M/S D. KHOSLA AND COMPANYversusTHE UNION OF INDIA
- Citation
- 2024 INSC 587
- Decided
- 7 August 2024
- Disposal
- Dismissed
Holding
In the absence of any express provision in the award, contract or statute, interest cannot be awarded on interest; the 15% post‑award interest is payable only on the principal sum of compensation.
Summary
The petitioner, M/s D. Khosla & Co., obtained an arbitration award in 1997 that granted simple interest of 12% for the pre‑award period and 15% for the post‑award period, both described as payable on the "amount awarded" (the principal compensation of Rs.21,56,745). The petitioner later claimed that the 15% post‑award interest should be calculated on the principal sum plus the accrued 12% pre‑award interest, effectively seeking interest on interest. The trial court and the Gujarat High Court rejected this claim, holding that the award did not expressly provide for compound interest. On appeal, the Supreme Court examined the relevant statutory provisions—Arbitration Act, 1940; Interest Act, 1978; and CPC—and the case law on interest awards. It concluded that neither the statutes nor the award confer power to award interest on interest unless expressly stipulated, and the term "amount awarded" refers only to the principal compensation. Consequently, the Special Leave Petition was dismissed, confirming that the 15% interest applies only to the principal sum.
Issues considered
- Whether interest can be awarded on interest (interest upon interest) under the Arbitration Act, 1940, the Interest Act, 1978 and the Code of Civil Procedure, 1908 when the award does not expressly provide for it.
- Whether the 15% post‑award interest is payable on the principal sum alone or on the principal sum together with the pre‑award 12% interest.
Legislation cited
- Arbitration Act, 1940s. 14, s. 17, s. 29
- Code of Civil Procedure, 1908s. 34
- Interest Act, 1978s. 3(3)
Subjects
Judgment
[2024] 8 S.C.R. 113 : 2024 INSC 587
M/s D. Khosla and Company
v.
The Union of India
(Special Leave Petition (Civil) No. 812 of 2014)
07 August 2024
[Pamidighantam Sri Narasimha and Pankaj Mithal,* JJ.]
Issue for Consideration
Arbitrator passed award granting interest for two periods-(i) Pre-
award period, from the date of completion of the work up to the
date of the award @ 12% per annum (simple interest); and (ii) Post-
award, from the date of the award till the date of its payment or the
date of the court decree @ 15% per annum. Whether interest was
payable on interest or whether 15% interest per annum awarded
would be on the principal sum award plus 12% per annum interest
on it for the pre-award period.
Headnotes†
Arbitration Act, 1940 – ss.29, 17 – Interest Act, 1978 – s.3 –
Code of Civil Procedure, 1908 – s.34 – Court /Arbitrator if can
award compound interest or interest upon interest unless
specifically provided under the statute or the terms and
conditions of the contract:
Held: No – Though, there is no dispute as to the power of the
courts to award interest on interest or compound interest in a given
case subject to the power conferred under the statutes or under the
terms and conditions of the contract but, where no such power is
conferred ordinarily, the courts do not award interest on interest –
Neither the Act specifically empowers the Arbitrator or the Court
to award interest upon interest or compound interest nor there is
any other provision which provides for grant of compound interest
or interest upon interest – s.34, CPC is also silent in this regard
whereas s.3(3) of the Interest Act specifically prohibits the same –
In the present case, the award and the decree nowhere awarded 15%
interest per annum on the amount awarded including the interest
component i.e. the pre-award interest – This could not have been
done even otherwise as there is no provision to that effect under
the relevant statutes or the contract – The interest awarded under
the award in the first part, was simple interest @ 12% per annum
* Author
114 [2024] 8 S.C.R.
Digital Supreme Court Reports
on the ‘amount awarded’ whereas in the second part, interest @
15% per annum was awarded referring to the ‘amount awarded’ –
The amount awarded in both the situations referred to the principal
amount of compensation awarded i.e. Rs.21,56,745/- and was same
and cannot be two distinct amounts – Concurrent judgments of the
courts below not interfered with. [Paras 23, 24, 27, 28]
Case Law Cited
Oil and Natural Gas Commission v. M.C. Clelland Engineers S.A.
