Created byFuzzy Cloud

Supreme Court of India

M/S ULTRA-TECH CEMENT LTD.versusMAST RAM & ORS.

Citation
2024 INSC 709
Decided
20 September 2024
Disposal
Case Allowed

Holding

The Scheme of Arrangement retains the liability for the Supplementary Award with JAL, Section 101 does not apply, and the State must pay the compensation to the landowners and recover it from JAL.

Summary

The Supreme Court examined a dispute arising from the acquisition of 56.14 bighas of land for a safety zone around a cement plant, where the original award of compensation was paid by Jaiprakash Associates Ltd (JAL) and a supplementary award was later issued. The key issue was whether the liability for the supplementary compensation fell on Ultra‑Tech Cement Ltd (the appellant) or JAL, given the Scheme of Arrangement approved by the NCLT that transferred the cement business but excluded certain liabilities. The Court held that the Scheme’s Clause 7.1 expressly retained pending litigation and related liabilities, including the land‑acquisition compensation, with JAL because the acquisition proceedings began before the Scheme’s effective date. It further ruled that Section 101 of the 2013 Act did not apply because the land was utilized as a safety zone, and that the State of Himachal Pradesh, as a welfare state, must ensure prompt payment of compensation under Article 300‑A. Consequently, the State and the Land Acquisition Collector were directed to pay the supplementary compensation to the landowners and recover the amount from JAL.

Issues considered

  • Whether the subject land and associated liabilities were transferred to the appellant under the Scheme of Arrangement.
  • Whether the appellant or JAL is legally obliged to pay the compensation determined under the Supplementary Award.
  • Whether Section 101 of the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013 permits the return of the land to the original owners at this stage.
  • Whether the State of Himachal Pradesh, as a welfare state, bears the responsibility to ensure full payment of the compensation under the Supplementary Award.

Legislation cited

Subjects

Section 101Section 38Section 391-394Article 300-ACompensationLand acquisitionScheme of ArrangementLiabilityWelfare StateReturn of landSupplementary Award

Judgment

                 [2024] 9 S.C.R. 443 : 2024 INSC 709

                       M/s Ultra-Tech Cement Ltd.
                                    v.
                            Mast Ram & Ors.
                      (Civil Appeal No. 10662 of 2024)
                             20 September 2024
               [J.B. Pardiwala* and Manoj Misra, JJ.]

                            Issue for Consideration
       Whether the subject land and all other liabilities associated with it
       were transferred to the Appellant in terms of the Scheme; Whether
       it was the Appellant or JAL who was legally obliged to pay the
       compensation amount determined under the Supplementary
       Award; Whether the land in terms of Section 101 of the Right
       to Fair Compensation and Transparency in Land Acquisition,
       Rehabilitation and Resettlement Act, 2013 can be returned to the
       Respondent Nos. 1-6 at this stage under the scheme of the Act; In
       other words, what is the scope of Section 101; Whether the State
       of Himachal Pradesh, being a welfare state, had the responsibility
       to ensure full payment of compensation amount determined under
       the Supplementary Award dated 02.05.2022.

                                  Headnotes†
       Land Acquisition Act, 1894 – Land Acquisition, Rehabilitation
       and Resettlement Act, 2013 – The High Court allowed the writ
       petition filed by the Respondent Nos. 1 to 6 herein (original
       petitioners) and directed the Appellant herein to pay the
       requisite amount towards compensation as determined in the
       Supplementary Award dated 02.05.2022 passed by the Land
       Acquisition Collector (LAC) (Respondent No. 10) in the first
       instance with liberty to recover the same from JAL (Respondent
       No. 11) if permissible under the legal relationship between the
       two companies – Correctness:
       Held: An analysis of the Scheme agreed between the Appellant
       and JAL is the key to determine who should pay the amount
       determined under the Supplementary Award dated 02.05.2022 –
       Clause 1.1 (o) defines the “Effective Date” as the date on which
       the Scheme becomes effective in accordance with its terms, which
       shall be the Closing Date [defined in Clause 1.1(k) and Clause

* Author
444                                                            [2024] 9 S.C.R.

                       Digital Supreme Court Reports


       10.1] – The said date was decided to be 29.06.2017 among the
       parties – The parties by way of Clause 1.1(w)(ix) agreed that all
       litigations pertaining to the business and assets being transferred
       to the Appellant that arose before or on the Closing Date would not
       be transferred to the Appellant and will remain with JAL – Clause
       7.1 of the Scheme states without any ambiguity that any legal
       or other proceeding by or against JAL or its unit operating the
       cement project relating to the JAL Business as defined in Clause
       1.1(w), initiated on or arising and pending before the Effective
       Date shall remain with JAL – The facts indicate that the land
       acquisition proceedings had commenced before the Effective Date
       of the Scheme (i.e. 29.06.2017) and the compensation remained
       undetermined as on the Effective Date – These facts attract
       the application of Clause 7.1 of the Scheme as the acquisition
       proceedings and the liability to pay compensation associated with it
       squarely falls within the meaning of ‘other proceedings’ as intended
       by the parties under the said Clause – JAL has also not disputed
       that it had made payment of the amount determined under the
       Award of 2018 i.e., Rs. 10,77,53,842/- after the Effective Date of
       the Scheme – The said amount has already been disbursed to
       the landowners – After the LAC determined the amount under the
       Award dated 08.06.2018, JAL paid the same without any protest
       or reference to the Scheme – Therefore, at the stage of the
       Supplementary Award pertaining to the same land and same
       original landowners, JAL cannot be allowed to take the plea that
       the payments with respect to the subject land were required to be
       made by the Appellant. [Paras 21, 22, 24, 26, 27, 28, 29]
       Land Acquisition, Rehabilitation and Resettlement Act,
       2013 – s.101 – It is the case of JAL that the substantial delay
       in acquisition of the subject land has frustrated its purpose,
       and it could not make any use of the land – It was submitted
       that if the Appellant does not require the said land, then it
       should be returned to the original landowners and the amount
       of Rs. 10,77,53,842/- paid under the Award of 2018 should be
       refunded to JAL:
       Held: The necessary conditions for the application of Section
       101 are: (1) the land should be unutilized; and (2) the period it
       remains not in use should be at least five years from the date
       of taking of possession – There is no merit in the contention
       of JAL that the land be returned to the original landowners –
[2024] 9 S.C.R.                                                           445

             M/s Ultra-Tech Cement Ltd. v. Mast Ram & Ors.


     While period of five years has elapsed from the date of taking of
     possession by JAL, the first condition that the land should remain
     unutilized is not fulfilled – The subject land was acquired for the
     purpose of providing a safety zone to the mining area of the
     cement plant – No other use except that the subject land may
     pose hazard to the residents was envisaged during the acquisition
     proceedings – JAL cannot pray for return of the land as that
     would result in endangering the lives and property of the original
     landowners – It is also found that the subject land has been in
     use all throughout the operation of the cement project by serving
     as a safety zone and the condition of being unutilized is not
     satisfied – It is not in dispute that the Supplementary Award had
     to be passed as the compensation for standing crops, structures
     and other damages for the subject land which could not be fixed
     and evaluated under the Award No. 1 dated 08.06.2018 – The
     passing of Supplementary Award was not a fresh exercise but rather
     a continuation/extension of the Award of 2018 – Therefore, when
     JAL has already paid the compensation amount as determined
     under the previous Award without any demur, it cannot be allowed
     to question its liability under the Supplementary Award and make
     a plea for return of the land at this stage on the ground that
     the purpose of the land is frustrated due to delay in acquisition
     proceedings. [Paras 35, 36, 37, 38, 39]
     Land Acquisition, Rehabilitation and Resettlement Act, 2013 –
     s.101 – Scope of:
     Held: The instant section was introduced in the 2013 Act for
     the first time as a beneficial provision for the landowners whose
     lands were usurped but remained unutilized or were not used
     in accordance with the purpose stated in the notifications under
     Section 4 – However, the application of the Section is warranted
     only in the circumstances where the return of the land would
     benefit the landowners – The party which has failed to utilize the
     land cannot plead for the return of the land and consequent refund
     of the compensation paid, as that would tantamount to taking
     advantage of its own wrong or default. [Para 40]
     Constitution of India – Art.300-A – Role of the State under
     Article 300-A of the Constitution – Responsibility of State to
     ensure full payment of compensation determined:
     Held: It is settled that once the compensation has been determined,
     the same is payable immediately without any requirement of a
446                                                             [2024] 9 S.C.R.

