Created byFuzzy Cloud

Supreme Court of India

M/S. ASSOCIATED CONSTRUCTIONversusPAWANHANS HELICOPTERS PVT LTD

Citation
2008 INSC 604
Decided
7 May 2008
Disposal
Appeal(s) allowed

Holding

The Court held that where the contract contains a clause (clause 43) allowing escalation claims and time is of the essence, the arbitrator’s award granting such escalation is permissible and cannot be set aside, as courts do not sit in appeal over arbitral awards unless they are unconscionable.

Summary

The appellant, Mis. Associated Construction, entered into a construction contract with the respondent, Pawanhans Helicopters, which required completion within four months. Delays caused by the respondent led the appellant to issue a "No Dues Certificate" under alleged economic duress and later claim price escalation under clause 43 of the contract. An arbitral tribunal awarded the appellant escalation amounts, which the respondent challenged under sections 30 and 33 of the Arbitration Act, 1940. The High Court Division Bench set aside the award, holding that clause 34 barred escalation and that the "No Dues Certificate" was not given under duress. The Supreme Court reversed this, holding that clause 43 permits escalation claims when time is of the essence, that the arbitrator’s view was permissible, and that courts cannot sit as an appellate body over arbitral awards unless they are unconscionable. Consequently, the appeals were allowed, the Division Bench order set aside, and the Single Judge’s decision restored.

Issues considered

  • The scope of judicial interference with an arbitral award under sections 30 and 33 of the Arbitration Act, 1940.
  • Whether clause 34 of the contract bars any claim for price escalation.
  • Whether clause 43 provides a separate remedy for escalation despite clause 34.
  • Whether the "No Dues Certificate" was issued under duress, affecting the contractor’s right to further payment.
  • Whether the contractor is entitled to escalation compensation for delays attributable to the respondent beyond the contract period.

Legislation cited

Subjects

ArbitrationArbitral awardEscalation clauseContract interpretationDuressNo Dues CertificateTime is of the essenceSection 30 Arbitration Act 1940Section 33 Arbitration Act 1940Construction contract

Judgment

                          [2008] 7 3 C.R 970


A               MIS. ASSOCIATED CONSTRUCTION
                                   v.
              PAWANHANS HELICOPTERS PVT LTD
              (Civil Appeals Nos. 3376-3377 of 2008)
                             MAY 7, 2008
B
    [TARUN CHATTERJEE AND HARJIT SINGH BEDI, JJ.]

          Arbitration - Award - Challenge to - Held: The Court
    does not sit in appeal over an arbitral award - If view taken by
c   arbitrator permissible, it cannot be interfered with, on the
    premise that a different view is also possible - On facts. it
    cannot be said that the arbitra! award was so unconscionable
    that it required interference by Court

        Contract - For construction work - Between Appellant
D and Respondent-Government undertaking - Delay in                     ..
  complr->tion of work on account of reasons attributable to
  Respondent - Respondent demanded "No Dues Certificate"
  for release of payment - Appellant gave such certificate -
  Claim towards escalation by Appellant - On facts held: Even
E assuming that there could be no price escalation during
  pendency of the contract, such embargo could not be carried
  beyond that period as time was essence of the contract- Plea
  raised by Appellant that it issued "No Dues Certificate" under
  duress not an after thought.
F       Appellant-contracting firm entered into a contract for
  construction work with the Respondent, a Government
  of India undertaking. The construction work was
  scheduled to be completed in 4 month but the Appellant
  could not meet the deadline due to the fault of the
G Respondent. The Respondent demanded a "No Dues
  Certificate" for release of payment. Appellant gave such
  certificate allegedly "under duress" as it was in economic           ..
  distress. There was a disagreement between the parties
  over the payment of bills. The matter was referred for
H                             970
          MIS ASSOCIATED CONSTRUCTION v. PAWANHANS              971
                     HELICOPTERS PVT LTD.