[1999] 2 SCR 830 : (1999) 4 SCC 327; State of Haryana and
Others v. S.L. Arora and Company [2010] 2 SCR 297 : (2010)
3 SCC 690; Hyder Consulting (UK) Limited v. Governor, State
of Orissa [2014] 14 SCR 1029 : (2015) 2 SCC 189; UHL Power
Company Limited v. State of Himachal Pradesh [2022] 1 SCR 1 :
(2022) 4 SCC 116 – referred to.
List of Acts
Arbitration Act, 1940; Interest Act, 1978; Code of Civil Procedure,
1908.
List of Keywords
Award of interest; Interest upon interest; Compound interest;
Interest on the amount awarded; Interest awarded in two parts;
Pre-award interest and post-award interest on the principal
amount; Simple interest; Simple interest on the amount awarded;
Amount awarded; Principal amount; Principal amount awarded;
Principal amount of compensation awarded; Principal sum.
Case Arising From
CIVIL APPELLATE JURISDICTION: Special Leave Petition (Civil)
No.812 of 2014
From the Judgment and Order dated 06.09.2013 of the High Court
of Gujarat at Ahmedabad in SCA No.3036 of 2009
Appearances for Parties
Ms. Jyoti Mendiratta, Sourabh Malhotra, Ms. Ananya Basudha, Advs.
for the Petitioners.
Ms. Aishwarya Bhati, A.S.G., Ms. Sthavi Asthana, Akshaja Singh,
Nitesh Shrivastav, Dr. N. Visakamurthy, Chitrangada Rastravara,
Mukul Singh, Amit Sharma Ll, Kartikeya Asthana, Mukesh Kumar
Maroria, Advs. for the Respondent.
[2024] 8 S.C.R. 115
M/s D. Khosla and Company v. The Union of India
Judgment / Order of the Supreme Court
Judgment
Pankaj Mithal, J.
1. Heard Smt. Jyoti Mendiratta, learned counsel for the petitioner and
Smt. Aishwarya Bhati, learned A.S.G. for the Union of India.
2. In connection with a contract of 1984-85 between the petitioner and
the respondent, an award came to be passed by the Arbitrator on
17.09.1997 under the Indian Arbitration Act, 1940.1 It was made the
rule of the court under Section 14 read with Section 17 of the Act
and a decree was accordingly drawn.
3. The award vide its paragraph 12 provided for the interest on the
amount awarded. The interest was awarded for two periods viz. (i)
from the date of completion of the work up to the date of the award
@ 12% per annum (simple interest); and (ii) @ 15% per annum from
the date of the award till the date of its payment or the date of the
court decree, whichever is earlier.
4. The portion of the award which is relevant for our purpose concerning
interest is reproduced hereinbelow:
“12. Interest:- The Union of India shall pay to M/s D Khosla &
Company simple interest @ 12% per annum on the amount
awarded from the date of completion of work upto the date
of award and 15% from the date of award to the date of
its payment or date of court decree whichever is earlier.”
(emphasis supplied)
5. The decree of the court that was drawn according to the award
reads as under:
“02) Decree for Rs.21,56,745 (Rupees Twenty One Lac
Fifty Six thousands seven hundred and forty five) in terms
of Arbitration Award to be drawn on payment of the Court
Fees by the Opponent no.1. Opponent no.2- Union of
India is hereby ordered to pay interest @ 12% p.a. on the
awarded amount up to the date of the award and interest
1 hereinafter referred to as ‘the Act’
116 [2024] 8 S.C.R.
Digital Supreme Court Reports
@ 15% p.a. from the date of award till the realization of
the decreetal amount as per the terms of award.”
(emphasis supplied)
6. A simple reading of the aforesaid decree reveals that interest has
been awarded in two parts on the amount of Rs.21,56,745/- i.e. (i)
12% per annum on the awarded amount up to the date of award;
and (ii) 15% per annum from the date of award till the realization of
the decretal amount.
7. It appears that the petitioner was paid the principal amount of
compensation awarded and interest of 12% and 15% for the two
periods i.e. pre-award and post-award on the principal amount
awarded. However, petitioner was not satisfied and he moved
execution for the realization of certain amount as shortfall of the
interest. The petitioner contended that insofar as 15% interest is
concerned, it is payable on the principal amount of compensation
awarded plus 12% simple interest on the said amount. In other words,
petitioner sought to include 12% interest in the principal amount of
compensation awarded for the purposes of claiming 15% simple
interest for the post-award period.
