Created byFuzzy Cloud

Supreme Court of India

MAHARASHTRA STATE ELECTRICITY DISTRIBUTION COMPANY LIMITEDversusADANI POWER MAHARASHTRA LIMITED AND ANOTHER

Citation
2023 INSC 399
Decided
20 April 2023
Disposal
Dismissed

Holding

The SHAKTI Policy constitutes a change in law under Clause 13.1.1 of the PPAs, and the APTEL’s order allowing APML’s relief is affirmed.

Summary

Maharashtra State Electricity Distribution Co. Ltd. (MSEDCL) and ADANI Power Maharashtra Ltd. (APML) entered into four long‑term power purchase agreements. APML claimed compensation for a "change in law" after the Ministry of Coal introduced the New Coal Distribution Policy 2013 and later the SHAKTI Policy, which altered the assured domestic coal supply. The Maharashtra Electricity Regulatory Commission (MERC) allowed relief, but the Appellate Tribunal for Electricity (APTEL) dismissed MSEDCL’s cross‑appeal and upheld APML’s claim. MSEDCL appealed to the Supreme Court, raising five issues including whether the SHAKTI Policy constitutes a change in law, the adequacy of notice, the method of computing compensation, the requirement of advance intimation, and the entitlement to carrying cost. The Court held that the SHAKTI Policy does amount to a change in law under Clause 13.1.1 of the PPAs, that the APTEL’s findings were not perverse or extraneous, and that the restitutionary principle applies. Consequently, the Supreme Court dismissed the appeals.

Issues considered

  • Whether the introduction of the SHAKTI Policy amounts to a change in law under the PPAs and whether APML gave the required notice of such change
  • Whether MERC was correct in limiting the domestic coal shortfall to a maximum of 25% of the assured coal quantity after the SHAKTI Policy
  • Whether the method of computing change‑in‑law compensation should be based on the lower of the bid‑submitted SHR/Auxiliary consumption or actual values, and the appropriate GCV of coal
  • Whether MERC was justified in directing APML to provide advance intimation of the impact on energy charge when using alternate coal for merit order dispatch
  • Whether MSEDCL is justified in contesting APML’s entitlement to carrying cost

Legislation cited

Subjects

electricitychange in lawpower purchase agreementSHAKTI Policycompensationtariffcarrying costrestitutionMERCAPTEL

Judgment

668                       [2023]
               SUPREME COURT     5 S.C.R. 668
                              REPORTS                       [2023] 5 S.C.R.


A        MAHARASHTRA STATE ELECTRICITY DISTRIBUTION
                    COMPANY LIMITED
                                       v.
       ADANI POWER MAHARASHTRA LIMITED AND ANOTHER
B                     (Civil Appeal Nos. 677-678 of 2021)
                                APRIL 20, 2023
                 [B. R. GAVAI AND VIKRAM NATH, JJ.]
             Electricity– Change in Law– SHAKTI Policy, if amounts to
      Change in Law –ADANI Power Maharashtra Limited (APML) and
C
      Maharashtra State Electricity Distribution Company Limited
      (MSEDCL) entered into four long term Power Project
      Agreements(PPAs)–APML filed petition seeking compensation in
      Tariff on account of Change in Law under the PPAs before
      Maharashtra Electricity Regulatory Commission (MERC) –Allowed–
D     Subsequently, APML filed a fresh petitionbefore MERC seeking
      reliefin support of Change of Law under the respective PPAs fornon-
      availability/short supply of domestic coal under SHAKTI Policy after
      March, 2017, which was allowed– Cross-appeals filed before APTEL
      – Appeal filed by MSEDCL was dismissed while that of APML was
      allowed –Held: If there is a Change in any consent, approval or
E
      licence available/obtained for the project, otherwise than for the
      default of theseller, which results in any change in any cost of the
      business of selling electricity, then the said seller will begoverned
      under Clause 13.1.1 of the PPA – Modification to NCDP 2007by
      the communication dtd. 31st July 2013amounts to Change in Law
F     and the generating companies are entitled to compensation on
      account of such Change in Law –SHAKTI Policy also reduces the
      ACQ as assured under the 2007 NCDP and thus,will also have to
      be held to be Change in Law –Further, the restitutionary principle
      will also be applicable on account of change occurring due to the
      introduction of SHAKTI Policy –View taken by APTEL is neither in
G
      ignorance of the mandatory statutory provisions nor based on
      extraneous consideration or ex-facie arbitrary/illegal – Thus, no
      interference warranted.
            Energy Watchdog v. Central Electricity Regulatory
            Commission and Others (2017) 14 SCC 80;
H
                                        668
   MAHARASHTRA STATE ELECTRICITY DISTRIBUTION CO. LTD. v.               669
            ADANI POWER MAHARASHTRA LTD.


