Created byFuzzy Cloud

Supreme Court of India

NATIONAL HIGHWAY AUTHORITY OF INDIAversusM/S. GANGA ENTERPRISES AND ANR.

Citation
2003 INSC 434
Decided
28 August 2003
Disposal
Appeal(s) allowed

Holding

Forfeiture of the bid security is valid; an on‑demand bank guarantee is a separate contract that can be enforced even if the underlying contract is not concluded, and such disputes are contractual and not within the jurisdiction of Article 226.

Summary

The National Highways Authority of India (NHAI) issued a tender for toll collection requiring a bid security of Rs 50 lakh in the form of an on‑demand bank guarantee, which could be forfeited if the bidder withdrew his bid within the 120‑day validity period. Ganga Enterprises submitted the bid, became the highest bidder, but withdrew the bid on 20 Nov 1997 before the validity expired. NHAI accepted the bid on 21 Nov 1997, but since the bidder had withdrawn, the performance security was not furnished and the agreement was not signed; consequently NHAI encashed the bank guarantee. Ganga Enterprises filed a writ petition for refund of the forfeited amount, which the Delhi High Court allowed, holding that an offer could be withdrawn before acceptance and that forfeiture was void. The Supreme Court reversed this, ruling that forfeiture of the bid security was valid because the bank guarantee is a separate contract of guarantee that can be enforced irrespective of the existence of an underlying contract, and that such contractual disputes are not maintainable under Article 226. The writ petition was dismissed.

Issues considered

  • Whether the forfeiture of bid security on withdrawal of a bid before acceptance is permissible under the Indian Contract Act.
  • Whether a dispute arising from the forfeiture of bid security is maintainable under Article 226 of the Constitution.
  • Whether an on‑demand bank guarantee can be enforced irrespective of the existence of an underlying contract.

Legislation cited

Subjects

tenderbid securitybank guaranteeforfeitureon‑demand guaranteecontract of guaranteewithdrawal of offerArticle 226contractual disputeNHAIgovernment contract

Judgment

A             NATIONAL HIGHWAY AUTHORITY OF INDIA
                                        v.
                     MIS. GANGA ENTERPRISES AND ANR.

                               AUGUST 28, 2003

B                    [S.N. VARIAVA AND H.K. SEMA, JJ.]

         Contract:

        Tender-Forfeiture of bid security-Bidders required to furnish bid
C security and performance security-Bid SPcurity to be forfeited if bidder
  withdrew his bid during period of bid validity-Respondent gave his bid/
  offer and furnished bank guarantee for bid security-Later, when he came
  to be highest bidder, withdrew his bid before expiry of period of bid
  validity-Appellant encashed the bank guarantee-Writ petition by
  respondent for refund of amount allowed by High Court-Held, by
D invoking the bank guarantee and/or enforcing the bid security, there is no
  statutory right, exercise of which was being fettered-There is no term in
  the contract which is contrary to the provisions of the Contract Act-The
  Contract Act merely provides that a person can withdraw his offer before
  its acceptance-But withdrawal of an offer, before it is accepted, is a
E completely different aspect from forfeiture ofearnest/security money which
  has been given for a particular purpose-A person may have a right to
  withdraw his offer but if he has made his offer on a condition that some
  earnest money will be forfeited for not entering into contract or if some
  act is not performed, then even though he may have a right to withdraw
F his offer, he has no right to claim that the earnest/security be returned to
  him-Forfeiture of such earnest/security, in no way, affects any statutory
  right unde1 .. 1e Contract Act-Such earnest/security is given and taken to
  ensure that a contract comes into existence-In government contracts, such
  a term is always included in order to ensure that only a genuine party
G makes a bid
          Contract-Contract of guarantee-Tender-Bid security by way of
    bank guarantee-Forfeiture of on withdrawal of bid during period of bid
    validity-A contract of guarantee is a complete and separate contract by
    itself-The law regarding enforcement of an "on demand bank guarantee"
H   is very clear-If the enforcement is in terms of the guarantee, then Courts
                                       114
          NATIONAL HJGHWAY AUTHORITY OF INDIA v. GANGA ENTERPRISES     115

    must not interfere with the enforcement of bank guarantee-The existence A
    or non-existence of an underlying contract become irrelevant when the
    invocation is in terms of the bank guarantee-The bank guarantee
    stipulated that if the bid was withdrawn within 120 days or if the
    performance security was not given or if an agreement was not signed, the
    guarantee could be enforced-The bank guarantee was enforced because B
    the bid was withdrawn within 120 days-Therefore, it could not be said
    that the invocation ofthe bank guarantee was against the terms of the bank
    guarantee-If the guarantee was rightly invoked, there was no question of
    directing refund-Bank guarantee-Courts' power to interferewith.