8. The Principal Senior Civil Judge, Khambhalia, in Execution Petition
No.9 of 2006 preferred by the petitioner, refused to accept the
contention of the petitioner so as to award 15% interest on the
principal amount of compensation awarded plus 12% simple interest
thereof. In a way, he declined to grant interest upon interest for the
reason that the Arbitrator has not awarded it in so many words.
9. In the petition preferred by the petitioner before the High Court, the
same view was adopted by the High Court vide its judgment and
order dated 06.09.2013. It held that as the Arbitrator had used word
‘simple interest’ and had not specifically awarded compound interest,
therefore, the petitioner is only entitled to simple interest @ 12% per
annum on the amount awarded as compensation for the pre-award
period and simple interest @ 15% per annum for the post-award
period only on the amount of compensation awarded.
10. Aggrieved by the judgment and order of the High Court dated
06.09.2013 and that of the Principal Senior Civil Judge, Khambhalia,
dated 29.08.2008, the petitioner has preferred this Special Leave
Petition.
[2024] 8 S.C.R. 117
M/s D. Khosla and Company v. The Union of India
11. Ms. Mendiratta, learned counsel for the petitioner argued that 12%
interest per annum awarded for the pre-award period is part of
the principal sum and it has lost its character as separate interest.
Therefore, 15% interest per annum awarded for the post-award
period is both on the principal sum and the 12% interest inclusive.
12. In contrast, Ms. Aishwarya Bhati, learned Additional Solicitor General
appearing on behalf of the respondent, has argued that though there
is no controversy with regard to the power of the arbitrator to award
interest on interest or compound interest in a given case. However,
it cannot be paid to the claimant until and unless it is specifically
granted by the award or the order of court.
13. In the instant case, the arbitrator had granted interest for two separate
periods on the principal sum adjudged only and there is no direction
that the interest for the subsequent period would be payable on the
principal sum adjudged including interest for the first period.
14. The sole simple issue herein for our opinion is whether interest is
payable on interest or whether 15% interest per annum awarded
would be on the principal sum award plus 12% per annum interest
on it for the pre-award period.
15. Section 29 of the Act provides that the court may in the decree order
interest at the rate deemed reasonable to be paid on the principal
sum as adjudged by the award meaning thereby in drawing the
decree, the court may order for payment of interest on the principal
sum as adjudged by the award. In other words, the court cannot
order for payment of interest on interest but only on the principal
sum adjudged.
16. Since the award under the Act is in the nature of a decree in terms
of Section 17 of the aforesaid Act, it attracts the provisions of the
Code of Civil Procedure2 also to a limited extent namely insofar as
award of interest is concerned and for the execution of the decree
drawn pursuant to the award.
17. Section 34 of the CPC provides that where the decree is for payment
of money, the court may order interest at such rate as the court
deems reasonable to be paid on the principal sum adjudged. Again,
2 hereinafter referred to as “CPC”
118 [2024] 8 S.C.R.
Digital Supreme Court Reports
the reading of the aforesaid Sub-Section (1) of Section 34 CPC would
reveal that the interest is payable on the principal sum adjudged and
not on interest part of the award.
18. The Interest Act, 1978 vide Sub-Section (3) of Section 3 specifically
lays down that nothing in Section 3 which permits the court to award
interest shall empower the court to award interest upon interest. It
means that ordinarily the courts are not entitled to award interest
upon interest unless specifically provided either under any statute
or under the terms and conditions of the contract.
19. In Oil and Natural Gas Commission vs. M.C. Clelland Engineers
S.A.3 which was also a case under the Act, this Court observed that
there cannot be any doubt that the Arbitrators have power to grant
interest akin to Section 34 CPC and it is clear that interest is not
permissible upon interest awarded but only upon the claim made.
In the aforesaid case, the claim made was in two parts, and in the
second part, interest on delayed payment was also claimed. In that
situation, the court held that the interest awarded would form part
of the damages or compensation for delayed payment and would
become part of the principal amount and thus, in that circumstances,
Arbitrator has the power to grant interest on interest which partakes
the compensation awarded.
