LEELA HOTELS LTD.versusHOUSING & URBAN DEVELOPMENT CORPORATION LTD.
- Citation
- 2011 INSC 800
- Decided
- 15 November 2011
- Disposal
- Appeal(s) allowed
- Bench
- ALTAMAS KABIR
Holding
In the absence of any agreement, a creditor may appropriate a payment received under an arbitral award first towards interest and thereafter towards principal.
Summary
Leela Hotels Ltd. entered into a sub‑lease with HUDCO for a hotel project, which was later cancelled, leading to arbitration. The arbitrator awarded HUDCO to pay Leela Hotels a principal sum plus interest. HUDCO deposited Rs 89.78 crores, claiming it was towards the principal, while Leela Hotels argued it should first be applied to interest. The Supreme Court held that, absent any agreement on allocation, the creditor is entitled to appropriate payments first against interest and then principal, rejecting HUDCO's unilateral stipulation. It also clarified that an arbitral award is enforceable as a decree under Section 36 of the Arbitration and Conciliation Act, 1996. Consequently, the appeal was allowed, restoring the Single Judge’s order and setting aside the Division Bench’s decision.
Issues considered
- The appropriate appropriation of a payment made by a judgment‑debtor under an arbitral award – whether it should first be applied to interest or to principal.
- Whether Section 59 and 60 of the Indian Contract Act, 1872, apply to the allocation of such payment.
- Whether an arbitral award under the Arbitration and Conciliation Act, 1996, is to be treated as a decree for purposes of enforcement under the Code of Civil Procedure.
Legislation cited
Subjects
Judgment
[2011] 13 (ADDL.) S.C.R. 156
A LEELA HOTELS LTD.
v.
HOUSING & URBAN DEVELOPMENT CORPORATION
LTD.
(Civil Appeal No. 9763 of 2011)
B NOVEMBER 15, 2011
[ALTAMAS KABIR, CYRIAC JOSEPH AND SURINDER
SINGH NIJJAR, JJ.]
C ARBITRATION:
Award - Principal and interest payable under award -
Appropriation of by creditor - Debtor depositing Rs. 89. 78
crores with the assertion that it represented the net principal
amount due and payable to the credit9r - According to the
D calculation sheets of the creditor, the said sum deposited was
appropriated towards the interest due under the award - Held:
Admittedly, there was no agreement between the parties as
to how the amounts to be paid in terms of the award were to
be appropriated by the creditor - Accordingly, in terms of the
E we// settled principle that in such cases it was for the creditor
to appropriate such payment firstly against the interest
payable, would be squarely attracted to the facts of the case
- The deposit made by the debtor with the assertion that it
was towards the principal amount, was accepted by the creditor
F without prejudice to its rights and contentions in the
proceedings - Accordingly, the creditor cannot be denied its
dues on a unilateral stipulation that the amount of Rs. 89. 78
crores was being deposited as against the principal sum due
in terms of the award - Since the said amount was accepted
G by the creditor on protest, it would be entitled to appropriate
the same against the interest which was due and payable till
that date on the principal amount, as has been asserted by it
- Section 59 of the Contract Act was not attracted in the case
- Contract Act, 1872 - ss. 59 and 60.
H 156
LEELA HOTELS LTD. v. HOUSING & URBAN 157
DEVELOPMENT CORP. LTD.
Arbitration and Conciliation Act, 1996: A
s. 36 - Award of arbitrator - Enforcement of - HELD:
Such an award has to be enforced under the Code of Civil
Procedure in the same manner as it were a decree of the
court.
B
Consequent upon cancellation of a lease agreement
for construction of a Five-Star Hotel, the dispute between
the parties was referred to the arbitrator, who allowed the
claims of the appellant and rejected the counter-claim
made by the respondent-HUDCO. The arbitrator held that C
the appellant was entitled to recover and HUDCO was
obliged to pay, inter alia, the amounts received by it from
the appellant along with 20% interest thereon for the
period the amount(s) remained with HUDCO till the date
of the Award. HUDCO filed its objections uls 34 of the D
Arbitration and Conciliation Act, 1996, which was
dismissed by the Single Judge of the High Court on 20-
1-2003. Before the said petition was dismissed, HUDCO
undertook to deposit the principal sum awarded by the
arbitrator on or before 21.10.2002. Such deposit (Rs. E
89,78,84,930/) was allowed to be made without prejudice
to the rights and contentions of HUDCO in the
proceedings before the High Court. Subsequently, by
order dated 21.10.2002, the said position was reiterated
and it was recorded that the deposit made by HUDCO F
would be without prejudice to the rights and contentions
of the parties in the pending proceedings. The first
appeal from the order dated 20-1-2003, having been
dismissed by the Single Judge of the High Court on 9-
11-2004, the respondent filed a special leave petition G
before the Supreme Court, which was dismissed on 12-
2-2008, but the rate of interest was reduced from 20% to
18%. Meanwhile HUDCO had also paid a sum of Rs.59.61
crores to the appellant on 23-3-2006. It paid a further sum
of Rs.48.09 crores on 16.4.2008. With these payments, H
158 SUPREME COURT REPORTS (2011] 13 (ADDL.) S.C.R.
A according to HUDCO, the award was satisfied.
