Created byFuzzy Cloud

Supreme Court of India

MAHARASHTRA STATE ELECTRICITY DISTRIBUTION COMPANY LIMITEDversusADANI POWER MAHARASHTRA LIMITED & ORS.

Citation
2023 INSC 208
Decided
3 March 2023
Disposal
Dismissed

Holding

The Court held that under the Change in Law clause, generators are entitled to compensation calculated on the basis of actual or regulatory parameters (whichever is lower) for SHR and on an ‘as‑received’ basis for GCV, to restore them to the economic position as if the NCDP 2007 had not been altered, and dismissed the appeals.

Summary

Maharashtra State Electricity Distribution Company Ltd (MSEDCL) entered long‑term power purchase agreements (PPAs) with Adani Power Maharashtra Ltd (APML) and other generators, relying on the New Coal Distribution Policy (NCDP) 2007 which assured 100% domestic coal supply. The 2013 amendment to the NCDP reduced the guaranteed domestic coal to 65‑75% of the annual contracted quantity, causing a shortfall that the generators claimed as a ‘Change in Law’ under Article 10 of the PPAs. MSEDCL argued that the generators should bear the risk and that compensation should be based on bid parameters such as the station heat rate (SHR) and gross calorific value (GCV) quoted in the bids. Expert bodies (CERC, MERC, APTEL) held that compensation must be calculated on actual or regulatory parameters (whichever is lower) and that GCV should be measured on an ‘as‑received’ basis. The Supreme Court, relying on the principles of restitution articulated in Energy Watchdog, Adani Rajasthan and UHBVNL, affirmed that the generators are entitled to compensation that restores them to the position as if the NCDP 2007 had not been altered, and dismissed the appeals.

Issues considered

  • The appropriate basis for calculating Change in Law compensation – whether bid‑quoted SHR and GCV or actual/regulatory parameters should be used.
  • Whether the shortfall in domestic coal should be assessed by taking the maximum of actual quantum offered by CIL and the minimum assured quantum under NCDP 2013.
  • Whether the amendment of NCDP 2007 by NCDP 2013 constitutes a ‘Change in Law’ triggering compensation under the PPAs.
  • Whether courts should intervene in the determinations made by expert regulatory bodies such as CERC, MERC and APTEL.
  • Whether the late‑payment surcharge under Articles 8.3.5 and 8.8.3 of the PPAs is payable.

Legislation cited

Subjects

Power Purchase AgreementChange in LawCoal Supply ShortfallCompensationElectricity RegulationTariffStation Heat RateGross Calorific ValueRestitutionExpert Regulatory Bodies

Judgment

                         [2023] 8 S.C.R. 85                             85


   MAHARASHTRA STATE ELECTRICITY DISTRIBUTION                           A
              COMPANY LIMITED
                                 v.
     ADANI POWER MAHARASHTRA LIMITED & ORS.
                   (Civil Appeal No. 684 of 2021)                       B
                         MARCH 03, 2023
           [B. R. GAVAI AND VIKRAM NATH, JJ.]
       Power – Long-term Power Purchase Agreements (PPAs) –
Supply of coal to power producers – Change of New Coal
                                                                        C
Distributional Policy, 2007 (NCDP, 2007) by New Coal
Distributional Policy, 2013 (NCDP 2013) – Claim for ‘Change in
Law’ relief compensation – Operating parameters – Held: In the
Energy Watchdog case as well as in Adani Rajasthan case, the
Supreme Court held that on account of the Change in Law, the
generating companies were entitled to compensation so as to restore     D
the party to the same economic position as if such Change in Law
had not occurred – Had the Change in Law not occurred, the
generating companies would have been entitled to the supply as
assured by the Coal India Ltd. (CIL)/Coal Companies under the
Fuel Supply Agreement (FSA) – The submission that when the bidders
                                                                        E
submitted their bids, this was a risk they knowingly took, is without
substance – The generators are not claiming compensation on the
basis of rise in price of coal or on the ground of force majeure –
Their claims, in fact, are on the basis of the Change in Law, which
this Court, in the case of Energy Watchdog as well as in Adani
Rajasthan case, has upheld on the ground of Change in Law – The         F
contention of the Distribution companies (DISCOMS) that the Adani
Rajasthan case is not applicable to the facts of the present case
inasmuch as in Adani Rajasthan case, the State of Rajasthan had
assured 100% coal supply and that it was not a case of FSA, is
without substance – In the present case also, the NCDP 2007 had
                                                                        G
assured 100% fuel/coal supply of the normative value – The
restitutionary principle has been stated by this Court in the case of
Uttar Haryana Bijli Vitran Nigam Limited (UHBVNL) – Undisputedly,
the claim of respondent no.1-APML stands on the basis of the Change
in Law – The DISCOMS, which are instrumentalities of the State,
cannot be expected to argue contrary to the stand of the Government,    H
                                 85
86            SUPREME COURT REPORTS                       [2023] 8 S.C.R.


A    which clearly provides that the generators would be entitled to pass-
     through for the coal required to be imported or purchased from the
     open market on the ground of Change in Law – The stand taken by
     the DISCOMS that, since the loss being sustained by the generating
     companies is on account of non-fulfillment of obligation by CIL/
     Coal Companies, they should be relegated to the remedy available
B    to them in law against the CIL/Coal Companies, is totally
     unreasonable – The claim is based on change of NCDP 2007 by
     NCDP 2013, which, undisputedly, is covered by the term ‘Change
     in Law’ – Compensation – ‘Change in law’ compensation.
           Judicial Review – Of decision taken by expert bodies – Central
C    Electricity Authority (CEA), Central Electricity Regulatory
     Commission (CERC) and Appellate Tribunal for Electricity (APTEL)
     –Held: – These bodies are bodies consisting of experts in the field
     – Courts should be slow in interfering with the decisions taken by
     the experts in the field and unless it is found that the expert bodies
D    have failed to take into consideration the mandatory statutory
     provisions or the decisions taken are based on extraneous
     considerations or they are ex facie arbitrary and illegal, it will not
     be appropriate for the Court to substitute its views with that of the
     expert bodies.
            Electricity Act, 2003 – Purpose and Object – One of the major
E
     reasons for the enactment of the Electricity Act was the deterioration
     in performance of the State Electricity Boards – It is seen that in a
     number of matters, concurrent orders passed by the Regulatory Body
     and the Appellate Forum are assailed – Such litigation would, in
     fact, efface the purpose of the Electricity Act.
F          Vivek Narayan Sharma v. Union of India 2023 SCC
           OnLine SC 1 – followed.
           Energy Watchdog v. Central Electricity Regulatory
           Commission and others (2017) 14 SCC 80 and Jaipur
           Vidyut Vitaran Nigam Ltd. and others v. Adani Power
G          Rajasthan Limited and another 2020 SCC Online SC
           697 – relied on.
           Uttar Haryana Bijli Vitran Nigam Limited (UHBVNL)
           and another v. Adani Power Limited and others (2019)
           5 SCC 325 : [2019] 4 SCR 487; Reliance Infrastructure
H          Limited v. State of Maharashtra and others (2019) 3
MAHARASHTRA STATE ELECTRICITY DISTRIBUTION CO. LTD. v.                   87
         ADANI POWER MAHARASHTRA LTD.

        SCC 352: [2019] 1 SCR 886; Central Warehousing                   A
        Corporation v. Adani Ports Special Economic Zone
        Limited (APSEZL) and others 2022 SCC OnLine SC
        1398;Maharashtra State Electricity Distribution
        Company Limited v. Maharashtra Electricity Regulatory
        Commission and others (2022) 4 SCC 657; Tamil Nadu
                                                                         B
        Generation & Distribution Corporation Limited v. PPN
        Power Generating Company Private Limited (2014) 11
        SCC 53 : [2014] 4 SCR 667 and Nabha Power Limited
        (NPL) v. Punjab State Power Corporation Limited
        (PSPCL) and another (2018) 11 SCC 508: [2017] 14
        SCR 301 – referred to.                                           C
                        Case Law Reference
(2017) 14 SCC 80                 relied on        Para 22
[2017] 14 SCR 301                referred to      Para 43 (xxvi)
[2019] 4 SCR 487                 referred to      Para 44 (xviii)        D
(2022) 4 SCC 657                 referred to      Para 45 (ix)
[2014] 4 SCR 667                 referred to      Para 45 (ix)
[2019] 1 SCR 886                 referred to      Para 121
        CIVIL APPELLATE JURISDICTION : Civil Appeal No.684 of            E
2021.
      From the Judgment and Order dated 14.09.2020 of the Appellate
Tribunal for Electricity in Appeal No.182 of 2019.
        With                                                             F
        Civil Appeal No.6927 of 2021.
      Balbir Singh, A.S.G., Gopal Jain, G. Umapathy, M. G.
Ramachandran, Dr. A. M. Singhvi, Darius Khambata, Sajan Poovayya,
Siddhartha Dave, S. B. Upadhyay, Sr. Advs., Anup Jain, Udit Gupta for
M/s. Udit Kishan and Associates, G. Sai Kumar, Samir Malik, Ms. Ekssha   G
for M/s. D.S.K. Legal, Anand K. Ganesan, Nikunj Dayal, Ms. Poorva
Saigal, Amal Nair, Shubham Arya, Ms. Kriti Soni, Ms. Ritu Apurva, Ms.
Pallavi Saigal, Ms. Ritu Apurv, Ravi Nair, Ms. Shikha Sood, Ms. Reeha
Singh, Ms. Anumeha Smiti, Aneesh Bajaj, Navin Prakash, Ms. Anushree
Bardhan, Ms. Srishti Khindaria, Vishrov Mukherjee, Pukhrambam
                                                                         H
88                SUPREME COURT REPORTS                              [2023] 8 S.C.R.


A    Ramesh Kumar, Girik Bhalla, Yasashwi Kant, Mrs. Priyanka Vyas,
     Mahesh Agarwal, Amit Kapur, Ms. Geetika Sharma, Ms. Poonam
     Sengupta, Ms. Sakshi Kapoor, Avishkar Singhvi, Arshit Anand, Saunak
     Rajguru, Aman Sharma, Ms. Deepsika Mishra, Ankitesh Ojha, Karan
     Rukhana, E. C. Agrawala, Ms. Pallavi Sharma, Vaibhav Kalra, Nishant
     Kumar, Ms. Anisha Upadhyay, Advs. for the appearing parties.
B
            The Judgment of the Court was delivered by
            B. R. GAVAI, J.
                                           INDEX*
            I.      INTRODUCTION………………………..Paras 1 and 2
C
            II.     FACTS IN CIVIL APPEAL NO.684 OF
                    2021……..................................................Paras 3 to 29
            III.    FACTS IN CIVIL APPEAL NO.6927 OF
                    2021………….........................................Paras 30 to 39
D           IV.     SUBMISSIONS ON BEHALF OF THE
                    DISCOMS ……….......................................... Paras 43
            V.      SUBMISSIONS ON BEHALF OF THE
                    GENERATING COMPANIES ……......Paras 44 and 45
E           V.      RELEVANT DOCUMENTS………….... Paras 46 to 83
            VI.     JUDGMENTS CITED…………………...Paras 84 to 93
            VII. STATUTORY PROVISIONS WITH REGARD TO
                 REGULATORY MECHANISM………..Paras 94 to 104

F           VIII. CONSIDERATIONS…………………Para 105 onwards
                                List of abbreviations:
            1.      ACQ                -      Annual Contracted Quantity
            2.      APML               -      Adani Power Maharashtra
                                              Limited
G
            3.      APTEL              -      Appellate Tribunal for
                                              Electricity
            4.      C&AG               -      Comptroller and Auditor
                                              General of India
H    *Ed Note : Pagination in the Index is as per the original judgment.
MAHARASHTRA STATE ELECTRICITY DISTRIBUTION CO. LTD. v.      89
    ADANI POWER MAHARASHTRA LTD. [B. R. GAVAI, J.]

    5.    CCEA        -    Cabinet Committee on             A
                           Economic Affairs
    6.    CERC        -    Central Electricity Regulatory
                           Commission
    7.    CIL         -    Coal India Limited
                                                            B
    8.    CPP         -    Captive Power Plants
    9.    DISCOMS     -    Distribution Companies
    10.   FSA         -    Fuel Supply Agreement
    11.   GCV         -    Gross Calorific Value
    12.   GMR         -    GMR Warora Energy Ltd.           C
    13.   GMRETL-          GMR Energy Trading Limited
    14.   IPPs        -    Independent Power Producers
    15.   LoA         -    Letter of Assurance
    16.   MERC        -    Maharashtra Electricity          D
                           Regulatory Commission
    17.   MoC         -    Ministry of Coal
    18.   MoP         -    Ministry of Power
    19.   MSEDCL      -    Maharashtra State Electricity
                                                            E
                           Distribution Company Limited
    20.   NCDP        -    New Coal Distributional Policy
    21.   PLF         -    Plant Load Factor
    22.   PPAs        -    Power Purchase Agreements
    23.   PSA         -    Power Sale Agreement             F
    24.   RFP         -    Request for Proposal
    25.   SECL        -    South Eastern Coal Limited
    26.   SHR         -    Station Heat Rate
    27.   TPPs        -    Thermal Power Stations           G
    28.   UHBVNL      -    Uttar Haryana Bijli Vitran
                           Nigam Limited
    29.   WCL         -    Western Coal Limited

                                                            H
90             SUPREME COURT REPORTS                           [2023] 8 S.C.R.


A          INTRODUCTION
           1. The questions involved in both these appeals, as in several other
     appeals, are common.
           2. Three of the issues involved in the present appeals are also
     involved in the other appeals which were listed along with these two
B
     appeals. However, the other appeals also involve some other ancillary
     and incidental issues. As such, at the request of the learned counsel for
     the parties, we have heard the present appeals. We have also heard the
     learned counsel appearing in the other appeals on the three questions
     which are common.
C
           FACTS IN CIVIL APPEAL NO. 684 OF 2021
            3. The facts, in brief, which arise in Civil Appeal No.684 of 2021
     are thus:
            4. The appellant-Maharashtra State Electricity Distribution
D    Company Limited (hereinafter referred to as “MSEDCL”) has entered
     into a long-term Power Purchase Agreements (“PPAs” for short) with
     Adani Power Maharashtra Limited (hereinafter referred to as “APML”).
     The first of the PPAs is dated 8th September 2008 for 1320 MW (“1320
     MW PPA” for short); the second one is dated 31st March 2010 for 1200
     MW (“1200 MW PPA” for short); the third one is dated 9th August 2010
E    for 125 MW (“125 MW PPA” for short); and the fourth one is dated
     16th February 2013 for 440 MW (“440 MW PPA” for short). These
     PPAs were entered into in pursuance of the competitive bidding
     processes conducted by the appellant-MSEDCL under Section 63 of
     the Electricity Act, 2003 (hereinafter referred to as “the Electricity Act”)
F    read with the Standard Bidding Guidelines issued by the Ministry of
     Power (“MoP” for short).
            5. Article 10 of the 1200 MW PPA dated 31st March 2010 entered
     into between the appellant-MSEDCL and respondent No.1-APML deals
     with “Change in Law”.
G           6. Article 10.1.2 defines the term “Change in Law”.
            7. Article 10.2 deals with the application and principles for
     computing the impact of Change in Law. Article 10.2.1 provides that
     while determining the consequence of a Change in Law under Article
     10, due regard has to be given to the principle, that to compensate the
H
MAHARASHTRA STATE ELECTRICITY DISTRIBUTION CO. LTD. v.                         91
    ADANI POWER MAHARASHTRA LTD. [B. R. GAVAI, J.]

Party affected by such Change in Law is to restore through monthly             A
Tariff Payment, to the extent contemplated in Article 10, the affected
Party to the same economic position as if such Change in Law has not
occurred.
       8. Article 10.3 deals with “Relief for Change in Law”. Article
10.3.1 provides relief for Change in Law during the Construction Period,       B
whereas Article 10.3.2 provides for compensation to be paid on account
of Change in Law during Operating Period. For claiming relief on account
of a Change in Law, the Party is required to approach the Appropriate
Commission along with documentary proof of such increase/decrease
in the cost of the Power Station or revenue/expense for establishing the
impact of such Change in Law. Article 10.3.4 provides finality to the          C
decision of the Appropriate Commission with regard to compensation
determined under Articles 10.3.1 and 10.3.2.
       9. On 18th October 2007, the Government of India, through the
Ministry of Coal (“MoC” for short), issued the New Coal Distributional
Policy, 2007 (hereinafter referred to as “the NCDP, 2007”). As per the         D
NCDP 2007, 100% of the quantity as per the normative requirement of
the consumers was to be considered for the supply of coal, through Fuel
Supply Agreement (“FSA” for short) by Coal India Limited (“CIL” for
short) at fixed prices to be declared/notified by CIL. The NCDP, 2007
also provided that to meet the domestic requirement of coal, CIL may
                                                                               E
have to import coal as may be required from time to time, if feasible.
CIL was to adjust its overall price accordingly. It further provided that it
was the responsibility of CIL/Coal Companies to meet the full
requirement of coal under FSAs even by resorting to imports, if necessary.
      10. It is not in dispute that in accordance with the NCDP, 2007,
APML had applied for coal linkage to MoC. It is also not in dispute that       F
Western Coal Limited (“WCL” for short) and South Eastern Coal Limited
(“SECL” for short) issued two Letters of Assurance (LoAs) in favour
of APML and assured supply of coal.
      11. Undisputedly, FSA was executed between APML and WCL
for domestic coal linkage. Subsequently, the FSA was amended and the           G
quantum of coal assured by WCL was transferred to SECL.
      12. It is also not in dispute that subsequently, on 21st June 2013,
the Cabinet Committee on Economic Affairs (“CCEA” for short), in
view of the persistent shortage of domestic coal, approved a revised
mechanism for coal supply to power producers.                                  H
92             SUPREME COURT REPORTS                           [2023] 8 S.C.R.


