Created byFuzzy Cloud

Supreme Court of India

KUKREJA CONSTRUCTION COMPANY & OTHERSversusSTATE OF MAHARASHTRA & OTHERS

Citation
2024 INSC 692
Decided
13 September 2024

Holding

The Supreme Court held that the doctrine of delay and laches does not bar the grant of additional FSI/TDR, and the High Court’s dismissal on that ground is set aside.

Summary

The appellants, owners of land reserved for Development Plan Roads under the Maharashtra Regional and Town Planning Act, constructed the roads at their own cost, surrendered the land to the Mumbai Municipal Corporation and were granted 25% transferable development rights (TDR). They later claimed the balance 75% (or 100% in some cases) of additional FSI/TDR based on the Supreme Court’s decision in Godrej & Boyce I, but the Bombay High Court dismissed their writ petitions on the ground of delay and laches. The appellants appealed, and the Corporation also filed appeals against the High Court’s orders. The Supreme Court held that once compensation in the form of FSI/TDR is determined, it is a vested right enforceable irrespective of any delay, and the doctrines of delay, laches, abandonment or waiver do not apply. Consequently, the High Court’s dismissal on those grounds was set aside, the Corporation’s appeals were dismissed, and the respondents were directed to grant the balance FSI/TDR within three months, with a specific direction to consider the nature of amenities in the Kukreja case.

Issues considered

  • Whether the doctrine of delay and laches can be invoked to deny additional FSI/TDR under Section 126(1)(b) of the MRTP Act.
  • Whether the 2016 amendment to Regulation 34 of the Development Control Regulations applies retrospectively to cases where the amenity was developed before the amendment.
  • Whether the Mumbai Municipal Corporation’s appeals merit interference with the High Court’s order.
  • Whether entitlement to additional FSI/TDR is a vested right that must be honoured irrespective of the claimant’s delay.

Legislation cited

Subjects

Acquisition of land for public purposesDevelopment Plan RoadAmenityDelay and lachesFloor Space IndexTransferrable Development RightsCompensationArticle 300-AAbandonmentWaiverRetrospective legislation

Judgment

                 [2024] 9 S.C.R. 830 : 2024 INSC 692

             Kukreja Construction Company & Others
                                v.
                 State of Maharashtra & Others
                      (Civil Appeal No. 9702 of 2024)
                            13 September 2024
                     [B.V. Nagarathna* and
                Nongmeikapam Kotiswar Singh, JJ.]


                          Issue for Consideration
       Whether the High Court was right in declining to grant relief to
       the writ petitioners-appellants herein on the ground of delay and
       laches; whether the appeals filed by the respondent-Mumbai
       Municipal Corporation would call for any interference; what order
       to be passed.

                                 Headnotes†
       Maharashtra Regional and Town Planning Act, 1966 –
       s.126(1)(b) – Acquisition of land required for public purposes
       specified in plans – Development Control Regulations for
       Greater Bombay, 1991 – Regulations 33; 34 r/w Para 6 of
       Appendix-VII – Determination of compensation in form of Floor
       Space Index (FSI) and/or Transferrable Development Rights
       (TDR) – Claim for additional FSI/TDR against the development/
       construction of the amenity on the surrendered land at owner
       or lessee’s cost – Inapplicability of doctrine of delay and
       laches – Appellants-land owners held plots reserved in the
       sanctioned development plan for Development Plan Road
       (DP Road) – Appellants had constructed DP Road at their
       own cost and voluntarily surrendered the reserved lands to
       the respondent-Corporation, were granted 25% TDR for the
       construction of said amenity at their cost – Later, after the
       judgment of Supreme Court in Godrej & Boyce Manufacturing
       Company Limited v. State of Maharashtra reported as [2009]
       1 SCR 1016 (Godrej & Boyce I) holding that the owner or
       lessee would be entitled to FSI or TDR equivalent to 100%
       of the area of the road constructed by them, the appellants


* Author
[2024] 9 S.C.R.                                                            831

               Kukreja Construction Company & Others v.
                     State of Maharashtra & Others

     claimed additional FSI/TDR – Rejected by High Court on the
     ground of delay and laches – Correctness:
     Held: Not correct – Question of delay and laches would not
     arise in present cases – Once the compensation is determined
     in the form of FSI/TDR, the same is payable even without any
     representation or request being made, as otherwise there would
     be a breach of Article 300-A of the Constitution – Respondent did
     not establish that owing to a short delay even if it had occurred in
     any of these cases owing to uncertainty in law, it was prejudiced
     by the same or that third-party rights were created which could
     not be disturbed owing to delay or laches – Neither the doctrine
     of delay and laches nor the principle of abandonment of claim or
     waiver would apply in these cases – Rather, the delay occurred
     on the part of the Mumbai Municipal Corporation in complying
     with the Regulations insofar as the appellants are concerned –
     High Court not right in dismissing the writ petitions on the ground
     of delay and laches, impugned order set aside to that extent –
     However, reasoning of the High Court holding that the 2016
     notification amending Regulation 34 of the 1991 DCR would not
     apply retrospectively or retroactively to a land reserved under the
     development plan which is surrendered and amenity is developed
     on the said land by the owner or lessee thereof at his own cost
     prior to the amendment, not interfered on merits – Respondent to
     consider the case of writ petitioners-appellants herein in light of
     Godrej & Boyce I case and release the balance FSI/TDR to the
     appellants however, in the case of appellant – Kukreja Construction
     company and others, the respondent to consider the nature of
     the amenities constructed and thereafter consider their case for
     additional FSI/TDR. [Paras 4.8, 18, 20]

                              Case Law Cited
     Godrej & Boyce Manufacturing Company Limited v. State of
     Maharashtra [2009] 1 SCR 1016 : (2009) 5 SCC 24; Municipal
     Corporation of Greater Bombay v. Natwar Parikh & Co. Pvt. Ltd.,
     Civil Appeal No. 1748 of 2015; Noida Entrepreneur Association
     v. NOIDA [2011] 8 SCR 25 : (2011) 6 SCC 508; Sukh Dutt Ratra
     v. State of Himachal Pradesh [2022] 2 SCR 1041 : (2022) SCC
     OnLine SC 410; Lalaram v. Jaipur Development Authority [2015]
     14 SCR 403 : (2016) 11 SCC 31; Moon Mills Ltd. v. M.R. Meher,
832                                                            [2024] 9 S.C.R.

                       Digital Supreme Court Reports


       President, Industrial Court, Bombay, AIR 1967 SC 1450; M/s Dehri
       Rohtas Light Railway Company Limited v. District Board, Bhojpur,
       [1992] 2 SCR 155 : (1992) 2 SCC 598; Hindustan Petroleum
       Corporation Ltd. v. Dolly Das (1999) 4 SCC 450; Mohar Singh
       (Dead) Thr. Lrs. v. State of UP Collector [2023] 14 SCR 842 : 2023
       INSC 1019; Godrej & Boyce Manufacturing Co. Ltd. v. Municipal
       Corporation of Greater Mumbai [2023] 6 SCR 56 : (2023) SCC
       OnLine SC 592; A.P. SRTC v. S. Jayaram (2004) 13 SCC 792;
       Municipal Corporation of Greater Bombay v. Yeshwant Jagannath
       Vaity [2011] 5 SCR 653 (2011) 11 SCC 88; Vidya Devi v. State of
       Himachal Pradesh [2020] 1 SCR 749 : (2020) 2 SCC 569; Dehri
       Rohtas Light Rly. Co. Ltd. v. District Board, Bhojpur [1992] 2 SCR
       155 : (1992) 2 SCC 598; Tukaram Kana Joshi v. Maharashtra
       Industrial Development Corporation [2012] 13 SCR 29 : (2013) 1
       SCC 353; Kazi Moinuddin Kazi Bashiroddin v. Maharashtra Tourism
       Development Corporation [2022] 7 SCR 509 : (2022) SCC OnLine
       SC 1325; G.T. Lad v. Chemical and Fibres of India Ltd. [1979] 2
       SCR 613 : (1979) 1 SCC 590; State of Punjab v. Davinder Pal Singh
       Bhullar [2011] 15 SCR 540 : (2011) 14 SCC 770 – referred to.
       Natwar Parikh & Co. Pvt. Ltd. v. State of Maharashtra, 2014 SCC
       Online Bom 495 – referred to.

                                  List of Acts
       Maharashtra Regional and Town Planning Act, 1966; Development
       Control Regulations for Greater Bombay, 1991; Mumbai Municipal
       Corporation Act, 1888; Constitution of India.

                               List of Keywords
       Acquisition of land for public purposes; Sanctioned development
       plan; Development Plan Road (DP Road); Amenity; Delay and
       laches; Mumbai Municipal Corporation; Compensation; Floor Space
       Index (FSI); Transferrable Development Rights (TDR); Additional
       FSI/TDR; Development Rights Certificates; Surrendered plot/
       land; Development/construction of the amenity on surrendered
       land at owner or lessee’s cost; Article 300-A of the Constitution of
       India; Principle of abandonment of claim or waiver; Abandonment/
       waiver of rights; Retrospective; Retroactive; Construction of road;
       Surrender of land reserved for road; Development right; Planning
       Authority; Development Authority; Appropriate Authority; Free of
       cost; Free from all encumbrances.
[2024] 9 S.C.R.                                                           833

               Kukreja Construction Company & Others v.
                     State of Maharashtra & Others

                            Case Arising From
     CIVIL APPELLATE JURISDICTION: Civil Appeal No. 9702 of 2024
     From the Judgment and Order dated 18.12.2018 of the High Court
     of Judicature at Bombay in WP No.1898 of 2009
     With
     Civil Appeal Nos. 9703, 9704, 9705, 9706, 9707, 9708, 9709, 9710,
     9711, and 9712 of 2024

                         Appearances for Parties
     R. Venkataramani, AG, ANS Nadkarni, Pravin K. Samdani, Amar
     Dave, Shikhil Suri, Ms. Liz Mathew, Sr. Advs., Ms. Asha Gopalan
     Nair, Ms. Nivedita Nair, S.S. Rebello, Ms. Deepti Arya, Ms. Manisha
     Gupta, Rishikesh Haridas, Ms. Himanshi Nagpal, M/s. Pratap and
     Co., Ms. Pallavi Pratap, Sandip Patil, Raghav Gupta, Gaurav
     Gopal, Chiranjivi Sharma, Filji Frederick, Ms. Apoorva Kaushik,
     Vasu Gupta, Uday Mathur, Pranaya Goyal, Mahesh Agarwal,
     Rishi Agrawala, Ankur Saigal, Anshuman Srivastava, Divyanshu
     Srivastava, Kaustubh Singh, Ms. Vidisha Swarup, E. C. Agrawala,
     Ms. Madhu Suri, Ms. Jyoti Suri, Ms. Wamika Chadha, Ms. Vidhi
     Kapoor, Ms. Ishita Ahuja, Ms. Divya Swami, Aaditya Aniruddha
     Pande, Naresh Jain, Ms. Arati Agarwal, Ms. Neha, Alok Kumar,
     Rameshwar Prasad Goyal, Mukul Taly, Phiroze Merchant, Ms.
     Mamta Singh, Ms. Anchala C., Ms. Mallika Agarwal, Ms. Bagavathy
     Vennimalai, Navneet R., Rahul Chitnis, Siddharth Dharmadhikari,
     Bharat Bagla, Sourav Singh, Aditya Krishna, Ms. Preet S. Phanse,
     Adarsh Dubey, Advs. for the appearing parties.

                 Judgment / Order of the Supreme Court

                                Judgment

     Nagarathna, J.

     These appeals have been filed against three impugned judgments
     and orders of the High Court of Judicature at Bombay, namely,
     i)     Judgment dated 18.12.2018 whereby Writ Petition Nos.
            1898/2009, 1823/2012, 839/2015, 2871/2015, 2107/2016,
            2170/2016, 384/2017 and 541/2017 were rejected on the ground
834                                                          [2024] 9 S.C.R.

                        Digital Supreme Court Reports


              of delay and laches and the writ petitioners therein/appellants
              herein have filed an appeal. Writ Petition Nos. 203/2014 and
              2262/2010 were allowed and Writ Petition No.1860/2017 was
              partly allowed.
       As against Writ Petition No.203/2014, Municipal Corporation of Greater
       Mumbai (hereinafter referred as “Mumbai Municipal Corporation”) has
       filed Civil Appeal No.9708/2024 arising out of Special Leave Petition
       (Civil) No.13365/2019. However, as against orders in Writ Petition
       No.2262/2010 and 1860/2017, there are no Special Leave Petitions
       filed by the Mumbai Municipal Corporation;
       ii)    Judgment and Order dated 18.10.2019/08.11.2019 whereby Writ
              Petition No.2531/2009 was allowed and the Mumbai Municipal
              Corporation has filed Civil Appeal No.9711/2024 arising out of
              Special Leave Petition (Civil) No.10430 of 2020;
       iii)   Judgment dated 20.10.2022 whereby Writ Petition No.411/2013
              was allowed and the Mumbai Municipal Corporation has filed
              Civil Appeal No.9712/2024 arising out of Special Leave Petition
              (Civil) No.606 of 2023.
       1.1 Thus, there are sets of judgments and orders of the Bombay
           High Court which have been considered together owing to
           their similarity.
       1.2 The High Court considered the writ petitions on the issue
           concerning the implementation of the decision of this Court
           in Godrej & Boyce Manufacturing Company Limited
           vs. State of Maharashtra (2009) 5 SCC 24 (“Godrej &
           Boyce I”). The said decision dealt with Regulation 34 read with
           Para 6 of Appendix-VII to the Development Control Regulations
           for Greater Bombay, 1991 (“the DCR” for short).