In the execution petition, the case of the appellant ..
was that the sum of Rs.89,78,84,930/- deposited by
HUDCO was appropriated towards the interest due under
B the award; whereas the stand of the respondent-HUDCO
was that the said amount should be appropriated
towards the principal sum payable to the appellant under
the award. The Single Judge of the High Court directed
the payment to the appellant as per its calculations.
C However, the Division Bench of the High Court held that
the said amount deposited by HUDCO would be
appropriated towards the principal amount due and not
towards the interest; and set aside the order of the Single
Judge.
D In the instant appeal, the question for consideration
before the Court was: whether the amount/ deposited
and/or paid by the respondent to the appellant in terms
of the Award of the Arbitrator, was first to be appropriated
towards payment of the interest due on the principal sum
E or whether the same was to be appropriated against the
principal sum itself.
Allowing the appeal, the Court
HELD: 1.1 Admittedly, there was no agreement
F between the parties as to how the amounts to be paid in
terms of the Award were to be appropriated by the
appellant. Accordingly, the well settled principle that in
such cases it was for the creditor to appropriate such
payment firstly against the interest payable, would be
G squarely attracted to the facts of this case. [para 26) [173-
H; 174-A·B]
1.2 In the instant case, a unilateral assertion had been
made by HUDCO as the debtor that the sum of Rs.89.78
H crores was being tendered as payment towards the
LEELA HOTELS LTD. v. HOUSING & URBAN 159
DEVELOPMENT CORP. LTD.
principal amount and that there was, therefore, no other A
amount/ due and payable to the creditor-appellant; but
the amount as deposited was accepted by the appellant
without prejudice to its rights and contentions in the
appeal. [para 27] [174-F-H]
B
1.3 The philosophy behind the principle set out in
Meka Venkatadri's case and as reiterated in Rai Bahadur
Seth Nemichand's case and also in Smithaben's case and
then consistently followed by this Court, is that a debtor
cannot be allowed to take advantage of his default to C
deny to the creditor the amount to which he would be
entitled on account of such default, by way of elimination
of the principal amount due itself, unless, of course, the
provisions of s.59 of the Contract Act, 1872, were
attracted or there was a separate agreement between the
parties in that regard. That is not so in the instant case D
and, accordingly, the creditor cannot be denied its dues
on a unilateral stipulation that the amount of Rs.89.78
crores was being deposited as against the principal sum
due in terms of the Award. Since the said amount was
accepted by the appellant on protest, it would be entitled E
to appropriate the same against the interest which was
due and payable till that date on the principal amount, as
has been asserted by it. [para 28] [175-A-D]
Mis l.C.D.S. Ltd. Vs. Smithaben H. Patel & Ors., (1999) F
3 SCC 80; Meghraj Vs. Mst. Bayabai & others, 1970 (1) SCR
523 =AIR 1970 SC 161- relied on.
Meka Venkatadri Appa Rao Bahadur Zamindar Garu &
Ors. Vs. Raja Parthasarathy Appa Rao Bahadur Zamindar G
Garu, AIR 1922 PC 233; and Rai Bahadur Seth Nemichand
Vs. Seth Radha Kishen, AIR 1922 PC 26 - referred to.
1.4 The Division Bench of the High Court erred in
presuming that the said amount had been accepted by
H
160 SUPREME COURT REPORTS [2011] 13 (ADDL.) S.C.R.
A the appellant on account of good business sense in view
of the uncertainty of the final outcome of the case. The
Division Bench of the High Court should have proceeded
on the basis of the principles of law as laid down by this
Court in Smithaben's case, keeping in mind the earlier
8 decisions of the Privy Council in both Meka Venkatadri's
case and Rai Bahadur Seth Nemichand's case in
interfering with the judgment of the Single Judge. The
Division Bench seems to have erroneously taken the
presence of the counsel for the appellant, when the said
C undertaking of the respondent was recorded, in coming
to the conclusion that since no objection had been raised
with regard to the said deposit, it must be presumed that
it had the consent of the appellant and, therefore, was
covered by the provisions of ss. 59 and 60 of the
Contract Act. [para 29) [175-E-H]
0
2. Regarding the question as to whether the Award
of the Arbitrator tantamounts to a decree or not, the
language used in s.36 of the Arbitration and Conciliation
Act, 1996, makes it very clear that such an Award has to
E be enforced under the Code of Civil Procedure in the
same manner as it were a decree of the court. The said
language leaves no room for doubt as to the manner in
which the Award of the Arbitrator was to be accepted.