                        Digital Supreme Court Reports


       representation or request by the landowners and a duty is cast on
       the State to pay such compensation to the land losers, otherwise
       there would be a breach of Article 300-A of the Constitution – In the
       instant case, the Government of Himachal Pradesh as a welfare
       State ought to have proactively intervened in the matter with a view
       to ensure that the requisite amount towards compensation is paid
       at the earliest – The State cannot abdicate its constitutional and
       statutory responsibility of payment of compensation by arguing that
       its role was limited to initiating acquisition proceedings under the
       MOU signed between the Appellant, JAL and itself – This Court finds
       that the delay in the payment of compensation to the landowners
       after taking away ownership of the subject land from them is in
       contravention to the spirit of the constitutional scheme of Article
       300A and the idea of a welfare State – The State Government,
       in peculiar circumstances, was expected to make the requisite
       payment towards compensation to the landowners from its own
       treasury and should have thereafter proceeded to recover the
       same from JAL – Instead of making the poor landowners to run
       after the powerful corporate houses, it should have compelled JAL
       to make the necessary payment – Also, the State of Himachal
       Pradesh, being a welfare state, did not ensure payment of
       compensation to the Respondent Nos. 1-6 before taking possession
       of their land – A bare reading of Section 38 of the 2013 Act
       indicates that the payment of full and final compensation to the
       land owners is a precursor to taking possession of the land sought
       to be acquired from such persons – In fact, the landowners had
       to approach the High Court to seek directions to the LAC for
       passing of the supplementary award which was finally passed on
       02.05.2022 that is, after a period of almost four years from the date
       of passing of the Award of 2018 – Further, Section 41 of 1894 Act
       necessitates an agreement between the appropriate government
       and the company for whose purpose the land is being acquired –
       One of the purposes of such an agreement is to ensure that
       payment towards the cost of acquisition is made by the company
       to the appropriate government and it is only upon such payment
       that the land is transferred to the company – Thus, it can be said
       that JAL was mandated to make the requisite payment to the State
       of Himachal Pradesh prior to the subject land being transferred
       to it – However, even before the amount of compensation could
       be determined by way of a supplementary award as stipulated in
       the Award dated 08.06.2018, the subject land stood transferred to
[2024] 9 S.C.R.                                                           447

             M/s Ultra-Tech Cement Ltd. v. Mast Ram & Ors.


     JAL – This is in contravention of Section 38 of the 2013 Act and
     Section 41 of the 1894 Act respectively – Thus, the Respondent
     Nos. 7 (State of Himachal Pradesh) and 10 (LAC) are directed
     to pay the compensation amount of Rs. 3,05,31,095/- – The total
     amount paid by the State shall be recovered from the Respondent
     No. 11 (JAL). [Paras 47, 48, 50, 52, 54, 55, 58]

                             Case Law Cited
     Kolkata Municipal Corporation & Anr. v. Bimal Kumar Shah & Ors.
     [2024] 5 SCR 831 : 2024 SCC OnLine SC 968 – relied on.
     Roy Estate v. State of Jharkhand [2009] 7 SCR 343 : (2009) 12
     SCC 194; Union of India v. Mahendra Girji (2010) 15 SCC 682;
     Mansaram v. S.P. Pathak [1984] 1 SCR 139 : (1984) 1 SCC 125;
     Dharnidhar Mishra (D) and Another v. State of Bihar and Others
     [2024] 6 SCR 714 : 2024 SCC OnLine SC 932; State of Haryana v.
     Mukesh Kumar [2011] 14 SCR 211 : (2011) 10 SCC 404; Tukaram
     Kana Joshi and Ors. thr. Power of Attorney Holder v. M.I.D.C. and
     Ors. [2012] 13 SCR 29 : (2013) 1 SCC 353; Kukreja Construction
     Company & Ors. v. State of Maharashtra & Ors., 2024 SCC OnLine
     SC 2547; Premlal & Ors. v. State of Himachal Pradesh & Ors.,
     CWP No. 481 of 2010 – referred to.

                                List of Acts
     Land Acquisition Act, 1894; Land Acquisition, Rehabilitation and
     Resettlement Act, 2013; Companies Act, 1956; Constitution of India.

                             List of Keywords
     Section 101 of Land Acquisition, Rehabilitation and Resettlement
     Act, 2013; Section 38 of Land Acquisition, Rehabilitation and
     Resettlement Act, 2013; Section 41 of Land Acquisition Act, 1894;
     Sections 391-394 of the Companies Act, 1956; Article 300-A of
     the Constitution of India; Payment of compensation; Return of
     acquired land; Agreement with appropriate government; Power to
     take possession of land to be acquired.
                            Case Arising From
     CIVIL APPELLATE JURISDICTION: Civil Appeal No. 10662 of 2024
     From the Judgment and Order dated 12.07.2022 of the High Court of
     Himachal Pradesh at Shimla in CWP No.2350 of 2018
448                                                                                 [2024] 9 S.C.R.

                              Digital Supreme Court Reports


                                   Appearances for Parties
       Navin Pahwa, Sr. Adv., Mahesh Agarwal, Rishi Agrawala, Ankur
       Saigal, Victor Das, Ms. Geetika Sharma, Sudipto Sicar, Ms. Manavi
       Agarwal, E. C. Agrawala, Advs. for the Appellant.
       Puneet Rajta, A.A.G., Ranjit Kumar, Sr. Adv., Subhash Chandran
       Kr, Virender Thakur, Ms. Krishna Lr, Biju P Raman, Himanshu
       Tyagi, Vikrant Narayan Vasudeva, Sarthak Chiller, Rohit Lochav,
       Ms. Sharmila Upadhyay, Pawan R Upadhyay, Sarvjit Pratap Singh,
       M/s. Unuc Legal Llp, Advs. for the Respondents.
                       Judgment / Order of the Supreme Court

                                             Judgment
       J.B. Pardiwala, J.
       For the convenience of exposition, this judgment is divided into the
       following parts: -
                                                   INDEX*

        I.       FACTUAL MATRIX …………………………………………                                                       3

        II.      SUBMISSIONS ON BEHALF OF THE APPELLANT ….....                                         8

        III.     SUBMISSIONS ON BEHALF OF THE RESPONDENT
                 NOS. 1-6 …………………………………..........................                                      12

        IV.      SUBMISSIONS ON BEHALF OF THE RESPONDENT
                 NO. 10 …...........................................................................   13

        V.       SUBMISSIONS ON BEHALF OF THE RESPONDENT
                 NO. 11.............................................................................   15

        VI.      ISSUES FOR DETERMINATION …………………………                                                   17

        VII.     ANALYSIS …………………………………………………..                                                        18

                 A. Scheme of Arrangement between the Appellant and
                    JAL under Sections 391 to 394 respectively of the
                    Companies Act, 1956 ………………….....................                                   18


* Ed. Note: Pagination as per the original Judgment.
[2024] 9 S.C.R.                                                                      449

             M/s Ultra-Tech Cement Ltd. v. Mast Ram & Ors.