       Maharashtra State Electricity Distribution Company               A
       Limited (MSEDCL) v. ADANI Power Maharashtra
       Limited (APML) and Others 2023 SCC OnLine 233;
       Jaipur Vidyut Vitaran Nigam Limited and Others v.
       ADANI Power Rajasthan Limited and Another 2020
       SCC OnLine SC 697; Uttar Haryana Bijli Vitran Nigam
                                                                        B
       Limited (UHBVNL) and another v. Adani Power Limited
       andOthers (2019) 5 SCC 325 : [2019] 4 SCR 487–
       relied on.
       MSEDCL v. GMR Warora Energy Ltd. and Others Civil
       Appeal No. 6927 of 2021; ADANI Power Limited v.
       Central Electricity Regulatory Commission 2018 SCC               C
       OnLine APTEL 5 – referred to.
                       Case Law Reference
[2019] 4 SCR 487               relied on              Para 32
      CIVIL APPELLATE JURISDICTION : Civil Appeal Nos.677-              D
678 of 2021.
      From the Judgment and Order dated 28.09.2020 of the Appellate
Tribunal for Electricity in Appeal Nos.116 and 155 of 2019.
      Gopal Jain, G. Umapathy, M. G. Ramachandran, Niranjan Reddy,
                                                                        E
Dr. A.M. Singhvi, Darius J. Khambata, Vikram Nankani, Sajan Poovayya,
Siddhartha Dave, Sr. Advs., Anup Jain, Udit Gupta, Ms. Prachi Gupta,
Vyom Chaturvedi for M/s. Udit Kishan and Associates, Ms. Poorva
Saigal, Shubham Arya, Nikunj Dayal, Ms. Pallavi Saigal, Ravi Nair,
Ms. Shikha Sood, Ms. Reeha Singh, Ms. Anumeha Smiti, Aneesh Bajaj,
Vishrov Mukherjee, Ms. Akhila Palem, Ms. Juhi Senguttuvan,              F
Pukhrambam Ramesh Kumar, Mahesh Agarwal, Amit Kapur, Ms.
Poonam Sengupta, Avishkar Singhvi, Arshit Anand, Saunak Rajguru,
Aman Sharma, Ms. Aparajita, Ms. Deepshikha Mishra, Ankitesh Ojha,
Karan Rukhana, E. C. Agrawala, Ms. Pallavi Sharma, Ms. Vidhi Thacker,
Advs. for the appearing parties.
                                                                        G
       The Judgment of the Court was delivered by
       B. R. GAVAI, J.
    1. The present appeals challenge the judgment and order dated
  th
28 September 2020 passed by the Appellate Tribunal for Electricity
                                                                        H
670               SUPREME COURT REPORTS                        [2023] 5 S.C.R.