A            13. Thereafter, the Government of India, through the Ministry of
     Coal, issued Office Memorandum dated 26th July 2013 (hereinafter
     referred to as “NCDP 2013”), thereby approving a revised arrangement
     for the supply of coal to the identified Thermal Power Stations (“TPPs”
     for short). The said Office Memorandum provided that FSAs will be
     signed for the domestic coal quantity of 65%, 65%, 67%, and 75% of
B
     Annual Contracted Quantity (“ACQ” for short) for the remaining four
     years of the 12th Plan for the power plants having normal coal linkages.
     It further provided that to meet the balance FSA obligations towards the
     requirement of the said 78,000 MW TPPs, CIL may import coal and
     supply the same to the willing power plants on a cost-plus basis. It further
C    provided that the power plants may also directly import coal themselves,
     if they so opt, in which case, the FSA obligations on the part of CIL to
     the extent of import component would be deemed to have been
     discharged.
            14. On 31st July 2013, the MoP issued a letter to the Central
D    Electricity Regulatory Commission (“CERC” for short) and State
     Electricity Regulatory Commissions to consider as pass-through in tariff
     the cost of alternate coal (procured to meet the shortfall in supply of
     domestic linkage coal) on a case to case basis.
           15. Contending that on account of the Change in Law, APML
E    was entitled to compensation, APML filed a Petition bearing Case No.189
     of 2013 on 17th December 2013 before the Maharashtra Electricity
     Regulatory Commission (“MERC” for short).
            16. MERC, vide order dated 15th July 2014, disposed the said
     Petition (i.e. Case No. 189 of 2013) by approving a framework for
F    determination of compensatory fuel charge, in view of the CCEA decision
     of 21st June 2013 and the MoP’s advice dated 31st July 2013.
           17. In compliance with the MERC’s order dated 15th July 2014,
     APML filed another Petition before the MERC bearing Case No. 140
     of 2014 on 23rd July 2014, inter alia, for approving a mechanism for the
G    determination of compensatory tariff.
           18. The MERC, vide its order dated 20th August 2014, formulated
     a mechanism for the pass-through in tariff of the compensatory fuel
     charge that had been allowed in Case No.189 of 2013.
           19. Subsequently, APML filed a Review Petition before the MERC
H    bearing Case No.159 of 2014. The same was disallowed by the MERC
MAHARASHTRA STATE ELECTRICITY DISTRIBUTION CO. LTD. v.                        93
    ADANI POWER MAHARASHTRA LTD. [B. R. GAVAI, J.]

as being devoid of merits except on the issue of the effectiveness of the     A
compensatory fuel charge.
       20. On 28th January 2016, the MoP issued the revised Tariff Policy.
As per clause 6.1 of the revised Tariff Policy, the Appropriate Commission
was required to consider the cost of imported/market-based e-auction
coal procured for making up the shortfall in the domestic coal for pass-      B
through in tariff of competitively bid projects.
      21. Thereafter, on 9th March 2016, APML filed appeals before
the Appellate Tribunal for Electricity (hereinafter referred to as
“APTEL”), being Appeal Nos. 129 of 2016 and 130 of 2016, challenging
the orders passed by the MERC in Case Nos.189 of 2013 and 140 of              C
2014. MSEDCL too filed cross-appeals against the MERC orders being
Appeal Nos. 187 and 188 of 2016.
      22. On 4th May 2017, the learned APTEL remanded the issues
raised in the cross-appeals filed by APML and MSEDCL for fresh
consideration by the MERC in the light of the judgment of this Court in       D
the case of Energy Watchdog v. Central Electricity Regulatory
Commission and others1 which was decided on 11th April 2017.
        23. By order dated 7th March 2018, the MERC decided Case
No.189 of 2013 and 140 of 2014, wherein, while allowing the claims of
APML for relief on account of a Change in Law for 1180 MW capacity,           E
it restricted it to the extent of the minimum supply obligations specified
for the CIL subsidiaries for the last four years of the 12th Five Year Plan
period i.e. Financial Year 2013-14 to Financial Year 2016-17 as per the
NCDP, 2013. It further held that the alternate coal quantity for meeting
the domestic coal shortfall shall be computed based on the Station Heat
Rate (“SHR” for short) mentioned by APML in the bid documents and             F
the middle value of the Gross Calorific Value (“GCV” for short) range
of assured coal grade for domestic coal as per the FSA/LoA/MoU.
      24. Being aggrieved thereby, APML preferred appeals before the
learned APTEL. The learned APTEL framed the following three issues:
                                                                              G
         “Issue No. 1:     Whether the MERC was correct in holding
                           that the net SHR submitted by the Appellant
                           in its bid or SHR and Auxiliary Consumption
                           norms specified for new generating stations

1
    (2017) 14 SCC 80                                                          H
94            SUPREME COURT REPORTS                           [2023] 8 S.C.R.


A                               under the MYT Regulations, 2011, whichever
                                is superior shall form the basis for computing
                                Change in Law compensation under the
                                PPAs?
           Issue No. 2:         Whether the MERC was correct in holding
B                               that the reference GCV of domestic coal
                                supplied by CIL shall be the middle value of
                                GCV range of assured coal grade in LoA/FSA/
                                MoU and not the GCV as received?
           Issue No. 3:         Whether the MERC was correct in holding
C                               that for the purpose of Change in Law
                                compensation for 1180 MW capacity, shortfall
                                in domestic linkage coal shall be assessed by
                                considering the coal supply as the maximum
                                of (1) actual quantum of coal offered for
                                offtake by CIL under the LoA/FSA and (2)
D                               the minimum assured quantum in NCDP 2013
                                for the respective year?”
            25. On Issue No.1, the learned APTEL held that APML was
     entitled to compensation on the ground of Change in Law based on the
     SHR specified in the MERC MYT Regulations 2011 or the actual SHR
E    achieved by APML, whichever is lower.
            26. On Issue No.2, the learned APTEL held that the compensation
     for the Change in Law approved by the MERC shall be computed based
     on the actual GCV of coal received.

F           27. On Issue No.3, the learned APTEL held that under the NCDP,
     2007, there was an assurance of 100% coal supply and as such, while
     granting compensation on the ground of Change in Law, it was not justified
     to restrict it to the maximum of 35% to 25% for the respective four
     years of the 12th Plan.
           28. The learned APTEL held that the restitution principle has to
G
     be applied. It further held that to protect the interests of consumers, the
     Generators had itself indicated that the parameters which are more
     beneficial to the consumers i.e. the lower amongst the actual or as per
     the Regulations would protect the interests of the consumers.

H
MAHARASHTRA STATE ELECTRICITY DISTRIBUTION CO. LTD. v.                      95
    ADANI POWER MAHARASHTRA LTD. [B. R. GAVAI, J.]

      29. Being aggrieved thereby, the MSEDCL has approached this           A
Court by way of Civil Appeal No.684 of 2021.
      FACTS IN CIVIL APPEAL NO.6927 OF 2021
      30. In Civil Appeal No.6927 of 2021, the MSEDCL challenges
the concurrent orders passed by the CERC dated 15th November 2018
and the order passed by the learned APTEL dated 16th July 2021.             B

      31. MSEDCL issued a Request for Proposal (RFP) on 15th May
2009 and initiated the competitive bidding process for procurement of
power on long-term basis. GMR Warora Energy Ltd. (“GMR” for short)
submitted its bid on 7th August 2009 and emerged as one of the successful
bidders with a levelized tariff of Rs. 2.879/kWh. Accordingly, the PPA      C
was executed for the procurement of 200 MW of power on 17th March
2010 by MSEDCL on long-term basis. Similarly in March 2012,
Respondent No. 2-Union Territory of Dadra & Nagar Haveli (“DNH”
for short) issued an RFP for the procurement of power through
competitive bidding and GMR emerged as one of the successful bidders.       D
      32. Consequently, respondent No. 1 in Civil Appeal No.6927 of
2021 i.e. GMR entered into the following long-term PPAs for the supply
of power from the Project:
      (a) Supply and sale of 200 MW of power on a long-term basis to
      MSEDCL in terms of PPA dated 17th March 2010. The cut-off             E
      date for this PPA is 31st July 2009. Supply of power in terms of
      the PPA commenced from 17th March 2014.
      (b) Supply and sale of 200 MW of power on long term basis to
      Electricity Department, DNH in terms of PPA dated 21st March
      2013. The cut-off date of this PPA is 1st June 2012. Supply of        F
      power in terms of the PPA commenced from 1st April 2013.
      (c) Supply and sale of 150 MW of power on long term basis to
      TANGEDCO through back-to-back arrangements as follows:
               (i) Power Sale Agreement (PSA) dated 1st March 2013
         between GMR Energy Trading Limited (GMRETL) and GMR,               G
         based on which a bid was submitted to TANGEDCO;
               (ii) PPA dated 27th November 2013 between GMRETL
         and TANGEDCO for the supply of power from GMR to
         TANGEDCO. The cut-off date of this PPA is 27th February
         2013.                                                              H
96            SUPREME COURT REPORTS                           [2023] 8 S.C.R.


A                    (iii) PPA dated 3 rd May 2014 between GMR and
               GMRETL recording the terms and conditions in accordance
               with PPA between GMRETL and TANGEDCO. The supply
               of power under the PPA commenced on 22nd October 2015.
            33. Petition No. 8/MP/2014 was filed by GMR claiming
B    compensation on account of the impact of the Change in Law events
     during the Operation period and Construction period under MSEDCL
     and DNH PPAs. The Commission, by order dated 1st February 2017,
     had allowed some of the claims of GMR on the ground of Change in
     law. Vide the said order, it has also disallowed some of the claims.
     Aggrieved by the said order, GMR filed Appeal No. 111 of 2017 before
C    the learned APTEL in respect of the compensation claims disallowed by
     the Commission. Similarly, Appeal No. 290/2017 was filed by DNH Power
     Distribution Company Ltd against the said order dated 1 st February 2017
     disputing the compensation claims allowed to GMR under some Change
     in Law events.
D           34. During the pendency of the above said appeals, GMR has
     filed Petition (i.e. Petition No.88/MP/2018) seeking the following reliefs:
           “(a) Confirms that the following operational parameters which
           are imperative of calculation of compensation due to the Petitioner
           on account of change in law events, are to be considered on actuals:
E
                      (i) Auxiliary Power Consumption
                      (ii) Station Heat Rate
                      (iii) Gross calorific Value
           (b) Confirm that levy of Service Tax & Swachh Bharat Cess on
F
           coal transportation is on all components as per rail invoice;
           (c) Release of amounts due to the Petitioner from Respondent
           No. 1, MSEDCL in light of the Commission’s order dated 1.2.2017
           in Petition No. 8/MP/2014.”
G         35. Two of the issues involved in the present appeals with regard
     to SHR and GCV also fell for consideration before the CERC.
             36. The CERC found that the CERC norms applicable for the
     period 2009-14 and 2014-19 do not provide the norms for 300 MW units.
     It further found that the CERC norms provide for a degradation factor
H    of 6.5% and 4.5% respectively towards Heat Rate over and above the
MAHARASHTRA STATE ELECTRICITY DISTRIBUTION CO. LTD. v.                      97
    ADANI POWER MAHARASHTRA LTD. [B. R. GAVAI, J.]

Design Heat Rate. It found that since the Design Heat Rate is 2211          A
kcal/kWh, the gross Heat Rate works out to 2355 kcal/kWh and 2310
kcal/kWh for the period 2009-14 and 2014-19 respectively. It directed
that the SHR of 2355 kcal/kWh during the period 2009-14 and 2310
kcal/kWh during the period 2014-19 or the actual SHR, whichever was
lower, shall be considered for calculating the coal consumption for
                                                                            B
compensation under the Change in Law.
      37. Insofar as the GCV is concerned, the CERC found that in the
2014 Tariff Regulations of the Commission, the measurement of GCV
has been specified on “as received” basis. It, therefore, found that it
would be appropriate if the GCV on “as received” basis is considered
for computation of compensation for Change in Law.                          C

      38. Being aggrieved by the order passed by the CERC dated 15th
November 2018, the MSEDCL preferred an appeal being Appeal No.342
of 2019 before the learned APTEL. The learned APTEL did not find
merit in the submission of the MSEDCL and as such, dismissed the
appeal by judgment and order dated 16th July 2021.                          D

     39. Being aggrieved thereby, MSEDCL has approached this Court
by way of Civil Appeal No.6927 of 2021.
     40. The arguments on behalf of the appellant-MSEDCL in Civil
Appeal No.684 of 2021 were advanced by Shri Gopal Jain, learned Senior      E
Counsel, whereas arguments in Civil Appeal No.6927 of 2021 were
advanced by Shri G. Sai Kumar, learned counsel.
       41. We have also heard Shri Balbir Singh, learned Additional
Solicitor General and Shri M.G. Ramachandran, learned Senior Counsel
appearing for some of the State Electricity Distribution Companies, whose   F
matters are not being decided by this judgment, but wherein the aforesaid
three questions/issues are common.
      42. On behalf of the respondent-APML as well as the respondent-
GMR, Dr. Abhishek Manu Singhvi, learned Senior Counsel advanced
the arguments. His arguments were supplemented by Shri Vishrov
                                                                            G
Mukherjee, learned Counsel.
      SUBMISSIONS ON BEHALF OF THE DISCOMS
       43. The main arguments that were advanced on behalf of the
Distribution Companies (hereinafter referred to “DISCOMS”) are as
under:                                                                      H
98          SUPREME COURT REPORTS                           [2023] 8 S.C.R.


A    (i)      The SHR and GCV value are declared in the bid document
              and it is not permissible for the Generating Companies to
              claim advantage on the basis of SHR value which is different
              than the one quoted i.e. the SHR value as provided in the
              Tariff Regulations or the actual. It is their submission that
              the declaration of operational parameters i.e. SHR and GCV
B
              were the mandate of the bid in case of Case-1 competitive
              bidding process. It is submitted that if deviation from such
              declared bid parameters for compensating the bidder/
              Generating Companies/ Generators under the PPA on the
              ground of Change in Law is permitted, it will take away the
C             very sanctity of the bid.
     (ii)     It is submitted that to ensure serious participation in the bid
              process and for timely completion of commencement of
              supply of power, the Competitive Bidding Guidelines 2005
              itself mandates the bidder/generator/Generating Companies
D             to have a ‘firm’ fuel arrangement. It is their submission
              that it is mandatory for the bidder/generator to declare the
              ‘quantity’ of fuel required to generate power for the entire
              term of the PPA. The DISCOMS argued that the quantity
              of fuel can only be ascertained by applying the SHR and
              GCV components as declared in the bid.
E
     (iii)    It is submitted that the RFP itself mandated the participating
              bidders/generators to submit documentary evidence with
              regard to the ‘quantity’ of fuel required to generate power
              for the entire term of 25 years of the PPA.

F    (iv)     It is submitted that for ascertaining the ‘quantity’, it was
              also necessary for the bidder/generator to provide
              ‘supporting computation’ by declaring the SHR and GCV
              value applicable for the entire term of the PPA.
     (v)      It is the contention on behalf of the DISCOMS that the
G             bidder/generator, while submitting his/its bids, is required to
              submit the bids by taking into consideration all factors,
              including risks regarding fluctuations, availability of fuel/
              coal, etc. It is submitted that if there is any change with
              regard to the availability of fuel or the rate at which a bidder/
              generator is required to procure the coal, then the bidder/
H
MAHARASHTRA STATE ELECTRICITY DISTRIBUTION CO. LTD. v.                        99
    ADANI POWER MAHARASHTRA LTD. [B. R. GAVAI, J.]

            generator has to suffer the consequences thereof as he/it         A
            has submitted his/its bid with eyes open.
    (vi)    The thrust of the argument of the DISCOMS is that in a
            competitive bid based PPA under Section 63 of the
            Electricity Act, the quoted tariff is sacrosanct and it is not
            open for the respondent/generator to seek higher tariff or        B
            extra compensation under the PPA, except as per Article
            13 of the PPA dealing with impact of Change in Law. It is
            submitted that the reliance placed by the learned APTEL
            on the judgment of this Court in the Case of Energy
            Watchdog (supra) is totally misconceived.
                                                                              C
    (vii)   It is, therefore, submitted that the relief for the impact of
            NCDP 2013 is admissible only to the extent of the changes
            brought about by the NCDP 2013 and not in excess thereof.
            It is submitted that the Change in Law made by the Central
            Government on 31st July 2013 was vis-à-vis the NCDP 2007
            which was in force as on the cut-off date provided in Article     D
            13.1 of the PPA i.e. 7 days before the bid submission date.
            It is submitted that the very purpose of compensating the
            party affected by Change in Law is to restore, through
            monthly tariff payments, the affected party to the same
            economic position as if the Change in Law had not occurred.       E
    (viii) It is submitted that as per para 2.2 of the NCDP 2007 read
           with para 5.2, CIL was entitled to meet the shortfall in the
           availability of domestic coal by importing coal. In such event,
           the Generators were required to pay the higher cost of
           imported coal to CIL. It is submitted that while submitting        F
           the bids, the bidders/generators, therefore, had submitted
           their bids for supply of electricity to the DISCOMS knowing
           the position that they will not be compensated for higher
           cost of imported coal separately, over and above the quoted
           tariff /quoted energy charges, in the event of supply of
           imported coal by CIL.                                              G
    (ix)    It is contended that, if in the event the Generator could
            have procured the fuel/coal at a lesser price, then the benefit
            which would have occurred to him/it on account of such
            saving in procurement would have gone to him/it. On the
            same analogy, if the Generator is required to obtain the fuel/    H
100                  SUPREME COURT REPORTS                            [2023] 8 S.C.R.


