Created byFuzzy Cloud

Supreme Court of India

M/S ADANI POWER (MUNDRA) LTD.versusGUJARAT ELECTRICITY REGULATORY COMMISSION AND ORS.

Citation
2019 INSC 711
Decided
2 July 2019
Disposal
Appeal(s) allowed

Holding

A termination of the PPA under Article 3.4.2 is valid when the seller fails to comply with the conditions in Article 3.1.2, without requiring a separate agreement on the breach, and the parties must approach CERC for determination of compensatory tariff.

Summary

The Gujarat Electricity Regulatory Commission (GERC) procured power through a competitive bidding process and selected M/s Adani Power (Mundra) Ltd. (the appellant) for a 1000 MW supply at Rs 2.35/kWh, contingent on an assurance from Gujarat Mineral Development Corporation (GMDC) to provide indigenous coal. When GMDC failed to finalize a Fuel Supply Agreement, the appellant issued a notice terminating the Power Purchase Agreement (PPA) on 28 December 2009, invoking Article 3.4.2 of the PPA. GERC and the Appellate Tribunal held the termination illegal, but the Supreme Court found that a harmonious reading of Articles 3.1.2 and 3.4.2 allowed either party to terminate on non‑compliance, and that the appellant’s termination was valid and entitled to liquidated damages. The Court also held that the parties should be referred to the Central Electricity Regulatory Commission (CERC) under Section 62 of the Electricity Act, 2003 to determine a compensatory tariff. Consequently, the appeal was allowed, the termination was declared valid, and the CERC was directed to fix the tariff within three months.

Issues considered

  • The validity of the appellant's termination of the Power Purchase Agreement under Article 3.4.2 in view of non‑fulfilment of conditions in Article 3.1.2.
  • Whether the termination can be invoked only when both parties agree that a condition has been violated.
  • The appropriate interpretation of the contractual clauses using the principles of harmonious construction and business efficacy.
  • The entitlement of the appellant to compensatory tariff and liquidated damages after termination.

Legislation cited

Subjects

Power Purchase AgreementTerminationContract InterpretationBusiness EfficacyLiquidated DamagesElectricity Act 2003Compensatory TariffHarmonious Construction

Judgment

                         [2019] 8 S.C.R. 1017                           1017


             M/S ADANI POWER (MUNDRA) LTD.                              A
                                 v.
 GUJARAT ELECTRICITY REGULATORY COMMISSION AND
                       ORS.
                  (Civil Appeal No.11133 of 2011)                       B
                           JULY 02, 2019
   [ARUN MISHRA, B. R. GAVAI AND SURYA KANT, JJ.]
       Electricity Act, 2003 – ss. 86 (1) (F), 95 – Respondent
No. 2-Procurer initiated the process of bidding for supply of power
                                                                        C
on long term basis, by issuing Request for Qualification – Three
separate bids were invited – Appellant was selected as a successful
bidder in respect of bid no. 2 for supplying 1000 MW power at the
rate of Rs. 2.35 per Kwh – Consequently, Power Purchase Agreement
(PPA) came to be entered into between the procurer and the appellant
– Appellant contended that the bid submitted by it was on the basis     D
of the assurance given by Gujarat Mineral Development
Corporation (GMDC) to supply coal – It was also contended that,
the GMDC was not abiding by the said assurance – There was a
dispute between the appellant and the GMDC with regard to certain
terms and conditions of the Fuel Supply Agreement (FSA) and as
                                                                        E
such FSA could not be finalized – Various communications were
exchanged between the Government of Gujarat, appellant and
GMDC to find out a solution – Finally, appellant by a communication
dated 28.12.2009, issued notice to the procurer, terminating the
PPA with effect from 04.01.2010 – Procurer filed petition u/ss.
86(1)(F), 95 of the Act, 2003 before Commission – The Commission        F
held that the termination was illegal and directed the appellant to
supply the power to the procurer at the rate determined in the PPA
– Aggrieved, appellant filed appeal before the Appellate Tribunal,
which was dismissed – On appeal, held: Appellate Tribunal depicted
an erroneous approach – It is settled that to harmonize is not to
                                                                        G
destroy any statutory provision or render it otiose – A harmonious
reading of Art. 3.4.2 and Art. 3.1.2 of the PPA indicated that in the
event of non-compliance of any of the conditions as stipulated in
Art. 3.1.2 within the period prescribed thereunder, either of the
parties, i.e., the seller or the procurer have the right to terminate
                                                                        H
                                1017
1018            SUPREME COURT REPORTS                        [2019] 8 S.C.R.


 A     the contract – Further, Appellate Tribunal was totally incorrect in
       holding that the provisions u/Art. 3.4.2 of the PPA can be invoked
       only when there is an agreement between the parties that there is a
       violation of any of the conditions specified in Art. 3.1.2 of the PPA
       – If such a view of the Appellate Tribunal is accepted, it will amount
       to inserting a totally new condition in Art. 3.4.2 of the PPA and
 B
       would amount to re-writing the contract between the parties; it would
       violate the provisions of Art. 3.4.2 of the PPA – And it will make the
       provisions of Art. 3.4.2 a dead letter and render them otiose – Also,
       it cannot said to be a condition which is necessary to give business
       efficacy to the contract – Besides, Appellate Tribunal erred in holding
 C     that the bid of the appellant was not on the basis of the commitment
       by the GMDC to supply indigenous coal – As it is clear from various
       communication between Government of Gujarat, Procurer and
       GMDC that the bid of the appellant was on the basis of the
       commitment by the GMDC to supply the indigenous coal – Thus,
       the termination of PPA by appellant was legal and valid –
 D
       Interpretation of Statutes – Harmonious Construction.
              Electricity Act, 2003 – s.62 – Determination of compensatory
       tariff by Central Electricity Regulatory Commission (CERC) –
       Respondent No.2-procurer initiated the process of bidding for supply
       of power – Appellant was selected as a successful bidder for
 E     supplying 1000 MW power at rate of Rs. 2.35 per kwh – Appellant
       contended that the bid submitted by it was on basis of the assurance
       given by Gujarat Mineral Development Corporation (GMDC) to
       supply coal – It was also contended that GMDC did not abide by
       the said assurance – Appellant terminated the PPA – Procurer filed
 F     petition u/ss.86(1)(f) & 95 of the Act before the Commission – The
       Commission and the Appellate Tribunal held that the termination
       was illegal and directed the appellant to supply the power to the
       procurer at the rate determined by PPA – On appeal, held:
       Termination by appellant was valid and legal – Appellant supplied
       electricity to the procurer in accordance with the decision of the
 G     Commission and the Appellate Tribunal – In order to do economic
       justice, on the principle of business efficacy, the appellant entitled
       for adjustment of cost of the project and also entitled to the interest
       on the expenditure incurred by it for completion of project –
       Therefore, parties relegated to the CERC for determination of the
 H
      M/S ADANI POWER (MUNDRA) LTD. v. GUJARAT                           1019
        ELECTRICITY REGULATORY COMMISSION

compensatory tariff payable to the appellant from the date of            A
termination of the PPA – CERC (Terms and Conditions of Tariff)
Regulations 2009.
     Doctrines/Principles – Principle of Business Efficacy –
Discussed.
      Allowing the appeal, the Court                                     B

      HELD: 1. The observations of the Appellate Tribunal
depicted a totally erroneous approach. A harmonious reading of
Article 3.4.2 and Article 3.1.2 of Power Purchase Agreement
(PPA) clearly indicates that in the event of non-compliance of any
of the conditions as stipulated in Article 3.1.2 within the period       C
prescribed thereunder, either of the parties, i.e., the seller or
the procurer have the right to terminate the contract. However,
in either of the events, it is the seller’s liability to pay the
liquidated damages at the rate of Rs. 10 lakhs per Mega Watt.
[Para 25] [1047-B-C]                                                     D
       2. This Court is of the considered view that the finding of
the Appellate Tribunal that the provisions under Article 3.4.2 of
the PPA can be invoked only when there is an agreement between
the parties that there is violation of any of the conditions specified
in Article 3.1.2 of the PPA is totally incorrect. If such an argument    E
is accepted, it will amount to inserting a totally new condition in
Article 3.4.2 of the PPA and would amount to re-writing the
contract between the parties; it would do total violence to the
provisions of Article 3.4.2 of the PPA. It cannot be said to be a
condition which is either reasonable or equitable; it also cannot
be said to be a condition which is necessary to give business            F
efficacy to the contract; it also cannot be said to be a test which
justifies the Officious Bystander Test; it also cannot be said to
be a condition which is capable of the clear expression; it is also
not a condition which does not contradict any expressed terms of
the contract. On the contrary, is a condition which would totally        G
change the tenor of Article 3.4.2 of the PPA. We are, therefore,
of the considered view that the Appellate Tribunal has grossly
erred in coming to the conclusion that Article 3.4.2 of the PPA
could be invoked only in the event that there is an agreement

                                                                         H
1020            SUPREME COURT REPORTS                      [2019] 8 S.C.R.


 A     with regard to violation of any of the conditions in Article 3.1.2.
       [Para 26] [1047-D-F]
             3. This Court finds, that both the Commission and the
       Appellate Tribunal have grossly erred in arriving at finding that
       termination can be effected under Article 3.4.2 only if there is an
 B     agreement with regard to non-compliance of condition under
       Article 3.4.2 by both the parties. If the finding of the Appellate
       Tribunal is accepted, it w ill be amounting to making
       provisions of Article 3.4.2 a dead letter and rendering them otiose.
       [Para 31] [1051-F-G]
 C           4. In the present case, the perusal of various Articles would
       reveal that provisions under Article 14 are general in nature.
       The provision under Article 3.4.2 is specific, only to be invoked
       in the case of non-compliance with any of the conditions as
       provided under Article 3.1.2. As such, the special provision made
       in Article 3.4.2 will exclude the applicability of general provisions
 D     contained in Article 14 of the contract. [Para 34] [1051-F]
             5. In the brief summary of the Project given in the said bid
       document, it has been specifically mentioned by the appellant
       that the bid was submitted on the basis of indigenous coal supply
       committed by the Gujarat Mineral Development Corporation
 E     (GMDC). The bid documents also form part of the PPA between
       the parties. [Para 37] [1052-C]
             6. It could thus be clearly seen that even the Government
       of Gujarat has also clearly indicated that the bid submitted by the
       appellant in the competitive bid was on the basis of the
 F     commitment for supply of coal from Morga-II mines by the
       GMDC. It has, therefore, requested the Managing Director,
       GMDC to give 50 per cent of coal from Morga block to the
       appellant. The State Government had, therefore, requested that
       the Managing Director of the GMDC to go for coal allotment
 G     from Morga block. It could thus be seen that, even the procurer
       was aware that the bid of the appellant was on the basis of the
       commitment by the GMDC to supply the indigenous coal.
       [Paras 39 and 41] [1053-B, C, F-G]