       Relevant facts:
2.     With regard to the order dated 18.12.2018, the writ petitioners before
       the High Court (appellants herein) were holding plots of land shown
       as reserved in the sanctioned development plan under the provisions
       of the Maharashtra Regional and Town Planning Act, 1966 (“MRTP
       Act” for short) which were reserved for Development Plan Road (“DP
       Road” for short). According to the writ petitioners, they constructed
       DP Roads at their own cost and voluntarily surrendered the reserved
[2024] 9 S.C.R.                                                      835

               Kukreja Construction Company & Others v.
                     State of Maharashtra & Others

     lands to the Mumbai Municipal Corporation. In lieu thereof, in terms
     of clause (b) of sub-section (1) of Section 126 of the MRTP Act read
     with Regulations 33 and 34 as well as Para 5 of Appendix-VII of
     DCR, the writ petitioners were granted Floor Space Index (“FSI” for
     short) and/or Transferrable Development Rights (“TDR” for short)
     in the form of Development Rights Certificates (“DRC” for short)
     equal to the gross area of the plots surrendered by them. Para 6 of
     Appendix-VII (as it stood prior to its amendment) provided that when
     an owner or a lessee also develops or constructs the amenities on
     the surrendered plot at his own cost and hands over the developed/
     constructed amenity to the Municipal Commissioner, he is entitled to
     DRC in the form of FSI or TDR equivalent to the area of construction/
     development done by him. The expression “amenity” has been
     defined in sub-section (2) of Section 2 of the MRTP Act as well as
     clause (7) of Regulation 3 of DCR.
     2.1 For the purpose of implementation of the DCR, two Circulars
         were issued on 09.04.1996 and 05.04.2003. By Circular dated
         09.04.1996, the DRC equivalent to 15% area of the DP Road
         constructed by the owner or lessee on the surrendered plot
         was to be provided when the owner or lessee surrendered the
         developed amenity together with the reserved plot. By Circular
         dated 05.04.2003, the figure was enhanced to 25%.
     2.2 In Godrej & Boyce I, this Court held that the expression
         “equivalent” in Para 6 of Appendix-VII would entitle the owner or
         lessee to 100% FSI or TDR for the construction of an amenity at
         his cost. Therefore, FSI or TDR for construction of an amenity
         would not be confined to 15% or 25% of DP Road area and it
         would be equivalent to 100% of the area of the road constructed
         by the owner or the lessee.
     2.3 The grievance of the writ petitioners before the High Court was
         that the Mumbai Municipal Corporation had declined to grant
         100% additional TDR equivalent to the area of the amenity
         developed. By a notification issued on 16.11.2016, Regulation 34
         of the DCR was amended. As a result, Appendix-VII was virtually
         obliterated from the DCR. The notification dated 16.11.2016 was
         assailed and question arose as to whether the modifications
         made by the notification amending Regulation 34 of the DCR
         would have retrospective or retroactive operation.
836                                                        [2024] 9 S.C.R.

                      Digital Supreme Court Reports


       2.4 The High Court made a brief reference to the facts of each
           of the writ petitions and considered the detailed submissions
           made on behalf of the writ petitioners, the Mumbai Municipal
           Corporation and the State Government.

       Contentions before the High Court:
3.     It was contended on behalf of the writ petitioners before the High
       Court that the unamended Regulation 33(1) of the DCR enabled the
       owner of the land to seek benefit of FSI of the land reserved for DP
       Road and utilize the same on the remaining land. Till 17.06.2010,
       there was no entitlement to seek FSI under Regulation 33 for
       construction of an amenity and the amenity TDR was available
       only under Regulation 34 read with Para 6 of Appendix-VII. The
       amendment made on 17.06.2010 to Regulation 33 resulted in the
       owner, who had constructed the road, instead of TDR, to opt for
       FSI to be utilized on the remainder of the land. He would then be
       entitled to an extent of 25% of the FSI. But if the owner constructed
       an amenity but did not avail FSI benefit on the remainder land, the
       benefit was separated from the land and given in the form of TDR
       under Regulation 34 read with Para 6 of Appendix-VII. That Para 6
       of Appendix-VII was not amended as such on 17.06.2010 after the
       decision of this Court in Godrej & Boyce I as no amendment was
       carried out as such. However, by the notification dated 16.11.2016,
       the entire Regulation 34 and Appendix-VII were substituted. As per
       the amended provision, the owner was eligible to obtain TDR for the
       land at the rate mentioned in Para 4.1 of the amended Regulations
       as the owner who developed the amenity thereon became eligible
       to receive TDR in terms of Para 4.2 but by this, Regulation 33(1)
       did not undergo any amendment.
       3.1 It was contended that the aforesaid amendment should be
           construed to be prospective as otherwise it would apply to
           cases where amenity was developed and surrendered earlier,
           and hence would be unconstitutional. It was pointed out
           that subsequent to the judgment of this Court in Godrej &
           Boyce I, in the case of Municipal Corporation of Greater
           Bombay vs. Natwar Parikh & Co. Pvt. Ltd., Civil Appeal
           No.1748 of 2015 (“Natwar Parikh”) this Court had rejected
           the prayer of the Mumbai Municipal Corporation to revisit the
           decision in the case of Godrej & Boyce I and had also rejected
[2024] 9 S.C.R.                                                       837

               Kukreja Construction Company & Others v.
                     State of Maharashtra & Others

           the prayer for declaring that the said judgment would have
           only a prospective effect. In the said case, this Court had also
           rejected an argument of delay and laches.
     3.2 It was further contended that the notification dated 16.11.2016
         could not have a retrospective effect as the decision of this
         Court in Godrej & Boyce I could not have been nullified by
         taking away the vested right conferred, without altering the
         basis of the judgment.
     3.3 It was next contended that clause (b) of sub-section (1) of
         Section 126 of the MRTP Act, which was incorporated into
         the statute book with retrospective effect from 25.03.1991,
         would imply that prior to the said date, there was no provision
         for FSI/TDR for construction of a road by the owner. That
         for the first time w.e.f. 17.06.2010, provision was made for
         an additional 25% FSI for construction of DP Road. Since a
         road falls within the definition of amenity under the DCR as
         well as MRTP Act, compensation in the form of FSI/TDR for
         the construction of an amenity as provided by the relevant
         DCR ought to have been granted to the petitioners. This was
         having regard to Regulation 34 read with Appendix-VII which
         is a complete code for grant of TDR. It was submitted that the
         scheme of an additional 100% TDR on account of construction
         of an amenity was in lieu of payment of compensation in an
         acquisition proceeding.
     3.4 The contention of the Mumbai Municipal Corporation, on the other
         hand, was that the decision of this Court in Godrej & Boyce I,
         was per incuriam as it ignored the effects of Regulation 33 of the
         DCR. It was contended that if the compensation had been paid
         partly or fully by any means, TDR could not be granted. That in
         the case of the writ petitioners, the compensation in the form
         of 10% or 25% additional TDR had already been granted and
         the notification dated 16.11.2016 had removed the basis of the
         decision of this Court in Godrej & Boyce I and there was now
         a prohibition for issuance of TDR in favour of the persons who
         had already been compensated. They further contended that
         the impugned notification would apply even to cases pending
         before the High Court and the Mumbai Municipal Corporation
         as the judgment in Godrej & Boyce I had been nullified by the
838                                                         [2024] 9 S.C.R.

                      Digital Supreme Court Reports


            said notification. Further, there cannot be 100% TDR in respect
            of the area of the amenity developed, and therefore, to cure
            the defect, the notification dated 16.11.2016 was enforced and
            that the DCR applicable on the date of deciding an application
            for grant of development permission would govern the decision
            on the application.
       3.5 By way of reply, the writ petitioners contended before the High
           Court that the notification dated 16.11.2016 was not a validating
           Act. It was merely a delegated legislation which could not nullify
           the judgment of the Apex Court. The right to claim TDR on the
           development of the amenity vests in the owner the moment the
           permission is granted by the Municipal Corporation to construct
           the road/amenity. The judgment in Godrej & Boyce I is not per
           incuriam and had been applied in other subsequent cases. The
           object of giving a benefit under Regulation 34 is owing to lack
           of financial capacity of the Municipal Corporation to construct
           amenities by itself. Hence, the writ petitioners sought relief
           under Regulation 34 of the DCR.

       Consideration by the High Court:
4.     On a consideration of the rival submissions and taking note of
       the fact that the contention of the Mumbai Municipal Corporation
       was that the decision of this Court in Godrej & Boyce I was per
       incuriam, the High Court considered the provisions of the Act and
       the Regulations in extenso. The High Court noted that in almost all
       the cases the action of surrendering the land and developing the
       amenities had been completed by 17.06.2010 when Regulation 33
       underwent an amendment. Therefore, on a consideration of the
       erstwhile Regulation 33, the High Court observed that the same
       was applicable to a case where the owner, including a lessee,
       had surrendered the land or area required for road widening or
       for construction of a new road proposed under the development
       plan or those proposed under the Mumbai Municipal Corporation
       Act, 1888 (“the Act of 1888” for short). Thus, it would apply to the
       lands reserved in the development plan for construction of new roads
       or for road widening and also to the lands which were within the
       road-line as fixed under the Act of 1888 on which a road had not yet
       been constructed. The said provision was not applicable to any other
       amenity. It was further observed that a part of FSI could be used on
[2024] 9 S.C.R.                                                      839

               Kukreja Construction Company & Others v.
                     State of Maharashtra & Others

     the plot remaining after such surrender and the balance FSI was to
     be permitted to be utilised as TDR by issuing DRC. Such TDR was
     to be governed by Regulation 34 as that is the provision for grant of
     TDR. Thereafter, the road and land would stand transferred in the
     city survey record in the name of the Mumbai Municipal Corporation
     and vest in the Corporation.
     4.1 Reference was then made to Regulation 34 and Appendix-VII,
         which deals with TDR. The concept of TDR is that FSI available
         in respect of one plot of land could be permitted to be utilised
         on another plot of land. Para 6 of Appendix-VII dealt with a case
         where the owner or lessee developed or constructed the amenity
         on the surrendered land. In such a case, it was relatable to
         clause (b) of sub-section (1) of Section 126 of the MRTP Act. The
         said Act defines “amenity” under sub-section (2) of Section 2 of
         the MRTP Act, as also in clause (7) of Regulation 3 of the DCR.
         The High Court observed that Regulation 33(1) gave effect to
         clause (b) of sub-section (1) of Section 126 of the MRTP Act.
         That Para 5 of Appendix-VII pertains to the extent of TDR to
         be granted against the surrender of a reserved land. Para 5 of
         Appendix-VII is significant inasmuch as it deals with a case
         where the owner or lessee develops or constructs an amenity on
         the surrendered plot at his own cost subject to such stipulation
         as may be prescribed by the Municipal Commissioner. That the
         expression ‘amenity’ would include a road and the construction
         or development of the road would have to be at the cost of
         the owner. In such an event, under Para 6 of Appendix-VII,
         the grant of additional FSI in the form DRC is equivalent to the
         area of construction/development done by the owner as per
         the stipulations prescribed by the Commissioner. This is like a
         compensation granted for construction of an amenity as provided
         in clause (b) of sub-section (1) of Section 126 of the Act.
     4.2 The High Court again considered the argument of the Mumbai
         Municipal Corporation made before this Court to the effect
         that the value of the amenity developed or constructed by
         the owner for which an additional TDR was sought must be
         commensurate to the value of the amenity and not the area of
         the amenity, which argument had been repelled by this Court
         in Godrej & Boyce I. Thus, the High Court on considering the
         judgment of this Court in Godrej & Boyce I observed that the
840                                                          [2024] 9 S.C.R.

                       Digital Supreme Court Reports


            additional TDR was required to be granted as per DCR and
            in particular Para 6 of Appendix-VII equivalent to the area
            constructed or developed and not on the basis of the value of
            the development of the amenity. Hence, the High Court observed
            that when a land which is reserved in the development plan
            under the MRTP Act for a public purpose is surrendered by
            the owner or lessee free of cost and the amenity is developed
            thereon, on its surrender, the owner or lessee will be entitled
            to FSI/TDR equivalent to the area of the surrendered land
            and an additional TDR equivalent to the area of the amenity
            developed or constructed by him.
       4.3 While considering the arguments on behalf of the Mumbai
           Municipal Corporation with regard to Regulation 33, the High
           Court observed that the said Regulation provided that only a
           part of the land FSI can be used on the remaining portion of
           the land and the balance FSI had to be provided in the form
           of TDR, as per Appendix-VII. That Appendix-VII read with
           Regulation 34 dealt only with grant of TDR and the conditions
           on which TDR can be granted. Even the TDR available in terms
           of the Regulation 33(1) will be governed by Regulation 34
           read with Appendix-VII. This is particularly so, as per Para 5
           of Appendix-VII which applied to the grant of TDR in respect of
           land covered by Regulation 33(1). That Para 6 of Appendix-VII
           dealt with both situations, i.e., where the entire land held by the
           owner or lessee was reserved or a part thereof was reserved
           and the land was surrendered to the Corporation. Para 6 also
           dealt with grant of an additional TDR for construction of an
           amenity in terms of clause (b) of sub-section (1) of Section 126
           of the MRTP Act. Regulation 33(1) dealt with FSI or TDR in
           lieu of surrender of land required for roads whereas Para 6 of
           Appendix-VII dealt with the grant of FSI or TDR in respect of the
           road developed at the cost of the owner or the lessee. That this
           Court in Godrej & Boyce I had considered Regulation 33 also.
       4.4 Considering Regulation 33 which had undergone an amendment
           on 17.06.2010, the High Court observed that prior to the
           amendment, the said Regulation did not deal with FSI or TDR
           in lieu of the construction of road. It dealt with only FSI or TDR
           against the surrender of land reserved for road. However, after
           amendment, when a road constructed as per the stipulation of
[2024] 9 S.C.R.                                                         841