A     (hereinafter referred to as ‘APTEL’), in cross appeals being Appeal
      No. 116 of 2019, filed by Maharashtra State Electricity Distribution
      Company Limited (hereinafter referred to as ‘MSEDCL’), the appellant
      herein, and Appeal No. 155 of 2019, filed by ADANI Power Maharashtra
      Limited (hereinafter referred to as ‘APML’), respondent No. 1 herein,
      thereby challenging the order dated 7th February 2019, passed by
B
      Maharashtra Electricity Regulatory Commission (hereinafter referred
      to as ‘MERC’).
               2. The facts, in brief, giving rise to the present appeals are as
      under:
C             APML and MSEDCL had entered into four long term Power
      Project Agreements (hereinafter referred to as ‘PPA’) dated (a) 8th
      September, 2008 for 1320 MW (hereinafter referred to as ‘1320 MW
      PPA’); (b) 31st March, 2010 for 1200 MW (hereinafter referred to as
      ‘1200 MW PPA’); (c) 9th August, 2010 for 120 MW (hereinafter referred
      to as ‘120 MW PPA’) and (d)16th February, 2013 for 440 MW (hereinafter
D     referred to as ‘440 MW PPA’), pursuant to the competitive bidding
      process conducted by MSEDCL.
             3. APML, being aggrieved by the Change in Law on account of
      the Ministry of Coal bringing into force the New Coal Distribution Policy,
      2013 (hereinafter referred to as ‘NCDP, 2013’), which revised the
E     arrangements prescribed under New Coal Distribution Policy, 2007
      (hereinafter referred to as ‘NCDP, 2007’) for supply of coal, had filed a
      petition being Case No. 189 of 2013, seeking compensation in Tariff on
      account of Change in Law under the PPAs before MERC. Finally, in
      the light of the judgment of this Court in the case of Energy Watchdog
F     v. Central Electricity Regulatory Commission and Others1, the said
      petition, after being remanded by the APTEL, was heard afresh by the
      MERC.
             4. Vide order dated 7th March, 2018, the MERC allowed the claims
      of APML on account of Change in Law due to changes brought about
G     by NCDP, 2013. APML, thereafter, preferred a review petition, being
      Review Petition No. 167 of 2018 seeking extension of Change in Law
      relief for domestic coal shortfall beyond March, 2017 on account of
      changes introduced by the Scheme for Harnessing and Allocating Koyala
      (Coal) Transparently in India (hereinafter referred to as ‘SHAKTI
      1
H         (2017) 14 SCC 80
   MAHARASHTRA STATE ELECTRICITY DISTRIBUTION CO. LTD. v.                   671
      ADANI POWER MAHARASHTRA LTD. [B. R. GAVAI, J. ]


Policy’) which had been released by the Ministry of Power on 22nd           A
May, 2017. As per Clause 6.1 of the SHAKTI Policy, the Appropriate
Commission was required to consider the cost of imported/market based
e-auction coal procured for making up the shortfall in the domestic coal
for pass-through.
        5. The MERC dismissed the said review petition. However, liberty    B
was granted to APML to file a fresh petition to seek extension of Change
in Law relief for domestic coal shortfall beyond March, 2017 in view of
the introduction of the SHAKTI Policy. Subsequently, APML filed a
fresh petition, being Case No. 290 of 2018, before the MERC seeking
relief in support of Change of Law under the respective PPAs for non-
availability/short supply of domestic coal under SHAKTI Policy after        C
March, 2017.
       6. The MERC, vide its order dated 7th February 2019, allowed the
petition and granted relief for Change in Law due to the promulgation of
SHAKTI Policy. However, the relief was directed to be computed on
the same methodology and parameters as approved by the MERC vide            D
its order dated 7th March, 2018. Cross appeals were filed before the
APTEL by APML and MSEDCL against the aforesaid order.
      7. The learned APTEL framed the following five issues for
adjudication :
                                                                            E
      “Issue No.1:-       Whether introduction SHAKTI Policy does
                          not amount to Change in Law under the PPAs
                          entered into between APML and MSEDCL
                          and whether APML has not provided notice
                          of such Change in Law to the Respondent
                          MSEDCL.                                           F
      Issue No.2:-        Whether the MERC is correct in holding that
                          for the purpose of Change in Law
                          compensation, shortfall in domestic coal shall
                          be limited to a maximum of 25% of ACQ after
                          the introduction of SHAKTI Policy.                G
      Issue No.3:-        (a) whether the MERC was correct in holding
                          that the SHR submitted by the Appellant in its
                          bid or SHR and Auxiliary Consumption norms
                          specified for new generating stations under the
                          MYT Regulations, 2011, whichever is superior      H
672           SUPREME COURT REPORTS                         [2023] 5 S.C.R.


