LARSEN AND TOUBRO LTD.versusFERTILIZER AND CHEMICALS TRAVANCORE LTD.
- Citation
- 2007 INSC 1140
- Decided
- 12 November 2007
- Disposal
- Dismissed
- Bench
- ARIJIT PASAYAT
Holding
The arbitration proceedings are governed by the Standard Conditions, and the Managing Director may act as arbitrator; the Special Conditions do not supersede the Standard Conditions.
Summary
Larsen & Toubro Ltd entered into a purchase order with Fertilizer and Chemicals Travancore Ltd that contained both Standard Conditions and Special Conditions. A dispute arose over the arbitration clause: the appellant sought an independent sole arbitrator under the Special Conditions, while the respondent insisted that, per Article 26 of the Standard Conditions, its Managing Director was the designated arbitrator. The Kerala High Court rejected the appellant's arbitration request, prompting a writ petition and subsequent appeals to the Supreme Court. The Supreme Court held that the arbitration provisions in the Standard Conditions governed the contract, and that the Special Conditions merely amended the applicable arbitration law, venue, and language without superseding the Standard Conditions. It further ruled that the Managing Director could validly act as arbitrator and that no reasonable apprehension of bias existed. Consequently, the appeals were dismissed.
Issues considered
- Whether the arbitration clause in the contract is governed by the Standard Conditions or the Special Conditions.
- Whether the Managing Director of the respondent can be considered an independent arbitrator.
- Whether the amendment in the Special Conditions supersedes the arbitration provisions of the Standard Conditions.
Legislation cited
Subjects
Judgment
LARSEN AND TOUBRO LTD. A
V.
FERTILIZER AND CHEMICALS TRAVANCORE LTD.
NOVEMBER 12, 2007
B
[DR. ARIJIT PASAYAT AND LOKESHWAR
SINGHPANTA,JJ.)
Arbitration-Contract entered between Appellant and
Respondent-Contained two different set ofconditions viz. 'Standard C
Conditions 'and 'Special Conditions '--Dispute between Appellant and
Respondent-Arbitration proceedings sought to be initiated-
Disagreement between parties over the governing provisions-Held:
Arbitration proceedings to be governed by the 'Standard Conditions'
and not 'Special Conditions' as contended by Appellant- 'Special D
Conditions' themselves showed that the 'Standard Conditions'
contained provisions for arbitration.
Appellant and Respondent had entered into a contract vide a
purchase order. The purchase order contained two different set of
terms and conditions viz. 'Standard Conditions' and 'Special E
Conditions'.
Disputes having arisen between the parties, Appellant invoked
the 'Special Conditions' and suggested three names to Respondent
for appointment of an independent sole arbitrator. Respondent took F
the stand that in view ofArticle 26 of the 'Standard Conditions', only
the Managing Director of Respondent could be appointed as a
named arbitrator and accordingly declined to appoint a sole
independent arbitrator.
In appeals to this Court it was contended by the Appellants that G
the Managing Director of Respondent cannot be treated as an
independent arbitrator and arbitration proceedings between the
parties was to be governed by the 'Special Conditions' and not the
'Standard Conditions'.
1085 H
1086 SUPREME COURT REPORTS [2007] 11 S.C.R.
A Dismissing the appeals, the Court
HELD: 1.1. The stand of the Appellant that the special
conditions of the work order superseded the standard terms and
conditions, is not correct. The apprehension that named arbitrator
B may not act fairly is without any foundation.
[Paras 8 and 11) (1090-E; 1092-CJ ';-
1.2. The special conditions themselves show that articles 25 and
26 of the Standard terms and conditions contained provisions for
arbitration. [Para 12) [1092-F)
c 1.3 ..BY Article 16 of the special terms and conditions of
purchase there. was an amendment to Article 25 of the Standard
terms and conditions. Similar was the amendment to Article 26 of
·the Standard terms and Conditions for erection and commissioning
in Article 16 of the Special Conditions ofwork attached to the work
D
order. The amendments incorporated by the Special conditions only
provide that the provisions of the relevant Arbitration Act and the
rules made thereunder and any statutory modifications thereof for
the time being in force will be applicable and the venue of arbitration
and language of the proceedings.