               Kukreja Construction Company & Others v.
                     State of Maharashtra & Others

           the Commissioner was handed over to the Commissioner free of
           cost, an initial FSI equivalent to 25% of the area of construction
           of road can be granted. A part of the FSI can be consumed
           on the remaining land and the remaining part of the FSI will
           be provided in the form of TDR. Therefore, the amendment to
           Regulation 33(1) was applicable to reservation of road and not
           for any other amenity. It was also clarified that the amendment
           will not apply where the FSI granted in lieu of road had been
           utilized and full occupation certificate had been granted prior
           to 17.06.2010. Therefore, after 17.06.2010, in case of a land
           reserved for road or road widening which was surrendered, if
           the amenity being a road had been constructed by the owner
           on the land surrendered, the additional FSI as provided in
           clause (b) of sub-section (1) of Section 126 of the MRTP Act will
           be 25% of the area of the construction of road. Hence, Para 6
           of Appendix-VII to Regulation 34 would apply and the owner or
           the lessee will not get TDR equivalent to entire area of the road
           constructed by him but it will be confined to 25% of the area.
     4.5 It was clarified that pursuant to notification dated 16.11.2016,
         Para 4.2 of the Schedule to the notification would be the only
         clause applicable to the grant of TDR against construction
         of amenity and that from 16.11.2016, Para 6 of Appendix-VII
         would not apply to the lands with amenity surrendered after
         that date. In other words, Regulation 34 stands substituted by
         the Schedule to the said notification. It was further observed
         by the High Court that the said notification dated 16.11.2016
         did not have a retrospective operation and it also did not take
         away the basis of the decision in Godrej & Boyce I.
     4.6 It was further clarified by the High Court that in the case of
         Natwar Parikh & Co. Pvt. Ltd. vs. State of Maharashtra,
         2014 SCC Online Bom 495 (“Natwar Parikh & Co. Pvt.
         Ltd.”), 25% TDR was granted to the petitioner therein in the
         year 2006-2007. Subsequent to the decision of this Court in
         Godrej & Boyce I, the petitioner therein had filed a petition. On
         the facts of the case in Natwar Parikh & Co. Pvt. Ltd., it was
         observed that there was no delay or laches. The said decision
         of the High Court was sustained by this Court in Civil Appeal
         No.1748 of 2015. This Court had also rejected the argument that
         the judgment in Godrej & Boyce I should apply prospectively.
842                                                            [2024] 9 S.C.R.

                        Digital Supreme Court Reports


       4.7 Finally, it was held that additional FSI or TDR in terms of Para 6
           of Appendix-VII as well as in terms of clause (1) of Regulation 33
           becomes available on surrender of the land reserved with
           or without amenity, as the case may be. After 17.06.2010, if
           there is surrender of land reserved for road or road widening
           on which road is constructed by the owner or lessee, the FSI
           or TDR will be available in respect of amenity of road as per
           Regulation 33(1) as amended. Therefore, the right to get FSI
           or TDR accrues at the time of surrender.
       4.8 Thereafter, the High Court went into the facts of each of the writ
           petitions. Accordingly, the High Court passed the following order:
            i)     We hold that the notification dated 16th November 2016 is
                   legal and valid. However, the said notification will not have
                   retrospective or retroactive application to a land reserved
                   under the development plan which is surrendered and
                   amenity is developed on the said land by the owner or
                   lessee thereof at his own cost prior to 16th November 2016.
                   Such cases will be governed by the Regulation 33(1) and
                   clauses (5) and 6 of Appendix VII. In case of a land reserved
                   for a road, either in development plan under the MRTP
                   Act or under the provisions of the said Act of 1888 and
                   surrender is made and road is developed on or after 17th
                   June 2010 but before 16th November 2016, the FSI or TDR
                   in lieu of amenity will be governed by the Regulation 33(1)
                   as amended on 17th June 2010.
            ii)    We reject the argument that the decision of the Apex Court
                   in the case of Godrej & Boyce Manufacturing Company
                   Limited (supra) is per incuriam.
            iii)   We hold that whether the writ jurisdiction of this Court
                   under Article 226 of the Constitution of India can be allowed
                   to be invoked on the basis of the said decision or not
                   depends upon the facts of each case and the conduct of
                   the petitioners especially the delay and laches on their part;
            iv)    Writ Petition No.203 of 2014 is allowed. We direct the
                   third respondent-MMRDA to make recommendation
                   to the Mumbai Municipal Corporation for grant of 75%
                   additional FSI/TDR in terms of the aforesaid decision
                   of the Apex Court within a period of two months from
[2024] 9 S.C.R.                                                           843

                  Kukreja Construction Company & Others v.
                        State of Maharashtra & Others

                   today. The Municipal Corporation shall examine the said
                   recommendation and if the petitioners are otherwise entitled
                   to TDR for amenity in terms of the aforesaid decision of the
                   Apex Court, necessary DRC shall be issued within a period
                   of two months from the date on which recommendation
                   of MMRDA is received.
           v)      Writ Petition No.1898 of 2009 is rejected;
           vi)     In Writ Petition No.2262 of 2010, the petitioners will be
                   entitled to additional 100% amenity FSI in terms of the
                   aforesaid decision of the Apex Court provided by producing
                   the documents, they satisfy the Mumbai Municipal
                   Corporation that work was actually carried out by them
                   for developing the recreation grounds and the ground;
           vii)    Writ Petition No.1823 of 2012 is rejected.
           viii) Writ Petition No.839 of 2015 is rejected.
           ix)     Writ Petition No.2871 of 2015 is rejected.
           x)      Writ Petition No.2107 of 2016 is rejected.
           xi)     Writ Petition No.2170 of 2016 is rejected.
           xii)    Writ Petition No.384 of 2017 is rejected.
           xiii) Writ Petition No.541 of 2017 is rejected.
           xiv) Writ Petition No.1860 of 2017 is partly allowed. We direct
                the Mumbai Municipal Corporation to grant additional FSI in
                respect of amenity of road as provided by Regulation 33(1)
                as amended with effect from 17th June 2010.
           xv) We make it clear that wherever we have held that the
               petitioners are entitled to 100% amenity TDR in accordance
               with clause 6 of Appendix VII in terms of the aforesaid
               decision of the Apex Court, the Mumbai Municipal
               Corporation will have to examine whether the petitioners
               are otherwise eligible for grant of TDR.”
     4.9 Out of all the writ petitions disposed of, Writ Petition No.203
         of 2014 was allowed and a direction was issued to the MMRDA
         to make recommendations to Mumbai Municipal Corporation for
         grant of 75% additional FSI/TDR in terms of the decision of this
         Court in Godrej & Boyce I within two months from the said date
844                                                           [2024] 9 S.C.R.

                       Digital Supreme Court Reports


            of disposal. A further direction was issued to Mumbai Municipal
            Corporation to consider the said recommendation and to pass
            orders for issuance of DRC within a period of two months from
            the date on which recommendation of MMRDA was received,
            provided the writ petitioner was otherwise entitled to TDR for
            amenity in terms of the judgment of this Court in Godrej & Boyce I.
       4.10 Similarly, in Writ Petition No.2262 of 2010, additional FSI to
            the extent of 100% on amenity was granted in terms of the
            decision of this Court in Godrej & Boyce I provided the writ
            petitioner therein produced the documents and satisfied the
            Mumbai Municipal Corporation that work was actually carried
            out for developing the recreation grounds and ground.
       4.11 Writ Petition No.1860 of 2017 was partly allowed to the effect
            that Mumbai Municipal Corporation ought to grant additional FSI
            in respect of amenity of road as provided by Regulation 33(1)
            as amended with effect from 17.06.2010. It was also observed
            that the petitioners therein are entitled to 100% amenity TDR
            in accordance with Para 6 of Appendix-VII in terms of the
            aforesaid decision of this Court in Godrej & Boyce I and Mumbai
            Municipal Corporation was to examine whether the petitioners
            therein were otherwise eligible for grant of TDR.
       4.12 With regard to those cases which were dismissed on the ground
            of delay and laches, appeals have been filed by the private
            petitioners therein. Appeal has been filed by Mumbai Municipal
            Corporation against the order in writ petition No.203 of 2014
            but no appeal has been filed against the order in Writ Petition
            Nos.2262/2010 and 1860/2017.
       There are two more impugned judgments in Writ Petition Nos.
       2531/2009 and 411/2013 against which the Mumbai Municipal
       Corporation has filed its appeals.
       4.13 At this stage, it may be mentioned that where the writ petitions
            were dismissed by the High Court on the ground of delay and
            laches, there is no observation in those writ petitions denying
            the benefit on merits. Insofar as in three cases where the writ
            petitions were allowed, there is only one appeal filed by the
            Mumbai Municipal Corporation as the orders in Writ Petition
            No.2262 of 2010 and Writ Petition No.1860/2017 have been
            accepted by it.
[2024] 9 S.C.R.                                                    845

                  Kukreja Construction Company & Others v.
                        State of Maharashtra & Others

     4.14 The details of the three cases in which appeals have been
          filed by the Mumbai Municipal Corporation are noted as under:-
           (i)     WP No.2531 of 2009 – Starwing Developers Private
                   Limited vs. Municipal Corporation of Greater Mumbai -
                   disposed of on 18.10.2019
           (ii)    WP No.203 of 2014 – Apurva Natvar Parikh and Co.
                   Private Ltd. vs. State of Maharashtra and Others -
                   disposed of on 18.12.2018
           (iii) WP No.411 of 2013 – Arvind Kashinath Dadarkar and
                 Others vs. Municipal Corporation of Greater Mumbai
                 and Others – disposed of on 20.10.2022.

     Starwing Developers Private Limited:
5.   In Starwing Developers Private Limited vs. State of Maharashtra
     (“Starwing Developers Private Limited”), Writ Petition No.2531
     of 2009 disposed by the High Court on 18.10.2019, unamended
     Regulation 33 and Regulation 34 as they stood prior to 2010 were
     considered in depth. It was observed that Regulation 34 as it
     stood at the relevant time provided that in certain circumstances,
     the development potential of a plot of land could be separated
     from the land itself and could be made available to the owner
     of the land in the form of TDR which would be subjected to
     Regulation 34 and Appendix-VII. It was observed that Appendix-VII
     titled “Regulations for the grant of Transferable Development
     Rights (TDRs) to owners/developers and conditions for grant of
     such rights” had a scheme for the award of TDR to the owner of
     the plot of land which was reserved for public purpose and for
     additional amenities in the form of FSI. As per the conditions set
     out therein, such award would entitle the owner of the land to
     FSI in the form of DRC which he could use for himself or transfer
     to any other person. Para 5 of the Appendix provided that the
     built- up area for the purposes of FSI credited in the form of
     DRC shall be equal to the gross area of the reserved plot to be
     surrendered and will proportionately increase or decrease according
     to the permissible FSI of the zone where the TDR has originated.
     Para 6 provided that when an owner or a lessee also developed
     or constructed an amenity on the surrendered plot at his own cost,
     subject to such stipulations which may be prescribed and to the
     satisfaction thereof and hands over the developed or constructed
846                                                           [2024] 9 S.C.R.

                       Digital Supreme Court Reports


       amenity to the Commissioner or the appropriate authority free
       of cost, he would be granted further DR in the form of FSI equivalent to
       the area of construction/development done by him, utilisation of which
       would be subject to the regulations contained in the said Appendix.
       5.1 Contrasting Regulation 34 with Regulation 33, it was observed
           that the latter pertained to additional FSI which may be allowed
           to certain categories. Sub-regulation (1) as it stood at the
           relevant time, provided that the Commissioner could permit the
           additional FSI on 100% of the area required for road widening
           or for construction of new roads under the development plan.
           Such FSI so surrendered would be utilisable on the remainder
           of the land up to a limit of 40% in respect of the plots situated in
           Mumbai city and 80% in respect of the plots situated in suburbs
           and extended suburbs. The balance FSI remaining thereafter
           was allowed to be utilised as a development right in accordance
           with the regulations governing TDRs. In the said case, it was
           again contended on behalf of the Mumbai Municipal Corporation
           that the petitioner therein having utilised 100% FSI for surrender
           of land without cost on the same layout, was governed by
           Regulation 33 and therefore, could not claim any additional
           FSI/TDR for having constructed the amenities. This contention,
           in fact, was squarely identical to those in the case of Apurva
           Natwar Parikh & Co. Pvt. Ltd which case is discussed later.
       5.2 It was pointed out that till the amendment on 17.06.2010,
           there was no provision in Regulation 33 for claiming FSI for
           construction of amenities and the same could be claimed only
           in terms of Regulation 34 read with Para 6 of Appendix-VII. On
           the other hand, it was contended by the Municipal Corporation
           that Regulation 33 was not brought to the notice of this Court
           in Godrej & Boyce I and that by notification dated 16.11.2016
           the Regulation was amended to restrict the benefit of additional
           TDR for development of amenities which was to cure a defect
           in the legislation. The said contention was considered in light of
           the amendment to Regulation 33 with effect from 17.06.2010,
           by which a clause was added to sub-regulation (1) and it was
           observed that the amendment to Regulation 33(1) was applicable
           to roads and not to any other amenity. Moreover, this portion of
           the amendment would not apply where the FSI granted in lieu
           of road is utilised and full occupation certificate was granted
           prior to 17.06.2010. Therefore, from 17.06.2010 in case of a
[2024] 9 S.C.R.                                                         847

               Kukreja Construction Company & Others v.
                     State of Maharashtra & Others

           land reserved for road or road widening which was surrendered,
           if the amenity of the road was constructed by the owner of the
           land surrendered, the additional FSI as provided in clause (b) of
           sub-section (1) of Section 126 will be 25% from the area of the
           construction of the road. Therefore, for such amenity, in terms
           of Para 6 of Appendix-VII, the owner or a lessee will not get
           TDR equivalent to entire area of the road constructed by him.
           It will remain confined to 25% of the area. It was observed that
           Regulation 33(1) as amended on 17.06.2010 was not modified
           by the impugned notification dated 16.11.2016.