[para 30) [176-A-B]
F
3. The judgment and order of the Division Bench of
the High Court is set aside and that of the Single Judge
restored. [para 31] [176-C]
NALCO Vs. Prestee/ & Fabrication Pvt. Ltd., (2004) 1
G SCC 540; Paramjeet Singh Patheja Vs. /CDS Ltd., 2006
=
Suppl. (8) SCR 178 (2006) 13 SCC 322; Morgan
Securities and Credit Pvt. Ltd. Vs. Modi Rubber Ltd., 2006
=
Suppl. (10) SCR 1022 (2006) 12 SCC 642; West Bengal
Essential Commodities Supply Corporation Vs. Swadesh
H
LEELA HOTELS LTD. v. HOUSING & URBAN 161
DEVELOPMENT CORP. LTD.
Agro Farming & Storage Pvt. Ltd. & Anr., 1999 Suppl. A
(2) SCR 399 =(1999) 8 sec 315 - cited.
Case Law Reference:
1970 (1) SCR 523 relied on para 8
B
2004 (1) sec 540 cited para 20
2006 Suppl. (8) SCR 178 cited para 20
2006 Suppl. (10) SCR 1022 cited para 20
1999 Suppl. (2) SCR 399 cited para 20 c
AIR 1922 PC 26 relied on para 20
AIR 1922 PC 233 relied on para 26
CIVIL APPELLATE JURISDICTION : Civil Appeal No. D
9763 of 2011.
From the Judgment & Order dated 20.07.2009 of the High
Court of Delhi at New Delhi in EFA (OS) No. 4 of 2009.
Ashok Desai, Mukul Rohtagi, Abhimanyu Mahajan, Rahul E
Pratap, "Coac" for the Appellant.
Parag P. Tripathi, ASG Shadan Farasat. Sanjay Kumar,
Ayush Agrawal (for Suresh A. Shroff & Co.) for the Respondent.
The Judgment of the Court was delivered by F
ALTAMAS KABIR, J. 1. Leave granted.
2. This Appeal has been filed by Leela Hotels Ltd. against
the judgment and order dated 20th July, 2009, passed by the G
Division Bench of the Delhi High Court in EFA(OS) No.4 of
2009, heard along with several Miscellaneous Applications
setting aside the order dated 19th November, 2008, passed
by the learned Single Judge, who had directed payment to the
Appellant herein as per its calculations. It is the common case H
162 SUPREME COURT REPORTS [2011) 13 (ADDL.) S.C R
A of the parties that on 17th October, 1996, the Housing and
Urban Development Corporation Ltd. (HUDCO) invited offers
for grant of sub-lease of land measuring 11,480 sq. meters in
HUDCO Place situated in Andrews Ganj, New Delhi, for
construction of a Five-Star Hotel thereupon. The Appellant
B herein being the highest bidder, a letter of allotment of the said
land was issued to it on 31st March, 1997, which was followed
by a perpetual sub-lease dated 4th July, 1997. Out of the total
consideration, the first instalment comprising 40% of the
consideration amount was paid by the Appellant herein on 10th
c April, 1997. The second and third instalments, each amounting
to Rs.65,38,29,000/-, were payable by 31st March, 1998, and
31st March, 1999, respectively. It was stipulated in the sub-
lease that in case of default in payment of the second and third
instalments, the same could be paid along with interest at tlie
D rate of 20% per annum within three months of the due date. It
was further stipulated that in default of payment even in terms
of the said relaxation, the allotment would automatically stand
cancelled and in such event 50% of the amount paid upto that
date would stand forfeited and the balance 50% would be
E refunded without interest. Admittedly, the second instalment was
paid by the Appellant herein along with interest for the delayed
payment and ground rent was also paid till 31st March, 1998.
Since, however, the Appellant defaulted in payment of the third
instalment, the lease agreement was cancelled and as per the
terms of the agreement 50% of the total amount paid by the
F Appellant amounting to Rs.76,28,00,500/-was refunded by the
Corporation to the Appellant, while forfeiting the balance 50%.
3. Being aggrieved by the steps taken by the Respondent
Corporation, the Appellant filed a Petition before the Chief
G Justice of the Delhi High Court to appoint an Arbitrator in terms
of the arbitration clause, which was registered as Arbitration
Application No.193of1999. On 23rd June, 1999, an Arbitrator
was appointed by the Delhi High Court before whom the
Appellant herein claimed a sum of Rs.142, 16,08,896/- from the
H Respondent Corporation along with interest at the rate of 20%
LEELA HOTELS LTD. v. HOUSING & URBAN 163
DEVELOPMENT CORP. LTD. [ALTAMAS KABIR, J.]
per annum along with a further sum of Rs.19,24,45,800/- A
comprising the ground rent paid along with interest thereon at
the rate of 25% per annum along with a sum of Rs.5,98,22,058/
- towards refund of property tax. A sum of Rs.5,62,27,715/-was
also claimed by way of damages.