A                             shall form the basis for computing Change in
                              Law compensation under the PPAs?
                              (b) Whether the MERC was correct in holding
                              that the reference GCV of domestic coal
                              supplied by CIL shall be the middle value of
B                             GCV range of assured coal grade in LoA/
                              PSA/MoU and not the GCV as received?
           Issue No.4:-       Whether the MERC was justified in directing
                              APML to provide advance intimation of impact
                              on energy charge by using alternate coal for
                              the purpose of Merit Order Despatch?
C
           Issue No.5:-       Whether the Respondent MSEDCL is justified
                              in contesting APML’s entitlement to Carrying
                              Cost.”
            8. The APTEL, vide judgment and order dated 28th September
D     2020, answered the issues as under:
           “15.1     Issue No.1:-We hold that the introduction of SHAKTI
                     POLICY amounts to change in law and all the
                     ingredients of change in law are:, duly met under the
                     respective PPAs. The impugned order is therefore
                     affirmed on this issue.
E
           15.2      Issue No.2:- We hold that findings in the impugned
                     order relating to the issue of restricting the quantum of
                     shortfall in domestic coal to a maximum of 25% are
                     against the basic principles of restitution I under the
                     change in law provisions of the PPAs.
F
           15.3      Issue No.3:- In line with our judgment dated 14.09.2020
                     in Appeal No.182 of 2019, we hold that the change in
                     law compensation shall be calculated based on the SHR
                     specified in the MERC MYT Regulations, 2011 or the
                     actual SHR whichever is lower and actual GCV of coal
G                    as received as the plant site.
           15.4      Issue No.4:- We find that the directions issued by the
                     State Commission regarding advance intimation
                     requirement is not consistent with normal Rules of MOD
                     preparation and also does not provide a level playing
H                    field for IPPs.
   MAHARASHTRA STATE ELECTRICITY DISTRIBUTION CO. LTD. v.                   673
      ADANI POWER MAHARASHTRA LTD. [B. R. GAVAI, J. ]


      15.5       Issue No.5:- We find that allowance of carrying cost       A
                 is a settled position of law and the State Commission
                 has already allowed the same to the Appellant, APML.”
      9. Consequently, the APTEL dismissed the appeal preferred by
MSEDCL and allowed the appeal preferred by APML. Hence, MSEDCL
has preferred the present appeals.                                          B
      10. We have heard Shri Gopal Jain, learned Senior Counsel
appearing on behalf of the appellant-MSEDCL and Dr. Abhishek Manu
Singhvi, learned Senior Counsel appearing on behalf of respondent No.
1–APML.
                                                                            C
       11. Shri Jain submitted that the SHAKTI Policy (Part-B) restores
the position as covered by NCDP 2007. He, therefore, submits that,
since under the SHAKTI Policy there is 100% assured coal supply, then
there is no question of APML being compensated on account of shortfall
in coal supply. He submits that SHAKTI Policy is in continuation of
NCDP 2007. However, this has not been taken into consideration by the       D
learned APTEL.
       12. Shri Jain further submits that both APTEL and MERC have
failed to take into consideration that APML had not complied with the
condition of serving a mandatory notice to MSEDCL for Change in Law
under Article 13.3.2 of the 1320 MW PPA.                                    E

      13. Dr. Singhvi, on the contrary, submits that undisputedly, SHAKTI
Policy would amount to Change in Law. He submits that there is a
concurrent finding of fact by both APTEL and MERC that SHAKTI
Policy is a Change in Law event.
                                                                            F
       14. Dr. Singhvi further submits that there is also a concurrent
finding by APTEL and MERC on the issue of mandatory notice. He
submits that unless these findings are found to be perverse or are based
on extraneous consideration, it will not be permissible for this Court to
interfere with the same.
                                                                            G
      15. When the batch of appeals was being heard, it was agreed
between all the parties that this Court should first decide Civil Appeal
No. 684 of 2021 (Maharashtra State Electricity Distribution Company
Limited (MSEDCL) v. ADANI Power Maharashtra Limited (APML)
                                                                            H
674                   SUPREME COURT REPORTS                      [2023] 5 S.C.R.


