Created byFuzzy Cloud

Supreme Court of India

NIRMITI DEVELOPERS THROUGH ITS PARTNERS & ANR.versusTHE STATE OF MAHARASHTRA & ORS.

Citation
2025 INSC 265
Decided
25 February 2025
Disposal
Appeal(s) allowed

Holding

The reservation of the land lapsed under Sections 49(7), 126 and 127 of the Maharashtra Regional & Town Planning Act, 1967, and the land is free for the appellants to use.

Summary

The appellants purchased a 50,138 sq.ft. plot in Amravati that had been reserved for a private school under the Maharashtra Regional & Town Planning Act, 1967. The original owners served a purchase notice under Section 49 in 2006, which was confirmed in 2007, but the authorities failed to acquire the land within the one‑year period prescribed by Section 49(7). Subsequent attempts to acquire the land under Sections 126 and 127 also failed, and no compensation was paid. The Supreme Court held that the reservation lapsed on 2 January 2008 under Section 49(7) and, by operation of Sections 126 and 127, the land was released from reservation, allowing the appellants to use it. The Court also invoked Article 142 to do complete justice given the thirty‑year delay. The High Court order was set aside and the appeals were allowed.

Issues considered

  • The reservation of the plot under the MRTP Act lapses if acquisition is not completed within the statutory time‑frame prescribed in Sections 49, 126 and 127.
  • Whether Section 49(7) can be invoked by the present purchasers, who were not the original owners, to claim that the reservation has lapsed.
  • Whether the gross delay of nearly thirty years justifies a declaration of lapse under Article 142 of the Constitution.
  • Whether the authorities’ failure to take any steps after the purchase notice amounts to a lapse of reservation under the MRTP Act.

Legislation cited

Headnote

Issue for Consideration Whether the reservation of the plot of land lapsed under Sections 49, 126 and 127 of the Maharashtra Regional & Town Planning Act, 1967 due to the failure of the authorities to acquire it within the statutory timeframe, thereby entitling the land as permissible under law. Headnotes† Maharashtra Regional & Town Planning Act, 1967 – Section 49, Section 126 and Section 127 – Reservation to lapse if no step taken for acquisition of land within the prescribed time period – Landowners are free to use land as

Subjects

de‑reservation of landland acquisitionreservation lapseSection 49 MRTP ActSection 126 MRTP ActSection 127 MRTP ActArticle 142property rightspublic purpose

Judgment

                 [2025] 2 S.C.R. 1206 : 2025 INSC 265

           Nirmiti Developers Through its Partners & Anr.
                                  v.
                   The State of Maharashtra & Ors.
                  (Civil Appeal No(s). 3238-3239 of 2025)
                               25 February 2025
              [J.B. Pardiwala* and R. Mahadevan, JJ.]


                            Issue for Consideration
       Whether the reservation of the plot of land lapsed under Sections 49,
       126 and 127 of the Maharashtra Regional & Town Planning Act,
       1967 due to the failure of the authorities to acquire it within the
       statutory timeframe, thereby entitling the appellants to use the land
       as permissible under law.

                                   Headnotes†
       Maharashtra Regional & Town Planning Act, 1967 – Section
       49, Section 126 and Section 127 – Reservation to lapse if no
       step taken for acquisition of land within the prescribed time
       period – Landowners are free to use land as if there was no
       reservation:
       Vide the revised development plan for Amravati under the
       Maharashtra Regional & Town Planning Act, 1967 [‘MRTP Act’], plot
       of land measuring 50,138 sq. ft. reserved for a private school for
       Respondent No. 5, a Public Trust – No steps were taken between
       1993 and 2006 by Respondents to acquire the property – On
       04.07.2006, the erstwhile owners served a purchase notice under
       Section 49 of the MRTP Act – Respondent No. 1 confirmed the
       notice on 02.01.2007 and ordered Respondent No. 5 to complete
       acquisition within 12 months, failing which the reservation would
       lapse – Acquisition proceedings were not completed by 02.01.2008,
       and no compensation was deposited by Respondent No. 5 with
       any authority – The erstwhile owners sold the land in December
       2015 to the Appellants – In March 2016, the Appellants filed a
       writ petition in the High Court seeking either compensation from
       Respondent No. 5 for land reserved for it or declaration that the
       reservation had lapsed under Section 49(7) – The High Court in
       impugned order disposed of the Writ Petition taking the view that

* Author
[2025] 2 S.C.R.                                                                  1207

            Nirmiti Developers Through its Partners & Anr. v.
                     The State of Maharashtra & Ors.

     Section 49(7) would not apply to the present Appellants as the
     erstwhile owners did not use the land after de-reserving it – Appeal
     against impugned order allowed – Held, as per Section 49(7), the
     reservation lapsed on 02.01.2008, allowing the erstwhile owners
     to use the plot of land as permissible in law.
     Held: It is clear that the scheme of Sections 126 and 127 that if a
     period of 10 years has elapsed from the date of publication of the
     plan in question, and no steps for acquiring the land have been
     taken, then once a purchase notice is served under Section 127,
     steps to acquire the land must follow within a period of one year
     from the date of service of such notice, or else the land acquisition
     proceedings would lapse – The principles underlying in Section 127
     of the MRTP Act is either to utilize the land for the purpose for which
     it is reserved in the timeline given or let the owner utilize the land for
     the purpose as permissible under the town planning scheme – The
     reservation shall be deemed to have lapsed if no steps are taken for
     acquisition of the said land within the prescribed period – Indisputably,
     in the present case, the respondents have not taken any steps to
     issue notification after receipt of the notice. [Paras 34, 47]

     MRTP Act, 1967 – Section 126 and Section 127 – Statutory period
     of ten years sacrosanct – Reservation to lapse after ten years:
     Held: The landowner cannot be deprived of the use of the land for
     years together – Once an embargo has been put on a landowner
     not to use the land in a particular manner, the said restriction
     cannot be kept open-ended for indefinite period – The statute has
     provided a period of ten years to acquire the land under Section
     126 of the Act – Additional one year is granted to the landowner
     to serve a notice for acquisition – Such timeline is sacrosanct
     and has to be adhered to – It is declared that the reservation of
     the plot in question could be said to have lapsed by efflux of time
     even under Sections 126 and 127 of the MRTP Act. [Paras 50,51]

     Constitution of India – Article 142 – Reservation to have lapsed
     owing to gross delay of thirty years:
     Held: Having regard to the gross delay of almost thirty years in
     acquiring the land, even without the aid of Section 127 of the MRTP
     Act, in exercise of jurisdiction under Article 142 of the Constitution
     to do complete justice in the matter, the reservation would have
     been declared as having lapsed. [Para 52]
1208                                                         [2025] 2 S.C.R.

                          Supreme Court Reports


                                List of Acts
     Maharashtra Regional & Town Planning Act, 1967.

                             List of Keywords
     De-reserving land; Acquisition; Land Acquisition; Lapse; Reservation
     of land.

                            Case Arising From
     CIVIL APPELLATE JURISDICTION: Civil Appeal No(s). 3238-3239
     of 2025
     From the Judgment and Order dated 09.02.2017 and 07.04.2017
     of the High Court of Judicature at Bombay at Nagpur in WP No.
     1935 of 2016 and MCA No. 373 of 2017

                         Appearances for Parties
     Advs. for the Appellants:
     Gagan Sanghi, Mrs. Farah Hashmi, Rameshwar Prasad Goyal.
     Advs. for the Respondents:
     Nitin Lonkar, Siddharth Dharmadhikari, Aaditya Aniruddha Pande,
     M/s. Black & White Solicitors.

                Judgment / Order of the Supreme Court

                                 Judgment

     J.B. Pardiwala, J.