 H
      M/S ADANI POWER (MUNDRA) LTD. v. GUJARAT                          1021
        ELECTRICITY REGULATORY COMMISSION

      7. In that view thereof, after the GMDC resiling from its         A
commitment and refusing to enter into Fuel Supply Agreement
(FSA) with the appellant, the appellant was justified in invoking
Article 3.4.2 of the PPA, in view of non-compliance of Condition
No. (ii) in Article 3.1.2 since it had failed to produce the Fuel
Supply Agreement. [Para 43] [1054-E]
                                                                        B
       8. In the light of the aforesaid finding, this Court fails to
understand as to how the Appellate Tribunal has come to a finding
that the bid of the appellant was not on the basis of the commitment
by the GMDC to supply indigenous coal. This Court is of the
considered view that the Appellate Tribunal has erred both on
facts and in law. This Court is of the considered view that the         C
appellant was entitled in law as well as on facts to invoke Article
3.4.2 of the PPA and terminate the agreement. [Para 44]
[1054-H; 1055-A]
       9. Now, the question would arise as to at what rate the
appellant is entitled to compensatory tariff from the date of supply    D
of power. Undisputedly, even after the PPA was validly terminated,
the appellant continued to take the project to its logical end. After
commissioning of the project, it has started supplying electricity
to the procurer in accordance with the decision of the Commission
and the Appellate Tribunal. The appellant must have incurred            E
huge expenditure on the same. In order to do economic justice,
on the principle of business efficacy, the appellant would be
entitled for adjustment of cost of the project and would also be
entitled to the interest on the expenditure incurred by it for
completion of the project. The expenditure towards running of
the project after obtaining the coal from the open market would         F
also be required to be taken into consideration. The appellant
would also be entitled to the interest on the delay of payment
after it receives payment upon determination of the rate which
would be determined by the Central Electricity Regulatory
Commission (CERC). [Para 49] [1056-D-G]                                 G
      10. Section 62 of the Electricity Act, 2003, provides entire
mechanism for determination of the tariff by the CERC. It will
also be relevant to note that the CERC (Terms and Conditions
of Tariff) Regulations 2009 also consider various factors which
                                                                        H
1022            SUPREME COURT REPORTS                       [2019] 8 S.C.R.


 A     are required to be taken into consideration by the CERC while
       determining the compensatory tariff. This Court finds that it will
       be appropriate to relegate the parties to CERC for determination
       of the compensatory tariff payable to the appellant from the date
       of termination of the PPA. After such determination, the procurer
       would be entitled to adjust the amount if already paid in accordance
 B
       with affidavit dated 23.11.2015, from the amount so determined
       by the CERC. [Para 50] [1056-G-H; 1057-A]
             Calcutta Gas Company (Proprietary) Ltd. v. State of West
             Bengal and others AIR 1962 SC 1044 : [1962] Suppl.
             SCR 1 – followed.
 C
             Rajasthan State Industrial Development and Investment
             Corporation and Anr. v. Diamond & Gem Development
             Corporation Ltd. & Anr. (2013) 5 SCC 470 : [2013]
             4 SCR 331 ; Bharat Aluminium Company v. Kaiser
             Aluminium Technical Services INC (2016) 4 SCC 126 :
 D           [2016] 1 SCR 364 ; Nabha Power Ltd. (NPL) v. Punjab
             State Power Corporation Ltd. (PSPCL) and Anr. (2018)
             11 SCC 508 ; Sultana Begum v. Prem Chand Jain AIR
             1997 SC 1006 : [1996] 9 Suppl. SCR 707 ; Anwar
             Hasan Khan v. Mohammed Shafi and others AIR 2001
 E           SC 2984 ; J.K. Cotton Spinning and Weaving Mills Co.
             Ltd. v. State of Uttar Pradesh, AIR 1961 SC 1170 :
             [1961] SCR 185 ; Maharashtra State Board of
             Secondary and Higher Secondary Education and Ors.
             v. Paritosh Bhupeshkumar Sheth and Ors. (1984) 4
             SCC 27 : [1985] 1 SCR 29 – relied on.
 F
             Indian Oil Corporation v. Amritsar Gas Services Ltd.,
             (1991) 1 SCC 533 : [1990] 3 Suppl. SCR 196 ; Her
             Highness Maharani Shanti Devi Gaekwad v. Savji
             Haribhai Patel & Ors. (2001) 5 SCC 101 : [2001] 2
             SCR 590 ; Vermagiri v. Transco, 2007 SCC online
 G           APTEL 107 – referred to.
             Attorney General of Belize v. Belize Telecom Ltd., (2009)
             1 WLR 1988 (PC) – referred to.


 H
      M/S ADANI POWER (MUNDRA) LTD. v. GUJARAT                            1023
        ELECTRICITY REGULATORY COMMISSION

                       Case Law Reference                                 A
[1990] 3 Suppl. SCR 196          referred to             Para 10
[2001] 2 SCR 590                referred to              Para 10
[2013] 4 SCR 331                relied on                Para 16
[2016] 1 SCR 364                relied on                Para 17          B
(2018) 11 SCC 508               relied on                Para 18
[1962] Suppl. SCR 1             followed                 Para 28
[1996] 9 Suppl. SCR 707         relied on                Para 29
                                                                          C
AIR 2001 SC 2984                relied on                Para 29
[1961] SCR 185                  relied on                Para 32
[1985] 1 SCR 29                 relied on                Para 33
      CIVIL APPELLATE JURISDICTION : Civil Appeal No. 11133
of 2011.                                                                  D
      From the Judgment and Order dated 07.09.2011 of the Appellate
Tribunal for Electricity in Appeal No. 184 of 2010.
      Gopal Jain, Sr. Adv., Ashish Prasad, Ms. Mukta Dutta, Avinash
Tripathi, Mahfooz A. Nazki, Praveen Kumar, Advs. for the Appellant.
                                                                          E
     M. G. Ramachandran, Sr. Adv., Ms. Ranjeetha Ramachandran,
Ms. Vishakha, Ms. Puja Singh for Mrs. Hemantika Wahi, Ms. Swati
Bhardwaj, M/S. Parekh & Co., Prashant Bhushan, Advs. for the
Respondents.
      The Judgment of the Court was delivered by                          F
      B. R. GAVAI, J.
       1. The appellant has approached this Court being aggrieved by
the judgment and order passed by the Appellate Tribunal for Electricity
(“the Appellate Tribunal” for short) in Appeal No. 184 of 2010 dated
07.09.2011 thereby dismissing the appeal filed by the present appellant   G
and confirming the judgment and order passed by the Gujarat Electricity
Regulatory Commission (“the Commission” for short) dated 31.08.2010.


                                                                          H
1024             SUPREME COURT REPORTS                            [2019] 8 S.C.R.


 A            2. The facts in brief giving rise to the present appeal are as under.
              Respondent No. 2, namely, Gujarat Urja Vikas Nigam Ltd.
       (hereinafter referred to as “the procurer”) is a holding company engaged
       in the business of bulk purchases from the power generators and supply
       to the distribution companies in the State of Gujarat. On 01.02.2006, the
 B     procurer initiated the process of bidding for supply of power on long
       term basis, by issuing a Request For Qualification (“RFQ” for short).
       Three separate bids for purchase of power in accordance with the
       provisions of Section 63 of the Electricity Act, 2003 were invited. Each
       of the three bids envisaged purchase of power to the maximum extent
       of 2000 Mega Watt (“MW” for short). The RFQ was followed by
 C     Request For Proposal (“RFP” for short) on 24.11.2006. The present
       matter concerns bid No. 2 in respect of which the appellant was selected
       as a successful bidder.
              3. On being successful in the bidding process, the procurer issued
       a Letter of Intent (“LOI” for short) in respect of bid no. 2, to the appellant
 D     on 11.01.2007 for supplying 1000 MW power at the rate of Rs. 2.35 per
       Kwh. Consequently, the Power Purchase Agreement (“PPA” for short)
       came to be entered into between the procurer and the appellant, for
       purchase and sale of 1000 MW power from the appellant’s power project
       at Korba, Chhatisgarh, at the delivery point at Nani Khakhar in the State
 E     of Gujarat. Similarly, on 06.02.2007 another PPA came to be executed
       by the procurer with the appellant in respect of bid No. 1, which project
       was to be executed by using imported coal. The rate determined was
       Rs. 2.89 per unit in respect of bid No. 1.
              4. On 12.02.2007, the appellant informed the procurer that it would
 F     supply power against bid No. 2, from Mundra Power Project in Gujarat
       instead of Chhatisgarh Project. Accordingly, a supplemental PPA was
       entered into between the appellant and the procurer on 18.04.2007, to
       off take the contracted capacity of 1000 MW against bid No. 2, from
       Mundra Power Project.

 G            5. The appellant contended that, the bid submitted by it in respect
       of bid No. 2 was on the basis of the assurance given by Gujarat Mineral
       Development Corporation (“GMDC” for short) to supply 4 million tonnes
       of coal. It also contended that, the GMDC was not abiding by the said
       assurance. So it addressed a communication to the Government of Gujarat
       on 21.05.2007 to find out a solution. Since the Fuel Supply Agreement
 H
    M/S ADANI POWER (MUNDRA) LTD. v. GUJARAT                                   1025
ELECTRICITY REGULATORY COMMISSION [B. R. GAVAI, J.]

(“FSA” for short) could not be executed, as contemplated between the           A
appellant and the GMDC; the appellant informed the procurer that the
FSA between it and the GMDC had not yet been finalized. Again, a
communication came to be addressed by the appellant on 01.05.2008 to
the Government of Gujarat, requesting it to impress upon the GMDC to
adhere to its assurance and supply the coal from the coal blocks allocated
                                                                               B
to the GMDC. The procurer, thereafter, in the month of June, 2008,
addressed a communication to the appellants stating that, since it had
not complied with certain conditions stipulated in the PPA and as such, it
should furnish an additional performance bank guarantee. The appellant
addressed another communication to the procurer on 17.01.2009,
reiterating its inability to supply the power to the procurer in the absence   C
of FSA with GMDC. It also informed that it had no other option except
to terminate the PPA. On 27.02.2009, the Government of Gujarat wrote
to the GMDC, asking it to supply coal to the appellant from Naini block.
       6. It appears that there was a dispute between the appellant and
the GMDC with regard to certain terms and conditions of the FSA and            D
as such the FSA could not be finalized. The record would further reveal,
that there was a long correspondence between the Government of
Gujarat, the GMDC, the procurer and the appellant with regard to the
commitment by the GMDC to supply coal to the appellant in respect of
bid No. 2 and non-adherence by the GMDC to abide by the said
commitment. The appellant addressed a communication dated 15.11.2008           E
specifically informing the procurer that the bid was on the basis of the
assurance by the GMDC to supply coal. It also informed the procurer
that though it was in a position to comply with all other conditions
subsequent but they are unable to execute the FSA since the GMDC
had not cooperated in the matter. Another communication was addressed          F
by the appellant on 17.01.2009 reiterating that in the absence of FSA
with the GMDC, the appellant will not be in a position to supply contracted
capacity of power to GUVNL/the procurer in the absence of FSA with
the GMDC. It further informed that the appellant shall have no other
option than to terminate the PPA unless the coal supply comes from the
GMDC from Morga-II coal block. However, it appears that, thereafter,           G
there was an attempt to amicably settle the matter between the appellant,
the procurer, the GMDC as well as the Government of Gujarat. As
such, the appellant addressed communication dated 28.04.2009 keeping
its notices dated 15.11.2008 and 17.01.2009 in abeyance till the matter
                                                                               H
1026             SUPREME COURT REPORTS                            [2019] 8 S.C.R.