E [Paras 11and12) (1092-C, D, E, F, G)
· Secretary to Government, Transport Deptt., Madras v.
Munuswanty Mudliar and Anr., [1988) Suppl. SCC 651, referred to.
CIVIL APPELLATE JURISDICTION: Civil Appeal No. 5159 of
F 2007.
From the final Judgment and Order dated 18.12.1999 of the High
Court ofKerala at Emakulam in A.R. No. 29of1999.
WITH
G
C.A. No. 5160 of 2007
V.A. Mohta, Nilkanta Nayak, Shweta Bharti, Aditi Mohan, Neelam
and Niranjana Singh for the Appellant.
C.N. Sree Kumar for the Respondent.
H
LARSEN AND TOUBRO LTD. v. FERTILIZER AND 1087
CHEMICALSTRAVANCORELTD.[PASAYAT,J.]
The Judgment of the Court was delivered by A
DR. ARIJIT PASAYAT, J. 1. Leave granted.
2. Challenge in these appeals is to the order passed by the learned
Single Judge of the Kerala High Court disposing of arbitration request
filed before him. B
3. Background facts in a nutshell are as follows:-
Appellant and the respondent entered into a contract vide purchase
orderno.3020/02-2701/016/1018 dated 7.1.1995. Alleging that in breach
of the terms and conditions of the purchase order certain amounts were c
withheld, the appellant invoked the arbitration agreement purportedly in
terms of new Article 26 of the Special Conditions and suggested thre~
names for appointment of an independent sole arbitrator and called upon
the respondent to name one out of the three names. The respondent took,
the stand that it is only the Managing Director of the respondent who can D
be appointed as a named arbitrator as per Article 26 of the Standard
Conditions and refused to appoint a sole independent arbitrator. The High
Court of Kerala was moved seeking appointment of an arbitrator by
Arbitration Request 29/99. Learned Single Judge declined the arbitration
request on the ground that terms and conditions of the purchase order
provides for arbitration by the Chairman and Managing Director of the E
respondent. A writ petition was filed under Article 226 of the Constitution
oflndia, 1950 (in short the 'Constitution'). During pendency of the said
writ petition this Court in CA Nos. 3777, 4168 and 4169 of2003 held
that the order passed under Section 11 of the Arbitration and Conciliation
Act, 1996 (in short the 'Act') is a judicial order and writ petition challenging F
the said order under Article 226 of the Constitution is not maintainable.
Therefore, this appeal has been filed.
4. In support of the appeals, learned counsel for the appellant
submitted that the provision contained in Article 26 of the Standard G
Conditions is not the actual provision for arbitration. The same is contained
in the special te1ms and conditions attached to the purchase order and
the work order respectively. The purchase order and the work order
contained special conditions, standard terms and conditions. By Article
16 of the Special terms and Conditions of the purchase, there is
H
1088 SUPREME COURT REPORTS [2007] 11 S.C.R.
A amendment to the article 25 of the standard conditions. There is similar
amendment to article 26 of the standard terms so far as it related to
commissioning. The provisions contained in the standard conditions in both
the cases, it was submitted by learned counsel for the appellant, is not
actual provision for arbitration. The general condition stated that all
B disputes and differences are required to he referred to the Chairman and
Managing Director of the respondent-:company for his decision and it will
be binding on the parties. It was further contended that the provisions
contained in the special conditions by themselves do not have any
provision for arbitration. It does not have any clause that disputes and
C difference shall be settled by arbitration. In both the cases, the special
conditions specifically state that it is by way of amendment of general
condition only and not in supersession of that provision. The Chairman
and the Managing Director of the respondent-company cannot be treated
as independent person to be appointed as arbitrator. This was essentially
the stand which did not find acceptance. It is submitted by learned counsel
D for the appellant that certain changes were suggested by the respondent.
5. Learned counsel for the respondent on the other hand submitted
that the High Court view is unexceptionable.
