
                                                                                               c
                         the same was rejected and on such rejection, a public
                         announcement was made discontinuing the agreement
                         between the owners of the land and the proposed Tirupati
-- ..-       I           Cooperative Housing Society.
                                                                                               D
                               8. Mr. Ranjit Kumar urged that the owners of the property
                          had never entered into any agreement with Maruti Corporation-
    ,•                    Respondent No.1 herein, which filed a suit identical to that filed
                         by Tirupati Cooperative Housing Society, relying on the same
                         cheques by which Tirupati had advanced certain sums to the            E
                         owners of the property. Mr. Ranjit Kumar also urged that, in any
                         event, even if the case of the Respondent No.1 is accepted as
                         correct, for 19 years it had not applied for exemption to develop
             j
                         the land under Section 20 of the Land Ceiling Act, 1976, without
                         which it was not possible to develop the property. It is only after   F
~·                       the repeal of the Land Ceiling Act, 1976, on 19th March, 1999,
                         that the Respondent No.1 filed the aforesaid suit seeking
~
                         enforcement of an agreement alleged to have been entered into
....                     between the parties on 19th May, 1980, when exemption under
                         Section 20 of the said Act was no longer required.
                                                                                               G
             ~               9. Mr. Ranjit Kumar submitted that initially when the First
                         Appeal of the Respondent No.1 was admitted in the Gujarat
                         High Court, an order was also passed in Civil Application
                         No.2405 of 2008 to the effect that if the property in question
                         was dealt with in any way the same would be subject to the            H
    536        SUPREME COURT REPORTS               (2009] 5 S.C.R.
                                                                      •
A decision in the appeal. Learned counsel urged that since in its
                                                                          ._
  order the High Court had embodied the principles of Section
  52 of the Transfer of Property Act, 1882 and there was no bar
  to the alienation of the property, as many as 280 plots had been
  sold to different purchasers by way of registered sale deeds
                                                                          -
B and they had started construction on the plots which they had       '
  acquired presumably after obtaining necessary development
  permission sanctioned by the Rajkot Municipal Corporation. It
  was submitted that up to such point there could be no objection
  with regard to the orders passed in the First Appeal. Thereafter,
c when the interim order was modified on 22nd April, 2008, on
  the same application and the owners of the property were
  restrained from selling the same, the said modification, though
  not called for, was still capable of being defended.

        10. The real problem was created when on 7th May, 2008,
D on a fresh Civil Application for Injunction No.5618 of 2008 filed
  on 6th May, 2008, an order was passed by the Division Bench
  which not only had serious consequences for the transferees
                                                                      '   -
                                                                          ~




                                                                          ~
                                                                                  •




  but also for the owners of the land who were parties to the suit.           '
  The order which has been extracted hereinabove directed that
E no construction be raised on the disputed land and if any further
  construction was raised, the Respondent No.1 herein would be
  at liberty to approach the concerned police authorities who were
  directed to take immediate steps to stop the construction on
  the disputed land. Mr. Ranjit Kumar emphasised that the cryptic
F manner in which the said application was disposed of by such
  a mandatory order, was contrary to all legal principles and even
                                                                          .,.
                                                                          ;.-




  procedural law. He submitted that no liberty to deal with the
  fresh application filed on 16.5.2008 was even given by the
  Division Bench to the respondents in the appeal and on the very
G next  day on 7th May, 2008, without even giving any reasons for
  passing such an order, it disposed of the same finally to the
  severe prejudice of the appellant and the Respondent Nos. 2-
  7 herein and the 280 transferees to whom plots had been
  conveyed and that too when they were not parties to the appeal.
H
           KISHORSINH RATANSINH JADEJA v. MARUTI CORP. &                537
      t               ORS. [ALTAMAS KABIR, J.]
               11. It was also submitted that no thought was even given A
          to the principles embodied in Order XXXIX Rules 1 and 2 of
          the Code of Civil Procedure before such a drastic order of
          injunction was passed by the High Court in the First Appeal.
          Mr. Ranjit Kumar submitted that the basic principles for granting
                                                    1
          injunction involving the making out of a prima facie case, the B
          balance of convenience and inconvenience, and irreparable
          loss and injury, were not even taken into consideration when
          the orders of injunction were passed.