1.   Leave granted.
2.   These captioned appeals arise from an order passed by the High
     Court of Judicature at Bombay, Nagpur Bench, dated 09-02-2017
     in Writ Petition No.1935/2016 by which the Writ Petition filed by the
     appellants – herein came to be disposed of reserving liberty for the
     appellants to take necessary steps as open to them in law.
3.   The facts giving rise to these petitions may be summarized as under.
4.   The subject-matter of this litigation is a vacant plot of land admeasuring
     50,138 sq.ft (46.5 R) in Survey No. 81/3 (New) 3 (old) in Mouza
     Rajapeth, Amravati, Maharashtra. This plot originally was jointly owned
[2025] 2 S.C.R.                                                     1209

            Nirmiti Developers Through its Partners & Anr. v.
                     The State of Maharashtra & Ors.

     by Smt Akhtar Bano Rashid, Abdul Majid A. Samad & Mohammad
     Sajid A. Samad (previous owners) respectively, and formed part of
     the larger plot admeasuring 2.47 Hectare. The property in question
     is situated within the municipal limits of Respondent No.3 – herein.
5.   The erstwhile owners had submitted a lay-out plan for development of
     2.47 hectare to Respondent No.3. The Respondent No.3 sanctioned
     the development plan for the residential area and the remaining area
     admeasuring 50,138 Sq.ft. was reserved for Government school.
6.   On 25-02-1993, a revised development plan for Amravati under the
     Maharashtra Regional and Town Planning Act, 1966 (for short “the
     MRTP Act”) came into effect in which the property was shown as
     reserved for a private school in favour of the Respondent No.5 vide
     Reservation No.195. Till 2006, i.e., almost for a period of 13 years,
     no steps were taken to acquire the property.
7.   On 04-07-2006, the original owners served the purchase notice under
     Section 149 of the MRTP Act on the Respondent No.1 calling upon
     the said respondent either to acquire the property or to release it
     from reservation.
8.   On 02-01-2007 the Respondent No.1 acknowledged the purchase
     notice. The Respondent No.1 directed the Respondent No.5 to
     complete the acquisition proceedings within a period of one year,
     failing which the reservation in its favour would lapse.
9.   On 29-12-2007, the Respondent No.5 requested the Respondent
     No.7 to initiate proceedings for acquiring the land under Section
     126 of the MRTP Act.
10. Till 02-01-2008, no action was taken by the Respondent No.5 to
    commence the acquisition proceedings within one year of confirmation
    of the purchase notice.
11. On 13-08-2014, the previous owners issued a purchase notice under
    Section 127 of the MRTP Act to the Respondent Nos.1,3,4 and 6
    respectively requesting them to acquire the land.
12. On 12-06-2015, the Respondent No.6 received the proposal from
    Respondent No.5 to acquire the land.
13. On 30-12-2015, the petitioner – herein purchased the property from
    the erstwhile owners for Rs.1.26 Crore.
1210                                                          [2025] 2 S.C.R.

                         Supreme Court Reports


14. On 16-03-2016, the appellants filed a Writ Petition praying that (a) the
    Respondent No.5 be directed to deposit the amount of compensation
    to be paid to the appellants for acquisition under the new Land
    Acquisition Act, 2017 and complete the acquisition & (b) declare that
    the reservation had lapsed under Section 49(7) of the Act.
15. On 01-10-2016, reply was filed by the Respondent Nos. 6 and 7
    respectively stating that on 12-6-2015, proposal from the Respondent
    No.5 was received and LAC was registered but till that date the
    Respondent No.5 had not deposited a single penny with the LAO
    and the Respondent Nos.6 and 7 had reasons to believe that the
    Respondent No.5 was not interested in developing the said land.
16. On 13-10-2016, the Respondent No.3 filed an additional claim not
    disclosed by the appellants in their notice dated 13-8-2014.
17. In such circumstances, referred to above, the petitions filed by the
    appellants came to be disposed of by the High Court which reads thus:-
     Order dated 09-02-2017 reads thus:-
          “Heard Shri G.K Mundhada, learned Counsel for the
          petitioners, Shri N. Rao, learned A.G.P. for respondent
          nos.1,2,4,6 and 7, Shri R. Darda, learned Counsel for
          respondent nos. 3 and 4 and Shri S. Ghodeswar, learned
          Counsel for respondent no.5.
          2. Petitioner is a purchaser who has bought property from
          original owners. Original owners issued a notice under
          Section 49[1] of the Maharashtra Regional and Town
          Planning Act, that notice is dated 04-07-2006. It was
          confirmed on 02-01-2007, within a period of one year,
          thereafter no steps for acquisition were taken. Original
          owners thereafter did not take any steps for development.
          They have sold the property on 31-12-2015 to the present
          developer.
          3. Effort of learned counsel for the petitioners is to urge that
          before that in 2015, original owners had sought permission
          to raise compound wall and the same was declined. Thus,
          after confirmation of purchase notice, expiry of period of
          one year therefrom, at least for a period of 6 years no steps
          to develop the same were taken by the original owners.
[2025] 2 S.C.R.                                                           1211

            Nirmiti Developers Through its Partners & Anr. v.
                     The State of Maharashtra & Ors.

           4. Two separate procedures are deliberately made available
           under the Act. A person who wants to immediately develop
           his property can take recourse to section 49, otherwise he
           has to wait for a period of 10 years as envisaged under
           Section 127[1] thereof. Section 49 is not meant for getting
           the property de-reserved and then to wait for appropriate
           time to sell out it in open market.
           5. Here petitioner is a developer, it has not taken any steps
           after purchase to issue notice either under Section 49 or
           under Section 127 of the Act.
           6. Notice given by the previous land owners was under
           Section 49 only and as no advantage of de-reservation
           was taken for more than 6 years, we find that, that notice
           or then the benefits flowing therefrom cannot accrue to
           the benefits of present petitioners. Hence, with liberty to
           petitioner to take such other steps as are open to him in
           law, we dispose of the present petition. No costs.”
     Order dated 07-04-2017: (IN REVIEW PETITION)
           “Heard Shri S.K. Mishra, learned Senior Counsel with
           Shri G.K. Mundhada, learned Counsel for applicants and
           learned A.G.P. for non-applicant nos. 1,2,6 and 7.
           2. Learned Senior Counsel submits that literal meaning of
           Section 49 of the Maharashtra Regional and Town Planning
           Act, 1966 should be adhered to and as the reservation had
           already lapsed, purchaser is not required to go through·
           the rigmarole of serving notice either under Section 49
           or under Section 127 again. He contends that the finding
           of this Court in paragraph no.4 are, therefore, contrary to
           Scheme of Section 49.
           3. This Court has already in judgment in case of Kishor
           Maganlal Vyas vs. State of Maharashtra and others (Writ
           Petition No. 506/2011. Dated 11-06-2012), held that
           normally procedure for de-reservation is Section 127,
           wherein the local authority gets time of 10 years to acquire
           the property. However, to mitigate the hardship caused
           to a genuine needy owner, a provision has been made
           in Section 49 and hence, a specified class of owners
           emerging therein can only take recourse to it.
1212                                                          [2025] 2 S.C.R.

                         Supreme Court Reports


          4. Here we have found that after lapsing of reservation
          for a period of 6 years the earlier owner had not either
          developed the property or sold it out. Thus, the property
          was lying as it is, and hence, recourse to Section 49 itself
          is found not proper. De-reservation here was used to get
          the best desired price after waiting for long time. Section
          127 of the Act gives reasonable time to acquiring body to
          act and acquire. De-reservation thereunder may therefore
          enure to the benefit of purchaser also. Same cannot be
          said in respect of Section 49 de-reservation. Section 49
          operates on personal need of the owner and it cannot
          enure to the benefit of purchaser like petitioner. It is in this
          background, that we have held that the purchaser from that
          owner [present applicant] has not taken necessary steps
          either under Section 49 or under Section 127 of the Act.
          5. We, therefore, find no case made out warranting review.
          Misc. Civil Application is thus rejected. No costs.”
18. The High Court took the view that the person intending to develop his
    property at the earliest can take recourse of Section 49 otherwise he
    has to wait for a period of 10 years as envisaged under Section 127(1)
    thereof.
19. The High Court took notice of the fact that although the original
    owners had completed the procedure to get the land de-reserved
    by issuing notice under Section 49 yet as they sold the plot to the
    present appellants Section 49 would not apply to the purchasers. In
    other words, Section 49 according to the High Court is not meant
    for getting the property de-reserved and then to wait for appropriate
    time to sell it in the open market.
20. According to the High Court, the petitioner being a developer had
    not taken any steps after purchase, i.e., to issue notice either under
    Section 49 or under Section 127 of the Act.
21. The High Court, taking the view, as aforesaid, disposed of the petition
    granting liberty to the appellants – herein to take appropriate steps
    in accordance with law.
22. We heard Mr. Gagan Sanghi, the learned counsel appearing for
    the appellants and Mr. Suhaskumar Kadam, the learned counsel
    appearing for Respondent No.3 – Corporation.
[2025] 2 S.C.R.                                                           1213

            Nirmiti Developers Through its Partners & Anr. v.
                     The State of Maharashtra & Ors.

23. Section 49 of the MRTP Act reads thus:-
           “49. Obligation to acquire land on refusal of permission
           or on grant of permission in certain cases.—(1) Where—
                (a) any land is designated by a plan as subject to
                compulsory acquisition, or
                (b) any land is allotted by a plan for the purpose of
                any functions of a Government or local authority or
                statutory body, or is land designated in such plan as
                a site proposed to be developed for the purposes of
                any functions of any such Government, authority or
                body, or
                (c) any land is indicated in any plan as land on which a
                highway is proposed to be constructed or included, or
                (d) any land for the development of which permission
                is refused or is granted subject to conditions, and
                any owner of land referred to in Clause (a), (b), (c)
                or (d) claims—
                     (i) that the land has become incapable of
                     reasonably beneficial use in its existing state, or
                     (ii) (where planning permission is given subject
                     to conditions) that the land cannot be rendered
                     capable of reasonably beneficial use by the
                     carrying out of the permitted development in
                     accordance with the conditions; or
                (e) the owner of the land because of its designation
                or allocation in any plan claims that he is unable to
                sell it except at a lower price than that at which he
                might reasonably have been excepted to sell if it were
                not so designated or allocated, the owner or person
                affected may serve on the State Government within
                such time and in such manner, as is prescribed by
                regulations, a notice (hereinafter referred to as “the
                purchase notice”) requiring the Appropriate Authority
                to purchase the interest in the land in accordance
                with the provisions of this Act.
1214                                                      [2025] 2 S.C.R.