A     and Others2) and Civil Appeal No. 6927 of 2021 (MSEDCL v. GMR
      Warora Energy Ltd. and Others) inasmuch as three of the issues
      involved in all the appeals were common. It was submitted that those
      two appeals could be decided by deciding the three common issues.
      However, insofar as the other appeals are concerned, in addition to the
      three common issues, certain additional issues were also involved.
B
               16. The said three common issues are thus:
               (i)      Whether Change in Law relief on account of NCDP 2013
                        should be on ‘actuals’ viz. as against 100% of normative
                        coal requirement assured in terms of NCDP 2007 OR
C                       restricted to trigger levels in NCDP 2013 viz. 65%, 65%,
                        67% and 75% of Assured Coal Quantity (ACQ)?
               (ii)     Whether for computing Change in Law relief, the operating
                        parameters be considered on ‘actuals’ OR as per technical
                        information submitted in bid?
D              (iii)    Whether Change in Law relief compensation to be granted
                        from 1st April 2013 (start of Financial Year) or 31st July
                        2013 (date of NCDP 2013)?
            17. Vide the judgment and order dated 3rd March 2023 in the case
      of MSEDCL v. APML and Others (supra), this Court decided those
E     two appeals after considering the aforesaid three issues.
              18. The first issue was answered by this Court, holding that the
      Change in Law relief for domestic coal shortfall should be on ‘actuals’
      i.e. as against 100% of normative coal requirement assured in terms of
      NCDP, 2007. Insofar as the second issue is concerned, it was held that
F     the Station Heat Rate (SHR) and Auxiliary consumption should be
      considered as per the Regulations or actual, whichever is lower. The
      third issue was answered by holding that the Start date for the Change
      in Law event for the NCDP, 2013 is 1st April 2013.
            19. Insofar as Issue Nos. 2 and 3 as framed by the APTEL are
G     concerned, the same stand squarely covered by the judgment of this
      Court in the case of MSEDCL v. APML and Others (supra). The
      remaining three issues, which are required to be considered in the present
      appeals, are thus:
      2
          2023 SCC OnLine 233
H
   MAHARASHTRA STATE ELECTRICITY DISTRIBUTION CO. LTD. v.                        675
      ADANI POWER MAHARASHTRA LTD. [B. R. GAVAI, J. ]


       “Issue No.1:-        Whether introduction SHAKTI Policy does              A
                            not amount to Change in Law under the PPAs
                            entered into between APML and MSEDCL
                            and whether APML has not provided notice
                            of such Change in Law to the Respondent
                            MSEDCL.
                                                                                 B
       Issue No. 2:- .      ....
       Issue No. 3:-        …………
       Issue No. 4:-        Whether the MERC was justified in directing
                            APML to provide advance intimation of impact
                            on energy charge by using alternate coal for         C
                            the purpose of Merit Order Despatch?
       Issue No. 5:-        Whether the Respondent MSEDCL is justified
                            in contesting APML’s entitlement to Carrying
                            cost.”
                                                                                 D
      20. We will first consider the question as to whether the SHAKTI
Policy would amount to Change in Law.
       21. It will be apposite to refer to some relevant parts of the judgment
of this Court in the case of Energy Watchdog (supra), which read thus:
       “50. ……Even otherwise, from a reading of Clause 13, it is clear           E
       that Clause 13.1.1 is in four different parts. The first part speaks
       of enacted laws; the second speaks of interpretation of such laws
       by courts or other instrumentalities; the third speaks of changes in
       consents, approvals or licences which result in change in cost of
       the business of selling electricity; and the fourth refers to any
                                                                                 F
       change in the declared law of the land for the project, cost of
       implementation of resettlement and rehabilitation or cost of
       implementing the environmental management plan. “Competent
       court” in Clause 13.1.2 is defined as meaning only the judicial
       system of India.
       ……                                                                        G

       56. However, insofar as the applicability of Clause 13 to a change
       in Indian law is concerned, the respondents are on firm ground. It
       will be seen that under Clause 13.1.1 if there is a change in any
       consent, approval or licence available or obtained for the project,
                                                                                 H
676              SUPREME COURT REPORTS                            [2023] 5 S.C.R.