         Constitution of India, 1950:                                         c
         Articles 226 and 299-Contractual disputes-Writ petition-
    Maintainability of-Tender-Forfeiture of bid security-Writ petition for
    refand of amount allowed by High Court-Held, disputes relating to
    contracts cannot be agitated under Article 226-The dispute in this case   D
    was regarding the terms of offer-It was thus a contractual dispute in
    respect of which a writ court was not the proper forum.

         Kera/a State Electricity Board v. Kurien E. Kalathil, (2000) 6 SCC
    293; State of V.P. v. Bridge & Roof Co. (India) Ltd, (1996) 6 sec 22      E
'
    and B.D.A. v. Ajai Pal Singh, (1989) 2 SCC 116, relied on.

         Verigamto Naveen v. Government of A.P., (2001) 8 SCC 344 and
    Harminder Singh Arora v. Union of India, (1986) 3 SCC 247, held
    inapplicable.
                                                                              F
         CIVIL APPELLATE JURlSDICTION : Civil Appeal No. 4123 of
    1999.

         From the Judgment and Order dated 30.10.98 of the Delhi High Court
    in C.W.P. No. 739 of 1998.
                                                                              G
         Mukul Rohatgi, Raju Ramachandran, Additional Solicitor Generals,
    Dushyant Dave, Sanjeev Sachdeva and Ms. Priya Puri, Mrs. Niranjan
    Singh, Mrs. Anil Katiyar, Lakshmi Raman Singh, Kamal Mohan Gupta,
    Mrs. Rita Choudhary, Manish Kumar and Sunil Kumar Jain for the
    apearing parties.                                                         H
    116                   SUPREME COURT REPORTS (2003] SUPP. 3 S.C.R.

A         The following Order of the Court was delivered :

         This appeal is against the Judgement of the High Court of Delhi dated
    30th October, 1998.

          Briefly stated, the facts are as follows :
B
          The Appellant issued a tender notice calling for tenders for collection
    of toll on a portion of the highway running through Rajasthan. The last
    date of submission of bid was 31st July, 1997. It was also provided that
    toll plazas would be got completed by the authority and handed over to
C   the selected enterprise. There was two types of securities to be furnished,
    one being a bid security in an amount of Rs. 50 lakhs (Rupees fifty lakhs
    only). The other was a performance security by way of a bank guarantee
    of Rs. 2 Crores (Rupees Two crores only). Clauses 7.1 to 8 deal with bid
    security. They read as under :-
D
             "7. Bid Security.

             7. I. The bidder shall furnish, as a part of his bid, a Bid Security
             in an amount of Rs. 50 Lakhs (Rupees Fifty Lakhs only), or an
             equivalent amount in a freely convertible currency. The Bid
E            Security shall, at the bidder's opinion, be in the form of a Bank
             Draf, or Guarantee from a Bank located in India. The Bank
             Guarantee shall be in the Form of Bank Guarantee for Bid
             Security included herein, valid of 150 days after the last date for
             submission of the bid.
F
             7.2. A bid not accomoanied by an acceptable bid security shall
             be rejected by National Highways Authority of India as non-
             responsive.


G            7.3. The Bid Security of unsuccessful bidders will be returned by
             National Highways Authority of India as promptly as possible but
             not later than 30 days after the expiratio;i of the period of bid
             validity.

             7.4. The Bid Security of the successful bidder will be returned
H
      NATIONAL HIGHWAY AUTHORITY OF INDIA r. GANGA ENTERPRISES            117

         by National Highways Authority oflndia soon after the bidder has        A
         furnished the required Performance Security.

         7.5. The Bid Security may be forfeited :

         (a)   if the bidder withdraws his bid during the period of bid
               validity; or                                                      B
         (b)   in case the successful bidder fails within the specified period
               to

               (i)   furnish the required Performance Security; and

               (ii) sign the Agreement.
                                                                                 c
         8.    Bid Validity.

             Bid shall remain valid for a period of 120 days after the last
         date of bid submission."                                                D
Thus, it is to be seen that the bid security of Rs. 50 lakhs was not for
performance of the contract. It was in essence an earnest to be given to
ensure that the bidder did not withdraw his bid during the period of bid
validity and/or that after acceptance the performance security is furnished
and the Agreement signed. The other terms pertained to the anticipated           E
contract for collection of toll. It must be mentioned that the bid validity
period was 120 days.

      In terms of this tender document the Respondent gave his bid or offer.
The offer/bid was in terms of the tender and thus it was also in two parts.      F
The first part being an offer that the bid would not be withdrawn during
the bid validity period and/or that on acceptance the performance security
would be furnished and the Agreement signed. The second part of the offer
dealt with the terms and conditions pertaining to the performance of the
contract of collection of tolls, ifthe offer was accepted. As earnest/security
for performance (of the first part of the offer) the Respondent along with       G
his bid furnished a bank guarantee in a sum ofRs .. 50 Lakhs as bid security.
The bank guarantee furnished was a "on demand guarantee" which
specifically provided that the bank guarantee could be enforced "on
demand" if the bidder withdraws his bid during the period of bid validity
or if the bidder, having beeen notified of the acceptance of his bids, fails     H
    118                    SUPREME COURT REPORTS [2003] SUPP. 3 S.C.R.

