Created byFuzzy Cloud

Supreme Court of India

NATIONAL HIGHWAY AUTHORITY OF INDIAversusT. YOUNIS & ANR.

Citation
2026 INSC 616
Decided
2 June 2026
Disposal
Appeal(s) allowed

Holding

The limitation period under Section 34(3) of the Arbitration and Conciliation Act, 1996 begins to run from the date the arbitral tribunal disposes of a Section 33 application, irrespective of whether that application is ultimately allowed or dismissed.

Summary

The National Highway Authority of India (NHAI) sought arbitration under the National Highways Act for compensation relating to land acquisition, resulting in an arbitral award on 03‑02‑2022. Both parties filed applications under Section 33 of the Arbitration and Conciliation Act, 1996, which were dismissed by the arbitrator on 04‑07‑2022; the certified order was received by NHAI on 15‑09‑2022. NHAI then filed applications under Section 34 of the same Act on 07‑11‑2022, seeking to set aside the award, and obtained condonation of delay from the trial court. The High Court held that the limitation period under Section 34(3) could not be computed from the disposal of the Section 33 applications and dismissed the applications as time‑barred. The Supreme Court clarified that the limitation under Section 34(3) starts from the date the arbitral tribunal disposes of a Section 33 application, regardless of the outcome of that application, and restored the condonation order. Consequently, the High Court's judgment was set aside and the appeal was allowed.

Issues considered

  • From which date does the limitation period under Section 34(3) of the Arbitration and Conciliation Act, 1996 commence – the date of the original award or the date of disposal of a Section 33 application?
  • Whether only a maintainable or successful application under Section 33 can defer the commencement of the limitation period under Section 34(3).

Legislation cited

Headnote

Issue for Consideration Whether the limitation u/s.34(3) of the Arbitration and Conciliation Act, 1996 would commence from the date of the original award or from the date on which the application u/s.33 came to be disposed of. Headnotes† Arbitration and Conciliation Act, 1996 – ss.33, Act, 1956 – ss.3A(1), 3G(1) – Acquisition of land by the Central Government – The Competent Authority determined the compensation – Appellant invoked Arbitration u/s.3G(1) – The Arbitrator passed an Award on 03.2.2022 by granting the benefit of ss.23(1- A), 23(2),

Subjects

Section 34(3) of the Arbitration and Conciliation Act, 1996Section 33 of the Arbitration and Conciliation Act, 1996Section 3G of the National Highways Act, 1956Limitation PeriodCommencement of LimitationTime-Barred ChallengeEnhancement of CompensationExtension of LimitationLand Acquisition Proceedings

Judgment

            [2026] 7 S.C.R. 11 : 2026 INSC 616

           National Highway Authority of India
                            v.
                     T. Younis & Anr.
                 (Civil Appeal No. 8388 of 2026)
                           02 June 2026
[Pamidighantam Sri Narasimha and Alok Aradhe, JJ.]


                      Issue for Consideration
 Whether the limitation u/s.34(3) of the Arbitration and Conciliation
 Act, 1996 would commence from the date of the original award or
 from the date on which the application u/s.33 came to be disposed of.

                             Headnotes†
 Arbitration and Conciliation Act, 1996 – ss.33, 34 – National
 Highways Act, 1956 – ss.3A(1), 3G(1) – Acquisition of land
 by the Central Government – The Competent Authority
 determined the compensation – Appellant invoked Arbitration
 u/s.3G(1) – The Arbitrator passed an Award on 03.2.2022 by
 granting the benefit of ss.23(1- A), 23(2), 28 and s.34 of the
 Land Acquisition Act, 1894 – Both Appellant and Respondent
 no.1 filed separate applications u/s.33, which were dismissed
 by the Arbitrator by a common order dated 04.07.2022 – The
 certified copy of the said order was received by the Appellant
 on 15.09.2022 – Appellant filed applications u/s.34 of the
 Act along with applications seeking condonation of delay –
 Respondent no.1 raised an objection – The Principal District &
 Sessions Judge condoned the delay in filing the applications
 u/s.34 of the Act – Respondent no.1 challenged the same
 by filing a writ petition – The High Court concluded that the
 benefit of limitation u/s.34(3) of the Act was not available and,
 therefore, the limitation could not be computed from the date
 of disposal of such applications – Consequently, the arbitration
 applications were dismissed – Correctness:
 Held: The issue involved in the instant appeal is no longer
 res integra – It is settled that for the purposes of computation
 of limitation u/s.34(3) of the Act, it is the date of disposal of the
 application u/s.33 of the Act that would earmark the starting point
 of limitation for filing an application u/s.34 of the Act – A plain
12                                                             [2026] 7 S.C.R.