A             otherwise than for the default of the seller, which results in any
              change in any cost of the business of selling electricity, then the
              said seller will be governed under Clause 13.1.1. It is clear from a
              reading of the Resolution dated 21-6-2013, which resulted in the
              letter of 31-7-2013, issued by the Ministry of Power, that the earlier
              coal distribution policy contained in the letter dated 18-3-2007
B
              stands modified as the Government has now approved a revised
              arrangement for supply of coal. It has been decided that, seeing
              the overall domestic availability and the likely requirement of power
              projects, the power projects will only be entitled to a certain
              percentage of what was earlier allowable……”
C            22. It can thus be seen that this Court has held that if there is a
      Change in any consent, approval or licence available or obtained for the
      project, otherwise than for the default of the seller, which results in any
      change in any cost of the business of selling electricity, then the said
      seller will be governed under Clause 13.1.1 of the PPA. As already
D     discussed hereinabove, this Court has consistently held that modification
      to NCDP 2007 by the communication dated 31st July 2013 would amount
      to Change in Law and the generating companies would be entitled to
      compensation on account of such Change in Law. Undisputedly, SHAKTI
      Policy also reduces the ACQ as was assured under the 2007 NCDP.
      Consequently, SHAKTI Policy will also have to be held to be Change in
E     Law.
            23. A three-Judges Bench of this Court in the case of Jaipur
      Vidyut Vitaran Nigam Limited and Others v. ADANI Power
      Rajasthan Limited and Another3, has also considered the effect of
      SHAKTI Policy and held that the seller would be entitled to the benefit
F     occurring on account of SHAKTI Policy. As such, the contention that
      SHAKTI Policy does not amount to Change in Law is without substance.
            24. Following the judgments in the case of Energy Watchdog
      (supra) and ADANI Power Rajasthan Limited (supra), this Court, in
      the case of MSEDCL v. APML and Others (supra),observed thus:
G
              “130. The MoP, thereafter, addressed a communication dated
              31st July 2013 to the Secretary, CERC specifically pointing out
              the decision of the CCEA to the effect that the higher cost of
              imported coal was to be considered for pass-through as per the
      3
          2020 SCC OnLine SC 697
H
MAHARASHTRA STATE ELECTRICITY DISTRIBUTION CO. LTD. v.                   677
   ADANI POWER MAHARASHTRA LTD. [B. R. GAVAI, J. ]


  modalities suggested by CERC. The communication states that,           A
  as per the decision of the Government, the higher cost of import/
  market based e-auction coal will have to be considered for being
  made a pass-through on a case to case basis by CERC/SERC to
  the extent of shortfall in the quantity indicated in the LoA/FSA.
  131. The Tariff Policy dated 28th January 2016 issued by the MoP       B
  in paragraph 6.1 also specifically notes this position and states
  that, in case of reduced quantity of domestic coal supplied by CIL
  vis-à-vis the assured quantity or quantity indicated in LoA/FSA,
  the cost of imported/market based e-auction coal procured for
  making up the shortfall shall be considered for being made a pass-
  through by the Appropriate Commission.                                 C

