SANGAMNER BHAG SAHAKARI KARKHANA LTD.versusMIS. KRUPP INDUSTRIES LTD.
- Citation
- 2002 INSC 269
- Decided
- 7 May 2002
- Disposal
- Disposed off
- Bench
- R C LAHOTI
Holding
The award was within the scope of the arbitration agreement and the civil judge’s discretion to remit it to the arbitrators was proper.
Summary
The appellant, a cooperative sugar factory, entered into a contract with the respondent for the design and supply of machinery, which contained an arbitration clause. Disputes arising under the contract were referred to two arbitrators who awarded Rs. 151.97 lacs to the appellant. The civil judge, finding apparent errors and a breach of natural justice, remitted the award to the arbitrators for a fresh determination under Section 16(1)(c) of the Arbitration Act, 1940. The High Court set aside the remittance, holding that part of the award was beyond the arbitrators' jurisdiction. The Supreme Court held that the disputes fell within the scope of the arbitration clause, the arbitrators had jurisdiction, and the civil judge’s discretion to remit the award was proper. Consequently, the High Court’s order was set aside, the civil judge’s order restored, and the award remitted to the arbitrators.
Issues considered
- Whether the arbitrators exceeded their jurisdiction by deciding matters beyond the scope of the arbitration clause.
- Whether the civil court correctly exercised its discretion under Section 16(1)(c) of the Arbitration Act, 1940 to remit the award back to the arbitrators.
Legislation cited
- Arbitration Act, 1940s. 16(1), s. 16(1)(c), s. 2(a)
Subjects
Judgment
-> SANGAMNER BHAG SAHAKARI KARKHANA LTD. A
v.
MIS. KRUPP INDUSTRIES LTD.
MAY7,2002
[R.C. LAHOTI AND B.N. AGRA WAL, JJ.] B
Arbitration Act, 1940-Sections 2(a) and 16(/)-Arbitration
agreement-Dispute-Arbitration clause-Reference-Scope of-Dispute
arising out of contract between the parties, arbitrators seized of the dispute, C
parties joining in contest before arbitrator. arbitrator passing an awCzrd-
Civil Judge remilling the award to arbitrator-However, High Court setting
aside remission order holding award beyond jurisdiction of arbitrator-On
facts, held, such award within the scope of reference to an arbitrator-
Remission of award by the Court in exercise of discretion correct.
D
Appellant-co--0perative sugar factory entered into an agreement with
respondent for design, manufacture, procurement and supply of machinery and
equipments. Disputes arose between the parties which were referred for
arbitration. Arbitrators passed an award directing Rs. 151.97 lacs to be paid
by the respondent to the appellant. Award was filed in the Court. Parties filed E
objections against the award. Civil Judge directed the award to be remitted
back to the arbitrators for rendering a fresh award. Appellant filed a revision
challenging remittance of the award while the respondent filed appeal
submitting that the award should have been set aside and there was no occasion
. for remitting the award to the arbitrators. Single Judge of High Court set
aside the remittance of the award to the arbitrators and also the award to the
extent of Rs. I 07.54 Lacs with interest since it was beyond the scope of
F
reference to the arbitrator. However, rest of the award was made rule of the
Court. Hence the present appeals.
Disposing of the appeals, the Court
G
HELD: It is the substance of the claim made before arbitrators which
has to be seen. Court would not construe the nature of claim by adopting too
technical an approach or by indulging into hair-splitting. Else the whole
purpose behind holding arbitration proceedings as an alternate to civil court's
forum would stand defeated. The arbitration clause and the disputes referred H
875
876 SUPREME COURT REPORTS (2002] 3 S.C.R.
A and adjudicated upon by the arbitrators have been perused carefully. It is
difficult to sustain the finding of the High Court that the arbitrators had
determined an issue which was beyond the scope of reference to the arbitration.
The disputes did arise out of the contract between the parties and the
arbitrators were seized of the disputes within the scope of reference to them.
B The parties have also joined in the contest before the arbitrators having
understood the scope of controversy. No fault can be found with the discretion
exercised by the Civil Judge, Senior Division, High Court has erroneously
formed an opinion that part of the award was beyond the jurisdiction of the
arbitrators. Thus, the order of High Court is set aside and that of the Civil
Judge is restored. The award shall stand remitted to the arbitrators in the
C terms as directed by the Civil Judge. (879-G, H; 880-A, B; D-F)
Renusagar Power Co. ltd. v. General Electric Company and Anr., (1984)
4 SCC 679 and Ramachandra Reddy and Co. v. State ofA. P. and Ors., (200 I)
4 sec 241, referred to.
0 CIVIL APPELLATE JURISDICTION : Civil Appeal Nos. 3365-66 of
2002.
From the Judgment and Order dated 20.10.2000 of the Mumbai High
Court in C.R.A. No. 801 of2000 with Appeal from Order No. 50 of2000.
