R V PRASANNAKUMAAR & ORS.versusMANTRI CASTLES PVT. LTD & ANR.
- Citation
- 2019 INSC 174
- Decided
- 11 February 2019
- Disposal
- Disposed off
- Bench
- D Y CHANDRACHUD
Holding
The NCDRC may award just compensation and interest at 6% per annum until each purchaser is offered possession, and the contract‑specified rate of Rs 3 per sq ft per month is inadequate.
Summary
The flat purchasers entered into a purchase agreement that required possession by 31 January 2014, but the occupation certificate was only obtained on 10 February 2016. The National Consumer Disputes Redressal Commission (NCDRC) awarded compensation at Rs 3 per sq ft per month for the delay and interest at 6% per annum, but limited the interest to the period up to 31 July 2016. The purchasers appealed, arguing that the compensation rate was inadequate and that interest should continue until actual possession is offered; the developer appealed, contending that the agreement’s terms should control the award. The Supreme Court held that the stipulated Rs 3 per sq ft rate does not constitute just compensation, that the NCDRC’s jurisdiction to award just compensation and interest is not constrained by the contract, and that interest liability must continue until each buyer is offered possession. Accordingly, the Court allowed the purchasers’ appeal, modified the NCDRC order to extend interest until possession, and dismissed the developer’s appeals.
Issues considered
- Whether the compensation rate of Rs 3 per sq ft per month stipulated in the flat purchase agreement is just and reasonable under the Consumer Protection Act, 1986.
- Whether the NCDRC can award interest at 6% per annum beyond the period specified in the agreement and beyond 31 July 2016.
- Whether the liability to pay interest continues until actual possession is offered to each flat purchaser.
- Whether a purchaser who files a consumer complaint is entitled to possession despite the developer’s refusal.
Legislation cited
- Consumer Protection Act, 1986s. 12(1)(c)
Subjects
Judgment
[2019] 5 S.C.R. 821 821
R V PRASANNAKUMAAR & ORS. A
v.
MANTRI CASTLES PVT. LTD & ANR.
(Civil Appeal No. 1232 of 2019)
FEBRUARY 11, 2019 B
[DR. DHANANJAYA Y CHANDRACHUD AND
HEMANT GUPTA, JJ.]
Consumer Protection Act, 1986: Interest – Award of –
Justification – On facts, breach of flat purchase agreement – Outer C
date for handing over possession was 31.01.2014, however the
buyers received occupation certificate on 10.02.2016 – Consumer
complaint – Award of compensation by the National Consumer
Disputes Redressal Commission for delayed handing over of
possession from 01.02.2014 till 31.07.2016 as per the agreement,
D
at the rate of INR 3 per sq. ft. per month – National Commission
also awarded interest at the rate of 6 per cent per annum –
Justification of – Held: Compensation at the rate of 3 per sq. ft. per
month does not provide just or reasonable recompense to the flat
purchaser who has invested money and that too in a city like
Bangalore – Jurisdiction of the NCDRC to award just compensation E
cannot be constrained by the terms of the agreement – There was a
delay of at least two years in handing over the possession – Thus,
the award of interest at the rate of 6 per cent is reasonable and
justified – Liability of the developer to pay interest would continue
to operate until the date the respective flat purchasers is offered
F
possession – Furthermore, the flat purchasers who had moved
NCDRC in a representative capacity for redressal of their grievances
not disentitled to receive possession of the flat.
Allowing C.A. No. 1232 of 2019 and dismissing C.A.Nos.