                       Supreme Court Reports


        (2) The purchase notice shall be accompanied by a copy
        of any application made by the applicant to the Planning
        Authority, and of any order or decision of that Authority
        and of the State Government, if any, in respect of which
        the notice is given.
        (3) On receipt of a purchase notice, the State Government
        shall forthwith call from the Planning Authority and the
        Appropriate Authority such report or records or both, as
        may be necessary, which those authorities shall forward
        to the State Government as soon as possible but not later
        than thirty days from the date of their requisition.
        (4) On receiving such records or reports, if the State
        Government is satisfied that the conditions specified in
        sub-section (1) are fulfilled, and that the order or decision
        for permission was not duly made on the ground that the
        applicant did not comply with any of the provisions of this
        Act or rules or regulations, it may confirm the purchase
        notice, or direct that planning permission be granted without
        condition or subject to such conditions as will make the land
        capable of reasonably beneficial use. In any other case,
        it may refuse to confirm the purchase notice, but in that
        case, it shall give the applicant a reasonable opportunity
        of being heard.
        (5) If within a period of six months from the date on which
        a purchase notice is served the State Government does not
        pass any final order thereon, the notice shall be deemed
        to have been confirmed at the expiration of that period.
        (6) [* * *]
        (7) If within one year from the date of confirmation of the
        notice, the Appropriate Authority fails to make an application
        to acquire the land in respect of which the purchase
        notice has been confirmed as required under Section
        126, the reservation, designation, allotment, indication or
        restriction on development of the land shall be deemed
        to have lapsed; and thereupon, the land shall be deemed
        to be released from the reservation, designation, or, as
        the case may be, allotment, indication or restriction and
[2025] 2 S.C.R.                                                         1215

            Nirmiti Developers Through its Partners & Anr. v.
                     The State of Maharashtra & Ors.

           shall become available to the owner for the purpose of
           development otherwise permissible in the case of adjacent
           land, under the relevant plan.
24. Section 126 of the MRTP Act reads thus:
           “126. Acquisition of land required for public purposes
           specified in plans
           (1) When after the publication of a draft Regional plan, a
           Development or any other plan or town planning scheme,
           any land is required or reserved for any of the public
           purposes specified in any plan or scheme under this Act at
           any time, the Planning Authority, Development Authority, or
           as the case may be, [any Appropriate Authority may, except
           as otherwise provided in section 113A] [acquire the land,—
                “(a) by agreement by paying an amount agreed to, or
                (b) in lieu of any such amount, by granting the land-
                owner or the lessee, subject, however, to the lessee
                paying the lessor or depositing with the Planning
                Authority, Development Authority or Appropriate
                Authority, as the case may be, for payment to the
                lessor, an amount equivalent to the value of the
                lessor’s interest to be determined by any of the said
                Authorities concerned [on the basis of the principles
                laid down in the Right to Fair Compensation and
                Transparency in Land Acquisition, Rehabilitation and
                Resettlement Act, 2013], Floor Space Index (FSI)
                or Transferable Development Rights (TDR) against
                the area of land surrendered free of cost and free
                from all encumbrances, and also further additional
                Floor Space Index or Transferable Development
                Rights against the development or construction of
                the amenity on the surrendered land at his cost, as
                the Final Development Control Regulations prepared
                in this behalf provide, or
                (c) by making an application to the State Government
                for acquiring such land [under the provisions of the
                Right to Fair Compensation and Transparency in
                Land Acquisition, Rehabilitation and Resettlement
1216                                                    [2025] 2 S.C.R.

                      Supreme Court Reports


             Act, 2013] , and the land (together with the amenity,
             if any so developed or constructed) so acquired
             by agreement or by grant of Floor Space Index
             or additional Floor Space Index or Transferable
             Development Rights under this section [or under the
             provisions of the Right to Fair Compensation and
             Transparency in Land Acquisition, Rehabilitation and
             Resettlement Act, 2013], as the case may be, shall
             vest absolutely free from all encumbrances in the
             Planning Authority, Development Authority, or as the
             case may be, any Appropriate Authority.
        (2) On receipt of such application, if the State Government
        is satisfied that the land specified in the application is
        needed for the public purpose therein specified, or 4[if the
        State Government (except in cases falling under section
        49 5[and except as provided in section 113A)] itself is of
        opinion] that any land included in any such plan is needed
        for any public purpose, it may make a declaration to that
        effect in the Official Gazette, [in the manner provided
        in section 19 of the Right to Fair Compensation and
        Transparency in Land Acquisition, Rehabilitation and
        Resettlement Act, 2013], in respect of the said land. The
        declaration so published shall, notwithstanding anything
        contained in the said Act, be deemed to be a declaration
        duly made under the said section:
        [Provided that, subject to the provisions of sub-section
        (4), no such declaration shall be made after the expiry of
        one year from the date of publication of the draft Regional
        Plan, Development Plan or any other Plan, or Scheme,
        as the case may be.]
        [(3) On publication of a declaration under the said 3
        [section 19], the Collector shall proceed to take order for
        the acquisition of the land under the said Act; and the
        provisions of that Act shall apply to the acquisition of the
        said land with the modification that the market value of
        the land shall be,—
        (i) where the land is to be acquired for the purposes of
        a new town, the market value prevailing on the date of
[2025] 2 S.C.R.                                                           1217

            Nirmiti Developers Through its Partners & Anr. v.
                     The State of Maharashtra & Ors.

           publication of the notification constituting or declaring the
           Development Authority for such town;
           (ii) where the land is acquired for the purposes of a
           Special Planning Authority, the market value prevailing
           on the date of publication of the notification of the area
           as undeveloped area; and
           (iii) in any other case, the market value on the date of
           publication of the interim development plan, the draft
           development plan or the plan for the area or areas for
           comprehensive development, whichever is earlier, or as
           the case may be, the date of publication of the draft Town
           Planning Scheme:
           Provided that, nothing in this sub-section shall affect the
           date for the purpose of determining the market value of land
           in respect of which proceedings for acquisition commenced
           before the commencement of the Maharashtra Regional
           and Town Planning (Second Amendment) Act, 1972:
           Provided further that, for the purpose of clause (ii) of this
           sub-section, the market value in respect of land included
           in any undeveloped area notified under sub-section (1) of
           section 40 prior to the commencement of the Maharashtra
           Regional and Town Planning (Second Amendment) Act,
           1972, shall be the market value prevailing on the date of
           such commencement.]
           [(4) 5[Notwithstanding anything contained in the proviso
           to sub-section (2) and subsection (3), if a declaration,]
           is not made, within the period referred to in sub-section
           (2) (or having been made, the aforesaid period expired
           on the commencement of the Maharashtra Regional and
           Town Planning 6[(Amendment) Act, 1993),] the State
           Government may make a fresh declaration for acquiring the
           land [under the provisions of the Right to Fair Compensation
           and Transparency in Land Acquisition, Rehabilitation
           and Resettlement Act, 2013], in the manner provided by
           sub-sections (2) and (3) of this section, subject to the
           modification that the market value of the land shall be
           the market value at the date of declaration in the Official
           Gazette, made for acquiring the land afresh.]”
1218                                                        [2025] 2 S.C.R.