         arbitration. The arbitral award passed was in favour of A
         Appellant. on which the Respondent moved the High
         Court. The Single Judge too held in favour of Appellant
         stating that clauses 18 and 34 of the contract, when read
         together, provided for the payment of escalation charges
......   as the work had not been completed within four months B
         on account of the fault on the part of the Respondent and
         that the said clauses did not prohibit such payment, more
         particularly as time was essence of the contract and as the
         contract was not on a fixed price, the prohibition of
         escalation was, if at all, to be read during the period of c
         contract only. The Single Judge also repelled the arguments
         of the Respondent that after having submitted the final bill
         on 25th October 1991, it was not open to the Appellant to
         submit a second final bill on 2nd February 1993 by
         observing that the payment received as a consequence of
                                                                      D
         the bills submitted on 25th October 1991, was "under
         duress" and it is on that account that the App~llant had
         given the aforesaid "No Dues Certificate". The Division
         Bench of the High Court however set aside the order of
         the Single Judge. Hence the present appeals.
                                                                      E
               Allowing the appeals, the Court
               HELD:1.1. Clause 43 and 43 (1) and (2) of the contract
         in question when read together clearly visualize escalation
         of price on account of reasons beyond the control of the
~        .
         contractor and attributable to the other side. Moreover, F
         clause 43 (2) clearly states that the remedy under clause 43(1)
         would be in addition to such other remedy that may be open
         to the contractor under the other provisions. Clause 43
         should be read in aid of the contractor as it clearly provides
         for indemnity in case there was a delay in the completion of G
         the work which could be attributable to the Respondent.
         Further, even assuming for a moment that there could be
          no price escalation during the period of 4 months i.e. during
         the pendency cf the contract, such embargo would not be
          carried beyond that period as time was the essence of the H
    972      SUPREME COURT REPORTS               [2008] 7 S.C.R.


A   contract. [Paras 7, 11] [981-C,D, 984-F,G]
       1.2. The Court does not sit as one in appeal over the
  award of the arbitrator and if the view taken by the
  arbitrator is permissible, no interference is called for on
  the premise that a different view was also possible. Also,
8 in commercial transactions, all situations cannot be
  visualized and the positive and unchallenged finding in
  the present case is that the delay in the execution of the
  work was occasioned on account of reasons attributable
  the to Respondent. It cannot, therefore, be said that the
C award of the arbitrator was so unconscionable that it
  required interference. [Para 7] [981-D,E,F,G]
       1.3. It was open to the Appellant-contractor to
  contend that it was liable to be compensated on account
D of the fact that delay had been occasioned on account of
  reasons attributable to Respondent. [Para 1O] [984-E]            ..
         MCD v M!s.Jagan Nath Ashok Kumar & Anr. (1987) 4
    SCC 497; PM.Paul v. Union of India (1989) Supp 1 SCC 368
    and K.N.Sathyapalan (0) By Lrs. v. State of Kera/a & Anr.
E   (2006) 12 SCALE 654- referred to.
        2.1. The desperate tone of the Appellant-contractor
  is supported by the letter of 10th January 1991 in which it
  was noted that though repeated requests had been made
  for the payment atleast against the bills certified by the
F Architect, a huge amount had been blocked arbitrarily over
  a long period of time and a request was made for its
  release. The letter dated 21st November 1991 is again a
  reminder to the Respondent asking for payment and that
  in case there was a dispute, the matter be referred to the
G arbitrator and submitting that payment should be made
  atleast with respect to those dues which had been
  certified by the Architect. The letter dated 9th December
  1991 from Respondent to the contractor shows that
  payment could be considered provided the contractor
H submitted a "No Claim Certificate". It appears that such
          MIS. ASSOCIATED CONSTRUCTION v. PAWANHANS             973
                      HELICOPTERS PVT LTD.

         certificate was indeed issued but with no result on which A
         the contractor in his letter dated 26th December 1991 in
         reply to the letter dated 9th December 1991, once again
         submitted that the payments be released in so far as they
         had been certified by the ArchitectsfConsultants and if
,_       there was a dispute regarding the other payments, they B
         should be referred to an arbitrator. When no action was
         taken, another letter dated 5th May 1992 was addressed
         to Respondent by the contractor stating that as they were
         facing economic duress on account of the payment being
         held back, and as a "No Claim Certificate" had been c
         issued, the payment be defrayed as promised or else they
         might have to refer the matter to the arbitrator. [Paras 12,
         15] [985-E,H, 986-A,F,G]
               2.2. It appears however that no steps were taken on
 .       which the contractor addressed a letter dated 2nd D
         February 1993 for payment of dues and again stated that
         if the payment was not made, the dispute should be
         referred to the arbitrator. In response to this letter,
         Respondent in its letter dated 9th February 1993 replied
         that the matter was under scrutiny and it would take about E
         2 months for verification and that the contractor would
         be informed in due course. As no reply was received, a
         letter dated 21st May 1993 was addressed by the
         contractor relating to the undertaking that the enquiry
         would be completed within 2 months but complaining that F
         nothing had been done and on the contrary on 8th June
         1993 the claim for any payment was rejected by
         Respondent observing that as a "No Dues Certificate" had
         been submitted by the contractor, the question of any
         balance payment being due did not arise. It is at this stage
                                                                      G
         that the contractor had invoked the clause for arbitration.
         The correspondence shows that the contractor was
     >   compelled to issue a "No Dues Certificate" and in this view
         of the matter, it could not be said that the contractor was
         bound by what he had written. It is also clear that there is
                                                                      H
    974       SUPREME COURT REPORTS                (2008] 7 S.C.R