6. At this juncture it would be necessary to take note of the few
E conditions :
Clause 16 of the Work Order reads as follows:-
"16. Work Order Conditions:
F The order shall be governed by the above conditions as well as
by the conditions stipulated in Attachment I, II and III of this Work
Order, except the following:
The order shall be governed by the present special conditions
of work (W.O. Attachment Ill) as well as by the conditions
G stipulated in Attachment I, and II of this Work Order, except
the following:
Spec. No.3020/CS/04: Standard Terms and Conditions of Erection
& Commissioning.
H Art. 4.0.0 Taxes, Duties and Levies (comment)
I
1
LARSEN AND TOUBRO LTD. v. FERTILIZERAND 1089
~
CHEMICALSTRAVANCORELTD.[PASAYAT,J.]
I
Taxes shall be as per Article 4.0.0. However, at present conditions; A
tax on this Work Order is not applicable.
Art. 13.0.0 Termination (comment)
FACT can terminate the Work Order without giving any reason
provided that reasonable cost for termination and actual out-of- B
+ pocket expenses will be reimbursed.
Art. 15.0.0 Changes (Amendment)
FACT shall issue amendment orders which provide for changes in
the scope of work required by FACT under the Work Order, and c
for equitable adjustment in the price and delivery/completion time,
if any, hereunder.
Art. 21.0.0 Tests on Completion & Taking Over (New Article
Added).
D
Art. 21.5.0 (New Article)
The Primary Reformer Package under the scope of this Work
Order shall be deemed to be taken over by FACT immediately
after satisfactory pre-commissioning is over within 10 days of
Contractor's notice to Owner for commencement of commissioning E
after pre-commissioning, whichever is earlier. In case taking over
is delayed due to no fault of Contractor, after the notice given by
Contractor in this regard about the Completion, the entire Primary
Reformer Package is deemed to be taken over by FACT.
Art. 24.0.0 Indemnification F
Secondary liability such as indemnification for loss caused by
stoppage of plant of like will be excluded from Contractor's
liabilities under the Work Order.
Art. 26.0.0 Applicable Law and Settlement of Disputes G
-( (an1endment)
The provisions of the Indian Arbitration Act, 1940 and the rules
there under, any statutory, modifications there for the time being in
force will be applied.
H
+-
\
1090 SUPREME COURT REPORTS [2007] 11 S.C.R.
A The venue for the arbitration shall be Cochin, and the language of
the proceedings shall be the English language.
During the arbitration proceedings, both parties shall continue to
discharge their obligations under the Work Order."
B 7. There was addition and not substitution of condition. Without
amendment there was arbitration clause and if there was no amendment
the only substitution, then that there was no arbitration clause. In the
arbitration request in the statement of facts it has been clearly stated that
article 26 of the standard terms and conditions of purchase form part of
c the work order. The same read as follows:
"Article 26: Work Order shall be subject to and shall in all respects
be governed by Indian law. Any dispute or difference connected
with or arising out of WORK ORDER which cannot be settled
by mutual agreement of the parties shall be referred to the
D Chairman & Managing Director offACT, and his decision will be
binding on the parties. Any legal proceeding relating to this WORK
ORDER shall be limited to Courts oflaw under the jurisdiction of
the Kerala High Court at Emakulam District, Kerala State, India."
E 8. The stand of the learned counsel for the appellant that the special
conditions of the work order superseded the standard terms and
conditions, is not correct. The mere fact that the arbitrator was named
does not render the arbitration proceedings invalid.
9. In Secretary to Government, Transport Deptt., Madras v.
F Munuswamy Mudliar and Anr., [1988] Suppl. SCC 651 it was noted
as follow:
"7. Pursuant to this the Superintending Engineer of that Circle, at
the relevant time, was previously appointed as arbitrator. There was
succession to that office by another incumbent and the succeeding
G Superintending Engineer wanted to continue the arbitration
proceedings but before that an application was made under
Section 5 of the Arbitration Act, 1940 (hereinafter called 'the Act')
for removal of the arbitrator, before the learned Judge of the City
Civil Court, Madras."