  132. Undisputedly, in the case of Energy Watchdog (supra) as
  well as in Adani Rajasthan case (supra) this Court has held that
  on account of the Change in Law, the generating companies were
  entitled to compensation so as to restore the party to the same
  economic position as if such Change in Law had not occurred.           D
  Had the Change in Law not occurred, the generating companies
  would have been entitled to the supply as assured by the CIL/
  Coal Companies under the FSA.
  133. It is contended by the DISCOMS that in the case of Energy
  Watchdog (supra), this Court has specifically held that the doctrine   E
  of force majeure was not applicable if there was an unexpected
  rise in the price of coal and, as such, it will not absolve the
  generating companies from performing their part of the contract.
  It is submitted that when the bidders submitted their bids, this was
  a risk they knowingly took. We find the said submission to be          F
  without substance. The generators are not claiming compensation
  on the basis of rise in price of coal or on the ground of force
  majeure. Their claims, in fact, are on the basis of the Change in
  Law, which this Court, in the case of Energy Watchdog (supra)
  as well as in Adani Rajasthan case (supra), has upheld on the
  ground of Change in Law.                                               G
  134. The contention of the DISCOMS that the Adani Rajasthan
  case (supra) is not applicable to the facts of the present case
  inasmuch as in Adani Rajasthan case (supra), the State of
  Rajasthan had assured 100% coal supply and that it was not a
                                                                         H
678             SUPREME COURT REPORTS                            [2023] 5 S.C.R.


A            case of FSA, is, in our considered view, without substance. In the
             present case also, the NCDP 2007 had assured 100% fuel/coal
             supply of the normative value.
             135. The restitutionary principle has been stated by this Court in
             the case of Uttar Haryana Bijli Vitran Nigam Limited
B            (UHBVNL) (supra) thus:
                “10. Article 13.2 is an in-built restitutionary principle which
                compensates the party affected by such change in law and
                which must restore, through monthly tariff payments, the
                affected party to the same economic position as if such change
C               in law has not occurred. This would mean that by this clause a
                fiction is created, and the party has to be put in the same
                economic position as if such change in law has not occurred
                i.e. the party must be given the benefit of restitution as
                understood in civil law. ………….””

D            25. As such the restitution principle, as has been consistently applied
      by this Court on account of Change in Law, will also be applicable on
      account of change occurring due to the introduction of SHAKTI Policy.
            26. The contention of the appellant that the SHAKTI Policy brings
      back the position of NCDP 2007 and assures 100% coal supply, is not
E     factually correct. A perusal of the SHAKTI Policy would reveal that
      SHAKTI Policy assures 70% of ACQ as against 100% in 2007 NCDP.
          27. In that view of the matter, we find that the contention that
      SHAKTI Policy restores the position of 2007 NCDP is factually incorrect.
              28. Insofar as Change in Law Notice is concerned, the APTEL,
F     in its judgment and order, observed thus:
             “13.7 We have considered the submissions made by APML vis-
             a-vis the findings in the impugned order. It is relevant to note that
             no submission to the contrary has been advanced by the
             Respondent, MSEDCL on this issue. In the Impugned Order,
G            MERC appears to have expanded the intent of Change in Law
             notice as a means of intimation to the buyer of power that on
             account of intended use of alternate coal, the cost of power is
             likely to increase and then the distribution licensee may decide to
             not schedule such costly power. Firstly, no such intent can be
             deciphered from the provisions of the PPA which require a change
H
      MAHARASHTRA STATE ELECTRICITY DISTRIBUTION CO. LTD. v.                     679
         ADANI POWER MAHARASHTRA LTD. [B. R. GAVAI, J. ]


         in law notice to be given to the procurers. MERC has not                A
         deliberated upon how this regime will impact the implementation
         of change in law provision in other scenarios. For example, if
         there is a change in rates of taxes or duties, which entitles the
         generator to seek change in law relief, can it still be said that the
         procurer should be intimated about the impact of such changes in
                                                                                 B
         taxes or duties to enable them to decide whether to schedule power
         or not. In our view, this does not appear to be the intent of change
         in law notice to the procurers under the PPAs. This is for the
         simple reason that whether there will be impact on MSEDCL
         would be known only after MERC decides the change in law
         claim. Until such time notice given by sellers merely to intimate       C
         the occurrence of change in law event, in our view, will not
         influence decisions related to scheduling of power on merit order
         principles. In any event in far as preparation of MOD stack is
         concerned, the normal practice is to prepare MOD on the basis
         of the energy charge bill of (n-1)th or (n-2)th month is taken into
                                                                                 D
         account in the order of precedence. Therefore, the impact of a
         regular or consistent usage of alternate coal will in anyway be
         reflected in the MOD stack, albeit with the lag of one or two
         months.”
       29. The aforesaid finding of APTEL cannot be said to be perverse
or based on extraneous consideration or in contravention of any of the           E
statutory provisions.
         30. That leaves us with the issue with regard to Carrying Cost.
       31. In the case of ADANI Power Limited v. Central Electricity
Regulatory Commission4, the CERC had come to a conclusion that                   F
there was no provision in the PPA for payment of Carrying Cost for the
period from the date of the Change in Law event till the date of approval
by the Commission. As such, the Commission had rejected the prayer of
the generating company to grant carrying Cost on restitutionary principles
from the date of Change in Law till the date of decision. The APTEL,
while reversing the judgment of the CERC and allowing the Carrying               G
Cost, had observed thus:
         “29. To our mind such adjustment in the tariff is nothing less then
         re-determination of the existing tariff.
4
    2018 SCC OnLine APTEL 5                                                      H
680                SUPREME COURT REPORTS                             [2023] 5 S.C.R.