                           Supreme Court Reports


      reading of s.34(3), read in the light of the law laid down in Geojit,
      makes it clear that once jurisdiction u/s.33 is formally invoked
      and such proceedings are entertained by the Arbitral Tribunal,
      the limitation for filing an application u/s.34 would commence only
      from the date on which such request is disposed of by the Arbitral
      Tribunal – In the facts of the present case, it is not in dispute
      that the certified copy of the common order dated 04.07.2022
      disposing of the applications u/s.33 was received by the Appellant
      on 15.09.2022 and that the applications u/s.34 were thereafter
      filed on 07.11.2022 – Thus, even reckoning limitation from the
      date of receipt of the order disposing of the applications u/s.33,
      the applications u/s.34 of the Act were instituted within the period
      contemplated u/s.34(3) of the Act – Therefore, the contention
      of the Respondent that the applications u/s.34 of the Act were
      barred by limitation does not merit acceptance – Accordingly, the
      impugned judgment and order dated 22.01.2024 passed by the
      High Court is set aside – The orders dated 05.08.2023 passed
      by the Principal District and Sessions Judge condoning the delay
      in filing the applications u/s.34 of the Act, are restored – The
      applications u/s.34 of the Act, to be decided on their own merits,
      in accordance with the law. [Paras 18-20]

                               Case Law Cited
      State of Arunachal Pradesh v. Damani Construction Co. [2007] 3
      SCR 416 : (2007) 10 SCC 742; Geojit Financial Services Ltd. v.
      Sandeep Gurav, 2025 INSC 1021 : [2025] 8 SCR 1427; Ved
      Prakash Mithal and Sons v. Union of India, 2018 SCC OnLine
      SC 3181; USS Alliance v. State of U.P., 2023 SCC OnLine SC
      778 – referred to.

                                 List of Acts
      Arbitration and Conciliation Act, 1996; National Highways Act,
      1956; Land Acquisition Act, 1894.

                              List of Keywords
      Section 34(3) of the Arbitration and Conciliation Act, 1996; Section
      33 of the Arbitration and Conciliation Act, 1996; Section 3G of the
      National Highways Act, 1956; Limitation Period; Commencement of
      Limitation; Time-Barred Challenge; Enhancement of Compensation;
      Extension of Limitation; Land Acquisition Proceedings.
[2026] 7 S.C.R.                                                         13

           National Highway Authority of India v. T. Younis & Anr.


                                     Case Arising From
      CIVIL APPELLATE JURISDICTION: Civil Appeal No. 8388 of 2026
      From the Judgment and Order dated 22.01.2024 of the High Court
      of Karnataka Circuit Bench at Dharwad in WP No. 105176 of 2023

                                 Appearances for Parties
      Advs. for the Appellant(s):
      Ms. Pinky Anand, Sr. Adv., Tarun Dua, Sumit Gupta, Ms. Saudamini
      Sharma, Akshay Kumar Tiwari, Ms. Tanya Shrotriya, Venkita
      Subramoniam T.R.
      Advs. for the Respondent(s):
      Sushil Kumar Jain, Sr. Adv., Anandakumar A Magadum, Darpan
      Km, Ms. Amrita Sharma, Rajat Jonathan Shaw, Ajay Magadum,
      Ms. Easha Chandhok, Prashant Upadhyay, Ms. Mahima Sadawat,
      Sidharth Jain, Ms. Rashi Bansal.

                     Judgment / Order of the Supreme Court

                                           Judgment

1.    Leave granted.
2.    The present appeal arises from the judgment and order dated
      22.01.2024, passed by the High Court of Karnataka, Dharwad
      Bench, (“High Court”) by which the writ petition1 preferred by the
      Respondents was allowed. By the said order, the High Court, set
      aside the order dated 05.08.2023 passed by the Principal District
      and Sessions Judge, Bellary, whereby delay in filing the applications
      under Section 34 of the Arbitration and Conciliation Act, 1996 (“the
      Act”) was condoned.
3.    Facts leading to filing of this appeal are that on 15.12.2009, the
      Ministry of Shipping, Road Transport and Highways issued a
      preliminary notification under Section 3A(1) of the National Highways
      Act, 1956, (‘1956 Act’) for acquisition of land in Bellary District.
      The said notification included the land belonging to Respondent
      No.1 as well. By a declaration dated 14.12.2010 issued under



1    Writ Petition No. 105176 of 2023 (GM-RES).
14                                                             [2026] 7 S.C.R.