                12. In addition to the above, Mr. Ranjit Kumar also referred
          to the decision of this Court in Mandali Ranganna & others
                                                                               c
           vs. T. Ramachandra [(2008) 11 SCC 1] wherein an additional
          principle was sought to be enunciated relating to grant of
          injunction by way of an equitable relief. This Court held that in
           addition to the three basic principles, a Court while granting
    '<"
          injunction must also take into consideration the conduct of the      D
          parties. It was observed that a person who had kept quiet for
          a long time and allowed others to deal with the property
J
          exclusively would not oe entitled to an order of injunction. The
          Court should not interfere only because the property is a very
          valuable one. Grant or refusal of injunction has serious             E
          consequences depending upon the nature thereof and in
          dealing with such matters the Court must make all endeavours
          to protect the interest of the parties.

                13. Mr. Ranjit Kumar submitted that having filed the suit for F
          enforcement of its purported rights under the Agreement of 1980
          in the year 1999 and having allowed the owners of the property
          to deal with the same and certain rights having been created
          in favour of third parties when there was no restraint orders of
          the Courts, the High Court erred in granting such an interim G
          order with such drastic consequences without even giving the
          persons, who were to be adversely affected by the order, an
          opportunity of being heard.

              14. Opposing the submissions made on behalf of the
          appellant and the Respondent Nos.2 to 7, Mr. Soli J. Sorabjee,       H
    538        SUPREME COURT REPORTS                  (2009) 5 S.C.R.


A learned senior counset, submitted that it was necessary to clear
  the impression that had been given that the Respondent No.1-
  Maruti Corporation came into existence only on 21st June, 1989.
  He submitted that, on the other hand, the Respondent No.1 was
  in existence even in 1980, but as an unregistered partnership,
B and that it became a registered partnership on 21st June, 1989.
  Mr. Sorabjee submitted that the question of the existence of
  Maruti Corporation or the validity of the agreement executed
  between Maruti Corporation and the owners of the property
  would have to be considered on evidence and till a decision
c was arrived at in the matter, it was only appropriate that the
  status-quo of the property be maintained, particularly when a
  large number of transfers are alleged to have been made,
  which could make the relief sought for by the Respondent No.1
  a mere paper relief, if it ultimately succeeded.
D      15. Mr. Sorabjee also contended that when the application
  for a restraint order against construction was sought to be filed
  on 6th May, 2008, neither the appellant nor the other
  respondents had disclosed the fact that such transactions had
  already taken place and that the transferees had started raising
E their construction on the basis of such conveyances.
        16. Mr. Sorabjee took pains to point out that while in the
  suit all the issues had been decided against the plaintiff, the
  issue relating to limitation had, however, been decided in favour
F of the plaintiff and it was held that the suit for specific relief was
  not barred by limitation. Mr. Sorabjee submitted that since the
  injunction order was in force since 7th May, 2008 and more than
  10 months had passed since then, without disturbing the interim
  order of stay, the High Court could be requested to dispose of
  the First Appeal which is pending before it expeditiously.
G
       17. Mr. Huzefa Ahmadi, who appeared for the Respondent
  No.1 - Maruti Corporation in Special Leave Petition (Civil) No.          ,-
  12855 of 2008, while adopting Mr. Sorabjee's submissions,
  urged that the Tirupati Cooperative Housing Society had been
H created by Maruti Corporation with a definite object in mind.
        KISHORSINH RATANSINH JADEJA v. MARUTI CORP. &               539
• He submitted that the lands in question were agricultural in A
                   ORS. [AlTAMAS KABIR, J.]