B
4. The learned Arbitrator allowed the claims of Leela
Hotels and rejected the counter-claim made by HUDCO. In his
Award, the learned Arbitrator held that Leela Hotels was entitled
to recover and HUDCO was obliged to pay damages
computed with regard to the amounts paid as the first and
second instalments of the premium, together with interest paid C
with the second instalment, less the amount refunded by
HUDCO to Leela Hotels under letter dated 8th July, 1999, and
as further reduced by the amount of property tax paid by
HUDCO on behalf of Leela Hotels to the Municipal Corporation
of Delhi. It was also directed that the interest at the rate of 20% D
per annum would be paid by HUDCO to Leela Hotels on the
amount representing property tax for the period during which
the amount remained with HUDCO until payment to MCD and
also on the amount refunded by HUDCO under its letter dated
8th July, 1999, for the period for which that amount remained E
with HUDCO until repayment to Leela Hotels. Leela Hotels was
also held to be entitled to such interest on the balance of the
amount from the date of the respective payments made initially
by Leela Hotels to HUDCO till the date of the Award.
F
5. The Appellant filed its objections under Section 34 of
the Arbitration and Conciliation Act, 1996, hereinafter referred
to as the "1996 Acf', before the High Court. The same was
dismissed by the High Court by its order dated 21st January,
2003. Before the said petition was dismissed, the Respondent G
herein undertook to deposit the principal sum awarded by the
Arbitrator on or before 21st October, 2002. The said sum of
Rs.89,78,84,930/-, was allowed to be deposited without
prejudice to the rights and contentions of the Respondent
herein. When the cheque for the aforesaid amount was brought H
164 SUPREME COURT REPORTS [2011] 13 (ADDL.) S.C.R.
A to Court on 21st October, 2002, the said Respondent got it
recorded that it represented the net principal amount due and
payable to the Appellant herein under the Award and that the
said deposit was without liability on its part to pay future interest
thereupon.
B
6. The first appeal from the said order dated 20th January,
2003, having been dismissed by the High Court on 9th
November, 2004, the Respondent filed a Special Leave
Petition before this Court, which was dismissed on 12th
February, 2008. Although, the Special Leave Petition was
C dismissed, the rate of interest for the pre-Award period was
reduced from 20% to 18% per annum. Furthermore, since this
Court had directed the Appellant to pay or deposit 50% of the
balance decretal amount, the Respondent paid a sum of
Rs.59.61 crores to the Appellant herein on 23rd March, 2006.
D The Respondent paid a further sum of Rs.48.09 crores to the
Appellant herein on 16th April, 20C8, which, according to the
Respondent, satisfied the decree. This, in fact, was the genesis
of the dispute between the parties.
E 7. As far as the Appellant herein was concerned, in its
calculation sheet the sum of Rs.89,78,84,930/- was shown to
be appropriated towards the interest due under the Award. A
claim was also made for interest on the interest. On the other
hand, in the calculation sheet filed by the Respondent herein it
F was indicated that the aforesaid amount deposited should be
appropriated towards the principal sum payable to the Appellant
herein under the Award and had calculated simple interest at
the rate awarded by the Arbitrator as modified by this Court.
Consequently, as was noted by the Division Bench of the Delhi
G High Court, the controversy which surfaced on account of the
contesting claims of the parties was whether the aforesaid
amount could be adjusted, as claimed by the Appellant herein,
towards the interest, or was the Appellant obliged to
appropriate the said sum towards the principal sum due to it
under the Award. A further question which surfaced was whether
H
LEELA HOTELS LTD. v. HOUSING & URBAN 165
DEVELOPMENT CORP. LTD. [ALTAMAS KABIR, J.]
the Appellant herein was entitled to charge interest on interest A
or compound interest in accordance with the method indicated
in the calculation sheet filed by it.
8. In dealing with the first question as to whether the
payment made by the judgment-debtor is to be appropriated B
first towards discharge of the principal or towards discharge
of the interest, the Division Bench noted the decision of this
court in Mis /.C.D.S. Ltd. Vs. Smithaben H. Patel & Ors.
((1999) 3 SCC 80), wherein, this Court had held that Sections
59 and 60 of the Contract Act, 1872, would only be applicable C
at the pre-decretal stage and not thereafter and that post-
decretal payments would have to be made either in terms of
the decree or in accordance with the agreement arrived at
between the parties, though, on the genuine principles indicated
in Sections 59 and 60 of the aforesaid Act. After referring to
various other decisions of this Court and the Lahore High Court, D
the Division Bench of the High Court referred to the decision
in Meghraj Vs. Mst. Bayabai & others, [AIR 1970 SC 161],
wherein the law in this regard was laid down by this Court that
the general rule of appropriation of payment towards a decretal
amount is that such an amount is to be adjusted firstly strictly E
in accordance with the directions contained in the decree and
in the absence of such direction, adjustments would have to be
made firstly towards payment of interest and costs and,
thereafter, in payment of the principal amount. It was, however,
indicated that such a principle would be subject to an exception F
when the parties might agree to the adjustment of the payment
in any manner despite the decree. It was, accordingly, held that
unless the Respondent herein was able to show that the parties
had either impliedly or expressly agreed to adjustment of the
said sum of Rs.89,78,84,930/- towards the principal amount, G
the Appellant herein would be entitled to appropriate the said
amount fully towards the payment of interest.