            B. Return of acquired land under the 2013 Act …………                        25

            C. Impugned Order of the High Court …...………………                            28

            D. Role of the State under Article 300-A of the
               Constitution ……...….................................................   30

      VIII. CONCLUSION ……………………………………………...                                           37


1.   Leave Granted.
2.   This appeal arises from the order passed by the High Court of
     Himachal Pradesh at Shimla dated 12.07.2022 in Civil Writ Petition
     No. 2350/2018 filed by the Respondent Nos. 1 to 6 herein (original
     petitioners) by which the High Court allowed the writ petition and
     directed the Appellant herein to pay the requisite amount towards
     compensation as determined in the Supplementary Award dated
     02.05.2022 passed by the Land Acquisition Collector, Arki (“LAC”)
     (Respondent No. 10) in the first instance with liberty to recover the
     same from M/s Jaiprakash Associates Limited (“JAL”) (Respondent
     No. 11) if permissible under the legal relationship between the two
     companies.
     I.    FACTUAL MATRIX
3.   The State of Himachal Pradesh (Respondent No. 7) issued a
     notification dated 25.07.2008 under Section 4 of the Land Acquisition
     Act, 1894 (the “1894 Act”) through its Department of Industries
     declaring its intention to acquire the subject land admeasuring 56-14
     bigha, situated at Mauza Bhalag, Tehsil Arki, District Solan, Himachal
     Pradesh (the “subject land”) in favour of Jaypee Himachal Cement
     project, a unit of JAL, invoking special powers in cases of urgency
     as provided under Section 17 of the 1894 Act. It appears that the
     purpose for acquiring the subject land was to create a safety zone
     surrounding the mining area. In other words, the subject land was
     situated in the vicinity of the leasehold area of the mining project
     and could not have been otherwise used for residential purposes
     or creation of any other structures. Subsequently notifications were
     also issued under Sections 6 and 7 respectively of the 1894 Act.
4.   It appears from the materials on record that during the acquisition
     proceedings, some of the landowners, including the Respondent Nos.
450                                                           [2024] 9 S.C.R.

                       Digital Supreme Court Reports


       1-6 herein did not allow the authorities to undertake the evaluation
       of their houses, trees, structures, etc., standing on the subject land
       for the purpose of determination of compensation.
5.     The acquisition proceedings ultimately came to be challenged by
       some of the landowners before the High Court by way of CWP No.
       2949 of 2009 titled as Premlal & Ors. v. State of Himachal Pradesh
       & Ors. and CWP No. 481 of 2010 titled as Chunni Lal & Ors. v.
       State of Himachal Pradesh & Ors. inter alia, on the ground that
       sub-section (4) of Section 17 of the 1894 Act could not have been
       invoked as the acquisition was not for any public purpose. The High
       Court passed an ad interim order dated 14.12.2011 granting stay on
       the acquisition proceedings.
6.     The High Court by a common judgment dated 23.06.2016 dismissed
       the writ petitions referred to above inter alia, on the ground that
       acquisition of the lands in question was for a public purpose as the
       said land contained vital raw material (limestone) for the manufacturing
       of cement and the usage of such mineral wealth would advance the
       public purpose of infrastructure development.
7.     As the writ petitions stood dismissed, the Land Acquisition Collector,
       Arki proceeded to pass the Award No. 1/2018 dated 08.06.2018 as per
       Section 11(1) of the 1894 Act and Section 24(1)(a) of the Right to Fair
       Compensation and Transparency in Land Acquisition, Rehabilitation
       and Resettlement Act, 2013 (the “2013 Act”) determining the
       compensation to the tune of Rs. 10,77,53,842.27/- (Rupees Ten
       Crore Seventy Seven Lakh Fifty Three Thousand Eight Hundred and
       Forty Two and Twenty Seven paisa Only) along with the incidental
       charges @ 2% amounting to Rs. 9,09,315.12/-. The LAC clarified
       in the award passed by him that the compensation amount towards
       the houses and other structures constructed prior to the date of
       notification under Section 4, whose survey was not allowed by the
       landowners during the acquisition proceedings would be considered
       in the supplementary award that may be passed separately after the
       reports regarding the valuation of structures were received.
8.     The amount as determined under the Award dated 08.06.2018 was
       deposited by JAL and disbursed to the landowners. The possession
       certificate dated 07.06.2019 in respect of the subject land was issued
       in favour of JAL. Subsequently, the entries in the revenue record of
       the subject land in favour of JAL came to be mutated on 12.11.2020.
[2024] 9 S.C.R.                                                        451

             M/s Ultra-Tech Cement Ltd. v. Mast Ram & Ors.


9.   Being dissatisfied with the Award dated 08.06.2018, the Respondent
     Nos. 1-6 herein filed writ petition no. 2350 of 2018 before the High
     Court on 16.09.2018, praying for a direction to the LAC to pass a
     supplementary award after quantifying the compensation for the
     damage caused to the structures and standing crops on the subject
     land for the period between 2008 and 2018 as well as for a direction
     to the LAC to pass a fresh award under the provisions of the 2013
     Act to provide additional amount @ 12% on market value with effect
     from the date of notification under Section 4 till the date of Award
     dated 18.06.2018. On 12.07.2019, the Respondent Nos. 1-6 also
     filed a Reference Petition under the 2013 Act praying inter alia for
     the enhancement of the amount of compensation determined under
     the Award dated 08.06.2018.
10. On 24.11.2021, the High Court passed an order directing the
    LAC to pass a supplementary award in accordance with law. On
    23.05.2022, the High Court recorded that the supplementary award
    dated 02.05.2022 had been passed in compliance with its order dated
    24.11.2021 under which an additional amount of Rs. 3,02,75,605/-
    along with incidental charges @ 2% of total assessment value was
    to be paid by JAL. Thus, the total additional amount determined
    was Rs. 3,05,31,095/- (Rupees Three Crore Five Lakh Thirty One
    Thousand and Ninety Five). However, the High Court recorded on
    20.06.2022 that the said amount had not been deposited in terms
    of its order dated 23.05.2022.
11. During the pendency of the acquisition proceedings, JAL entered into
    an agreement with the Appellant herein for the transfer of the cement
    project in question. In this regard, a Scheme of Arrangement was
    signed between the Appellant, JAL and Jaypee Cement Corporation
    Ltd. (the unit of JAL operating the cement project) (the “Scheme”) under
    the relevant provisions of the Companies Act, 1956. The Scheme was
    approved by the National Company Law Tribunal (“NCLT”) Mumbai
    Bench on 15.02.2017 and NCLT Allahabad Bench on 02.03.2017.
12. On 21.06.2017, the Director of Industries, Department of Industries,
    Government of Himachal Pradesh issued a letter to JAL and the
    Appellant acknowledging the approval given by the Joint Secretary to
    the Government of Himachal Pradesh as regards the transfer of the
    cement plant, as per the Scheme approved by the NCLT and as per
    the Tripartite Agreement between the Appellant, JAL and Government
    of Himachal Pradesh respectively, entered into on 29.06.2017.
452                                                           [2024] 9 S.C.R.

                       Digital Supreme Court Reports


13. In such circumstances, the High Court examined the relationship
    between the Appellant and JAL and also referred to the Scheme
    for the purpose of determining the issue as to who should pay the
    compensation amount determined under the Supplementary Award
    to the Respondent Nos. 1-6 respectively.
14. On 12.07.2022, the High Court relying on Clause 7.1 of the Scheme,
    passed the impugned order, directing the Appellant to pay the
    compensation amount at the first instance and left it open for the
    Appellant to recover the same from JAL later, if permissible in law.
15. In view of the aforesaid, the Appellant is before this Court with the
    present appeal.
       II.   SUBMISSIONS ON BEHALF OF THE APPELLANT
16. Mr. Navin Pahwa, the learned senior counsel appearing for the
    Appellant made the following submissions:
       a.    The High Court, in its impugned order, erred in directing
             the Appellant to pay the compensation amount determined
             under the Supplementary Award because the initial Award
             dated 08.06.2018 as well as the Supplementary Award dated
             02.05.2022 were passed by the LAC fixing the liability to pay
             compensation on JAL.
       b.    The High Court failed to consider that under the Scheme
             between the Appellant and JAL, as sanctioned by NCLT,
             Mumbai on 15.02.2017 and NCLT, Allahabad on 02.03.2017,
             all contingent liabilities pertaining to matters relating to the
             “JAL Business” (as defined in Clause 1.1(w) of the Scheme),
             including those of pending litigations where the disputed
             claims were not crystallized on or before the effective date,
             i.e., 29.06.2017, would be the sole liability of JAL. Since the
             acquisition proceedings for the subject land were initiated by a
             notification under Section 4 of the 1894 Act dated 25.07.2008,
             therefore, the litigation was pending as on 29.06.2017 (the
             “Effective Date”) and the disputed claim was not crystallized till
             the passing of the Supplementary Award dated 02.05.2022.
       c.    The High Court erred in recording that the Appellant had made
             the payment under the Award dated 08.06.2018, whereas
             factually, it was JAL who had paid the compensation amount
[2024] 9 S.C.R.                                                          453