A to furnish the performance security or fails to sign the Agreement. The
    amount of the Bank? Guarantee was to be paid by the bank without demur
    on the written demand merely stating that one of these conditions had been
    fulfilled. The moment the bank guarantee was given and accepted by the
    Appellants the first portion of the offer, regarding bid security, stood
B   accepted. Of course, this did not mean that a competed contract in respect
    of the work of toll collection had come into existence.

         It is an admitted position that 120 days would have come to an end
    of 28th November, 1997. In August the technical bids were opened. In
    September the financial bids were opened, wherein it was found that the
C   Respondent was the highest bidder.

         On 20th November, 1997 the Respondent withdrew his bid i.e. he
  ·withdrew his bid before the expiry of 120 days. On 21st November, 1997,
   the Appellants accepted the offer of the Respondent. However, as the
D Respondent had withdrawn his bid the performance guarantee was not
   furnished and the Agreement was not entered into. The Appellants thus
   encashed the bank guarantee for Rs. 50 lakhs.

          The Respondent then filed a Writ Petition in the High Court, for
E refund of the amount. On the pleadings before it, the High Court raised
    two questions viz. {a) whether the forfeiture of security deposit is without
    authority of law and without any binding contract between the parties and
    also contrary to Section 5 of the Contract Act and (b) whether the writ
    petition is maintainable in a claim arising out of a breach of contract.
    Question (b) should have been first answered as it would go to the root
F   of the matter. The High Court instead considered question (a) and then
    chose not to answer question (b). In our view, the answer to question (b)
    is clear. It is settled law that disputes relating to contracts cannot be agitated
    under Article 226 of the Constitution of India. It has been so held in the
    cases of Kera/a State Electricity Board v. Kurien E. Ka/athil reported in
G   [2000] 6 sec 293, State ofU.P. v. Bridge & Roof Co. (India) Ltd. reported
    in (1996) 6 SCC 22 and B.D.A. v. Ajai Pal Singh reported in (1989) 2 SCC
    116. This is settled law. The dispute in this case was regarding the terms
    of offer. They were thus contractual disputes in respect of which a Writ
    Court was not the proper forum. Mr. Dave however relied upon the cases
H   of Verigamto Naveen v. Government ofA.P. reported in [200 l] 8 sec 344
       NATIONAL HIGHWAY AUTHORITY OF INDIA v. GANGA ENTERPRISES          119

and Harminder Singh Arora v. Union of India reported in [1986] 3 SCC            A
247. These however are cases where the Writ Court was enforcing a
statutory right or duty. These cases do not lay down that a Writ Court can
interfere in a matter of contract only. Thus on the ground of maintainability
the Petition should have been dismissed.

      By the impugned Judgment the Writ Petition has been allowed. The          B
High Court holds that the offer was withdrawn before it was accepted and
thus no completed contract had come into existence. The High Court holds
that in law it is always open to a party to withdraw its offer before its
acceptance. To this proposition there can be no quarrel. We therefore did
not permit Mr. Dave to cite authorities for the proposition that an offer can   C
be withdrawn before it is accepted.

         The Court, however, then goes on to hold as under :