        nature and could not, therefore, be acquired by any other body
        other than a cooperative society. It was on account of such bar
        that the Tirupati Cooperative Housing Society was proposed
        to be created on grounds of expediency and was yet to be
 .      registered. He also submitted that the payments made to the
        owners by Tirupati Cooperative Housing Society had been
                                                                           B

        made from the account of Maruti Corporation and consequently
       when exemption under Section 20 of the Land Ceiling Act,
        1976, was not granted to the proposed Cooperative Society,
       the Respondent No.1 filed a separate suit for specific              c
       performance of the agreement which had been entered into with
       the Maruti Corporation and the payments made by Tirupati
       Cooperative Housing Society were shown to be the payments
       which had been made by Maruti Corporation. Mr. Ahmadi also
       submitted that Maruti Corporation could not apply for exemption
.!>                                                                        D
       under Section 20 of the Land Ceiling Act, 1976, and as a
       consequence it filed the suit for specific performance only after
       the said Act was repealed, thereby doing away with the
       necessity of obtaining exemption under Section 20 thereof. Mr.
       Ahmadi also contended that unless the appellant and the other
                                                                           E
       joint owners of the property and their transferees were suitably
       restrained from dealing with the properties during the pendency
       of the two appeals before the first Appellate Court, the appeals
       would be rendered infructuous as it would become impossible
.,     once the constructions had come up, to revert back to the
       position when the plots were still undeveloped.                     F

            18. On a careful consideration of the submissions made
       on the behalf of the respective parties, the scenario which
       emerges is that while on the one hand the Respondent No.1 is
       strongly in favour of the status quo of the suit lands being        G
       maintained during the pendency of the suit for specific                 /



  ·V   performance filed by it, the appellant and the other joint owners
       have projected a case of both balance of convenience and
       inconvenience and irreparable loss on being restrained from
       developing their own property by the Respondent No.1,               H
    540        SUPREME COURT REPORTS                 [2009] 5 S.C.R.
                                                                             •
A purportedly on the basis of a spurious document. Mixed with
  the aforesaid issues is the issue of the 280 transferees to whom
  plots have been conveyed by the owners and who were
  enjoying the same by raising structures which were at different
  stages of construction. We are faced with a situation where
B inspite of having obtained the said plots at a point of time when          ~

  the injunction against the owners was not in force, the
  transferees, who were not even parties before the Court, have
  been restrained by an interim order of injunction of a mandatory
  nature which seriously affects them, but without giving them any
c opportunity of hearing.
          19. We have to consider the effect of the third order
   passed on 7th May, 2008, on Civil Application for Injunction
   No.5618 of 2008 filed of the previous day on 6th May, 2008,
  ordering that no construction be raised on the disputed lands
D on the 280 transferees who were in the process of raising their
  constructions. As will be apparent from the order itself, the
  same was passed in great haste without even giving the owners
  of the lands an opportunity of contesting the application. In fact,
  the application was disposed of by a cryptic order which does
E not even contain any reason for passing the same. The Division
  Bench has merely indicated that to avoid further complications
  and multiplicity of litigation, the order was being passed not to
  raise constructions on the disputed land, without even taking
  into consideration the several transferees who were to be
                                                                         ~
F adversely affected by such an order. Even the appellant herein
  and the Respondents No.2 to 7 were not given an opportunity
  of filing any affidavit to counter the statements and allegations
  made in the application for injunction.

G         20. It is quite obvious that the High Court was completely
    oblivious to the facts of the case and passed different orders
    at different times on the applications filed at regular intervals   -.
    by the Respondent No.1 Corporation.

       21. The reasoning provided in the interim order dated 22nd
H April, 2008, is, to say the least, legally untenable. Having
          l:<ISHORSINH RATANSINH JADEJA v. MARUTI CORP. & 541
                       ORS. [ALTAMAS KABIR, J.]
r
         passed an order earlier on 29th February, 2008, based on the      A
         principle of lis pendens, the Division Bench of the High Court
         in its second order dated 22nd April, 2008, observed that when
         the First Appeal was admitted and the matter in dispute as
         regards the property in question was sub-judice, the properties
         in question should not be sold and passed an order which was      8
"        contrary to the initial ordeYwhicn was made in keeping with
         Section 52 of the Transfer of Property Act.

             22. It is well established, that· while passing an interim
         order of injunction under Order XXXIX Rules 1 and 2 CPC, the
         Court is required to consider three basic principles, namely,
                                                                           c
               (i)     prima facie case;

               (ii)    balance of convenience and inconvenience; and
                                                                           D
~              (iii)   irreparable loss and injury.