             M/s Ultra-Tech Cement Ltd. v. Mast Ram & Ors.


           under the said Award. The High Court also failed to consider that
           by making the payment under the Award dated 08.06.2018, JAL
           had accepted its liability for claims arising out of the acquisition
           proceedings.
     d.    The subject land was acquired for JAL. Accordingly, the LAC
           had issued a possession certificate dated 07.06.2019 in favour
           of JAL and handed over spot possession of the subject land
           to it under Section 16 of the 1894 Act. The subject land was
           duly mutated in the name of JAL vide Mutation No. 232 dated
           12.11.2020. The High Court failed to take into consideration the
           fact that the subject land had not been transferred as an asset
           to the Appellant under the Scheme. To establish the same,
           the Appellant had placed on record and referred to a Chart
           of Comparison of Khasra Numbers under the Scheme and
           the Khasra Numbers which were transferred to JAL under the
           Award dated 08.06.2018 contending that none of the Khasra
           Numbers of the subject land or portions thereof overlap with
           the Khasra Numbers of the land/assets transferred under the
           Scheme. Therefore, since the Appellant was not enjoying the
           possession or benefit, if any, of the subject land, the liability
           of paying the compensation under the Supplementary Award
           could not have been fastened on it.
     e.    As per the Scheme, the Appellant only purchased certain
           assets listed in the Schedule-I and Schedule-IA thereof on a
           “slump exchange basis” and did not take over JAL. Mr. Pahwa
           clarified that JAL is a surviving entity and the High Court had
           erred in understanding that JAL stood merged or transferred
           with the Appellant.
     f.    Mr. Pahwa also brought our attention to the order passed
           by this Court dated 16.12.2019 in Ultratech Cement Ltd. v.
           Tonnu Ram, SLP (C) (Diary) No. 42997 of 2019 wherein this
           Court clarified that the impugned judgment of the High Court of
           Himachal Pradesh could not have been construed as permitting
           third party to pursue claim for recovery against the Appellant
           in disregard of the Scheme and the executing court would be
           duty-bound to examine the purport of the Scheme and pass
           orders strictly in consonance therewith.
454                                                             [2024] 9 S.C.R.

                       Digital Supreme Court Reports


            The relevant observations made by this Court in Tonnu Ram
            (supra) are reproduced below:
                  “…It cannot be construed as permitting third party
                  to pursue claim for recovery against the petitioner in
                  disregard of the scheme of arrangement propounded
                  by the NCLT in respect of respondent No.4- M/s.
                  Jaiprakash Industries.
                  Despite this clear position, if any third party intends to
                  pursue remedy against the petitioner, the Executing
                  Court would be duty bound to examine the purport
                  of the stated scheme propounded by the NCLT
                  and pass orders strictly in consonance therewith.
                  It would be open to the petitioner to invite attention
                  of the Executing Court or any other Forum about the
                  relevant provisions in the scheme in support of the
                  argument that the liability to pay the dues will remain
                  that of respondent No.4- M/s. Jaiprakash Industries
                  as per the stated scheme.”
                                                   [Emphasis supplied]
       g.   The senior counsel also submitted that JAL had made a
            declaration on oath in Form-16A under Order XXI Rule 41(2)
            of the Code of Civil Procedure, 1908 dated 04.12.2023 in Civil
            Revision Petition No. 174 of 2022 titled Tohnu Ram (Deceased)
            v. M/s Ultratech Cement Ltd. before the High Court of Himachal
            Pradesh which read as follows:
                  “…(e) Other Property: List of Property of Jaiprakash
                  Associates Ltd., i.e. Land measuring 56-14 bigha,
                  situate at village bhalag, PO Kandhar, Tehsil Arki,
                  Distt. Solan (HP), vide which the Mutation was
                  attested on 12.11.2020 in favour of Jaiprakash
                  Associates Ltd…”
       Therefore, in view of the above, the subject land remained in
       ownership of JAL and the Appellant had no connection with the
       subject land, directly or indirectly and that the subject land was neither
       acquired for the benefit of the Appellant nor was it transferred under
       the Scheme to the Appellant.
[2024] 9 S.C.R.                                                           455

              M/s Ultra-Tech Cement Ltd. v. Mast Ram & Ors.


     III.   SUBMISSIONS ON BEHALF OF THE RESPONDENT NOS. 1-6
17. Mr. Biju P. Raman, the learned counsel appearing for the Respondent
    Nos. 1-6 made the following submissions:
     a.     The subject land forms a part of the safety zone area meant
            for the cement plant that was being operated by the cement
            unit of JAL. The District Administration acquired 56.14 bhigas
            of land and the Award for the same was passed on 08.06.2018
            by the LAC, Arki.
     b.     The plant/project had been taken over by the Appellant herein
            by acquiring all the assets and liabilities of JAL in the year 2017
            and all movable and immovable assets and liabilities ancillary
            thereto were transferred to the Appellant, which was affirmed
            by a tripartite Memorandum of Understanding signed between
            the Appellant, JAL and the Government of Himachal Pradesh
            (the “MOU”) dated 29.06.2017.
     c.     The High Court vide order dated 12.07.2022 recorded the
            submission of the Respondent Nos. 1-6 that the payment
            towards the Award No. 1 of 2018 pertaining to the subject land
            was deposited by the Appellant.
     d.     The Appellant and JAL are trying to escape from their legal
            obligation and liability to pay the compensation amount
            as determined under the Supplementary Award to the
            Respondents and are in collusion with each other creating
            an inter-se dispute with the intention of depriving the original
            landowners of their legitimate right to receive compensation
            due to them.
     e.     The subject land was acquired for public purpose and was
            being utilized by the Appellant for its purposes.
     IV.    SUBMISSIONS ON BEHALF OF THE RESPONDENT NO. 10
18. Mr. Puneet Rajta, the learned Additional Advocate General appearing
    for the Respondent No. 10 i.e., the Land Acquisition Collector, Arki
    made the following submissions:
     a.     The subject land was acquired in the year 2018 for providing a
            safety zone to the cement plant which had already been taken
            over by the Appellant in the year 2016.
456                                                           [2024] 9 S.C.R.

                       Digital Supreme Court Reports


       b.   The acquired land is being utilized by the Appellant as a safety
            zone for the cement plant being run by them. However, the land
            is recorded in the name of JAL.
       c.   The role of the State was limited to the extent of initiating the
            acquisition proceedings and as per the MOU signed with the
            Government of Himachal Pradesh, all costs pertaining to the
            acquisition/transfer of land would be borne by the company
            only. It was clarified that the State had no role to play in the
            business of manufacturing or running the cement plant of the
            company and all payments under the Award No. 1 of 2018 dated
            08.06.2018 stood paid to the landowners by JAL.
       d.   The Supplementary Award was passed on 02.05.2022 in
            accordance with the direction of the High Court dated 16.09.2018
            in CWP No. 2350 of 2018 and the High Court through a separate
            order dated 12.07.2022 directed the Appellant to make the
            payment to the landowners and recover the said amount from
            JAL. The said order was challenged by the Appellant and this
            Court while issuing notice vide order dated 22.08.2022 directed
            that there shall be a stay of operation and implementation of
            the impugned order of the High Court.
       e.   The land is being used by the Appellant for the purpose of
            operating the cement plant however, they are raising disputes
            only with the view to deny the rights of the landowners. Therefore,
            the liability for payment of compensation be fixed as against the
            Appellant or JAL. It was submitted that if the State was directed
            to compensate the landowners, it would have to do so out of
            public funds and seek reimbursement.
       V.   SUBMISSIONS ON BEHALF OF THE RESPONDENT NO. 11
19. Mr. Ranjit Kumar, the learned senior counsel appearing for the
    Respondent No. 11 i.e., M/s Jaiprakash Associates Limited (JAL)
    made the following submissions:
       a.   During the process of passing of the Supplementary Award
            dated 02.05.2022, JAL had clarified that that it had handed
            over the cement project to the Appellant on 29.06.2017 and the
            subject land was acquired for the purpose of mining activities
            and safety zone. It was asserted that the subject land was an
            integral part of the cement project. Therefore, whosoever was
[2024] 9 S.C.R.                                                          457

