PTC INDIA LTD.versusGAJENDRA HALDEA AND ORS.
- Citation
- 2009 INSC 476
- Decided
- 9 April 2009
- Disposal
- Appeal(s) allowed
- Bench
- ARIJIT PASAYAT
Holding
The order of the Appellate Tribunal for Electricity is beyond its jurisdiction and is set aside.
Summary
PTC India Ltd. appealed against an order of the Appellate Tribunal for Electricity (ATE) that, invoking Sections 60 and 66 of the Electricity Act, 2003, directed all Electricity Regulatory Commissions to fix trading margins as if they were tariff determinations. The appellant contended that the Tribunal lacked authority to make such directions under its revisional powers under Section 121 and that the respondent, Gajendra Haldea, was not an aggrieved person because he had not initiated any proceeding before a Commission. The High Court examined the scope of Sections 60, 66, 121 and the standing provisions, relying on the Supreme Court’s decision in Grid Corporation of Orissa Ltd. v. Gajendra Haldea (2008). It held that the Tribunal’s order exceeded its jurisdiction and that the respondent could not be treated as a person aggrieved under the Act. Consequently, the Tribunal’s order was set aside and the appeal was allowed.
Issues considered
- Whether the Appellate Tribunal for Electricity can, under Section 121, direct Regulatory Commissions to fix trading margins as if they were tariff determinations.
- Whether the respondent Gajendra Haldea has locus standi to challenge the Tribunal’s order under the Electricity Act, 2003.
Legislation cited
- Electricity Act, 2003s. 111, s. 121, s. 142, s. 60, s. 66
Subjects
Judgment
[2009] 5 S.C.R. 815
_;
PTC INDIA LTD. A
v.
GAJENDRA HALDEA AND ORS.
(Civil Appeal No. 68 of 2007)
APRIL 09, 2009
B
[DR. ARIJIT PASAYAT AND ASOK KUMAR
GANGULY, JJ.]
ELECTRICITY ACT, 2003:
c
ss. 60 and 121 -Appellate Tribunalfor Electricity- Power
of - Plea that Tribunal invoked s. 60 to direct all Regulatory
Commissions to fix trading margins as if it involved tariff
determination - HELD: Order passed by Tribunal cannot be
maintained and is set aside. D
The instant appeal was filed against the order of the
Appellate Tribunal for Electricity. It was contended that in
view of s.60 of the Electricity Act, 2003, the Tribunal was
not empowered to fix trading margins in respect of
traders, intermediators etc. in exercise of its revisional E
supervisory powers u/s 121 of the Electricity Act, 2003. It
was also submitted that neither respondent no. 1 initiated
any proceedings before the Regulatory Commission
concerned nor did he make any grievance relating to
excessive exercise/non-exercise of jurisdiction by such F
Regulatory Commission.
Allowing the appeal, the Court
HELD: In view of the decision in Grid Corporation's*
case, the order passed by the Tribunal cannot be G
~ maintained and the same is set aside. [Para 6) (820-C-D]
Grid Corporation of Orissa Ltd. v. Gajendra Haldea and
815 H
816 SUPREME COURT REPORTS [2009] 5 S.C.R.
A Ors. 2008 (11) SCALE 313, relied on.
Case Law Reference: -
2008 (11) SCALE 313 relied on para 3
B CIVIL APPELLATE JURISDICTION: Civil Appeal No. 68
of 2007.
From the Judgment & Order dated 22.12.20Q6 of the
Appellate Tribunal for Electricity, New Delhi in Petition No. 1
of 2005.
c
Shanti Bhsuhan, M.G. Ramachandran, H.K. Puri, Pratik
Dham, C.K. Rai, D. Julis Regmei, Sridhar Potaraju, Sanjeev
Kumar, Avinash Menon, Vishal Gupta, Kumar Mihir (M/s. for
Khaitan & Co.) H. Wahi, Mamta Tushir, Somnath Padhan, Fox
D Mandal & Co., Ugra Shankar Prasad, A.K. Ganeshan, S.
Shashtri, K.V. Mohan, Jagjit Singh Chhabra, Raj Kumar Mehta,
U. Sharma, Amit Kapur, Poonam Verma, Anupam Verma, A.
Guneshwar Sharma, Shrestha Verma, Richa Srivastava (for
Gopal Jain), lndu Sharma for the appearing parties.
E The Judgment of the Court was delivered by
DR. ARIJIT PASAYAT, J. 1. Challenge in this appeal is
to the judgment passed by the Appellate Tribunal for Electricity,
New Delhi (hereinafter referred to as to the 'Tribunal'). The
F appeal has been filed under Section 125 of the Electricity Act,
2003 (in short the 'Act').
2. The primary stand of the appellant is that though the
Tribunal accepted that Electricity Regulatory Commissions (in
short the 'Regulatory Commission') did not have any power to
G determine tariff for trading, it invoked Sections 60 and 66 of
the Act to direct all Regulatory Commissions to fix trading
margins as if it involved tariff determination. Stand of the ~ .
appellant is that only appropriate Regulatory Commission can
invoke provisions of Section 60 upon arriving at a finding that
H
)
PTC INDIA LTD. v. GAJENDRA HALDEA AND ORS. 817
[DR. ARIJIT PASAYAT, J.]