E R.F. Nariman, R.N. Dhorde, P.R. Malpani, S.K. Verma and Shivaji
M. Jadhav for the Appellant.
P.M. Amin, Ketan Parikh, Atul Desai, Pratap Venugopal, P.S. Sudhir and
K.J. John for the Respondent.
F The Judgment of the Court was delivered by ...
R.C. LAHOTI, J. Leave granted in both petitions.
The appellant is a co-operative sugar factory manufacturing sugar from
sugarcane. On 17 .11.1992 an agreement was entered into between the appellant
G and the respondent for design, manufacture, procurement and supply of
machinery and equipments for moderanisation with continuous fermentation
process based on "Encillium Process", developed and patented by Council
for Scientific. and Industrial Research, New Delhi and National Chemical ~
Laboratory, Pune. Disputes arose between the parties. The agreement dated
H 17 .11.1992 contained an arbitration clause pursuant whereto the disputes were
SANGAMNER BHAG SAHAKARI KARKHANA 1'. KRUPP INDUSTRIES LTD. [R.C. LAHOTI, J.] 877
referred for arbitration by two arbitrators, one appointed by each of the A
parties. By their award dated 20th June, 1999, 'the learned Arbitrators directed
->
an amount of Rs. 151.97 lacs to be paid by the respondent to the appellant
in full and final settlement of all claims by and between the parties.
The award was filed in the Court of the Civil Judge, Senior Division,
Sangamner. Both the parties preferred objections against the award. After B
hearing the learned counsel for the parties, by its judgment dated 6.5.2000 the
learned Civil Judge directed the award to be remitted back to the learned
arbitrators for rendering a fresh award consistently with the directions given
by the learned Civil Judge. The appellant preferred a revision laying challenge
to the direction of the Court remitting the award while the respondent preferred C
an appeal submitting that on the view taken by the learned Civil Judge, Senior
Division the award itself should have been set aside and there was no
occasion for remitting the award to the arbitrators. The learned Single Judge
of the High Court heard the revision and the appeal together. By the impugned
order the learned Judge has dismissed the civil revision and allowed the
appeal. As a result the order of the learned Civil Judge, Senior Division D
remitting the award to the arbitrators has been set aside and the award to the
extent of Rs. I 07.54 lacs and the interest thereon in the sum of Rs. 28.74 lacs
l has been set aside. The rest of the award has been made a rule of the Court.
Feeling aggrieved by the impugned judgment of the High Court petitions
have been filed by the appellants seeking leave to file appeals by special E
leave.
We have heard the learned counsel for the parties at length who have
apart from making legal submissions carried the Court through the pleadings,
the relevant correspondence between the parties, several documents and the
proceedings before the arbitrators. However, it is not necessary for us to deal F
with the same in very many details as we have formed an opinion that the
impugned judgment of the High Court deserves to be set aside and the order
of the learned Civil Judge deserves to be restored.
A perusal of the judgment of the learned Civil Judge, Senior Division
shows the learned Judge having formed an opinion that the award suffered G
from an error apparent on its face. There was an omission on the part of the
learned arbitrators to consider a few relevant documents available on record
which in the opinion of the learned Civil Judge iftaken into consideration the
finding of the arbitrators would not have been what it is. The learned Civil
Judge also formed an opinion that there was a violation of the principles of H
~,
J
878 SUPREME COURT REPORTS [2002] 3 S.C.R.
A natural justice inasmuch as the parties were not afforded a hearing on the
issue on which the learned arbitrators had based their decision. The learned .. _
Civil Judge was of the opinion that on totality of the facts and circumstances
of the case instead of setting aside the award the same des~rved to be
remitted to the arbitrators with the request to render the award afresh. The
High Court has however formed an opinion that to the extent to which the
B · award has been set aside by the High Court it was beyond the scope of
reference to the arbitration and hence there was no question of th~ parties
being afforded an opport1Jnity of re-arguing the same question before the
arbitrators as the arbitrators could not assume jurisdiction over an issue
which was not referred to them.
On 19th October, 1994 the appellant served a notice on the respondent
setting out several disputes arising between the parties. One of the disputes
raised therein reads as under:
"Till today, we have spent Rs. 107.54 lakhs on the said plant,
which it is abundantly clear that will not give required results as
D
agreed npt even optimum to the norms laid down by the excise rules.
Therefore, Rs. 107.54 lakhs will be straight way loss to my client and
there will be also loss of interest at the rate of 18% per year from l st
May, 1993 onwards. In the circumstances my clients have instructed
me to call upon you which I hereby do to reimburse the loss suffered
E by my clients to the tune of Rs .. 237.83 lakhs within a week from
today."