A   voluminous correspondence over a span of almost 2
    years between the submission of the first final bill on 3rd
    June 1991 and the second final bill dated 2nd February
    1993 and as such the claim towards escalation or the plea
    of the submission of a "No Dues Certificate" under duress
B   being an after thought is not acceptable. [Para 16] [987 -       .•
    B-G]

          Mis. Ambica Construction v. Union of India (2006} 12
    SCALE 149 - referred to.
c       3. In the facts and circumstances of the case, in that
    Respondent has taken advantage of a beleaguered
    contractor, and has behaved in a most unbecoming
    manner in pushing it ever deeper into the chasm, the
    Appellant-contractor will have its costs which are
    computed at Rs.10,000/- [Para 17] [988-F,G]
0
        CIVIL APPELLATE JURISDCTION : Civil Appeal Nos.
    3376-3377 of 2008
          From the Judgment & Order dated 7.6.2007 0f the High
E   Court of Bombay in Appeal No. 840/1999 in Arbitration Petition
    No. 106 of 1997 and Appeal No. 1455/1999 in Arbitration
    Petition No. 108 of 1997
        Shyam Divan, Ajay Kumar, Richa Srivastava and lndu
    Sharma for the Appellant.
F        Raju Ramachandran, J. Buther, Amit Kumar, Geeta Kalra
    and Susmita Lal for the Respondent.
          The Judgment of the Court was delivered by
          HARJIT SINGH BEDI, J. 1. Leave granted.
G
       2. The respondent, Pawanhans Helicopters Pvt. Ltd.
  (hereinafter called "Pawanhans") a Government of India
  undertaking, floated two tenders for allocation of work for
  construction of a compound wall and a bridge over a nala.
H Pursuant to the aforesaid information, several tenders were
       MIS. ASSOCIATED CONSTRUCTION v. PAWANHANS                   975
        HELICOPTERS PVT LTD. [HARJIT SINGH BEDI, J]
 •
      received and the tenders of the appellant (hereinafter called the A
      "contractor") were ultimately accepted. Pursuant to the aforesaid,
      two formal agreements providing for the terms and conditions
      of the contract in the shape of general conditions of the contract
      and special conditions of the contract governing the execution
...   of work were duly signed on 12th October 1999. As per the B
      contract the work was required to be completed within four
      months. It appears that on account of some delay which was
      attributable to Pawanhans, the work did not proceed as per
      schedule and the contractor accordingly informed Pawanhans
      by letters dated 15th February 1990, 23rd February 1990, 24th      c
      March 1990, 26th June 1990 and 6th July 1990 that the work
      was getting delayed as the requisite facilities for its completion
      had not been provided and highlighting several factors
      attributable to it had supervened which had led to the delay. The
      contractor also in the meanwhile vide letters dated 27th July 1990
                                                                          D
      and 6th August 1990 requested the respondent to release the
      outstanding bills against the work already completed and also
      requested for the "Virtual Completion Certificate" vide letter
      dated 25th August 1990. As some work on the compound wall
      still remained to be completed, the contractor agreed to take
      up this assignment subject to waiver of the discount of 8.2% E
      which was to be given to Pawanhans till then and the completed
      works were duly handed over to Pawanhans on the 12th
      November 1990. The contractor had also submitted a bill dated
      23rd June 1991 and it was conveyed to Pawanhans that it
      expected compensation on account of the variation in the terms F
      of the contract. Pawanhans thereupon advised the contractor
      to submit a final bill which too was submitted. The bill was
      verified by Pawanhans and referred to the contractor yet again
      with objections. The contractor vide letter dated 21st November
      1991 disputed the verification as being without any foundation G
      and also reserved its right to seek arbitration. After a protracted
      correspondence, Pawanhans vide letter of 9th December 1991
 '    advised the contractor to submit a "No Claim Certificate" as a
      pre-condition for the release of the balance payment. The
      contractor wrote to Pawanhans that it was in dire need of H
    976       SUPREME COURT REPORTS                  [2008] 7 S.C.R.
                                                                        •
A finances and was being subjected to duress but nevertheless
  submitted a "No Dues Certificate" dated 17tn February 1992
  once again specifically highlighting that the same was being
  issued under duress. It appears that despite the issuance of
  the aforesaid certificate, Pawanhans still did not release the
B payment on which the contractor wrote another letter dated 5th        ..
  May 1992 and several letters thereafter but again to no effect,
  and on the contrary received a letter dated sth June 1992 from
  Pawanhans asking for a "No Dues Certificate" as per the
  enclosed specimen without attaching any condition to the same.
c The contractor, now in a desperate situation, submitted yet
  another "No Claim Certificate" dated 18th June 1992 as per
  directions. After receiving the aforesaid document, Pawanhans
  in its letter dated 9th February 1993 informed the contractor that
  a period of two months would be required for the scrutiny of its
  bills and vide letter dated 21st May 1993 also intimated that the
D
  bills had been submitted for verification by the ArchitecUEngineer
                                                                        ..
  as per the terms of the contract and that ;n case it was willing to
  defray the payment, the matter could be referred to arbitration.
  The contractor finally received a communication dated ath June
  1993 pointing out that as all payments due under the contract
E
  had been made and as a "No Dues Certificate" had been
  furnished, no further amount was due. The contractor accordingly
  served a notice dated 28th June 1993 on Pawanhans invoking
  the clause relating to arbitration. The matter was referred to
  arbitration by two registered Architects as per the clause. The
F contractor submitted its statement of claim for the outstanding            •
  amount plus compensation and damages on 5th August 1994.
  The arbitrators passed two awards on 31st December 1996,
  one with respect to the contract for the compound wall and the
  second for the construction of the bridge awarding certain
G amounts to the contractor. Aggrieved by the awards, Pawanhans
  filed two separate petitions under sections 30 and 33 of the
  Arbitration Act, 1940 before the Bombay High Court for a
  direction that the awards be set aside.
          The learned Single Judge in his judgment and order dated
H
          MIS. ASSOCIATED CONSTRUCTION v. PAWANHANS                   977
           HELICOPTERS PVT LTD. [HARJIT SINGH BEDI, J.]