,. a particular licensee or generator had conducted himself in the A
specified manner which has an adverse effect on competition
in the electricity industry. According to the appellant the Tribunal
issued directions on assumptions and presumptions without
~
any adjudication on tests laid down in Section 60 of the Act. In
essence, the stand is that the Tribunal is not empowered to B
determine tariff in exercise of its revisional supervisory powers
under Section 121 of the Act. It was pointed out that the
exercise of power under Section 121 of the Act was not
permissible because respondent No.1-Gajendra Haldea had
neither initiated any proceedings before the concerned c
Regulatory Commission and had also not made any grievance
relating to excessive exercise or non exercise of jurisdiction by
such Regulatory Commission. Strong reliance is placed on a
;
decision of this Court in Grid Corporation of Orissa Ltd. v.
Gajendra Haldea and Ors. (2008 (11) SCALE 313) holding
D
that respondent-Gajendra Ha Idea cannot be treated. as a
person aggrieved under the Act.
3. Respondent No.1 on the other hand supported the
judgment and submitted that Grid Corporation's case (supra)
has no application to the facts of the case. E
4. In order to appreciate the rival submissions Section 111
needs to be noted. The same reads as follows:
"111. Appeal to Appellate Tribunat.-(1) Any person
aggrieved by an order made by an adjudicating officer F
under this Act (except under section 127) or an order made
by the Appropriate Commission under this Act may prefer
an appeal to the Appellate Tribunal for Electricity:
Provided that any person appealing against the G
order of the adjudicating officer levying any penalty shall,
while filing the appeal, deposit the amount of such penalty:
Provided further that where in any particular case, the
Appellate Tribunal is of the opinion that the deposit of such
H
818 SUPREME COURT REPORTS [2009] 5 S.C.R.
A penalty would cause undue hardship to such person, it may
dispense with such deposit subject to such conditions as
it may deem fit to impose so as to safeguard the realisation
of penalty.
(2) Every appeal under sub-section (1) shall be filed within
B
a period of forty five days from the date on which a copy
of the order made by the adjudicating officer or the
Appropriate Commission is received by the aggrieved
person and it shall be in such form, verified in such manner
and be accompanied by such fee as may be prescribed:
c
Provided that the Appellate Tribunal may entertain an
appeal after the expiry of the said period of forty-five days
if it is satisfied that there was sufficient cause for not filing
it within that period.
D
(3) On receipt of an appeal under sub-section (1 ), the
Appellate Tribunal may, after giving the parties to the
appeal an opportunity of being heard, pass such orders
thereon as it thinks fit, confirming, modifying or setting
aside the order appealed against.
E
(4) The Appellate Tribunal shall send a copy of every order
made by it to the parties to the appeal and to the
concerned adjudicating officer or the Appropriate
Commission, as the case may be.
F
(5) The appeal filed before the Appellate Tribunal under
sub-section (1) shall be dealt with by it as expeditiously as
possible and endeavour shall be made by it to dispose of
the appeal finally within one hundred and eighty days from
G the date of receipt of the appeal:
Provided that where any appeal could not be
disposed of within the said period of one hundred and
eighty days, the Appellate Tribunal shall record its reasons
in writin{J for not disposing of the appeal within the said
H period.
PTC INDIA LTD. v. GAJENDRA HALDEA AND ORS. 819
J [DR. ARIJIT PASAYAT, J.]
(6) The Appellate Tribunal may, for the purpose of A
examining the legality, propriety or correctness of
Appropriate Commission under this Act, as the case may
be, in relation to any proceeding, on its own motion or
otherwise, call for the records of such proceedings and
make such order in the case as it thinks fit." B
5. In Grid Corporation's case (supra) it was inter-alia
observed as follows:
"15. It is unnecessary to go into the question as to the
nature of the transaction, because respondent No.1- C
Gajendra Haldea in order to prove that he had locus standi
relied on Sections 121 and 142 of the Act. It was also
· stated that it is not in the nature of PIL. It was stated that
the prayer for refund was not being pressed.
D
16. A bare reading of Sections 121 and 142 of the Act
which read as follows shows that those provisions are not
applicable.
"121. Power of Appellate Tribunal- The Appellate
Tribunal may, after hearing the Appropriate E
Commission or other interested party, if any, from
time to time, issue such orders, instructions or
directions as it may deem fit, to any Appropriate
Commission for the performance of its statutory
function under this Act. F
"142. Punishment for non-compliance of directions
by Appropriate Commission.-ln case any
complaint is filed before the Appropriate
Cpmmission by any person or if that Commission G
is satisfied that any person has contravened any of
the provisions of this Act or the rules or regulations
made thereunder, or any direction issued by the
Commission, the Appropriate Commission may
after giving such person an opportunity of being H
820 SUPREME COURT REPORTS [2009] 5 S.C.R.
A heard in the matter, by order in writing, direct that,
without prejudice to any other penalty to which he
may be liable under this Act, such person shall pay,
by way of penalty, which shall not exceed one lakh
rupees for each contravention and in case of a
B continuing failure with an additional penalty which
may extend to six thousand rupees for every day
during which the failure continues after
contravention of the first such direction."
17. Therefore, the Appellate Tribunal was wrong in
c interfering with the conclusions of CERC that respondent
No.1 's petition was not entertainable and/or maintainable."
6. The order passed by the Tribunal cannot be maintained
in view of what is stated in Grid Corporation's case (supra) arid
D is set aside. The appeal is allowed without any order as to
costs.
R.P. Appeal allowed.
•
Search Indian case law
Ask in plain English, not just keywords. 25,000 AI words free, no card.