9. It may be indicated that on 11th October, 2002, the
Respondent herein undertook to deposit the principal amount H
166 SUPREME COURT REPORTS [2011] 13 (ADDL.) S.C.R
A awarded by the Arbitrator on or before 21st October, 2002.
Such deposit was allowed to be made without prejudice to the
rights and contentions of HUDCO in the proceedings before
the High Court. Subsequently, by order dated 21st October,
2002, the said position was reiterated and it was recorded that
B the deposit made by the Respondent would be without prejudice
to the rights and contentions of the parties in the pending
proceedings and without any liability on the part of the
Respondent to make payment of further interest on the above-
mentioned amount. The Division Bench took the view that
c having regard to the submissions made on behalf of the
Respondent herein that the said amount of Rs.89,78,84,930/-
was on account of the principal sum due and payable to the
Appellant herein under the Award, and since no objection had
been raised by the Appellant herein to such contention, it would
D have to be held that the said sum had, in fact, been adjusted
towards the principal sum. After observing that before
withdrawing the amount, the Appellant herein had neither sought
permission of the Court to appropriate the sum towards interest
nor given any intimation regarding withdrawal of the said
E amount, the Division Bench made it clear that the said amount
would be appropriated towards the principal amount due and
not towards interest. The Division Bench noted that the amount
being withdrawn was without prejudice to the Appellant's rights
towards payment of interest. The Division Bench took the view
that since the Respondent herein was keen to avoid the
F possibility of paying further interest on the principal sum, in the
event of its objections being dismissed, it offered to deposit
the principal sum payable under the Award. The Division Bench
observed that it made good business sense on the part of the
Appellant, at that time, to accept the aforesaid amount towards
G the principal sum payable to it under the Award and to utilize
the said sum for its business, instead of waiting for the final
outcome of the litigation between the parties. The Division
Bench came to the conclusion that it was in such circumstances
that the Respondent had agreed to deposit the said sum of
H
LEELA HOTELS LTD. v. HOUSING & URBAN 167.
DEVELOPMENT CORP. LTD. [ALTAMAS KABIR, J.]
Rs.89,78,84,930/- specifically, towards the principal amount A
under the Award.
10. The Division Bench further observed that both the
parties were duly represented by their respective counsel, when
the Respondent herein offered and undertook to deposit the B
principal amount awarded by the Arbitrator and also insisted
that it be recorded as part of the proceedings that the said
payment was to be appropriated towards the principal amount
awarded by the learned Arbitrator and was without any further
liability on the part of the Respondent to make payment of
further interest on the said amount. The Division Bench based C
its judgment, to a large extent, on the assumption that since the
Appellant had remained silent to the said stipulation made on
behalf of the Respondent, it would have to be presumed that
the Appellant herein had consented to the said proposal.
D
11. On such reasoning, !he Division Bench set aside the
order passed by the learned Single Judge on 19th November,
2008, and after noting that a sum of Rs.50.54 crores had been
deposited by the Respondent No.1 herein during the pendency
of the Appeal, directed him to decide in the light of the judgment E
rendered by the Division Bench as to whether any further amount
was payable by the Respondent No.1 herein to the Appellant
in terms of the judgment. Consequential directions were also
given on the outcome of such findings.
12. As mentioned hereinbefore, this Appeal is directed F
against the said judgment of the Division Bench dated 20th July,
2009.
13. Appearing for the Appellant, Mr. Ashok Desai, learned
Senior Advocate, submitted that the crucial question to be G
considered and decided in this case was whether the amounts
deposited or paid by HUDCO from time to time were to be
appropriated first towards the interest payable on the principal
amount, following the decision in Smithaben's case (supra), or
towards the principal, having regard to the provision in the H
168 SUPREME COURT REPORTS [2011] 13 (ADDL.) S.C.R.
A Award relating to future interest which states that Leela Hotels
is entitled to interest at the rate of 15% per annum from the date
of the Award to the date of recovery. Mr. Desai submitted that
the language of the Award is clear that the amount on which
future interest has to be calculated includes interest awarded
B by the Arbitrator till the date of the Award. Mr. Desai submitted
that it was not a case of compound interest, but a case of
calculating simple interest on the amount as remained unpaid
each year. Mr. Desai also submitted that after the Award had
been passed, Leela Hotels had calculated interest on the basis
c of yearly rests, but subsequently gave up its claim on the basis
of compound interest and limited its claim to simple interest
after appropriating the amount received from HUDCO first
towards interest and then towards principal, in accordance with
the decision in Smithaben's case (supra). Mr. Desai submitted
D that the High Court had erred in accepting the calculation made
by HUDCO which had not computed the amount awarded by
the Arbitrator and had not computed future interest in terms of
the Award.