 A     was resolved between the appellant and the GMDC/Government of
       Gujarat. It, however, appears that the said attempts were not fruitful.
               Finally, the appellant by a communication dated 28.12.2009, issued
       notice to the procurer, terminating the PPA with effect from 04.01.2010.
       The procurer addressed a communication to the Government of Gujarat
 B     on 30.12.2009, requesting the Government to impress upon the appellant
       to withdraw its termination notice dated 28.12.2009 and also impress
       upon the GMDC for resolution of FSA with the appellant. The procurer
       also addressed a communication to the appellant on 05.01.2010,
       requesting it to keep the notice of termination dated 28.12.2009 in
       abeyance. On 06.01.2010, the appellant addressed another communication
 C     to the procurer, informing it that since the period of termination has already
       expired, the PPA stands terminated with effect from 4.01.2010. The
       appellant also deposited an amount of Rs. 25 crores with the procurer
       towards liquidated damages in addition to the performance bank
       guarantee of Rs. 75 crores, which was already with the procurer. On
 D     13.01.2010 the procurer sent a letter to the appellant, returning the amount
       of Rs. 25 crores and calling upon it to withdraw the termination notice.
       However, the appellant asserted that termination was valid.
              7. The procurer, thereafter, filed a petition under Sections 86(1)(f)
       and 95 of the Electricity Act, 2003, for adjudication of the dispute between
 E     the procurer and the appellant on 01.02.2010 before the Commission.
       The Commission by its judgment dated 31.08.2010 allowed the petition
       of the procurer, holding that the termination of the PPA was illegal and
       directed the appellant herein to supply the power to the procurer at the
       rate determined in the PPA. Being aggrieved, the appellant approached
       the Appellate Tribunal for Electricity. By the judgment and order impugned
 F     dated 07.09.2011, the Appellate Tribunal dismissed the appeal. Hence,
       the present appeal.
             8. We have heard Mr. Gopal Jain, learned senior counsel for the
       appellant, and Mr. M.G. Ramachandran, learned senior counsel for the
       respondent(s).
 G
             9. The main contention raised on behalf of the appellant is that the
       bid which was submitted by the appellant in respect of bid No. 2 was on
       the basis of the commitment given to it by the GMDC that it will supply
       the coal. It is submitted that the PPA executed between the appellant
       and the procurer was on the premise that the GMDC would abide by its
 H
    M/S ADANI POWER (MUNDRA) LTD. v. GUJARAT                                     1027
ELECTRICITY REGULATORY COMMISSION [B. R. GAVAI, J.]

commitment. It is also submitted that since the GMDC had failed to               A
abide by its commitment and had not executed the FSA with the appellant,
there was a non-compliance with the conditions stipulated in Article 3.1.2
of the PPA and therefore the appellant was entitled to terminate the
agreement, by giving 7 days notice in writing in accordance with the
provisions of Article 3.4.2 of the PPA. So the only liability of the appellant
                                                                                 B
was to pay the liquidated damages at the rate of Rs. 10 lakhs per Mega
Watt of the contracted capacity, which is worked out to Rs. 100 crores
for 1000 MW.
       10. It is the submission of Mr. Jain, learned senior counsel, that
the Commission and the Appellate Tribunal have grossly erred in holding
that unless there was an agreement between the parties to the effect             C
that there was non-compliance with the conditions mentioned in Article
3.1.2 of the PPA, the appellant was not entitled to invoke the provisions
of Article 3.4.2 of the PPA. Mr. Jain further submitted that since the
contract also provided for liquidated damages, the Commission as well
the Appellate Tribunal, ought not to have given a direction for specific         D
performance. Reliance in this respect is placed on the judgments of this
Court in the case of Indian Oil Corporation vs. Amritsar Gas Services
Ltd., (1991) 1 SCC 533 and Her Highness Maharani Shanti Devi
Gaekwad vs. Savji Haribhai Patel & Ors. (2001) 5 SCC 101.
      11. Mr. Jain further submitted that the Appellate Tribunal by the          E
impugned judgment has varied the terms of the contract executed between
the parties, which is not permissible in law. Reliance in this respect is
placed on the judgments of this Court in the case of Vermagiri vs.
Transco, 2007 SCC On Line APTEL 107 and Gujarat Urja Vikas Nigam
Ltd. vs. Solar Semiconductor Power Company, (2017) 16 SCC 498.
                                                                                 F
       12. Per contra, Mr. Ramachandran, learned senior counsel
appearing on behalf of the procurer, would submit that the PPA which
was entered into between the parties, was not executed on the basis of
commitment by the GMDC. He submits that the procurer is not concerned
with the issue as to from where the appellant would arrange for its
supply of coal. The PPA between the appellant and the procurer is only           G
in respect of supply of power. It is submitted that on the GMDC’s failure
to adhere to its commitment to supply indigenous coal, it was the
responsibility of the appellant to make arrangement for an alternative
source and to enter into FSA with any other coal supplier. It is submitted
that as a matter of fact, the appellant is importing the coal from other         H
1028            SUPREME COURT REPORTS                            [2019] 8 S.C.R.


 A     nations and using it for generation of power, both for the plant under bid
       No. 1 and the plant under bid No. 2. Shri Ramachandran, learned senior
       counsel, further submits that, by not making arrangements for fuel supply,
       it is the appellant who had committed default and, therefore, a party in
       default cannot be permitted to terminate the agreement. Reliance in this
       respect is placed on various judgments of English Courts as well as this
 B
       Court. Reliance is also placed on various judgments of this Court, in
       support of the proposition that in spite of the provision of liquidated
       damages in the PPA, the courts are not powerless to direct a specific
       performance of the contract.
              13. Shri Ramachandran further submitted that the contract is
 C     required to be read as a whole and the provisions of the contract cannot
       be read in isolation. He, therefore, submits that the Commission as well
       as the Appellate Tribunal has rightly held that Article 3.4.2 and Article
       14.1 and Article 14.2 have to be read together. Thus, no fault could be
       found with the reasoning given by the Commission as well as the Appellate
 D     Tribunal. Learned senior counsel, therefore, submits that the appeal has
       no merit and deserves to be dismissed.
              14. For appraising the rival submissions it would be necessary to
       refer to certain clauses of the PPA:
               The relevant part of Article 3 reads thus:
 E
               “3. Article 3: CONDITIONS SUBSEQUENT TO BE
                      SATISFIED BY THE SELLER AND THE
                      PROCURER
               3.1      Satisfaction of conditions subsequent by the Seller
 F             3.1.1    xxx
               3.1.2    The seller agrees and undertakes to duly perform and
                       complete the following activities within (i) Twelve (12)
                       Months from the Effective Date or (ii) Fourteen (14)
                       Months from the date of issue of Letter of Intent,
 G                     whichever is later, unless such completion is affected
                       due to the Procurer’s failure to comply with its obligations
                       under this Agreement or by any Force Majeure event or
                       if any of the activities is specifically waived in writing
                       by the Procurer :
 H
    M/S ADANI POWER (MUNDRA) LTD. v. GUJARAT                                 1029
ELECTRICITY REGULATORY COMMISSION [B. R. GAVAI, J.]

             i. xxx                                                          A
             ii.the Seller shall have executed Fuel Supply Agreement
                  and provided the copies of the same to the Procurer.”


             The relevant part of Article 3.4 reads thus:                    B
     “3.4 Consequences of non-fulfilment of conditions under
           Article 3.1
     3.4.1    xxx
     3.4.2   Subject to Article 3.4.3, if:
                                                                             C
     (i)     fulfilment of any of the conditions specified in Article
             3.1.2 is delayed beyond the period of three (3) Months
             and the Seller fails to furnish any additional Performance
             Guarantee to the Procurer in accordance with Article
             3.4.1 hereof; or
                                                                             D
     (ii)     the Seller furnishes additional Performance Guarantee
             to the Procurer in accordance with Article 3.4.1 hereof
             but fails to fulfil the conditions specified in Article 3.1.2
             for a period of eight (8) months beyond the period
             specified therein, the procurer or the Seller shall have
             the right to terminate this Agreement by giving a notice        E
             to the Seller/ Procurer in writing of at least seven (7)
             days.
              If the Procurer or the Seller elects to terminate this
             Agreement in the event specified in the preceding
             paragraph of this Article 3.4.2, the Seller shall be liable     F
             to pay to the Procurer an amount equivalent to Rupees
             Rs. 10.00 lakhs per MW of the Contracted Capacity as
             liquidated damages. The Procurer shall be entitled to
             recover this amount of damages by invoking the
             Performance Guarantee to the extent of an amount                G
             equivalent to Rupees 10.00 lakhs per MW of the
             Contracted Capacity and shall then return the balance
             Performance Guarantee, if any, to the Seller. If the
             Procurer is unable to recover the said amount or any
             part thereof from the Performance Guarantee the
                                                                             H
1030           SUPREME COURT REPORTS                            [2019] 8 S.C.R.


 A                    amount not recovered from the Performance Guarantee,
                      if any, shall be payable by the Seller to the Procurer
                      within ten (10) days from the end of eight (8) Months
                      period from the due date of completion of conditions
                      subsequent. It is clarified for removal of doubt that this
                      Article shall survive the termination of this Agreement.
 B
              3.4.3In case of inability to the Seller to fulfil the conditions
                      specified in Article 3.1.2 due to any Force Majeure event,
                      the time period for fulfilment of the Condition Subsequent
                      as mentioned in Article 3.1.2, shall be extended for the
                      period of such Force Majeure event, subject to a
 C                    maximum extension period of ten (10) Months,
                      continuous or non-continuous in aggregate. Thereafter,
                      this Agreement may be terminated by the Procurer or
                      the Seller by giving a notice of at least seven (7) days, in
                      writing to the Other Party.”
 D            Since both the Commission and the Appellate Tribunal have
       referred to Article 14, we also reproduce the same.
              “14. ARTICLE 14 : EVENTS OF DEFAULT AND
                    TERMINATION

 E            14.1    Seller Event of Default
               The occurrence and continuation of any of the following events,
               unless any such event occurs as a result of a Force Majeure
               Event or a breach by Procurer of their obligations under this
               Agreement, shall constitute a Seller Event of Default:
 F            i)      the failure to Commission any Unit by the date falling
                      twelve (12) Months after its Scheduled Commercial
                      Operation Date, or
              ii)     after the commencement of construction of the Project,
                      the abandonment by the Seller or the Seller’s
 G                    Construction Contractors of the construction of the
                      Project for a continuous period of two (2) Months and
                      such default is not rectified within thirty (30) days from
                      the receipt of first notice from the Procurer in this regard,
                      or
 H
    M/S ADANI POWER (MUNDRA) LTD. v. GUJARAT                                1031
ELECTRICITY REGULATORY COMMISSION [B. R. GAVAI, J.]

     iii)   if at any time following a Unit being Commissioned and          A
            during its retest, as per Article 8, such Unit’s Tested
            Capacity is less than ninety two (92) per cent of its
            Rated Capacity, as existing on the Effective Date, and
            such Tested Capacity remain below ninety two (92)
            percent even for a period of three (3) Months thereafter
                                                                            B
            and also the Seller is unable to make available the full
            Contracted Capacity at the Delivery Point from the
            Tested Capacity of the Unit(s) of the Power Station; or
     iv)    after Commercial Operation Date of Contracted
            Capacity, the Seller fails to achieve Average Availability
            of sixty five per cent (65%), for a period of twelve (12)       C
            consecutive Months or within a non-consecutive period
            of twelve (12) Months within any continuous aggregate
            period of thirty six (36) Months, or
     v)     the Seller fails to make any payment (a) of an amount
            exceeding Rupees One (1) Crore required to be made              D
            to Procurer under this Agreement, within three (3)
            Months after the Due Date of an undisputed invoice /
            demand raised by the Procurer on the Seller or (b) of
            an amount upto Rupees One (1) Crore required to be
            made to Procurer under this Agreement within six (6)            E
            Months after the Due Date of an undisputed invoice /
            demand, or
     vi)    any of the representations and warranties made by the
            Seller in Schedule 10 of this Agreement; being found to
            be untrue or inaccurate. Further, in addition to the above,     F
            any of the undertakings submitted by the Seller at the
            time of submission of the Bid being found to be breached
            or inaccurate, including but not limited to undertakings
            from its parent company/affiliates related to the
            minimum equity obligation; Provided however, prior to
            considering any event specified under this sub-article          G
            to be an Event of Default, the Procurer shall give a
            notice to the Seller in writing of at least thirty (30) days,
            or

                                                                            H
1032    SUPREME COURT REPORTS                              [2019] 8 S.C.R.