                         Supreme Court Reports


25. We must now look into Section 127 of the MRTP Act. Section 127
    reads thus:
          “127. Lapsing of reservations.—(1) If any land reserved,
          allotted or designated for any purpose specified in any
          plan under this Act is not acquired by agreement within
          ten years from the date on which a final Regional Plan, or
          final Development Plan comes into force [or if a declaration
          under sub-section (2) or (4) of Section 126 is not published
          in the Official Gazette within such period, the owner or any
          person interested in the land may serve notice, alongwith
          the documents showing his title or interest in the said
          land, on the Planning Authority, the Development Authority
          or, as the case may be, the Appropriate Authority to that
          effect; and if within twelve months] from the date of the
          service of such notice, the land is not acquired or no
          steps as aforesaid are commenced for its acquisition, the
          reservation, allotment or designation shall be deemed to
          have lapsed, and thereupon, the land shall be deemed to
          be released from such reservation, allotment or designation
          and shall become available to the owner for the purpose
          of development as otherwise, permissible in the case of
          adjacent land under the relevant plan.
          (2) On lapsing of reservation, allocation or designation of
          any land under sub-section (1), the Government shall notify
          the same, by an order published in the Official Gazette.”
26. Section 127 of the MRTP Act is enacted for lapsing of reservation,
    allotment or designation for any purpose specified in the plan. The
    section prescribes, that if any land reserved, allotted or designated for
    any purpose specified in any plan under this Act is not acquired by
    agreement within ten years from the date on which a final Regional
    Plan or Development Plan comes into force or if proceedings for the
    acquisition of such land under this Act or under the Land Acquisition
    Act are not commenced within such period the owner or any, person
    interested in the land may serve notice on the Planning Authority,
    Development Authority or as the case may be, Appropriate Authority
    to that effect. If the concerned Authority within twelve months from the
    date of service of such notice, fails to acquire the land or no steps as
    aforesaid are initiated for its acquisition the reservation, allotment or
[2025] 2 S.C.R.                                                             1219

            Nirmiti Developers Through its Partners & Anr. v.
                     The State of Maharashtra & Ors.

     designation shall be deemed to have lapsed, and thereupon the land
     shall be deemed to be released from such reservation, allotment or
     designation and shall become available to the owner for the purpose
     of development as otherwise, permissible in the case of adjacent
     land under the relevant plan.

     POSITION OF LAW
27. This Court in Chhabildas v. State of Maharashtra and others reported
    in 2018 INSC 106 while explaining Sections 49 and 127 of the MRTP
    Act respectively observed as under:
           “9. The scheme of Section 49 of the MRTP Act is to lay
           down timelines within which the appropriate authority must
           make an application to acquire the land in respect of which
           a purchase notice has been confirmed. The moment any
           of the conditions specified in the sub-section (1) are met,
           the owner or person affected may serve on the State
           Government, within the time and manner prescribed by
           regulations, a purchase notice requiring the appropriate
           authority to purchase the interest in the land in accordance
           with the provisions of this Act.
           10. On the receipt of the purchase notice as per sub-section
           (3), the State Government is to forthwith call from the
           planning authority or the appropriate authority such report
           or records as may be necessary, which the authority shall
           then forward to the State Government as soon as possible
           but not later than 30 days from the date of acquisition.
           11. In sub-section (4), if the State Government is satisfied
           that the conditions specified in sub-section (1) are fulfilled,
           it may either confirm the purchase notice; refuse to confirm
           the purchase notice; or direct that planning permission be
           granted with or without conditions. Under sub-section (5),
           if the steps contemplated after service of purchase notice
           leads to a situation where the State Government does not
           pass any orders thereon, the notice shall be deemed to
           have been confirmed at the expiration of that period. And
           finally, under sub-section (7), if within one year from the
           date of confirmation of purchase notice, the appropriate
           authority fails to make an application to acquire the land in
1220                                                        [2025] 2 S.C.R.

                       Supreme Court Reports


        respect of which the purchase notice has been confirmed,
        the reservation, designation, allotment, indication or
        restriction on development of the land shall be deemed
        to have lapsed. Section 49(6), which was deleted by
        Maharashtra Act 6 of 1976, read as follows:
             “Upon confirmation of the notice, the State Government
             shall proceed to acquire the land or that part of any
             land regarding which the notice has been confirmed,
             within one year of the confirmation of the purchase
             notice, in accordance with the provisions of Chapter
             VII.”
        It is clear that, under this provision, if within one year
        from the confirmation of the purchase notice, the State
        Government did not acquire the land, then the consequence
        would be that the acquisition shall be deemed to have
        lapsed. This was a salutary provision, but seems to have
        been deleted so that Section 49 cases are brought on par
        with Section 126 cases.
        12. The object of Section 49 is thus clear that once a
        purchase notice is received by the authorities, there arises,
        as the marginal note to the Section also indicates, an
        obligation to acquire land. The timelines contemplated by
        the section also indicate that the owner or person affected
        cannot be left to hang indefinitely without a decision to follow
        up the purchase notice by acquisition of the land in question.
        13. However, it has been argued on behalf of the State that
        Section 49 abruptly ends with sub-section (7), after which
        there are no timelines indicated as to what is to happen after
        the appropriate authority makes an application to acquire
        the land within one year from the date of confirmation of
        the notice. In our view, this argument must be rejected,
        inasmuch as Section 49(1) itself states that the purchase
        notice must require the appropriate authority to purchase
        the interest in the land “in accordance with the provisions
        of this Act”. This being so, once the appropriate authority
        makes the necessary application to acquire the land within
        time under Section 49(7), we move over to Sections 126
        and 127 of the Act.
[2025] 2 S.C.R.                                                           1221

            Nirmiti Developers Through its Partners & Anr. v.
                     The State of Maharashtra & Ors.

           14. Under Section 126(1)(c), when after the publication
           of a draft regional plan or development or other plan,
           any land is required or reserved for a public purpose,
           the appropriate authority may make an application to the
           State Government, for acquiring such land under the Land
           Acquisition Act. Under sub-section (2) thereof, on receipt
           of such application, if the State Government is satisfied
           that the land specified in the application is needed for the
           public purpose specified therein, then excepting the cases
           falling under Section 49, the State Government may make
           a declaration under Section 6 of the Land Acquisition Act,
           to that effect. However, such declaration under Section
           126(2) must be made within a period of one year from
           the date of publication of the plan in question.
           15. A purchase notice may be served under Section 49,
           after the expiry of one year from the date of publication of
           the plan in question, in which case Section 126(2) of the Act
           will not apply. Under Section 126(4), the State Government
           may make a declaration under Section 6 subject to the
           modification that the market value of the land shall be the
           market value at the date of the declaration in the official
           gazette made for acquiring the land. But this does not
           mean that the State Government has carte blanche to do
           as it pleases. Ordinarily, the State Government is bound
           to act under Section 126(4) within a reasonable time from
           the appropriate authority making an application to acquire
           the land. This should ordinarily be within a period of one
           year from the date such an application is made. However,
           if such declaration is not made within the aforesaid period,
           it will be open for the aggrieved person to move the Court
           to direct the State Government to make the requisite
           declaration immediately.
           16. But the matter does not end here. Thereafter, Section
           127 kicks in. If a declaration under Section 6 of the Land
           Acquisition Act is not made within a period of 10 years
           from the date on which a plan comes into force under
           sub-section (4) of Section 126, the owner or any person
           interested in the land may serve a purchase notice on the
           authorities, and if within one year from the date of service
1222                                                        [2025] 2 S.C.R.

                         Supreme Court Reports


          of such notice, the land is not acquired or no steps are
          commenced for its acquisition, the reservation, allotment
          or designation shall be deemed to have lapsed.”
28. In Girnar Traders v. State of Maharashtra reported in (2007) 7 SCC
    555, a three-Judge Bench, by a majority judgment delivered by
    Naolekar, J. framed the question before the Court thus:
          “19. The question that requires consideration and answer
          in the present case is: Whether the reservation has lapsed
          due to the failure of the planning authority to take steps
          within the period of six months from the date of service of
          the notice of purchase as stipulated by Section 127 of the
          MRTP Act; and also the question as regards applicability
          of new Section 11-A of the LA Act to the acquisition of
          land under the MRTP Act.”
29. After setting out Sections 126 and 127 respectively, this Court
    then laid down the scheme of Section 126, which makes it clear
    that the Section 6 notification under the Land Acquisition Act is
    to be issued, in cases where acquisition is made under Section
    126(1)(c), in pursuance of an application by an appropriate authority
    to the State Government within one year from the publication of the
    plan in question, or by way of the State Government making a fresh
    declaration beyond a period of one year under Section 126(4). This is
    stated by the Court in para 28 as follows: (Girnar case SCC para 28)
          “28. Sub-section (2) of Section 126 provides for one year’s
          limitation for publication of the declaration from the date
          of publication of the draft plan or scheme. Sub-section
          (4), however, empowers the State Government to make
          a fresh declaration under Section 6 of the LA Act even
          if the prescribed period of one year has expired. This
          declaration is to be issued by the State Government for
          acquisition of the land without there being any application
          moved by the planning/local authority under clause (c) of
          Section 126(1).”
30. Insofar as Section 127 is concerned, the Court went on to hold:
    (Girnar case, paras 31-32)
          “31. Section 127 prescribes two-time periods. First, a period
          of 10 years within which the acquisition of the land reserved,
[2025] 2 S.C.R.                                                            1223

            Nirmiti Developers Through its Partners & Anr. v.
                     The State of Maharashtra & Ors.

           allotted or designated has to be completed by agreement
           from the date on which a regional plan or development
           plan comes into force, or the proceedings for acquisition
           of such land under the MRTP Act or under the LA Act are
           commenced. Secondly, if the first part of Section 127 is
           not complied with or no steps are taken, then the second
           part of Section 127 will come into operation, under which
           a period of six months is provided from the date on which
           the notice has been served by the owner within which the
           land has to be acquired or the steps as aforesaid are to
           be commenced for its acquisition. The six month period
           shall commence from the date the owner or any person
           interested in the land serves a notice on the planning
           authority, development authority or appropriate authority
           expressing his intent claiming dereservation of the land. If
           neither of the things is done, the reservation shall lapse. If
           there is no notice by the owner or any person interested,
           there is no question of lapsing reservation, allotment
           or designation of the land under the development plan.
           Second part of Section 127 stipulates that the reservation
           of the land under a development scheme shall lapse if the
           land is not acquired or no steps are taken for acquisition
           of the land within the period of six months from the date
           of service of the purchase notice. The word “aforesaid”
           in the collocation of the words “no steps as aforesaid are
           commenced for its acquisition” obviously refers to the steps
           contemplated by Section 126 of the MRTP Act
           32. If no proceedings as provided under Section 127
           are taken and as a result thereof the reservation of the
           land lapses, the land shall be released from reservation,
           allotment or designation and shall be available to the
           owner for the purpose of development. The availability
           of the land to the owner for the development would only
           be for the purpose which is permissible in the case of
           adjacent land under the relevant plan. Thus, even after
           the release, the owner cannot utilise the land in whatever
           manner he deems fit and proper, but its utilisation has
           to be in conformity with the relevant plan for which the
           adjacent lands are permitted to be utilised.”
1224                                                        [2025] 2 S.C.R.