A                      coal at a higher price then he/it cannot be heard to say that
                       he/it should be compensated for the same.
               (x)     It is submitted that, as a matter of fact, till 31st July 2013 i.e.
                       when the NCDP 2013 was brought into effect, there could
                       have been no claims from the Generators for increase in
B                      tariff to be allowed for higher coal cost on account of
                       imported coal supply. It is submitted that if the NCDP 2013
                       had not brought about a Change in Law, the position as
                       prevalent before would have continued. It is submitted that
                       this Court has consistently held that an unprecedented
                       increase in input cost cannot be a ground for a supplier not
C                      to perform the obligations under a binding contract or seek
                       higher price or compensation for such performance.
               (xi)    It is the submission of the DISCOMS that the benefit on
                       account of the Change in Law brought into effect by the
                       NCDP 2013 has to be restricted only to the extent of shortfall
D                      as provided by the said policy. It is submitted that if it was
                       the intention of the NCDP 2013 to provide for relief through
                       the Change in Law/policy decision for the shortfall even
                       below the specified percentages i.e. for entire shortfall on
                       actual basis, then there was no rationale in specifying the
E                      percentages in the NCDP 2013.
               (xii)   It is further contended by the DISCOMS that the contention
                       of the Generating Companies that Shakti Policy 2017 was
                       a continuation of NCDP 2013 is incorrect. It is submitted
                       that the first part under (A) of the Shakti Policy 2017 deals
F                      with the old regime of LoA/FSA which is the NCDP aspect.
                       The second part under (B) deals with the new transparent
                       coal allocation policy called SHAKTI. It is submitted that,
                       as a matter of fact, SHAKTI and allocation of coal
                       thereunder was admissible only to Entities which did not
                       have any LoA/FSA under the NCDP 2007 or the NCDP
G                      2013. Reliance in this respect has been placed on the
                       judgment of this Court in the case of Jaipur Vidyut Vitaran
                       Nigam Ltd. and others v. Adani Power Rajasthan
                       Limited and another2 (hereinafter referred to as “Adani
                       Rajasthan case”)
H     2
          2020 SCC Online SC 697
MAHARASHTRA STATE ELECTRICITY DISTRIBUTION CO. LTD. v.                     101
    ADANI POWER MAHARASHTRA LTD. [B. R. GAVAI, J.]

    (xiii) It is submitted that the law laid down by this Court in the     A
           case of Energy Watchdog (supra) has been applied by the
           learned APTEL in a patently erroneous and perverse
           manner.
    (xiv) It is submitted that the total quantum of coal required is to
          be computed not in an abstract manner but is to be               B
          necessarily based on the SHR of the power station. It is
          submitted that the SHR has nothing to do with coal quality
          or GCV of coal. It is submitted that the SHR is the boiler
          and turbine characteristic of a thermal power station and,
          therefore, indicative of the quality and efficiency of the
          machine. It is submitted that the quantum of coal requirement    C
          is less with lower SHR and increases with higher SHR,
          inasmuch as it relates to the ability and efficiency of the
          machines to extract heat energy from coal to produce per
          unit of electricity.
    (xv) It is submitted that in Case 2 bidding, the net SHR is a          D
         bidding parameter as coal linkage is arranged by the entity
         inviting bids, and actual cost of coal is allowed as a pass-
         through in the tariff as per the formula specified. It is their
         submission that there are no quoted energy charges in Case
         2 bidding but only quoted fixed charges. It is submitted that,    E
         whereas, in Case 1 bidding, SHR may not, as such, be the
         criteria for selection but is a necessary requirement/
         condition to be given for identifying the quantum of coal
         required to generate electricity over the length of the PPA.
         While submitting his/its bid and quoting energy charges, the
         bidder/generator was required to take into consideration the      F
         quantum of coal requirement which, in turn, is based on the
         SHR and auxiliary consumption parameters to be given by
         the bidder/generator. It is submitted that the coal Supply
         Agreement for quantum of coal is signed by CIL only for
         the quantum as determined above, based on the SHR and             G
         operating parameters provided by the bidder/generator. It
         is submitted that the view taken by the learned APTEL is
         contrary to the view taken by it between the same parties
         in its judgment dated 13th April 2018 in Appeal No. 210 of
         2017.
                                                                           H
102      SUPREME COURT REPORTS                            [2023] 8 S.C.R.


A     (xvi) It is submitted that if the SHR which is higher than the one
            quoted by the bidder/generator is to be taken into
            consideration, then it will amount to granting premium to
            the Generator for its inefficiency. It is submitted that if the
            coal consumption increases on account of highest SHR,
            the excess expenditure on quantum of coal is to be borne
B
            by the Generator.
      (xvii) It is submitted that if the bid assumed SHR is 2200 kcal/kg
             and actual SHR is 2300 kcal/kg, when the quoted tariff is
             based on the SHR of 2200 kcal/kg, for Change in Law
             impact, SHR of 2300 kcal/kg cannot be permitted to be
C            used for computation of compensation for Change in Law.
      (xviii) It is submitted that the impugned judgment permitting the
              actual SHR or the SHR given in Tariff Regulations,
              whichever is lower, if upheld, would amount to converting
              the scope of Section 63 tariff determination into a Section
D             62 cost plus tariff determination. It is submitted that this is
              impermissible in a competitive bid based PPA.
      (xix) It is further submitted that the MERC Tariff Regulations
              expressly provides that the Tariff Regulations will have no
              application to Section 63 tariff determination and the same
E             is governed by the guidelines of the Central Government
              under Section 63 of the Electricity Act.
      (xx) It is submitted that perusal of Regulation 2(2)(a) of the
              Central Electricity Regulatory Commission (Terms and
              Conditions of Tariff) Regulations, 2019 would reveal that
F             they are not applicable where the tariff has been discovered
              through tariff based competitive bidding in accordance with
              the guidelines issued by the Central Government and adopted
              by the Commission under Section 63 of the Electricity Act.
      (xxi) It is submitted that when admittedly there is bid assumed
              SHR as per bidding conditions, the learned APTEL cannot
G             ignore the same on the purported ground of equity and
              provide for an alternate parameter for computational
              purpose of actual SHR with the ceiling as under the Tariff
              Regulations. It is submitted that this will result in changing
              the bidding terms and conditions after the bid was accepted
H             and became final.
MAHARASHTRA STATE ELECTRICITY DISTRIBUTION CO. LTD. v.                       103
    ADANI POWER MAHARASHTRA LTD. [B. R. GAVAI, J.]

    (xxii) It is further submitted that the finding that the GCV             A
           computation is to be made on ‘as received’ basis, is also
           patently erroneous. It is submitted that the real purpose
           behind relying on the said methodology of computation is to
           recover the grade slippage in the coal grade actually supplied
           as against the coal grade billed by the Coal Company and
                                                                             B
           all the losses in the heat value of the coal during the time
           period when the coal is taken delivery from the coal mines
           and transported to the Power Plant and unloading at the
           Power Plant site.
    (xxiii) It is submitted that the evaluation of GCV on air dried basis
            by Coal Company was well known/existing even prior to            C
            bidding and the Generators were very much aware of it.
            Accordingly, the same has already been factored into while
            the Generators submitted their bids. As such, if the
            computation of GCV is permitted on ‘as received’ basis,
            the Generators will be doubly compensated. In any case, it       D
            is submitted that if the Generators had any issues with
            regard to the grade of coal i.e. GCV range and quantum,
            then that is an issue between the Generators and the
            respective Coal Companies, which is required to be resolved
            under the FSA between them. The DISCOMS cannot be
            roped into for the resolution of such disputes between the       E
            Generators/Generating Companies and the Coal Companies.
    (xxiv) Lastly, it is submitted that since the letter of the MoP, which
           has been considered as a Change in Law event, is dated
           31st July 2013, the learned APTEL could not have given
           effect to the same from 1st April 2013. It is submitted that      F
           this would permit giving the benefit of compensation with
           retrospective effect.
    (xxv) Insofar as the reliance placed by the Generating Companies
          on the judgment of this Court in Adani Rajasthan case is
          concerned, it is submitted that the said judgment would not        G
          be applicable to the facts of the present case. It is submitted
          that in the said case, there was no FSA and the State
          Government had undertaken to supply the entire coal
          quantum.
                                                                             H
104               SUPREME COURT REPORTS                        [2023] 8 S.C.R.


A         (xxvi) It is further submitted that the judgment of this Court in the
                 case of Nabha Power Limited (NPL) v. Punjab State
                 Power Corporation Limited (PSPCL) and another3 would
                 also not be applicable to the facts of the present case
                 inasmuch as the said case was under Case-2.
B         (xxvii)It is submitted that the inability of a Generator to seek
                 sufficient relief from the Coal Companies cannot be a reason
                 to claim relief from the Distribution Licensees/DISCOMS
                 or the consumers. The DISCOMS cannot be penalized on
                 account of failure by the Coal Companies of supplying
                 sufficient coal.
C         (xxviii) An additional ground in Civil Appeal No.6927 of 2021 raised
                 is that CERC has erred in holding that the principle of late
                 payment surcharge envisaged in Articles 8.3.5 and 8.8.3 of
                 the PPA is applicable towards payment of the balance
                 amounts by MSEDCL in respect of the relief under Change
D                in Law.
          SUBMISSIONS ON BEHALF OF THE GENERATING
          COMPANIES
          44. As against this, it is submitted on behalf of the Generating
      Companies as under:
E         (i)    It is submitted that under the NCDP 2007, 100% normative
                 coal requirement of Generating Companies was assured to
                 be supplied by the CIL. However, by NCDP 2013, the
                 responsibility of CIL to supply coal was reduced to 65%,
                 65%, 67% and 75% of ACQ for the remaining years of the
                 12th Five Year Plan i.e. Financial Year 2013-14 to Financial
F
                 Year 2016-17.
          (ii) It is submitted that the NCDP has been held to be a law for
                 the purposes of the Electricity Act. It is, therefore, submitted
                 that the Generating Companies are entitled to compensation
                 for the shortfall of coal in terms of NCDP 2013 and the
G                same has to be paid on actuals, i.e. to the extent the shortfall
                 in coal supply actually exists.
          (iii) It is submitted that the said issue is no more res integra
                 and is covered by the judgment of this Court in the case of
      3
          (2018) 11 SCC 508
H
MAHARASHTRA STATE ELECTRICITY DISTRIBUTION CO. LTD. v.                         105
    ADANI POWER MAHARASHTRA LTD. [B. R. GAVAI, J.]

               Energy Watchdog (supra) and in Adani Rajasthan case             A
               (supra).
         (iv) It is submitted that, as per the guideless issued by the MoP,
               for Case-1 bidding, SHR and GCV are not bid parameters.
               The SHR and GCV mentioned in the bid is part of technical
               information and is not relevant for computing Change in         B
               Law compensation. It is submitted that there are substantial
               distinctions between Case-1 and Case-2 bid. The first one
               is that in Case-1 bid, SHR and GCV are not bid parameters,
               whereas in Case-2, SHR and GCV are bid parameters.
               Secondly, in Case-1 bidding, energy charge is not computed
               since the energy charge forms part of quoted tariff, whereas    C
               in Case-2 bidding, energy charge is computed based on the
               net heat rate quoted in the financial bid. Thirdly, in Case-1
               bidding, the PPA has no definition of quoted Net Heat Rate/
               SHR, whereas in Case-2 bid, the PPA defines quoted Net
               Heat Rate/SHR. It is, therefore, submitted that in Case-1       D
               bid there is no consideration of SHR and GCV in the formula
               of energy charge, whereas in Case-2 bid, these two
               parameters provide the formula for computing energy
               charge.
         (v) It is submitted that the learned APTEL in the case of
               Wardha Power v. Reliance Infrastructure & Ors.4 has             E
               held that if SHR and GCV as submitted in the bid are
               considered for Change in Law compensation, it may result
               in over or under recovery and should be considered only on
               ‘actuals’. It is submitted that the said judgment in Wardha
               Power (supra) has not been challenged/appealed against          F
               and has thus attained finality.
         (vi) The Generators further rely on the judgment of this Court
               in Adani Rajasthan case (supra). It is submitted that in
               the said case, the learned APTEL had held that operational
               parameters (like SHR and Auxiliary consumption) must be
                                                                               G
               considered as per ‘normative’ value, and this view has been
               upheld by this Court.
         (vii) It is further submitted that the MERC in its order dated 7th
               March 2018 in Case No.123 of 2017 (JSW v. MSEDCL)
4
    Appeal No.288 of 2013                                                      H
106         SUPREME COURT REPORTS                         [2023] 8 S.C.R.


A            has held that the lower of actual or normative parameter
             for Auxiliary consumption (an operational parameter like
             SHR) has to be considered for Change in Law
             compensation. It is submitted that the MSEDCL has not
             challenged the said judgment, which has thus attained finality.
B     (viii) It is submitted that the SHR is continuously being monitored
             and its actual value, as certified by Energy Auditors, is
             submitted to MSEDCL along with claims. As such, ‘actuals’
             can be ascertained and verified for computation purposes.
      (ix) It is submitted that, equally, the GCV of coal is certified by
             third party sampling agencies. A GCV certificate is
C            submitted to MSEDCL for each railway rake separately,
             along with claim. Such ‘actuals’ on ‘as received’ basis can
             be ascertained/verified for computational purposes.
      (x)     It is further submitted that some of the DISCOMS in the
              proceedings before the CERC have contended that the
D             SHR shall be considered after ascertaining actual design
              heat rate and margin as per CERC Regulations from time
              to time. They have further taken a stand that Auxiliary
              Consumption shall be considered as per CERC Regulations.
              On affidavit, it is also stated that GCV of alternate coal
E             shall be as certified by a Third Party Sampling Agency, for
              which the Commission should provide appropriate guideline.
              It is, however, submitted that now the DISCOMS are taking
              a U-turn by contending that the SHR should be based on
              bid assumed parameters.
      (xi)    It is submitted that, in any case, to maintain balance, APML
F
              had itself offered for the benefit to be granted on the lower
              of ‘actual’ or ‘normative’ SHR as per Regulations. The
              same has been accepted by the learned APTEL. It is
              submitted that this will ensure that no inefficiency is passed
              on to consumers and, at the same time, the Generator is
G             restituted.
      (xii) It is submitted that had there been no occurrence of Change
            in Law event, i.e. there was no shortfall in coal supply, the
            tariff payment to the Generating Companies would have
            been based on quoted energy charge. In such a situation,
H           SHR and GCV of coal would not have come into the picture.
MAHARASHTRA STATE ELECTRICITY DISTRIBUTION CO. LTD. v.                       107
    ADANI POWER MAHARASHTRA LTD. [B. R. GAVAI, J.]

          However, when there is an occurrence of Change in Law              A
          event, the principle of ‘Restitution’ comes into play. It is
          submitted that ‘restitution’ can take place only with
          consideration of ‘actual’ parameters.
    (xiii) It is submitted that taking this into consideration, expert
           bodies like the CERC and APTEL have allowed the SHR               B
           and GCV to be determined on ‘actual’ basis.
    (xiv) It is submitted that the SHR indicated in the bid as part of
          technical information does not conform to the mandate of
          restitution as it cannot put the Generator back to the same
          economic position had Change in Law event not occurred.            C
    (xv) It is submitted as per the NCDP 2007, 100% normative
         requirement of coal was to be supplied by the CIL. However,
         due to shortfall of coal in the country, the responsibility of
         CIL to supply coal was reduced to 65%, 65%, 67% and
         75% of the ACQ. The shortfall in coal was to be met either
                                                                             D
         by the CIL or by the Generating Companies/Generators by
         importing coal. It is submitted that the higher cost of such
         imported coal was allowed to be a pass-through.
    (xvi) It is submitted that a conjoint reading of CERC statutory
          advice dated 20th May 2013, CCEA decision dated 21st June
                                                                             E
          2013, MoP letter dated 31st July 2013, and clause 6.1 of the
          Tariff Policy 2016 issued by the MoP would reveal that
          pass-through of the higher cost of quantity of shortfall in
          coal procured from alternate sources was to be allowed. It
          is submitted that this position has been upheld by the
          judgments of this Court in the case of Energy Watchdog             F
          (supra) and Adani Rajasthan case (supra).
    (xvii) It is submitted that this pass-through is by way of restitution
           due to shortfall in 100% assured quantity of coal and it cannot
           be limited to the percentages/trigger levels specified in the
           NCDP 2013. It is submitted that the principle of restitution      G
           would require the pass-through to the extent the supply from
           CIL was cut down. It is submitted that an argument to the
           contrary has already been rejected by this Court in the case
           of Adani Rajasthan case (supra).

                                                                             H
108                   SUPREME COURT REPORTS                          [2023] 8 S.C.R.


A              (xviii) In addition to the judgments of this Court in the cases of
                       Energy Watchdog (supra) and Adani Rajasthan case
                       (supra), the Generating Companies also rely on the judgment
                       of this court in the case of Uttar Haryana Bijli Vitran
                       Nigam Limited (UHBVNL) and another v. Adani Power
                       Limited and others5.
B
               (xix) It is also submitted that the contention on the part of the
                     DISCOMS that Adani Rajasthan case (supra) would not
                     be applicable to the facts of the present case, inasmuch as
                     there was no FSA scenario, is also factually incorrect.
C            45. In addition to the aforesaid submissions, the respondent in
      Civil Appeal No.6927 of 2021 i.e. GMR, the following submissions have
      been made.
               (i)      That Schedule 10 of the PPA executed between GMR and
                        MSEDCL clearly mentions that the levelized tariff will be
D                       as per CERC Regulations.
               (ii)     It is submitted that the normative SHR as mentioned in the
                        bid is computed assuming power plant is operating at 85%
                        of the Plant Load Factor (“PLF” for short). It is, however,
                        submitted that the PLF is at the sole discretion of the
E                       procurer-DISCOMS as they decide the quantum of power
                        to off-take.
               (iii)    It is submitted that the SHR is a real-time operating
                        parameter which varies from time to time, and it is computed
                        by working out the total electricity generated from the
F                       amount of coal consumed in heat value (kCal) terms.
               (iv)     It is further submitted that the GCV of coal actually delivered
                        at site and fed to the boiler varies from wagon to wagon. It
                        cannot be a homogeneous value.
               (v)      It is further submitted that the details given in the bid with
G                       regard to SHR and GCV were only indicative of the coal
                        linkage to show that GMR had the necessary means to
                        supply power on sustained basis and was a serious bidder,
                        and to further demonstrate its meeting of the eligibility
                        requirement prescribed under the RFP.
      5
H         (2019) 5 SCC 325
MAHARASHTRA STATE ELECTRICITY DISTRIBUTION CO. LTD. v.                         109
    ADANI POWER MAHARASHTRA LTD. [B. R. GAVAI, J.]