                                    Supreme Court Reports


       Section 3D(2), the land vested in the Central Government free from
       all encumbrances. The competent authority by an Award dated
       05.12.2011, determined the compensation under Section 3G(1) of
       the 1956 Act.
4.     The Appellant invoked the remedy of Arbitration under Section 3G(5)
       of the 1956 Act. The Deputy Commissioner-Cum-Arbitrator, Bellary
       (Arbitrator) vide Award dated 16.02.2013, redetermined the market
       value of agricultural land at the rate of Rs.362/- per sq. metre, whereas
       the market value of the non-agricultural land was assessed at Rs.741/-
       per sq. metre. The High Court by an order dated 16.03.2019 set
       aside the Arbitral Award dated 16.02.2013 and remitted the matter
       to the Arbitrator for de novo consideration.
5.     Pursuant to the remand, the Arbitrator conducted fresh proceedings
       and passed an Award on 03.2.2022 by granting the benefit of Section
       23(1-A), 23(2), 28 and Section 34 of the Land Acquisition Act, 1894
       (1894 Act). On 08.03.2022, the Appellant filed application under
       Section 33(1)(a) of the Act before Arbitrator seeking correction of
       Arbitral Award, inter alia on the ground that grant of additional market
       value under Section 23 and interest under Section 34 of the 1894 Act
       is not legally sustainable. On 10.03.2022, the Respondent No.1 filed
       an application under Section 33(4) of the Act seeking an additional
       award of 50% over and above the market value on the ground that
       such a claim had been raised during the Arbitral Proceeding, but the
       same was omitted in the final Award. The Arbitrator by a common
       order dated 04.07.2022, dismissed the applications filed under
       Section 33 of the Act by the Appellant as well as Respondent No.1.
       The certified copy of the said order was received by the Appellant
       on 15.09.2022.
6.     On 29.10.2022, the Appellant filed applications under Section 34 of
       the Act along with applications seeking condonation of delay2. The
       Respondent No. 1 raised an objection contending that the applications
       under Section 34 of the Act were filed with delay which was beyond
       the condonable period of delay of 120 days, as provided, in proviso
       to Section 34(3) of the Act. The Principal District & Sessions Judge,
       Bellary by an order dated 05.08.2023 condoned the delay in filing the
       applications under Section 34 of the Act and allowed the same. The


2     Arbitration Application Nos. 3/2022 and 4/2022.
[2026] 7 S.C.R.                                                               15

            National Highway Authority of India v. T. Younis & Anr.


      Respondent No.1 challenged the aforesaid order dated 05.08.2023
      in a Writ Petition3.
7.    The High Court by a judgment and order dated 22.01.2024, held
      that Section 33(1) (a) of the Act permits correction of computation,
      clerical or typographical errors or errors of similar nature. It was further
      held that the prayer made in the application filed by the Appellant
      seeking modification of the Arbitral Award did not fall within the
      purview of Section 33(1)(a) of the Act and hence the same was not
      maintainable. The High Court concluded that the benefit of limitation
      under Section 34(3) of the Act was not available and, therefore,
      the limitation could not be computed from the date of disposal of
      such applications. Consequently, the arbitration applications4 were
      dismissed. Aggrieved by the judgment of the High Court, the Appellant
      has filed the present appeal.
8.    We have heard Ms. Pinky Anand, learned senior counsel appearing
      for the Appellant and Mr. Sushil Kumar Jain, learned senior counsel
      appearing for the Respondent.
9.    The learned senior counsel appearing for the Appellant submitted
      that both the parties had filed applications under Section 33 of the
      Act, therefore, the Appellant could not have filed the application under
      Section 34 of the Act, before disposal of the said applications. It is
      contended that High Court erred in refusing to exclude the period
      spent in disposal of the application under Section 33 while computing
      the limitation under Section 34(3) of the Act and erred in placing
      reliance on the decision in State of Arunachal Pradesh v. Damani
      Construction Co.5 It is urged that the application under Section
      33(1)(a) merely sought correction of clerical and typographical errors
      in the Arbitral Award and did not amount to review of the Award. It
      is submitted that the issue involved in the appeal is no longer res
      integra and has been dealt with by this Court in Geojit Financial
      Services Ltd. v. Sandeep Gurav6.
10. Per contra, learned senior counsel for Respondent No.1 submitted
    that the application filed by the Appellant under Section 33(1)(a) of the


3    W.P. No. 105176/2023.
4    Arbitration Application Nos. 3/2022 and 4/2022.
5    (2007) 10 SCC 742
6    2025 INSC 1021.
16                                                            [2026] 7 S.C.R.