                         Supreme Court Reports


31. The Court then went on to consider Municipal Corpn. of Greater
    Bombay v. Dr Hakimwadi Tenants’ Assn reported in 1988 Supp SCC
    55, and was of opinion that, the observations on the expression “no
    steps as aforesaid are commenced for its acquisition” stipulated under
    Section 127 were obiter in nature. The majority then went on to state
    the law under Section 127 as follows: (Girnar case paras 54-57)
          “54. When we conjointly read Sections 126 and 127 of
          the MRTP Act, it is apparent that the legislative intent is
          to expeditiously acquire the land reserved under the Town
          Planning Scheme and, therefore, various periods have
          been prescribed for acquisition of the owner’s property. The
          intent and purpose of the provisions of Sections 126 and
          127 has been well explained in Municipal Corpn. of Greater
          Bombay case [Municipal Corpn. of Greater Bombay v. Dr
          Hakimwadi Tenants’ Assn., 1988 Supp SCC 55]. If the
          acquisition is left for time immemorial in the hands of the
          authority concerned by simply making an application to
          the State Government for acquiring such land under the
          LA Act, 1894, then the authority will simply move such
          an application and if no such notification is issued by the
          State Government for one year of the publication of the
          draft regional plan under Section 126(2) read with Section
          6 of the LA Act, wait for the notification to be issued by the
          State Government by exercising suo motu power under
          sub-section (4) of Section 126; and till then no declaration
          could be made under Section 127 as regards lapsing of
          reservation and contemplated declaration of land being
          released and available for the landowner for his utilisation
          as permitted under Section 127. Section 127 permitted
          inaction on the part of the acquisition authorities for a
          period of 10 years for dereservation of the land. Not
          only that, it gives a further time for either to acquire the
          land or to take steps for acquisition of the land within a
          period of six months from the date of service of notice
          by the landowner for dereservation. The steps towards
          commencement of the acquisition in such a situation
          would necessarily be the steps for acquisition and not a
          step which may not result into acquisition and merely for
          the purpose of seeking time so that Section 127 does not
          come into operation.
[2025] 2 S.C.R.                                                              1225

            Nirmiti Developers Through its Partners & Anr. v.
                     The State of Maharashtra & Ors.

           55. Providing the period of six months after the service
           of notice clearly indicates the intention of the legislature
           of an urgency where nothing has been done in regard
           to the land reserved under the plan for a period of 10
           years and the owner is deprived of the utilisation of his
           land as per the user permissible under the plan. When
           mandate is given in a section requiring compliance within a
           particular period, the strict compliance is required therewith
           as introduction of this section is with legislative intent to
           balance the power of the State of “eminent domain”. The
           State possessed the power to take or control the property
           of the owner for the benefit of public cause, but when the
           State so acted, it was obliged to compensate the injured
           upon making just compensation. Compensation provided
           to the owner is the release of the land for keeping the land
           under reservation for 10 years without taking any steps
           for acquisition of the same.
           56. The underlying principle envisaged in Section 127 of
           the MRTP Act is either to utilise the land for the purpose
           it is reserved in the plan in a given time or let the owner
           utilise the land for the purpose it is permissible under the
           town planning scheme. The step taken under the section
           within the time stipulated should be towards acquisition
           of land. It is a step of acquisition of land and not step
           for acquisition of land. It is trite that failure of authorities
           to take steps which result in actual commencement of
           acquisition of land cannot be permitted to defeat the
           purpose and object of the scheme of acquisition under
           the MRTP Act by merely moving an application requesting
           the Government to acquire the land, which Government
           may or may not accept. Any step which may or may not
           culminate in the step for acquisition cannot be said to be
           a step towards acquisition.
           57. It may also be noted that the legislature while enacting
           Section 127 has deliberately used the word “steps” (in
           plural and not in singular) which are required to be taken
           for acquisition of the land. On construction of Section 126
           which provides for acquisition of the land under the MRTP
           Act, it is apparent that the steps for acquisition of the land
           would be issuance of the declaration under Section 6 of the
1226                                                        [2025] 2 S.C.R.

                         Supreme Court Reports


          LA Act. Clause (c) of Section 126(1) merely provides for a
          mode by which the State Government can be requested for
          the acquisition of the land under Section 6 of the LA Act.
          The making of an application to the State Government for
          acquisition of the land would not be a step for acquisition
          of the land under reservation. Sub-section (2) of Section
          126 leaves it open to the State Government either to
          permit the acquisition or not to permit, considering the
          public purpose for which the acquisition is sought for by
          the authorities. Thus, the steps towards acquisition would
          really commence when the State Government permits the
          acquisition and as a result thereof publishes the declaration
          under Section 6 of the LA Act.”
32. The scheme of Sections 126(2) and (4) was again reiterated in para
    61 as follows: (Girnar case para 161)
          “61. Proviso to sub-section (2) of Section 126 prohibits
          publication of the declaration after the expiry of one
          year from the date of publication of draft regional plan,
          development plan or any other plan or scheme. Thus,
          from the date of publication of the draft regional plan,
          within one year an application has to be moved under
          clause (c) of Section 126(1) which should culminate into
          a declaration under Section 6 of the LA Act. As per the
          proviso to sub-section (2) of Section 126, the maximum
          period permitted between the publication of a draft regional
          plan and declaration by the Government in the Official
          Gazette under Section 126(2) is one year. In other words,
          during one year of the publication of the draft regional plan,
          two steps need to be completed, namely, (i) application
          by the appropriate authority to the State Government
          under Section 126(1)(c); and (ii) declaration by the State
          Government on receipt of the application mentioned in
          clause (c) of Section 126(1) on satisfaction of the conditions
          specified under Section 126(2). The only exception to this
          provision has been given under Section 126(4).”
33. In Shrirampur Municipal Council v. Satyabhamabai Bhimaji Dawkher
    reported in (2013) 5 SCC 627, this Court reiterated the findings given
    in Girnar (supra) majority judgment, and held that there was no
    conflict between the judgment in Hakimwadi (supra) and the majority
    judgment in Girnar(supra). This Court, thereafter, went on to hold:
[2025] 2 S.C.R.                                                              1227

            Nirmiti Developers Through its Partners & Anr. v.
                     The State of Maharashtra & Ors.

           “42. We are further of the view that the majority in Girnar
           Traders [Girnar Traders v. State of Maharashtra, (2007)
           7 SCC 555] had rightly observed that steps towards
           the acquisition would really commence when the State
           Government takes active steps for the acquisition of the
           particular piece of land which leads to publication of the
           declaration under Section 6 of the 1894 Act. Any other
           interpretation of the scheme of Sections 126 and 127 of
           the 1966 Act will make the provisions wholly unworkable
           and leave the landowner at the mercy of the Planning
           Authority and the State Government.
           43. The expression “no steps as aforesaid” used in
           Section 127 of the 1966 Act has to be read in the context
           of the provisions of the 1894 Act and mere passing of a
           resolution by the Planning Authority or sending of a letter
           to the Collector or even the State Government cannot
           be treated as commencement of the proceedings for the
           acquisition of land under the 1966 Act or the 1894 Act.
           By enacting Sections 125 to 127 of the 1966 Act, the
           State Legislature has made a definite departure from the
           scheme of acquisition enshrined in the 1894 Act. But a
           holistic reading of these provisions makes it clear that while
           engrafting the substance of some of the provisions of the
           1894 Act in the 1966 Act and leaving out other provisions,
           the State Legislature has ensured that the landowners/other
           interested persons, whose land is utilised for execution of
           the development plan/town planning scheme, etc., are not
           left high and dry. This is the reason why time-limit of ten
           years has been prescribed in Section 31(5) and also under
           Sections 126 and 127 of the 1966 Act for the acquisition of
           land, with a stipulation that if the land is not acquired within
           six months of the service of notice under Section 127 or
           steps are not commenced for acquisition, reservation of
           the land will be deemed to have lapsed. Shri Naphade’s
           interpretation of the scheme of Sections 126 and 127, if
           accepted, will lead to absurd results and the landowners
           will be deprived of their right to use the property for an
           indefinite period without being paid compensation. That
           would tantamount to depriving the citizens of their property
           without the sanction of law and would result in violation
           of Article 300-A of the Constitution.”
1228                                                         [2025] 2 S.C.R.