              "The statutory right having been so exercised, the fetter
         imposed by the clause to the contrary in the tender documents and D
         the bank guamatee could not override the provisions of the Indian
         Contract Act. Any clause in so far as it is contrary of comes in
         conflict with the provisions of the Indian Contract Act is inoperative
         and void and connot be enforced. To have an enforceable contract
         there must be an offer and unconditional acceptance. A person E
         who makes an offer has the right of withdrawing it before
         acceptance. Until the offer is accepted unconditionally it creates
         no legal right and the bid can be withdrawn at any time. Once it
         is held that there is no completed contract between the parties no
         further question can arise. There can be no breach of contract. F
         There is no statutory rule or an act whenunder the security deposit
         in the form of a bank guarantee could be claimed by the
         respondent No. 2. The position may, however, be different ifthere
         is a statutory rule having force of law precluding withdrawal of
         a bid before its acceptance. The petitioner was entitled to withdraw G
         the bid because the prohibition against withdrawal does not have
         the force of law and there was no consideration to bind him down
         to the condition. In the present case there was no acceptance by
         respondent No. 2 on the date of withdrawal of the bid by the
         petitioner. In the circumstances the invocation and encashment of
         the bank guarantee is illegal and void and is liable to be set aside." H
    120                  SUPREME COURT REPORTS (2003) SUPP. 3 S.C.R.
A       In our view, the High Court fell in error in so holding. By invoking
  the bank guarantee and/or enforcing the bid security, there is no statutory
  right, exercise of which was being fettered. There is no term in the contract
  which is contrary to the provisions of the Indian Contract Act. The Indian
  Contract Act merely provides that a person can withdraw his offer before
B its acceptance. But withdrawal of an offer, before it is accepted, is a
  completely different aspect from forfeiture of earnest/security money
  which has been given for a particular purpose. A person may have a right
  to withdraw his offer but if he has made his offer on a condition that some
  earnest money will be forfeited for not entering into contract or if some
  act is not performed, then even though he may have a right to withdraw
C his offer, he has no right to claim that the earnest/security be returned to
  him. Forfeiture of such earnest/security, in no way, affects any statutory
  right under the Indian Contract Act. Such earnest/security is given and
  taken to ensure that a contract comes into existence. It would be an
  anomalous situation that a person who, by his own conduct, precludes the
D coming into existence of the contract is then given advantage or benefit
  of his own wrong by not allowing forfeiture. It must be remembered that,
  particularly in government contracts, such a term is always included in
  order to ensure that only a genuine party makes a bid. If such a term was
  not there even a person who does not have the capacity or a person who
E has no intention of entering into the contract will make a bid. The whole
  purpose of such a clause i.e. to see that only genuine bids are received
  would be lost if forfeiture was not permitted.

        There is another reason why the impugned Judgment cannot be
F sustained. It is settled Jaw that a contract of guarantee is a complete and
  separate contract by itself. The Jaw regarding enforcement of an "on
  demand bank guarantee" is very clear. If the enforcement is in terms of
  the guarantee, then Courts must not interfere with the enforcement of bank
  guarantee. The Court can only interfere if the invocation is against terms
  of the guarantee or if there is any fraud. Courts cannot restrain invocation
G of an "on demand guarantee" in accordance with its terms by looking at
  terms of the underlying contract. The existence or non-existence of an
  underlying contract become irrelevant when the invocation is in terms of
  the bank guarantee. The bank guarantee stipulated that if the bid was
  withdrawn within 120 days or if the performance security was not given
H or if an Agreement was not signed, the guarantee could be enforced. The
           NATIONAL HIGHWAY AUTHORITY OF INDIA v. GANGA ENTERPRISES         121
    bank guarantee was enforced because the bid was withdrawn within 120 A
    days. Therefore, it could not be said that the invocation of the bank

-   guarantee was against the tenns of the bank guarantee. If it was in tenns
    of the bank guarantee, one fails to understand as to how the High Court
    could say that the guarantee could not have been invoked. If the guarantee
    was rightly invoked, there was no question of directing refund as has been B
    done by the High Court.

          Mr. Dave submitted that the Respondent had no option· but to
    withdraw his offer as the Appellants had not completed the toll plazas. He
    pointed out that the period of the contract was to be from !st October, 1997
    to 30th September, 1999. He submitted that even though the contract, if        C
    accepted, was to commence from I st October 1997, the Appellants had not
    accepted the offer till 20th November, 1997 and thus Respondent had to
    withdraw his offer. He submitted that it has come on record that the toll
    plazas were not completed till March, 1998. He submitted that the
    Respondent was forced to withdraw his offer because of the inaction/           D
    negligence on the part of the Appellant. He submitted that under these
    circumstances Respondent shold not be penalized by forfeiture of his
    deposit. We are unable to accept this submission. The Bid security was
    given to meet a specific contingency viz. non-withdrawal of the offer within
    120 days. The contingency having arisen, Appellants were entitled to           E
    forfeit. It may only be mentioned that in the proposed Agreement there
    is a clasue which provides that if therre is a delay on the part of the
    Appellants, which results in delay in the work of collection of toll, the
    amount payable by the Respondent would be reduced pro-rata. Thus by
    reason of the delay Respondent would not have suffered. Also Respondent
    was well aware that 120 days would end on 28th November, 1997. Thus            F
    the Respondent was aware when he gave his offer, that acceptance could
    be delayed till 28th November, 1997. Thus non-acceptance till 20th
    November, 1997 was not a ground would justify action of Respondent in
    withdrawing his offer.
                                                                                   G
         In this view of the matter, the impugned Judgment is set aside. The
    Appeal is accordingly allowed. The Writ Petition of the Respondents shall
    stand dismissed. There will be no order as to costs.

    R.P.                                                      Appeal allowed.


)


Search Indian case law

Ask in plain English, not just keywords. 25,000 AI words free, no card.

Try "tender"Sign in to search

For a digitally signed copy suitable for filing, refer to the court's own website. Only the court can issue one.