 A     vii)    if the Seller :
               a) assigns or purports to assign any of its assets or
                   rights in violation of this Agreement; or
               b) transfers or novates any of its rights and / or
                  obligations under this agreement, in violation of this
 B                Agreement; or
       viii)   if (a) the Seller becomes voluntarily or involuntarily the
               subject of any bankruptcy or insolvency or winding up
               proceedings and such proceedings remain uncontested
               for a period of thirty (30) days, or (b) any winding up or
 C             bankruptcy or insolvency order is passed against the
               Seller, or (c) the Seller goes into liquidation or dissolution
               or has a receiver or any similar officer appointed over
               all or substantially all of its assets or official liquidator is
               appointed to manage its affairs, pursuant to Law, except
 D             where such dissolution or liquidation of the Seller is for
               the purpose of a merger, consolidation or reorganization
               and where the resulting entity has the financial standing
               to perform its obligations under this Agreement and
               creditworthiness similar to the Seller and expressly
               assumes all obligations of the Seller under this
 E             Agreement and is in a position to perform them; or
       ix)     the Seller repudiates this Agreement and does not rectify
               such breach even within a period of thirty (30) days
               from a notice from the Procurer in this regard; or

 F     x)      except where due to Procurer’s failure to comply with
               its material obligations, the Seller is in breach of any of
               its material obligations pursuant to this Agreement or of
               any of the RFP Documents where the Procurer and
               Seller are parties, and such material breach is not
               rectified by the Seller within thirty (30) days of receipt
 G             of first notice in this regard given by the Procurer to the
               Seller;
       xi)     the Seller fails to complete/fulfill the activities /conditions
               specified in Article 3.1.2, beyond a period of 8 Months
               from the specified period in Article 3.1.2 and the right
 H
    M/S ADANI POWER (MUNDRA) LTD. v. GUJARAT                              1033
ELECTRICITY REGULATORY COMMISSION [B. R. GAVAI, J.]

             of termination under Article 3.4.2 is invoked by the         A
             Procurer; or
     xii)    any direct or indirect change in the shareholding of the
             Seller in contravention of the terms of the Bid RFP
             Documents; or
     xiii)   The Seller fails to provide additional bank guarantee to     B
             the Procurer in accordance with Article 3.4.1 of this
             Agreement, or
     xiv)    Occurrence of any other event that is specified in this
             Agreement to be a material breach / default of the Seller.
                                                                          C
     14.2    Procurer Event of Default
      The occurrence and the continuation of any of the following
      events, unless any such event occurs as a result of a Force
      Majeure Event or a breach by the Seller of its obligations under
      this Agreement, shall constitute the Event of Default on the        D
      part of the Procurer:
      i)     the Procurer fails to pay (with respect to a Monthly Bill
             or a Supplementary Bill) an amount exceeding 15% of
             the most recent undisputed Monthly Bill for a period of
             ninety (90) days after the Due Date and the Seller is
                                                                          E
             unable to recover the amount outstanding to the Seller
             through the Collateral Arrangement and Letter of Credit;
             or
      ii)    the Procurer repudiates this Agreement and does not
             rectify such breach even within a period of thirty (30)
                                                                          F
             days from a notice from the Seller in this regard; or
      iii)   except where due to any Seller’s failure to comply with
             its obligations, the Procurer is in material breach of any
             of its obligations pursuant to this Agreement or of any
             of the RFP Documents where the Procurer and the
             Seller are Parties, and such material breach is not          G
             rectified by the Procurer within thirty (30) days of
             receipt of notice in this regard from the Seller to the
             Procurer; or

                                                                          H
1034   SUPREME COURT REPORTS                             [2019] 8 S.C.R.


 A     iv)     any representation and warranties made by any of the
               Procurer in Schedule 9 of this Agreement being found
               to be untrue or inaccurate. Provided however, prior to
               considering any event specified under this sub-article
               to be an Event of Default, the Seller shall give a notice
               to the concerned Procurer in writing of at least thirty
 B
               (30) days; or
       v)      if (a) the Procurer becomes voluntarily or involuntarily
               the subject of any bankruptcy or insolvency or winding
               up proceedings and such proceedings remain
               uncontested for a period of thirty (30) days, or (b) any
 C             winding up or bankruptcy or insolvency order is passed
               against the Procurer, or (c) the Procurer goes into
               liquidation or dissolution or has a receiver or any similar
               officer appointed over all or substantially all of its assets
               or official liquidator is appointed to manage its affairs,
 D             pursuant to Law, except where such dissolution or
               liquidation of the Procurer is for the purpose of a merger,
               consolidation or reorganization and where the resulting
               entity has the financial standing to perform its obligations
               under this Agreement and has creditworthiness similar
               to the Procurer and expressly assumes all obligations
 E             of the Procurer under this Agreement and is in a position
               to perform them; or;
       vi)     occurrence of any other event which is specified in this
               Agreement to be a material breach or default of the
               Procurer.
 F
       14.3    Procedure for cases of Seller Event of Default
              14.3.1 Upon the occurrence and continuation of any Seller
                      Event of Default under Article 14.1, the Procurer
                      shall have the right to deliver to the Seller a
 G                    Procurer Preliminary Default Notice, which shall
                      specify in reasonable detail, the circumstances
                      giving rise to the issue of such notice.
              14.3.2 Following the issue of Procurer Preliminary
                     Default Notice, the Consultation Period of ninety
 H
    M/S ADANI POWER (MUNDRA) LTD. v. GUJARAT                             1035
ELECTRICITY REGULATORY COMMISSION [B. R. GAVAI, J.]

                 (90) days or such longer period as the Parties          A
                 may agree, shall apply.
          14.3.3 During the Consultation Period, the Parties shall,
                 save as otherwise provided in this Agreement,
                 continue to perform their respective obligations
                 under this Agreement.                                   B
          14.3.4 After a period of seven (7) days following the
                 expiry of the Consultation Period and unless the
                 Parties shall have otherwise agreed to the contrary
                 or the Seller Event of Default giving rise to the
                 Consultation Period shall have been remedied and,       C
                (a) in case the Contracted Capacity from a Power
                     Station is less than 50% of the installed
                     capacity of such Power Station, the Procurer
                     may terminate this Agreement. Provided such
                     seller shall have the liability to make payments    D
                     for Capacity Charges based on Normative
                     Availability to the Procurer for the period three
                     (3) years from the eighth day after the expiry
                     of the Consultation Period. Provided further
                     that at the end of the three year period, this
                     Agreement shall automatically terminate and         E
                     thereafter, the Seller shall have no further
                     Capacity Charge liability towards the
                     Procurer. Provided further, the Procurer shall
                     have the right to terminate this Agreement
                     even before the expiry of such three year           F
                     period provided on such termination, the future
                     Capacity Charge liability of the Seller shall
                     cease immediately.
                (b) in case the Contracted Capacity from a Power
                     Station is more than or equal to 50% of the         G
                     installed capacity of such Power Station, the
                     Lenders may exercise or the Procurer may
                     require the Lenders to exercise their
                     substitution rights and other rights provided to
                     them, if any, under Financing Agreements and
                     the Procurer would have no objection to the         H
1036   SUPREME COURT REPORTS                         [2019] 8 S.C.R.


 A                      Lenders exercising their rights if it is in
                        consonance with provisions of Schedule 14.
                        Alternatively, in case the Lenders do not
                        exercise their rights as mentioned herein
                        above, the Capacity Charge of the Seller shall
                        be reduced by 20% for the period of Seller
 B
                        Event of Default and the Procurer may
                        terminate this Agreement and the provisions
                        of Article 14.3.4 (a) shall apply mutatis
                        mutandis.
       14.4 Termination for Procurer Events of Default
 C
            14.4.1 Upon the occurrence and continuation of any
                   Procurer Event of Default pursuant to Article 14.2
                   (i), the seller shall follow the remedies provided
                   under Article 11.5.2.
 D          14.4.2 Without in any manner affecting the rights of the
                   Seller under Article 14.4.1, on the occurrence of
                   any Procurer Event of Default specified in Article
                   14.2 the Seller shall have the right to deliver to
                   the Procurer a Seller Preliminary Default Notice,
                   which notice shall specify in reasonable detail the
 E                 circumstances giving rise to its issue.
            14.4.3 Following the issue of a Seller Preliminary Default
                    Notice, the Consultation Period of ninety (90) days
                    or such longer period as the Parties may agree,
                    shall apply.
 F
            14.4.4 During the Consultation Period, the Parties shall
                   continue to perform their respective obligations
                   under this Agreement.
            14.4.5. (i) After a period of seven (7) days following the
                    expiry of the Consultation Period and unless the
 G
                    Parties shall have otherwise agreed to the contrary
                    or the Procurer Event of Default giving rise to
                    the Consultation Period shall have been remedied,
                    the Seller shall be free to sell the Contracted
                    Capacity and associated Available Capacity to any
 H
    M/S ADANI POWER (MUNDRA) LTD. v. GUJARAT                              1037
ELECTRICITY REGULATORY COMMISSION [B. R. GAVAI, J.]

                third party of his choice. Provided the Procurer          A
                shall have the liability to make payments for
                Capacity Charges based on Normative Availability
                to the Seller for the period three (3) years from
                the eighth day after the expiry of the Consultation
                Period. Provided further that in such three year
                                                                          B
                period, in case the Seller is able to sell electricity
                to any third party at a net price at the Delivery
                Point which is in excess of the Energy Charges,
                then such excess realization will reduce the
                Capacity Charge payments due from the Procurer.
                For the avoidance of doubt, the above excess              C
                adjustment would be applied on a cumulative basis
                for the three-year period. During such period, the
                Seller shall use its best effort to sell the Contracted
                Capacity and associated Available Capacity
                generated or capable of being generated to such
                                                                          D
                third parties at the most reasonable terms available
                in the market at such time, having due regard to
                the circumstances at such time and the pricing of
                electricity in the market at such time. Provided
                further, the Seller shall ensure that sale of power
                to the shareholders of the Seller or any direct or        E
                indirect affiliate of the Seller/shareholders of the
                Seller, is not at a price less than the Tariff, without
                obtaining the prior written consent of the Procurer.
                Such request for consent would be responded to
                within a maximum period of three (3) days failing
                                                                          F
                which it would be deemed that the Procurer has
                given his consent. Provided further that at the end
                of the three-year period, this Agreement shall
                automatically terminate and thereafter, the
                Procurer shall have no further Capacity Charge
                liability towards the Seller. Provided further, the       G
                Seller shall have the right to terminate this
                Agreement even before the expiry of such three
                year period provided on such termination, the
                future Capacity Charge liability of the Procurer
                shall cease immediately.”
                                                                          H
1038             SUPREME COURT REPORTS                            [2019] 8 S.C.R.