             M/s Ultra-Tech Cement Ltd. v. Mast Ram & Ors.


           operating the cement plant and carrying out the mining activities
           was responsible for maintaining the safety zone. Accordingly,
           it was the duty of the Appellant to pay the amount determined
           under the Supplementary Award.
     b.    During the course of the hearing of the Writ Petition No. 2350 of
           2018, the Appellant had stated that it did not require the subject
           land for its projects. The Counsel contended that since JAL had
           already handed over the cement project to the Appellant and
           the subject land was acquired for the purpose of safety zone
           for the said project, the Appellant cannot say that they never
           had any need for this particular land.
     c.    Although the State Government had handed over the symbolic
           possession of the subject land in favour of JAL on 07.06.2019 yet
           the physical possession of this land remained with the villagers/
           landowners including Respondent Nos. 1-6 who had illegally
           occupied the subject land and had constructed houses/structures
           on the same even after the deliverance of the Award dated
           08.06.2018 and the Supplementary Award dated 02.05.2022.
     d.    It was submitted that the substantial delay in the issuance of
           the Award by the LAC had frustrated the purpose of acquisition
           for JAL. Since the entire project has been under the custody
           and possession of the Appellant, it is the appropriate party to
           address the issue of the requirement of the subject land for the
           purpose of Mining Activities & Safety Zone. If the Appellant is not
           interested in the subject land, then the same should be returned
           to the original landowners (Respondent Nos. 1-6 herein) and
           the amount deposited as an award of Rs. 10,77,53,842/- in the
           year 2018 should be refunded to JAL.
     e.    Mr. Kumar contended that according to the statement provided by
           the Appellant to the High Court, it can be reasonably concluded
           that the Appellant does not require the land in question, which
           was acquired for the purpose of Mining Activities and Safety Zone
           for the Cement project. Therefore, the Appellant may proceed
           to submit an application in this regard to the Government of
           Himachal Pradesh, as submitted before the High Court.
     f.    The Counsel reiterated that JAL had sold out and handed over
           the entire cement project to the Appellant in the year 2017,
           which included the acquired private land and government land
458                                                             [2024] 9 S.C.R.

                         Digital Supreme Court Reports


              diverted for this purpose. It was submitted that the subject land
              was required for an entity involved in cement production in the
              area, therefore, the responsibility for maintaining the Safety Zone
              of the cement project was with the Appellant. If the Appellant is
              not interested in the acquired subject land, then the same may
              be returned and the amount of Rs. 10,77,53,842/- deposited
              as award in the year 2018 be refunded to JAL.
       VI.    ISSUES FOR DETERMINATION
20. Having heard the learned counsel appearing for the parties and having
    gone through the materials on record, the following four questions
    fall for our consideration: -
       i.     Whether the subject land and all other liabilities associated with
              it were transferred to the Appellant in terms of the Scheme?
       ii.    Whether it was the Appellant or JAL who was legally obliged
              to pay the compensation amount determined under the
              Supplementary Award?
       iii.   Whether the land in terms of Section 101 of the 2013 Act can
              be returned to the Respondent Nos. 1-6 at this stage under
              the scheme of the Act? In other words, what is the scope of
              Section 101?
       iv.    Whether the State of Himachal Pradesh, being a welfare state, had
              the responsibility to ensure full payment of compensation amount
              determined under the Supplementary Award dated 02.05.2022?
       VII. ANALYSIS
       A.     Scheme of Arrangement between the Appellant and JAL
              under Sections 391 to 394 respectively of the Companies
              Act, 1956
21. An analysis of the Scheme agreed between the Appellant and JAL as
    sanctioned by the NCLT, Mumbai and NCLT, Allahabad respectively
    is the key to determine who should pay the amount determined
    under the Supplementary Award dated 02.05.2022. With respect to
    the Scheme, the following questions need to be looked into:
       i.     Whether the dispute pertaining to payment of the requisite
              amount under the Supplementary Award arose before or after
              the “Effective Date” fixed in the Scheme?
[2024] 9 S.C.R.                                                               459

                 M/s Ultra-Tech Cement Ltd. v. Mast Ram & Ors.


     ii.   Whether the subject land is an integral part of the cement
           project and the liability of paying compensation under the
           Supplementary Award for the said land can be imposed on the
           Appellant despite the said land not being in its name?
22. Clause 1.1 (o) defines the “Effective Date” as the date on which the
    Scheme becomes effective in accordance with its terms, which shall
    be the Closing Date [defined in Clause 1.1(k) and Clause 10.1]. The
    said date was decided to be 29.06.2017 among the parties.
23. Clause 1.1(w) defines the business and assets transferred by JAL
    to the Appellant. The definition of the same is reproduced below:
           “…(w) “JAL Business” means the business of
           manufacturing, sale and distribution of cement and clinker
           manufactured at the JAL Cement Plants, including all
           rights to operate such business, its movable or immovable
           assets, captive power plants, DG sets, coal linkages, rights,
           privileges, liabilities, guarantees, land, leases, licenses,
           permits, mining leases, prospecting licenses for mining of
           limestone, letters of intent for mining of limestone, tangible
           or intangible assets, goodwill, all statutory or regulatory
           approvals, logistics, marketing, warehousing, selling
           and distribution networks (marketing employees, offices,
           depots, guest houses and ether related facilities for the JAL
           Business), employees, existing contracts including fly-ash
           contracts, railway sidings, fiscal incentives in relation to the
           JAL Business, more particularly described in Schedule I
           hereto, but does not include
           (i)     construction equipment and such assets to be listed
                   in Schedule II.
           (ii)    any liability including contingent liability disclosed in
                   the balance sheet of JAL Business on the Closing
                   Date provided to the Transferee, other than those
                   included in the JAL Financial Indebtedness and JAL
                   Net Working Capital;
           (iii) any guarantee or deposits for any disputes;
           (iv) the JAL Excluded Employees;
           (v)     JAL Non Moving Stores, Doubtful Receivables of
                   the JAL Business, non-recoverable debtors, loans
460                                                         [2024] 9 S.C.R.

                     Digital Supreme Court Reports


                or advances in the books of the Transferor1. For
                this purpose, non-recoverable debtors; loans or
                advances shall refer to such debtors; loans or
                advances for which Transferor1 has not received
                any confirmation for the receivables as mentioned
                in Clause 9.1 (i);
          (vi) coal mitting block - Mandla (North) and the related
               guarantees, deposits etc;
          (vii) fiscal incentives in relation to the JAL Business that
                accrue up to the Closing Date;
          (viii) any intellectual property of Transferor1;
          (ix) litigations pertaining to the JAL Business as of
               the Closing Date;
          (x)   freehold plot of land admeasuring about 1087 square
                metres at Varanasi and land admeasuring 24.7 acres
                outside the Balaji plant in Krishna, Andhra Pradesh;
          (xi) 180 megawatt power plant at Churk, Uttar Pradesh;
          (xii) railway siding in Turki, Rewa, Madhya Pradesh;
          (xiii) Related Party payables or receivables; and
          (xiv) Ghurma limestone mine, Padrach limestone mine
                and Bari dolomite mine
          It is clarified that the guarantee listed in Schedule III B,
          which shall be updated as of the Closing Date, shall be
          the only guarantees which shall be taken over by the
          Transferee on the Closing Date…”
                                               [Emphasis Supplied]
24. The parties by way of Clause 1.1(w)(ix) agreed that all litigations
    pertaining to the business and assets being transferred to the
    Appellant that arose before or on the Closing Date would not be
    transferred to the Appellant and will remain with JAL.
25. The aforesaid aspect has been further elaborated under Clause 7
    of the Scheme which is reproduced below:
[2024] 9 S.C.R.                                                             461

             M/s Ultra-Tech Cement Ltd. v. Mast Ram & Ors.