On 26.12.1994 once again a notice was served by the appellant on the
respondent appointing its own arbitrator calling upon the respondent to
appoint its and in the contents of the notice it was specifically stated that
F they were the questions, disputes and differences mentioned in the notice
dated 19.10.1994 which shall be referred to the arbitration. During the pendency
of the arbitration proceeding, on 24th July, 1995, a memorandum of
understanding was arrived at between the parties which suggests that it was
the dispute referred to in the notice dated 19.10.1994 for which trial-runs were
G being conducted. The notice dated 12.9.1995 served by the appellant on the
respondent reiterates that it was the failure on the part of the respondent to
manufacture and supply the plant and comply with the terms of agreement
that had caused total failure entitling the appellant for refund of total amount
of advance paid by the appellant to the respondent. In its reply dated 30.9.1995
the respondent had told the appellant that the matter was already before the
H arbitrators and the respondent reserved the right to file an appropriate written
SANGAMNER BHAG SAHAKARI KARKHANA v. KRUPP INDUSTRIES LTD. [R.C. LAHOTI. J.J 879
statement before the arbitrator disputing the claim made by the appellant and A
-· it was not necessary to give a detailed reply in response to the appellant's
notice. We have also perused the statements of claim and their responses
filed by the parties before the arbitrators. We find that the claim for Rs. 107.54
lacs and the interest thereon raised by the appellant against the respondent
was very much before the arbitrators and the parties also proceeded on the
assumption that this dispute was before the arbitrators and liable to be B
adjudicated upon by them. Issues Nos. 10, 11 and 12 framed by the arbitrators
are:
• "(10)0(/es the claimant prove that it spent Rs. 107.54 lacs on the plant
and the plant has gone waste for not getting· the guaranteed C
performance?
{11) ls the claimant entitled to Rs. 107.54 lacs as actual damages?
{12) Is the claimant entitled to Rs. 45.46 lacs as interest on the said
amount of Rs. 107.54 lacs?"
The issues are widely worded and include within their sweep the dispute D
arising for decisions and as was adjudicated upon by the award.
The arbitration agreement between the parties opens as under:
"18.0 Arbitration
E
If at any time there should be any question, dispute or difference
between the parties in respect of any matter arising out of or in
relation to this agreement, either party may give to the other party
notice in writing of the existence of such question, dispute or
difference and the same shall be referred to arbitration"
F
In Renusagar Power Co. Ltd. v. Genero/ Electric Company and Anr.
(1984] 4 SCC 679, this Court has held; "Whether a given dispute inclusive of
the arbitrator's jurisdiction comes within the scope of purview of an arbitration
clause or not primarily depends upon the terms of the clause itself, it is a
question of what the parties intend to provide and what language they
employ. Expressions such as 'arising out of or 'in respect of or 'in connection G
with' or in relation to' or 'in consequence of or "concerning' or 'relating to'
the contract are of the widest amplitude." In our opinion, it is the substance
of the claim made before arbitrators which has to be seen. The Court would
not construe the nature of claim by adopting too technical an approach or
by indulging into hair-splitting. Else the whole purpose behind holding H
880 SUPREME COURT REPORTS [2002] 3 S.C.R.
A arbitration proceedings as an alternate to civil court's forum would stand
defeated. We have carefully perused the arbitration clause and the disputes
referred and adjudicated upon by the arbitrators. We find it difficult to sustain
the finding of the High Court that the arbitrators had determined an issue
which was beyond the scope of reference to the arbitration. The disputes did
arise out of the contract between the parties and the arbitrators were seized
B of the disputes within the scope of reference to them. The parties have also
joined in the contest before the arbitrators having understood the scope of
controversy, as already stated hereinabove.
Clause ( c) of sub-section (I) of Section 16 contemplates an award being ..
C remitted to the arbitrators or Umpire for reconsideration upon such terms as
the Court thinks fit where an objection to the legality of the award is apparent
upon the face of it. As held recently by this Court in Ramachandra Reddy
and Co. v. State of A.P. and Ors., [2001) 4 SCC 241 the jurisdiction to remit
an award by the Court to the arbitrators is a discretionary jurisdiction conferred
on the Court and so long as the said discretion has been judicially exercised
D an Appellate Court would not be justified in interfering with the exercise of
discretion unless the discretion is misused. In our opinion no fault can be
found with the discretion exercised by the leamed Civil Judge, Senior Division.
The High Court has erroneously formed an opinion that part of the award was
beyond the jurisdiction of the arbitrators.
E For the foregoing reasons the appeals are allowed. The judgment of the
High Court is set aside and that of the learned Civil Judge, Senior Division
is restored. The award shall stand remitted to the arbitrators in the terms as
directed by the learned Civil Judge, Senior Division. However, the time of six
months appointed for giving the award shall run, from the date of
p communication of this order to the arbitrators.
The appeals stand disposed of in the terms abovesaid. No order as to
the costs.
N.J. Appeals disposed of.
Search Indian case law
Ask in plain English, not just keywords. 25,000 AI words free, no card.