 A            15. Before we proceed to consider the rival submissions, it will be
       appropriate to refer to certain judgments of this Court on the interpretation
       of clauses of the contract between the parties.
             16. This Court in the case of Rajasthan State Industrial
       Development and Investment Corporation and Anr. vs. Diamond &
 B     Gem Development Corporation Ltd. & Anr. reported in (2013) 5 SCC
       470 observed thus:
             “23. A party cannot claim anything more than what is covered
             by the terms of contract, for the reason that contract is a
             transaction between the two parties and has been entered into
 C           with open eyes and understanding the nature of contract. Thus,
             contract being a creature of an agreement between two or more
             parties, has to be interpreted giving literal meaning unless, there is
             some ambiguity therein. The contract is to be interpreted giving
             the actual meaning to the words contained in the contract and it is
             not permissible for the court to make a new contract, however
 D           reasonable, if the parties have not made it themselves. It is to be
             interpreted in such a way that its terms may not be varied. The
             contract has to be interpreted without any outside aid. The terms
             of the contract have to be construed strictly without altering the
             nature of the contract, as it may affect the interest of either of the
 E           parties adversely. [Vide United India Insurance Co. Ltd. v.
             Harchand Rai Chandan Lal, (2004) 8 SCC 644, and Polymat
             India (P) Ltd. v. National Insurance Co. Ltd., (2005) 9 SCC
             174.]
             24. In DLF Universal Ltd. v. Town and Country Planning
 F           Deptt., (2010) 14 SCC 1, this Court held: (SCC pp. 14-15, paras
             13-15)
                 “13. It is a settled principle in law that a contract is interpreted
                 according to its purpose. The purpose of a contract is the
                 interests, objectives, values, policy that the contract is designed
 G               to actualise. It comprises the joint intent of the parties. Every
                 such contract expresses the autonomy of the contractual parties’
                 private will. It creates reasonable, legally protected expectations
                 between the parties and reliance on its results. Consistent with
                 the character of purposive interpretation, the court is required
                 to determine the ultimate purpose of a contract primarily by
 H
    M/S ADANI POWER (MUNDRA) LTD. v. GUJARAT                                     1039
ELECTRICITY REGULATORY COMMISSION [B. R. GAVAI, J.]

        the joint intent of the parties at the time of the contract so           A
        formed. It is not the intent of a single party; it is the joint intent
        of both the parties and the joint intent of the parties is to be
        discovered from the entirety of the contract and the
        circumstances surrounding its formation.
        14. As is stated in Anson’s Law of Contract :                            B
           ‘a basic principle of the common law of contract is that the
           parties are free to determine for themselves what primary
           obligations they will accept.... Today, the position is seen in
           a different light. Freedom of contract is generally regarded
           as a reasonable, social, ideal only to the extent that equality       C
           of bargaining power between the contracting parties can
           be assumed and no injury is done to the interests of the
           community at large.’
        15. The Court assumes:
           ‘that the parties to the contract are reasonable persons who          D
           seek to achieve reasonable results, fairness and efficiency...
           In a contract between the joint intent of the parties and the
           intent of the reasonable person, joint intent trumps, and the
           Judge should interpret the contract accordingly.’ “
      17. This Court in the case of Bharat Aluminium Company vs.                 E
Kaiser Aluminium Technical Services INC reported in (2016) 4 SCC
126 observed thus:
     “10. In the matter of interpretation, the court has to make different
     approaches depending upon the instrument falling for interpretation.
     Legislative drafting is made by experts and is subjected to scrutiny        F
     at different stages before it takes final shape of an Act, Rule or
     Regulation. There is another category of drafting by lawmen or
     document writers who are professionally qualified and experienced
     in the field like drafting deeds, treaties, settlements in court, etc.
     And then there is the third category of documents made by laymen
                                                                                 G
     who have no knowledge of law or expertise in the field. The legal
     quality or perfection of the document is comparatively low in the
     third category, high in second and higher in first. No doubt, in the
     process of interpretation in the first category, the courts do make
     an attempt to gather the purpose of the legislation, its context and
     text. In the second category also, the text as well as the purpose          H
1040            SUPREME COURT REPORTS                               [2019] 8 S.C.R.


 A           is certainly important, and in the third category of the documents
             like wills, it is simply intention alone of the executor that is relevant.
             In the case before us, being a contract executed between the two
             parties, the court cannot adopt an approach for interpreting a statue.
             The terms of the contract will have to be understood in the way
             the parties wanted and intended them to be. In that context,
 B
             particularly in agreements of arbitration, where party autonomy is
             the ground norm, how the parties worked out the agreement, is
             one of the indicators to decipher the intention, apart from the plain
             or grammatical meaning of the expressions and the use of the
             expressions at the proper places in the agreement.”
 C            18. Recently, this Court had an occasion to consider the issue
       with regard to interpretation of certain clauses of PPA, in the case of
       Nabha Power Ltd. (NPL) vs. Punjab State Power Corporation Ltd.
       (PSPCL) and Anr. reported in 2018 (11) SCC 508. The Court referred
       to various English and Australian judgments as well as the judgments by
 D     this Court on the issue. We do not wish to burden this judgment with all
       the English and Australian judgments reproduced in the said judgment.
       However, it will be relevant to refer to the following passage of the
       decision of the Privy Council in the case of Attorney General of Belize
       vs. Belize Telecom Ltd., (2009) 1 WLR 1988 (PC): reproduced in Nabha
       Power Ltd.
 E
             “17. The question of implication arises when the instrument does
             not expressly provide for what is to happen when some event
             occurs. The most usual inference in such a case is that nothing is
             to happen. If the parties had intended something to happen, the
             instrument would have said so. Otherwise, the express provisions
 F           of the instrument are to continue to operate undisturbed. If the
             event has caused loss to one or other of the parties, the loss lies
             where it falls.”
             19. We may also gainfully reproduce certain judgments which
       have been reproduced in the case of Nabha Power Ltd. (supra).
 G
             “46. There were, once again, parallel developments in India during
             this period in various High Courts but the views of this Court can
             be found expression in Dhanrajamal Gobindram v. Shamji
             Kalidas and Co., (1961) 3 SCR 1020: AIR 1961 SC 1285
             (AIR pp. 1291 – 92, para 19)
 H
    M/S ADANI POWER (MUNDRA) LTD. v. GUJARAT                                    1041
ELECTRICITY REGULATORY COMMISSION [B. R. GAVAI, J.]

       “19. .... Commercial documents are sometimes expressed in                A
       language which does not, on its face, bear a clear meaning.
       The effort of courts is to give a meaning, if possible. This was
       laid down by the House of Lords in Hillas & Co. v. Arcos
       Ltd. {1932 All ER Rep 494 (HL)}, and the observations of
       Lord Wright have become classic, and have been quoted with
                                                                                B
       approval both by the Judicial Committee and the House of Lords
       ever since. The latest case of the House of Lords is Adamastos
       Shipping Co. Ltd. v. Anglo-Saxon Petroleum Co. Ltd. {1959
       AC 133 : (1958) 2 WLR 688 (HL)}. There, the clause was
       “This bill of lading”, whereas the document to which it referred
       was a charter-party. Viscount Simonds summarised at AC p.                C
       158 all the rules applicable to construction of commercial
       documents, and laid down that effort should always be made
       to construe commercial agreements broadly and one must not
       be astute to find defects in them, or reject them as
       meaningless.”
                                                                                D
    47. In Union of India v. D.N. Revri & Co.{(1976) 4 SCC 147},
    P.N. Bhagwati, J. (as he then was), speaking for the Bench of
    two Judges said in para 7 as under : (SCC p. 151)
       “7. It must be remembered that a contract is a commercial
       document between the parties and it must be interpreted in               E
       such a manner as to give efficacy to the contract rather than
       to invalidate it. It would not be right while interpreting a contract,
       entered into between two lay parties, to apply strict rules of
       construction which are ordinarily applicable to a conveyance
       and other formal documents. The meaning of such a contract
       must be gathered by adopting a common sense approach and                 F
       it must not be allowed to be thwarted by a narrow, pedantic
       and legalistic interpretation. ...”
    48. Lastly, in Satya Jain v. Anis Ahmed Rushdie {(2013) 8 SCC
    131}, Ranjan Gogoi, J., elucidated the well-established principles
    of the classic test of business efficacy to achieve the result of           G
    consequences intended by the parties acting as prudent
    businessmen. It was opined as under: (SCC pp. 143-44, paras 33-
    35)
       “33. The principle of business efficacy is normally invoked to
       read a term in an agreement or contract so as to achieve the             H
1042      SUPREME COURT REPORTS                            [2019] 8 S.C.R.