14. On the second issue as to how the money paid by
E HUDCO is to be appropriated, Mr. Desai urged that in
Smithaben's case (supra), it had been very clearly explained
that in view of the consistent view taken first by the Privy Council
and then by this Court, the general rule of appropriation of
payment towards a decretal amount is that such an amount is
F to be adjusted firstly in accordance with the directions
contained in the decree and in the absence of such directions,
adjustment should firstly be made in payment of interest and
costs and thereafter towards payment of the principal amount.
Mr. Desai urged that the Division Bench had misapplied the
G ratio in Smithaben's case (supra) in assuming that the unilateral
and voluntary deposit offered to be made by HUDCO in Court
amounted to such deposit being made upon an implied
acceptance that the same would be appropriated towards the
principal amount.· It was urged that the issue of implied
H agreement had never been raised or argued before the learned
LEELA HOTELS LTD. v. HOUSING & URBAN 169
DEVELOPMENT CORP. LTD. [ALTAMAS KABIR, J.]
A
Single Judge and there is no pleading in support thereof. Mr.
Desai also urged that the provisions of Sections 59 and 60 of
the Indian Contract Act would also have no application to the
facts of this case since they only applied in regard to distinct
debts and not for enforcing a decree or what is regarded as a
decree by legal fiction. B
15. Mr. Desai submitted that the judgments of both the
learned Single Judge and the Division Bench were centered
around the payment of Rs.89.78 crores and the manner in
which the same was to be appropriated. It was urged that since C
the same was paid after the passing of the decree, Leela
Hotels is entitled to appropriate the said amount first towards
the interest and costs and then towards the principal. Mr. Desai
urged that on account of the wrong assumptions made by the
Division Bench, its judgment under appeal was liable to be set D
aside.
16. On the other hand, appearing for HUDCO, Mr. Parag
P. Tripathi, learned Additional Solicitor General, firstly urged
that the issue regarding charging of compound interest did not
survive, since the parties had agreed that no compound interest E
was payable in terms of the Award. As to the other question
as to whether the sums deposited by HUDCO were to be
appropriated first against the interest and then against the
principal, it was contended that the same was no longer res
integra since the Award had made it clear that the first payment F
of Rs.76.28 crores had to be reduced from the principal amount
which was due. The learned ASG submitted that it was for the
first time before this Court that the Appellant has contended that
the sum of Rs.76.28 crores would be appropriated first towards
the interest and then towards the principal amount. The learned G
ASG pointed out that the refund had been made even prior to
the making of a Reference to the Arbitrator or pronouncing of
the Award i.e. at the pre-decretal stage and, accordingly, when
the refund was made, there was no determination as to whether
any payment was due from HUDCO to the Appellant. H
170 SUPREME COURT REPORTS [2011] 13 (ADDL.) S.C.R.
A Accordingly, the contention of Leela Hotels that the said refund
of Rs. 76.28 crores was to be first appropriated towards the
interest does not even arise. It was also submitted that the first
payment of 50% of the awarded amount amounting to Rs.76.28
crores was, therefore, treated by the Award to be payment
B appropriated towards the principal and since the Award had
not been challenged by the Appellant herein, the objections to
the Award under Section 34 of the Act filed by the Respondent
also stood concluded by the decision of this Court in Civil
Appeal No.1094 of 2006.
c 17. As regards the second amount of Rs.89.78 crores
tendered by HUDCO in the Delhi High Court on 21st October,
2002, during the pendency of the proceedings under Section
34 of the Arbitration and Conciliation Act, 1996, it was
submitted by the learned ASG that the same has to be
D appropriated towards the principal amount due from HUDCO
to Leela Hotels. It was submitted that the said amount was in
the nature of a pre-decretal payment a1d that the appropriation
of the amount will have to be in the manner indicated by the
Respondent to which there had been no demur.
E
18. It was next submitted by the learned ASG that analogy
of a post-decretal payment cannot be applied to an Arbitration
Award under the 1996 Act for the simple reason that the
Arbitration Award under the 1996 Act does not attain the status
F or character of a decree within the meaning of the Code of Civil
Procedure. It is to be executed "as if it were a decree", which
means that it is not a decree.
19. It was thirdly urged by the learned ASG that assuming
that the Award could be treated as a decree and the second
G payment is a post-decretal payment, even then the said
payment will have to be treated as appropriation towards the
principal sum, since Leela Hotels had been duly intimated of
the nature of the deposit and by way of an impliell contract,
Leela Hotels had appropriated the said sum towards the
H principal.
LEELA HOTELS LTD. v. HOUSING & URBAN 171
DEVELOPMENT CORP. LTD. [ALTAMAS KABIR, J.]
20. The learned ASG referred to the decision of this Court A
in NALCO Vs. Presteel & Fabrication Pvt. Ltd. [(2004) 1 SCC
540], wherein it had been held that there is no question of any
decree being honoured pursuant to the passing of an Award
and unlike a judgment within the meaning of the Civil Procedure
Code, an Award remains unenforceable during the period B
available for challenging the Award, and, thereafter, till such time
as the Petition under Section 34 is disposed of by the
appropriate Court. Reference was also made to the decision
of this Court in (1) Paramjeet Singh Patheja Vs. /COS Ltd.