1443-1444 of 2019, the Court
G
HELD: 1.1 The view of the National Consumer Disputes
Redressal Commission-NCDRC that the rate which has been
stipulated by the developer, of compensation at the rate of 3 per
sq. ft. per month does not provide just or reasonable recompense
to a flat buyer who has invested money and has not been handed
H
821
822 SUPREME COURT REPORTS [2019] 5 S.C.R.
A over possession as on the stipulated date of 31 January 2014, is
accepted. This in a city such as Bangalore does not provide just
or adequate compensation. The jurisdiction of the NCDRC to
award just compensation under the provisions of the Consumer
Protection Act, 1986 cannot in the circumstances be constrained
by the terms of the agreement. The agreement in its view is one
B
sided and does not provide sufficient recompense to the flat
purchasers. [Para 9][825-D-F]
1.2 The outer date for handing over possession was 31
January 2014. The admitted facts indicate that the occupation
certificate was received on 10 February 2016. Consequently,
C there was a delay of at least two years since possession could not
have been handed over prior to obtaining the occupation
certificate. In the circumstances, the award of interest at the rate
of 6 per cent is reasonable and justified. The NCDRC however,
came to the conclusion that interest should be awarded only for
D the period from 1 February 2014 to 31 July 2016. There is merit
in the submission of the flat buyers that the liability to pay interest
has been inappropriately confined only upto 31 July 2016. The
developer, in the affidavit by way of evidence of its representative
before the NCDRC, admitted that as many as 43 complainants,
who had asked for possession were not given possession for the
E simple reason that they had moved the NCDRC in a consumer
complaint. The fact that the flat purchasers had moved the NCDRC
in a representative capacity for the redressal of their grievances
is no justification to deny them possession in accordance with
the terms of the agreement. [Para 10-13][825-G-H; 826-A-C; F]
F 1.3 It emerges that even according to the developer, out of
55 flat purchasers, possession had been handed over to 16 and it
was stated that possession to 9 more buyers would be offered
within a period of one week. As amongst the 55 purchasers, 25
persons have been now offered possession and an additional 2
G would be offered possession shortly hereafter. [Paras 15, 16]
[827-D-F]
1.4 The NCDRC was not justified in proceeding on the basis
that the liability to pay interest would cease to operate as on 31
July 2016. Since possession has not been handed over, the
H developer cannot avoid the liability to pay interest at the rate
R V PRASANNAKUMAAR & ORS. v. MANTRI CASTLES PVT. 823
LTD & ANR.
awarded by the NCDRC until the date when possession is actually A
handed over. The liability of the developer to pay interest at the
rate of 6 per cent per annum would continue to operate until the
date on which each of the respective flat purchasers is offered
possession; The order passed by the NCDRC confining the award
of interest for the period from 1 February 2014 to 31 July 2016 is
B
modified in terms of the directions issued. [Para 17, 18]
[827-F-H; 828-A-B]
CIVIL APPELLATE JURISDICTION : Civil Appeal No. 1232
of 2019.
From the Judgment and Order dated 08.06.2018 of the National C
Consumer Disputes Redressal Commission in Consumer Complaint No.
913 of 2016.
With
Civil Appeal Nos. 1443-1444 of 2019.
D
Bishwajit Bhattacharya, P. S. Narasimha, Sr. Advs., Chandrachud
Bhattacharya, Abhinav Mukerji, Shekhar G. Devasa, Manish Tiwari, Luv
Kumar, Advs. for the appearing parties.
The Judgment of the Court was delivered by
DR. DHANANJAYA Y. CHANDRACHUD, J. E
1. The National Consumer Disputes Redressal Commission
(“NCDRC”) by its impugned order dated 8 June 2018 disposed of the
consumer complaint filed in a representative capacity under Section
12(1)(c) of the Consumer Protection Act, 1986. The NCDRC has come
to the conclusion that though under the terms of the flat purchase F
agreement, possession was liable to be handed over to the buyers on 31
January 2014, there was a breach on the part of the developer in
complying with its contractual obligations. The NCDRC has noticed that
the occupation certificate was received only on 10 February 2016 and it
was thereafter that from May 2016, certain letters offering possession
were issued by the developer. Based on this, the NCDRC awarded G
compensation upto 31 July 2016 in the form of interest at the rate of 6
per cent per annum.
2. There is a finding in the impugned order that though the flat
purchase agreement contained a stipulation for the payment of
compensation at the rate of INR 3 per sq. ft. per month for delayed H
824 SUPREME COURT REPORTS [2019] 5 S.C.R.
A handing over of possession, the amount as stipulated is too meager to
fulfil the requirement of just compensation to the purchasers.