         (vi)   It is submitted that the supporting documents/information      A
                regarding fuel only provides the quantity of coal required
                for the project at Normative PLF and SHR computed as
                per CERC norms, which is 2355 kCal/kWh. It is submitted
                that MSEDCL is now insisting on Design Gross Heat Rate
                of 2211 kCal/kWh, which was not considered even for
                                                                               B
                computation of quantum of coal at the time of bid
                submission.
       (vii) It is further submitted that the Central Electricity Authority,
              vide Notifications dated 17th October 2017 and 18th October
              2017, has even allowed for loss in GCV from ‘as received
              basis’ to ‘as fired basis’ and as such, there is no reason as    C
              to why GCV could not be computed on ‘as received basis’.
       (viii) It is further submitted that the MSEDCL cannot be permitted
              to equate GMR’s case with APML and Rattan India Power
              Limited inasmuch as GMR falls under the jurisdiction of
              CERC, whereas the other two fall under the jurisdiction of       D
              MERC.
       (ix) Insofar as late payment charges are concerned, it is
              submitted that MSEDCL had unilaterally deducted the
              amount, which is contrary to the provisions of the PPA and
              as such, both CERC and learned APTEL have rightly held           E
              that GMR was entitled to late payment surcharge in terms
              of Article 8.3.5. Reliance in this respect is placed on the
              judgment of this Court in the case of Maharashtra State
              Electricity Distribution Company Limited v.
              Maharashtra Electricity Regulatory Commission and
              others 6and Tamil Nadu Generation & Distribution                 F
              Corporation Limited v. PPN Power Generating
              Company Private Limited7
       RELEVANT DOCUMENTS
       46. For considering the rival submissions, it will be relevant to
refer to certain documents placed on record.                                   G
       47. The MoP notified the Competitive Bidding Guidelines, 2005
(hereinafter referred to as “the said Guidelines”) on 19th January 2005.
The said Guidelines were framed under Section 63 of the Electricity
6
    (2022) 4 SCC 657
7
    (2014) 11 SCC 53                                                           H
110                SUPREME COURT REPORTS                         [2023] 8 S.C.R.


A     Act. It will be relevant to refer to the following part of the preamble of
      the said Guidelines.
             “1.        Preamble
             ………..
             These guidelines have been framed under the above provisions of
B            section 63 of the Act. The specific objectives of these guidelines
             are as follows:
                 1. Promote competitive procurement of electricity by
                 distribution licensees;
                   2. Facilitate transparency and fairness in procurement
C                  processes;
                   3. Facilitate reduction of information asymmetries for various
                   bidders;
                   4. Protect consumer interests by facilitating competitive
                   conditions in procurement of electricity;
D
                   5. Enhance standardization and reduce ambiguity and hence
                   time for materialization of projects;
                   6. Provide flexibility to suppliers on internal operations while
                   ensuring certainty on availability of power and tariffs for
                   buyers.”
E
           48. Paragraph 2 of the said Guidelines deals with the scope of the
      Guidelines. Para 2.2 of the said Guidelines reads thus:
            “2.2. The guidelines shall apply for procurement of base-load,
            peak-load and seasonal power requirements through competitive
            bidding, through the following mechanisms:
F
            (i)       Where the location, technology, or fuel is not specified by
                      the procurer (Case 1);
            (ii)      For hydro-power projects, load center projects or other
                      location specific projects with specific fuel allocation such
G                     as captive mines available, which the procurer intends to
                      set up under tariff based bidding process (Case 2).
            However separate RFP shall be used for procuring base load or
            peak load or seasonal load requirements as the case may be.”
             49. It can thus be seen that Para 2.2 distinguishes two types of
H     cases, viz., Case-1 and Case-2. Case-1 deals with the case where the
MAHARASHTRA STATE ELECTRICITY DISTRIBUTION CO. LTD. v.                            111
    ADANI POWER MAHARASHTRA LTD. [B. R. GAVAI, J.]

location, technology, or fuel is not specified by the procurer. Case-2            A
deals with hydro-power projects, load center projects or other location
specific projects with specific fuel allocation such as captive mines
available, which the procurer intends to set up under tariff based bidding
process.
        50. Paragraph 3 of the said Guidelines deals with preparation for         B
inviting bids. Clause (I) of Para 3.2 deals with Case-2, whereas clause
(II) of Para 3.2 deals with Case-1. Sub-clause (i) of clause (II) of Para
3.2 requires the bidder to undertake site identification and land acquisition.
The bidder is required to submit a copy of notification issued for the land
in question under Section 4 of the Land Acquisition Act, 1894. For the
part of land excluding that which is to be acquired under the Land                C
Acquisition Act, 1894, the bidder is required to furnish documentary
evidence to establish allotment/ lease/ ownership/ vesting of at least
one-third area of the said land. Under sub-clause (ii), the bidder is required
to submit environmental clearance for the power station. Under sub-
clause (iii), the bidder is required to supply forest clearance, if applicable,   D
for the land for the power station. Sub-clause (iv) is the most important
for the resolution of the present dispute, which reads thus:
       “3.        Preparation for inviting bids
       3.1        …………
       3.2        (I)      ……………                                                  E
                  (II)     ………………
                  (i)       ………………
                  (ii)      ………………
                  (iii)     ………………                                                F
                 iv) Fuel Arrangements: (a) In the following cases fuel
                 arrangements shall have to be made for the quantity of
                 fuel required to generate power from the phase of the
                 power station from which power is proposed to be
                 supplied at Normative Availability for the term of the           G
                 PPA.
                          In case of domestic coal, the Bidder shall have
                          made firm arrangements for fuel tie up either by
                          way of coal block allocation or fuel linkage
                                                                                  H
112            SUPREME COURT REPORTS                           [2023] 8 S.C.R.


A                            In case of domestic gas, the Bidder shall have
                             made firm arrangements for fuel tie up by way of
                             long term fuel supply agreement for the term &
                             quantity as per Government of India gas allocation
                             policy
B                      b) Fuel arrangements in the following cases shall have
                       to be made for the quantity of fuel required to generate
                       power from the power station for the total installed
                       capacity.
                             In case of imported coal, the Bidder shall have
C                            either acquired mines having proven reserves for
                             at least 50% of the quantity of coal required OR
                             shall have a fuel supply agreement for at least
                             50% of the quantity of coal required for a term of
                             at least five (5) years or the term of the PPA,
                             whichever is less.
D
                             In case of RLNG, the Bidder shall have made
                             firm arrangements for fuel tie up by way of fuel
                             supply agreement for at least 50% of the quantity
                             of fuel required for a term of at least five (5)
                             years or the term of the PPA, whichever is less.
E
                       Blending of Imported and Domestic coal may be used
                       in which case, criteria for imported and domestic coal
                       shall be met separately in the ratio of blending.”
            51. It can thus be seen that in case of domestic coal, the bidder is
      required to make firm arrangements for fuel tie up either by way of coal
F     block allocation or fuel linkage.
            52. Clause (b) of sub-clause (iv) of clause (II) of Para 3.2 deals
      with imported coal, in which case the bidder shall have either acquired
      mines having proven reserves for at least 50% of the quantity of coal
      required OR shall have a fuel supply agreement for at least 50% of the
G     quantity of coal required for a term of at least five years or the term of
      the PPA, whichever is less.
              53. Paragraph 4 of the said Guidelines deals with Tariff Structure.
      It will be relevant to refer to Para 4.2, which reads thus:
            “4. Tariff Structure
H
MAHARASHTRA STATE ELECTRICITY DISTRIBUTION CO. LTD. v.                          113
    ADANI POWER MAHARASHTRA LTD. [B. R. GAVAI, J.]

      4.1        ……..                                                           A
      4.2. In case of long term procurement with specific fuel allocation
      (Case 2), the procurer shall invite bids on the basis of capacity
      charge and net quoted heat rate. The net heat rate shall be ex-bus
      taking into account internal power consumption of the power
      station. The energy charges shall be payable as per the following         B
      formula:
      Energy Charges = Net quoted heat rate X Scheduled
      Generation X Monthly Weighted Average Price of Fuel/
      Monthly Average Gross Calorific Value of Fuel
      If the price of the fuel has not been determined by the Government        C
      of India, government approved mechanism or the Fuel Regulator,
      the same shall have to be approved by the appropriate Regulatory
      Commission.
      In case of coal/lignite fuel, the cost of secondary fuel oil shall be
      factored in the capacity charges.”                                        D
      54. It can thus be seen that insofar as Case-2 is concerned, the
procurer is required to invite bids on the basis of capacity charge and net
quoted heat rate. The net heat rate is required to be ex-bus taking into
account internal power consumption of the power station. It further
provides that if the price of the fuel is not determined by the Government      E
of India, government approved mechanism or the Fuel Regulator, the
same shall have to be approved by the appropriate Regulatory
Commission.
       55. Para 4.4 provides that the capacity charge shall be paid based
on actual availability, as per charges quoted in Rs./kwh and shall be           F
limited to the normative availability. It further provides that the normative
availability for Case-1 and thermal stations under Case-2 shall be a
maximum of 85%.
      56. Para 4.7 is another important clause for the resolution of the
present dispute, which reads thus:                                              G
      “4.7. Any change in law impacting cost or revenue from the
      business of selling electricity to the procurer with respect to the
      law applicable on the date which is 7 days before the last date for

                                                                                H
114             SUPREME COURT REPORTS                            [2023] 8 S.C.R.


A           RFP bid submission shall be adjusted separately. In case of any
            dispute regarding the impact of any change in law, the decision of
            the Appropriate Commission shall apply.”
             57. It can thus be seen that any Change in Law impacting cost or
      revenue from the business of selling electricity to the procurer with respect
B     to the law applicable on the date which is 7 days before the last date for
      RFP bid submission shall be adjusted separately. It provides that in case
      of any dispute regarding the impact of any Change in Law, the decision
      of the Appropriate Commission shall apply.
            58. It will also be relevant to refer to Para 4.12, which reads thus:
C           “4.12 No adjustment shall be provided for heat rate degradation
            of the generating stations. Even in case of bids based on net heat
            rate, the bidder shall factor in site conditions, loading conditions,
            frequency variations etc and no adjustment shall be allowed on
            the quoted net heat rate for the duration of the contract.”
D            59. It can thus be seen that no adjustment is to be provided for
      heat rate degradation of the generating stations. Even in case of bids
      based on net heat rate, the bidder shall factor in site conditions, loading
      conditions, frequency variations etc. and no adjustment shall be allowed
      on the quoted net heat rate for the duration of the contract.
E            60. The NCDP 2007 would be of vital importance. Clause 2.2
      thereof deals with Power Utilities including Independent Power Producers
      (IPPs)/Captive Power Plants (CPPs) and Fertilizer Sector. Clause 2.2
      reads thus:
            “2. Distribution and Pricing of coal to different consumers/
F           sector(s):
            2.1.       ………………
            2.2 Power Utilities including Independent Power Producers
            (IPPs)/Captive Power Plants(CPPs) and Fertilizer Sector
G              100% of the quantity as per the normative requirement of the
            consumers would be considered for supply of coal, through Fuel
            Supply Agreement (FSA) by Coal India Limited (CIL) at fixed
            prices to be declared/notified by CIL. The units/power plants,
            which are yet to be commissioned but whose coal requirements
            has already been assessed and accepted by Ministry of Coal and
H
MAHARASHTRA STATE ELECTRICITY DISTRIBUTION CO. LTD. v.                           115
    ADANI POWER MAHARASHTRA LTD. [B. R. GAVAI, J.]

      linkage/Letter of Assurance (LoA) approved as well as future               A
      commitments would also be covered accordingly.”
       61. It can thus be seen that the NCDP 2007 assured 100% of the
quantity as per the normative requirement of the consumers for supply
of coal, through FSA by CIL at fixed prices to be declared/notified by
CIL. It further provided that the units/power plants, which are yet to be        B
commissioned but whose coal requirements has already been assessed
and accepted by MoC and linkage/Letter of Assurance (LoA) approved
as well as future commitments would also be covered in accordance
therewith.
       62. It will also be relevant to note the following part of clause 5.2     C
of the NCDP 2007.
      “5.        Policy for New Consumers
      5.1.       ……………
      5.2.       ……………In order to meet the domestic requirement                  D
      of coal, CIL may have to import coal as may be required from
      time to time, if feasible. CIL may adjust its overall price accordingly.
      Thus, it will be the responsibility of CIL/Coal companies to meet
      full requirement of coal under FSAs even by resorting to imports,
      if necessary.”
                                                                                 E
       63. It can thus be seen that clause 5.2 of the NCDP 2007 provides
that in order to meet the domestic requirement of coal, CIL may have to
import coal as may be required from time to time, if feasible. It further
provided that CIL would adjust its overall price accordingly. The NCDP
2007 emphasizes the responsibility of CIL/Coal Companies to meet full
requirement of coal under FSAs even by resorting to imports, if necessary.       F
      64. It will also be relevant to refer to the communication addressed
by the MoP dated 9th May 2013 to the Secretary, CERC.
      “Subject: Impact on tariff on the concluded PPAs due to domestic
      coal availability.
                                                                                 G
      Sir,
             Coal linkages have been granted for power projects under
      the New Coal Distribution Policy 2007 (NCDP), which mandates
      that CIL will meet 100% of normative requirement of power sector.
      Para 5.2 of NCDP provides that “In order to meet the domestic              H
116      SUPREME COURT REPORTS                           [2023] 8 S.C.R.


A     requirement of coal, CIL may have to import coal as may be
      required from time to time, if feasible. CIL may adjust its overall
      price accordingly. Thus, it will be the responsibility of CIL/
      Coal companies to meet full requirement of coal under FSAs
      even by resorting to imports, if necessary”. Post NCDP MoC
      granted linkages between 2008-2010 with the assumption that it
B
      would meet coal requirement at around 85% PLF. On this basis
      LoAs were issued by coal companies, after getting commitment
      guarantees in the form of Bank Guarantee from the developers
      thereby undertaking an explicit obligation to supply coal to the
      extent of the specified quantity to the power developer. Having
C     obtained the LOA the developers would have proceeded on the
      assumption of getting the requisite quantity of domestic coal with
      the disincentive trigger of 90% of LoA quantity prevailing under
      the then Fuel Supply Agreement (FSA) with a provision for CIL
      resorting to import of coal to bridge the gap, if any. It is assumed
      that the power producers would have factored this assurance
D
      regarding coal supply while submitting their bids in response to
      Case 1 and Case 2 competitive bidding for long term power
      purchase agreements. Thus, while the fuel price risk would have
      been taken into account and factored in the escalable component
      of energy charges, it is assumed that no fuel availability risk would
E     have been taken into consideration on account of the LOAs given
      by CIL.
      2. It now transpires that on account of the limited availability of
      coal Ministry of Col has indicated that CIL may not be in a position
      to supply more than 60 to 65% of ACQ to those power producers
F     who had been earlier issued LOAs of normative quantities
      corresponding to 85% PLF. Simultaneously, it has been proposed
      that the disincentive trigger for coal supply would be brought down
      from 90% to 60 to 65% by CIL in the new fuel supply agreements
      to be signed with these power producers. This obviously would
      create a situation where the power producers would have to arrange
G     fuel from open market including imports either through CIL or
      directly. In view of this scenario, PPAs which are already
      concluded between the developers and discoms as a result of
      competitive bidding in the last few years based on domestic coal
      linkage (LOA) may have to use imported coal to bridge the
H     shortage of domestic coal in order to fulfil that contractual
MAHARASHTRA STATE ELECTRICITY DISTRIBUTION CO. LTD. v.                        117
    ADANI POWER MAHARASHTRA LTD. [B. R. GAVAI, J.]

      obligations. The Association of Power Producers represented on          A
      this issue of shortage of domestic coal and its consequential effect
      on the concluded PPAs through competitive bidding route.
      3. The Cabinet Committee on Economic Affairs (CCEA) has also
      considered the situation arising out of the inadequate availability
      of coal leading to this non-fulfilment of the LOA commitments on        B
      the part of CIL. CCEA has decided the following guidelines in its
      meeting held on 06.02.2013 in respect of generating plants
      commissioned/to be commissioned during the period 1.4.09 to
      31.03.15:
      i)    CIL will provide imported coal on cost plus basis to all          C
            producers willing to take such cost;
      ii)   That the higher cost of imported coal will be allowed as a
            pass through.
      3. In view of the circumstances stated above CERC is requested
      to advice the Government on the manner in which the issue of            D
      fuel availability risk arising out of CIL’s inability to meet its LOA
      commitments could be addressed with regard to power producers
      who have already entered into long term PPAs with distribution
      companies based on such commitments and the feasibility of passing
      on the additional cost of procuring market fuel incurred by the         E
      power developers on account of the circumstances stated in the
      aforesaid paras. CERC is also requested to suggest appropriate
      ways for issuing advisory to SERCs/State Governments which
      may necessitated to be issued by MoP for the implementation of
      the above.
                                                                              F
      4. CERC’s considered advice is requested in this matter at the
      earliest.
      5. This issues with the approval of MOSP (I/C).”
      65. Perusal of the communication dated 9th May 2013 would clearly
show that the NCDP 2007 mandates that CIL will meet 100% of                   G
normative requirement of power sector. It states that, post NCDP 2007,
MoC has granted linkages between 2008-2010 with the assumption that
it would meet coal requirement at around 85% of the PLF. On that
basis, the LoAs were issued by Coal Companies, after getting
commitment guarantees in the form of Bank Guarantees from the
                                                                              H
118                SUPREME COURT REPORTS                        [2023] 8 S.C.R.