     Apurva Natwar Parikh & Co. Pvt. Ltd.:
6.   In the case of Apurva Natwar Parikh & Co. Pvt. Ltd. vs. State
     of Maharashtra, Writ Petition No.203 of 2014 filed before the High
     Court, the surrender of land was in the form of deed of conveyance
     and handing over of possession was in February, 2007 and
     within three years from the surrender i.e. February, 2010, the writ
     petitioner/appellant herein requested an officer of MMRDA to
     recommend to the Mumbai Municipal Corporation to issue 100%
     additional TDR in respect of construction of amenity. In December,
     2010, DRC of 25% of the amenity was granted. The balance 75%
     had not been paid. Hence, the writ petition was filed in October, 2013.
     Actually, within one month from the date of decision in the case of
     Godrej and Boyce I, the petitioner applied to the respondent-MMRDA
     for recommending to the Mumbai Municipal Corporation for grant of
     100% TDR in respect of the amenity and the said application was
     acted upon and 25% FSI was granted in December, 2010. Therefore,
     the High Court held that conduct of the petitioner is not such that it
     will prevent the Writ Court from granting relief in terms of the decision
     in Godrej & Boyce I.

     Arvind Kashinath Dadarkar:
7.   In Arvind Kashinath Dadarkar vs. Municipal Corporation of
     Greater Mumbai, Writ Petition No.411 of 2013 (“Arvind Kashinath
     Dadarkar”), disposed of on 20.10.2022, another Division Bench of
     the High Court of Bombay while adverting to Godrej & Boyce I and
     Apurva Natvar Parikh & Co. Pvt. Ltd., and Starwing Developers
     Private Limited, allowed the writ petition and directed that TDR be
     issued to the petitioner therein.
848                                                        [2024] 9 S.C.R.

                      Digital Supreme Court Reports


       Submissions:
8.     We have heard the arguments of the respective Senior Counsel and
       other Counsel on both sides and perused the material on record.

       Submissions on behalf of the Appellants:
       8.1 Learned senior counsel, Sri Pravin Samdani, contended that
           the impugned judgment dated 18.12.2018 has, in fact, upheld
           petitioners’ right to 100% additional TDR and has applied
           the judgment of this Court in Godrej & Boyce I. However,
           reliefs were declined to certain writ petitioners on the ground
           of delay and laches in claiming the additional TDR in time.
           Consequently, the writ petitions were dismissed by the High
           Court. Being aggrieved by the dismissal of the writ petitions,
           the writ petitioners before the High Court have preferred these
           appeals. Therefore, this Court may reverse the finding of the
           High Court on the issue of the delay and laches and grant the
           reliefs to these appellants as the other writ petitioners have
           been granted by the High Court.
       8.2 In this regard, it was submitted that the compensation payable
           to the landowners/lessees for acquisition of their land for
           a public purpose is, in fact, held in trust by the acquiring
           body, i.e., the Mumbai Municipal Corporation in the instant
           case. Once the compensation is determined, the same was
           payable and the reliefs could not have been denied by the
           High Court on the ground of delay or laches. In this context,
           reliance was placed on Noida Entrepreneur Association vs.
           NOIDA (2011) 6 SCC 508 (Para 38-39) (“Noida Entrepreneur
           Association”).
       8.3 It was next submitted that the State is the guardian or custodian
           and protector of the rights of the citizens. This casts a duty
           and obligation on the State to pay compensation to land
           losers for lands compulsorily acquired. The right to receive a
           fair compensation is a constitutional right guaranteed under
           Article 300A of the Constitution of India which can also be
           traced to Article 21 of the Constitution of India as a citizen
           cannot be deprived of his property, save in accordance with
           law. It was contended that the mandate of Section 126(1)(b)
           of the MRTP Act and the DCR be complied with by the
[2024] 9 S.C.R.                                                           849

                  Kukreja Construction Company & Others v.
                        State of Maharashtra & Others

           respondent-Mumbai Municipal Corporation vis-à-vis the
           appellants herein. Otherwise, the denial of compensation would
           amount to usurping the citizens’ property without authority of
           law and in breach of the constitutional rights of the citizens.
           In this context, reliance was placed on Vidya Devi vs. State
           of Himachal Pradesh (2020) 2 SCC 569 (Para 12.9 to
           12.14); Sukh Dutt Ratra vs. State of Himachal Pradesh
           (2022) SCC OnLine SC 410 (Para 13-27); and Lalaram Vs.
           Jaipur Development Authority (2016) 11 SCC 31 (Para 124
           & 129); Kazi Moinuddin Kazi Bashiroddin vs. Maharashtra
           Tourism Development Corporation (2022) SCC OnLine SC
           1325 (Para 26).
     8.4 In the above backdrop, learned senior counsel, Sri Pravin
         Samdani submitted that the High Court was not right in
         dismissing the writ petitions on the ground of delay and laches
         when the respondent – Mumbai Municipal Corporation had not
         proved that:
           (i)     the delay amounted to laches;
           (ii)    owing to delay and during the interregnum, the
                   respondent-Mumbai Municipal Corporation had altered its
                   position to its prejudice; and
           (iii) certain rights had accrued which could not be disturbed
                 by grant of reliefs to the writ petitioners/appellants herein.
     In this context, reliance was placed on Moon Mills Ltd. vs.
     M.R. Meher, President, Industrial Court, Bombay, AIR 1967
     SC 1450 (Para 9); M/s Dehri Rohtas Light Railway Company
     Limited vs. District Board, Bhojpur (1992) (2) SCC 598
     (Para 13); Hindustan Petroleum Corporation Ltd. vs. Dolly
     Das (1999) 4 SCC 450] (Para 8); and Tukaram Kana Joshi vs.
     Maharashtra Industrial Development Corporation (2013) 1
     SCC 353 (Para 12); and Mohar Singh (Dead) Thr. LRs. vs. State
     of UP Collector, 2023 INSC 1019 (Para 12).
     8.5 It was further urged that the Mumbai Municipal Corporation
         has not asserted that owing to the alleged delay on the
         part of the appellants herein in making their claim under
         Section 126(1)(b) of the MRTP Act, there was any prejudice
         caused to it.
850                                                         [2024] 9 S.C.R.

                      Digital Supreme Court Reports


       8.6 It was also submitted that the observations of the High Court
           in the impugned judgment that there was a waiver or an
           abandonment of their rights by the writ petitioners/appellants
           herein are contrary to the facts and law. In this regard reference
           was made to Godrej & Boyce Manufacturing Co. Ltd. vs.
           Municipal Corporation of Greater Mumbai (2023) SCC
           OnLine SC 592 (Paras 8, 15 and 18) (“Godrej & Boyce II”);
           G.T. Lad vs. Chemical and Fibres of India Ltd. (1979) 1
           SCC 590 (Para 5 & 6); A.P. SRTC vs. S. Jayaram (2004) 13
           SCC 792 (Para 5); and State of Punjab vs. Davinder Pal
           Singh Bhullar (2011) 14 SCC 770 (Para 37 to 42).
       8.7 Petitioners’ counsel therefore sought for allowing these appeals
           by setting aside that portion of the order of the High Court
           declining to grant relief on the ground of delay and laches.
       8.8 On the merits of the case, Sri Samdani submitted that
           Section 2(2) of the MRTP Act defines an amenity which is also
           defined under Regulation 3(7) of DCR. Section 126(1)(b) of MRTP
           Act provides for compulsory acquisition, wherein compensation
           is provided in the form of FSI or TDR in two parts: (i) for the
           land; and (ii) for development/construction of the amenity at
           the cost of the owner on the surrendered land in terms of the
           DCR. That Regulations 33(1) and 34 prior to their amendment
           in the year 2010 provided a mechanism for grant of TDR for
           both the first as well as the second component. This Court had
           interpreted the aforesaid provisions in the case of Godrej &
           Boyce I. This Court observed that the grant of additional TDR
           was for construction or development of the amenity. However,
           in the year 2010, there was an amendment which stated that
           in addition to the land component of FSI/TDR, the land owner
           would be entitled to receive only additional 25% FSI/TDR for
           construction of road. However, the additional 25% could be used
           as FSI on the remainder of the plot if the remainder of the plot
           could consume to the extent of 40/80% of the remaining land
           after surrender. The balance FSI/TDR was eligible to be paid as
           TDR under Paras 5 and 6 of Appendix-VII-A and Regulation 34
           of the DCR. This amendment of 17.06.2010 was subsequent
           to the judgment of this court in Godrej & Boyce I. However,
           there was no alteration to Regulation 34 and Paras 5 and 6 of
           Appendix-VII-A of the DCR. This amendment was in the form
[2024] 9 S.C.R.                                                          851

               Kukreja Construction Company & Others v.
                     State of Maharashtra & Others

           of delegated legislation and was only prospective in nature. But
           by the amendment of 16.11.2016, the entire Regulation 34 and
           Appendix-VII-A was amended. As a result of the amendment, if
           the land owner desired to obtain TDR for the land component,
           the owner was eligible to do so at the rate mentioned in Para 4.1
           of amended Regulation. If the landowner also developed the
           amenity, the owner became eligible to receive compensatory
           TDR in terms of Para 4.2 of the amended Regulation.
     8.9 According to learned senior counsel, this amendment is also
         prospective. It was further submitted that by the amendment of
         Regulation 34 of the DCR, the basis of the judgment in Godrej &
         Boyce I was not removed. The intention of the amendment was
         to grant additional compensation to the landowner in view of the
         enforcement of Right to Fair Compensation and Transparency in
         Land Acquisition, Rehabilitation and Resettlement Act, 2013 and
         not to remove the basis of the judgment in Godrej & Boyce I.
         There was no intention to validate any action of the Corporation
         of curtailing amenity TDR to 25% or to validate Circulars based
         on which it was sought to be curtailed to 25%. Therefore, the
         judgment of this Court in Godrej & Boyce I remains intact.
     8.10 It was further submitted that the right to receive compensation
          for acquisition is a vested right and a constitutional right and the
          same cannot be taken away by an amendment to the statute.
     8.11 It was next submitted that the attempt of the Mumbai Municipal
          Corporation to deny balance 75% TDR in view of the notification
          dated 16.11.2016 is unsustainable. This is because the writ
          petitioners’ right to receive the balance TDR is a vested right
          which arose under the old DCR and continues even after the
          amendment. Further, a person cannot be denied compensation
          by a subsequent legislation when the entitlement is recognized
          under a prior legislation. The High Court has rightly held that
          the DCR amended was prospective and not retrospective.

     Submissions on behalf of the Respondents:
9.   Per contra, learned senior counsel Sri Nadkarni, appearing for the
     respondent – Mumbai Municipal Corporation submitted a chart giving
     details of each of the appellants/writ petitioners before the High
     Court. The relevant chart is extracted hereinbelow:
852                                                                     [2024] 9 S.C.R.

                        Digital Supreme Court Reports



       SR. NO./   PARTICULARS        DATE OF       WHETHER       APPLICATION DELAY
       RELEVANT                      HANDING       HANDED        FOR
       REGULATION                    OVER OF       OVER          ADDITIONAL
                                     AMENITY       AMENITY       AMENITY FSI/
                                                   COMPLIES      TDR AFTER
                                                   WITH ALL      GODRIJ
                                                   CONDITIONS    & BOYCE
                                                                 JUDGMENT
                                                                 (06.02.2009)
       1.         KUKREJA            28.01.1994    --NO— In the 31.08.2009       6-15 years
       REGULATION CONSTRUCTION                     constructed                   (calculated
       34         CO. & ORS.                       road the                      from the
                  VS. STATE OF                     sewer lines                   date of
                  MAHARASHTRA                      were not laid                 handing over
                                                   down nor
                  & ORS. SLP (C)                                                 of amenity)
                                                   the street
                  NO.5273.2019                     lights were
                  WP(C) NO.                        laid down.
                  1898/2009                        On failure
                                                   to comply
                                                   parties are
                                                   required to
                                                   pay prorate
                                                   charges. As
                                                   regard to
                                                   street lights
                                                   the prorate
                                                   charges were
                                                   paid after
                                                   delay, Sewer
                                                   lines were not
                                                   paid.
       2.         NANABHOY           1. 13.04.2004 YES            For 6 cases    8-16 years
       REGULATION JEEJEEBHOY         2. 20.03.2001                – 11.07.2014   (calculated
       33(1)      PVT. LTD. & ANR.   3. 27.03.2002                For 4 cases    from the
                  VS. STATE OF       4. 06.09.2001                – 19.08.2014   date of
                  MAHARASHTRA        5. 13.02.2006                For one case   handing over
                  & ANR. SLP (C)     6. 27.10.1997                – 26.08.2014   of amenity)
                  NO.8664/2019 WP    7. 27.10.1997
                  (C) NO.541/2017    8. 29.10.1997
                                     9. 21.12.2002
                                     10. 14.12.2001
                                     /22.05.2002
                                     11. 14.08.2002
       3.         JITENDRA           05.03.2005     YES          24.02.2009      4 years
       REGULATION AMRITLAL                                                       (calculated
       33(1)      SETH & ORS.                                                    from the
                  VS. STATE OF                                                   date of
                  MAHARASHTRA                                                    handing over
                  & ORS. SLP                                                     of amenity)
                  (C) NO.8204
                  / 2019 WP(C)
                  NO.1823/2012
[2024] 9 S.C.R.                                                                      853

               Kukreja Construction Company & Others v.
                     State of Maharashtra & Others