         9th December 1998 held that clauses 18 and 34 of the contract A
         when read together, provided for the payment of escalation
         charges as the work had not been completed within four months
         on account of the fault on the part of the respondent and that the
         said clauses did not prohibit such a payment, more particularly
         as time was the essence of the contract and as the contract B
         was not on a fixed price, the prohibition of escalation was if at
         all to be read during the period of contract only. The learned
         Single Judge also repelled the arguments of the respondent
         that after having submitted the final bill on 25th October 1991, it
         was not open to the appellant herein to submit a second final      c
         bill on 2nd February 1993 by observing that the payment
         received on the 4th July 1993 as a consequence of the bills
         submitted on 25th October 1991, was under duress and it is on
         that account that the appellant had given the aforesaid
         certificate. Some objections raised by the respondent herein
                                                                             D
         were however accepted by the learned Single Judge and the
         award was acc0rdingly modified and it is the admitted case
         that the aforesaid modification has been accepted and was not
         challenged before the Division Bench by the contractor.
               2. Two appeals were thereafter filed by Pawanhans before E
         the Division Bench of the Bombay High Court. The Division
         Bench vide its order dated 7th June 2007 allowed the appeals
         and set aside the order dated 9th December 1998 of the learned
         Single Judge as also the two awards dated 31st December 1996
         by highlighting as a preface that it could not be disputed that the F
         scope for interference by the court under section 30 or 33 of the
"        Arbitration Act was limited as the court could not sit as a court
         of appeal on the decisions arrived at by the arbitrator. The Court
         then applied the aforesaid principle to the facts of the case and
         relied on clauses 18 and 34 ibid observed that a plain reading
                                                                             G
         of the said clauses did not visualize any claim for escalation or
         reduction towards the cost of the work and again reiterated that
    >·   clause 34 of the agreement prohibited the contractor from
         claiming any extra amount on account of fluctuation of price.
         The Court further observed, somewhat in contradiction, that a
                                                                             H
    978       SUPREME COURT REPORTS                  [2008] 7 S.C.R

                                                                        •
A   remedy towards the escalation of price had been provided by
    clause 43 of the contract and clause 43-1 (E) specifically
    provided, the procedure whereby such a claim could be made
    and as the procedure prescribed by the clause had not been
    adopted, it was not open to the contractor to contend before the
B   arbitrator that it was entitled to some payments on account of
    price escalation. The Court finally concluded that:
          "Once it is clear that the respondents are not entitled to
          claim escalation charges and the entire dispute, which is
          the subject matter of the appeals being related to the
c         escalation charges, the impugned orders, to the extent
          they confirm the award in relation to the escalation
          charges, are liable to be set aside and the petitions filed
          by the appellants challenging the awards in relation to the
          grant of the escalation charges are liable to be allowed to
D         that extent. Consequently, the claims for interest on the
          amount of darrages awarded towards the escalation arP
          also liable to be set aside."
          3. The Division Bench then examined the is:?.ues raised
E   by the contractor as to whether that "No Due Certificate" had
    been given under duress and held that there was no evidence
    to show that the said certificate had been given under duress or
    coercion and as the certificate itself provided a clearance of no
    dues, the contractor could not now turn and say that any further
    payment was still due on account of the second final bill. The
F   Division Bench accordingly allowed the appeal. The matter is
    before us in these circumstances.
        4. Mr. Shyam Divan, the learned senior counsel for the
  contractor, has raised several arguments before us during the
G course of the hearing. He has first pointed out that the awards
  rendered by the arbitrator were non-speaking and in this view
  of the matter, the scope for judicial interference was extremely
  limited and interference with the findings of the Arbitrators was.
  therefore not called for. He has also pleaded that clauses 18
H and 34, as per their plain interpretation themselves visualized a
                M/S. ASSOCIATED CONSTRUCTION v. PAWANHANS                    979
                 HELICOPTERS PVT LTD. [HARJIT SINGH BED!, J]
       '
               claim for escalation where the delay had been caused by the A
               opposite party and that in any case, the bar on the escalation, if
               at all, could be restricted only for the period of contract i.e. four
               months and not thereafter. He has also submitted that clause
~
               43-1 (C) on which reliance had been placed by the Division
      ...      Bench for non-suiting the contractor, was misplaced as this B
               clause too did not specifically or even by implication whittle down
               the effects of clauses 18 and 34. It has also been argued that
               the finding of the Division Bench that there was no duress on
               the contractor relating to the issuance of the "No Claim
               Certificates" was incorrect in the light of the voluminous evidence c
               to the contrary on record.