A     developers, thereby undertaking an explicit obligation to supply coal to
      the extent of the specified quantify to the power developer. It further
      states that having obtained the LoA, the developers would have
      proceeded on the assumption of getting the requisite quantity of domestic
      coal with the disincentive trigger of 90% of LoA quantity prevailing under
      the then FSA with a provision for CIL resorting to import of coal to
B
      bridge the gap, if any. It specifically mentions that the power producers
      would have factored in this assurance regarding coal supply while
      submitting their bids in response to Case-1 and Case-2 competitive bidding
      for long-term PPAs.
             66. The said communication further records that it now transpires
C     that on account of the limited availability of coal, MoC has indicated that
      CIL may not be in a position to supply more than 60 to 65% of ACQ to
      those power producers who had been earlier issued LoAs of normative
      quantities corresponding to 85% of the PLF. It was proposed that the
      disincentive trigger for coal supply would be brought down from 90% to
D     60 to 65% by CIL in the new FSAs to be signed with these power
      producers. It further states that in view of this scenario, PPAs which
      are already concluded between the developers and the DISCOMS as a
      result of competitive bidding in the last few years based on domestic
      coal linkage (LoA) may have to use imported coal to bridge the shortage
      of domestic coal in order to fulfil their contractual obligations.
E
            67. The communication further records that the CCEA has also
      considered the situation arising out of the inadequate availability of coal
      leading to the non-fulfilment of its LOA commitments on the part of the
      CIL. The CCEA, therefore, in its meeting held on 6th February 2013 has
      decided the following guidelines in respect of generating plants
F     commissioned/to be commissioned during the period 1st April 2009 to
      31st March 2015:
            ii)      That CIL will provide imported coal on cost plus basis to all
                     producers willing to take such cost;

G           iii)     That the higher cost of imported coal will be allowed as a
                     pass-through.
             68. The communication therefore requested the CERC to advise
      the Government on the manner in which the issue of fuel availability
      risk, arising out of CIL’s inability to meet its LOA commitments, could
      be addressed. The CERC was also requested to suggest appropriate
H
MAHARASHTRA STATE ELECTRICITY DISTRIBUTION CO. LTD. v.                          119
    ADANI POWER MAHARASHTRA LTD. [B. R. GAVAI, J.]

ways for issuing advisories to SERCs/State Governments by the MoP,              A
which may be necessitated for the implementation of the above.
       69. In pursuance of the aforesaid Communication dated 9 th May
2013, the CERC issued Statutory Advice on 20th May 2013 under Section
79(2) of the Electricity Act regarding impact on tariff of the concluded
PPAs due to domestic coal availability. It will be relevant to refer to the     B
following part of the said statutory advice.
      “2. The matter was considered in the Commission. The
      Commission appreciates the need for securing fuel supply for
      various projects in order to ensure optimum generation from the
      power plants in the country. Non-availability of adequate quantum         C
      of coal has posed serious challenge to power generation as
      reflected in the data compiled by the Central Electricity Authority
      (CEA): the Plant Load Factor (PLF) of the generating stations
      across the country has been severely affected for want of
      adequate coal supply by CIL/Coal Companies.
                                                                                D
      3. The proposal to make CIL supply imported coal on cost plus
      basis to all power projects commissioned or to be commissioned
      during the period 1.4.2009 to 31.3.2015 and willing to take such
      coal would require appropriate change in the NCDP, as at present
      it is the full responsibility of CIL to meet full requirement of coal
      under FSAs even by resorting to import; if necessary. As a follow         E
      up, the FSAs between the CIL/its subsidiaries and the power
      producers will have to be modified through Supplementary
      Agreements.”
       70. It can thus clearly be seen that the CERC has noted that the
non-availability of adequate quantum of coal has posed serious challenge        F
to power generation as reflected in the data compiled by the Central
Electricity Authority (CEA). It further noted that the PLF of the generating
stations across the country has been severely affected for want of
adequate coal supply by CIL/Coal Companies. It further records that to
give effect to the proposal to make CIL supply imported coal on cost            G
plus basis to all power projects commissioned or to be commissioned
during the period from 1st April 2009 to 31st March 2015 and willing to
take such coal, would require appropriate change in the NCDP, as at
present it is the full responsibility of CIL to meet full requirement of coal
under FSAs even by resorting to import, if necessary. It further states
that as a follow up, the FSAs between the CIL/its subsidiaries and the          H
120            SUPREME COURT REPORTS                           [2023] 8 S.C.R.


A     power producers will have to be modified through Supplementary
      Agreements.
            71. After referring to clause 10.1.1 of the Standard PPA for
      Procurement of Power under Case-1 Bidding Procedure, which deals
      with ‘Change in Law’, the statutory advice states thus:
B           “For claiming any benefits under change in law, the Project
            Developer would have to move the appropriate Commission and
            the decision of that Commission in this regard would be final, in
            terms of the provisions of Articles 10.3.3 and 10.3.4 of the Standard
            PPA. The appropriate Commissions are expected to take decisions
C           on the merits of each case including the claims of the Project
            Developers for compensation on account of imported coal after
            consultation with the stakeholders.”
            72. It can thus be seen that the CERC states that for claiming any
      benefits under the Change in Law, the Project Developer would have to
D     move the appropriate Commission. It further records that the appropriate
      Commissions are expected to take decisions on the merits of each case
      including the claims of the Project Developers for compensation on
      account of imported coal after consultation with the stakeholders.
            73. Subsequent to the aforesaid communication, the MoC issued
E     a Press Release on 21st June 2013. It will be relevant to refer to the
      following part of the said Press Release.
            “The Cabinet Committee on Economic Affairs (CCEA) today
            approved the following mechanism for supply of coal to power
            producers:
F           (i) Coal India Ltd. (CIL) to sign Fuel Supply Agreements (FSA)
            for a total capacity of 78000 MW including cases of tapering
            linkage, which are likely to be commissioned by 31.03.2015. Actual
            coal supplies would however commence when long term Power
            Purchase Agreements (PPAs) are tied up.
G           (ii) Taking into account the overall domestic availability and actual
            requirements, FSAs to be signed for domestic coal quantity of 65
            percent, 65 percent, 67 percent and 75 percent of Annual
            Contracted Quantity (ACQ) for the running four years of the
            12th Five Year Plan.
H
MAHARASHTRA STATE ELECTRICITY DISTRIBUTION CO. LTD. v.                      121
    ADANI POWER MAHARASHTRA LTD. [B. R. GAVAI, J.]

      (iii) To meet its balance FSA obligations, CIL may import coal and    A
      supply the same to the willing Thermal Power Plants (TPSs) on
      cost plus basis. TPPs may also import coal themselves. MoC to
      issue suitable instructions.
      (iv) Higher cost of imported coal to be considered for pass through
      as per modalities suggested by CERC. MoC to issue suitable orders     B
      supplementing the New Coal Distribution Policy (NCDP). MoP
      to issue appropriate advisory to CERC/SERCs including
      modifications if any in the bidding guidelines to enable the
      appropriate Commissions to decide the pass through of higher
      cost of imported coal on case to case basis.”
                                                                            C
       74. It is thus clear that taking into account the overall domestic
availability and actual requirements, FSAs were to be signed for domestic
coal quantity of 65%, 65%, 67% and 75% of ACQ for the running/
remaining four years of the 12th Five Year Plan. It can further be seen
that the CCEA has also taken a decision that CIL may import coal to
meet its balance FSA obligations and supply the same to the willing         D
TPPs on cost plus basis. TPPs may also be permitted to import coal
themselves. It further provided that the higher cost of imported coal was
to be considered for pass-through as per the modalities suggested by the
CERC.
      75. In pursuance thereof, the Government of India, through MoC,       E
issued Office Memorandum dated 26th July 2013. The said Office
Memorandum reads thus:
      “Sub:     New Coal Distribution Policy - further instructions
                regarding implementation thereof.
                                                                            F
             The New Coal Distribution Policy (NCDP) was issued vide
      this Ministry’s Office Memorandum NO. 23011/4/2007-CPD
      dated 18.10.2007, laying down the guidelines for distribution and
      pricing of coal to various sectors. As per para 2.2 of the said
      policy, Power Utilities including Independent Power Producer were
      to be supplied 100 per cent of the quantity as per their normative    G
      requirement through Fuel Supply Agreement(s) (FSAs) by Coal
      India Limited (CIL) at fixed prices to be declared/notified by CIL.
      As per para 5.2, in order to meet the domestic requirement, CIL
      was to import coal as required from time to time, if feasible and
      adjust the overall price accordingly.
                                                                            H
122             SUPREME COURT REPORTS                           [2023] 8 S.C.R.


A           2. Government has now approved a revised arrangement for
            supply of coal to the identified Thermal Power Stations (TPPs) of
            78,000 MW capacity commissioned or likely to be commissioned
            during the period from 01.04.2009 to 31.03.2015. Taking into
            account the overall domestic availability and the likely actual
            requirements of these TPPs, it has been decided that FSAs will
B
            be signed for the domestic coal quantity of 65%, 65%, 67% and
            75% of ACQ for the remaining four years of the 12th Plan for the
            power plants having normal coal linkages. Cases of tapering
            linkage would get coal supplies as per the Tapering Linkage Police.
            To meet its balance FSA obligations towards the requirement of
C           the said 78,000 MW TPPs, CIL may import coal and supply the
            same to the willing power plants on cost plus basis. Power plants
            may also directly import coal themselves, if they so opt, in which
            case, the FSA obligations on the part of CIL to the extent of import
            component would be deemed to have been discharged.
D           3. Para 2.2 and 5.2 of the New Coal Distribution Policy issued
            vide OM No. 23011/4/2007-CPD dated 18.10.2007 stand modified
            to the above extent.
            4. The above guidelines will also be applicable to the distribution
            of coal from Singreni Collieries Company Limited (SCCL).
E           5. CIL and its subsidiaries and SCCL are advised to take further
            action accordingly.”
             76. It can thus be seen that the NCDP 2013 also specifically
      states that, as per NCDP 2007 and specifically paragraph 2.2 thereof,
      Power Utilities, including IPPs, were to be supplied 100% of the quantity
F     as per their normative requirement through FSAs by CIL at fixed prices
      to be declared/notified by CIL. It further reiterates that, as per para 5.2,
      in order to meet the domestic requirement, CIL was to import coal as
      required from time to time, if feasible, and adjust the overall price
      accordingly.
G            77. Para 2 of the NCDP 2013 states that the Government has
      now approved a revised arrangement for supply of coal to the identified
      TPPs of 78,000 MW capacity commissioned or likely to be commissioned
      during the period from 1st April 2009 to 31st March 2015. It states that,
      taking into account the overall domestic availability and the likely actual
      requirements of these TPPs, it was decided that FSAs will be signed for
H
MAHARASHTRA STATE ELECTRICITY DISTRIBUTION CO. LTD. v.                       123
    ADANI POWER MAHARASHTRA LTD. [B. R. GAVAI, J.]

the domestic coal quantity of 65%, 65%, 67% and 75% of ACQ for the           A
remaining four years of the 12th Plan for the power plants having normal
coal linkages. It further states that to meet the balance FSA obligations
towards the requirement of the said 78,000 MW TPPs, CIL may import
coal and supply the same to the willing power plants on cost plus basis.
It further states that the power plants may also directly import coal
                                                                             B
themselves, if they so opt, in which case, the FSA obligations on the part
of CIL to the extent of import component would be deemed to have
been discharged.
      78. Immediately thereafter, on 31st July 2013, the MoP addressed
a communication to the Secretary, CERC. It will be relevant to refer to
Para 2 of the said communication, which reads thus:                          C

      “2. After considering all aspects and the advice of CERC in this
      regard, Government has decided the following in June, 2013:
          i)     taking into account the overall domestic availability and
                 actual requirements, FSAs to be signed for domestic         D
                 coal component for the levy of disincentive at the
                 quantity of 65%, 65%, 67% and 75% of Annual
                 Contracted Quantity (ACQ) for the remaining four years
                 of the 12th Plan.
          ii)    to meet its balance FSA obligations, CIL may import         E
                 coal and supply the same to the willing TPPs on cost
                 plus basis. TPPs may also import coal themselves if
                 they so opt.
          iii)   higher cost of imported coal to be considered for pass
                 through as per modalities suggested by CERC.”               F
       79. It can thus clearly be seen that the Government, after
considering all aspects and the advice of CERC in this regard, decided
that the higher cost of imported coal was to be considered for pass-
through as per modalities suggested by the CERC.
    80. It will also be relevant to refer to Para 4 of the said              G
communication, which reads thus:
      “4. As per decision of the Government, the higher cost of import/
      market based e-auction coal be considered for being made a pass
      through on a case to case basis by CERC/SERC to the extent of
      shortfall in the quantity indicated in the LoA/FSA and the CIL         H
124            SUPREME COURT REPORTS                           [2023] 8 S.C.R.


A           supply of domestic coal which would be minimum of 65%, 65%,
            67% and 75% of LoA for the remaining four years of the 12th
            Plan for the already concluded PPAs based on tariff based
            competitive bidding.”
            81. Perusal of para 4 would clearly reveal that the higher cost of
B     import/market based e-auction coal was to be considered for being made
      a pass-through on a case to case basis by CERC/SERC to the extent of
      shortfall in the quantity indicated in the LoA/FSA. It further reiterates
      that CIL may supply domestic coal which would be minimum of 65%,
      65%, 67% and 75% of LoA for the remaining four years of the 12th
      Plan for the already concluded PPAs based on tariff based competitive
C     bidding.
             82. The MoP thereafter vide Resolution dated 28th January 2016
      notified the ‘Tariff Policy’. It will be relevant to refer to clause 6.1 of
      the said Policy, which reads thus:

D           “6.0 GENERATION
                       ………………
            6.1 Procurement of power
            As stipulated in para 5.1, power procurement for future
            requirements should be through a transparent competitive bidding
E
            mechanism using the guidelines issued by the Central Government
            from time to time. These guidelines provide for procurement of
            electricity separately for base load requirements and for peak
            load requirements. This would facilitate setting up of generation
            capacities specifically for meeting such requirements.
F
            However, some of the competitively bid projects as per the
            guidelines dated 19th January, 2005 have experienced difficulties
            in getting the required quantity of coal from Coal India Limited
            (CIL). In case of reduced quantity of domestic coal supplied by
            CIL, vis-a-vis the assured quantity or quantity indicated in Letter
G           of Assurance/FSA the cost of imported/market based e-auction
            coal procured for making up the shortfall, shall be considered for
            being made a pass through by Appropriate Commission on a case
            to case basis, as per advisory issued by Ministry of Power vide
            OM No. FU-12/2011-IPC (Voi-IJI) dated 31.7.2013.”
H
MAHARASHTRA STATE ELECTRICITY DISTRIBUTION CO. LTD. v.                         125
    ADANI POWER MAHARASHTRA LTD. [B. R. GAVAI, J.]

       83. It is thus clear that the Tariff Policy dated 28th January 2016     A
provided that the power procurement for future requirements should be
through a transparent competitive bidding mechanism using the guidelines
issued by the Central Government from time to time. It further provides
the guidelines for procurement of electricity separately for base load
requirements and for peak load requirements. It further notes that some
                                                                               B
of the competitively bid projects as per the guidelines dated 19 th January,
2005 have experienced difficulties in getting the required quantity of
coal from CIL. It further provides that in case of reduced quantity of
domestic coal supplied by CIL vis-à-vis the assured quantity or quantity
indicated in LoA/FSA, the cost of imported/market based e-auction coal
procured for making up the shortfall shall be considered for being made        C
a pass-through by Appropriate Commission on a case to case basis.
This is in pursuance of the advisory issued by Ministry of Power dated
31st July 2013.
      JUDGMENTS CITED
       84. Having considered these documents, we will now consider             D
the judgments which are relied on by both the parties.
        85. In the case of Energy Watchdog (supra), after several rounds
of litigation, the learned APTEL held that generation and sale of power
by Adani Power to GUVNL and Haryana Utilities was a composite
scheme within the meaning of Section 79(1)(b) of the Electricity Act           E
and, therefore, the CERC would have jurisdiction to proceed further in
the matter. It further held that force majeure was made out on the facts
of the said cases and reversed the CERC’s/Commission’s order on that
score. It also held that the Change in Law provisions do not apply to
foreign law and, therefore, changes in Indonesian law did not come within      F
the scope of the provisions. Insofar as changes in Indian law were
concerned, it held that the government policies that were relied upon did
not constitute “law”. The said decision of the learned APTEL was assailed
before this Court. This Court while rejecting the argument on the ground
of force majeure observed thus:
                                                                               G
      “42. It is clear from the above that the doctrine of frustration
      cannot apply to these cases as the fundamental basis of the PPAs
      remains unaltered. Nowhere do the PPAs state that coal is to be
      procured only from Indonesia at a particular price. In fact, it is
      clear on a reading of the PPA as a whole that the price payable
                                                                               H
126            SUPREME COURT REPORTS                            [2023] 8 S.C.R.