           “7. LEGAL PROCEEDINGS
           7.1 All legal or other proceedings (whether civil or
           criminal, including before any statutory or judicial
           or quasi-judicial authority or tribunal) by or against
           the Transferor1 and /or the Transferor2, initiated on
           or arising and pending before the Effective Date,
           and relating to the JAL Business and the JCCL
           Business shall remain with the Transferor1 and/or the
           Transferor2, as the case may be.
           7.2 In the event any case or matter pertaining to
           contingent liabilities being in the nature of disputed claims,
           not crystallized on the Closing Date or guarantees listed in
           Schedule III A and Schedule XI A or any similar instrument
           by whatsoever name called which have been advance
           against disputes related to the JAL Business or the JCCL
           Business existing on the Closing Date, or pertaining to NPV
           of afforestation charges in respect of mining land being
           Block 1, 2, 3, 4 and Ningha of Dalla Plant and Jaypee Super
           Plant, by force of law are transferred to the Transferee, then
           the Transferor1 and the Transferor 2, shall have full control
           in respect of the defence of such proceedings including
           filing the necessary appeals, revisions, etc.. provided that
           the Transferor1 and the Transferor2, as the case may be,
           shall not, take any action that is detrimental to the operation
           of the JAL Business and the JCCL Business. Provided that
           in respect of such cases pertaining to immovable properties
           which are part of the JAL Business or the JCCL Business,
           as the case may be the Transferee shall have a right to
           participate in such proceedings to ensure that no action
           detrimental to the operation of JAL Business and the JCCL
           Business is taken. It is clarified that: (a) any liabilities in
           respect of cases or matter referred to in this Clause 7.2
           shall be paid by the Tranferor1 or the Transferor2 and if
           paid by the Transferee, the same shall be reimbursed by
           the Transferor1 or the Transferor2 within 7 (seven) days
           of such payment; and (b) the aforesaid bank guarantees
           provided by the Transferor1 and the Transferor2 in respect
           of the contingent liabilities being in the nature of disputed
           claims related to the JAL Business or the JCCL Business
462                                                        [2024] 9 S.C.R.

                     Digital Supreme Court Reports


          shall continue wherever required and the Transferee shall
          have no obligation to replace such bank guarantees on the
          Closing Date and in the event the period of any such bank
          guarantee expires after the Closing Date, the Transferor1
          and /or the Transferor2, as the case may be, shall renew
          or replace such guarantees wherever required.
          7.3 The Transferor1, the Transferor2 and the Transferee
          shall give full and timely cooperation to each other for
          the pursuit of such case or matter. The Transferee shall
          promptly give necessary authorization, power of attorney,
          board resolution, etc. for pursuit of such case or matter to
          the Transferor1 and the Transferor2. ”
                                               [Emphasis Supplied]
26. Clause 7.1 of the Scheme states without any ambiguity that any
    legal or other proceeding by or against JAL or its unit operating the
    cement project relating to the JAL Business as defined in Clause
    1.1(w), initiated on or arising and pending before the Effective Date
    shall remain with JAL.
27. It is pertinent to note that the subject land was acquired under the
    compulsory provisions of the 1894 Act to provide a safety zone
    for the cement plant and mining areas. Therefore, the land was
    acquired in connection with the JAL Business. The acquisition
    proceedings began with the notification issued under Section 4
    dated 25.07.2008 which was stayed by the High Court of Himachal
    Pradesh on 14.12.2011. After the disposal of the writ petitions filed by
    the original landowners, the operation of the stay on the acquisition
    proceedings came to an end on 23.06.2016. As the next step towards
    the proceedings, an Award dated 08.06.2018 was passed. The
    facts indicate that the land acquisition proceedings had commenced
    before the Effective Date of the Scheme (i.e. 29.06.2017) and the
    compensation remained undetermined as on the Effective Date. To
    our understanding, these facts attract the application of Clause 7.1
    of the Scheme as the acquisition proceedings and the liability to pay
    compensation associated with it squarely falls within the meaning of
    ‘other proceedings’ as intended by the parties under the said Clause.
28. JAL has also not disputed that it had made payment of the amount
    determined under the Award of 2018 i.e., Rs. 10,77,53,842/- after
[2024] 9 S.C.R.                                                        463

             M/s Ultra-Tech Cement Ltd. v. Mast Ram & Ors.


     the Effective Date of the Scheme. The said amount has already
     been disbursed to the landowners. There is nothing on record to
     show that the payment of compensation amount at that time was
     contested by JAL.
29. Further, the exercise of determination of compensation amount which
    is a part of the acquisition proceedings remained pending even
    after the Effective Date of the Scheme. After the LAC determined
    the amount under the Award dated 08.06.2018, JAL paid the same
    without any protest or reference to the Scheme. Therefore, at the
    stage of the Supplementary Award pertaining to the same land and
    same original landowners, JAL cannot be allowed to take the plea
    that the payments with respect to the subject land were required to
    be made by the Appellant.
30. As regards the contention of JAL that the subject land formed an
    integral part of the cement project transferred to the Appellant for
    the purpose of payment of compensation determined under the
    Supplementary Award, we find it difficult to accept the same. The
    subject land was acquired as a safety zone for the cement project
    and in light of the several safety hazards as stated in the Award No.
    1 of 2018, the land had to be acquired to safeguard the lives and
    property of the original landowners.
31. However, we take notice of the fact that the subject land was not
    covered under the list of assets transferred to the Appellant under
    the Scheme and remains in the ownership of the JAL till date. While
    we agree that the acquisition of the subject land was done for the
    purposes of the cement project, we cannot accept the contention of
    JAL that the liabilities arising out of the said land should be fastened
    upon the Appellant without any such liabilities being covered by the
    Scheme, not even on the strength of the argument that the subject
    land was integral to the cement project.
32. We may only say that the issue regarding the ownership of the subject
    land may be decided between the parties i.e., the Appellant and JAL
    amongst themselves. In our considered view, disputes regarding the
    ownership of the subject land, if any cannot be an impediment to the
    legitimate rights of the original landowners to receive compensation.
    Therefore, the contention of JAL that the Appellant should pay the
    amount as determined under the Supplementary Award because the
    subject land was integral to the cement project is rejected.
464                                                        [2024] 9 S.C.R.

                      Digital Supreme Court Reports


       B.   Return of acquired land under the 2013 Act
33. It is the case of JAL that the substantial delay in acquisition of the
    subject land has frustrated its purpose, and it could not make any
    use of the land. It was submitted that if the Appellant does not require
    the said land, then it should be returned to the original landowners
    and the amount of Rs. 10,77,53,842/- paid under the Award of 2018
    should be refunded to JAL.
34. The return of acquired land is governed by Section 101 of the 2013
    Act which is reproduced below:
            “101. Return of unutilised land.– When any land acquired
            under this Act remains unutilised for a period of five
            years from the date of taking over the possession, the
            same shall be returned to the original owner or owners or
            their legal heirs, as the case may be, or to the Land Bank
            of the appropriate Government by reversion in the manner
            as may be prescribed by the appropriate Government.
            Explanation.—For the purpose of this section, “Land
            Bank” means a governmental entity that focuses on the
            conversion of Government owned vacant, abandoned,
            unutilised acquired lands and tax-delinquent properties
            into productive use.”
                                               [Emphasis Supplied]
35. The necessary conditions for the application of Section 101 are: (1)
    the land should be unutilized; and (2) the period it remains not in use
    should be at least five years from the date of taking of possession.
36. We do not find any merit in the contention of JAL that the land be
    returned to the original landowners. While we agree that a period
    of five years has elapsed from the date of taking of possession by
    JAL, the first condition that the land should remain unutilized is not
    fulfilled.