                          Supreme Court Reports


      Act, in substance was an attempt to review the Arbitral Award and not
      merely an application for correction of clerical or typographical errors.
      It was contended that Appellant had sought modification of substantive
      findings in the Award which fell outside the limited scope of Section
      33(1)(a). It was urged that only an application which is maintainable
      under Section 33 could extend the limitation under Section 34(3)
      of the Act. Relying on State of Arunachal Pradesh (supra), it was
      contended that since the Appellant’s application under Section 33 of
      the Act was itself not maintainable, it could not claim exclusion of time
      spent in disposal of the said application for the purposes of limitation.
      It was argued that Arbitral Tribunal had become functus officio after
      passing of the Award and therefore the merits of the dispute could
      not be reopened in the guise of an application under Section 33 of
      the Act. It was further argued that Appellant’s applications under
      Section 34 were barred by limitation as the same were filed beyond
      the statutory outer limit prescribed under Section 34(3) of the Act,
      even assuming that the Appellant is entitled to exclusion of time for
      the period spent in disposal of application under Section 33 of the Act.
11. Having heard the rival contentions and perusing the material on
    record, the issue that arises is whether the limitation under Section
    34(3) would commence from the date of the original award or from
    the date on which the application under Section 33 came to be
    disposed of.
12. For the sake of convenience, the relevant part of Sections 33 and 34
    of the Act, are extracted below:
           Section 33
           “33. Correction and interpretation of award; additional
           award. — (1) Within thirty days from the receipt of the
           arbitral award, unless another period of time has been
           agreed upon by the parties—
           a party, with notice to the other party, may request the
           arbitral tribunal to correct any computation errors, any
           clerical or typographical errors or any other errors of a
           similar nature occurring in the award;
           (b) if so agreed by the parties, a party, with notice to the
           other party, may request the arbitral tribunal to give an
           interpretation of a specific point or part of the award.
[2026] 7 S.C.R.                                                            17

         National Highway Authority of India v. T. Younis & Anr.


           (2) If the arbitral tribunal considers the request made under
           sub-section (1) to be justified, it shall make the correction
           or give the interpretation within thirty days from the receipt
           of the request and the interpretation shall form part of the
           arbitral award.
           (3) The arbitral tribunal may correct any error of the type
           referred to in clause (a) of sub-section (1), on its own
           initiative, within thirty days from the date of the arbitral
           award…”

           Section 34
           “34. Application for setting aside arbitral award.
           (…)
           (3) An application for setting aside may not be made after
           three months have elapsed from the date on which the
           party making that application had received the arbitral
           award or, if a request had been made under section 33,
           from the date on which that request had been disposed
           of by the arbitral tribunal:
           Provided that if the Court is satisfied that the applicant was
           prevented by sufficient cause from making the application
           within the said period of three months it may entertain the
           application within a further period of thirty days, but not
           thereafter.”
13. Section 33 of the Act deals with the request made to the Arbitral
    Tribunal for correction and interpretation of the award as well as for
    rendering additional award. An application under Section 33 of the
    Act is required to be made within a period of 30 days from the date
    of the receipt of the award. From careful scrutiny of Section 34(3)
    of the Act, it is evident that where a request under Section 33 of
    the Act has been made, the limitation for filing an application under
    Section 34 of the Act shall be reckoned from the date on which such
    request is disposed of by the Arbitral Tribunal. The said provision
    does not distinguish between the applications which are ultimately
    allowed or dismissed. The said provision also does not indicate that
    only an application which is maintainable under Section 33 of the
    Act would defer the commencement of litigation under Section 34(3)
18                                                            [2026] 7 S.C.R.