A           for the supply of coal is entirely for the person who sets up the
            power plant to bear. The fact that the fuel supply agreement has
            to be appended to the PPA is only to indicate that the raw material
            for the working of the plant is there and is in order. It is clear that
            an unexpected rise in the price of coal will not absolve the
            generating companies from performing their part of the contract
B
            for the very good reason that when they submitted their bids, this
            was a risk they knowingly took. We are of the view that the mere
            fact that the bid may be non-escalable does not mean that the
            respondents are precluded from raising the plea of frustration, if
            otherwise it is available in law and can be pleaded by them. But
C           the fact that a non-escalable tariff has been paid for, for example,
            in the Adani case, is a factor which may be taken into account
            only to show that the risk of supplying electricity at the tariff
            indicated was upon the generating company.”
             86. This Court, thereafter, considered as to whether any Change
D     in Law could be stretched to mean “all laws”. This Court held that Clause
      4.7 read with Clause 5.17 of the Guidelines would reveal that it would
      not include changes in Indonesian law, being foreign and not Indian law.
            87. In Energy Watchdog (supra), this Court also had an occasion
      to consider the MoP communication dated 31st July 2013, the relevant
E     part of which has already been reproduced by us herein above. This
      Court observed thus:
            “56. However, insofar as the applicability of Clause 13 to a change
            in Indian law is concerned, the respondents are on firm ground. It
            will be seen that under Clause 13.1.1 if there is a change in any
F           consent, approval or licence available or obtained for the project,
            otherwise than for the default of the seller, which results in any
            change in any cost of the business of selling electricity, then the
            said seller will be governed under Clause 13.1.1. It is clear from a
            reading of the Resolution dated 21-6-2013, which resulted in the
            letter of 31-7-2013, issued by the Ministry of Power, that the earlier
G           coal distribution policy contained in the letter dated 18-3-2007
            stands modified as the Government has now approved a revised
            arrangement for supply of coal. It has been decided that, seeing
            the overall domestic availability and the likely requirement of power
            projects, the power projects will only be entitled to a certain
H
MAHARASHTRA STATE ELECTRICITY DISTRIBUTION CO. LTD. v.                        127
    ADANI POWER MAHARASHTRA LTD. [B. R. GAVAI, J.]

      percentage of what was earlier allowable. This being the case, on       A
      31-7-2013…..”
      88. This Court, thereafter, referred to the Tariff Policy dated 28th
January 2016, the relevant part of which has already been reproduced
by us herein above. This Court observed thus:
      “57. Both the letter dated 31-7-2013 and the revised Tariff Policy      B
      are statutory documents being issued under Section 3 of the Act
      and have the force of law. This being so, it is clear that so far as
      the procurement of Indian coal is concerned, to the extent that
      the supply from Coal India and other Indian sources is cut down,
      the PPA read with these documents provides in Clause 13.2 that          C
      while determining the consequences of change in law, parties shall
      have due regard to the principle that the purpose of compensating
      the party affected by such change in law is to restore, through
      monthly tariff payments, the affected party to the economic position
      as if such change in law has not occurred. Further, for the operation
      period of the PPA, compensation for any increase/decrease in            D
      cost to the seller shall be determined and be effective from such
      date as decided by the Central Electricity Regulation Commission.
      This being the case, we are of the view that though change in
      Indonesian law would not qualify as a change in law under the
      guidelines read with the PPA, change in Indian law certainly            E
      would.”
      89. It can thus clearly be seen that insofar as the arguments with
regard to effect of the Change in Law being given on the basis of ACQ
is concerned, the same stands specifically rejected.
       90. A bench of three learned Judges of this Court in Adani             F
Rajasthan case (supra) also had an occasion to consider a similar issue.
An argument which is sought to be advanced before us that the Change
in Law claim may be confined only to 35 to 40% was also advanced in
the said case. Rejecting the said contention, this Court observed thus:
      “50. Shri C. Aryama Sundaram argued that the FSA related                G
      approximately 61 per cent of the fuel requirement. Thus, the
      change in law claim may be confined to 35 to 40 per cent. The
      argument cannot be accepted as bidding was not based on dual
      fuel, but was evaluated on domestic coal. There was no such
      stipulation that evaluation of bidding was done on domestic basis;
                                                                              H
128            SUPREME COURT REPORTS                           [2023] 8 S.C.R.


A           the tariff was to be worked out in the aforesaid ratio of 60 : 40 per
            cent of imported coal and domestic coal respectively. Apart from
            that, we find from the order of the APTEL, that change in law
            provision would be limited to a shortfall in the supply of domestic
            linkage coal......
B           51. It was clarified that APRL would be entitled to relief under
            the change in law provision to the extent of shortage in supply in
            domestic linkage coal. Thus, we find no merit in the submission
            raised. We find the findings of the APTEL to be reasonable, proper,
            and unexceptional.”
C           91. In the said case (i.e. Adani Rajasthan case) also, the provision
      with regard to the Change in Law was similar to the one that falls for
      consideration in the present case. This Court observed thus:
             “59. The change in policy and in the terms and conditions
            prescribed for obtaining any consents, clearances and permits or
D           the inclusion of any new terms or conditions for obtaining such
            consents, clearances, and permits are also included. The
            submission raised on behalf of appellant that there is no question
            seeking benefit due to change in foreign law is based on wrong
            factual premise. The relief was not claimed on the basis of change
            in foreign law. Apart from that, admission has been relied upon
E           change in law. The PPA was based on the domestic law and
            there was a change in domestic law. Thus, consequences must
            follow. The Government of Rajasthan entered into a MoU with
            APRL with respect to coal linkage in 2008 to provide coal linkage
            or coal from other sources.
F           60. We find similarity in the present case as well as the Energy
            Watchdog. The factual matrix was similar with the present case.
            We find that the RERC and the APTEL have recorded the
            concurrent finding on facts. We find no ground to interfere. No
            substantial question of law is involved. It was held in Energy
G           Watchdog, that change in law was brought about in the NCDP of
            2007 by the decision of 26.7.2013. It is provided in Article 10.2.1
            how the change in law is to be applied to compensate for the
            impact.”
          92. In the case of Uttar Haryana Bijli Vitran Nigam Limited
      (UHBVNL) (supra), this Court observed thus:
H
MAHARASHTRA STATE ELECTRICITY DISTRIBUTION CO. LTD. v.                           129
    ADANI POWER MAHARASHTRA LTD. [B. R. GAVAI, J.]

       “13. A reading of Article 13 as a whole, therefore, leads to the          A
       position that subject to restitutionary principles contained in Article
       13.2, the adjustment in monthly tariff payment, in the facts of the
       present case, has to be from the date of the withdrawal of
       exemption which was done by administrative orders dated 6-4-
       2015 and 16-2-2016. The present case, therefore, falls within Article
                                                                                 B
       13.4.1(i). This being the case, it is clear that the adjustment in
       monthly tariff payment has to be effected from the date on which
       the exemptions given were withdrawn. This being the case,
       monthly invoices to be raised by the seller after such change in
       tariff are to appropriately reflect the changed tariff. On the facts
       of the present case, it is clear that the respondents were entitled       C
       to adjustment in their monthly tariff payment from the date on
       which the exemption notifications became effective. This being
       the case, the restitutionary principle contained in Article 13.2 would
       kick in for the simple reason that it is only after the order dated 4-
       5-2017 [Adani Power Ltd. v. Uttar Haryana Bijli Vitran Nigam
                                                                                 D
       Ltd., 2017 SCC OnLine CERC 66] that CERC held that the
       respondents were entitled to claim added costs on account of
       change in law w.e.f. 1-4-2015. This being the case, it would be
       fallacious to say that the respondents would be claiming this
       restitutionary amount on some general principle of equity outside
       the PPA. Since it is clear that this amount of carrying cost is only      E
       relatable to Article 13 of the PPA, we find no reason to interfere
       with the judgment of the Appellate Tribunal.
       93. This Court specifically rejected the contention of the DISCOMS
that the Generator was claiming the restitutionary amount on some general
principle of equity outside the PPA. This Court held that the amount of          F
carrying cost was relatable to Article 13 of the PPA.
       STATUTORY PROVISIONS WITH REGARD TO
       REGULATORY MECHANISM
       94. We will now consider the relevant provisions of the Electricity
Act.                                                                             G
      95. Section 70 of the Electricity Act deals with constitution of the
Central Electricity Authority (“CEA”). The CEA shall consist of not
more than 14 Members (including its Chairperson) of whom not more
than 8 are required to be full-time Members to be appointed by the
                                                                                 H
130             SUPREME COURT REPORTS                            [2023] 8 S.C.R.


A     Central Government. It will be relevant to refer to sub-section (5) of
      Section 70 of the Electricity Act, which reads thus:
             “(5) The Members of the Authority shall be appointed from
             amongst persons of ability, integrity and standing who have
             knowledge of, and adequate experience and capacity in, dealing
B            with problems relating to engineering, finance, commerce,
             economics or industrial matters, and at least one Member shall be
             appointed from each of the following categories, namely:—
                    (a) engineering with specialisation in design, construction,
                    operation and maintenance of generating stations;
C                   (b) engineering with specialisation in transmission and supply
                    of electricity;
                    (c) applied research in the field of electricity;
                    (d) applied economics, accounting, commerce or finance.”
D            96. It can thus clearly be seen that the Members of the CEA are
      required to be persons who have adequate experience and capacity in
      dealing with problems relating to engineering, finance, commerce,
      economics or industrial matters. Four of the Members are required to be
      from the categories as mentioned in clauses (a) to (d). One of them has
      to be an engineer with specialization in design, construction, operation
E
      and maintenance of generating stations. One of them has to be an engineer
      with specialization in transmission and supply of electricity; one has to
      be a person who is expert in applied research in the field of electricity;
      one of them has to be an expert in applied economics, accounting,
      commerce or finance.
F
             97. Section 73 of the Electricity Act deals with functions and duties
      of the CEA. The CEA is required to advise the Central Government on
      various matters with regard to generation, transmission, trading,
      distribution and utilization of electricity. It is also required to advise the
      Central Government on any matter on which its advice is sought or
G     make recommendation to that Government on any matter if, in the opinion
      of the CEA, the recommendation would help in improving the generation,
      transmission, trading, distribution and utilization of electricity.
            98. Section 76 of the Electricity Act provides for constitution of
      the CERC. The CERC is a five member body which consists of a
H     Chairperson and three other Members, and the Chairperson of the CEA
MAHARASHTRA STATE ELECTRICITY DISTRIBUTION CO. LTD. v.                         131
    ADANI POWER MAHARASHTRA LTD. [B. R. GAVAI, J.]

who shall be the ex officio Member. A high-level Selection Committee           A
consisting of 6 high officials selects the Members of the CERC and the
learned APTEL.
       99. Section 77 of the Electricity Act provides for qualifications for
appointment of Members of the CERC. Sub-section (1) of Section 77
provides that Chairperson and the Members of the CERC shall be persons         B
having adequate knowledge of, or experience in, or shown capacity in,
dealing with, problems relating to engineering, law, economics, commerce,
finance or management. It further requires that one person to be
appointed must be having qualifications and experience in the field of
engineering with specialization in generation, transmission or distribution
of electricity. One person to be appointed has the qualifications and          C
experience in the field of finance. Clause (c) of sub-section (1) of Section
77 of the Electricity Act requires that two persons are required to have
qualifications and experience in the field of economics, commerce, law
or management. The proviso to sub-section (1) of the Section 77 of the
Electricity Act provides that not more than one Member shall be appointed      D
under the same category under clause (c).
       100. Sub-section (2) of Section 77 of the Electricity Act, which is
a non-obstante clause, empowers the Central Government to appoint
any person as the Chairperson from amongst persons who is, or has
been, a Judge of the Supreme Court or the Chief Justice of a High Court        E
notwithstanding anything contained in sub-section (1). However, such
appointment cannot be made except after consultation with the Chief
Justice of India.
       101. Section 79 of the Electricity Act deals with the functions of
the CERC. One of the functions of the CERC under clause (a) of sub-            F
section (1) of Section 79 is to regulate the tariff of generating companies
owned or controlled by the Central Government. Clause (b) requires it
to regulate the tariff of generating companies other than those owned or
controlled by the Central Government specified in clause (a), if such
generating companies enter into or otherwise have a composite scheme
for generation and sale of electricity in more than one State.                 G
       102. Similarly, Section 82 of the Electricity Act deals with
constitution of a State Commission. Section 83 of the Electricity Act
permits a Joint Commission to be constituted by an agreement between
two or more Governments of States. It also permits the Central
Government to constitute a Joint Commission in respect of one or more          H
132               SUPREME COURT REPORTS                          [2023] 8 S.C.R.


A     Union Territories, and one or more Governments of States. Under Section
      84, the persons to be appointed as the Chairperson and the Members of
      the State Commission are required to have adequate knowledge of, and
      have shown capacity in, dealing with problems relating to engineering,
      finance, commerce, economics, law or management. Sub-section (2) of
      Section 84 of the Electricity Act permits the State Government to appoint
B
      any person as the Chairperson from amongst persons who is, or has
      been, a Judge of a High Court. However, such an appointment can be
      made only after consultation with the Chief Justice of that High Court. A
      high-level Selection Committee under the Chairmanship of a person who
      has been a Judge of the High Court, the Chief Secretary of the concerned
C     State and the Chairperson of the CEA or the Chairperson of the CERC
      selects the Chairperson and the Members of the State Commission.
      Analogous to Section 79, Section 86 of the Electricity Act defines the
      functions of the State Commission. Clause (b) of sub-section (1) of
      Section 86 of the Electricity Act requires the State Commission to regulate
      electricity purchase and procurement process of distribution licensees
D
      including the price at which electricity shall be procured from the
      generating companies or licensees or from other sources through
      agreements for purchase of power for distribution and supply within the
      State.
             103. Section 110 of the Electricity Act provides for establishment
E     of the Appellate Tribunal. Section 111 of the Electricity Act provides for
      appeal to Appellate Tribunal by any person aggrieved by an order made
      by an adjudicating officer under the said Act (except under Section 127)
      or an order made by the Appropriate Commission. Section 112 deals
      with composition of the Appellate Tribunal. It provides that it shall consist
F     of a Chairperson and three other Members. Section 113 provides for
      qualifications for appointment of Chairperson and Members of Appellate
      Tribunal. Only a person who is, or has been a Judge of the Supreme
      Court or the Chief Justice of a High Court is entitled to be the Chairperson
      of the Appellate Tribunal. For being a Member of the Appellate Tribunal,
      following three categories have been provided for:
G
            (i)     A person is, or has been, or is qualified to be, a Judge of a
                    High Court; or
            (ii)    A person is, or has been, a Secretary for at least one year
                    in the Ministry or Department of the Central Government
H                   dealing with economic affairs or matters or infrastructure;
MAHARASHTRA STATE ELECTRICITY DISTRIBUTION CO. LTD. v.                           133
    ADANI POWER MAHARASHTRA LTD. [B. R. GAVAI, J.]

                 or                                                              A
         (iii)   A person is, or has been, a person of ability and standing,
                 having adequate knowledge or experience in dealing with
                 the matters relating to electricity generation, transmission
                 and distribution and regulation or economics, commerce,
                 law or management.                                              B
      104. It can thus be seen that the CEA, CERC and learned APTEL
are bodies consisting of experts in the field.
         CONSIDERATIONS
       105. The issues with regard to SHR and GCV have been                      C
considered by the CERC in its order dated 15th November 2018 in the
case of GMR Warora Energy Limited v. Maharashtra State
Electricity Distribution Company Limited & Anr 8. It will be relevant
to reproduce the relevant part of the CERC’s order dated 15th November
2018, which reads thus:
                                                                                 D
         “29. The submissions regarding SHR and GCV have been
         considered. The APTEL in its judgement dated 12.9.2014 in Appeal
         No. 288 of 2013 (M/s Wardha Power Company Limited V
         Reliance Infrastructure Limited & anr) has ruled that compensation
         under Change in Law cannot be correlated with the price of coal
         computed from the energy charge and the technical parameters            E
         like the Heat Rate and gross GCV of coal given in the bid
         documents for establishing the coal requirement. The relevant
         observations of APTEL are extracted as under:
                 “26. The price bid given by the Seller for fixed and variable
                 charges both escalable and non-escalable is based on the        F
                 Appellant’s perception of risks and estimates of expenditure
                 at the time of submitting the bid. The energy charge as
                 quoted in the bid may not match with the actual energy
                 charge corresponding to the actual landed price of fuel.
                 The seller in its bid has also not quoted the price of coal.
                                                                                 G
                 Therefore, it is not correct to co-relate the compensation
                 on account of Change in Law due to change in cess/excise
                 duty on coal, to the coal price computed from the quoted
                 energy charges in the Financial bid and the heat rate and
8
    Petition No.88/MP/2018
                                                                                 H
134      SUPREME COURT REPORTS                           [2023] 8 S.C.R.


A           Gross Calorific value of Coal given in the bidding documents
            by the bidder for the purpose of establishing the coal
            requirement. The coal price so calculated will not be equal
            to the actual price of coal and therefore, compensation for
            Change in Law computed on such price of coal will not
            restore the economic position of the Seller to the same level
B
            as if such Change in Law has not occurred.”
      30. In the light of the above observations, the technical parameters
      such as Heat Rate and GCV of coal as per the bidding document
      cannot be considered for deciding the coal requirement for the
      purpose of calculating the relief under Change in law. Therefore,
C     the submissions of the Respondent, MSEDCL to consider the bid
      parameters are not acceptable. The Respondent has also relied
      on MERC order with regard to GCV. As regards SHR, it was
      also suggested by MERC that net SHR as submitted in the bid or
      SHR norms specified for new thermal stations as per MYT
D     Regulations, whichever is superior, shall be applicable. In our view,
      the decision in the said order has been given in the facts of the
      case and does not have any binding effect in case of the projects
      regulated by this Commission. Moreover, the SHR given in the
      bid are under test conditions and may vary from actual SHR. The
      Commission after extensive stakeholders consultation has
E     specified the SHR norms in the 2014 Tariff Regulations. Therefore,
      it would be appropriate to take SHR specified in the Regulations
      as a reference point instead of other parameters as suggested by
      MSEDCL.
      31. In the present case, the Petitioner has considered SHR of
F     2355 kcal/Kwh whereas, the Respondent MSEDCL has
      considered the Design Heat Rate of 2211 kcal/kWh as submitted
      in the RFP. It is pertinent to mention that the CERC norms
      applicable for the period 2009-14 and 2014-19 do not provide the
      norms for 300 MW units, but provide for a degradation factor of
G     6.5% and 4.5% respectively towards Heat Rate over and above
      the Design Heat Rate. As the Design Heat Rate is 2211 kcal/
      kWh, the gross Heat Rate works out to 2355 kcal/kWh (2211 x
      1.065)and 2310 kcal/kWh (2211 x 1.045) for the period 2009- 14
      and 2014-19 respectively. Accordingly, we direct that the SHR of
      2355 kcal/kWh during the period 2009-14 and 2310 kcal/kwh during
H
MAHARASHTRA STATE ELECTRICITY DISTRIBUTION CO. LTD. v.                       135
    ADANI POWER MAHARASHTRA LTD. [B. R. GAVAI, J.]

      the period 2014- 19 or the actual SHR whichever is lower, shall        A
      be considered for calculating the coal consumption for the purpose
      of compensation under change in law. The Petitioner and the
      Respondent MSEDCL are directed to carry out reconciliation on
      account of these claims annually.
      32. In case of GCV, the Respondent has submitted that it should        B
      be mid value of GCV band which should be applied on GCV
      measured on ‘as billed’ basis. In our view, on account of the grade
      slippage of the coal supplied by CIL, it would not be appropriate
      to consider GCV on ‘as billed’ basis. In the 2014 Tariff Regulations
      of the Commission, the measurement of GCV has been specified
      as on ‘as received’ basis. Therefore, it will be appropriate if the    C
      GCV on ‘as received’ basis is considered for computation of
      compensation for Change in law.”
        106. The CERC has referred to the judgment of the learned
APTEL dated 12th September 2014 in Appeal No. 288 of 2013 in the
case of M/s Wardha Power Company Limited v. Reliance                         D
Infrastructure Limited & anr. wherein the learned APTEL has held
that it is not correct to co-relate the compensation on account of Change
in Law due to change in cess/excise duty on coal to the coal price
computed from the quoted energy charges in the financial bid and the
heat rate and GCV of coal given in the bidding documents by the bidder       E
for the purpose of establishing the coal requirement. The learned APTEL
has held that the coal price so calculated will not be equal to the actual
price of coal and therefore, compensation for Change in Law computed
on such price of coal will not restore the economic position of the seller
to the same level as if such Change in Law had not occurred.
                                                                             F
        107. The CERC has further found that the SHR given in the bid
are under test conditions and may vary from actual SHR. The CERC
has specifically observed that after extensive stakeholders’ consultation,
the CERC has specified the SHR norms in the 2014 Tariff Regulations.
It, therefore, found that it will be appropriate to take SHR specified in
the Regulations as a reference point instead of other parameters as          G
suggested by MSEDCL.
       108. The CERC further found that the CERC norms applicable to
the period 2009-14 and 2014-19 do not provide the norms for 300 MW
units, but provide for a degradation factor of 6.5% and 4.5% respectively
                                                                             H
136            SUPREME COURT REPORTS                          [2023] 8 S.C.R.