37. The subject land was acquired for the purpose of providing a safety
    zone to the mining area of the cement plant. The objective for acquiring
    the subject land mentioned in the Award of 2018 is reproduced below:
            “…3. Compulsory Acquisition by invoking the provisions
            of Section 17 (4)
[2024] 9 S.C.R.                                                        465

             M/s Ultra-Tech Cement Ltd. v. Mast Ram & Ors.


           During the process of Notification issued under Section
           - 4 of the Land Acquisition Act, the matter was taken up
           for compulsory acquisition U/s 17(4) of Land Acquisition,
           Act, 1894 with the Govt. or Himachal Pradesh for the
           reasons that the land area under acquisition fell just
           below the mine leasehold area and was necessarily
           required as Mining Area Safety Zone. As the land area
           under acquisition cannot be allowed for any residential
           purpose in view of safety reasons and because the
           land proposed for acquisition is located just along
           the bank or Bhalag Nallah and most of the residents
           of village Bhalag had been constructing structures in
           large numbers on the right Bank of Nallah in Bhalag
           village, therefore provisions of compulsory acquisition
           needed to be invoked.
           Furthermore, to invoke the provisions of compulsory
           acquisition, it was submitted vide this office letter No.
           2766 dated 06.01.2009 to Pr. Secretary (Industries) GoHP
           that the main dumping site of the project at Baga -
           Sehnali is situated above village Bhalag and during the
           unprecedented I I heavy rain season of 2007 – 08, muck
           had over flown into the Bhalag Nallah endangering
           the Safety Zone area under proposed acquisition…”
                                               [Emphasis Supplied]
38. Therefore, the acquisition of the subject land was done as a safety
    measure for the residents of the area and not to be used actively in
    the cement project. No other use except that the subject land may
    pose hazard to the residents was envisaged during the acquisition
    proceedings. JAL cannot pray for return of the land as that would
    result in endangering the lives and property of the original landowners.
    We find that the subject land has been in use all throughout the
    operation of the cement project by serving as a safety zone and the
    condition of being unutilized is not satisfied.
39. It is not in dispute that the Supplementary Award had to be passed as
    the compensation for standing crops, structures and other damages
    for the subject land which could not be fixed and evaluated under
    the Award No. 1 dated 08.06.2018. The same was also recorded
    in the Award of 2018. We find that the passing of Supplementary
466                                                          [2024] 9 S.C.R.

                       Digital Supreme Court Reports


       Award was not a fresh exercise but rather a continuation/extension
       of the Award of 2018. Therefore, when JAL has already paid the
       compensation amount as determined under the previous Award
       without any demur, it cannot be allowed to question its liability under
       the Supplementary Award and make a plea for return of the land at
       this stage on the ground that the purpose of the land is frustrated
       due to delay in acquisition proceedings.
40. At this stage, it is necessary for us to discuss the purport of Section
    101 of the 2013 Act. The instant section was introduced in the 2013
    Act for the first time as a beneficial provision for the landowners
    whose lands were usurped but remained unutilized or were not used
    in accordance with the purpose stated in the notifications under
    Section 4. However, the application of the Section is warranted only
    in the circumstances where the return of the land would benefit the
    landowners. The party which has failed to utilize the land cannot
    plead for the return of the land and consequent refund of the
    compensation paid, as that would tantamount to taking advantage
    of its own wrong or default.
       C.    Impugned Order of the High Court
41. The High Court directed the Appellant herein to pay compensation
    amount determined under the Supplementary Award at the first
    instance and if permissible, recover the same from JAL.
42. We find that the High Court’s reasoning for passing such a direction
    is unsustainable for the following reasons:
       i.    The High Court has referred to Clause 7.1 of the Scheme but
             has not applied it correctly in any manner, thereby ignoring the
             Scheme of Arrangement between the parties.
       ii.   The High Court has also recorded that JAL has been taken
             over by the Appellant herein and that the Appellant had made
             payment of compensation under the Award No. 1 of 2018 dated
             08.06.2018. We find that these are incorrect facts on the basis
             of the materials presented to us by the parties to this appeal.
             JAL has only transferred the cement project and clinkerisation
             business to the Appellant by way of the Scheme and is still
             existing independently of the Appellant’s control in respect of
             its other functions.
[2024] 9 S.C.R.                                                            467

              M/s Ultra-Tech Cement Ltd. v. Mast Ram & Ors.


            The documents on record also show that it was JAL that had
            made payments under the Award of 2018 and not the Appellant.
     iii.   The High Court failed to consider that the ownership of the
            subject land continued to be with JAL despite the Scheme
            being brought into effect on 29.06.2017. The Appellant cannot
            be directed to make payment of the amount determined by the
            Supplementary Award for the portions of land which are neither
            in its ownership nor possession.
     iv.    The High Court also failed to consider the order of this Court in
            Tonnu Ram (supra) dated 16.12.2019 which imposed a duty
            on the executing court to examine the purport of the Scheme
            propounded by the NCLT and pass orders strictly in consonance
            therewith. It was held that it would be open to the Appellant to
            take support of the relevant provisions of the Scheme in support
            of the argument that the liability to pay the dues remains with
            JAL as per the stated scheme.
     D.     Role of the State under Article 300-A of the Constitution
43. The Right to Property in our country is a net of intersecting rights which
    has been explained by this Court in Kolkata Municipal Corporation
    & Anr. v. Bimal Kumar Shah & Ors., 2024 SCC OnLine SC 968.
    A division bench of this Court identified seven non-exhaustive sub-
    rights that accrue to a landowner when the State intends to acquire
    his/her property. The relevant observations of this Court under the
    said judgment are reproduced below:
            “…27.
            … Seven such sub-rights can be identified, albeit non-
            exhaustive. These are: i) duty of the State to inform the
            person that it intends to acquire his property – the right
            to notice, ii) the duty of the State to hear objections to
            the acquisition – the right to be heard, iii) the duty of the
            State to inform the person of its decision to acquire – the
            right to a reasoned decision, iv) the duty of the State to
            demonstrate that the acquisition is for public purpose –
            the duty to acquire only for public purpose, v) the duty
            of the State to restitute and rehabilitate – the right of
            restitution or fair compensation, vi) the duty of the
            State to conduct the process of acquisition efficiently
468                                                         [2024] 9 S.C.R.

                      Digital Supreme Court Reports


            and within prescribed timelines of the proceedings –
            the right to an efficient and expeditious process, and
            vii) final conclusion of the proceedings leading to vesting
            – the right of conclusion…”
                                               [Emphasis Supplied]
       This Court held that a fair and reasonable compensation is the sine
       qua non for any acquisition process.
44. In Roy Estate v. State of Jharkhand, (2009) 12 SCC 194; Union
    of India v. Mahendra Girji, (2010) 15 SCC 682 and Mansaram
    v. S.P. Pathak, (1984) 1 SCC 125, this Court underscored the
    importance of following timelines prescribed by the statutes as well
    as determining and disbursing compensation amount expeditiously
    within reasonable time.
45. The subject land came to be acquired by invoking special powers in
    cases of urgency under Section 17(4) of the 1894 Act. The invocation
    of Section 17(4) extinguishes the statutory avenue for the landowners
    under Section 5A to raise objections to the acquisition proceedings.
    These circumstances impose onerous duty on the State to facilitate
    justice to the landowners by providing them with fair and reasonable
    compensation expeditiously. The seven sub-rights of the landowners
    identified by this Court in Kolkata Municipal Corporation (supra)
    are corresponding duties of the State. We regret to note that the
    amount of Rs. 3,05,31,095/- determined as compensation under the
    Supplementary Award has not been paid to the landowners for a
    period of more than two years and the State of Himachal Pradesh
    as a welfare State has made no effort to get the same paid at the
    earliest.
46. This Court has held in Dharnidhar Mishra (D) and Another v.
    State of Bihar and Others, 2024 SCC OnLine SC 932 and State
    of Haryana v. Mukesh Kumar, (2011) 10 SCC 404 that the right to
    property is now considered to be not only a constitutional or statutory
    right, but also a human right. This Court held in Tukaram Kana Joshi
    and Ors. thr. Power of Attorney Holder v. M.I.D.C. and Ors., (2013)
    1 SCC 353 that in a welfare State, the statutory authorities are legally
    bound to pay adequate compensation and rehabilitate the persons
    whose lands are being acquired. The non-fulfilment of such obligations
    under the garb of industrial development, is not permissible for any
[2024] 9 S.C.R.                                                      469