      SR. NO./   PARTICULARS      DATE OF       WHETHER      APPLICATION DELAY
      RELEVANT                    HANDING       HANDED       FOR
      REGULATION                  OVER OF       OVER         ADDITIONAL
                                  AMENITY       AMENITY      AMENITY FSI/
                                                COMPLIES     TDR AFTER
                                                WITH ALL     GODRIJ
                                                CONDITIONS   & BOYCE
                                                             JUDGMENT
                                                             (06.02.2009)
      4.         GEETA ALIAS      20.05.2005    YES          For Balance      4½ years
      REGULATION CHANDANI                                    75% additional   (calculated
      34         UMESH GANDHI                                TDR on           from the
                 SLP (C)                                     01.12.2009,      date of
                 NO.15702/2019                               20.06.2014,      handing over
                 WP(C)                                       01.12.2014,      of amenity)
                 NO.839/2015                                 20.02.2016
      5.         MCGM V.          07.02.2007    YES          Balance          No delay
      REGULATION APURVA                                      75% TDR          case as
      34         NATWAR                                      14.12.2011       High Court
                 PAREKH & CO.                                (Godrej &        allowed the
                 PVT. LTD &                                  Boyce case –     WP
                 ORS. SLP (C)                                after 2 years
                 NO.13365/2019                               applied)
                 WP(C)
                 NO.203/2014
      6.         OBEROI REALITY   1. 26.05.04   YES          10.06.2016       8 years
      REGULATION LTD. ANR.        2. 16.04.08                                 (calculated
      33(1)      VS. MCGM &       3. 29.03.08                                 from the
                 ANR. SLP (C)                                                 date of
                 NO.8520/2019                                                 handing over
                 WP(C)                                                        of amenity)
                 NO.384/2017
      7.         GIRDHARLAL       13.12.1995    YES          05.08.2014       18 years
      REGULATION D. RUGHANI                                                   (calculated
      33(1)      ALIAS THAKAR                                                 from the
                 HUF & ANR.                                                   date of
                 VS. STATE OF                                                 handing over
                 MAHARASTHRA                                                  of amenity)
                 & ORS. SLP (C)
                 NO.5745/2020
                 WP(C)
                 NO.2170/2016
      8.         JAMEEL A.      29.07.2004      YES          28.07.2014       4 years from
      REGULATION HUSSAIN & ORS.                                               notification
      33(1)      V. STATE OF                                                  dated
                 MAHARASHTRA                                                  17.06.2010
                 & ORS. SLP (C)
                 NO.8704/2019
                 WP(C)
                 NO.2871/2015
854                                                                [2024] 9 S.C.R.

                      Digital Supreme Court Reports



       SR. NO./   PARTICULARS     DATE OF      WHETHER      APPLICATION DELAY
       RELEVANT                   HANDING      HANDED       FOR
       REGULATION                 OVER OF      OVER         ADDITIONAL
                                  AMENITY      AMENITY      AMENITY FSI/
                                               COMPLIES     TDR AFTER
                                               WITH ALL     GODRIJ
                                               CONDITIONS   & BOYCE
                                                            JUDGMENT
                                                            (06.02.2009)
       9.         BYRAMJI         05.06.2007   YES          No Application   9 years (wrt
       REGULATION JEEJEEBHOY                                made for 75%     the WP filed)
       34         PVT LTD. ANR.                             additional.
                  VS. STATE OF
                  MAHARASHTRA
                  SLP (C)
                  NO.8552/2019
                  WP(C)
                  NO.2107/2016
       10.        MCGM V.         29.12.2007   YES          ……………….          1½ years
       REGULATION STARWING                                                   (calculated
       33(1)      SLP (C)                                                    from the
                  NO.10430/2020                                              date of
                  WP(C)                                                      rejection by
                  NO.2531/2009                                               the State
                                                                             Government
                                                                             on
                                                                             15.07.2008
                                                                             and
                                                                             thereafter
                                                                             WP filed on
                                                                             05.12.2009)

       9.1 Insofar as the appellant – M/s Kukreja Construction Company,
           it was submitted that the conditions which are required to be
           complied with for seeking compensation under Section 126(1)(b)
           of the MRTP Act have not been met and therefore, unless and
           until the said conditions are complied with, the said appellant
           would not be entitled to compensation under the scheme of
           the Act and the Regulations made thereunder. As far as the
           other appellants are concerned, he fairly submitted that even
           according to the Mumbai Municipal Corporation they have
           complied with the conditions as required under the scheme and
           therefore, their cases could be considered if they are otherwise
           eligible for compensation being paid to them in case they are
           successful in these appeals.
       9.2 Learned senior counsel also strenuously sought to buttress
           the submissions made on behalf of the Mumbai Municipal
[2024] 9 S.C.R.                                                          855

               Kukreja Construction Company & Others v.
                     State of Maharashtra & Others

           Corporation before the High Court regarding the judgment of
           this Court in Godrej & Boyce I, but did not persuade himself
           to do so. Ultimately, he supported the order of the High Court
           in denying the reliefs to the writ petitioners who had delayed
           in making their claims. He contended that the High Court was
           right in declining to grant the relief to the said parties.
     9.3 Sri Nadkarni contented that firstly, the High Court was right in
         declining relief based on the judgment of this Court in Godrej
         and Boyce I owing to delay, as those developers who already
         availed of the TDR and accepted the same without any protest
         or demur could not again agitate the matter after the judgement
         of this Court in Godrej and Boyce I. Secondly, there was
         a crystallisation of the compensation payable in the form of
         FSI/TDR as on the date of the notice of acquisition which in this
         case could be either the publication of the development plan or
         the date of preliminary notification under the Acquisition Act and
         that the owner or lessee could not have returned for a second
         helping or make an additional claim of 100% TDR since the value
         of the land as on the date when the project was conceived or
         when the benefits were received would have been lesser than
         the value of the land on the date of the filing of the writ petition.
         Thirdly, any grant of additional TDR despite there being a delay
         would result in unjust enrichment of the owner and the lessee
         who could get an advantage of escalation in price of land which
         is contrary to public interest. Therefore, for this reason also, the
         High Court was justified in declining to grant relief on the ground
         of delay and laches. Hence, there is no merit in these appeals.
     9.4 Learned senior counsel submitted that in the event this Court
         is to condone the delay and laches and thereby modifies the
         impugned judgment of the High Court then, in the case of
         the appellants in CA No. 9702 of 2024, (Kukreja Construction
         company and others) this Court may direct that only on complying
         with the mandatory requirements could the said appellant avail
         of the benefits of additional FSI/TDR in accordance with law
         as indicated in the table above.
     9.5 Learned senior counsel, Sri Nadkarni, with reference to our
         order dated 06.08.2024, sought further instruction on Estate
         Investment Company Ltd. and Ever-smile Construction being
856                                                           [2024] 9 S.C.R.

                       Digital Supreme Court Reports


             granted relief of 100% of TDR rights in terms of Section 126(1)(b)
             of the MRTP Act as well as the DCR. He fairly submitted that
             there is no dispute that the aforesaid two entities were indeed
             granted 100% TDR rights. Further, there has been no appeal
             filed with regard to the order of the High Court in Writ Petition
             No. 1860 of 2017 and Writ Petition No.2262 of 2010. Learned
             senior counsel, Sri Nadkarni, also submitted that insofar
             as the judgment of the High Court assailed in Civil Appeal
             Nos.9711/2024 and 9712/2024, they may be disposed in light
             of the prevalent law.

       Reply arguments:
10. By way of reply, learned senior counsel, Sri Samdani and other learned
    counsel contended that the Mumbai Municipal Corporation cannot
    be permitted to raise any contention contrary to the judgment of this
    Court in Godrej & Boyce I which is holding the field and there is
    no contention raised by the Municipal Corporation either before the
    High Court or this Court which can lead to a reconsideration of the
    said judgment. Hence, they sought for application of the judgment
    of this Court in Godrej & Boyce I to their cases as well.
       10.1 Learned counsel for the respondents in the three appeals
            filed by the Mumbai Municipal Corporation supported the
            impugned order passed by Bombay High Court and contented
            that having regard to the judgment of this Court in Godrej
            & Boyce I and the order passed in Civil Appeal No. 1748
            of 2015 which arose from the judgment of the Bombay High
            Court in the case of Natwar Parikh & Co. Pvt. Ltd, there is
            no merit in these appeals. Hence, they contended that the
            appeals filed by the Mumbai Municipal Corporation may be
            dismissed.

       Points for consideration:
11. In light of the aforesaid contentions, the following points would arise
    for our consideration: -
       (i)   Whether the High Court was right in declining to grant relief
             to the writ petitioners/appellants herein on the ground of delay
             and laches?
[2024] 9 S.C.R.                                                           857

                Kukreja Construction Company & Others v.
                      State of Maharashtra & Others

     (ii)   Whether the appeals filed by the respondent-Mumbai Municipal
            Corporation would call for any interference by this Court?
     (iii) What order?

     Godrej & Boyce I:
12. At the outset, it would be useful to refer to the dictum of this Court
    in Godrej & Boyce I which has been followed by the High Court
    in these cases. In the said case, this Court considered the scheme
    of development rights in respect of land acquired for the purpose
    specified in plans under Section 126 of the MRTP Act. Three modes
    of acquisition of land required for a public purpose specified in the
    plan are contemplated under Section 126 of the MRTP Act, which
    reads as under:
            “126. Acquisition of land required for public purposes
            specified in plans.— (1) Where after the publication of a
            draft Regional plan, a Development or any other plan or town
            planning scheme, any land is required or reserved for any of
            the public purposes specified in any plan or scheme under
            this Act at any time, the Planning Authority, Development
            Authority, or as the case may be, any Appropriate Authority
            may, except as otherwise provided in Section 113-A
            acquire the land,—
            (a) by agreement by paying an amount agreed to, or
            (b) in lieu of any such amount, by granting the land-owner
            or the lessee, subject, however, to the lessee paying
            the lessor or depositing with the Planning Authority,
            Development Authority or Appropriate Authority, as the
            case may be, for payment to the lessor, an amount
            equivalent to the value of the lessor’s interest to be
            determined by any of the said Authorities concerned on
            the basis of the principles laid down in the Right and Fair
            Compensation and Transparency in Land Acquisition,
            Rehabilitation and Resettlement Act, 2013, Floor Space
            Index (FSI) or Transferable Development Rights (TDR)
            against the area of land surrendered free of cost and free
            from all encumbrances, and also further additional Floor
            Space Index or Transferable Development Rights against
858                                                      [2024] 9 S.C.R.

                  Digital Supreme Court Reports


       the development or construction of the amenity on the
       surrendered land at his cost, as the Final Development
       Control Regulations prepared in this behalf provide, or
       (c) by making an application to the State Government for
       acquiring such land under the provisions of the Right and
       Fair Compensation and Transparency in Land Acquisition,
       Rehabilitation and Resettlement Act, 2013, and the
       land (together with the amenity, if any so developed or
       constructed) so acquired by agreement or by grant of
       Floor Space Index or additional Floor Space Index or
       Transferable Development Rights under this section or
       under the provisions of the Right and Fair Compensation
       and Transparency in Land Acquisition, Rehabilitation and
       Resettlement Act, 2013, as the case may be, shall vest
       absolutely free from all encumbrances in the Planning
       Authority, Development Authority, or as the case may be,
       any Appropriate Authority.
       (2) On receipt of such application, if the State Government
       is satisfied that the land specified in the application is
       needed for the public purpose therein specified, or if the
       State Government (except in cases falling under Section 49
       and except as provided in Section 113-A) itself is of opinion
       that any land included in any such plan is needed for any
       public purpose, it may make a declaration to that effect in
       the Official Gazette, in the manner provided in Section 19
       Right to Fair Compensation and Transparency in Land
       Acquisition, Rehabilitation and Resettlement Act, 2013,
       in respect of the said land. The declaration so published
       shall, notwithstanding anything contained in the said Act,
       be deemed to be a declaration duly made under the said
       section:
       Provided that, subject to the provisions of sub-section (4),
       no such declaration shall be made after the expiry of one
       year from the date of publication of the draft Regional
       Plan, Development Plan or any other Plan, or Scheme,
       as the case may be.
       (3) On publication of a declaration under the said Section 19,
       the Collector shall proceed to take order for the acquisition
[2024] 9 S.C.R.                                                           859

               Kukreja Construction Company & Others v.
                     State of Maharashtra & Others

           of the land under the said Act; and the provisions of that
           Act shall apply to the acquisition of the said land with the
           modification that the market value of the land shall be,—
           (i) where the land is to be acquired for the purposes of
           a new town, the market value prevailing on the date of
           publication of the notification constituting or declaring the
           Development Authority for such town;
           (ii) where the land is acquired for the purposes of a
           Special Planning Authority, the market value prevailing
           on the date of publication of the notification of the area
           as undeveloped area; and
           (iii) in any other case, the market value on the date of
           publication of the interim development plan, the draft
           development plan or the plan for the area or areas for
           comprehensive development, whichever is earlier, or as
           the case may be, the date of publication of the draft Town
           Planning Scheme:
           Provided that, nothing in this sub-section shall affect the
           date for the purpose of determining the market value of land
           in respect of which proceedings for acquisition commenced
           before the commencement of the Maharashtra Regional
           and Town Planning (Second Amendment) Act, 1972:
           Provided further that, for the purpose of clause (ii) of this
           sub-section, the market value in respect of land included
           in any undeveloped area notified under sub-section (1) of
           Section 40 prior to the commencement of the Maharashtra
           Regional and Town Planning (Second Amendment) Act,
           1972, shall be the market value prevailing on the date of
           such commencement.
           (4) Notwithstanding anything contained in the proviso to
           sub-section (2) and sub-section (3), if a declaration, is not
           made, within the period referred to in sub-section (2) (or
           having been made, the aforesaid period expired on the
           commencement of the Maharashtra Regional and Town
           Planning (Amendment) Act, 1993, the State Government
           may make a fresh declaration for acquiring the land
           under the provisions of the Right and Fair Compensation
860                                                          [2024] 9 S.C.R.