Accordingly, the following directions have been issued in the impugned
order;
“i) The OPs are directed to handover the possession to the
B complainants (if not already handed over) within a period of 60
days from the date of this order and the complainants are also
directed to complete all the formalities for taking the possession.
ii) The complainants are entitled to get compensation for delayed
possession from 01.02.2014 till 31.07.2016 as per the agreement
C i.e. @ Rs. 3/- per sq. ft. per month. Over and above this amount,
the opposite parties shall be liable to pay interest @ 6% p.a. from
01.02.2014 till 31.07.2016 on complainants deposited amounts with
the CPs before the due date of possession i.e. 31.01.2014.
iii) OPs are directed to complete the common facilities and
D amenities as per the agreement within a period of six months
from the date of this order, failing which the OPs shall pay
compensation @ Rs. 1,000/- per month to each of the complainants
under the present complaint.
iv) The OPs are also directed to pay Rs. 2,000/- (Rupees two
E thousand only) to each of the complainants towards cost of litigation
in the present case.
v) All these amounts except compensation for common facilities
and amenities shall be adjusted against the amount due on the
complainants, if any, at the time of handing over of the possession
F and if no amount is due on the complainants, then the amount
shall be paid by the OPs to the complainants on the date of
possession.”
3. Two sets of appeals have been filed against the order of the
NCDRC. Civil Appeal No. 1232 of 2019 has been instituted by the flat
purchasers while Civil Appeal Nos. 1443-1444 of 2019 is filed by the
G
developer.
4. The flat purchasers are aggrieved by the order of the NCDRC
since it grants interest only upto 31 July 2016 and not thereafter.
5. Mr. Bishwajit Bhattacharya, learned senior counsel appearing
H on behalf of the flat buyers has submitted that the NCDRC was in error
R V PRASANNAKUMAAR & ORS. v. MANTRI CASTLES PVT. 825
LTD & ANR. [DR. DHANANJAYA Y. CHANDRACHUD, J.]
in assuming that all flat buyers had been given letters of offer for A
possession prior to 31 July 2016 which it has been submitted, is factually
incorrect.
6. Learned senior counsel submitted that as a matter of fact,
possession has not been offered to all the purchasers even as on date
and hence there was no justification on the part of the NCDRC to fasten B
the liability to pay interest only upto 31 July 2016 and not thereafter.
7. On the other hand, Mr. P.S. Narasimha, learned senior counsel
appearing on behalf of the developer has submitted that in view of the
conditions contained in the flat purchase agreement allowing
compensation at the rate of Rs. 3 per sq. ft. per month, the award of C
interest of 6 per cent per annum was not justified.
8. We will at the outset deal with the submission of the developer
that the NCDRC was not justified in awarding interest at the rate of 6
per cent per annum and that the terms of the flat purchase agreements
must prevail. D
9. We are in agreement with the view of the NCDRC that the
rate which has been stipulated by the developer, of compensation at the
rate of 3 per sq. ft. per month does not provide just or reasonable
recompense to a flat buyer who has invested money and has not been
handed over possession as on the stipulated date of 31 January 2014. E
To take a simple illustration, a flat buyer with an agreement of a flat
admeasuring a 1000 sq. ft. would receive, under the agreement, not
more than Rs 3000 per month. This in a city such as Bangalore does not
provide just or adequate compensation. The jurisdiction of the NCDRC
to award just compensation under the provisions of the Consumer
Protection Act, 1986 cannot in the circumstances be constrained by the F
terms of the agreement. The agreement in its view is one sided and does
not provide sufficient recompense to the flat purchasers.
10. The outer date for handing over possession was 31 January
2014. The admitted facts indicate that the occupation certificate was
received on 10 February 2016. Consequently, there was a delay of at G
least two years since possession could not have been handed over prior
to obtaining the occupation certificate.
11. In the circumstances, the award of interest at the rate of 6 per
cent is reasonable and justified. The NCDRC however, came to the
H
826 SUPREME COURT REPORTS [2019] 5 S.C.R.
A conclusion that interest should be awarded only for the period from 1
February 2014 to 31 July 2016.