[(2006) 13 sec 322), wherein it was explained that the c
Arbitrator is not a Court and accordingly an arbitration is not
an adjudication and an Award is not a decree, (2) Morgan
Securities and Credit Pvt. Ltd. Vs. Modi Rubber Ltd. [(2006)
12 SCC 642] and (3) West Bengal Essential Commodities
Supply Corporation Vs. Swadesh Agro Farming & Storage D
Pvt. Ltd. & Anr. [(1999) 8 SCC 315), where similar views have
been expressed. Reference was also made to the decision of
the Privy Council in the case of Rai Bahadur Seth Nemichand
Vs. Seth Radha Kishen [AIR 1922 PC 26), wherein it was, inter
alia, held that a creditor to whom principal and interest are
owed is entitled to appropriate any indefinite payment which E
he gets from a debtor towards the payment of interest.
However, a debtor might in making a payment stipulate that it
was to be applied only towards the principal. If such a stipulation
was made, the creditor was at liberty to refuse the payment on
such terms, but then he would have to give back the money or F
the cheque by which the money was offered. If the amount was
accepted then the creditor would be bound by the appropriation
as proposed by the debtor.
21. As to the decision of this Court in Smithaben's case G
(supra), the learned ASG submitted that the payment was
unilaterally made out of Court by the debtor with a covering
letter, which was immediately responded to by the decree-
holder who made it clear that he had appropriated the amount
towards interest alone. This Court, therefore, held that the H
172 SUPREME COURT REPORTS [2011] 13 (ADDL.) S.C.R.
A creditor was not bound by the appropriation so made by the
debtor. The learned ASG submitted that in the instant case the
Respondent had tendered a sum of Rs.89.78 crores in Court
as payment towards the principal amount and the same had
been accepted by Leela Hotels without objection and
B accordingly the decision in Smithaben's case (supra) would
have no application to the facts of this case. The learned ASG
submitted that there being little or no substance in the Appeal,
the same was liable to be dismissed with costs.
C 22. Of the two issues involved in this matter, it appears that
the issue relating to charging of compound interest did not
survive since the parties had agreed that no compound interest
would be payable in terms of the Award. In fact, although such
an assertion had been made by the learned ASG, the same
was not seriously opposed by Mr. Desai who had taken the
D stand that this was not a case of compound interest, but a case
of calculating simple interest on the amount as remained
unpaid. Mr. Desai also accepted the position that after the
Award had been passed by the learned Arbitrator, Leela Hotels
had calculated the interest on the basis of yearly rests, but had
E subsequently given up its claim of compound interest and
limited its claim to simple interest after appropriating the
amount received from HUDCO, first towards interest and then
towards the principal in accordance with the decision in
Smithaben's case (supra).
F
23. Consequently, the only issue which remains for
decision is whether the amounts deposited and/or paid by
HUDCO to Mis Leela Hotels in terms of the Award of the
learned Arbitrator, was first to be appropriated towards
G payment of the interest due on the principal sum or whether the
same was to be appropriated against the principal sum itself.
24. From the submissions made on behalf of th.e
respective parties, the following payments appear to have been
made by HUDCO to the Appellant herein:-
H
LEELA HOTELS LTD. v. HOUSING & URBAN 173
DEVELOPMENT CORP. LTD. [ALTAMAS KABIR, J.]
(i) 12.07.1999 Rs.76.28 crores A
(ii) 21.10.2002 Rs.89.78 crores
(iii) March 2006 Rs.59.61 crores
(iv) May 2008 Rs.48.09 crores and B
(v) May 2009 Rs.50.54 crores.
It has been contended by the learned ASG that the amount
of Rs.89.78 crores having been paid towards the principal
amount, the other payments made subsequently were towards C
interest and, accordingly, there was no amount due and payable
to the Appellant. On the other hand, it has been claimed on
behalf of the Appellant that the said sum of Rs.89.78 crores had
been appropriated against the interest as per the decision in
Smithaben's case (supra), and, accordingly, the stand taken D
on behalf of HUDCO was erroneous.
25. As indicated hereinbefore, the submissions made by
the learned ASG on behalf of HUDCO was based on the
proposition as contained in Sections 59 and 60 of the Indian E
Contract Act, 1872, on account of the stipulation recorded on
behalf of HUDCO that the amount of Rs.89.78 crores was being
tendered towards the principal sum, to which there was no
objection from the Appellant and, accordingly, it must be held
that that since the amount had been received without demur, F
such payment fell within the provisions of Section 59 of the
aforesaid Act. In fact, the Division Bench of the High Court
proceeded to consider such payment and acceptance to be a
voluntary acceptance by the Appellant of the aforesaid amount
as appropriat"1on towards the principal as it made good
business sense to accept the same and to utilise the same in G
spite of waiting for something indefinite in the future. Such a
submission, though legal and correct, is not supported by the
materials on record.