                         Supreme Court Reports


34. It is, thus, clear that the scheme of Sections 126 and 127 respectively
    would leave nobody in doubt, for the reason that if a period of 10
    years has elapsed from the date of publication of the plan in question,
    and no steps for acquiring the land have been taken, then once a
    purchase notice is served under Section 127, steps to acquire the
    land must follow within a period of one year from the date of service
    of such notice, or else the land acquisition proceedings would lapse.
35. This Court in Chhabildas (supra) summed up the position in law as
    under:
          “24.1. In all Section 49 cases, where a purchase notice has
          been served and is confirmed within the period specified, the
          appropriate authority must make an application to acquire
          the land within one year from the date of confirmation of
          the notice. If it does not do so, the reservation, designation,
          etc. shall be deemed to have lapsed.
          24.2. If within the period specified in Section 49(7), the
          appropriate authority makes the requisite application, then
          the State Government may acquire the land by making a
          declaration under Section 6 of the Land Acquisition Act as
          set out under Section 126(4), wherein the market value
          shall be the market value of the land as on the date of
          Section 6 declaration. Ordinarily, such declaration must be
          made within 1 year of the date of receipt of the requisite
          application. In case this is not done, it will be open to the
          aggrieved person to move the Court to direct the State
          Government to make the requisite declaration immediately.
          24.3. If 10 years have passed from the date of publication of
          the plan in question, and a purchase notice has been served
          under Section 127, and no steps have been taken within a
          period of one year from the date of service of such notice,
          all proceedings shall be deemed to have lapsed. Thus, even
          in cases covered by Section 49, the drill of Section 126(4)
          and Section 127 will have to be followed, subsequent to
          the appropriate authority making an application to acquire
          the land within the period specified in Section 49(7).”
36. We take notice of the following:
     a.   On 11-01-1967, the MRTP Act came into force in the State of
          Maharashtra.
[2025] 2 S.C.R.                                                       1229

            Nirmiti Developers Through its Partners & Anr. v.
                     The State of Maharashtra & Ors.

     b.    The property in question – Vacant plot admeasuring 50,138.
           Sq ft in Survey No. 81/3 (NEW) 3 (old) in Mouza Rajapeth
           Amravati, Maharashtra was originally owned jointly by Smt.
           Akhtar Bano Rashid, Abdul Majid A. Samad and Mohd. Sajid
           A. Samad respectively which was a part of the bigger plot
           admeasuring 2.47 hectare.
     c.    The erstwhile owners had submitted Land Development Plan
           for development of 2.47 hectare. The respondent No. 3 herein
           sanctioned the development plan for residential area and the
           remaining area admeasuring 50,138 sq. ft. was reserved for
           Government school.
     d.    On 25-02-1993, the revised development plan for Amravati
           came into effect in which the property in question was shown
           as reserved for a private school i.e., for the respondent No.
           5. Respondent No. 5 is a Public Trust registered under the
           Maharashtra Public Trust Act, 1950.
     e.    From 1993 till 2006 no action was taken by the respondents
           to acquire the property for the private school.
     f.    On 04-07-2006, the erstwhile owners served purchase notice
           under Section 49 of the Act, 1966 on respondent No. 1 calling
           upon him either to acquire the said property or release it from
           reservation.
     g.    On 02-01-2007, the respondent No. 1 confirmed the purchase
           notice issued by the erstwhile owners.
     h.    By a letter dated 02-01-2007, the respondent No. 1 directed
           the respondent No. 5 to complete the acquisition proceedings
           within twelve months from the 02-01-2007 failing which the
           reservation would lapse and the property would stand released
           from reservation.
     i.    Respondent No. 1 was aware that the land acquisition
           proceedings had to be completed within twelve months from
           02-01-2007 i.e., by 02-01-2008 failing which the property would
           stand de-reserved by operation of Section 49(7) of the MRTP Act.
     j.    On 29-12-2007, i.e., just three days before the expiry of the last
           date of acquiring the property i.e., 02-01-2008, the respondent
           No. 5 issued a letter to the respondent No. 7 to commence the
           land acquisition proceedings under Section 126 of the MRTP Act.
1230                                                      [2025] 2 S.C.R.

                        Supreme Court Reports


     k.   On 13-08-2014, erstwhile owner issued purchase notice under
          Section 127 of the MRTP Act to Respondent Nos. 1,3,4 and 6
          requesting them to acquire their land.
     l.   Indisputably, till 2018 the respondent No. 3 did not make any
          application to acquire the property and no notification under
          Section 6 of the Land Acquisition Ac t, 1894 was published by
          the competent authority.
     m.   Indisputably, no amount towards compensation was deposited
          by the respondent No. 5 with any authority for the said property.
     n.   Thus, by operation of Section 49(7) of the MRTP Act reservation
          of the property lapsed on 02-01-2008 and the erstwhile owners
          were free to use the same as permissible in law.
     o.   On 09-04-2015, the erstwhile owners submitted an application
          addressed to the respondent No. 4 seeking permission to
          construct boundary wall surrounding the property with a view
          to prevent encroachment.
     p.   The respondent No. 4 vide letter dated 27-08-2015 declined to
          grant the permission to put up the wall on the ground that the
          property was reserved for respondent No. 5.
     q.   On 30-12-2015 by registered sale deed the erstwhile owners
          sold the property to the appellants herein.
     r.   On 16-03-2016 the appellants herein filed a writ petition seeking
          direction that either the respondent No. 5 shall deposit the
          amount towards compensation for the land reserved for it since
          1993 or declare that the reservation had lapsed under Section
          49(7) of the MRTP Act.
37. According to the learned counsel appearing for the appellants, in
    view of the aforesaid, the reservation lapsed even under Section
    127 on 13-08-2015.
38. It is very unfortunate to note that although the land was reserved
    almost 33 years back for the benefit of Respondent No.5 yet the
    said respondent was unable to avail the benefit of the same.
39. It does not make any good sense to keep a plot reserved in a
    development plan for past 33 years. The Authority did not allow the
    original owners to use the land and are now not permitting even the
    purchasers i.e. the appellants – herein to utilize the land.
[2025] 2 S.C.R.                                                            1231

            Nirmiti Developers Through its Partners & Anr. v.
                     The State of Maharashtra & Ors.

40. This Court in Chhabildas (supra) after explaining the provisions of
    Sections 49 and 127 of the MRT Act respectively thought fit to invoke
    Article 142 of the Constitution to do complete justice having regard
    to the long and inordinate delay in acquiring the land.
41. In the aforesaid context, we may refer to paras 25 to 31 of the
    Chhabildas (supra) as under:
           “25. The learned counsel appearing for the State has
           relied upon this Court’s judgment in Prakash R. Gupta v.
           Lonavala Municipal Council and others, (2009) 1 SCC 514,
           wherein this Court held that the scheme contemplated by
           Section 49 is totally different from that of Section 127, for
           the reason that there is no period of 10 years in Section
           49 as mentioned in Section 127.
           26. This judgment does not carry the matter any further
           as it is clear that, once an application is made within the
           requisite period contained in Section 49(7), land acquisition
           must follow in terms of Section 49(1) to purchase the
           interest in the land, in accordance with the provisions of
           the MRTP Act, as indicated above.
           27. This Court, in Hasmukhrai V. Mehta v. State of
           Maharashtra & Ors., (2015) 3 SCC 154, held that where
           an inordinately long delay takes place from the date on
           which the appropriate authority makes an application to
           acquire the land (in that case 20 years), the land in question
           stands released from reservation.
           28. In the aforesaid judgment, the purchase notice under
           Section 49 of the Act was dated 17th August, 2000. The
           Director, Town Planning, wrote a letter to the Chief Officer
           of the Khopoli Municipal Council stating that proceedings
           for land acquisition for an Agricultural Produce Market Yard
           would be initiated within one year from 16th March, 2001.
           Consequently, the Khopoli Municipal Council wrote a letter
           on 23rd April, 2001 to the Agricultural Produce Market
           Committee to initiate acquisition proceedings. As nothing
           was done, the Appellant ran from pillar to post and ultimately
           filed a writ petition in February, 2004, complaining that the
           Respondents are neither acquiring the land belonging to
           the Appellant nor releasing the same from reservation
           for the Agricultural Produce Market Yard. The High Court
1232                                                     [2025] 2 S.C.R.