                      5. Mr. Raju Ramachandran, the learned senior counsel
                appearing for Pawanhans has fairly and at the very outset
                pointed out that the award in question was non-speaking and
       .        as such the scope for interference by the court was limited. He
                has further rontended that it would perhaps be difficult to read
                                                                                    D

                into the clauses a complete bar towards escalation, as a court
                would be reluctant to visualize such a bar in the light of some
               ·unforeseen situations that might arise in the execution of a work
                and the gates, thus, could not for ever be closed, but has          E
                submitted that clause 43 provided for such an opening and as
                this procedure had not been adopted by the contractor, the claim
                under clauses 18 and 34 was not maintainable. He has also
...             submitted that the "No Dues Certificate" having once being given
                by the contractor, it was not open to it to make a volte-face and   F
                to challenge the said certificate on the ground that it had been
      "         given under duress and the finding of the Division Bench on this
                point was, therefore, correct.
                     6. We have heard the learned counsel for the parties and
               gone through the record. As would be apparent, the matter would      G
               rest on an interpretation of clauses 34, 43 (1) .and (2) of the
               General Conditions of the Contract and clause 18 of the Special
           >
               Conditions of the Contract. We reproduce herein below the
               clauses abovementioned:
                                                                                    H
    980        SUPREME COURT REPORTS                     [2008] 7 S.C.R.
                                                                             •
A         "34. The contractor shall not claim any extras for fluctuation
          of price and the contract price shall not be subject to any
          rise or fall of prices.
          43 (1) E. Architect's instructions issued in regard to the
          postponement of any work to be executed under the
B         provisions of this contract; and if the written application is
          made within a reasonable time of it becoming apparent
          that the progress of the work or of any part thereof has
          been affected as c.foresaid:

c         Then the Architect shall ascertain the amount of such loss
          and/or expenst: Any amount from time to time so
          ascertained shall be added to the amount which would
          otherwise be stated as due in such certificate.
          43 (2) The provisions of this condemn are without prejudice
D         to any other rights and remedies which the contractor may
          possess.
          18. It is specifically pointed out that the contractor shall not
          be entitled to any compensation whatsoever on account
          of:
E
          1.   Any delay in supply of any material.
          2.   Any increase in costs of any material.
          3.   Any subsequent increase in cost of any material due
F              to increase in other charges like Railway, Steamer,
               freights or taxes and duties.                                     •

          4.   Any increase in labour costs."
        7. We have examined the arguments raised by the learned
G counsel in the light of the aforesaid and other provisions. It is
  the admitted position that as per clause 38, the date of the
  commencement of the contract was 1st November. 1989 and
  the date stipulated for the completion of the work was 28 1h
  February 1990. It is also clear from sub-clause (7) of clause 1
H of the General Conditions that time would be the essence of the
           M/S. ASSOCIATED CONSTRUCTION v. PAWANHANS                      981
            HELICOPTERS PVT. LTD. [HARJIT SINGH BEDI, J.]

           contract. We also see from clause 43 aforequoted that this            A
           clause has within itself the clear indication that the embargo
           placed by clauses 18 and 34 was not sacrosanct as has been
           found by the Division Bench as there could be a situation where
           the contractor had suffered loss for whatever reasons which was