26. Admittedly, there was no agreement between the H
174 SUPREME COURT REPORTS [2011] 13 (ADDL.) S.C.R.
A parties as to how the amounts to be paid in terms of the Award
were to be appropriated by the Appellant. Accordingly, in terms
of the well settled principle that in such cases it was for the
creditor to appropriate such payment firstly against the interest
payable, would, in our view, be squarely attracted to the facts
B of this case. As was laid down by the Privy Council in Meka
Venkatadri Appa Rao Bahadur Zamindar Garu & Ors. Vs.
Raja Parthasarathy Appa Rao Bahadur Zamindar Garu [AIR
1922 PC 233], and later reiterated in Rai Bahadur Seth
Nemichand's case (supra), when monies are received without
c a definite appropriation on the one side or the other, the rule
which is well established in ordinary cases is that in those
circumstances, the money is first applied in payment of interest
and when that is satisfied, in payment of the capital. fn the latter
case, the said principal was restated and it was indicated that
a creditor to whom principal and interest are- awed is entitled
0
to appropriate any indefinite payment which he gets from a
debtor to the payment of interest. It was also indicated that a
debtor might in making a payment stipulate that it was to be
applied only towards the principal. If he did so, the creditor was
E at liberty to refuse payment on such terms, but then he would
have to give back the money or the cheque by which the money
is proffered and if the same is accepted, the creditor would then
be bound by the appropriation as proposed by the debtor.
27. In the instant case, a unilateral assertion had been
F made by HUDCO as the debtor that the sum of Rs.89. 78 crores
was being tendered as payment towards the principal amount
and that there was, therefore, no· other amounts due and
payable to the creditor Leela Hotels Ltd. The principle as laid
down in the two aforesaid decisions, and as subsequently
G followed in Smithaben's case (supra) will not apply in the facts
of the instant case, since the amount as deposited was
accepted by the Appellant without prejudice to its rights and
contentions in the appeal. Since the amount had been
accepted on protest, the principle laid down in Rai Bahadur
H Seth Nemichand's case (supra) will have no application.
LEELA HOTELS LTD. v. HOUSING & URBAN 175
DEVELOPMENT CORP. LTD. [ALTAMAS KABIR, J.]
28. The philosophy behind the principle set out in Meka A
Venkatadri's case (supra) and as reiterated in Rai Bahadur
Seth Nemichand's case (supra) and also in Smithaben's case
(supra) and then consistently followed by this Court, is that a
debtor cannot be allowed to take advantage of his default to
deny to the creditor the amount to which he would be entitled B
on account of such default, by way of elimination of the principal
amount due itself, unless, of course, the provisions of Section
59 of the Indian Contract Act, 1872, were attracted or there was
a separate agreement between the parties in that regard. That
is not so in the instant case and, accordingly, the creditor c
cannot be denied its dues on a unilateral stipulation that the
amount of Rs.89.78 crores was being deposited as against the
principal sum due in terms of the Award. Since the said amount
was accepted by the Appellant on protest, it would be entitled
to appropriate the same against the interest which was due and D
payable till that date on the principal amount, as has been
asserted by it.
29. In our view, the Division Bench of the Delhi High Court
erred in presuming that the said amount had been accepted
by the Appellant on account of good business sense in view of E
the uncertainty of the final outcome of the case. In our view, the
Division Bench of the High Court should have proceeded on
the basis of the principles of law as laid down by this Court in
Smithaben's case (supra), keeping in mind the earlier
decisions of the Privy Council in both Meka Venkatadri's case F
(supra) and Rai Bahadur Seth Nemichand's case (supra) in
interfering with the judgment of the learned Single Judge. The
Division Bench seems to have erroneously taken the presence
of the learned counsel for the Appellant, when the aforesaid
undertaking of the Respondent was recorded, in coming to the G
conclusion that since no objection had been raised with regard
to the said deposit, it must be presumed that it had the consent
of the Appellant and hence was covered by the provisions of
Sections 59 and 60 of the Indian Contract Act, 1872.
H
176 SUPREME COURT REPORTS [2011) 13 (ADDL.) S.C.R.
A 30. Regarding the question as to whether the Award of the
learned Arbitrator tantamounts to a decree or not, the language
used in Section 36 of the Arbitration and Conciliation Act, 1996,
makes it very clear that such an Award has to be enforced under
the Code of Civil Procedure in the same manner as it were a
B decree of the Court. The said language leaves no room for
doubt as to the manner in which the Award of the learned
Arbitrator was to be accepted.
31. Hence, the submissions made by the learned ASG on
behalf of HUDCO cannot be accepted and are, therefore,
C rejected. Consequently, the Appeal succeeds and the judgment
and order of the Division Bench of the High Court is set aside
and that of the learned Single Judge is restored.
32. Having regard to the nature of the issues involved in
D this case, the parties will bear their own costs.
R.P. Appeal allowed.
Search Indian case law
Ask in plain English, not just keywords. 25,000 AI words free, no card.