                      Supreme Court Reports


        dismissed the aforesaid writ petition stating that as the
        provisions of Section 127 were not attracted, there could
        be no lapse. This Court, after referring to Sections 49 and
        127 of the Act, held:
             “12. We think it pertinent to mention here that APMC,
             Respondent 5, even after service of notice, has not
             cared to contest this appeal. Also, we think it relevant
             to mention that till date no steps appear to have been
             taken for acquisition of the land in question or to
             release the same. The land of the appellant, in our
             opinion, cannot be held up, without any authority of
             law, as neither the same is purchased till date by the
             respondent authorities, nor acquired under any law,
             nor the appellant is being allowed to use the land
             for the last more than twenty years.”
        29. It thereafter referred to Vijayalakshmi v. Town Planning
        Member (2006) 8 SCC 502 and Girnar (supra) and then
        held:
             “15. In view of the principle of law laid down by
             this Court, as above, we are of the view that in the
             present case since neither have steps been taken
             by the authorities concerned for acquisition of the
             land, nor is the land of the appellant purchased under
             purchase notice, nor is he allowed to use the land for
             the last more than twenty years, the land will have
             to be released as the appellant cannot be deprived
             from utilising his property for an indefinite period.

                         xxx        xxx        xxx
             18. Accordingly, we allow the appeal and set aside
             the impugned order passed by the High Court. Since
             no steps appear to have been taken till date for the
             last more than twenty years either for acquisition or
             for purchase of the land under the MRTP Act, 1966
             by the authorities concerned, as such, the land in
             question stands released from reservation under
             Section 127 of the MRTP Act.”
        30. The aforesaid judgment lays down that since more than
        20 years had elapsed since the date of the purchase notice
[2025] 2 S.C.R.                                                             1233

            Nirmiti Developers Through its Partners & Anr. v.
                     The State of Maharashtra & Ors.

           under Section 49 on the facts of that case, the land will
           have to be released from acquisition. No doubt this Court
           held that over 20 years is an inordinately long period of
           delay, and therefore, lapsing has taken place under Section
           127 of the MRTP Act. However, on the facts of that case,
           no purchase notice under Section 127 was issued after
           10 years had elapsed from the date of publication of the
           requisite plan. This being the case, we read the judgment
           as having allowed a lapse to take place, in view of the
           inordinately long delay of over 20 years, by really doing
           complete justice on the facts of that case under Article
           142 of the Constitution of India.
           31. In the present case, 15 years have passed since the
           date of publication of the development plan, and over 10
           years have passed since the date of the purchase notice
           issued under Section 49. Considering the fact that there
           has been no stay at any stage by any Court, it is clear that
           an inordinately long period of time has elapsed, both since
           the date of publication of the development plan, as well as
           the date of the purchase notice served under Section 49.
           No doubt, the letter of 26.9.2008 shows that an application
           was made within the requisite time period to acquire the
           aforesaid land. However, on the facts of this case, since after
           the aforesaid letter nothing has been done to acquire the
           appellant’s property, we are of the view that the reservation
           contained in the development plan as well as acquisition
           proposal have lapsed. We make it clear that we hold this
           in order to do complete justice between the parties under
           Article 142 of the Constitution of India. However, in all
           future cases that may arise under the provisions of Section
           49, the drill of Section 127 must be followed, i.e. that after
           10 years have elapsed from the date of publication of the
           relevant plan, a second purchase notice must be served
           in accordance with the provisions of Section 127, in order
           that lapsing can take place under the aforesaid section.
           With these observations, the appeal is disposed of.”
42. In the context of delay, we would also like to refer to the decision of
    this Court in the case of Bhavnagar Universit v. Palitana Sugar Mills
    Pvt. Ltd. and Others reported in AIR 23 SC 511 more particularly
    paras 27, 32 to 35 and 38 respectively as under:
1234                                                       [2025] 2 S.C.R.

                       Supreme Court Reports


        “27. An owner of a property, subject to reasonable restrictions
        which may be imposed by the Legislature, is entitled to
        enjoy the property in any manner he likes. A right to use a
        property in a particular manner or in other words a restriction
        imposed on user thereof except in the mode and manner
        laid down under statute would not be presumed.

                          xxx        xxx        xxx
        32. Subsection (2) of Section 20, however, carves out an
        exception to the exercise of powers by the State as regards
        acquisition of the land for the purpose of carrying out the
        development of the area in the manner provided for therein;
        a bare reading whereof leaves no manner of doubt that
        in the event the land referred to under subsection (1) of
        Section 20 thereof is not acquired or proceedings under
        the Land Acquisition Act are not commenced and further
        in the event an owner or a person interested in the land
        serves a notice in the manner specified therein, certain
        consequences ensue, namely, the designation of the land
        shall be deemed to have lapsed. A legal fiction, therefore,
        has been created in the said provision.
        33. The purpose and object of creating a legal fiction in
        the statute is well known. When a legal fiction is created,
        it must be given its full effect. In East End Dwelling Co.
        Ltd. v. Finsbury Borough Council, [(1951) 2 All.E.R 587],
        Lord Asquith, J. stated the law in the following terms:”
        If you are bidden to treat an imaginary state of affairs as
        real, you must surely, unless prohibited from doing so,
        also imagine as real the consequences and incidents
        which, if the putative state of affairs had in fact existed,
        must inevitably have flowed from or accompanied it. One
        of these in this case is emancipation from the 1939 level
        of rents. The statute says that you must imagine a certain
        state of affairs; it does not say that having done so, you
        must cause or permit your imagination to boggle when it
        comes to the inevitable corollaries of that state of affairs.”
        The said principle has been reiterated by this Court
        in M. Venugopal v. Divisional Manager, Life Insurance
        Corporation of India, Machilipatnam, A.P. & Anr. [(1994) 2
[2025] 2 S.C.R.                                                            1235

            Nirmiti Developers Through its Partners & Anr. v.
                     The State of Maharashtra & Ors.

           SCC 323]. See also Indian Oil Corporation Limited v. Chief
           Inspector of Factories & Ors. etc., [(1998) 5 SCC 738],
           Voltas Limited, Bombay v. Union of India & Ors.,[(1995)
           Supp. 2 SCC 498], Harish Tandon v. Addl. District
           Magistrate, Allahabad, U.P. & Ors. [(1995) 1 SCC 537]
           and G. Viswanathan etc. v. Hon’ble Speaker, Tamil Nadu
           Legislative Assembly, Madras & Anr. [(1996) 2 SCC 353].
           34. The relevant provisions of the Act are absolutely
           clear, unambiguous and implicit. A plain meaning of the
           said provisions, in our considered view, would lead to
           only one conclusion, namely, that in the event a notice is
           issued by the owner of the land or other person interested
           therein asking the authority to acquire the land upon
           expiry of the period specified therein viz. ten years from
           the date of issuance of final development plan and in the
           event pursuant to or in furtherance thereof no action for
           acquisition thereof is taken, the designation shall lapse.
           35. This Court in Municipal Corporation of Greater Bombay’s
           case (supra), in no uncertain terms while construing the
           provisions of Section 127 of the Maharashtra Regional
           and Town Planning Act, 1966 held the period of ten years
           as reasonable in the following words:
                “While the contention of learned counsel appearing
                for the appellant that the words ‘six months from the
                date of service of such notice’ in Section 127 of the
                Act were not susceptible of a literal construction,
                must be accepted, it must be borne in mind that the
                period of six months provided by Section 127 upon
                the expiry of which the reservation of the land under
                a Development Plan lapses, is a valuable safeguard
                to the citizen against arbitrary and irrational executive
                action. Section 127 of the Act is a fetter upon the
                power of eminent domain. By enacting Section 127
                the legislature has struck a balance between the
                competing claims of the interests of the general public
                as regards the rights of an individual.”
     It was observed that:
           “The Act lays down the principles of fixation by providing
           first, by the proviso to Section 126(2) that no such
1236                                                    [2025] 2 S.C.R.