20. In State of Haryana and Others vs. S.L. Arora and Company,4
it was observed that interest, unless otherwise specified, refers to
simple interest and that interest is payable only on principal amount
and not on any accrued interest. It was further held that the compound
interest can be awarded if there is a specific provision under the
statute or in the contract for compounding of interest but no general
discretion lies with the courts or tribunals to award compound interest
or interest upon interest.
21. In Hyder Consulting (UK) Limited vs. Governor, State of Orissa,5
this Court was dealing with Section 31(7) of the Arbitration and
Conciliation Act, 1996, wherein for the purposes of payment of
post-award interest, the phrase ‘sum directed to be paid by award’
3 [1999] 2 SCR 830 : (1999) 4 SCC 327
4 [2010] 2 SCR 297 : (2010) 3 SCC 690
5 [2014] 14 SCR 1029 : (2015) 2 SCC 189
[2024] 8 S.C.R. 119
M/s D. Khosla and Company v. The Union of India
was used and it was held that it includes the pre-award interest
and, therefore, post-award interest is payable on the sum awarded
which includes pre-award interest. However, a distinction was made
between Section 31(7) which simply uses the word ‘sum’ and Section
34 CPC wherein the phrase ‘on principal sum adjudged’ has been
used. The departure in the use of the language in the two provisions
was held to be of great significance which clearly showed that the
term ‘sum’ under Section 31(7) refers to aggregate amount of the
award and the pre-award interest whereas ‘principal sum adjudged’
under Section 34 CPC refers only to the amount awarded.
22. The case of UHL Power Company Limited vs. State of Himachal
Pradesh,6 is again in relation to interpretation of Section 31(7) of
the Arbitration and Conciliation Act, 1996, wherein the principal laid
down in Hyder Consulting (UK) Limited (supra) has been accepted.
23. In the light of the above legal provisions and the case law on the
subject, it is evident that ordinarily courts are not supposed to grant
interest on interest except where it has been specifically provided
under the statute or where there is specific stipulation to that effect
under the terms and conditions of the contract. There is no dispute
as to the power of the courts to award interest on interest or
compound interest in a given case subject to the power conferred
under the statutes or under the terms and conditions of the contract
but where no such power is conferred ordinarily, the courts do not
award interest on interest.
24. Neither the Act specifically empowers the Arbitrator or the court to
award interest upon interest or compound interest nor there is any
other provision which provides for grant of compound interest or
interest upon interest. Even Section 34 CPC is silent in this regard
whereas Sub-Section (3) of Section 3 of the Interest Act specifically
prohibits the same.
25. In view of the above legal position, we have to examine the award
in question and the decree drawn in pursuance thereof to find out
if compound interest or interest upon interest has been awarded.
26. The relevant part of the award pertaining to the interest and that of
the decree has been reproduced hereinbefore.
6 [2022] 1 SCR 1 : (2022) 4 SCC 116
120 [2024] 8 S.C.R.
Digital Supreme Court Reports
27. A plain reading of the aforesaid award and decree reveals that interest
awarded under the award has been dissected into two parts. The first
part relates to the pre-award period from the date of the completion
of the work till the passing of the award whereas the second part is
the post-award period commencing from the date of the award till
the satisfaction of the award. In the first part, simple interest @ 12%
per annum has been awarded on the ‘amount awarded’ whereas
in the second part, interest @ 15% per annum has been awarded
referring to the ‘amount awarded’. The amount awarded in both the
situations have to be the same and cannot be two distinct amounts.
The ‘amount awarded’ refers to the principal amount of compensation
awarded that is Rs.21,56,745/-. The award and the decree nowhere
specifically contemplate for awarding 15% interest per annum on
the amount awarded including the interest component i.e. the pre-
award interest. This could not have been done even otherwise as
there is no provision to that effect under the relevant statutes or the
contract. No material has been placed before us or as a matter of
fact before any court below to show that the terms and conditions
of the contract contained any such provision.
28. In the light of the above discussion, we do not deem it appropriate
under the facts and circumstances of the case to exercise our
discretionary jurisdiction under Article 136 of the Constitution of India
so as to interfere with the opinion expressed concurrently by the two
courts below. Therefore, the Special Leave Petition is dismissed.
Result of the case: SLP dismissed.
†
Headnotes prepared by: Divya Pandey
Search Indian case law
Ask in plain English, not just keywords. 25,000 AI words free, no card.