A     towards Heat Rate over and above the Design Heat Rate. The CERC
      found that since the Design Heat Rate was 2211 kcal/kWh, the gross
      Heat Rate worked out to 2355 kcal/kWh (2211 x 1.065) and 2310 kcal/
      kWh (2211 x 1.045) for the period 2009-14 and 2014-19 respectively.
      The CERC, therefore, directed that the SHR of 2355 kcal/kWh during
      the period 2009-14 and 2310 kcal/kwh during the period 2014-19 or the
B
      actual SHR, whichever is lower, shall be considered for calculating the
      coal consumption for the purpose of compensation under the Change in
      Law.
            109. These findings of the CERC are affirmed by the learned
      APTEL in its Judgment dated 16th July 2021. The learned APTEL
C     observed thus:
                   “8.8 We are in agreement with the observations made by
                   the CERC. Relegating the Appellant to the contractual
                   remedy under the FSA when the genesis of the Appellant’s
                   claim is Change in Law under the PPA would not be
D                  appropriate. It is, however, made clear that if the Appellant
                   were to receive any disincentive or compensation from the
                   coal company on account of short supply or grade slippage,
                   such compensation will be adjusted/credited against the
                   Change in Law compensation payable by the Respondent,
E                  MSEDCL.”
             110. The learned APTEL in its judgment dated 14th September
      2020 in Appeal No.182 of 2019 in the case of Adani Power Maharashtra
      Limited (APML) v. Maharashtra State Electricity Distribution
      Company Ltd. (impugned in Civil Appeal No. 684 of 2021) has referred
F     to the order of MERC dated 7th March 2018 in Case No.123 of 2017
      (JSW Energy Ltd. v. MSEDCL), wherein it held that Auxiliary
      Consumption has to be considered as lower of actual or MYT norms for
      the purpose of the Change in Law compensation. The learned APTEL
      held that in view of its earlier order, the State Commission, being MERC,
      ought to have followed the same approach for SHR in the present case
G     also. It has been found that there is no reason for the MERC to apply
      two different principles for Auxiliary Consumption and SHR, when both
      are operational parameters and the Commission was dealing with the
      same PPA in both cases.
            111. The learned APTEL has also referred to the following
H     observations of the CERC in its order dated 16th May 2019 in the case
MAHARASHTRA STATE ELECTRICITY DISTRIBUTION CO. LTD. v.                        137
    ADANI POWER MAHARASHTRA LTD. [B. R. GAVAI, J.]

of GMR Warora Energy Limited v. MSEDCL and Anr. (Petition                     A
No.284/MP/2018):
          “52.   It is pertinent to mention that similar submissions of the
                 Respondent, MSEDCL were considered by the
                 Commission in Petition No.88/MP/2018 and it was
                 observed by order dated 15.11.2018 that SHR given in         B
                 the bid is under test conditions and may vary from actual
                 SHR. Therefore, it would only be correct to take SHR
                 specified in the tariff Regulations as a reference
                 point instead of other parameters suggested by
                 MSEDCL. It was also held that SHR as a bidding
                 document cannot be considered for deciding the coal          C
                 requirement for the purpose of calculating relief under
                 change in law…”
                                                     [emphasis supplied]
       112. The learned APTEL thereafter held that the SHR submitted          D
in the bid was not a bid parameter as per the bidding guidelines. It
concurred with the findings of the CERC that the SHR specified in the
Tariff Regulations was as a reference point. It held that it cannot be
used as the basis for computing the coal shortfall requirement and,
thereby, for computation of Change in Law compensation to be awarded
to the generating company. It held that such linking of Change in Law         E
compensation to the SHR mentioned in the bid documents would not
restitute the affected party to the same economic position as if the
approved Change in Law event had not occurred.
       113. Insofar as the GCV is concerned, the CERC in the case of
GMR Warora Energy Limited (supra) has specifically rejected the               F
contention of the MSEDCL that the GCV should be taken at the mid
value of GCV band which should be applied on GCV measured on ‘as
billed’ basis. The CERC held that, on account of the grade slippage of
the coal supplied by CIL, it would not be appropriate to consider GCV
on ‘as billed’ basis. It has been held that in the 2014 Tariff Regulations    G
of the Commission, the measurement of GCV has been specified as on
‘as received’ basis. Therefore, it will be appropriate if the GCV on ‘as
received’ basis is considered for computation of compensation for the
Change in Law. This finding of the CERC is affirmed by the learned
APTEL.
                                                                              H
138            SUPREME COURT REPORTS                          [2023] 8 S.C.R.


A            114. The learned APTEL in the case of Adani Power
      Maharashtra Limited (APML) (supra) has also considered the issue
      as to whether the reference GCV of domestic coal supplied by CIL for
      computing the Change in Law compensation should be “the middle value
      of GCV range of assured coal grade in LoA/FSA/MoU”. The learned
      APTEL observed that it was a fact that there is no guidance in the
B
      PPAs or in the bidding Guidelines as to the reference GCV that should
      be applied in case of the Change in Law claims in Case 1 bid projects
      where SHR or GCV is not a bid parameter. It, however, held that the
      overarching principle for Change in Law compensation was that the
      generating company should not be left with in a worse economic position.
C     It held that the GCV ‘as received’ should be the appropriate basis to
      assess the quantum of shortfall in domestic coal and calculate the Change
      in Law compensation accordingly.
             115. It is also relevant to note that the Comptroller and Auditor
      General of India (“C&AG” for short), in its Performance Audit Report
D     on “Fuel Management of Coal Based Power Stations of NTPC Limited”
      submitted to MoP, had observed that the ‘quality assessment of coal has
      inherent as well as manmade infirmities due to heterogeneous nature of
      coal and sampling errors’. The C&AG, therefore, recommended to the
      MoP that there was a need to appropriately review the methods for
      energy pricing and had requested the MoP to coordinate with CERC in
E     light of the audit findings. The MoP, therefore, addressed a communication
      dated 28th June 2017 to the CEA. In the said communication, the MoP
      had stated that the NTPC has highlighted the issues of sampling error on
      account of change of point of sampling for measurement of GCV from
      “as fired” to “as received” basis as per the 2014 Tariff Regulations,
F     non-homogeneous nature of samples taken from the wagons, loss of
      GCV from point of “as received” to the point of “as fired”, and difficulty
      with coal sampling through ‘Augurs’. It further states that the MoP had
      also sought views of the CERC on the said issue. The CERC had,
      therefore, requested the MoP for consulting CEA in this regard and
      accordingly the matter was referred to CEA.
G            116. The CEA in its communication dated 17th October 2017 stated
      thus:
             “The issue has been examined in CEA. After preliminary
             discussions with NTPC on the issue on 05.09.2017, CEA has also
             taken views of other specialist agencies in the field of coal such
H            as CIMFR and CPRI in the meeting held on 21.09.2017.
MAHARASHTRA STATE ELECTRICITY DISTRIBUTION CO. LTD. v.                         139
    ADANI POWER MAHARASHTRA LTD. [B. R. GAVAI, J.]

    It is acknowledged that there is a loss of GCV from point of “as           A
    received” to the point of “as fired” inside a power plant mainly
    due to following factors:
    (i)     Effect of Moisture in GCV of coal sample taken from
            Wagon Top
            As stated by C&AG, there are sampling errors on account            B
            of heterogeneous nature of coal. This issue was deliberated
            in detail with CIMFR and CPRI. Both CIMFR and CPRI
            acknowledged the difference in wagon top-bottom GCV
            due to heterogeneous nature of coal, tendency of moisture
            to settle at the bottom and exposure of top layer to               C
            atmosphere.
            CEA is of the view that GCV measurement of wagon top
            coal will give comparatively higher GCV value due to
            steeling of moisture at the bottom of the wagon and loss of
            moisture from wagon top during transportation of coal,             D
            however, loss in GCV will vary as per seasonal variations.
    (ii)    Loss in GCV during coal storage inside power plant
            CEA is of the view and also substantiated by many national
            and international papers that there is a loss of GCV in the
            coal stock where coal is stored inside the power plant, mainly     E
            due to oxidation and weathering effect. Further, most of
            the losses in GCV during long storage of coal takes place
            in the initial period of storage, mostly due to loss in volatile
            content.
    (iii)   Reduction in GCV during handling inside power plant                F
            C&AG in its Performance Audit Report has observed that
            GCV of coal progressively decreased from ‘as billed’ stage
            to ‘as fired’ stage.
            It is acknowledged that there are minor unavoidable losses
            inside the power plant in handling the coal starting from          G
            unloading point to the point of bunkering. Loss in GCV may
            occur mainly due to dust suppression measures used around
            coal conveyors and transfer points, loss in volatile matter
            during crushing of the coal etc.
                                                                               H
140               SUPREME COURT REPORTS                           [2023] 8 S.C.R.


A              CEA has also examined the views taken by various state regulators
               for considering such loss for the purpose of tariff allowed to
               generators. However, as the margin would vary from plant to
               plant, season to season and varying coal characteristics, CEA is
               of the opinion that a margin of 85-100 kcal/kg for a non-pit head
               station may be considered as a loss of GCV measured at wagon
B
               top till the point of firing of coal in boiler.”
            117. Vide Corrigendum dated 18th October 2017, in the last
      sentence, after the words wagon top, the words “at unloading point”
      were added.

C             118. The aforesaid advice was given by the CEA after holding
      meeting on 21st September 2017 with specialist agencies in the field of
      coal such as CIMFR and CPRI. It has also examined the views taken
      by various state regulators for considering such loss for the purpose of
      tariff allowed to generators. While considering at what point of time the
      margin may be considered as a loss of GCV, the CEA considered the
D     views of all the stakeholders. It, thereafter, opined that the loss of GCV
      should be measured at wagon top till the point of firing of coal in boiler.
             119. As already discussed herein above, the CEA is an independent
      body having Members who are experts in various fields related to
      electricity generation, transmission, finance, etc.
E            120. It could thus be seen that two expert bodies i.e. the CERC
      and the learned APTEL have concurrently held, after examining the
      material on record, that the factors of SHR and GCV should be considered
      as per the Regulations or actuals, whichever is lower. The CERC as
      well as the State Regulatory bodies, after extensive consultation with
F     the stakeholders, had specified the SHR norms in respective Tariff
      Regulations. In addition, insofar as GCV is concerned, the CEA has
      opined that the margin of 85-100 kcal/kg for a non-pit head station may
      be considered as a loss of GCV measured at wagon top till the point of
      firing of coal in boiler.
             121. In this respect, we may refer to the following observations
G
      of this Court in the case of Reliance Infrastructure Limited v. State of
      Maharashtra and others9.
               “38. MERC is an expert body which is entrusted with the duty
               and function to frame regulations, including the terms and conditions
      9
          (2019) 3 SCC 352
H
MAHARASHTRA STATE ELECTRICITY DISTRIBUTION CO. LTD. v.                            141
    ADANI POWER MAHARASHTRA LTD. [B. R. GAVAI, J.]

         for the determination of tariff. The Court, while exercising its         A
         power of judicial review, can step in where a case of manifest
         unreasonableness or arbitrariness is made out. Similarly, where
         the delegate of the legislature has failed to follow statutory
         procedures or to take into account factors which it is mandated
         by the statute to consider or has founded its determination of tariffs
                                                                                  B
         on extraneous considerations, the Court in the exercise of its power
         of judicial review will ensure that the statute is not breached.
         However, it is no part of the function of the Court to substitute its
         own determination for a determination which was made by an
         expert body after due consideration of material circumstances.
         39. In Assn. of Industrial Electricity Users v. State of                 C
         A.P. [Assn. of Industrial Electricity Users v. State of A.P., (2002)
         3 SCC 711] a three-Judge Bench of this Court dealt with the
         fixation of tariffs and held thus : (SCC p. 717, para 11)
            “11. We also agree with the High Court [S. Bharat
            Kumar v. State of A.P., 2000 SCC OnLine AP 565 : (2000) 6             D
            ALD 217] that the judicial review in a matter with regard to
            fixation of tariff has not to be as that of an appellate authority
            in exercise of its jurisdiction under Article 226 of the
            Constitution. All that the High Court has to be satisfied with is
            that the Commission has followed the proper procedure and             E
            unless it can be demonstrated that its decision is on the face of
            it arbitrary or illegal or contrary to the Act, the court will not
            interfere. Fixing a tariff and providing for cross-subsidy is
            essentially a matter of policy and normally a court would refrain
            from interfering with a policy decision unless the power
            exercised is arbitrary or ex facie bad in law.”                       F

      122. As already discussed herein above, various expert bodies
including the CERC and the learned APTEL, after taking into
consideration various relevant factors, have decided the issue with regard
to SHR and GCV. Not only that, but another expert body i.e. CEA has
also advised that GCV value has to be taken not only on ‘as received’             G
but on ‘as fired’ basis.
      123. Recently, the Constitution Bench of this Court in the case of
Vivek Narayan Sharma v. Union of India10 has held that the Courts
10
     2023 SCC OnLine SC 1
                                                                                  H
142             SUPREME COURT REPORTS                              [2023] 8 S.C.R.


A     should be slow in interfering with the decisions taken by the experts in
      the field and unless it is found that the expert bodies have failed to take
      into consideration the mandatory statutory provisions or the decisions
      taken are based on extraneous considerations or they are ex facie
      arbitrary and illegal, it will not be appropriate for this Court to substitute
      its views with that of the expert bodies.
B
              124. That leaves us with the third issue as to whether the MERC
      was correct in holding that, for the purpose of Change in Law
      compensation, shortfall in domestic linkage coal shall be assessed by
      considering the coal supply as the maximum of (1) actual quantum of
      coal offered for offtake by CIL under the LoA/FSA and (2) the minimum
C     assured quantum in NCDP 2013 for the respective year.
              125. Undisputedly, vide the NCDP 2007, insofar as the power
      utilities including IPPs/CPPs and Fertilizer Sector are concerned, the
      MoC had assured 100% of the quantity as per the normative requirement
      of the consumers for supply of coal, through FSA by CIL at fixed prices
D     to be declared/notified by CIL. The units/power plants, which were yet
      to be commissioned but whose coal requirements has already been
      assessed and accepted by the MoC and linkage/LoA approved as well
      as future commitments, were also to be covered by the said Policy. Para
      5.2 of the NCDP 2007 also provided that in order to meet the domestic
      requirement of coal, CIL may have to import coal as may be required
E     from time to time, if feasible. The CIL was to adjust its overall price
      accordingly. There was an unequivocal assurance given that it will be
      the responsibility of CIL/Coal Companies to meet full requirement of
      coal under FSAs even by resorting to imports, if necessary.
              126. However, in 2013, on account of the limited availability of
F     coal, the MoC had indicated that CIL may not be in a position to supply
      more than 60 to 65% of ACQ. The Union of India, therefore, realised
      that PPAs which are already concluded between the developers and the
      DISCOMS as a result of competitive bidding in the last few years based
      on domestic coal linkage (LoA) may have to use imported coal to bridge
      the shortage of domestic coal in order to fulfill their contractual obligations.
G             127. The CCEA considered the issue and decided that the higher
      cost of imported coal will be allowed as a pass-through. This is evident
      from the communication dated 9th May 2013 addressed by the MoP to
      the CERC.
              128. The CERC also considered the issue. It noted that it was the
H     full responsibility of CIL to meet full requirement of coal under FSAs
MAHARASHTRA STATE ELECTRICITY DISTRIBUTION CO. LTD. v.                       143
    ADANI POWER MAHARASHTRA LTD. [B. R. GAVAI, J.]

even by resorting to import, if necessary. After referring to the Change     A
in Law clause, the CERC, in its advice dated 20th May 2013, stated that
for claiming any benefit under Change in Law, the Project Developer
would have to move the appropriate Commission and the appropriate
Commissions are expected to take decisions on the merits of each case
including the claims of the Project Developers for compensation on
                                                                             B
account of imported coal. Such decisions were required to be taken
after consultation with the stakeholders.
       129. The Government of India through MoP, in its Press Note
dated 21st June 2013, published the decision of the CCEA which clearly
provided that the higher cost of imported coal was to be considered for
pass-through as per the modalities suggested by CERC.                        C
       130. The MoP, thereafter, addressed a communication dated 31st
July 2013 to the Secretary, CERC specifically pointing out the decision
of the CCEA to the effect that the higher cost of imported coal was to
be considered for pass-through as per the modalities suggested by CERC.
The communication states that, as per the decision of the Government,        D
the higher cost of import/market based e-auction coal will have to be
considered for being made a pass-through on a case to case basis by
CERC/SERC to the extent of shortfall in the quantity indicated in the
LoA/FSA.
       131. The Tariff Policy dated 28th January 2016 issued by the MoP      E
in paragraph 6.1 also specifically notes this position and states that, in
case of reduced quantity of domestic coal supplied by CIL vis-à-vis the
assured quantity or quantity indicated in LoA/FSA, the cost of imported/
market based e-auction coal procured for making up the shortfall shall
be considered for being made a pass-through by the Appropriate
Commission.                                                                  F
        132. Undisputedly, in the case of Energy Watchdog (supra) as
well as in Adani Rajasthan case (supra) this Court has held that on
account of the Change in Law, the generating companies were entitled
to compensation so as to restore the party to the same economic position
as if such Change in Law had not occurred. Had the Change in Law not         G
occurred, the generating companies would have been entitled to the supply
as assured by the CIL/Coal Companies under the FSA.
      133. It is contended by the DISCOMS that in the case of Energy
Watchdog (supra), this Court has specifically held that the doctrine of
force majeure was not applicable if there was an unexpected rise in the      H
144            SUPREME COURT REPORTS                          [2023] 8 S.C.R.