             M/s Ultra-Tech Cement Ltd. v. Mast Ram & Ors.


     welfare State as that would tantamount to uprooting a person and
     depriving them of their constitutional/human right.
47. That time is of the essence in determination and payment of
    compensation is also evident from this Court’s judgment in Kukreja
    Construction Company & Ors. v. State of Maharashtra & Ors.,
    2024 SCC OnLine SC 2547 wherein it has been held that once
    the compensation has been determined, the same is payable
    immediately without any requirement of a representation or request
    by the landowners and a duty is cast on the State to pay such
    compensation to the land losers, otherwise there would be a breach
    of Article 300-A of the Constitution.
48. In the present case, the Government of Himachal Pradesh as a
    welfare State ought to have proactively intervened in the matter with
    a view to ensure that the requisite amount towards compensation is
    paid at the earliest. The State cannot abdicate its constitutional and
    statutory responsibility of payment of compensation by arguing that
    its role was limited to initiating acquisition proceedings under the
    MOU signed between the Appellant, JAL and itself. We find that the
    delay in the payment of compensation to the landowners after taking
    away ownership of the subject land from them is in contravention to
    the spirit of the constitutional scheme of Article 300A and the idea
    of a welfare State.
49. Acquisition of land for public purpose is undertaken under the power
    of eminent domain of the government much against the wishes of
    the owners of the land which gets acquired. When such a power is
    exercised, it is coupled with a bounden duty and obligation on the
    part of the government body to ensure that the owners whose lands
    get acquired are paid compensation/awarded amount as declared
    by the statutory award at the earliest.
50. The State Government, in peculiar circumstances, was expected to
    make the requisite payment towards compensation to the landowners
    from its own treasury and should have thereafter proceeded to recover
    the same from JAL. Instead of making the poor landowners to run
    after the powerful corporate houses, it should have compelled JAL
    to make the necessary payment.
51. Although the requirement to pass a supplementary award for the
    purpose of determining additional compensation for the standing
470                                                           [2024] 9 S.C.R.

                       Digital Supreme Court Reports


       trees, damaged structures, houses, etc. had been envisaged and
       recorded in the Award dated 08.06.2018, yet the possession of the
       subject land came to be handed over to JAL vide the possession
       certificate dated 07.06.2019 without passing such a supplementary
       award. We are of the considered view that the omission or lapse to
       complete such exercise before taking possession of the land could
       be said to be in contravention of the mandate of Section 38(1) of the
       2013 Act. The relevant portion of Section 38 is reproduced below:
            “38. Power to take possession of land to be acquired. –
            (1) The Collector shall take possession of land after
            ensuring that full payment of compensation as well
            as rehabilitation and resettlement entitlements are paid or
            tendered to the entitled persons within a period of three
            months for the compensation and a period of six months
            for the monetary part of rehabilitation and resettlement
            entitlements listed in the Second Schedule commencing
            from the date of the award made under section 30: Provided
            that the components of the Rehabilitation and Resettlement
            Package in the Second and Third Schedules that relate to
            infrastructural entitlements shall be provided within a period
            of eighteen months from the date of the award: Provided
            further that in case of acquisition of land for irrigation or
            hydel project, being a public purpose, the rehabilitation
            and resettlement shall be completed six months prior to
            submergence of the lands acquired…”
                                                 [Emphasis supplied]
52. A bare reading of Section 38 as reproduced above indicates that
    the payment of full and final compensation to the land owners is a
    precursor to taking possession of the land sought to be acquired from
    such persons. It is clear from the facts that the acquisition proceedings
    herein failed to confirm to this statutorily mandated sequence of
    events. It is regrettable that the State of Himachal Pradesh, being
    a welfare state, did not ensure payment of compensation to the
    Respondent Nos. 1-6 before taking possession of their land. In fact,
    the landowners had to approach the High Court to seek directions to
    the LAC for passing of the supplementary award which was finally
    passed on 02.05.2022 that is, after a period of almost four years
    from the date of passing of the Award of 2018.
[2024] 9 S.C.R.                                                            471

             M/s Ultra-Tech Cement Ltd. v. Mast Ram & Ors.


53. Further, the acquisition proceedings for the subject land had
    commenced vide the notification under Section 4 dated 25.07.2008. In
    such circumstances it is necessary to consider the relevant provisions
    of the 1894 Act, more particularly Section 41 thereof which pertains
    to the process required to be followed in cases of acquisition of land
    for companies. The relevant portion of Section 41 of the 1894 Act
    is reproduced below:
           “41. Agreement with appropriate Government. –
           If the appropriate Government is satisfied [after considering
           the report, if any, of the Collector under section 5A, sub-
           section (2), or on the report of the officer making an inquiry
           under section 40 that the proposed acquisition is for any
           of the purposes referred to in clause (a) or clause (aa)
           or clause (b) of sub-section (1) of section 40, it shall
           require the Company to enter into an agreement
           with the appropriate Government, providing to the
           satisfaction of the appropriate Government for the
           following matters, namely :-
           (1) the payment to the appropriate Government of the
           cost of the acquisition;
           (2) the transfer, on such payment, of the land to the
           Company….”
                                                [Emphasis supplied]
54. Section 41 necessitates an agreement between the appropriate
    government and the company for whose purpose the land is being
    acquired. One of the purposes of such an agreement is to ensure
    that payment towards the cost of acquisition is made by the company
    to the appropriate government and it is only upon such payment
    that the land is transferred to the company. Thus, it can be said that
    JAL was mandated to make the requisite payment to the State of
    Himachal Pradesh prior to the subject land being transferred to it.
55. However, as discussed in the foregoing paragraphs, even before
    the amount of compensation could be determined by way of a
    supplementary award as stipulated in the Award dated 08.06.2018,
    the subject land stood transferred to JAL. This, in our view, is in
    contravention of Section 38 of the 2013 Act and Section 41 of the
    1894 Act respectively.
472                                                        [2024] 9 S.C.R.

                          Digital Supreme Court Reports


56. Thus, we deem it appropriate to direct the Respondent Nos. 7 and
    10 that is, the State of Himachal Pradesh and the Land Acquisition
    Collector, Arki, to pay the amount of Rs. 3,05,31,095/- to the
    Respondent Nos. 1-6 for expeditious conclusion of the acquisition
    proceedings. However, we clarify that the State shall recover the
    said amount from JAL as the liability to pay the cost of acquisition
    of the subject land ultimately falls on JAL in view of the aforesaid
    discussion.
       VIII. CONCLUSION
57. For all the foregoing reasons, this appeal succeeds and is hereby
    allowed in the aforesaid terms. The impugned order dated 12.07.2022
    passed by the High Court is set aside.
58. The Respondent Nos. 7 and 10 are directed to pay the compensation
    amount of Rs. 3,05,31,095/- (Rupees Three Crore Five Lakh
    Thirty-One Thousand and Ninety-Five Only) along with 9% interest
    thereupon from the date of passing of the Supplementary Award i.e.,
    02.05.2022 till the date of realization, within a period of fifteen days
    from today. The total amount paid by the State shall be recovered
    from the Respondent No. 11 (JAL).

       Result of the Case: Appeal allowed.



       †
           Headnotes prepared by: Ankit Gyan


Search Indian case law

Ask in plain English, not just keywords. 25,000 AI words free, no card.

Try "Section 101"Sign in to search

For a digitally signed copy suitable for filing, refer to the court's own website. Only the court can issue one.

M/S ULTRA-TECH CEMENT LTD. versus MAST RAM & ORS. — 2024 INSC 709 - Legal Desk AI