12. We find merit in the submission of the flat buyers that the
liability to pay interest has been inappropriately confined only upto 31
July 2016. We find from the record that the developer, in the affidavit by
B way of evidence of its representative before the NCDRC, admitted that
as many as 43 complainants, who had asked for possession were not
given possession for the simple reason that they had moved the NCDRC
in a consumer complaint. The relevant part of the affidavit is extracted
below:-
C “I state that rest of the 43 complaints who have asked for
possession have not been given possession for the reason that as
on 29.06.2016, the Opposite parties had received notice of this
Hon’ble Commission in respect of filing of the present case. In
the present dispute, the complainants have sought prayer at para
A to G under different heads. While they sought the relief of
D handing over possession of their respective flats in para A, at
paras B, C, D, E and F, they have also sought certain reliefs of
compensation by making certain allegations of deficiency in
service, compensation for delay in possession etc., against the
opposite parties. Therefore, during the pendency of present
E dispute, the complainants were not given possession in view of
the reliefs sought in paras B to F and the statement of allegations
made in the present complaint.”
13. The fact that the flat purchasers had moved the NCDRC in a
representative capacity for the redressal of their grievances is in our
F view, no justification to deny them possession. The fact that the flat
purchasers had moved the NCDRC would not disentitle them to receive
possession in accordance with the terms of the agreement.
14. When the appeal filed by the developer came up before this
Court on 1 February 2019, the following order was passed;
G “Delay condoned.
Mr. P.S. Narasimha, learned senior counsel, has stated before the
Court that 55 flat purchasers are involved in the building project in
question. Learned senior counsel states on instructions that
possession has been handed over to sixteen flat buyers and
H possession to nine flat buyers will be offered and handed over
R V PRASANNAKUMAAR & ORS. v. MANTRI CASTLES PVT. 827
LTD & ANR. [DR. DHANANJAYA Y. CHANDRACHUD, J.]
within a period of one week from today. These 25 persons, it has A
been submitted, have paid the entirety of their dues under the flat
purchase agreement.
In respect of remaining 30 flat buyers, Mr. Narasimha states that
there are outstanding payments.
Learned senior counsel appearing on behalf of the respondents B
disputes this position. Learned senior counsel for the respondents
has submitted that 95 per cent of the payment has been made
while the balance 5 per cent is payable at the time of possession.
In view of this controversy, we direct the petitioners to place on
record an affidavit indicating the amounts which have been C
received from the remaining 30 flat buyers and the amount which
is due and payable in terms of the agreements with them.
List on 11 February 2019.
In the meantime, no coercive steps shall be taken against the D
petitioners in pursuance of the impugned order of the NCDRC.”
15. From the above order it emerges that even according to the
developer, out of 55 flat purchasers, possession had been handed over to
16 and it was stated that possession to 9 more buyers would be offered
within a period of one week.
E
16. Mr. P.S. Narasimha, learned senior counsel has stated that in
addition to the above 9 flat buyers, the developer will be handing over
possession to 2 more flat buyers immediately. This indicates that as
amongst the 55 purchasers, 25 persons have been now offered
possession and an additional 2 would be offered possession shortly
F
hereafter.
17. In view of the above position, the NCDRC was not justified in
proceeding on the basis that the liability to pay interest would cease to
operate as on 31 July 2016. Since possession has not been handed over,
the developer cannot avoid the liability to pay interest at the rate awarded
by the NCDRC until the date when possession is actually handed over. G
18. Hence, while allowing the appeal, we issue the following
directions:
(i) The liability of the developer to pay interest at the rate of 6
per cent per annum shall continue to operate until the date on H
828 SUPREME COURT REPORTS [2019] 5 S.C.R.
A which each of the respective flat purchasers is offered
possession;
(ii) The order passed by the NCDRC confining the award of
interest for the period from 1 February 2014 to 31 July 2016
is modified in terms of the directions issued in clause (i) above;
B (iii) The NCDRC in execution of the impugned order as modified
by the present order, shall verify with reference to each flat
purchaser the date on which an offer of possession has been
made. The liability to pay interest at the rate of 6 per cent per
annum shall cease on the date when an offer of possession
C has been made to each of the flat purchasers.
19. Accordingly, the appeal filed by the flat purchasers (Civil Appeal
No. 1232 of 2019) is allowed and the appeals filed by the developer
(Civil Appeal Nos. 1443-1444 of 2019) are dismissed.
20. Pending application(s), if any, shall stand disposed of.
D
Nidhi Jain Appeals disposed of.
E
F
G
H
Search Indian case law
Ask in plain English, not just keywords. 25,000 AI words free, no card.