             None of the said principles have been considered by the
         High Court while passing the second and third interim orders
         dated 22nd April, 2008 and 7th May, 2008, nor has the High
         Court taken into account the long silence on the part of the      E
         Respondent No.1 Corporation in filing a suit after 19 years.

              23. In our view, while passing the interim order dated 7th
         May, 2008, the High Court ought to have considered the effect
         which its order would have on the 280 transferees to whom         F
A'
         some portions of the land had already been sold and who had
         commenced construction thereupon, particularly when they were
         not even parties in the appeal, nor were they heard before they
         were injuncted from continuing with the construction work. Such
         an order affecting third party rights in their absence, as they
                                                                           G
         were not parties to the proceedings, cannot be sustained having
         further regard to the manner in which the said order was
    ;.   passed. An application for an order which would have far and
         wide reaching consequences was sought to be disposed of by
         the Division Bench on the very next day without giving an
         opportunity of controverting the allegations made therein even    H
     542         SUPREME COURT REPORTS              [2009] 5 S.C.R.

                                                                            '
A to those who were parties in the suit, though it had been brought
   to the notice of the Court that conveyances had been executed
   in favour of 280 purchasers. This is not a case where the
  appellant and the other co-owners had violated any restraint
  order passed by the Court in transferring the plots in question
B to the said 280 transferees. The said transfers were effected         •
  at a point of time when there was no injunction or restraint order
  against the appellant and the other owners of the property and
  as far as the said transfers are concerned, the only order that
  could have been passed on the said application is the order
c which was passed at the first instance on 29th January, 2008,
  based on the principles of Section 52 of the Transfer of Property
  Act, 1882. The restraint order on the transferees must,
  therefore, be held to be bad and liable to be set aside.

           24. As far as the lands which the appellant and the other
D joint owners have been restrained from alienating by the
   second order dated 22nd April, 2008, are concerned, we are
   of the view that in the event the order of 22nd April, 2008, is
   set aside, the Respondent No.1 can be compensated in terms
  of money and no irreparable loss and injury will be caused to it
E on account thereof. On the other hand, if the owners of the
  property remain restrained from developing the same, it is they,
  who will suffer severe prejudice, as they will be deprived of the
  benefit of the user of their land during the said period. The
  balance of convenience and inconvenience is against grant of
F such injunction. The success of the suit for specific performance    ~

  filed by the Respondent No.1 depends to a large extent on
  tenuous proof of genuineness of the agreement sought to be
  enforced after 19 years, despite the finding of the Trial Court
  that the suit was not barred by limitation.
G
         25. The question of conduct of the Respondent No.1 also
    becomes relevant, inasmuch as, having slept over its rights for
                                                                       .;
    more than 19 years, it will be inequitable on its prayer to
    restrain the owners of the property from dealing with the same,
    having particular regard to the fact that a large portion of the
H
          KISHORSINH RATANSINH JADEJA v. MARUTI CORP. & 543
                     ORS. [AlTAMAS KABIR, J.]

         land has already been conveyed to as many as 280 purchasers        A
         who are in the process of erecting constructions thereupon.

              26. We are, therefore, unable to sustain the interim orders
         passed by the Division Bench of the Gujarat High Court on 22nd
         April, 2008 and 7th May, 2008 in the appeals pending before        B
         it.

               27. We, accordingly, set aside the orders dated 22nd
         April, 2008 and 7th May, 2008, passed by the Division Bench
         of the Gujarat High Court in F:A.No.853 of 2008 and C.A.
         Nos.2405 and 5618 of 2008 and maintain the initial order           C
         dated 29th February, 2008. The appeals and the connected
         Interlocutory Applications are, accordingly, disposed of.

             28. The High Court is requested to dispose of the appeals
•   ,~   pending before it at an early date without being influenced by     o
         any observations made in this judgment.
                29. There will be no order as to costs.
         R.P.                                      Appeals disposed of.


Search Indian case law

Ask in plain English, not just keywords. 25,000 AI words free, no card.

Try "interim injunction"Sign in to search

For a digitally signed copy suitable for filing, refer to the court's own website. Only the court can issue one.