                      Supreme Court Reports


        declaration under subsection (2) shall be made after the
        expiry of three years from the date of publication of the
        draft regional plan, development plan or any other plan,
        secondly, by enacting subsection (4) of Section 126 that
        if a declaration is not made within the period referred
        to in subsection (2), the State Government may make
        a fresh declaration but, in that event, the market value
        of the land shall be the market value at the date of the
        declaration under Section 6 and not the market value at
        the date of the notification under Section 4, and thirdly,
        by Section 127 that if any land reserved, allotted or
        designated for any purpose in any development plan is
        not acquired by agreement within 10 years from the date
        on which a final regional plan or development plan comes
        into force or if proceedings for the acquisition of such
        land under the Land Acquisition Act are not commenced
        within such period, such land shall be deemed to be
        released from such reservation, allotment or designation
        and become available to the owner for the purpose of
        development on the failure of the Appropriate Authority
        to initiate any steps for its acquisition within a period of
        six months from the date of service of a notice by the
        owner or any person interested in the land. It cannot
        be doubted that a period of 10 years is long enough.,
        The Development or the Planning Authority must take
        recourse to acquisition with some amount of promptitude
        in order that the compensation paid to the expropriated
        owner bears a just relation to the real value of the land
        as otherwise, the compensation paid for the acquisition
        would be wholly illusory. Such fetter on statutory powers
        is in the interest of the general public and the conditions
        subject to which they can be exercised must be strictly
        followed.”
        It is true that Section 21 of the Act imposes a statutory
        obligation on the part of the State and the appropriate
        authorities to revise the development plan and for the
        said purpose Section 9 to 20 ‘so far as may be’ would be
        applicable thereto, but thereby the rights of the owners in
        terms of subsection (2) of Section 20 are not taken away.

                         xxx        xxx       xxx
[2025] 2 S.C.R.                                                                1237

            Nirmiti Developers Through its Partners & Anr. v.
                     The State of Maharashtra & Ors.

           38. Section 21 does not envisage that despite the fact that
           in terms of subsection (2) of Section 20, the designation of
           land shall lapse, the same, only because a draft revised
           plan is made, would automatically give rise to revival
           thereof. Section 20 does not manifest a legislative intent
           to curtail or take away the right acquired by a landowner
           under Section 22 of getting the land defreezed. In the
           event the submission of the learned Solicitor General is
           accepted the same would completely render the provisions
           of Section 20(2) otiose and redundant.”
43. In the last, we may refer to the decision of this Court in the case
    of Chairman, Indore Vikas Pradhikaran v. Pure Industrial Coke and
    Chemicals Ltd. reported in (2007) 8 SCC 705 more particularly paras
    53, 54 and 55 respectively therein:
           “53. The right of property is now considered to be not only
           a constitutional right but also a human right.
           54. The Declaration of Human Rights (1789) enunciates
           under Article 17
                “since the right to property is inviolable and sacred, no
                one may be deprived thereof, unless public necessity,
                legally ascertained, obviously requires it and just and
                prior indemnity has been paid”.
           Further under Article 217 (IIII) of 10th December, 1948,
           adopted in the General Assembly Resolution it is stated
           that : (i) Everyone has the right to own property alone
           as well as in association with others. (ii) No one shall be
           arbitrarily deprived of his property.
           55. Earlier human rights were existed to the claim of
           individuals right to health, right to livelihood, right to shelter
           and employment etc. but now human rights have started
           gaining a multifacet approach. Now property rights are also
           incorporated within the definition of human rights. Even claim
           of adverse possession has to be read in consonance with
           human rights. As President John Adams (17971801)put it,:
           “Property is surely a right of mankind as real as liberty.”
           Adding,
1238                                                         [2025] 2 S.C.R.

                          Supreme Court Reports


                “The moment the idea is admitted into society that
                property is not as sacred as the laws of God, and
                that there is not a force of law and public justice to
                protect it, anarchy and tyranny commence”.”
44. The facts before us are very clear. We once again reiterate them
    before we close this matter:
    (i)    On 13-08-2014, the erstwhile owners issued purchase notice
           under Section 127 of the MRTP Act.
    (ii)   Development Plan came into effect on 25-02-1993.
    (iii) The land had to be acquired within ten years of 25-02-1993 in
          view of Section 127 of the Act which indisputably was not done.
    (iv) After the issuance of notice under Section 127 of the MRTP Act
         on 13-08-2014, the appropriate authority could have acquired
         the land within twelve months, i.e., on/or before 13-08-2015.
         The same was not done. This puts an end to the entire debate.
    (v)    The reservation could be said to have lapsed even under
           Section 127 on 13-08-2015.
45. In such circumstances, when the erstwhile owners sold the land
    to the appellants herein on 30-12-2015, there was no reservation.
46. This Court in the case of Prafulla C. Dave and Ors. v. Municipal
    Commissioner and Ors. reported in (2015) 11 SCC 90 held thus:
           “21. Under Section 127 of the M.R.T.P. Act, reservation,
           allotment or designation of any land for any public purpose
           specified in a development plan is deemed to have lapsed
           and such land is deemed to be released only after notice
           on the appropriate authority is served calling upon such
           authority either to acquire the land by agreement or to
           initiate proceedings for acquisition of the land either under
           the M.R.T.P. Act or under the Land Acquisition Act, 1894 and
           the said authority fails to comply with the demand raised
           thereunder. Such notice can be issued by the owner or any
           person interested in the land only if the land is not acquired
           or proceeding for acquisition are not initiated within 10
           years from the date on which the final development plan
           had come into force. After service of notice by the land
[2025] 2 S.C.R.                                                          1239

            Nirmiti Developers Through its Partners & Anr. v.
                     The State of Maharashtra & Ors.

           owner or the person interested, a mandatory period of six
           months has to be lapsed within which time the authority
           can still initiate the necessary action. Section 127 of the
           M.R.T.P. Act or any other provision of the M.R.T.P. Act
           does not provide for automatic lapsing of the acquisition,
           reservation or designation of the land included in any
           development plan on the expiry of 10 years. On the
           contrary, upon expiry of the said period of 10 years, the
           land owner or the person interested is mandated by the
           statute to take certain positive steps i.e. to issue/serve a
           notice and there must occur a corresponding failure on the
           part of the authority to take requisite steps as demanded
           therein in order to bring into effect the consequences
           contemplated by Section 127 of the M.R.T.P. Act………”
                                                 (Emphasis supplied)

47. Thus, the principles underlying in Section 127 of the MRTP Act is
    either to utilize the land for the purpose for which it is reserved in
    the timeline given or let the owner utilize the land for the purpose as
    permissible under the town planning scheme. The reservation shall
    be deemed to have lapsed if no steps are taken for acquisition of the
    said land within the prescribed period. Indisputably, in the present
    case, the respondents have not taken any steps to issue notification
    after receipt of the notice.
48. In Kolhapur Municipal corporation and Others v. Vasant Mahadev
    Patil (dead), through LRs & Ors. reported in (2022) 5 SCC 758, this
    Court held that when by operation of law the reservation is deemed to
    have lapsed under Section 127(1) of the MRTP Act, the reservation
    lapses for all purposes and for all times to come. In the said decision,
    this Court was further pleased to observe that on the deemed lapse
    of such reservation under Section 127(1) of the said Act no writ of
    mandamus can be issued by the High Court to direct acquisition of
    that land and pay compensation to the landowners as on the lapse
    of such reservation, the land becomes free and the landowners can
    use the land as if there was no reservation.
49. This Court in Municipal Corpn., Greater Mumbai v. Hiraman Sitaram
    Deorukhar reported in (2019) 14 SCC 411 was examining the
    reservation of land for a garden in a Development Plan in the year
1240                                                            [2025] 2 S.C.R.

                            Supreme Court Reports


     1966 but the same was not acquired even after purchase notice
     was served by the landowner. However, relying upon the judgment
     of this Court reported as Bangalore Medical Trust v. B.S. Muddappa
     reported in (1991) 4 SCC 54 and some other judgments, it was held
     that the land reserved for public park cannot be permitted to be
     converted for other public purposes.
50. The landowner cannot be deprived of the use of the land for years
    together. Once an embargo has been put on a landowner not to
    use the land in a particular manner, the said restriction cannot be
    kept open-ended for indefinite period. The statute has provided a
    period of ten years to acquire the land under Section 126 of the Act.
    Additional one year is granted to the landowner to serve a notice for
    acquisition prior to the amendment by Maharashtra Act 42 of 2015.
    Such timeline is sacrosanct and has to be adhered to by the State
    or by the authorities under the State.
51. In the result, the appeals are allowed and the impugned order passed
    by the High Court is set aside. It is declared that the reservation of
    the plot in question could be said to have lapsed by efflux of time
    in view of the provisions under Sections 126 and 127 of the MRTP
    Act respectively.
52. Having regard to the gross delay of almost thirty years even without
    the aid of Section 127 of the MRTP Act, we would have declared
    the reservation to have lapsed in exercise of our jurisdiction under
    Article 142 of the Constitution to do complete justice in the matter.
53. Pending applications if any shall stand disposed of.

     Result of the case: Appeals allowed.



     †
         Headnotes prepared by: Mukund P Unny, Hony. Associate Editor
                                 (Verified by: Shibani Ghosh, Adv.)


Search Indian case law

Ask in plain English, not just keywords. 25,000 AI words free, no card.

Try "de‑reservation of land"Sign in to search

For a digitally signed copy suitable for filing, refer to the court's own website. Only the court can issue one.

NIRMITI DEVELOPERS THROUGH ITS PARTNERS & ANR. versus THE STATE OF MAHARASHTRA & ORS. — 2025 INSC 265 - Legal Desk AI