H
I
j
LARSEN AND TOUBRO LTD. v. FERTILIZER AND 1091
CHEMICALSTRAVANCORELTD. [PASAYAT,J.]
10. Again in paras ll to 13 it was noted as follows: A
"11. This is a case of removal of a named arbitrator under Section
5 of the Act which gives jurisdiction to the court to revoke the
authority of the arbitrator. When the parties entered into the
contract, the parties knew the terms of the contract including
+ arbitration clause. The parties knew the scheme and the fact that B
the Chief Engineer is superior and the Superintending Engineer is
subordinate to the Chief Engineer of the particular Circle. In spite
of that the parties agreed and entered into arbitration and indeed
submitted to the jurisdiction of the Superintending Engineer at that
time to begin with, who, however, could not complete the arbitration c
because he was transferred and succeeded by a successor. In those
circumstances on the facts stated no bias can reasonably be
apprehended and made a ground for removal of a named arbitrator.
In our opinion this cannot be, at all, a good or valid legal ground.
Unless there is allegation against the named arbitrator either against D
his honesty or capacity or ma/a fide or interest in the subject matter
or reasonable apprehension of the bias, a named and agreed
arbitrator cannot and should not be removed in exercise of a
discretion vested in the Court under Section 5 of the Act.
12. Reasonable apprehension of bias in the mind of a reasonable E
man can be a ground for removal of the arbitrator. A predisposition
to decide for or against one party, without proper regard to the
true merits of the dispute is bias. There must be reasonable
apprehension of that predisposition. The reasonable apprehension
must be based on cogent materials. See the observations of Mustill F
and Boyd, Commercial Arbitration, 1982 edn., page 214.
Halsbury's Laws of England, 4th edn., Volume 2, para 551, page
282 describe that the test for bias is whether a reasonable intelligent
man, fully apprised of all the circumstances, would feel a serious
apprehension of bias. G
......,
13. This Court in International Authority ofIndia v. K D. Bali,
[1988] 2 sec 360 held that there must be reasonable evidence
to satisfy that there was a real likelihood of bias. Vague suspicions
of whimsical, capricious and unreasonable people should not be
made the standard to regulate normal human conduct. In this H
+-
'
1092 SUPREME COURT REPORTS [2007] 11 S.C.R.
A country in numerous contracts with the government, clauses
requiring the Superintending Engineer or some official of the
Government to be the arbitrator are there. It cannot be said that
the Superintending Engineer, as such cannot be entrusted with the
work of arbitration arid that an apprehension, simpliciter in the
mind of the contractor without any tangible ground, would be a
B
justification for removal. No other ground for the alleged
+
apprehension was indicated in the pleadings before the learned
Judge or the decision of the learned Judge. There was, in our
opinion, no ground for removal of the arbitrator. Mere imagination
of a ground cannot be an excuse for apprehending bias in the mind
c of the chosen arbitrator."
11. The apprehension that named arbitrator may not act fairly is
without any foundation. The High Court has rightly held that by article
16 of the ·special terms and conditions of purchase there was an
D amendment to article 25 which reads as follows:-
"The provisions of the Indian Arbitration Act, 1940, and the rules
thereunder, any statutory modifications thereof of the time being
in force will be applied. The venue of the arbitration shall be
Cochin, and the language of the proceedings shall be the English
E Language. During the arbitration proceedings, both parties shall
continue to discharge their obligations under the Purchase Order."
12. Similar was the amendment to Article 26 of the Standard terms
and Conditions for erection and commissioning in Article 16 of the Special
Conditions of work attached to the work order. The special conditions
F themselves show that articles 25 and 26 contained provisions for
arbitration. The amendments incorporated by the Special conditions only
provide that the provisions of the relevant Arbitration Act and the rules
made thereunder and any statutory modifications thereof for the time being .
in force will be applicable and the venue of arbitration and language of
G the proceedings.
)-
13. The appeals are sans me1it, deserve dismissal, which we direct.
B.B.B. Appeals dismissed.
..,
Search Indian case law
Ask in plain English, not just keywords. 25,000 AI words free, no card.