                        Digital Supreme Court Reports


            and Transparency in Land Acquisition, Rehabilitation
            and Resettlement Act, 2013, in the manner provided by
            sub-sections (2) and (3) of this section, subject to the
            modification that the market value of the land shall be
            the market value at the date of declaration in the Official
            Gazette, made for acquiring the land afresh.”
       In this case, we are concerned with Section 126(1)(b) of the MRTP Act.
       12.1 Under Section 126(1) of the MRTP Act, when land is required
            or reserved for any of the public purposes specified in any plan
            or scheme under the Act at any time, the Planning Authority, the
            Development Authority, or as the case may be, any Appropriate
            Authority may acquire the land by agreement by paying an
            amount agreed to landowner or lessee [Section 126(1)(a)]; the
            second mode is, in lieu of any such amount as mentioned above,
            by granting the landowner or the lessee, subject, however, to
            the lessee paying the lessor or depositing with the Planning
            Authority, the Development Authority or Appropriate Authority,
            as the case may be, for payment to the lessor, an amount
            equivalent to the value of the lessor’s interest to be determined
            by any of the said Authorities concerned on the basis of the
            principles laid down in the Land Acquisition Act, 1894, Floor
            Space Index (FSI) or Transferable Development Rights (TDR):
            (i)    against the area of land surrendered free of cost and free
                   from all encumbrances, and also
            (ii)   further additional FSI or TDR against the development or
                   construction of the amenity on the surrendered land at
                   his cost, as the Final Development Control Regulations
                   prepared in that behalf provide [Section 126(1)(b)].
                   The third mode being by acquisition of the land under the
                   relevant Act [Section 126(1)(c)].
       12.2 Thus, it is open to the landowner to surrender the plot of land
            “free of cost” and “free from all encumbrances” to the appropriate
            authority who may acquire the land by granting to the owner
            FSI or TDR against the area of the surrendered land. The
            scheme further provides for additional FSI or TDR against the
            development of construction of amenities (for which the plot
            is shown reserved in the plan) by the owner at his own cost.
[2024] 9 S.C.R.                                                       861

               Kukreja Construction Company & Others v.
                     State of Maharashtra & Others

     12.3 In Godrej & Boyce I, the appellants therein had their plots
          covered under the development plan as reserved for roads,
          which they voluntarily surrendered. In addition, they constructed
          on their respective pieces of land the development plan roads
          at their own cost and as per the specifications stipulated in the
          relevant rules. In the said case, there was no dispute between
          the parties in regard to the FSI or TDRs granted to them for
          the surrendered plots of land. The controversy was with regard
          to the FSI or TDRs for roads constructed on the surrendered
          lands at the owner’s cost. The landowners claimed that for
          constructing the roads they were entitled to FSI or TDRs for
          the whole of the surface area of the roads. They relied upon
          Para 6 of Appendix-VII to the DCRs. The Mumbai Municipal
          Corporation however relied upon a Circular dated 09.04.1996
          issued by the Municipal Commissioner, Municipal Corporation
          of Greater Bombay, which envisaged a graded scheme for grant
          of additional development rights for construction of amenities by
          the landowner, e.g. in case of amenities like general hospital,
          municipal primary school, etc. which allowed FSI equal to the
          built-up area of the structure but in case of DP road only 15%
          of the area of the road surface. The Circular was assailed by
          the landowners.
     12.4 In the said case, the Bombay High Court had accepted the
          contention advanced on behalf of the State of Maharashtra
          to the effect that by introducing a graded scheme for grant of
          additional FSI or TDR the Circular had eliminated the possibility
          of any discriminatory or arbitrary action on the part of the
          authority competent to issue the development right certificate.
          It was contended that grant of further additional TDR was
          commensurate to the value of the amenity constructed/developed
          on the surrendered land. Therefore, it was contended that Para 6
          of the Appendix-VII, unlike Para 5 didn’t use the words “equal to
          the gross area of the reserved plot” or “equal in area”. Instead,
          Para 6 used the words “equivalent to the area of construction/
          development”. That, Para 6 of Appendix-VII to the Regulations
          must be read with Section 126(1)(b) of the Act. It was evident
          that the said provision used the words “against the area of the
          land surrendered” and “against the development or construction
          of amenity on the surrendered land”. Therefore, the grant of
862                                                          [2024] 9 S.C.R.

                        Digital Supreme Court Reports


            additional development right was proportionate to the value
            of the amenity constructed by the owner at his own cost and
            the Circular issued by the Municipal Commissioner simply
            quantified the exchange value of different kinds of amenities
            in percentage terms depending upon their cost of construction
            and other relevant considerations.
       12.5 However, the aforesaid submission, which was accepted by
            the Bombay High Court was not agreed to by this Court and
            the judgment of the Bombay High Court was set-aside. While
            doing so, the submission on behalf of the appellants therein was
            accepted that the provision clearly envisaged grant of the FSI
            or TDR under two separate heads: one, for the land, and the
            other, for the construction of the amenity for which the land was
            designated in the development plan at the cost of the owner.
            The Court also held that Section 2(9-A) defined “development
            right” to include TDR and Section 126(1)(b) provided for:
            (i)    grant of FSI or TDR against the area of land surrendered
                   free of cost, and
            (ii)   further, additional FSI or TDR against the development or
                   construction of the amenity on the surrendered land at the
                   owner’s cost as the final Development Control Regulations
                   should provide.
       12.6 In the case of (i) above, FSI or TDR would be equal to the
            gross area of the surrendered plot, and for (ii) above i.e. for
            construction of the amenity, the extent of the FSI or TDR would
            be equivalent to the area of the construction/development made
            on the land.
       12.7 That Regulation 34 made provisions for transferability of the
            development rights and Appendix-VII referred to in Regulation 34
            provided for the extent of FSI or TDR admissible under the
            two heads. That the expression “equivalent to the area” of the
            construction or development made on the surrendered land in
            Para 6 of Appendix-VII would mean “equivalent to the area of
            construction/development”, that is to say, the additional DR would
            be the same in area as the amenity constructed/developed on
            the surrendered land. Hence, there cannot be a differentiation
            in the grant of additional TDR on a variable and sliding scale
[2024] 9 S.C.R.                                                         863

               Kukreja Construction Company & Others v.
                     State of Maharashtra & Others

           on the surrendered land for amenities constructed on the basis
           of the Circular issued by the Municipal Commissioner. Also, the
           Circular cannot override the provisions of the Regulations. It was
           further observed that the expressions “against the area of the
           land surrendered free of cost” and “against the development or
           construction of amenity on the surrendered land” would mean
           “in exchange for, in return for; as an equivalent or set-off for;
           in lieu of, instead of”. Section 126(1)(b) was a recompense to
           the landowner proportionate to the area of development or
           construction of the amenity on the surrendered land. Thus, in
           Para 5 of Appendix-VII to the Regulations, the expression “equal
           to the gross area of reserved plot” was relatable to the bare
           land and in Para 6 of the Appendix, the expression “equivalent
           to the area of the construction/development” would mean that
           “the area of construction or development” is the measure
           of equivalence. Therefore, there could be no other basis for
           determining the equivalence. Hence, the Circular was held to
           be without authority of law.

     Natwar Parikh & Co. Pvt. Ltd.:
13. Prior to the impugned judgments of the High Court, in Natwar Parikh
    & Co. Pvt. Ltd., a writ petition was filed before the Bombay High
    Court seeking a direction for grant of additional TDR/development
    rights certificate (DRC) for the balance 75% area as set out in the
    Schedules annexed to the writ petitions. In that case also, admittedly,
    the respondents therein had been granted 25% TDR/DRC in lieu of
    the construction of the specified DP Road and there was no challenge
    about the actual work done at the relevant time. Subsequent to the
    judgment of this Court in Godrej & Boyce I, the petitioner therein filed
    the petition. The respondent Mumbai Municipal Corporation sought to
    deny the same on a twofold contention: firstly, there was delay and
    laches; and, secondly, an attempt was made to reopen the issues on
    facts about the construction of the DP Road. The same were repelled
    by the High Court by holding that already 25% TDR had been granted
    and therefore, there could be no reopening of the controversy on that
    basis and the only question which remained was the entitlement of
    the petitioner to remaining 75% TDR/DRC as prayed.
     13.1 A contention was also sought to be raised by the
          respondent-Corporation that the petitioner therein had not
864                                                        [2024] 9 S.C.R.

                      Digital Supreme Court Reports


            built upon the amenity as contemplated under Regulation 34
            Appendix-VII Paras 5 and 6. The said contention was also
            repelled by holding that the right of the petitioner has already
            been crystallised and the cause of action was a continuing
            one and hence there was no question of delay and laches.
            Consequently, a direction was issued to grant additional TDR
            for the balance 75% area. It was also observed that the issues
            which were raised in the said case had been concluded by the
            judgment of this Court in the case of Municipal Corporation
            of Greater Bombay vs. Yeshwant Jagannath Vaity (2011) 11
            SCC 88 (“Yeshwant Jagannath Vaity”), “for other amenity”
            also.
       13.2 In Civil Appeal No.1748 of 2015 (Municipal Corporation of
            Greater Mumbai vs. Natwar Parikh and Co. Pvt. Ltd.), this
            Court by order dated 05.05.2016 has categorically observed
            that it was too late to re-visit the entire issue and to take a
            decision whether the judgment delivered earlier in Godrej &
            Boyce I should apply prospectively and not retrospectively. That
            is a matter which should have been agitated when Godrej &
            Boyce I was being heard. It was further observed that insofar as
            the 89 applicants who were then waiting to take an advantage
            of the aforesaid decision rendered by this Court, on the facts
            of the cases the applications ought to be considered and if a
            dispute arises the appropriate Court would take a decision in
            the matter. Consequently, the Civil Appeal filed by the Mumbai
            Municipal Corporation were dismissed.

       Godrej & Boyce II:
14. It would be useful to refer to another decision of this Court in the
    case of Godrej & Boyce II. In the said case, two questions arose
    for consideration in the context of grant of DRC for a total area of
    31,057.30 sq. metres, for the construction and development of the
    amenity namely, Recreation Ground. One of the questions considered
    was whether the High Court was right in concluding that there was
    an abandonment of claim by the appellants therein. Touching upon
    the facts of the case, this Court took note of the rejection of the
    claim by the Corporation vide communication dated 27.11.1998 for
    the grant of additional TDR made by application dated 17.04.1998;
    the resolution of the dispute of the said entity with the decision of
[2024] 9 S.C.R.                                                              865

               Kukreja Construction Company & Others v.
                     State of Maharashtra & Others

     this Court dated 06.02.2009 in Godrej & Boyce I (its own case);
     application being made for the grant of additional TDR on 03.11.2009
     being rejected and a fresh writ petition being filed in the year 2010.
     This Court considered the law of abandonment in the context of the
     contention raised by the Mumbai Municipal Corporation and it was
     observed in paragraphs 15 to 18 as under:
           “15. The law of abandonment is based upon the maxim
           invito beneficium non datur. It means that the law
           confers upon a man no rights or benefits which he
           does not desire. In P. Dasa Muni Reddy v. P. Appa Rao,
           this Court held that “abandonment of right is much more
           than mere waiver, acquiescence or laches…. Waiver is an
           intentional relinquishment of a known right or advantage,
           benefit, claim or privilege….”. In paragraph 13 of the said
           decision, this Court put the law pithily in the following words:
                “13…. There can be no waiver of a non-
                existent right. Similarly, one cannot waive
                that which is not one’s as a right at the time
                of waiver. …”
           16. Irrespective of whether the respondents concede
           or not, the Circular dated 09.04.1996 curtailed the
           rights of the owners to have additional TDR in certain
           circumstances. The Circular came under challenge before
           this Court and the decision of this Court in Godrej and
           Boyce Manufacturing Company Limited was delivered
           on 06.02.2009. As we have stated earlier, the decision in
           Godrej and Boyce Manufacturing Company Limited was
           in the case of the very appellant No. 1 herein though in
           respect of some other property.
           17. To put it differently, what was cited by the Municipal
           Corporation in their order of rejection dated 27.11.1998
           as an impediment for the grant of additional TDR was the
           subject matter of challenge in the first round. It was made
           by the very appellant No. 1 herein, though in respect of
           another property. If the said decision in the first round
           had gone against appellant No. 1 herein, the rejection
           of the claim of the appellants for additional TDR on the
           basis of “prevailing policy” would have become final and
           unquestionable.
866                                                             [2024] 9 S.C.R.