                          Supreme Court Reports


      of the Act. Had the legislature intended to restrict the benefit only to
      the applications which were ultimately allowed or which were held
      to be maintainable, it would have expressly provided so. The Court
      cannot read into the provision a restriction which the legislature itself
      has not consciously incorporated.
14. Once proceedings under Section 33 are initiated and entertained
    by the Arbitral Tribunal, the award remains subject to the
    limited jurisdiction of the tribunal for correction, interpretation, or
    supplementation as contemplated under the provision. So long as
    such proceedings remain pending, the parties cannot be compelled
    to institute proceedings under Section 34 merely as a matter of
    abundant caution. The parties can effectively pursue their remedy
    under Section 34 only upon conclusion of the proceedings under
    Section 33. Consequently, the limitation prescribed under Section
    34(3) can start only from the date on which the proceedings under
    Section 33 are disposed of.
15. In our view, the contention of the Respondent that only an application
    which is “maintainable” under Section 33 can defer the commencement
    of limitation under Section 34(3), cannot be accepted. Whether the
    application under Section 33 ultimately succeeds or fails, or whether
    the Arbitral Tribunal eventually finds that no correction or modification
    of the award is warranted, is not determinative for the purpose of
    Section 34(3). What is relevant is that whether the jurisdiction of the
    Arbitral Tribunal under Section 33 had been formally invoked and that
    such proceedings remained pending consideration before the tribunal.
16. The reliance placed by the Respondent on State of Arunachal
    Pradesh (supra) is misplaced. That case arose in an entirely different
    factual context where there was no formal application under Section
    33 invoking the jurisdiction of the Arbitral Tribunal. The party had
    merely addressed a letter, in substance seeking review of the award
    and certain ancillary clarifications beyond the contours of section
    33. It was in that context, that this Court held such communication
    could not entitle a fresh starting point of limitation under Section
    34(3). The facts of the present case stand on an entirely different
    footing. Here, formal applications under Section 33 were admittedly
    filed by both parties within the statutory period, and the same were
    entertained and disposed of by the Arbitral Tribunal by a common
    order dated 04.07.2022.
[2026] 7 S.C.R.                                                                                 19

           National Highway Authority of India v. T. Younis & Anr.


17. We are also of the view that the interpretation adopted by the High
    Court would defeat the scheme and object of the Act. If parties
    are compelled to institute proceedings under Section 34 during the
    pendency of proceedings, under Section 33 merely as a matter of
    abundant caution, it would result in multiplicity of proceedings and
    procedural uncertainty. At the same time, it is clarified that where
    applications under Section 33 are found to be sham, frivolous, or
    mala fide or solely filed for the purpose of defeating limitation under
    Section 34(3) of the Act, the courts would be justified in imposing
    exemplary and punitive costs, as maintaining the balance between
    preserving legitimate remedies and preventing abuse of process is
    fundamental to effective administration of justice.
18. Even otherwise, the issue involved in the instant appeal is no longer
    res integra. This Court7 after examining Sections 33 and 34(3) of the
    Act has held that for the purposes of computation of limitation under
    Section 34(3) of the Act, it is the date of disposal of the application
    under Section 33 of the Act that would earmark the starting point of
    limitation for filing an application under Section 34 of the Act. We are
    in agreement with the view taken by this Court in aforesaid decisions.
    A plain reading of Section 34(3), read in the light of the law laid down
    in Geojit (supra), makes it clear that once jurisdiction under Section
    33 is formally invoked and such proceedings are entertained by the
    Arbitral Tribunal, the limitation for filing an application under Section
    34 would commence only from the date on which such request is
    disposed of by the Arbitral Tribunal.
19. In the facts of the present case, it is not in dispute that the certified
    copy of the common order dated 04.07.2022 disposing of the
    applications under Section 33 was received by the Appellant on
    15.09.2022 and that the applications under Section 34 were thereafter
    filed on 07.11.2022. Thus, even reckoning limitation from the date of
    receipt of the order disposing of the applications under Section 33,
    the applications under Section 34 of the Act were instituted within
    the period contemplated under Section 34(3) of the Act. Therefore,
    the contention of the Respondent that the applications under Section
    34 of the Act were barred by limitation does not merit acceptance.



7   Ved Prakash Mithal and Sons v. Union of India, 2018 SCC OnLine SC 3181; USS Alliance v. State of
     U.P., 2023 SCC OnLine SC 778, Geojit (supra).
20                                                       [2026] 7 S.C.R.

                             Supreme Court Reports


20. Accordingly, the impugned judgment and order dated 22.01.2024
    passed by the High Court is set aside. The orders dated 05.08.2023
    passed by the Principal District and Sessions Judge, Ballari,
    condoning the delay in filing the applications under Section 34 of
    the Act, are restored. The applications under Section 34 of the Act,
    shall now be decided on their own merits, in accordance with the law.
21. The appeal is accordingly allowed. Pending application(s), if any,
    shall stand disposed of.

      Result of the case: Appeal allowed.




      †
          Headnotes prepared by: Ankit Gyan


Search Indian case law

Ask in plain English, not just keywords. 25,000 AI words free, no card.

Try "Section 34(3) of the Arbitration and Conciliation Act, 1996"Sign in to search

For a digitally signed copy suitable for filing, refer to the court's own website. Only the court can issue one.