 A        result or the consequence intended by the parties acting as
          prudent businessmen. Business efficacy means the power to
          produce intended results. The classic test of business efficacy
          was proposed by Bowen, L.J. in The Moorcock {(1889) LR
          14 PD 64 (CA)}. This test requires that a term can only be
          implied if it is necessary to give business efficacy to the contract
 B
          to avoid such a failure of consideration that the parties cannot
          as reasonable businessmen have intended. But only the most
          limited term should then be implied – the bare minimum to
          achieve this goal. If the contract makes business sense without
          the term, the courts will not imply the same. The following
 C        passage from the opinion of Bowen, L.J. in The Moorcock
          {(1889) LR 14 PD 64 (CA)} sums up the position : (PD p. 68)
             ‘...... In business transactions such as this, what the law
             desires to effect by the implication is to give such business
             efficacy to the transaction as must have been intended at
 D           all events by both parties who are businessmen; not to impose
             on one side all the perils of the transaction, or to emancipate
             one side from all the chances of failure, but to make each
             party promise in law as much, at all events, as it must have
             been in the contemplation of both parties that he should be
             responsible for in respect of those perils or chances.’
 E
       34. Though in an entirely different context, this Court in United
       India Insurance Co. Ltd. v. Manubhai Dharmasinhbhai
       Gajera {(2008) 10 SCC 404} had considered the circumstances
       when reading an unexpressed term in an agreement would be
       justified on the basis that such a term was always and obviously
 F     intended by and between the parties thereto. Certain observations
       in this regard expressed by courts in some foreign jurisdictions
       were noticed by this Court in para 51 of the Report. As the same
       may have application to the present case it would be useful to
       notice the said observations : (SCC p. 434)
 G        ‘51. ... “... ‘Prima facie that which in any contract is left to be
          implied and need not be expressed is something so obvious
          that it goes without saying; so that, if, while the parties were
          making their bargain, an officious bystander, were to suggest
          some express provision for it in their agreement, they would
 H        testily suppress him with a common “Oh, of course!” ’ Shirlaw
    M/S ADANI POWER (MUNDRA) LTD. v. GUJARAT                                   1043
ELECTRICITY REGULATORY COMMISSION [B. R. GAVAI, J.]

         v. Southern Foundaries (1926) Ltd. {(1939) 2 KB 206 :                 A
         (1939) 2 All ER 113 (CA)}, KB p. 227.”
                           *           *        *      *
         “...An unexpressed term can be implied if and only if the court
         finds that the parties must have intended that term to form part
         of their contract: it is not enough for the court to find that such   B
         a term would have been adopted by the parties as reasonable
         men if it had been suggested to them: it must have been a term
         that went without saying, a term necessary to give business
         efficacy to the contract, a term which, although tacit, formed
         part of the contract which the parties made for themselves.”          C
         Trollope and Colls Ltd. v. North West Metropolitan Regl.
         Hospital Board {(1973) 1 WLR 601 : (1973) 2 All ER 260
         (HL)}, WLR p. 609 C-D : All ER p. 268 a-b.’ (emphasis in
         original)
      35. The business efficacy test, therefore, should be applied only        D
      in cases where the term that is sought to be read as implied is
      such which could have been clearly intended by the parties at the
      time of making of the agreement. ...”
      After reproducing the paras from earlier judgment, this Court
through Sanjay Kishan Kaul, J. observed thus:                                  E
      “49. We now proceed to apply the aforesaid principles which
      have evolved for interpreting the terms of a commercial contract
      in question. Parties indulging in commerce act in a commercial
      sense. It is this ground rule which is the basis of The Moorcock
      {(1889) LR 14 PD 64 (CA)} test of giving “business efficacy” to          F
      the transaction, as must have been intended at all events by both
      business parties. The development of law saw the “five condition
      test” for an implied condition to be read into the contract including
      the “business efficacy” test. It also sought to incorporate “the
      Officious Bystander Test” [Shirlaw v. Southern Foundries
      (1926) Ltd. {(1939) 2 KB 206 : (1939) 2 All ER 113 (CA)}].               G
      This test has been set out in B.P. Refinery (Westernport)
      Proprietary Ltd. v. Shire of Hastings {1977 UKPC 13 : (1977)
      180 CLR 266 (Aus)} requiring the requisite conditions to be
      satisfied : (1) reasonable and equitable; (2) necessary to give
      business efficacy to the contract; (3) it goes without saying i.e.
                                                                               H
1044             SUPREME COURT REPORTS                            [2019] 8 S.C.R.


 A            the Officious Bystander Test; (4) capable of clear expression;
              and (5) must not contradict any express term of the contract. The
              same penta-principles find reference also in Investors
              Compensation Scheme Ltd. v. West Bromwich Building Society
              {(1998) 1 WLR 896 : (1998) 1 All ER 98 (HL)} and Attorney
              General of Belize v. Belize Telecom Ltd. {(2009) 1 WLR 1988
 B
              (PC)}. Needless to say that the application of these principles
              would not be to substitute this Court’s own view of the presumed
              understanding of commercial terms by the parties if the terms are
              explicit in their expression. The explicit terms of a contract are
              always the final word with regard to the intention of the parties.
 C            The multi-clause contract inter se the parties has, thus, to be
              understood and interpreted in a manner that any view, on a particular
              clause of the contract, should not do violence to another part of
              the contract.”
               20. It could thus be seen that it is more than well settled that the
 D     clauses in the agreement ought to be given the plain, literal and
       grammatical meaning of the expression used in the same. No doubt, that
       the courts will also try to gather as to what intention the parties wanted
       to give them. As has been held by Ranjan Gogoi, J. (as His Lordship
       then was) the principle of business efficacy could be invoked only if by
       a plain literal interpretation of the term in the agreement or the contract,
 E     it is not possible to achieve the result or the consequence intended by the
       parties acting as prudent businessmen. This test requires that a term can
       only be implied, if it is necessary to give business efficacy to the contract,
       to avoid such a failure of consideration that the parties cannot as
       reasonable businessmen have intended. If the contract makes business
 F     sense without the term, the courts will not imply the same. It is amply
       clear that courts can imply a clause only if it is found that the plain and
       literal meaning given to the expression used in the terms is not in a
       position to make out the intention of the parties. Reading an unexpressed
       term in an agreement would be justified on the basis that such a term
       was always and obviously intended by and between the parties thereto.
 G     An unexpressed term can be implied if and only if the court finds that
       the parties must have intended that term to form part of their contract. It
       is not enough for the court to find that such a term would have been
       adopted by the parties as reasonable men if it had been suggested to
       them. It must have been a term that went without saying, a term
 H     necessary to give business efficacy to the contract, a term which,
    M/S ADANI POWER (MUNDRA) LTD. v. GUJARAT                                    1045
ELECTRICITY REGULATORY COMMISSION [B. R. GAVAI, J.]

although tacit, forms part of the contract. As held in the case of Nabha        A
Power Ltd. (supra), for invoking the business efficacy test and carving
out an implied condition, not expressly found in the language of the
contract, the following five conditions will have to be satisfied:
      (1) Reasonable and equitable;
      (2) Necessary to give business efficacy to the contract;                  B

      (3) It goes without saying i.e. the Officious Bystander Test;
      (4) Capable of clear expression; and
      (5) Must not contradict any express term of the contract.
                                                                                C
      21. We have to examine the present case and the correctness or
otherwise of the judgment and order passed by the Appellate Tribunal
by applying the aforesaid tests.
       22. We have hereinbefore reproduced Articles 3 and 4 of the
PPA. Article 3 provides for conditions subsequent to be satisfied by the
                                                                                D
seller and the procurer. Clause (ii) of Article 3.1.2 requires the seller to
have executed FSA and provided the copies of the same to the procurer
within 12 months from the effective date or 14 months from the date of
issue of Letter of Intent, whichever is later, unless such completion is
affected due to the procurer’s failure to comply with its obligations under
the PPA or by any force majeure event. Article 3.4 provides for                 E
consequences of non-fulfilment of conditions under Article 3.1; sub-
clauses (i) and (ii) of Article 3.4.2 specifically provide that if fulfilment
of any of the conditions specified in Article 3.1.2 is delayed beyond the
period of 3 months and the seller fails to furnish any additional
performance guarantee to the procurer or if the seller after furnishing
                                                                                F
additional performance guarantee to the procurer fails to fulfil the
conditions specified in Article 3.1.2 for a period of 8 months beyond the
period specified therein, both the procurer or the seller shall have the
right to terminate the agreement by giving a notice to the other party in
writing of at least 7 days. The only requirement is that in the event of
termination either by the procurer or the seller, the seller shall be liable    G
to pay the procurer an amount equivalent to Rs. 10 lakhs per MW of the
contracted capacity as liquidated damages. It is thus clear that in the
event of non-compliance with any of the requirements as provided in
Article 3.1.2 within the period specified in the said Article, an option is
available both to the seller or the procurer to terminate the PPA. The
                                                                                H
1046               SUPREME COURT REPORTS                          [2019] 8 S.C.R.


 A     only requirement is that, in either of the situations, the liability would be
       only on the seller to pay the liquidated damages at the rate of Rs. 10
       lakhs per MW.
             23. The Appellate Tribunal has held that only in the event there is
       an agreement between the parties that any of the terms specified in
 B     Article 3.1.2 is violated, the provisions of Article 3.4.2 can be invoked.
            24. It will be relevant to quote certain observations made in the
       judgment of the Appellate Tribunal which are as follows:
             “85. The perusal of Article 3.1.2 of the PPA would make it clear
             that the Appellant undertook to perform the condition subsequent
 C           to the execution of the Power Purchase Agreement. The Seller’s
             right to terminate the Power Purchase Agreement as mentioned
             above can only arises upon the Procurer’s default in complying
             with its obligation under Article 3.1.2.
             ...
 D
             89.(iii) Article 3.4.2 provides a situation under which the Power
             Purchase Agreement can be terminated either by the Procurer or
             by the Seller only when the events provided in Article 3.4.2 (i)
             and (ii) arise or occur. Although Article 3.4.2 appears to provide a
             right to both the parties to terminate the PPA on happening of
 E           such events specified in Article 3.4.2 (i) and (ii), the same has to
             be read and interpreted along with the other Articles of the PPA.
             Article 3.4.2 further provides that the Seller shall be liable to pay
             the Procurer an amount of Rs.10 Lakhs per MW as liquidated
             damages if the Procurer or the Seller elects terminate the
 F           agreement on happening of events specified in the earlier part of
             the Article 3.4.2. From the reading of the said Article 3.4.2, it is
             clear that either party can terminate the PPA, if the events
             specified in Article 3.4.2 (i) and (ii) occur and in case of such
             termination by either party, the Seller alone has the obligation to
             pay liquidated damages.
 G
             ...
             89(vi) ..... If the seller fails to fulfill the conditions specified in
             Article 3.1.2, the right to terminate under Article 3.4.2 is invoked
             by the Procurer. Similarly, the ability of either party to terminate
             the PPA under Article 3.4.2 will arise only if both the parties accept
 H
    M/S ADANI POWER (MUNDRA) LTD. v. GUJARAT                                      1047
ELECTRICITY REGULATORY COMMISSION [B. R. GAVAI, J.]

       happening of events specified under Article 3.4.2 (i) and (ii). In         A
       other words, the termination by the Seller under Article 3.4.2 is
       possible if both the parties agree to the happening of the events
       contemplated therein and the Seller is willing to pay the liquidated
       damages if a dispute arises regarding the event of termination.”
        25. The aforesaid observations of the Appellate Tribunal, in our          B
view, depict a totally erroneous approach. A harmonious reading of Article
3.4.2 and Article 3.1.2 clearly indicates that in the event of non-compliance
of any of the conditions as stipulated in Article 3.1.2 within the period
prescribed thereunder, either of the parties, i.e., the seller or the procurer
have the right to terminate the contract. However, in either of the events,
it is the seller’s liability to pay the liquidated damages at the rate of Rs.     C
10 lakhs per Mega Watt.
       26. We are of the considered view that the finding of the Appellate
Tribunal that the provisions under Article 3.4.2 of the PPA can be invoked
only when there is an agreement between the parties that there is violation
of any of the conditions specified in Article 3.1.2 of the PPA is totally         D
incorrect. If such an argument is accepted, it will amount to inserting a
totally new condition in Article 3.4.2 of the PPA and would amount to
re-writing the contract between the parties; it would do total violence to
the provisions of Article 3.4.2 of the PPA. It cannot be said to be a
condition which is either reasonable or equitable; it also cannot be said         E
to be a condition which is necessary to give business efficacy to the
contract; it also cannot be said to be a test which justifies the Officious
Bystander Test; it also cannot be said to be a condition which is capable
of the clear expression; it is also not a condition which does not contradict
any expressed terms of the contract. On the contrary, is a condition
which would totally change the tenor of Article 3.4.2 of the PPA. We              F
are, therefore, of the considered view that the Appellate Tribunal has
grossly erred in coming to the conclusion that Article 3.4.2 of the PPA
could be invoked only in the event that there is an agreement with regard
to violation of any of the conditions in Article 3.1.2.
       27. The Tribunal, while arriving at its finding, has held that agreement   G
has to be read as a whole and if it is read as whole and if Articles 3.4.2
and 3.1.2 and Article 14 are harmoniously read, then the only conclusion
that can be drawn is that provisions of Article 3.4.2 can be invoked, only
if there is an agreement between the parties, that the conditions specified
                                                                                  H
1048            SUPREME COURT REPORTS                           [2019] 8 S.C.R.