A     price of coal and, as such, it will not absolve the generating companies
      from performing their part of the contract. It is submitted that when the
      bidders submitted their bids, this was a risk they knowingly took. We
      find the said submission to be without substance. The generators are not
      claiming compensation on the basis of rise in price of coal or on the
      ground of force majeure. Their claims, in fact, are on the basis of the
B
      Change in Law, which this Court, in the case of Energy Watchdog
      (supra) as well as in Adani Rajasthan case (supra), has upheld on the
      ground of Change in Law.
             134. The contention of the DISCOMS that the Adani Rajasthan
      case (supra) is not applicable to the facts of the present case inasmuch
C     as in Adani Rajasthan case (supra), the State of Rajasthan had assured
      100% coal supply and that it was not a case of FSA, is, in our considered
      view, without substance. In the present case also, the NCDP 2007 had
      assured 100% fuel/coal supply of the normative value.
            135. The restitutionary principle has been stated by this Court in
D     the case of Uttar Haryana Bijli Vitran Nigam Limited (UHBVNL)
      (supra) thus:
            “10. Article 13.2 is an in-built restitutionary principle which
            compensates the party affected by such change in law and which
            must restore, through monthly tariff payments, the affected party
E           to the same economic position as if such change in law has not
            occurred. This would mean that by this clause a fiction is created,
            and the party has to be put in the same economic position as if
            such change in law has not occurred i.e. the party must be given
            the benefit of restitution as understood in civil law. ………….”
F           136. Undisputedly, the claim of APML stands on the basis of the
      Change in Law. The DISCOMS, which are instrumentalities of the State,
      cannot be expected to argue contrary to the stand of the Government,
      which clearly provides that the generators would be entitled to pass-
      through for the coal required to be imported or purchased from the open
G     market on the ground of Change in Law.
            137. Shri M.G. Ramachandran, learned Senior Counsel has also
      made a submission that though the Change in Law event is dated 31st
      July 2013, the learned APTEL has erred in giving effect to the same
      from 1st April 2013. In this respect, it is to be noted that the Change in
      Law has been made applicable to the remaining four years of the 12 th
H
MAHARASHTRA STATE ELECTRICITY DISTRIBUTION CO. LTD. v.                         145
    ADANI POWER MAHARASHTRA LTD. [B. R. GAVAI, J.]

Plan for power plants. The MERC, in the case of APML, as well as the           A
CERC, in the case of GMR, has given effect to the Change in Law for
the last four financial years beginning from the Financial Year 2013-
2014. The financial year begins from 1st of April of every year. Apart
from that, from the perusal of the orders passed by the learned APTEL
in both the matters, it is clear that no such challenge was made before
                                                                               B
the learned APTEL, and, even in the present appeals, there is ground to
this effect in the Memo of Appeals. Only oral submissions have been
sought to be made in that regard.
       138. In view of the concurrent orders of the authorities with regard
to the date on which the Change in Law compensation is to be given, we
see no reason to entertain such a plea, which does not have a foundation       C
in the pleadings.
        139. Another contention raised on behalf of the DISCOMS is that
if the generators are permitted to claim compensation on the basis of
actual SHR or the SHR as per the Regulations, whichever is lower, it
will permit them to take advantage of their inefficiency. It is submitted      D
that lesser the SHR, greater the efficiency of the machine and, therefore,
higher the generation of electricity. Per contra, when the machine is
inefficient, the SHR is higher and the electricity generation is lower. The
SHR is not only dependent on the efficiency of the machine but on
various other factors. One of the other factors is the PLF. In this respect,   E
it will be relevant to refer to the statutory advice issued by the CERC on
20th May 2013, the relevant part of which has already been reproduced
hereinabove. It clearly states that for want of adequate coal supply by
CIL/Coal Companies, the PLF of the generating stations across the
country has been severely affected. As such, the contention in that regard,
in our considered view, is without substance.                                  F

       140. Apart from that, it appears that various DISCOMS are taking
self-contradictory stands. In Petition No. 97 of 2017 between M/s Adani
Power Limited v. Uttar Haryana Bijli Vitran Nigam Ltd. & Anr., the
DISCOMS have filed an affidavit stating thus:
                                                                               G
      “a.    While deciding the relief on account of Change in Law under
             Article 13 of the PPA may be pleased to consider improved
             efficiency parameters in line with CERC Tariff Regulations
             such that the impact on consumers of the Respondents in
             minimal in nature.
                                                                               H
146        SUPREME COURT REPORTS                           [2023] 8 S.C.R.


A     b.     Any relief (if granted), may be passed after considering
             the following significant observations:
             (i)    The actual impact of the said period should be
                    calculated on the basis of various factors namely the
                    quantum of requirement on normative procedures
B                   such as the following:
                    i.     Station Heat Rate shall be considered after
                           ascertaining actual design heat rate and
                           margin as per CERC regulations from time
                           to time.
C                   ii.    Similarly, Auxiliary Consumption shall be
                           considered as per CERC regulations.
                    iii.   GCV of alternate coal shall be as certified
                           by Third Party Sampling Agency for which
                           the Hon’ble Commission should provide
D                          appropriate the guideline.
                    iv.    The targeted PLF;
                    v.     The accurate date of actual coal utilized by
                           the Petitioner on a monthly and yearly basis;
E                   vi.    The quantity of coal offered by the MCL which
                           was rejected or not taken by the Petitioner;
                    vii.   The quantum of actual of electricity generated
                           by the Petitioner
                           Thus, it is submitted that the Petitioner’s claim
F                          for relief in this regard requires to be computed
                           in a categorical and systematic manner taking
                           the above parameters into consideration. The
                           Petitioner’s computation as stated in its petition
                           is therefore liable to be rejected as it is general
G                          and vague in nature.
             (ii)   Further, the Petitioner has indicated the impact limited
                    to the past period only. However, the Respondents
                    humbly request the Hon’ble Commission to only
                    approve such claims for the past period, after
H
MAHARASHTRA STATE ELECTRICITY DISTRIBUTION CO. LTD. v.                           147
    ADANI POWER MAHARASHTRA LTD. [B. R. GAVAI, J.]

                     considering the above along with a formula for the          A
                     future period.”
                                                      [emphasis supplied]
       141. It can thus be seen that the DISCOM-UHBVNL has itself
stated that improved efficiency parameters in line with CERC Tariff
Regulations should be considered for deciding the relief on account of           B
Change in Law, such that the impact on consumers of the respondents is
minimal in nature. It has also requested for any relief, if granted, to take
into consideration the SHR after ascertaining actual design heat rate
and margin as per CERC regulations from time to time. Similarly, it has
also requested that Auxiliary Consumption be considered as per the CERC          C
Regulations. Insofar as the GCV of alternate coal is concerned, it has
further stated that it has to be certified by Third Party Sampling Agency.
      142. It is not in dispute that the SHR is required to be audited
continuously and the GCV has to be certified by a Third Party Sampling
Agency.                                                                          D
       143. It is further pertinent to note that the MERC itself in its order
dated 7th March 2018 in Case No.123 of 2017 (JSW v. MSEDCL),has
taken a totally contradictory stand. It will be relevant to refer to paragraph
19.11 of the said order dated 7th March 2013, which reads thus:
       “19.11     In view of the above, financial impact of Change in            E
                  Law on the auxiliary consumption to restore the
                  generator to the same economic position as if such
                  Change in Law has not occurred is allowed. The
                  Change in Law shall be applicable on auxiliary
                  consumption of the Unit as per the Norms laid down             F
                  by the Commission or actual, whichever is less since
                  the tariff of the project is based on Competitive
                  Bidding the auxiliary power consumption
                  considered is not known. However this auxiliary
                  consumption should be at a normative value
                  corresponding to Scheduled generation only.                    G
                  Moreover, this Change in Law with respect to
                  auxiliary consumption shall not include power
                  consumption for staff colonies of the generating
                  station.”
                                                      [emphasis supplied]        H
148                SUPREME COURT REPORTS                           [2023] 8 S.C.R.


A            144. It is, thus, difficult to appreciate as to how the MERC, in one
      case, has taken a view that Change in Law on the Auxiliary Consumption
      has to be as per the Norms laid down by the Commission or actual,
      whichever is less, when it has rejected the same in the case of APML in
      the order dated 7th March 201811.
B            145. We may gainfully refer to the stand taken by the Union of
      India in the case of Energy Watchdog (supra), which reads thus:
                “15. The learned Attorney General appearing on behalf of the
                Union of India, submitted before us that he was not interested in
                the ultimate outcome of the appeals before us. He was only
                appearing in order to apprise us that the electricity sector,
C
                having been privatised, has largely fulfilled the object sought
                to be achieved by the 2003 Act, which is that electricity
                generation, being delicensed, should result in production of
                far greater electricity than was earlier produced. He urged
                us not to disturb the delicate balance sought to be achieved by
D               the Act i.e. that producers or generators of electricity, in order
                that they set up power plants, be entitled to a reasonable
                margin of profit and a reasonable return on their capital, so
                that they are induced to set up more and more power plants.
                This must be consistent with competitiveness among them, which
                then translates itself into reasonable tariffs that are payable by
E               consumers of electricity. For this purpose, he relied strongly upon
                Section 3 of the Electricity Act, which states that the Central
                Government, shall from time to time, prepare a National Electricity
                Policy and a tariff policy in consultation with the State
                Governments, and the authority for development of the power
                system, based on optimal utilisation of natural resources.
F
                According to him, the National Electricity Policy and Tariff
                Policy that are issued from time to time, being statutory in
                nature, are binding on all concerned. This is, in fact, further
                recognised by Section 61(i) by which the appropriate Commission,
                in specifying terms and conditions for determination of tariffs,
G               shall be guided by the National Electricity Policy and Tariff Policy.
                The Central Government’s role can further be seen even in
                Section 63, where guidelines that are binding on all are issued
                by the Central Government in cases where there is a
                transparent process of bidding.
      11
           Passed in Case Nos. 189 of 2013 and 140 of 2014
H
MAHARASHTRA STATE ELECTRICITY DISTRIBUTION CO. LTD. v.                         149
    ADANI POWER MAHARASHTRA LTD. [B. R. GAVAI, J.]

      16. Further, according to the learned Attorney General, Section          A
      79(4) also points in the same direction, stating that, in discharge of
      its functions, the Central Commission shall be guided by the National
      Electricity Policy, National Electricity Plan, and tariff policy
      published under Section 3. He also referred us to the Cabinet
      Committee for Economic Affairs recognising the overall
                                                                               B
      shortfall in manufacture of domestic coal and the new coal
      distribution policy issued in July 2013 pursuant to the Cabinet
      Committee which, according to him, are in the nature of
      binding directions making it clear that as generators of
      electricity, who depend upon indigenous coal, have been given
      less coal than was anticipated, should be allowed either to              C
      import the coal themselves, or purchase imported coal from
      Coal India Ltd., with the difference in price being passed
      through to them. He further referred to and relied upon the revised
      tariff policy of 28-1-2016 for the same purpose.”
                                                    [emphasis supplied]        D
       146. The submissions made by the learned Attorney General have
to be construed in reference to the purpose for which the Electricity Act
came to be enacted. Prior to the Electricity Act coming into effect, matters
with regard to generation, transmission, distribution and supply of
electricity were governed by three enactments, viz., the Indian Electricity    E
Act, 1910, the Electricity (Supply) Act, 1948 and the Electricity Regulatory
Commission Act, 1998. The Electricity (Supply) Act, 1948 mandated the
creation of a State Electricity Board. However, it was found that over a
period of time, the performance of the said Electricity Boards had
deteriorated on account of various factors. As such, it was found
necessary to enact a new legislation to meet various challenges. The           F
statement of objects and reasons would reveal that one of the main
features for enactment of the Electricity Act was delicensing of
generation and freely permitting captive generation. As such, the learned
Attorney General, in the case of Energy Watchdog (supra), stated that
the electricity sector, having been privatized, had largely fulfilled the      G
object sought to be achieved by the Electricity Act. After the enactment
of the Electricity Act, delicensed electricity generation resulted in
production of far greater electricity than was earlier produced. The
learned Attorney General had further urged the Court not to disturb the
delicate balance sought to be achieved by the Electricity Act, i.e. that
                                                                               H
150             SUPREME COURT REPORTS                             [2023] 8 S.C.R.


A     producers or generators of electricity, in order that they set up power
      plants, be entitled to a reasonable margin of profit and a reasonable
      return on their capital, so that they are induced to set up more and more
      power plants.
              147. It is further to be noted that, though it was sought to be
B     contended in the case of Energy Watchdog (supra) that in a case under
      Section 63 of the Electricity Act, the Commission was only to adopt a
      tariff as determined through a transparent process of bidding, this Court
      rejected the said contention. It held that, in fact, Sections 62 and 63 of
      the Electricity Act deal with ‘determination’ of tariff, which is part of
      ‘regulating’ tariff. It further held in a situation where the guidelines issued
C     by the Central Government under Section 63 cover the situation, the
      Central Commission is bound by those guidelines and must exercise its
      regulatory functions.
            148. It would be relevant to refer to clause 4.7 of the guidelines
      issued by the Union of India, which have been held to be binding in the
D
      case of Energy Watchdog (supra), which reads thus:
             “Clause 4.7. (amended)
               Any change in law impacting cost or revenue from the business
             of selling electricity to the procurer with respect to the law
E            applicable on the date which is 7 days before the last date for
             RFP bid submission shall be adjusted separately. In case of any
             dispute regarding the impact of any change in law, the decision of
             the appropriate Commission shall apply.”
            149. The judgment of this Court in the case of Energy Watchdog
F     (supra) has been approved by a three Judge Bench of this Court in
      Adani Rajasthan case (supra).
             150. In spite of this legal position and the stand taken by the Union
      of India, the DISCOMS are taking a stand which is contrary to the stand
      of the Union of India. In Energy Watchdog (supra), it was also sought
G     to be urged by DISCOMS that even on account of Change in Law,
      adjustments would not be permissible, which contention was outrightly
      rejected. We have come across a number of matters wherein concurrent
      orders passed by the Regulatory Body and the Appellate Forum are
      assailed. Such a litigation would, in fact, efface the purpose of the
H     Electricity Act. As already discussed herein above, one of the major
MAHARASHTRA STATE ELECTRICITY DISTRIBUTION CO. LTD. v.                          151
    ADANI POWER MAHARASHTRA LTD. [B. R. GAVAI, J.]

reasons for the enactment of the Electricity Act was the deterioration in       A
performance of the State Electricity Boards.
       151. In that view of the matter, we find that the stand taken by the
DISCOMS that, since the loss being sustained by the generating
companies is on account of non-fulfillment of obligation by CIL/Coal
Companies, they should be relegated to the remedy available to them in          B
law against the CIL/Coal Companies, is totally unreasonable. The claim
is based on change of NCDP 2007 by NCDP 2013, which, undisputedly,
is covered by the term ‘Change in Law’.
      152. Recently, this Court, in the case of Central Warehousing
Corporation v. Adani Ports Special Economic Zone Limited                        C
(APSEZL) and others 12, has deprecated the practice of different
instrumentalities of the State taking contradictory/different positions/
stands on the same issue.
       153. In the present case, the learned APTEL has also held that
SHR and GCV has to be taken into consideration as per the ‘actual’ or           D
the Tariff Regulations, whichever is lower and as such, balanced the
interests of generators as well as consumers.
      154. That leaves us to deal with the additional point raised in the
case of GMR (i.e. Civil Appeal No.6927 of 2021).
                                                                                E
       155. The CERC, apart from its finding on SHR and GCV, has
also directed late payment surcharge to be paid. The same has been
affirmed by the learned APTEL. The CERC as well as the learned
APTEL, on the interpretation of Articles 8.3.5 and 8.8.3 of the PPA,
have concurrently found that the procurer had delayed the payment by
not making the payment within the due date and, as such, GMR was                F
entitled to late payment surcharge. We find no reason to interfere with
the said concurrent findings of fact.
       156. We, therefore, find no merit in the appeals. The appeals are
dismissed. There shall be no order as to costs. Pending application, if
any, shall stand disposed of.                                                   G

Bibhuti Bhushan Bose                                       Appeals dismissed.
(Assisted by : Pranjal Singh and Rahul Rathi, LCRAs)


12
     2022 SCC OnLine SC 1398                                                    H


Search Indian case law

Ask in plain English, not just keywords. 25,000 AI words free, no card.

Try "Power Purchase Agreement"Sign in to search

For a digitally signed copy suitable for filing, refer to the court's own website. Only the court can issue one.