    ..     required to be reimbursed as per procedure prescribed in clause
           43. Clause 43 (2) also specifically provided that clause 43 was
                                                                                 B

           without prejudice to any other rights and remedies that the
           contractor might possess. We find from a reading of the judgment
           of the Division Bench that the contractor has been non-suited
           on the plea that it had failed to proceed under clause 43. On the     c
           contrary we believe that Clause 43 is a clause which should be
           read in aid of the contractor as it clearly provides for indemnity
           in case there was a delay in the completion of the work which
           could be attributable to Pawanhans. We are, further, of the
           opinion that even assuming for a moment that there could be no
                                                                                 D
~
    Jo     price escalation during the period of 4 months i.e. during the
         · pendency of the contract, such embargo would not be carried
           beyond that period as time was the essence of the contract.
           The learned Division Bench has relied upon a large number of
           judgments in support of its decision that in case of a clause
           barring the escalation in the price, it was not open to the           E
           contractor to claim any amount under that head. A perusal of the
           aforesaid judgments, however, do not show any provisiori in
           terms of clause 43, and that in any case, these judgments pertain
           to a claim of price escalation during the period of contract. It
           must also be borne in mind that a, court does not sit as one in       F
           appeal over the award of the arbittator and if the view taken by
           the arbitrator is permissible, no interference is called for on the
           premise that a different view was also possible. We also feel
           that in commercial transactions all situations cannot be
           visualized and the positive and unchallenged finding in the           G
           present case is that the delay in the execution of the work was
           occasioned on account of reasons attribtitable to Pawanhans.
    >      It cannot, therefore, be said that the award of the arbitrator was
           so unconscionable that it required interference. In MCD vs. Ml
           sJagan Nath Ashok Kumar & Anr (1987) 4 SCC 497, it was                H
    982 .    SUPREME COURT REPORTS                      [2008] 7 S.C.R.
                                                                                •
A   observed thus:

         "In this case:, there was no violation of any principles of
         natural justice. It is not a case where the arbitrator has
         refused cogent and material factors to be taken into
         e;onsideration. The award cannot be said to be vitiated by
B
         non-reception of material or non-consideration of the
         relevant aspects of the matter. Appraisement of evidence
         by the arbitrator is ordinarily never a matter which the
         court questions and considers. The parties have selected
         their own forum and the deciding forum must be conceded
c        the power of appraisement of the evidence. In the instant
         case, there was no evidence of violation of any principle
         of natural justice. The arbitrator in our opinion is the sole
         judge of the quality as well as quantity of evidence and it                  l
                                                                                      /'
         will not be for this Court to take upon itself the task of
                                                                                      ·~
D        being a judge of the evidence before the arbitrator. It may        ...
         be possible that on the same evidence the court might
         have arrived at a different conclusion than the one arrived
         at by the arbitrator but that by itself is no ground in our view
         for setting aside the award of an arbitrator." and further
E        concluded:

         "After all an arbitrator as a judge in the words of Benjamin
         N. Cardozo, has to exercise a discretion informed by
         tradition, methodized by analogy, disciplined by system,
         and subordinated to "the primordial necessity of order in
F        the social life''.                                                       •
        8. PM.Paul vs. Union of India (1989) Supp 1 SCC 368 is
  a case which is almost identical on facts. In this matter the work
  could not be completed during the period of the contract anc
G the contractor was accordingly granted extension of time to
  complete the same. By an order of this Court, the dispute was
  referred to an Arbitrator on the reference as to who was
  responsible for the delay in the completion of the work, what
                                                                            •
  were to be the repercussions of the delay and how to apportion
  the responsibility and the consequences. The arbitrator made
H
     M/S. ASSOCIATED CONSTRUCTION v. PAWANHANS                  983
      HELICOPTERS PVT LTD. [HARJIT SINGH BED!, J.]

    an award in favour of the contractor which was duly challenged A
    by the Union of India with the matter finally reaching this Court at
    the instance of the contractor and this is what the Court had to
    say.
          "It was submitted that if the contract work was not
          completed within the stipulated time which it appears was 8
          not done then the contractor has got a right to ask for
          extension of time, and he could claim difference in price.
          This is precisely what he has done and has obtained a
          portion of the claim in the award. It was submitted on
          behalf of the Union of India that failure to complete the C
          contract was not the case. Hence, there was no substance
          in the objections raised. Furthermore, in the objections
          raised, it must be within the time provided for the
          application under Section 30 i.e., 30 days during which
.         the objection was not specifically taken, we are of the D
          opinion that there is no substance in this objection sought
        . to be raised in opposition to the award. Once it was found
          that the arbitrator had jurisdiction to find that there was
          delay in execution of the contract due to the conduct of the
          respondent, the respondent was liable for the E
          consequences of the delay, namely, increase in prices.
          Therefore, the arbitrator had jurisdiction to go into this
          question. He has gone into that question and has awarded
          as he did."

         9. A similar view has been taken by this Court in               F
    K.N.Sathyapalan (D) By Lrs. vs. State of Kera/a & Anr. (2006)
    12 SCALE 654. It has been held as under:
         "We have. intentionally set out the background in which the
         Arbitrator made his award in order to examine the G
         genuineness and/or validity of the appellant's claim under
         those heads which had been allowed by the Arbitrator. It
         is quite apparent that the appellant was prevented by .
         unforeseen circumstances from completing the work within·.
         the stipulated period of eleven month and that such delay·.·
                                              .                       .'.··H
    984       SUPREME COURT REPORTS                   [2008] 7 S.C.R.