                        Digital Supreme Court Reports


            18. In other words, during the period from 1996 to 2009,
            the right to claim additional TDR was in suspended
            animation. Therefore, the appellants had to necessarily
            wait till the cloud over their right got cleared. To say
            that the wait of the appellants during the period of this
            cloudy weather, tantamount to abandonment, is clearly
            unjustified and unacceptable. Therefore, the finding
            recorded by the High Court on question No. 1 is not in
            tune with the law or the facts of the present case and
            hence question No.1 has to be answered in favour of
            the appellants herein.”
                                                       (underlining by us)
       14.1 The next question considered was whether the finding of fact
            arrived at by the High Court that the appellant therein did
            not and could not have developed the amenity, calls for any
            interference, especially in light of the statutory provisions and the
            facts of the case. The statutory provisions in Section 126(1)(b)
            were adverted to on the approach that the authorities ought to
            have in these matters and this Court observed as under:
            “21. As we have noted earlier, clauses (a), (b) and (c)
            were inserted by way of substitution in sub-section (1) of
            Section 126 under Maharashtra Act 10 of 1994 with effect
            from 25.03.1991.
            22. As per Section 126(1), whenever the Planning Authority
            or Development Authority finds after the publication of a
            draft Regional Plan or a Development Plan that any land
            is required or reserved for any of the public purposes
            mentioned in the plan, such authority may acquire the
            land for the said public purpose. This acquisition can be
            made by three different methods, indicated in clauses (a),
            (b) and (c). The methods of acquisition prescribed in
            clauses (a), (b) and (c) of sub-section (1) of Section 126,
            in simple terms are as follows:—
            (i)    The acquisition may be through an agreement entered
                   into with the owner, by paying an amount agreed to;
            (ii)   Alternatively, the acquisition may be by the grant of FSI
                   or TDR in lieu of any payment, along with Additional
[2024] 9 S.C.R.                                                          867

               Kukreja Construction Company & Others v.
                     State of Maharashtra & Others

                FSI or Additional TDR against the development or
                construction of the amenity on the surrendered land
                at the cost of the owner; or
           (iii) The acquisition may also be by requesting the
                 State Government to initiate the process of land
                 acquisition under the Right to Fair Compensation
                 and Transparency in Land Acquisition, Rehabilitation
                 and Resettlement Act, 2013.
           23. We are concerned in this case with the second
           method of acquisition of land indicated in clause (b) of
           sub-section (1) of Section 126. Under this clause, the
           owner and the planning authority are granted the leverage
           to agree that the compensation for the acquisition of the
           land will be for a consideration, not paid in the form of
           cash but granted in kind, in the form of two things, namely,
           (i) FSI or TDR for the area of land surrendered; and (ii)
           additional FSI or additional TDR against the development
           or construction of the amenity on the surrendered land.
           24. Once the parties are ad idem on the fact that the case
           is covered by clause (b), then what is necessary to be
           seen by Courts is : (i) whether the parties had agreed to
           give/take FSI or TDR in lieu of the amount of compensation?;
           and (ii) whether there was a valid claim for the grant of
           additional FSI or additional TDR towards the development
           or construction of the amenity on the surrendered land at
           the cost of the owner?.”
     14.2 This Court observed therein that there was no dispute on
          facts that the appellants therein had surrendered the land and
          accepted TDR in lieu of compensation. The only question was
          whether parties had satisfied the last limb of clause (b) which
          reads as under:
           “26. ……and also further additional Floor Space Index or
           Transferable Development Rights against the development
           or construction of the amenity on the surrendered land at
           his cost, as the Final Development Control Regulations
           prepared in this behalf provide,”
868                                                            [2024] 9 S.C.R.

                       Digital Supreme Court Reports


       14.3 It was observed that the owner of the land is under an obligation
            to develop or construct the amenity on the surrendered land at
            his cost and the Planning Authority has to reciprocate the same
            by granting additional FSI or additional TDR. While considering
            the said issue, both on facts as well as in law, this Court referred
            to the definition of the word “amenity” and “development” in
            Section 2(2) and 2(7) respectively of the Act and observed that
            the word “amenity” means several things including recreational
            grounds in respect of which the controversy arose in the said
            case. There was a dispute as to whether the appellant therein
            had not developed the recreational grounds. While considering
            the expression “development”, it was observed that the same
            was of wide import and in fact clause (b) of sub-section (1) of
            Section 126 of the Act has used both the expressions, namely
            (i) development; and (ii) construction. Therefore, the word
            “development” has to be understood to mean any activity which
            may or may not include construction. Therefore, the question in
            the said case was, whether, the appellant therein had developed
            or constructed any amenity which ought to be tested with
            reference to the final DCR. While referring to the definition of
            amenity in Regulation 2(7) which includes recreational grounds,
            reference was made to Regulation 34 and it was observed that
            Appendix-VII was later renumbered as Appendix-VII-A vide order
            dated 15.10.1997. It was observed that clauses (5), (6) and (7)
            of the Regulation 34 was the substratum of the controversy
            before the High Court.
       14.4 Going through the entire gamut of correspondence involved in
            the said case, it was held that all the activities undertaken by
            appellant No.1 therein through the Architects till handing over of
            the possession of the land were not towards the development
            of amenity and the grant of additional TDR. All these works
            were undertaken as part of the effort to make the Municipal
            Corporation accept the surrender of land and to grant TDR.
            On the facts of the said case, it was held that no amenity
            was developed as required by law by appellants Nos.1 and 2
            therein to be entitled to additional TDR. Therefore, on facts,
            it was held that appellant was not entitled for additional TDR.
            Accordingly, the view of the High Court was confirmed and the
            appeal was dismissed.
[2024] 9 S.C.R.                                                        869

               Kukreja Construction Company & Others v.
                     State of Maharashtra & Others

     Yeshwant Jagannath Vaity:
15. In Yeshwant Jagannath Vaity, the facts were that the respondents
    therein owned 10,000 sq. yards of land in Mulund village, which
    came within the area of Greater Bombay. A development plan was
    sanctioned for Greater Bombay in the year 1957. The said land was
    shown as reserved for public purpose of construction of a godown.
    However, the respondents and four other co-owners entered into a
    private agreement to handover possession of 10,000 sq. yards to
    the Municipal Corporation of Greater Bombay (MCGB) for temporary
    use as a truck terminal. The land was also to be used as a town
    duty office. The possession was handed over on 18.09.1961. The
    land was not put to any other use till November 1998. Therefore,
    Writ Petition No.3437 of 1988 was filed seeking a declaration
    that the land was not liable to be acquired which resulted into a
    compromise between the parties in which MCGB agreed to acquire
    and retain the area of 3500 sq. metres for the purpose of establishing
    and constructing an export octroi office. The respondents therein
    constructed the export office and also developed the surrounding
    area. The possession of the export office and the courtyard was
    handed over to the MCGB for which a possession receipt was also
    issued. An application was made by the respondents for TDR in
    respect of the export office being 3500 sq. metres equivalent of the
    100 per cent of the built-up area of the export office. However, insofar
    as the additional transferable rights in lieu of the development of
    the export courtyard surrounding the export office was concerned,
    the same was restricted to 466.96 sq. metres being 15 per cent of
    the built-up area of the courtyard.
     15.1 The respondents not having received a favourable response
          to their request filed a writ petition which was allowed by the
          High Court. The High Court while granting the relief relied upon
          the judgment of this Court in Godrej & Boyce I. In the appeal
          filed by the MCGB, several contentions were raised including
          the contention regarding the Circular dated 09.04.1996 having
          no bearing on Godrej & Boyce I, since it was issued after the
          landowners had surrendered their plot of land after construction
          of the roads as required by the Municipal Council while in the
          said case the said Circular was issued prior to the respondents
          No.1 and 3 therein completing the construction of an export
          office and asphalting of the courtyard and handing over the
870                                                        [2024] 9 S.C.R.

                      Digital Supreme Court Reports


            possession. Several arguments were advanced to distinguish
            the judgment of this Court in Godrej & Boyce I. This Court
            observed that the works done by the respondent therein was
            an amenity and the Circular dated 09.04.1996 did not have any
            bearing on the case as it was issued after the compromise in
            the Writ Petition on 10.03.1992 and the issuance of the letter
            of intent dated 22.02.1995. Accordingly, the appeal filed by the
            respondent MCGB was dismissed.
       15.2 The reasoning of this Court in the said judgment is squarely
            applicable to these cases. This Court held that the High Court
            was right in allowing the writ petition filed by the respondent
            therein and granting 100% TDR as against the development
            of the courtyard by asphalting the same.

       Delay and Laches:
16. However, most of the writ petitions which were filed by the appellants
    herein were dismissed on the ground of delay and laches by the
    Bombay High Court. We have already adverted to the judgment of
    this Court in Godrej & Boyce II on the aspect of abandonment of
    the claim. The contentions of learned senior counsel and learned
    counsel for the appellants would not call for a reiteration.
17. At this stage, we shall consider some of the judgments relied upon
    by the learned senior counsel for the respective parties.
       On the question of discretion of courts in considering the issue of
       delay and laches, this Court in Vidya Devi vs. State of Himachal
       Pradesh (2020) 2 SCC 569 (“Vidya Devi”) noted as under,
            “12.12. The contention advanced by the State of delay
            and laches of the appellant in moving the Court is also
            liable to be rejected. Delay and laches cannot be
            raised in a case of a continuing cause of action, or
            if the circumstances shock the judicial conscience of the
            Court. Condonation of delay is a matter of judicial
            discretion, which must be exercised judiciously and
            reasonably in the facts and circumstances of a case.
            It will depend upon the breach of fundamental rights, and
            the remedy claimed, and when and how the delay arose.
            There is no period of limitation prescribed for the
[2024] 9 S.C.R.                                                               871

                 Kukreja Construction Company & Others v.
                       State of Maharashtra & Others

           courts to exercise their constitutional jurisdiction to
           do substantial justice.”
                                                    (emphasis supplied)
     17.1 On the question of the principles the Court should rely upon
          when exercising the discretion to condone delay and laches,
          the following judgments are instructive.
           (a)    In Dehri Rohtas Light Rly. Co. Ltd. vs. District Board,
                  Bhojpur (1992) 2 SCC 598, this Court noted that:
                       “13... The principle on which the relief to the party
                       on the grounds of laches or delay is denied is
                       that the rights which have accrued to others by
                       reason of the delay in filing the petition should
                       not be allowed to be disturbed unless there is a
                       reasonable explanation for the delay. The real
                       test to determine delay in such cases is that
                       the petitioner should come to the writ court
                       before a parallel right is created and that the
                       lapse of time is not attributable to any laches
                       or negligence. The test is not as to physical
                       running of time. Where the circumstances
                       justifying the conduct exist, the illegality
                       which is manifest cannot be sustained on
                       the sole ground of laches.”
                                                    (emphasis supplied)
           (b)    In Tukaram Kana Joshi vs. Maharashtra Industrial
                  Development Corporation (2013) 1 SCC 353, this
                  Court held, albeit in the context of the State taking over
                  possession of land without any sanction of law, to the
                  following effect:
                       “12… Our Constitution is an organic and flexible
                       one. Delay and laches is adopted as a mode of
                       discretion to decline exercise of jurisdiction to
                       grant relief. There is another facet. The Court
                       is required to exercise judicial discretion. The
                       said discretion is dependent on facts and
                       circumstances of the cases. Delay and laches
872                                                           [2024] 9 S.C.R.

                       Digital Supreme Court Reports


                       is one of the facets to deny exercise of
                       discretion. It is not an absolute impediment.
                       There can be mitigating factors, continuity
                       of cause action, etc. That apart, if the whole
                       thing shocks the judicial conscience, then the
                       Court should exercise the discretion more so,
                       when no third-party interest is involved.”
                                                    (emphasis supplied)
            (c)   In Kazi Moinuddin Kazi Bashiroddin vs. Maharashtra
                  Tourism Development Corporation, 2022 SCC OnLine
                  SC 1325, at para 26, this Court noted that, in matters
                  relating to payment of amount of compensation to land
                  losers, if at all two views are possible, the view that
                  advances the cause of justice is always to be preferred
                  rather than the other view, which may draw its strength
                  only from technicalities.
       17.2 On the question of abandonment or waiver of rights, this Court
            in G.T. Lad vs. Chemical and Fibres of India Ltd. (1979) 1
            SCC 590 noted, albeit in the context of workmen abandoning
            service, that “to constitute abandonment, there must be total or
            complete giving up of duties so as to indicate an intention not
            to resume the same”. It further noted that such abandonment
            is always a question of intention.
       17.3 Further, in State of Punjab vs. Davinder Pal Singh Bhullar
            (2011) 14 SCC 770, this Court dealt with the doctrine of waiver.
            It held that, to constitute waiver, the person who is said to have
            waived, must have intentionally abandoned his rights with full
            knowledge after being fully informed of his rights.
18. In the following Writ Petitions by the impugned order dated 18.12.2018
    the Bombay High Court observed as follows and dismissed the Writ
    Petitions on the ground of delay and laches.

            “(i) WP No.1898 of 2009 –
                  Kukreja Construction and Others vs. The State
                  of Maharashtra and Others.
                  35. In Writ Petition No.1898/2009, the petitioners’ land
                  was reserved for 18.3 meters wide DP Road. The
[2024] 9 S.C.R.                                                             873

                  Kukreja Construction Company & Others v.
                        State of Maharashtra & Others

                   petitioners surrendered the reserved land and were
                   granted TDR in lieu of the reserved land. Thereafter,
                   the petitioners constructed DP Road as claimed in
                   the petition and a completion certificate was issued
                   on 19th August 1994. According to the case of the
                   petitioners, they carried out work of storm water drain
                   for which competition certificate was issued 17th March
                   2003. According to their case, the TDR in respect
                   of the land was issued on 16th March 1994 and 5th
                   April 2003. On 21st July 2003, the petitioners through
                   their Architect applied for grant of additional TDR
                   under clause (6) of Appendix-VII. But the application
                   made by the petitioner (Exhibit-I) shows that on 21st
                   July 2003, only 25% additional TDR was claimed in
                   respect of amenity of DP Road. It is not the case of
                   the petitioners that thereafter they followed the said
                   application by issuing reminders. For six years or
                   more, no claim was made for 100% TDR on account
                   of construction of the amenity. However, on 28th August
                   2009, through their Architect, the petitioners applied
                   for grant of additional TDR for the amenity equivalent
                   to 100% of the area. The said application was made
                   only after the decision of the Apex Court in the case
                   of Godrej & Boyce Manufacturing Co. Ltd. (supra)
                   and the present petition was lodged on 15th September
                   2009. Therefore, in facts of the case, no relief can be
                   granted as for a period of more than six years after
                   surrender, no claim was made for 100% TDR.

           (ii)    WP No.1823 of 2009 –
                   Jitendra Amritlal Sheth vs. State of Maharashtra
                   and Others.
                   37. Now, we come to Writ Petition No.1823/2012.
                   In this case, the possession of DP Road after its
                   construction was handed over by the petitioners to
                   the Municipal Corporation on 5th March 2005. On 24th
                   February 2009, the petitioners’ Architect for the first
                   time applied for 100% FSI in lieu of the constructed
                   amenity. There was inaction for more than 3 years and
874                                                     [2024] 9 S.C.R.