 A     in Article 3.1.2 have not been complied with. Let us test the correctness
       of this finding.
             28. The Constitution Bench of this Court in the case of Calcutta
       Gas Company (Proprietary) Ltd. vs. State of West Bengal and others
       reported in AIR 1962 SC 1044, while construing the entries in the List in
 B     Schedule VII of the Constitution has observed thus:
             “8 ….....The Rule of construction adopted by that decision for
             the purpose of harmonizing the two apparently conflicting entries
             in the two Lists would equally apply to an apparent conflict
             between two entries in the same List. Patanjali Sastri, J., as he
 C           then was, held in State of Bombay v. Narothamdas Jethabhai,
             1951 SCR 51 : (AIR 1951 SC69) that the words “administration
             of justice” and “constitution and organization of all courts” in item
             one of List II of the Seventh Schedule to the Government of India
             Act, 1935 must be understood in a restricted sense excluding from
             their scope “jurisdiction and powers of courts” specifically dealt
 D           with in item 2 of List II. In the words of the learned Judge, if such
             a construction was not given “the wider construction of entry 1
             would deprive entry 2 of all its contents and reduce it to useless
             lumber.” This rule of construction has not been dissented from in
             any of the subsequent decisions of this Court. It may, therefore,
 E           be taken as a well settled rule of construction that every attempt
             should be made to harmonize the apparently conflicting entries
             not only of different Lists but also of the same List and to reject
             that construction which will rob one of the entries of its entire
             content and make it nugatory.”

 F            Though the aforesaid observations are made while construing the
       entries in the List in Schedule VII and though while interpreting the
       clauses in the agreement the strict principle of interpretation would not
       be applicable, the Court can borrow the said principle while interpreting
       the same. It has been held by this Court that every attempt has to be
       made to harmonize apparently conflicting entries not only of different
 G     Lists but also of the same List and to reject that construction which will
       rob one of the entries of its entire content and make it nugatory.
            29. Again, while interpreting the provisions of Section 47 and Order
       XXI, Rule 2 of the CPC, this Court in the case of Sultana Begum vs.
       Prem Chand Jain reported in AIR 1997 SC 1006, has observed thus:
 H
    M/S ADANI POWER (MUNDRA) LTD. v. GUJARAT                                  1049
ELECTRICITY REGULATORY COMMISSION [B. R. GAVAI, J.]

      “12....... On a conspectus of the case law indicated above, the         A
      following principles are clearly discernible:
             (1) It is the duty of the Courts to avoid a head on clash
                 between two Sections of the Act and to construe the
                 provisions which appear to be in conflict with each
                 other in such a manner as to harmonize them.                 B
             (2) The provisions of one Section of a statute cannot be
                 used to defeat the other provisions unless the Court, in
                 spite of its efforts finds it impossible to effect
                 reconciliation between them.
             (3) It has to be borne in mind by all the Courts all the time    C
                  that when there are two conflicting provisions in an
                  Act, which cannot be reconciled with each other, they
                  should be so interpreted that, if possible, effect should
                  be given to both. This is the essence of the rule of
                  “harmonious construction”.                                  D
             (4) The Courts have also to keep in mind that an
                 interpretation which reduces one of the provisions as
                 a “dead letter” or “useless lumber” is not harmonious
                 construction.
             (5) To harmonize is not to destroy any statutory provision       E
                  or to render it otiose.”
                                                        (emphasis given)
      It could thus be seen that this Court has clearly held that to
harmonize is not to destroy any statutory provision or to render it otiose.
                                                                              F
This principle has been reiterated in the case of Anwar Hasan Khan
vs. Mohammed Shafi and others reported in AIR 2001 SC 2984. While
considering the provisions of U.P. Urban Buildings (Regulation of Letting,
Rent and Eviction) Act, this Court observed thus :
      “8. It is settled that for interpreting a particular provision of an
      Act, the import and effect of the meaning of the words and phrases      G
      used in the statute has to be gathered from the text, the nature of
      subject-matter and the purpose of intention of the statute. It is
      cardinal principle of construction of statute that effort should be
      made in construing its provisions by avoiding the conflict and
      adopting a harmonious construction. The statute or rules made           H
1050             SUPREME COURT REPORTS                            [2019] 8 S.C.R.


 A           thereunder should be read as a whole and one provision should be
             construed with reference to the other provision to make the
             provision consistent with the object sought to be achieved. The
             well-known principle of harmonious construction is that effect
             should be given to all the provisions and a construction that reduces
             one of the provision to a “dead letter” is not harmonious
 B
             construction.......”
              30. Applying the aforesaid principles to various clauses of the
       agreement, an attempt has to be made to harmoniously read the provisions
       of Articles 3.1.2, 3.4.2 and 14.1, 14.2, 14.3 and 14.4. An attempt has
       also to be made to give effect to all the provisions. If so read, it will be
 C     clear that Article 14 deals with various eventualities in which procurer
       or the seller can terminate the agreement. Article 14.1 provides for
       termination in the event of various defaults committed by the seller. Article
       14.3 provides for procedure to be followed in cases of default by the
       seller. Article 14.2 provides various grounds with regard to default by
 D     procurer. The procedure for termination in cases of default by the procurer
       has been provided in Article 14.4. Perusal of grounds stated in Articles
       14.1 and 14.2 would reveal that these are general in nature. Per contra,
       provisions of Article 3.4.2 would reveal that termination under this Article
       can be made only if there is non-compliance with any of the conditions
       in Article 3.1.2. The power is available to both procurer and seller.
 E     However, in either of the cases i.e. termination by seller or termination
       by procurer, there is a specific provision of damages at the rate of Rs 10
       lakhs per MW, whereas consequences of the termination in Articles
       14.1 and 14.2 are totally different. As such, effect will have to be given
       to both the provisions, which are independent of each other.
 F           31. We find, that both the Commission and the Appellate Tribunal
       have grossly erred in arriving at finding that termination can be effected
       under Article 3.4.2 only if there is an agreement with regard to non-
       compliance of condition under Article 3.4.2 by both the parties. If the
       finding of the Appellate Tribunal is accepted, it will be amounting to
 G     making provisions of Article 3.4.2 a dead letter and rendering them otiose.
              32. We further find that the Commission as well as the Appellate
       Tribunal has lost sight of one another important principle of law. This
       Court in the case of J.K. Cotton Spinning and Weaving Mills Co.
       Ltd. vs. State of Uttar Pradesh, reported in AIR 1961 SC 1170, while
 H
    M/S ADANI POWER (MUNDRA) LTD. v. GUJARAT                                     1051
ELECTRICITY REGULATORY COMMISSION [B. R. GAVAI, J.]

construing the provisions of Clause 5(a) and Clause 23 of the U.P.               A
Industrial Disputes Act and the U.P. Government Order issued under
the U.P. Industrial Disputes Act, has observed thus :
      “(10) Applying this rule of construction that in cases of conflict
      between a specific provision and a general provision the specific
      provision prevails over the general provision and the general              B
      provision applies only to such cases which are not covered by the
      special provision, we must hold that cl. 5(a) has no application in
      a case where a special provisions of cl. 23 are applicable.”
      33. The said principle has been reiterated by this Court in its
judgment in the case of Maharashtra State Board of Secondary and                 C
Higher Secondary Education and Ors. Vs. Paritosh Bhupeshkumar
Sheth and Ors. reported in (1984) 4 SCC 27. Para 20 of the said
judgment reads thus:
      “20. We consider that the above approach made by the High
      Court is totally fallacious and is vitiated by its failure to follow the   D
      well established doctrine of interpretation that the provisions
      contained in a statutory enactment or in rules/regulations framed
      thereunder have to be so construed as to be in harmony with each
      other and that where under a specific section or rule a particular
      subject has received special treatment, such special provision will
      exclude the applicability of any general provision which might             E
      otherwise cover the said topic.........”
       34. In the present case, the perusal of various Articles would
reveal that provisions under Article 14 are general in nature. The provision
under Article 3.4.2 is specific, only to be invoked in the case of non-
compliance with any of the conditions as provided under Article 3.1.2.           F
As such, the special provision made in Article 3.4.2 will exclude the
applicability of general provisions contained in Article 14 of the contract.
       35. After considering the legal position, let us examine some of
the factual aspects of the matter. It would be relevant to note that in the
bid dated 2.01.2007 submitted by the appellant, it is clearly mentioned          G
that the project is based on coal supply from the GMDC.
       36. It will also be relevant to refer to Clause 1.2 of Annexure 3 to
the bid document which gives details of the proposed project. Clause
1.2 reads as follows:
                                                                                 H
1052            SUPREME COURT REPORTS                           [2019] 8 S.C.R.


 A             “1.2 Fuel:
             The lead member, Adani Enterprises Ltd. has tied up the indigenous
             coal requirement of the Project with GMDC, who has been
             allocated Morga II coal block in the State of Chhatisgarh. Further
             with a view to ensure supply of fuel with optimum techno-
 B           commercial parameters, we have also tied up supply of imported
             coal with M/s Coal Orbis Trading GMBH, Germany and M/s Kowa
             Company Ltd. and accordingly executed separate MoUs with
             them dated 9th Sept 2006 and 21st Dec 2006 respectively.”
              37. In the brief summary of the Project given in the said bid
 C     document, it has been specifically mentioned by the appellant that the
       bid was submitted on the basis of indigenous coal supply committed by
       the GMDC. The bid documents also form part of the PPA between the
       parties.
              38. It will be relevant to note that after the communication dated
 D     15.11.2008 by the appellant to the procurer thereby conveying its intention
       to terminate the PPA in the wake of pending FSA with the GMDC for
       supply of power under bid No. 2, the Managing Director of Gujarat Urja
       Vikas Nigam Ltd., the procurer, had addressed a communication to the
       Principal Secretary, Energy and Petrochemicals Department, Government
       of Gujarat, requesting it to issue suitable directions since the issue
 E     regarding allocation of coal from the mines allocated to the GMDC was
       within the purview of Government of Gujarat. Thereafter, on 27.02.2009
       the Deputy Secretary of the Industries and Mines Department,
       Government of Gujarat, addressed a communication to the Managing
       Director of the GMDC. It will be relevant to record the following part of
 F     the said letter.
             “(b) So far as Naini block is concerned, GMDC had already given
             a commitment for supply of coal from Morga-II mines to M/s.
             Adani Ltd., for a 1000 MW plant on the basis of which M/s.
             Adani submitted their bid in the competitive tariff bid to GUVNL
 G           at Gujarat bus-bar. Considering this aspect and the full availability
             to the state, 50% block may be given M/s. Adani Ltd and remaining
             50% block may be given to Torrent Power Ltd., to exclusively
             provide power for Gujarat’s need. M/s.Adani and M/s.TPL have
             to sell power generated from Naini Block exclusively to GUVNL.
             No merchant sale is to be allowed to anyone else.
 H
    M/S ADANI POWER (MUNDRA) LTD. v. GUJARAT                                     1053
ELECTRICITY REGULATORY COMMISSION [B. R. GAVAI, J.]