A                  x. Further, the provisions of Article 13.2 i.e. restoring the
                   Appellant to the same economic position as if Change in Law
                   has not occurred is in consonance with the principle of
                   ‘restitution’ i.e. restoration of some specific thing to its rightful
                   status. Hence, in view of the provisions of the PPA, the
                   principle of restitution and judgement of the Hon’ble Supreme
B
                   Court in case of Indian Council for Enviro-Legal
                   Action v. Union of India, we are of the considered opinion
                   that the Appellant is eligible for Carrying Cost arising out of
                   approval of the Change in Law events from the effective date
                   of Change in Law till the approval of the said event by
C                  appropriate authority. It is also observed that the Gujarat Bid-
                   01 PPA have no provision for restoration to the same economic
                   position as if Change in Law has not occurred. Accordingly,
                   this decision of allowing Carrying Cost will not be applicable to
                   the Gujarat Bid-01 PPA.”
D           32. The same came to be challenged before this Court in the case
      of Uttar Haryana Bijli Vitran Nigam Limited (UHBVNL) and
      another v. Adani Power Limited and Others5. The court rejected the
      same and upheld the order of APTEL. As such, the contention in this
      regard needs to be rejected.
E            33. This Court, in the case of MSEDCL v. APML and
      Others(supra), after considering the relevant provisions under the
      Electricity Act, 2003 with regard to appointment, qualifications and
      Members of the CEA, CERC and the learned APTEL, held that these
      bodies are bodies consisting of experts in the field. After considering
      various judgments on the issue, this Court observed thus:
F
               “123. Recently, the Constitution Bench of this Court in the case
               of Vivek Narayan Sharma v. Union of India has held that the
               Courts should be slow in interfering with the decisions taken by
               the experts in the field and unless it is found that the expert bodies
               have failed to take into consideration the mandatory statutory
G              provisions or the decisions taken are based on extraneous
               considerations or they are ex facie arbitrary and illegal, it will not
               be appropriate for this Court to substitute its views with that of
               the expert bodies.”
      5
          (2019) 5 SCC 325
H
   MAHARASHTRA STATE ELECTRICITY DISTRIBUTION CO. LTD. v.                        681
      ADANI POWER MAHARASHTRA LTD. [B. R. GAVAI, J. ]


       34. In our view, the view taken by the APTEL cannot be said to            A
be a view taken in ignorance of the mandatory statutory provisions nor
can it be said that it is based on extraneous considerations. The view
also cannot be said to be ex-facie arbitrary or illegal. As such, in our
view, no interference would be warranted in the present appeals.
       35. In the result, the appeals are dismissed. Pending application(s),     B
if any, shall stand disposed of. No costs.

Divya Pandey                                                Appeals dismissed.
(Assisted by : Shevali Monga, LCRA)

                                                                                 C




                                                                                 D




                                                                                 E




                                                                                 F




                                                                                 G




                                                                                 H


Search Indian case law

Ask in plain English, not just keywords. 25,000 AI words free, no card.

Try "electricity"Sign in to search

For a digitally signed copy suitable for filing, refer to the court's own website. Only the court can issue one.