                Digital Supreme Court Reports


           11 months and claim for 100% additional TDR was not
           made. The averments made in the petition show that
           on 18th November 2009, a reminder was issued. By
           communication dated 7th December 2009, the proposal
           of the Architect was specifically rejected. The petition
           was affirmed on 30th July 2012 i.e. two years after the
           prayer for grant of 100% TDR was turned down. The
           explanation for delay given by way of amendment to
           the petition is that on 7th March 2010, a file containing
           correspondence and judgments of the Supreme Court
           was handed over to the attorneys. It is stated that
           amendment of 17th June 2010 to the DCR was made
           available to the petitioners in July 2010. On 8th January
           2011, the Legal Consultant of the fourth petitioner by
           writing an email enquired with the Solicitors whether
           draft was ready. On 25th January 2011, it is claimed
           that the draft was forwarded. Thereafter, on 18th July
           2011, a meeting was held between the petitioners,
           their Legal Consultant and Architect. It is claimed that
           the documents were furnished by the Architect to their
           advocate on 15th June 2012 and, ultimately, on 30th
           July 2012, the petition was filed. This is hardly an
           explanation for delay of 2½ years, especially when in
           the facts, of the case after construction of DP Road,
           the possession of the same was handed over on 5th
           March 2005. There is no explanation for not claiming
           100% TDR within three years from that date. Even
           after entrusting the case to the Advocate, there is a
           long delay. Hence, considering the gross delay and
           laches which is not at all explained, this is a case
           where a Writ Court should not allow the party to invoke
           its extra ordinary jurisdiction under Article 226 of the
           Constitution of India.

       (iii) WP No.839 of 2015 –
           Geeta alias Chandani Umesh Gandhi vs. The State
           of Maharashtra and others.
           38. In Writ Petition No.839/2015, the possession of DP
           Road was handed over to the Municipal Corporation
[2024] 9 S.C.R.                                                             875

               Kukreja Construction Company & Others v.
                     State of Maharashtra & Others

                on 20th May 2005. On 31st December 2006, 25% FSI/
                TDR in respect of the constructed road was granted.
                On 1st December 2009, the petitioner through her
                Architect requested to release balance 75% TDR
                towards the amenity developed. The perusal of the
                averments made in the petition shows that after
                lapse of 4½ years thereafter, by a letter dated 20th
                June 2014, the petitioner requested the Municipal
                Corporation to issue balance 75% TDR. Thereafter,
                there was a legal notice sent on 1 st December
                2014. The petition was filed one year thereafter in
                January 2015. There is absolutely no explanation
                as to why there is a complete inaction on the part
                of the petitioner from 1st December 2009 when the
                petitioner’s Architect applied for grant of remaining
                75% additional TDR till 20th June 2014 when similar
                request was made by the petitioner. As there is no
                explanation for this inaction for a period of more 4½
                years and the delay involved thereafter, this is not a fit
                case wherein a Writ Court should exercise jurisdiction
                under Article 226 of the Constitution of India.

           (iv) WP No.2871 of 2015 –
                Jameel A. Hussain and Others vs. State of
                Maharashtra and Others.
                39. In Writ Petition No.2871/2015, the reservation
                of the land claimed by the petitioners was for DP
                Road. The possession of the developed portion of the
                reserved land was taken over by the said Corporation
                on 29th July 2004. The completion certificate was
                issued on 23rd August 2014. It is claimed in the
                petition that FSI in respect of surrender of land was
                granted but FSI in respect of amenity constructed
                thereon was never granted. Going by the averments
                made in the petition, though the petitioners claim to
                have surrendered the reserved land with amenity
                on 29th July 2004, the petitioners never applied for
                grant of 100% TDR in respect of the amenity. Even
                after the decision of the Apex Court in the case of
876                                                        [2024] 9 S.C.R.

                  Digital Supreme Court Reports


             Godrej & Boyce Manufacturing Co. Ltd. (supra)
             which is of 6th February 2009, the petitioners did not
             apply for grant of additional FSI/ TDR in respect of
             amenity surrendered in the year 2004 and for the
             first time by a letter dated 17th February 2012, the
             petitioners applied for grant of additional TDR. The
             proposal for grant of additional TDR was rejected
             on 30th January 2015. Thereafter the petition was
             filed. Thus, after surrendering the reserved land on
             29th July 2004, the petitioners never claimed TDR
             in respect of the amenity developed by them till 17th
             February 2012. The application was made three years
             after the decision of the Apex Court in the case of
             Godrej & Boyce Manufacturing Co. Ltd. (supra).
             Considering this conduct of the petitioners which
             virtually amounts to abandonment of their right, no
             relief can be granted to the petitioners in this petition.

       (v)   WP No.2107 of 2016 –
             M/s Byramjee Jeejeebhoy Pvt. Ltd. and Another
             vs. The Municipal Corporation of Greater Mumbai
             and Others.–
             40. In Writ Petition No.2107/2016, according to the
             case of the petitioners, they constructed DP Road.
             They surrendered the reserved land on 5th June
             2007. Their Architects/ Licensed Surveyors made
             an application on 4th September 2009 for grant of
             100% additional TDR in the light of the decision of
             the Apex Court. A legal notice was issued by their
             advocate on 7th December 2009. Thereafter, the
             petitioners took no steps and after a gap of 6½ years
             on 21st July 2016, the petitioners called upon the
             said Corporation to grant additional FSI/TDR. The
             correspondence made by the petitioners in the year
             2009 was based on the decision of the Apex Court
             in the case of Godrej & Boyce Manufacturing Co.
             Ltd. (supra). The petitioners sought to rely upon
             the subsequent decision of the Apex Court dated
             5th May 2016 in the case of Municipal Corporation
[2024] 9 S.C.R.                                                           877

               Kukreja Construction Company & Others v.
                     State of Maharashtra & Others

                of Greater Mumbai v. Natvar Parikh & Co. Pvt. Ltd.
                (Civil Appeal No.1479/2015) which followed the
                decision of the Apex Court in the case of Godrej &
                Boyce Manufacturing Co. Ltd. (supra). There is no
                explanation offered in the petition as to why there was
                complete inaction on the part of the petitioners from
                2009 to 2016. Therefore, considering this conduct
                of the petitioners, they are dis-entitled to any relief.

           (vi) WP No.2170 of 2016 –
                Girdharlal D. Rughani Alia Thakkar H.U.F. and
                Another vs. The State of Maharashtra and Others.–
                41. In Writ Petition No.2170/2016, the case of the
                petitioners is that on 20th October 1995 they handed
                over the possession of their land reserved for DP
                Road to the said Corporation. They claimed that
                after completing the construction of DP Road on 20th
                October 1994, a completion certificate was granted
                by the Municipal Corporation. It is not the case of
                the petitioners that thereafter they applied for grant
                of additional 100% TDR in respect of the amenity
                developed. Only on 5th August 2014 (i.e. ten years after
                developing the amenity) that the petitioners applied
                for grant of additional TDR through their Architect. For
                a period of 10 years, the petitioners never claimed
                100% additional TDR in respect of the amenity. Even
                thereafter, no action is taken and the present petition
                is filed in July 2016. Considering the conduct of the
                petitioners, they are not entitled to any relief.

           (vii) WP No.384 of 2017 –
                Oberoi Realty Limited and Another vs. Municipal
                Corporation of Greater Mumbai and Others.–
                42. In Writ Petition No.384/2017, the case of the
                petitioners is that between 2004 and 2008, they
                developed seven DP Roads and handed over the
                possession thereof to the said Corporation. However,
                they made representation for the first time on 10th June
878                                                   [2024] 9 S.C.R.

                Digital Supreme Court Reports


           2016 claiming additional TDR in respect of amenity
           developed. The representation was rejected on 30th
           November 2016 by the said Corporation. Thus, even
           after the decision in the case of Godrej & Boyce
           Manufacturing Co. Ltd. (supra), the petitioners did
           not apply for grant of additional TDR. The petitioners
           sought additional TDR after lapse of eight years and
           more. Therefore, for a period of eight years or more,
           the petitioners never claimed additional TDR. Hence,
           considering the delay and laches on the part of the
           petitioners, no relief can be granted.

       (viii) WP No.541 of 2017 –
           Nanabhoy Jeejeebhoy Pvt. Ltd. and Another vs.
           The State of Maharashtra and Others. –
           43. In Writ Petition No.541/2017, the case of the
           petitioners is that there were eleven reservations on
           their property for DP Roads. The petitioners have
           referred to the said reservations as DP Road-I to DP
           Road-XI. According to the case of the petitioners,
           after developing the amenities, the possession of DP
           Roads was handed over to the said Corporation on
           13th April 2004, 20th March 2001, 27th March 2002, 6th
           September 2001, 13th February 2006, 27th October
           1997, 27th October 1997, 29th October 1997, 21st
           December 2002, 22nd May 2002 and 14th August
           2002 respectively. For the first time additional TDR
           was claimed by the petitioners by making application
           on 11th July 2014. Thus, in all cases except one, the
           possession was handed over after the development
           of DP Roads before the year 2003. In some cases,
           the possession of DP Road was handed over in the
           year 1997. In one case, the possession was handed
           over in the year 2006. Thus, after lapse of several
           years after handing over possession of DP Roads
           i.e. in 2014, belatedly a request was made for grant
           of additional TDR. The request was made after a
           gap of about 8 to 13 years for which there is no
           explanation. Thus, the petitioners by their conduct
[2024] 9 S.C.R.                                                        879

               Kukreja Construction Company & Others v.
                     State of Maharashtra & Others

                have virtually abandoned their claim for additional
                FSI/TDR in respect of amenity.”
     In all these cases, we find that the writ petitioners/appellants herein
     had surrendered the reserved land and had also been granted 25%
     TDR and a representation for additional TDR was made after the
     judgment of this Court in Godrej & Boyce I and in some cases, the
     representation was made early but in other cases, the representations
     were made after some time. It is also noted in Civil Appeal No.1748
     of 2015, in the case of Natwar Parikh, this Court had stated that
     the decision in Godrej & Boyce I could not be revisited inasmuch
     as the Mumbai Municipal Corporation could not seek to reargue the
     matter. Also, the facts in each case on the questions of delay was to
     be considered as observed by this Court. The issue of abandonment
     of claim has also been considered and negatived in the judgment
     of this Court in Godrej & Boyce II.
     We have referred to the decisions of this Court where the question
     of delay and laches would not arise in matters such as the present
     cases. When relief in the nature of compensation is sought, as in
     the instant case, once the compensation is determined in the form
     of FSI/TDR, the same is payable even in the absence of there being
     any representation or request being made. In fact, a duty is cast on
     the State to pay compensation to the land losers as otherwise there
     would be a breach of Article 300-A of the Constitution. As rightly
     contended by the learned senior counsel for the writ petitioners/
     appellants herein, the respondent-Mumbai Municipal Corporation has
     not established that owing to a short delay even if it has occurred in
     any of these cases owing to uncertainty in law, the Corporation has
     been prejudiced by the same or that the third-party rights had been
     created which could not be disturbed owing to delay or laches. The
     calculation of period of delay in the table submitted by learned senior
     counsel for the Mumbai Municipal Corporation is not acceptable in
     view of our discussion above. The decisions referred to by us above
     would clearly indicate that neither the doctrine of delay and laches
     nor the principle of abandonment of claim or waiver would apply
     in these cases. Rather the delay has occurred on the part of the
     Mumbai Municipal Corporation in complying with the Regulations
     insofar as these appellants are concerned.
     18.1 In view of the aforesaid discussion, we hold that the Bombay
          High Court was not right in dismissing the writ petitions on
880                                                           [2024] 9 S.C.R.

                          Digital Supreme Court Reports


               the ground of delay and laches. Hence, those portions of the
               impugned order of the High Court are set aside.
19. We also do not find any merit in the three appeals filed by the Mumbai
    Municipal Corporation. Having regard to the earlier judgments of this
    Court, we find that the reasoning of the High Court on merits in the
    three impugned decisions discussed above is just and proper which
    would not call for any interference by this Court.
20. Consequently, the civil appeals filed by the writ petitioners/appellants
    herein are allowed as under:
       (i)     Those portions of the impugned order dated 18.12.2018 by
               which the writ petitions were dismissed on the ground of
               delay and laches are set aside and the respondent Mumbai
               Municipal Corporation is directed to consider the case of those
               writ petitioners/appellants herein in light of the judgments of
               this Court in Godrej & Boyce I and release the balance FSI/
               TDR to the appellants.
       (ii)    However, in the case of appellant-Kukreja Construction company
               and others, the Mumbai Municipal Corporation is directed to
               consider the nature of the amenities constructed and thereafter
               to consider their case for additional FSI/TDR.
       (iii) The said exercise shall be carried out as expeditiously as
             possible and within a period of three months from today.
       20.1 The Civil Appeals filed by the Mumbai Municipal Corporation
            are dismissed and the cases of the respondents in those civil
            appeals shall be considered in terms of the judgments of this
            Court in Godrej & Boyce I and the balance FSI/TDR shall be
            released to the respondents therein within a period of three
            months from today.
       Parties to bear their respective costs.

       Result of the Case: A
                            ppeals filed by the appellants are allowed and
                           those of the Mumbai Municipal Corporation are
                           dismissed.



       †
           Headnotes prepared by: Divya Pandey


Search Indian case law

Ask in plain English, not just keywords. 25,000 AI words free, no card.

Try "Acquisition of land for public purposes"Sign in to search

For a digitally signed copy suitable for filing, refer to the court's own website. Only the court can issue one.

KUKREJA CONSTRUCTION COMPANY & OTHERS versus STATE OF MAHARASHTRA & OTHERS — 2024 INSC 692 - Legal Desk AI