       2. You are now, therefore requested to go for coal allotment from         A
       Morga block with M/s. KSK by way of the detailed FSA and to
       give 50% coal from Naini block to M/s. Adani and remaining
       50% coal to M/s.Torrent Power Ltd., as mentioned above.”
       39. It could thus be clearly seen that even the Government of
Gujarat has also clearly indicated that the bid submitted by the appellant       B
in the competitive bid was on the basis of the commitment for supply of
coal from Morga-II mines by the GMDC. It has, therefore, requested
the Managing Director, GMDC to give 50 per cent of coal from Morga
block to the appellant. The State Government had, therefore, requested
that the Managing Director of the GMDC to go for coal allotment from
Morga block.                                                                     C

       40. It will also be relevant to note that on 30.12.2009, the Executive
(Finance) of the procurer has addressed a letter to the Principal Secretary,
Energy and Petrochemicals Department, Government of Gujarat,
referring to the letter issued by the appellant on 28.12.2009. After referring
to Article 3.4.2 of the PPA, it is stated in the said communication as           D
under:
       “In light of above circumstances Government of Gujarat is
       requested to impress upon M/s.APL to withdraw the Notice of
       Termination of PPA dated 2nd February, 2007, executed with
       GUVNL, for supply of 1000 MW under bid specification no.02/               E
       LTPP/2006 and also impress upon GMDC for prompt necessary
       action for execution of FSA with M/s. APL to ensure supply of
       1000 MW power to GUVNL at competitive rate to meet future
       demand of the state. Further Government of Gujarat is requested
       to kindly issue suitable directives to GUVNL for further necessary        F
       action in the matter.”
      41. It could thus be seen that, even the procurer was aware that
the bid of the appellant was on the basis of the commitment by the
GMDC to supply the indigenous coal.
       42. In view of the aforesaid, it could be seen that the appellant as      G
well as the procurer and also the Government of Gujarat clearly
understood that the bid submitted by the appellant was on the basis of
the commitment of the GMDC to supply indigenous coal to it. It will be
pertinent to mention that the appellant had sent notices intimating its
intention to terminate the PPA on account of non-finalisation of FSA
                                                                                 H
1054             SUPREME COURT REPORTS                           [2019] 8 S.C.R.


 A     with the GMDC and also terminate the contract much prior to
       commissioning of the project and commencement of power supply to
       the procurer. Annexure III to the PPA would itself show that expected
       commercial date of operation is January, 2012, whereas termination is
       vide notice dated 28.12.2009. The materials placed on record would
       reveal that the appellant has supplied the power at the rate of Rs. 2.35
 B
       per unit (as per bid) after the PPA was terminated by it, to abide by the
       directions issued by the Commission. It may not be out of place to mention
       that the appellant was a successful bidder in respect of the two bids i.e.
       bid No. 1 and bid No. 2. Insofar as bid No. 2, which is the subject matter
       of the present proceedings, the bid of the appellant was accepted at the
 C     rate of Rs. 2.35 per unit whereas in the same bidding process, bid of the
       appellant for bid No. 1 was accepted at the rate of Rs. 2.89 per unit.
       The said Project was to be executed on the basis of imported coal supply.
       It is thus clear that the parties were very much aware that bid of the
       purchaser for bid No. 1 which was at a much lower price than the price
       for bid No. 2 was on account of the commitment to the appellant from
 D
       the GMDC that it would supply indigenous coal to it.
             43. In that view of the matter, after the GMDC resiling from its
       commitment and refusing to enter into FSA with the appellant, the
       appellant was justified in invoking Article 3.4.2 of the PPA, in view of
       non-compliance of Condition No. (ii) in Article 3.1.2 since it had failed to
 E     produce the Fuel Supply Agreement. It will also be relevant to refer to
       Paragraph 70 of the judgment of the Appellate Tribunal. Paragraph 70
       reads as under:
             “Admittedly, the Seller, the Appellant mentioned in the bid
             documents that “Adani Enterprises Limited has tied-up indigenous
 F           coal requirements of the project with the Gujarat Mineral
             Development Corporation, who has been allocated Morga-II Block
             in the State of Chhatisgarh”. The Appellant has also mentioned in
             the bid documents that with a view to ensure the supply of fuel,
             they have tied-up supply of imported coal with two foreign
 G           Companies and accordingly executed separate Memorandum of
             Understanding with them dated 9.9.2006 and 21.12.2006.”
             44. In the light of the aforesaid finding, we fail to understand as to
       how the Appellate Tribunal has come to a finding that the bid of the
       appellant was not on the basis of the commitment by the GMDC to
 H
    M/S ADANI POWER (MUNDRA) LTD. v. GUJARAT                                   1055
ELECTRICITY REGULATORY COMMISSION [B. R. GAVAI, J.]

supply indigenous coal. We are of the considered view that the Appellate       A
Tribunal has erred both on facts and in law. We are of the considered
view that the appellant was entitled in law as well as on facts to invoke
Article 3.4.2 of the PPA and terminate the agreement.
       45. Having held that the termination was legal and valid the question
arises as to what relief is to be granted to the appellant. On the basis of    B
the Order of the Commission and the Appellate Tribunal, the appellant is
continuing supply of electricity to the respondent No. 2, the procurer,
though it is the contention of the appellant that it has been sustaining
losses by doing so.
      46. It will be relevant to refer to certain subsequent developments.     C
The appellant had approached this Court by Interlocutory Application
No. 4 of 2015 for the following reliefs:
        “(a)    to stay the operation of the impugned judgment dated
                 7.9.2011 and suspend further supply of electricity in terms
                 of the PPA during the pendency of this Appeal.                D
        (b)    in the alternative to prayer (a) above, during the pendency
                 of the accompanying Civil Appeal the Hon’ble Court
                 may direct the Respondent(s) to pay the tariff as per
                 CERC norms for tariff on cost plus basis; and also make
                 the payment from the date of the supply of power under        E
                 the PPA of the differential amount between the PPA
                 tariff and the tariff as per CERC norms for tariff on
                 cost plus basis on the such terms and condition as this
                 Hon’ble court deems fit as just and proper.”
       47. The said application came up for consideration before the           F
Bench consisting of J. Chelameswar, and Abhay Manohar Sapre, JJ. It
appears that in the said I.A. an affidavit dated 23.11.2015 came to be
filed on behalf of the respondent No. 2, the procurer. It will be relevant
to note the averments made in the affidavit quoted in the Order dated
3.12.2015 passed by this Court.
                                                                               G
      “15. I submit that, without prejudice to the rights of the Respondent
          No.2 to contest the present appeal, the answering Respondent
          with the approval of Government of Gujarat has already shown
          its willingness to pay compensatory tariff prospectively (from
          next month of CERC order i.e. March 2014) subject to paras
                                                                               H
1056             SUPREME COURT REPORTS                            [2019] 8 S.C.R.


 A                12 and 13 above to resolve the issue by making suitable
                  adjustments in tariff which till date is not implemented because
                  of non acceptance by Appellant and other stakeholders.
             16. I say that without prejudice to its rights in the present appeals
                 the Respondent No.2 is willing to implement the decisions of
 B               State Govt. for paying compensatory tariff prospectively (from
                 next month of CERC order i.e. March 2014) to resolve the
                 issue by making suitable adjustment in tariff on the directions
                 of the Hon’ble Court. ...”
               48. This Court after hearing the parties observed that insofar as
 C     the question of permitting the supplier/procurer to pay the compensatory
       tariff, as indicated in its counter affidavit is concerned, it requires no
       permission from this Court and it was for the supplier/procurer to take a
       decision in accordance with law.
              49. Once we hold that termination is valid and legal, question would
 D     arise as to at what rate the appellant is entitled to compensatory tariff
       from the date of supply of power. Undisputedly, even after the PPA was
       validly terminated, the appellant continued to take the project to its logical
       end. After commissioning of the project, it has started supplying electricity
       to the procurer in accordance with the decision of the Commission and
       the Appellate Tribunal. The appellant must have incurred huge expenditure
 E     on the same. In order to do economic justice, on the principle of business
       efficacy, the appellant would be entitled for adjustment of cost of the
       project and would also be entitled to the interest on the expenditure
       incurred by it for completion of the project. The expenditure towards
       running of the project after obtaining the coal from the open market
 F     would also be required to be taken into consideration. The appellant
       would also be entitled to the interest on the delay of payment after it
       receives payment upon determination of the rate which would be
       determined by the Central Electricity Regulatory Commission (“CERC”
       for short). However, we find that it will not be appropriate for us to go
       into that exercise.
 G
             50. Section 62 of the Electricity Act, 2003, provides entire
       mechanism for determination of the tariff by the CERC. It will also be
       relevant to note that the CERC (Terms and Conditions of Tariff)
       Regulations 2009 also consider various factors which are required to be
       taken into consideration by the CERC while determining the
 H     compensatory tariff. We find that it will be appropriate to relegate the
    M/S ADANI POWER (MUNDRA) LTD. v. GUJARAT                                    1057
ELECTRICITY REGULATORY COMMISSION [B. R. GAVAI, J.]

parties to CERC for determination of the compensatory tariff payable to         A
the appellant from the date of termination of the PPA. After such
determination, the procurer would be entitled to adjust the amount if
already paid in accordance with affidavit dated 23.11.2015, from the
amount so determined by the CERC.
      51. Hence, the following order:                                           B
        (i)     The appeal is allowed.
        (ii)     The notice of termination of the PPA dated 28.12.2009
                is held to be legal and valid. It is also declared that the
                PPA stood validly terminated with effect from
                04.01.2010.                                                     C

        (iii)    The appellant would be at liberty to approach the CERC
                for determination of the compensatory tariff, including
                various aspects mentioned in paragraph 49, payable to it
                from the date of supply of electricity by it to the procurer.
                The CERC is directed to decide the said issue in the            D
                light of what has been observed by us hereinabove and
                in the light of the provisions of Section 62 of the
                Electricity Act so also the CERC (Terms and Conditions
                of Tariff) Regulations, 2009 within a period of three
                months from the appellant’s approaching it.                     E
        (iv)    The procurer shall make the payment to the appellant
                as determined by the CERC within a period of three
                months from the date of its determination.
        (v)      The procurer would be entitled to adjust the amount if
                already paid by it in pursuance of its affidavit dated          F
                23.11.2015 from the amount so determined by the
                supplier. The procurer shall be entitled to adjust the
                balance amount recoverable by it from the appellant
                towards liquidated damages of Rs. 100 Crore.
        (vi)    No order as to cost.                                            G


Ankit Gyan                                                    Appeal allowed.



                                                                                H


Search Indian case law

Ask in plain English, not just keywords. 25,000 AI words free, no card.

Try "Power Purchase Agreement"Sign in to search

For a digitally signed copy suitable for filing, refer to the court's own website. Only the court can issue one.