A         could have been prevented had the State Government
          stepped in to maintain the law and order problem which
          had been created at the work site. It is also clear that the
          rubble and metal, which would have been available at the
          departmental quarry at Mannady, had to be obtained from
B         quarries which were situated at double the distance, and
          even more, resulting in doubling of the transportation
          charges. Even the space for dumping of excess earth
          was not provided by the respondents which compelled
          the appellant to dump the excess earth at a place which
c         was for away from the work site entailing extra costs for
          the same.
               In the aforesaid circumstances, the Arbitrator appears
          to have acted within his jurisdiction in allowing some of
          the claims on account of escalation of costs which was
D         referable to the execution of the work during the extended
          period, In our judgment, the view taken by the High Court
          was on a rigid interpretation of the terms of contract and
          the Supplemental Agreement executed between the
          parties, which was not warranted by the turn of events."
E
          10. We are, therefore, of the opinion in the light of the
    aforesaid judgments, that it was open to the contractor to
    contend that it was liable to be compensated on account of the
    fact that delay had been occasioned on account of reasons
    attributable to Pawanhans. It is significant that the Division
F   Bench of the High Court has been silent on this aspect of the
    matter and has not referred to the finding of the learned Single
    Judge with regard to the responsibility for the delay.
          11. We are further of the opinion that clause 43 and 43 (1)
G   and (2) when read together clearly visualize escalation of price
    on account of reasons beyond the control of the contractor and
    attributable to the other side. Moreover clause 43 (2) clearly
    states that the remedy under clause 43(1) would be in addition
    to such other remedy that may be open to the contractor under
H   the other provisions.
 M/S. ASSOCIATED CONSTRUCTION v. PAWANHANS                    985
  HELICOPTERS PVT LTD. [HARJIT SINGH BEDI, J.]

       12. We have also gone through the record with respect to      A
the finding of the Division Bench that there was no duress or
 coercion on the contractor which had compelled it to give a "No
 Dues Certificate". Mr. Raju Ramachandran has, however,
submitted that the story about duress was an after thought in
the background that the first final bill had been submitted by the   B
contractor on the 3rd June 1991 and the second final bill on 2nd
 February 1993 i.e. almost 2 years later and that in any case, a
second final bill was not visualized under the contract. He has
submitted that the observation of the arbitrator that submission
of the second final bill was sanctioned as a trade practice was      c
without any basis. We have gone through the record in the light
of the submissions of the learned counsel. We first refer to the
letter of the contractor of 11th July 1990 to which reference has
been made by the Division Bench requesting Pawanhans to
ensure a regular power supply. The letter of 27th July 1990 by
                                                                     0
the contractor refers to the statement of accounts submitted by
it and requests for payment as per the accounts which had been
cleared by the Architect. It is to be noted that these letters are
on the record and were written by the contractor at the time when
the work was in the process of completion. The desperate tone
of the contractor is however supported by the letter of 1oth         E
January 1991 in which it was noted that though repeated
requests had been made for the payment atleast against the
bills certified by the Architect, a huge amount had been blocked
arbitrarily over a long period of time and a request was made
for its release. The letter dated 21st November 1991 is again a      F
reminder to Pawanhans asking for payment and that in case
there was a dispute, the matter be referred to the arbitrator and
submitting that payment shou Id be made atleast with respect to
those dues which had been certified by the Architect. The letter
dated 9th December 1991 from Pawanhans to the contractor             G
shows that payment could be considered provided the contractor
submitted a "No Claim Certificate". It appears that such
certificate was indeed issued but with no result on which the
contractor in his letter dated 25th December 1991 in reply to the
letter dated 9th December 1991, once again submitted that the        H
     986       SUPREME COURT REPORTS                     [2008] 7 S.C.R.


A    payments be released in so far as they had been certified by
     the Architects/Consultants and if there was a dispute regarding
     the other payments, they should be referred to an arbitrator and
     in desperation further adds:

           "However, if you want to hold us to economic duress by
B          not paying what you wish to pay, without "No Claim
           Certificate", we shall treat it as "Duress" and issue you
           such a certificate much against our willingness as we
           cannot afford to liquidate our dues by such a certificate.

c         Please do not hold us to a ransom and arrange to pay. In
     case you would still like to insist, let us know, so that we could
     issue you such a certificate under duress as we have serious
     financial problems."
          14. It appears that despite the pleading tone of the               .
;D   aforesaid letter no payment was made on which the contractor
     wrote yet another letter dated 17th February 1992 in which it
     was submitted as under:
           "lnspite of our claim statements, you have insisted on "No
           Claim Certificate", we hereby give you this certificate that
E
           we have "No Claims" and hence you pay us what you
           might have worked out as our "Final Dues".
           In case, you have a particular draft in which a "No Claim"
           Certificate need be issued to receive our dues of our bill,
F          please let us have the deft, or else this letter may be treated
           as the certificate of "No Claim" from our side."
        15. When no action was taken, another letter dated 5th
  May 1992 was addressed to Pawanhans by the contractor
  stating that as they were facing economic duress on account of
G the payment being held back, and as a "No Claim Certificate"
  had been issued, the payment be defrayed as promised or else               .
  they might have to refer the matter to the arbitrator. The letter
  dated 3th June 1992 is again tell-tale and we reproduce the
  contents hereunder:
H.
           M/S. ASSOCIATED CONSTRUCTION v. PAWANHANS                    987
            HELICOPTERS PVT LTD. [HARJIT SINGH BEDI, J.]

               "Kindly let us know what is it that we have to do to get A
               money which you say is payable but only on your extracting
               "No Claim" certificate under duress. Please take note if
               you fail to pay us our dues, we shall be constrained to take
               you to court for which you will blame yourself if it
               inconvenience is caused. It is a clear 15 days notice B
               please."

                 16. It appears however that no steps were taken on which
          the contractor addressed a letter dated 2nd February 1993 for
          payment of dues and again stated that if the payment was not
          made, the dispute should be referred to the arbitrator. In          c
          response to this letter, Pawanhans in its letter dated 9th February
          1993 replied that the matter was under scrutiny and it would
          take about 2 months for verification and that the contractor would
          be informed in due course. As no reply was received, a letter
    ...   dated 21st May 1993 was addressed by the contractor relating D
          to the undertaking that the enquiry would be completed within 2
          months but complaining that nothing had been done and on the
          contrary on gth June 1993 the claim for any payment was rejected
          by Pawanhans observing that as a "No Dues Certificate" had
          been submitted by the contractor, the question of any balance E
          payment being due did not arise. It is at this stage that the
          contractor had invoked the clause for arbitration. We have
          reproduced the correspondence in extenso to show that the
          contractor was compelled to issue a "No Dues Certificate" and
          in this view of the matter, it could not be said that the contractor F
          was bound by what he had written. It is also clear that there is
          voluminous correspondence over a span of almost 2 years
          between the submission of the first final bill on 3rd June 1991
          and the second final bill dated 2nd February 1993 and as such
          the claim towards escalation or the plea of the submission of a
                                                                               G
          "No Dues Certificate" under duress being an after thought is

"
    ..    not acceptable. In Mis. Ambica Construction vs. Union of India
          {2006) 12 SCALE 149 it was observed as under:
               "A glance at the said clause will immediately indicate that
               a No Claim Certificate is required to be submitted by a H
    988       SUPREME COURT REPORTS                     [2008] 7 S.C.R.


A         contractor once the works are finally measured up. In the
          instant case the work was yet to be completed and there
          is nothing to indicate that the works, as undertaken by the
          contractor, had been finally measured and on the basis of
          the same a No Objection Certificate had been issued by
          the appellant. On the other hand, even the first Arbitrator,
                                                                                •
B
          who had been appointed, had come to a finding that No
          Claim Certificate had been given under coercion and
          duress. It is the Division Bench of the Calcutta High Court
          which, for the first time, came to a conclusion that such No
c         Claim Certificate had not been submitted under coercion
          and duress.
          From the submissions made on behalf of the respective
          parties, and in particular from the submissions made on
          behalf of the appellant, it is apparent that unless a discharge
                                                                            •
D         certificate is given in advance, payment of bills are generally
          delayed. Although, Clause 43(2) has been included in the
          General Conditions of Contract, the same is meant to be
          a safeguard as against frivolous claims after final
          measurement. Having regard to the decision in the case
E         of Reshmi Constructions's (supra), it can no longer be
          said that such a clause in the contract would be an absolute
          bar to a contractor raising claims which are genuine, even
          after the submission of such No Claim Certificate."

        17. We are therefore of the opinion that the judgment of
F the Division Bench is erroneous and we accordingly set it aside.          '
  The judgment of the learned Single Judge is accordingly
  restored. In the facts and circumstances of the case, in that
  Pawanhans has taken advantage of a beleaguered contractor,
  and has behaved in a most unbecoming manner in pushing it
G ever deeper into the chasm, the contractor will have its costs
  which are computed at Rs.10,000/-. The appeals are accordingly
  allowed.
    B.B.B.                                           Appeals allowed.

H


Search Indian case law

Ask in plain English, not just keywords. 25,000 AI words free, no card.

Try "Arbitration"Sign in to search

For a digitally signed copy suitable for filing, refer to the court's own website. Only the court can issue one.